Вы находитесь на странице: 1из 39

SPECFICATION FOR

AIR COOLED CONDENSER





PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 1 of 39


















VOLUME-II

PART-C

CONTROL & INSTRUMENTATION

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 2 of 39

VOLUME-II, PART-C
CONTROL & INSTRUMENTATION
I N D E X
CLAUSE NO. DESCRIPTION
1.00.00 INTRODUCTION
2.00.00 CONTROL & INSTRUMENTATION SYSTEM
PHILOSOPHY
3.00.00 GENERAL TECHNICAL REQUIREMENTS
4.00.00 DATA SHEETS FOR FIELD INSTRUMENTS
AND CABLES
5.00.00 UTILITIES
6.00.00 CODES AND STANDARDS
7.00.00 INSTRUMENT INSTALLATION
ANNEXURE-1 DRIVE CONTROL INTERFACE


SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 3 of 39

VOLUME-II, PART-C
CONTROL & INSTRUMENTATION

1.00.00 INTRODUCTION

1.01.00 This specification is intended to cover all aspects of the design, engineering
manufacture, assembly, testing & inspection at manufacturer's works, delivery
at site and erection & commissioning of the complete Control &
Instrumentation System of Air cooled Condensor (ACC) package for 1 x 300
MW coal based thermal power plant at village - Bandakhar, Tehsil - Pali,
Korba district in state of Chhattisgarh.

1.02.00 The Control & Instrumentation for the unit shall comprise equipment
described and specified in this section and other part/section of this
specification document. In general only the major C & I systems and
conceptual guideline for the plant C & I have been indicated.
1.03.00 It is not the intent or purpose of this specification to give details of every
single item that might be required for completeness and/or proper integration
of the overall system. The bidder shall be responsible for providing all
materials, equipment and services, specified or otherwise which are required
to fulfill the intent of ensuring functional completeness, safety of plant and
personnel, operability, maintainability and reliability of the total work covered
under this specification, during any stage of execution of the contract and the
operating life of the plant; within the quoted price and without any further
commercial implication to the Purchaser/Owner.
1.04.00 In the event of any conflict between the requirements of any two (2) clauses
or documents forming a part of this contract the more stringent requirements
shall supply unless otherwise confirmed by the Owner in writing. The decision
of the Owner shall be final and binding in all such cases.

2.00.00 CONTROL & INSTRUMENTATION SYSTEM PHILOSOPHY

2.01.00 The Control & Instrumentation System shall mainly realize the following
functions in order to assist the operator to perform safe start up/shutdown and
normal/emergency operation of the plant.
1. Closed loop modulating control of parameters for optimized
operation of turbine, boiler and balance of the plant.
2. Open loop control for automatic sequential operation,
interlock and protection of various drives.
3. Continuous supervision of system parameters and equipment
operating conditions


SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 4 of 39

2.02.00 State-of-the-art-practices prevailing in the field of Control & Instrumentation
shall be considered to ensure safe, efficient and smooth operation of the air
cooled condenser with minimum interference of the operating personnel
during normal working of the plant.

2.03.00 The system design shall be such that no single point failure will result in total
system paralysis under any operational eventuality. Redundancy shall be
provided at appropriate levels for critical control system functions.

2.04.00 In the event of loss of a major plant item, activities of binary and analog
controls shall be coordinated to ensure that the plant is automatically brought
to a safe holding condition consistent with maintaining maximum generation
permissible under reduced plant availability.
2.05.00 The C & I System shall be configured to perform the following basic functions:
-

a) Automatic sequencing of the start-up and shutdown of major
equipment and auxiliaries including group/plant level start-
up to minimize operators intervention under normal
operating conditions.
b) Regulation functions for various valves and dampers to
achieve guaranteed performance and to achieve the most
fuel-efficient operation.
c) Protection of plant equipment and monitoring of equipment
life.

d) Acquisition, display and archiving of plant data and
generation of reports.
2.06.00 The entire operation of the air cooled condenser system will be through DCS
from central control room.

Sequence control of ACC fan will be implemented in DCS. Bidder to optimise
the % of VFD fans required for operation of the power plant meeting design
performance and without under cooling for complete year operation at various
temperatures. This system shall enable the operator for cold/warm/hot start-
up and safe shutdown and carryout normal operation from control room.

Hotwell control & CEP minimum recirculation control will be implemented in
DCS by CWPC.

The signals required for operation of ACC fans and associated valves will be
cabled to DCS.

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 5 of 39

Bidder shall consider all necessary field instruments, cable supply, cable
laying including cable trays and cable termination in DCS cabinet/DCS
remote I/O cabinets(supplied by BTG Vendor).

Bidder shall prepare I/O list, ACC logics and graphic screens for
implementation in DCS.


3.00.00 GENERAL TECHNICAL REQUIREMENTS

3.01.00 All equipment, system and associated accessories shall be from the latest
proven product range of qualified manufacturers. All materials and equipment
furnished for permanent installation shall conform to applicable local and
international codes and standards Specifications and shall be new, unused
and undamaged.

3.02.00 The equipment and systems shall be designed and constructed to meet
specification requirements, and shall perform accurately and safety under the
environmental and operating conditions described or implied in this
specification without undue heating, vibration, wear, corrosion or other
operating troubles during the continuous service life of the plant. It will be the
responsibility of bidder to fully acquaint himself with the functional
requirements and operating conditions for equipment, system/sub-system/
assemblies and accessories offered for this project. Additional features shall
be provided where required to meet service conditions, functional/descriptive
or parametric requirements for equipments/systems/assemblies/ accessories.

3.03.00 The design of the Control & Instrumentation system shall be such that
isolation of any piece of defective equipment/accessories should be possible
without shutting down the main equipment and should result in minimum
disturbance to the process.

3.04.00 The design of control systems and related equipment shall adhere to the
principle of fail safe operation at all system levels. Fail-safe Operation
means that loss of signal, loss of power supply/air supply or failure of any
component shall not cause a hazardous condition while at the same time
prevent occurrence of false trips.

The following types of failure as a minimum shall be taken into account:

a) Failure of sensors or transmitters, producing high or low signal.
b) Failure of controller during automatic operation.
c) Loss of motive power to final control element actuators.
d) Loss of control power.
e) Loss of instrument air supply.

