Section 01060 - Page 12

final acceptance of systems, or facilities, all temporary connections and piping installed by the Contractor
shall be removed at his expense in a manner satisfactory to the Contracting Officer.
3.7 CONTRACTOR PROVIDED ELECTRICITY
Electrical service is not available for use under this contract; therefore all electric current required by the
Contractor shall be the responsibility of the Contractor, furnished at his own expense. The Contractor
shall provide diesel generators to meet his demand requirements. Electricity required for final testing
systems will be the responsibility of the contractor. The means of doing so, such as by temporary
distribution systems, shall be the responsibility of the Contractor. All temporary connections for electricity
shall be subject to the approval of the Contracting Officer and shall comply with Corps of Engineers
manual EM 385-1-1 entitled Safety and Health Requirements Manual. All temporary lines shall be
furnished, installed, connected and maintained by the Contractor in a workmanlike manner satisfactory to
the Contracting Officer. Before final acceptance of systems, or facilities, all temporary connections
installed by the Contractor shall be removed at his expense in a manner satisfactory to the Contracting
Officer.
Refer to Para. 1.3 QUALITY ASSURANCE for specific requirements for electrical distribution boxes for
temporary power.
3.8 CONSTRUCTION SCHEDULE
3.8.1 GENERAL
a. This provision specifies the procedure for determination of time extensions for unusually severe
weather in accordance with FAR 52.249-10.
b. The listing below defines the anticipated monthly unusually severe weather for the contract period
and is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the
geographic location of the project. The schedule of anticipated unusually severe weather will
constitute the baseline for determining monthly weather time evaluations.
c. Upon award of this Contract and continuing throughout the Contract each month, actual unusually
severe weather days will be recorded on a calendar day basis (including weekends and holidays) and
compared to the monthly anticipated unusually severe weather in the schedule below. The term
"actual unusually severe weather days" shall include days actually impacted by unusually severe
weather. The Contractor's schedule must reflect the anticipated unusually severe weather days on all
weather dependent activities.
3.8.2 WEATHER DAY ALLOWANCE
VARDAK (WARDAK) PROVINCE
MEYDAN SHAHR
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC TOT
9 6 7 7 3 1 2 1 1 1 3 4 45









W912DQ-13-R-4034