actividad 1
06/07/14
13/07/14
20/07/14
27/07/14
03/08/14
10/08/14
$324,564.86
$289,024.00
$799,617.41
$1,465,073.24
$2,113,274.59
$313,944.26
$85,977.00
$106,802.50
$944,048.00
$919,870.00
$98,013.24
$172,735.29
$568,476.76
$2,278,500.00
$3,316,517.65
$1,209,147.06
$1,040,396.86
Formaleta de losa
Armado de refuerzo de losa
Puntos hidrulicos
Puntos sanitarios
Puntos elctricos
Colocacin losa
$903,481.76
$699,283.14
$197,321.04
$67,504.56
$355,468.24
$3,431,400.00
$43,342.94
Pgina 1
17/08/14
13/07/14
20/07/14
Fraguado losa
Fin Estructura
Paetes
Revoques
Desencofrado de losa
Fin Paetes
Terraza
Mortero impermeabilizado en losa
Ladrillo en losa
Fin Terraza
Instalacin Hidrulica
Puntos hidrulicos Piso 1
Puntos sanitarios Piso 1
Instalacin Ducha
Instalacin W.C.
Instalacin lavamanos
Instalacin Lavadero
Instalacin Tanque
Fin Hidraulica
Instalacin Elctrica
Instalacin Calentador
Puntos elctricos Piso 1
Cableado y aparatiado Piso 1
Fin Electrica
Acabados
Estuco y pintura
Colocacin Puertas y Ventanas
Aseo General
Retiro de escombros
Pgina 2
27/07/14
03/08/14
10/08/14
17/08/14
13/07/14
20/07/14
27/07/14
03/08/14
10/08/14
Fin de proyecto
Total
$2,878,279.51
$4,754,664.88
Pgina 3
$6,163,494.41
$3,153,025.68
$1,252,072.42
$3,542,247.50
17/08/14
24/08/14
31/08/14
$5,779.06
$313,716.00
$288,385.50
$4,193,884.08
Pgina 4
07/09/14
14/09/14
21/09/14
28/09/14
Fraguado losa
Fin Estructura
Paetes
Revoques
Desencofrado de losa
Fin Paetes
Terraza
Mortero impermeabilizado en losa
Ladrillo en losa
Fin Terraza
Instalacin Hidrulica
Puntos hidrulicos Piso 1
$21,411.76
24/08/14
31/08/14
07/09/14
14/09/14
21/09/14
$48,588.24
$6,506,916.00
$52,000.00
$140,364.00
$1,450,428.00
$149,957.50
$158,244.00
$330,236.94
Instalacin Lavadero
Instalacin Tanque
Fin Hidraulica
Instalacin Elctrica
Instalacin Calentador
Puntos elctricos Piso 1
Cableado y aparatiado Piso 1
$471,767.06
$84,785.00
$187,662.00
$108,965.00
$538,586.00
$198,041.00
$1,850,000.00
$554,587.50
$528,162.50
Fin Electrica
Acabados
Estuco y pintura
Colocacin Puertas y Ventanas
Aseo General
Retiro de escombros
$2,218,830.35
Pgina 5
$2,271,659.65
$1,506,945.88
$909,854.12
$80,000.00
$65,000.00
28/09/14
24/08/14
31/08/14
07/09/14
14/09/14
21/09/14
Fin de proyecto
Total
$4,823,176.40
$6,747,868.24
Pgina 6
$2,088,866.44
$6,741,386.41
$3,778,605.53
$1,054,854.12
28/09/14
$324,564.86
$289,024.00
$2,912,892.00
$1,779,017.50
$85,977.00
$106,802.50
$944,048.00
$919,870.00
$666,490.00
$2,278,500.00
$4,698,400.00
$1,739,680.00
$264,825.60
$1,258,950.00
$3,431,400.00
$49,122.00
$313,716.00
$288,385.50
$4,193,884.08
Pgina 7
Fraguado losa
Fin Estructura
Paetes
Revoques
Desencofrado de losa
Fin Paetes
Terraza
Mortero impermeabilizado en losa
Ladrillo en losa
Fin Terraza
Instalacin Hidrulica
Puntos hidrulicos Piso 1
Puntos sanitarios Piso 1
Instalacin Ducha
Instalacin W.C.
Instalacin lavamanos
$70,000.00
$6,506,916.00
$52,000.00
$1,590,792.00
$149,957.50
$158,244.00
$802,004.00
$84,785.00
$187,662.00
$108,965.00
Instalacin Lavadero
Instalacin Tanque
Fin Hidraulica
Instalacin Elctrica
Instalacin Calentador
Puntos elctricos Piso 1
Cableado y aparatiado Piso 1
$538,586.00
$198,041.00
$1,850,000.00
$554,587.50
$528,162.50
Fin Electrica
Acabados
Estuco y pintura
Colocacin Puertas y Ventanas
Aseo General
Retiro de escombros
$4,490,490.00
$2,416,800.00
$80,000.00
$65,000.00
Pgina 8
Fin de proyecto
Total
$46,978,541.54
Pgina 9