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 6 of 39


3.03.00 The instrument material specifications shall be consistent with the operating
parameters like temperature, pressure, corrosion conditions and other
process conditions. The instruments shall meet the brief technical
requirements as specified elsewhere.

3.06.00 To ensure safe operation of C & I equipments located in hazardous areas,
based on area classification requirement, transmitters shall be intrinsically
safe and JB/Switch shall have ex-proof enclosures.

3.07.00 Safety earthing and C & I system earthing shall be separate. Safety earthing
bus shall be connected to main plant earthing pit. Separate earth pits shall be
provided for C&I system earthing (electronic earth) to achieve less than 0.5
ohm resistance to ground. Separate earthing shall be provided for intrinsically
safe system.

3.08.00 All field mounted instruments shall have waterproof enclosures conforming to
IP-65. All panels/cabinets shall have protection class IP-54 in ventilated areas
and IP-42 in Air-conditioned area.

3.09.00 All field instruments shall be located in accessible/vibration free locations and
clearly visible range for all readable instruments. Access platforms with
ladders shall be provided for measuring instruments located at high or difficult
places.

3.10.00 Separate cable trays shall be provided for control cables and instrumentation
(signal) cables and separated from power cable trays by at least 600 mm.All
cable entry points to instruments, junction boxes of panel shall be provided
with suitable dust and watertight double compression type glands. All cables
from field to junction box shall be through flexible conduit upto main tray/sub-
tray.

3.12.00 Bidder to provide necessary provision in HT motors for vibration sensor as
per API 670


4.00.00 DATA SHEETS FOR FIELD INSTRUMENTS AND CABLES

4.01.00 PRESSURE GAUGE (PG)

01. Quantity : As per Service Requirement
02. Make : As per approved vendor list
03. Sensing Element : Bourdon Tube
04. MOC sensing & socket : AISI 316 SS
05. Movement material : AISI 304 SS
06. Case material : Stainless steel casing
bayonet type.
07. Accuracy : 1.0% of span or better.

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 7 of 39

08. Dial size : 150mm
09. Adjustment : Micrometer screw of zero
adjustment. Internal micro
meter
screw for range adjustment
10. Scale : Black lettering on white
background in 270 arc
11. Window : Shatterproof toughened
glass
12. Process connection : NPTM, Bottom entry
13. Element connection : Argon welding
14. Safety device : Blow out disc/Diaphragm at
the back
15. Enclosure class : IP 65
16. Ambient temperature : 0 50 C
17. Over range protection : 130 % of max range by
internal stop.
18. Nameplate : Tag number, service
engraved in SS plate.
19. Application standard : IS 3624 / 1996
20. Accessories : a) Snubbers for
pulsating fluid
application
b) Syphons for steam
services
c) For viscous & corrosive
services, Remote Seal
with Silicon Oil Filled
diaphragm seal adapter
flanges with nuts, bolts and
gasket
4.02.00 PRESSURE SWITCH (PS)

01. Quantity : As per Service Requirement
02. Range & Set Pressure : As per Service Requirement
03. Make : As per approved vendor list
04. Type : Seal Diaphragm
05. Sensing element material : SS316 diaphragm
06. Case material : Die-cast aluminum with
neoprene gaskets.
07. Performance : a) Accuracy1.0%
b) Accuracy of setting
indicator of 1.5%
c) Repeatability 1%
of span
08. Over range : 150% of maximum
pressure
09. Switch configuration : Two (2) Nos. SPDT type

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 8 of 39

10. Switch type : Snap acting, shock &
vibration proof
11. Switch rating : 240 V, 5A AC / 220 V, 0.5A DC
12. Ambient temperature : 0- 50C
13. Adjustability : a) Set point adjustable over
span range
b) Differential adjustable by
10% span
14. Cable Entry : 3/4" ET
15. Enclosure class : IP 65
16. Process connection : 1/2 NPT (M) bottom connected.
17. Name plate : Tag number, service engraved in
SS tag plate
18. Accessories : a) Snubbers for pulsating fluid
application
b) For viscous & corrosive
services, Remote Seal with
Silicon Oil Filled diaphragm
Seal adapter flanges with
nuts, bolts and gasket
4.03.00 PRESSURE TRANSMITTER (PT)

01. Quantity : As per Service
Requirement
02. Make : As per approved vendor list
03. Principle : Smart
04. Type : 2 Wire Microprocessor
based Transmitter
05. Output signal : 4 20 mA DC with HART
Protocol
06. Signal processing : Silicon solid state electronic
circuitry
07. Measuring element : Diaphragm
08. Measuring element material : AISI 316 (Stainless steel)
Diaphragm
09. Static pressure : 150% of maximum span
continuously without
affecting the calibration.
10. Operating voltage : 24 V DC
11. Ambient temperature : 0-50 C
12. Performance
a) Accuracy : 0.1% of span or better
b) Repeatability : 0.1% of span or better
13. Turn-down ratio : Minimum 40:1
14. Load impedance : 600 Ohm min at 24V DC
15. Response Time : 100 msec or better
16. Span / zero adjustment : Locally adjustable, non-
interacting facility for

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 9 of 39

Elevation & Suppression
by 100%
17. Enclosure class : IP-65
18. Output Indicator : LCD type in % and
engineering unit.
19. Cable Entry : ET
20. Process Connection : NPT
21. Nameplate : Tag number, service engraved in
SS tag plate.
22. Body : Forged Carbon steel (SS for DM
Water).
23. Accessories : a) Universal mounting
bracket suitable for
2 pipe and wall mounting.
b) Condensate pot for Steam
services.
c) High tensile carbon steel U
bolts.
d) Installation accessories
e) 2 way SS manifold,
constructed from SS316
bar stock.
f) Reverse polarity protection
required.

4.04.00 DIFFERENTIAL PRESSURE SWITCH (DPS)

01. Quantity : As per Service Requirement
02. Make, Model : As per Approved Vendor List
03. Type : Sealed diaphragm, piston
actuated type for high pressure &
diaphragm bellow and torque tube
for low pressure.
04. Sensing element material : AISI SS-316 diaphragm / piston.
All other wetted part SS316.
05. Case material : Epoxy coated steel plate or die-
cast aluminum alloy with
neoprene gasket and clear glass
where applicable.
06. Scale : Black graduation on white linear
scale. 0 100% with red pointer
for set point.
07. Performance : a) Accuracy1.0%
b) Accuracy of setting
Indicator of 1.5%
08. Over range : Static pressure on any one side,
the other side being open to
atmosphere.

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 10 of 39

09. Switch configuration : Two (2) Nos, SPDT type
10. Switch type : Snap acting, shock & vibration
proof
11. Switch rating : 240 V, 5A AC / 220, 0.5A V DC
12. Ambient temperature : 0 - 50C
13. Adjustability : a) Set point adjustable over
span range
b) Differential adjustable by
10% span
14. Cable connection : 3/4" ET compression gland
15. Enclosure class : IP 65
16. Process connection : 1/2 NPT (M) bottom connected.
17. Name plate : Tag number, service engraved is
SS tag plate
18. Accessories : a) Snubbers for pulsating fluid
application
b) Retention ring & screw for
surface mounting
c) 1/2" NPT 5-way valve SS-
316 manifold constructed
from bar stock.
d) 3/4" ET cable gland.

4.05.00 TEMPERATURE GAUGE (TG)

01. Quantity : As per Service Requirement
02. Range : As per Service Requirement
03. Make : As per approved vendor list
04. Type : Mercury filled, rigid stem type
05. Sensing element material : Bourdon AISI 316 SS
06. Movement material : AISI 304 SS
07. Bulb diameter and length : 11/70mm
08. Bulb material : AISI 316
09. Case material : Stainless steel casing bayonet
type
10. Accuracy : 1.0% of full scale deflection or
better.
11. Dial size : 150mm
12. Scale : Black lettering on white
background in 270 Arc
13. Window : Shatterproof toughened glass
14. Process connection : 1/2"NPT (M)
15. Mounting : Surface
16. Enclosure class : IP 65
17. Over range protection : 130 % of max range by internal
stop.
18. Zero Adjuster : Micro adjustable from front
19. Nameplate : Tag number, service engraved in

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 11 of 39

SS tag plate.
20. Compensation : Case compensation
21. Thermowell :
a. Standard : ASME - PTC 19.3
b. Body MOC : Stainless Steel - Barstock
c. Process Connection : M33 X 2 Screwed
d. Element Connection : NPTF
e. Extension length : As per Service Requirement
f. Insertion Length U : As per Service Requirement
22. Accessories : a) Installation accessories as
required.
b) Adjustable nipple union
nipple with thermo well
connection

4.06.00 THERMOCOUPLES (T/C)

01. Quantity : As per Service Requirement
02. Range : As per Service Requirement
03. Make : As per approved vendor list
04. Type : Duplex, ungrounded
05. Element : Type-K (Chromel / Alumel). 16
AWG Wire
06. Protecting Tube:
i) O.D : 8 mm (approx)
ii) Material : 316 SS Seamless
iii) Filling : Magnesium Oxide (Purity above
99.4%)
iv) Length : As per Service Requirement
07. Response time : < 20 seconds for measurement.
08. Head
i) Type : IP-65 universal screwed type
ii) Material : Die cast aluminum or better
iii) Terminal blocks : Nickel plated brass screw
type/silver plated
iv) Cable connection : 3/4" ET
v) Process Connection : NPTF
vi) Others : Terminal head cover with SS
chain and suitable gasket.
09. Standard : ANSI MC 94.1
10. Thermowell :
a. Standard : ASME - PTC 19.3
b. Body MOC : Stainless Steel - Barstock
c. Process Connection : M33 X 2 Screwed
d. Element Connection : NPTF
e. Extension length : As per Service Requirement
f. Insertion Length U : As per Service Requirement
11. Accessories : a) Adjustable nipple-union-

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 12 of 39

nipple with thermo well
connection
12. Nameplate : Tag number, service engraved in
SS tag plate

4.07.00 RESISTANCE TEMPERATURE DETECTOR (RTD)

01. Quantity : As per Service Requirement
02. Range : As per Service Requirement
03. Make : As per approved vendor list
04. Type : 3 wire, Duplex, ungrounded
05. Element : Pt-100 0.1/100 0hm at 0C,
06. Protecting Tube:
i) O.D : 8 mm
ii) Material : 316 SS Seamless
iii) Filling : Magnesium Oxide (Purity above
99.4%)
iv) Length : As per Service Requirement
07. Response time : < 20 seconds for measurement.
08. Head
i) Type : IP-65 universal screwed type
ii) Material : Die cast aluminum or better
iii) Terminal blocks : Nickel plated brass screw
type/silver plated
iv) Cable Entry : ET
v) Process Connection : NPTF
vi) Others : Terminal head cover with SS
chain and suitable gasket
09. Standard : Standard DIN 43760
10. Thermowell :
a. Standard : ASME - PTC 19.3
b. Body MOC : Stainless Steel Bar stock
c. Process Connection : M33 X 2 Screwed
d. Element Connection : NPTF
e. Extension length : As per Service Requirement
f. Insertion Length U : As per Service Requirement
11. Accessories : a) Adjustable nipple-union-
nipple with thermo well
connection
12. Nameplate : Tag number, service engraved in
SS tag plate

4.08.00 TEMPERATURE TRANSMITTER (TT)

01. Quantity : As per Service Requirement
02. Make : As per approved vendor list
03. Principle : Smart with HART Protocol
04. Type : 2 Wire

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 13 of 39

05. Input : Thermocouple / RTD
06. Range : As per Service Requirement
07. Output signal : 4 -20 mA DC with HART Protocol
08. Signal Processing circuitry : Microprocessor based solid state
electronic
09. Output indicator : LCD type
10. Body : Die Cast aluminum
11. Operating Voltage : 24 V DC
12. Ambient Temperature : 0 50 C
13. Performance :
a) Accuracy : 0.2% of span or better
b) Repeatability : 0.05% of span or better
c) Cold Junction
Compensation : Built-in
14. Load impedance : 600 Ohm min at 24V DC
15. Span / zero adjustment : Locally adjustable, non-
interacting
16. Calibration : As Per N.I.S.T Monograph 125
for T/C
16. Enclosure class : IP-65
17. Cable connection : 3/4 ET
18. Nameplate : Tag number, service engraved
on metallic tag plate rigidly fixed
to the body.
19. Accessories : a) Universal mounting
bracket suitable for 2
pipe and wall mounting.
b) High tensile carbon steel
U bolts.
4.09.00 TEMPERATURE SWITCH (TS)

01. Type : Mercury filled in
02. Sensing element material : Bellow / Bourdon AISI SS-316
03. Bulb Material : AISI SS 316
04. Capillary : Stainless steel armored
05. Movement Material : AISI SS - 304
06. Case Material : Epoxy coated steel plate or die-
cast aluminum alloy with
neoprene gasket and clear glass
where applicable conforming to
IP65.
07. Scale : Black lettering n white
background.
08. Over range protection : 120 %
09. Instrument connection : Bottom
10. Switch configuration : Two SPDT Lead wires (3+3
Nos.) are to be brought externally
to the male connector wherein

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 14 of 39

the female pug Connector will be
inserted to connect the control
room cables for easy removal &
re - calibration.
11. Switch rating : 240 V, 5A AC / 220, 0.5A V DC
12. Switch Type : Snap acting, shock & vibration
proof
13. Adjustability : a) Internal Set point
adjustable over span
range
b) Differential adjustable by
10% span (min)
14. Cable Connection : 3/4" ET compression gland

15. Compensation : a) Capillary compensation
with invar wire throughout
the capillary length.
b) Case compensation
16. Performance
i) Accuracy : 1.0% of full scale
ii) Repeatability : < 0.5% of full scale
iii) Response time : < 40 seconds with thermo well
17. Capillary length : 5 meters (local) /15 meters (local
panel)
18. Name plate : Tag number, service engraved is
SS tag plate
19. Accessories : a) Mounting accessories,
b) 3/4' ET cable gland.

4.10.00 LEVEL GAUGE (LG) FLOAT & BOARD

01. Make : As per approved vendor list
02. Service : As per Service requirement
03. Type : Float & Board type
04. Float material : SS-304 / 316
05. Float Wire : SS-304 / 316
06. Tank Height : As per Tank Height
08. Range : As per Tank Height
09. Scale : 4 broad Aluminium (in inches)
10. Accuracy : 2% of FSD
11. Bolts and nuts : Rust proof alloy steel
12. Process
a. Operating temperature: As per Service Requirement
b. Operating Pressure : As per Service Requirement
13. Accessories : a) Counter flange, nuts &
bolts,
suitable gasket etc.
b) Wire Rope, Nylon Roller,

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 15 of 39

Mounting brackets & all
other required fittings.

4.11.00 LEVEL GAUGE WITH SWITCH FLOAT & BOARD

01. Make : As per approved vendor list
02. Service : As per Process
03. Type : Float & Board Gauge with Low
Level Switch
04. Float & Wet material : SS-316
05. Float Wire : SS-316
06. Tank Height : As Required
07. Range : As Required
08. Scale : 4 broad Aluminium (in inches)
09. Accuracy : 2% of FSD
10. Bolts and nuts : Rust proof alloy steel
11. Process
a. Operating Temp. : As per Service Requirement
b. Operating Pressure : As per Service Requirement
12. Switch configuration : Micro, SPDT type (2 Nos.)
13. Switch type : Snap acting, 2 NO+ 2 NC
13. Switch rating : 240 V AC, 5A / 220, 0.5A V DC
14. Adjustability : Set point adjustable over span
range
15. Cable connection : 3/4" ET
16. Enclosure class : IP 65
17. Accessories : a) Counter flange, nuts &
bolts,
suitable gasket etc.
b) Wire Rope, Nylon Roller,
Mounting brackets & all
other required fittings.


4.12.00 LEVEL SWITCH RF TYPE

01. Quantity : As per Service Requirement
02. Service : Coal Bunker
03. Height : As per Service Requirement
04. Make/Model : As per approved vendor list
05. Type : RF type
06. Mounting : Side mounted
07. Supply voltage : 230 V AC
08. Contact type : Snap acting, 2 NO+ 2 NC
09. Contact rating : 240 V AC, 5A / 220 V, 0.5A DC
10. Adjustability : Set point adjustable over span
range
11. Performance :

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 16 of 39

a. Accuracy : 5% of FSR
b. Dead band : 2% of FSR
12. Cable connection : 3/4" ET
13. Response time : less than 1 sec
14. Sensing element : SS 316
14. Coat guard shield : SS 316
15. Insulation : PTFE

4.13.00 RADAR LEVEL TRANSMITTER

01. a) Type : Guided wave Radar type
transmitter
b) Probe : Coaxial
c) Probe material : SS 316 / SS 316L
02. Calibration Range : As per application
03. Process medium : As per application
04. Process temperature : As per application
05. Static pressure : Capable of working in vacuum
also
06. Power supply : Range to be specified by the bid
(loop power Available =24V DC)
07. Reverse polarity protection : Required
08. Output : 4 to 20 mA, 2Wire & HART
09. Accuracy : 10mm or better
10. Stability : As per process application
11. Communication : Communication / configuration
shall be possible either through
integral key pad and display or
through hand communicator. If
integral key pad is not available,
one number hand held
communicator common for all the
transmitters shall be supplied
12. Load limitation : Max 600 ohm at 24V
13. Span & Zero : Adjustable
14. Flange Mounting : Yes
15. Environmental protection : IP 66 or better
16. Process connection : Traditional flange with - 18
NPT on flange with process
adapters
17. Electronic housing : Aluminum alloy
18. Electrical connection : Preferably : 14 NPT with
gland

4.14.00 ULTRASONIC LEVEL TRANSMITTER

01. Type of transmitter : Non contact Microprocessor
based 2 wire type, HART protocol

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 17 of 39

Compatible
02. Output Signal : Galvanically isolated 4 20 mA
DC
along with superimposed digital
signal (HART protocol)
03. Sensor Accuracy : 0.5% of calibrated span
04. Sensor Repeatability : 3 mm or better
05. Power Supply : 18 - 36V DC
06. Temperature Compensation : To be provided within transducer
07. Configuration : Sensor and electronic unit are
separate. Electronic unit all be
possible to mount on the
accessible location near the
transducer. All cables, weather
proof fittings for connection
between transducer and
electronic unit.
08. Housing : IP 55 with durable corrosion
resistant Epoxy coating
09. Calibration : Through HART communicator

10. Zero and Span adjustment : Continuous, Tamper proof,
Remote as well as manual
adjustability. Provision to
calibrate the instrument without
any level in the tank or sump etc.
11. Sensor Material : Corrosion resistant application to
suit the individual
12. False signal tolerance : Facility to be provided. Shall
have adjustable damping circuitry.
13. Range : To be decided during detail
Engineering, with a facility to take
care of frequency attenuation
due to different obstructions
(Surface, vapor)
14. Display : Minimum 4 character display with
integral key pad, access
protected features.
15. Diagnostics : Loss of echo alarm
16. Load impedance : 500 minimum or as per vendor
spec.
17. Electrical connection : Plug and socket
18. Accessories : Canopy for protection sunlight
and Rain Mounting hardwares

4.15.00 DISPLACER TYPE LEVEL TRANSMITTER

01. Type : Smart

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 18 of 39

02. Float movement : Vertical
03. Stages of operation : Continuous
04. Material
a) Displacer/Float : AISI 316 SS/304 S
b) Wire rope, sleeve pipe: AISI 304 SS/316 SS
c) Torque tube : AISI 304 SS/316 SS/ Inconel
05. Transmission : 2-wire
06. Output Signal : 4-20 mA Protocol HART
07. Signal processing : Solid-state electronic circuitry
08. Static/overload pressure : Maximum static pressure without
permanent deformation or loss of
accuracy.
09. Turn-down ratio : 100: 1 minimum
10. Zero & Span : Easily accessible (local zero &
span adjustment and non-
interactive type)
11. Zero Suppression / elevation : i) Suppression = 150 % of
span (min.)
ii) Elevation = 50 % of span
(min.).
12. Enclosure class : IP-65 (explosion proof for
NEC class-1)
13. Body/Cage : Forged Carbon Steel or Stainless
Steel depending upon fluid
condition
14. Output Indicator : LCD type
15. Output Ripple : < 0.25% of span
16. Operating voltage : 16 48 V DC
17. Nameplate : Tag number and service
engraved in SS tag plate
18. Ambient Temperature : 0 - 50C
19. Load Impedance : 600 Ohms at 24 Volts (minimum)
20. Process connection : 50 NB ANSI RF Companion
flange
with nuts, bolts and gaskets
21. Performance
a) Accuracy : 0.5 % of span or better
b) Repeatability : 0.05 % of span or better
c) Sensitivity : 0.1 % of span or better
d) Hysteresis : 0.05 5 of span or better
e) Temperature : < 0.5 % of span / 50C
regardless of rate of calibration
change.
f) Power supply effect : 0.005 % / volt
22. Accessories : i) ANSI RF Counter
Flange; rating as per
process pressure.

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 19 of 39

Necessary nuts, bolts,
gaskets etc.
ii) Vent and drain plugs
iii) Stilling chamber
v) 3/4" ET cable gland
23. Preferred Features : a) Test plug connection and
cutout terminal physically
separated from other
electronics.
b) Electronic Damping
facility (adjustable)

4.16.00 DP TRANSMITTER (LT & FT)

01. Quantity : As per Service Requirement
02. Make : As per approved vendor list
03. Principle : Smart with HART Protocol
04. Type : 2 Wire Microprocessor based
Transmitter
05. Output signal : 4 20 mA DC with HART
Protocol
06. Signal processing : Silicon solid state electronic
circuitry
07. Measuring element : Diaphragm
08. Measuring element material : AISI 316 (Stainless steel)
Diaphragm
09. Static pressure : 150% of maximum span
continuously without affecting the
calibration.
10. Operating voltage : 24 V DC
11. Ambient temperature : 0-50 C
12. Performance
a) Accuracy : 0.05% of span or better
b) Repeatability : 0.05% of span or better
13. Turn-down ratio : 100:1
14. Load impedance : 600 Ohm min at 24V DC
15. Response Time : 100 msec or better
16. Span / zero adjustment : Locally adjustable, non-
interacting facility for Elevation &
Suppression by 100%
17. Enclosure class : IP-65
18. Output Indicator : LCD type in % and engineering
unit.
19. Cable Entry : ET
20. Process Connection : NPT
21. Nameplate : Tag number, service engraved in
SS tag plate.
22. Accessories : a) Universal mounting

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 20 of 39

bracket
suitable for 2 pipe and
wall
mounting.
b) High tensile carbon steel U
bolts.
c) Installation accessories
d) Condensate Pot for steam
service
e) 5 - way SS manifold,
constructed from SS316
bar stock.
f) Reverse polarity protection
required.

4.17.00 ROTAMETER

01. Quantity : As per Service Requirement
02. Type : Online Reading
03. Process Parameter : As per Service Requirement
04. Accuracy : 1% of FSD
05. Scale : Graduated-Engraved Black
lettering on white background, in
m/hr
06. Body : SS-316
07. Tube : Borosilicate glass
08. Float : SS-316
09. Stopper : SS-316
10. Gland packing : PTFE
11. End connection size/Type : As per Service / Flanged to ANSI
B16.5 CL150
12. Pressure drop : As per Requirement
13. Range : As per Requirement



4.18.00 FLOW ORIFICE

01. Quantity : As per Service Requirement
02. Service : Feed Water
03. Design Standard : BS- 1042
04. Flow element & type : Orifice / Concentric
05. Flow element material : SS 316
06. Flow element thickness : 3mm minimum
07. Pipe material : SA 106 GR B
08. Flange Material : SA 106 GR B
09. Type of tapping : Corner tapping
10. Number of tapings : Two pairs

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 21 of 39

11. Beta ratio : 0.4 to 0.7
12. Pressure loss (meter max) : 0.7 Kg/Cm2
13. Process Parameter : As per Table
14. Service : Feed Water
15. Flow Rate (Nor/ Max.) TPH : As per Service Requirement
16. Pressure (Kg/Cm
2
) : As per Service Requirement
17. Temperature C : As per Service Requirement
18. Density : 1
19. Pipe Size / MOC : As per Service Requirement
20. End Connection : As per Service Requirement
21. Accessories : SS316 Flanges, 1/2" root valves
(Globe), 1/2" Nipple (2 nos. of
Root valves if upstream pressure
>40 Kg/cm2)
Note:
The following Drawing / Document shall be submitted along with each
instrument.
GA drawing
Data Sheet
Flow orifice sizing calculation
Flow Vs Differential pressure curve

4.19.00 FLOW NOZZLE

01. Quantity : As per Service Requirement
02. Service : As per Service Requirement
03. Design Standard : BS-1042
04. Flow element & type : Flow Nozzle/ Long Radius
05. Flow element material : Alloy Steel
06. Pipe material : SA 335 P22
07. Pipe size : As per Service Requirement
08. End connection : Butt Weld
09. Type of tapping : D and D/2
10. Number of tapings : Two pairs
11. Beta ratio : 0.5 to 0.7
12. Pressure loss (meter max) : 0.4 Kg/Cm2
13. Service : As Required
14. Flow Rate : As per Service Requirement
15. Flow Rate (Nor/ Max.) TPH : As per Service Requirement
16. Pressure (Kg/Cm
2
) : As per Service Requirement
17. Temperature C : As per Service Requirement
18. Density : As per Service
19. Pipe Size / MOC : As per Service Requirement
20. End Connection : Butt Weld
21. Accessories : 1/2" root valves (Globe), 1/2"
Nipple
Test:
The Following test shall be carried out along with supply of instrument:

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 22 of 39

100% Radio graphic.
Hydro test.
Calibration test.
IBR test Certificate.
Note:
Drawing/ Document shall be submitted along with supply of instrument:
Fabrication & assembly drawing
Data Sheet
Flow Nozzle sizing Calculation
Flow Vs Differential pressure curve

4.20.00 FLOW SWITCHES (FS)

01. Type : Flapper
02. Material of sensing element : PP / Die Cast Aluminum, stoved,
enameled With anticorrosive
paint
03. Flow range and surge ratio : Later
04. Accuracy : 1 %
05. Contacts type, rating : Two (2) Nos, SPDT type with
snap
action
06. Enclosure class : IP 65
07. Connection Instrument/ : As per process requirements /
NPT (F) Conduit
08. Accessories : Isolation valve, drain and vent
plug on external cage, Bolt/Nut
and gaskets.

4.21.00 MASS FLOW METER

A. Sensor
01. Measuring principle : Coriolis Mass flow.
02. Primary Element : Flow tube of 316 SS or better
03. Heating Arrangement : Integral with Flow Element
04. Temp. control for heating : To be provided
05. Process connection : ANSI RF Flanged and rating as
per process required.
06. Drain : Self-draining facility
07. Accessories : Counter flanges, mounting nuts,
bolts, gaskets etc.
B. Transmitter
01. Measured quantities : Mass Flow rate, Total Mass
Flow, Density, Temperature as
minimum
02. Input Signal Processing : Digital processing
03. Display : Digital Display (LCD).

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 23 of 39

04. Output : 2 Nos. isolated output of 4-20mA
DC selectable from four
measured quantities.
05. Load : <750 ohms
06. Power supply : 240V AC, 50 HZ.
07. Turn Down : 100:1
08. Accuracy : 0.2% of measured value
09. Ambient Temperature : 85
10. Repeatability : 0.05%
11. Housing : IP 65(Explosion proof for NEC
Class-1)
12. Hazardous duty version : FM Standards.
13. Nameplate : Tag number, service engraved in
SS tag plate
14. Accessories : a) As required for field
mounting
b) Handheld configurator
c) Mounting U-bolts, nuts,
prefab cable etc.
d) ET cable gland.

4.22.00 MOTORISED VALVES

01. Quantity : As per Service Requirement
02. Valve service : Main Steam
03. Valve type : Gate Valve
04. Pipe size inlet / outlet : 250NB Sch 140 / 250NB Sch 140
05. Pipe MOC : SA-335 P22
06. Guiding : Later
07. Type of connection : Flanged
08. Material
i) Valve body : Later
ii) Stem : ANSI -316 SS
iii) Seat rings : ANSI -316 SS
iv) Plug : ANSI -316 SS
v) Bonnet gasket : Later
09. Port size : Later
10. Plug type : Later
11. Plug characteristic : Later
12. Differential pressure : Later
13. Maximum flow capacity :
a. Normal Flow in TPH : As per Service
b. Maximum Flow in TPH: As per Service
c. Operating Temp in
O
C : As per Service
d. Up steam Operating
Pressure in Kg/cm
2
:

As per Service
e. Down steam Operating
Pressure in Kg/cm
2
:

As per Service

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 24 of 39

14. Valve stem packing : Later
15. Type of actuator : Motor operated
16. Actuator make / model : Later
17. Signal range : Later
18. Integral Bypass Valve : 25NB Motorized Integral Valve
with All accessories
19. Accessories included : Electric motors, Position limit
switches & Torque limit switches,
Hand wheel, gear train,
mechanical position indicator,
internal wiring, integral starters
and terminal block etc.,
20. Noise ratio : < 85 db
21. Leakage class : Class IV
22. Minimum clearance required : As per standard for maintenance
purposes
23. Integral Bypass Valve : 25NB Motorized Integral Gate
Valve with all accessories
24. Make : As per approved vendor list.



4.23.00 CONTROL VALVE

01. Quantity : As per Service Requirement
02. Make : As per Approved Vendor List
03. Valve service : Later
04. Valve type & size : As per process requirement
05. Valve co-efficient : Later
06. Connection size inlet / outlet : As per process parameter
07. Guiding : Later
08. Type of connection : Later
09. Material
i) Valve body : Later
ii) Stem : ANSI -316 SS
iii) Seat rings : ANSI -316 SS
iv) Plug : ANSI -316 SS
v) Bonnet gasket : Later
10. Port size : Later
11. Plug type : Later
12. Plug characteristic : Later
13. Differential pressure : Later
14. Maximum flow capacity : Later
15. Valve stem packing : Later
16. Type of actuator : Pneumatic actuator
17. Actuator make & model : Later
18. Signal range : Later
19. Action on air failure : Fail to open or fail to close in a

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 25 of 39

direction safe for the process
20. Accessories included : Hand wheel, Limit switches, I/P
Converter, air lock relay, position
transmitter and JB etc.
21. Noise ratio : < 85 db
22. Leakage class : IV
23. Min. clearance required : As per standard for maintenance
purposes
24. Process Parameters:
a) Process Pressure : Later
b) Process Temperature : Later
c) Process Flow : Later
d) Line Size : Later


4.24.00 SOLENOID VALVE

01. Operating Principle : Electromagnetic (noiseless)
Latch
/ release coil shall be used in the
required application where the
safety is to be ensured.
02. Coil voltage rating : 240 V AC /110V AC / 24 V DC /
48
V DC / 220 V DC (As required).
03. Ways : 3 ways (NO + NC) [General],
other Depending on requirement
04. Port size : 1/2" NPT / as per site
requirement
05. Body : SS Bar Stock
06. Trim : AISI SS-316
07. Manual operator : In built
08. Duty : Suitable for continuous
energization
09. Sealing : Airtight and leak proof
10. Ambient temperature : 0 - 50
O
C
11. Fluid temperature : 0-150
O
C or as per application
12. Coil enclosure : Stainless Steel
13. Insulation : Class-H
14. Coil casing : IP-65 (Explosion proof for NEC
Class-1)
15. Mounting : On pipe or on panel
16. Cable connection : 3/4" ET Compression gland
17. Accessories : Mounting brackets, nuts and
bolts
18. Pressure Rating : As per application
19. Special feature : i) Temperature operated
fuse at explosion proof

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 26 of 39

enclosure.
ii) Solenoid valve directly
integral to actuator body
shall have NAMOOR
interface.

4.25.00 ELECTRO-PNEUMATIC CONVERTER (I/P)

01. Quantity : As per Service Requirement
02. Make : As per approved vendor list.
3. Type : Electro-Pneumatic Input
4. Input : 4-20 mA DC
5. Output : 0.2 to 1.0 kg/cm
6. Direct/reverse action : Provided
7. Enclosure class : IP 65
8. Mounting : Field (Pipe& wall) mounting
9. Air filter regulator : Sintered bronze, 5 Microns,
10Kg/cm
10. Output gauge : Provided
11. Connections : ET / NPT (Electrical/
Pneumatic)
4.26.00 AIR FILTER REGULATOR

01. Quantity : As per Service Requirement
02. Make : As per Approved Vendor List
03. Filter element : Sintered Bronze
04. Filter size : 5 microns
05. Input air : 10.0 Kg/Sq.cm (maximum)
06. Output : Adjustable from 0- 2.0 Kg / cm or
0 7.0 Kg/Sq.cm (continuous) as
applicable.
07. Effect of supply : Maximum 0.002 Kg/Sq. cm for a
change pressure variation in
supply pressure of Kg / Sq.cm
08. Bowl material : Metallic cover around high
Temperature Area / clear
transparent polycarbonate with
metallic cover for ordinary
applications.
09. Accessories : 2" dial size output pressure
gauge
10. Desirable feature : No perceptible drop of pressure
on opening the drain port.
4.27.00 JUNCTION BOX

01. Quantity : As per Service Requirement
02. Make : As per Approved Vendor list
03. Type : Flame proof/weather proof

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 27 of 39

04. Enclosure : IP-65
05. Material : Die cast aluminum with
protective coating
06. Cable entry : Bottom
07. Cable glands : Double compression type
Nickel plated brass with PVC
hoods.
08. Mounting : Outdoor
09. No. of terminals : As required with standardization
10. Terminals : Phoenix/Wagon
11. Grounding : Two terminals for body and
shield
ground
12. Door : Hinged, lockable type.

4.28.00 POSITIONER

01. Stroke Adjustment : Shall be possible.
02. Gauges : Supply, signal, output
03. Travel time of valve : < 10 seconds
04. Hysteresis : 0.5% of F.S.
05. Linearity : 1.0% of F.S.
06. Dead Band : 0.5% of F.S.

4.29.00 LIMIT SWITCH (LS)

01. Type : Dust proof momentary spring
return
02. Operating head : Adjustable roller Lever (32-82.5
mm) with 19 mm Dia and 8 mm
Dia Vide metal Roller.
03. Accuracy and differential : 0.2% of full scale
04. Differentialfixed/ adjustable : Adjustable
05. Contact Arrangement : SNAP Action
06. Number of contacts : 2 Normally Open (NO) & 2
Normally Closed (NC)
07. Contact rating : 5A, 240V/0.25A, 220V DC
08. Outlet Pressure gauge range : 50 mm diameter Range (0 -10)
09. Operating temperature range : Later
10. Cable Entry : 3/4" Double compression cable
gland
11. Enclosure class : IP 65
13. Accessories : Isolation valve, drain and vent
plug on external cage





SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 28 of 39


4.30.00 Control &Instrumentation Cables

4.30.01 600V GRADE SINGLE PAIR TWISTED INSTRUMENTATION SIGNAL
CABLE

CONSTRUCTION

a) Conductor: Each core shall be seven stranded annealed
copper electrolyte grade conductor of cross
section 1.0 mm2 generally complying to IS-8130.

b) Insulation: Each core shall be provided with extruded HR
PVC conforming to IS:5831 Type 'C'.
Insulation thickness shall be >=0.8 mm and shall
conform to relevant IS/other standard. Color of
insulation shall be white and black in a pair.

c) Twist: Every 2 core shall be twisted to form a pair and
number of twist shall be 20 twist per meter.

d) Shielding: The individual pair shall be shielded. Shield
shall be Aluminium backed by Mylar tape bonded
together side down helically applied with either
side 25% overlap and 100% coverage. Minimum
shield thickness shall be 0.05mm Drain wire
shall be 0.5 sq mm multi stranded bare tinned
annealed copper conductor. The drain wire shall
be in continuous contact with aluminium side of
the shield.

e) Inner sheath: Cables shall be provided with extruded HR PVC
inner sheath as per IS 5831 type ST1. The
color shall be black and minimum
thickness shall be >= 0.4 mm.
f) Armouring: Armouring applied over inner sheath shall be of
galvanised steel wire 1.4 mm dia as per IS 1554
part I and IS 3975.

g) Overall sheathing: The cable shall be sheathed with extruded HR
PVC type ST1 as per IS 5831 Color of sheath
be Black. Thickness of the sheath shall be as per
IS 1554 Part. I and >= 1.24 mm. FRLS PVC outer
sheath shall be provided.




SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 29 of 39

4.30.02 600V GRADE MULTIPAIR TWISTED INSTRUMENTATION SIGNAL
CABLES

GENERAL

Multi pair twisted instrumentation cables shall be same as Single pair
shielded cable.

Following additional features shall be applicable: -

a) Conductor: Each core shall be seven stranded annealed
copper electrolyte grade conductor of cross
section 0.75 mm2 generally complying to IS-8130.

b) Shielding: In addition to individual shielding of pair, overall
shielding shall be provided. Overall shield shall be
Aluminium backed mylar tape helically applied with
metallic side down either side 25% overlap and
100% coverage. Shield thickness shall be 0.075
mm. Drain wire shall be similar to individual pair drain
wire and shall be in continuous contact with the
Aluminium side of the overall shield.

b) Twist: Overall twist of all pair shall be as per
manufacturer standard

c) Pair-Identification : Pairs shall be identified by printing pair
numbers by black indelible ink on the white core
at interval not more than 250 mm. Conductor
insulation shall be black and white for each
pair.

4.30.03 600V GRADE SINGLE TRIAD SHIELDED CABLE

600V grade single triad cable shall be same as Single pair shielded cable.


4.30.04 600 GRADE MULTI TRIAD SHIELDED CABLE

600V grade multi triad cable shall be same as Multi triad shielded cable.









SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 30 of 39

4.30.05 1100V GRADE 2 CORE CONTROL CABLE

CONSTRUCTION

a) Conductor: Each core shall be seven stranded annealed tinned
copper conductor of cross section 1.5 mm2 generally
complying to IS 8130.

b) Insulation: Each core shall be provided with extruded HR PVC
insulation conforming to IS 5831 Type 'C'.
Insulation thickness shall be >= 0.8 mm. Color of core
insulation shall be black with core numbers printed in
white indelible ink at max. 150mm apart on each
conductor.

c) Inner sheath: Cables shall be provided with extruded HR PVC
inner sheath as per IS 5831 type ST1. The color shall
be black. Thickness of sheath shall be >= 0.3 mm.

d) Armouring : Armouring applied over inner sheath shall be of
galvanised steel wire 1.4 mm dia. as per IS 1554 part
I and IS 3975.

e) Overall : The cable shall be sheathed with extruded HR PVC
sheathing type ST1 as per IS 5831. Colour of
sheath shall be black. Thickness of the sheath shall
be >= 1.24 mm as per IS 1554 part-I. FRLS PVC
outer sheath shall be provided.


4.30.06 1100V GRADE Multi core control cables

Multi core control cables shall be same as two core control cable except for
the following features.
a) Conductor: Each core shall be seven stranded annealed tinned
copper conductor of cross section 0.75 mm2 generally
complying to IS 8130.


The core identification can be done by numbers. In that case, the
insulation of cores shall be of same color and number sequentially sorting
with number 1 for inner layer. The number shall be printed in Hindu Arabic
numerals on the outer surface of the cores. (All the numbers shall be of
same color which shall contrast with the color of the insulation. The
numerals shall be 1 eligible. Bidder may alternately offer color coded
conductors).



SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 31 of 39

4.30.07 Fibre Optic Cable (Mono type)

i. Cable Type : Mono-mode with minimum 4
fibers
ii. Wavelength band optimized : 850nm / 1300nm / 1550nm
iii. Mode field diameter : 9-10m + 10% of nominal
value
iv. Cladding diameter : 125m + 3
Non-concentricity core
/ Cladding : not more than 2m
Non-circularity of cladding : not more than 3m
vii. Cut-off wavelength : 1200nm
viii. Attenuation : 1. less than 0.3-0.4 dB/km at 1300nm
2. less than 0.15-0.25 dB/km
at 1550nm
Fibre optic cables shall be Rodent proof type and shall be laid through 30 mm dia
HDPE conduit


4.30.08 Fibre Optic Cable (Multi type)

i. Cable Type : Multi-mode with minimum 4
fibers
ii. Core / cladding diameter : 62.5 / 125 m
iii. Jacketing Material : Halogen Free, Flame
Retardant, Low Toxicity
iv. Attenuation @ 850 nm : Length (m) x 0.0035
db/m+2db maximum
v. Outside Diameter : 8.10 mm (0.324 in)
vi. Minimum Bend Radius : 12.5 cm (5 in)
vii. Minimum Bend Radius : 7.5 cm (3 in) (Long term)
viii. Cable Assembly : Tensile Load for attenuation
increase <0.5 db: 300 N
(66 lb) maximum
ix. Tensile Load at Installation : 1776 N (400 lb) max.
x. Connector Tensile Load MIC : 133 N (30lb)
xi. Minimum Crush Resistance : 46 N /cm (250 lb /in)
Fibre optic cables shall be Rodent proof type and will be laid through 30 mm
dia HDPE conduit


5.00.00 CODES & STANDARDS

5.01.00 GENERAL

5.02.00 All equipment, systems and works covered under the Bidders scope shall
comply with all statutory regulations and safety codes as applicable
internationally and in locality where the equipment will be installed.

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 32 of 39


5.03.00 The Bidders scope of supply shall include some items such as thermowells,
control valves and other in-line devices for main steam, feedwater system,
falling under the purview of Indian Boiler Regulation (IBR) Act. It shall be the
responsibility of the Bidder to obtain the necessary approval of the concerned
Inspecting Authority/Chief Inspector of Boilers for the design and design
calculations, manufacturing and erection procedures as called for under the
Indian Boiler Regulations Act.
5.04.00 The design, manufacture, inspection, testing and erection of the equipment
covered under this Specification shall conform to the standards and codes
(latest editions) including but not be limited to those mentioned below.
Contractor shall refer to the latest revision of all codes and standards.

Bidder shall however, follow sound Engg. practice throughout.

Temperature Measurement -ASME PTC 19.3
ANSI MC 96.1
IEC 751, IEC584.2
BS 1401
IS 2806

Pressure Measurement -ASME PTC 19.2
IEC 381
IS 3624

Flow Measurement -ASME PTC 19.5
BS 1042/ ISO 5167

Control Valves - ISA S 75.01-75.05
ANSI B16.34
ANSI B16.10

Sampling System -ASME PTC 19.11
ASTM D1198
ASTM A 269

Enclosures -IEC 529
IEC 79 (Hazardous)
IS 2147/IS 13947

Annunciator - ISA S 19.1

Boiler Safety Interlocks - NFPA Section 85B/D/E/F/G

Instrument Tubing, - ANSI B 16.11/B 31.1
Fitting


SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 33 of 39

Cables - IEEE 383 BS 6746 IS 5831
BS 5308 BS 6346 IS 10810
IS 1554 BS 6360 IS 694
IS 8130 BS 6500


6.00.00 INSTRUMENT INSTALLATION

6.01.00 General
a) Instrument process tubing and instrument air tubing to be designed in
accordance with the instrument installation drawings.

b) All instruments, process connections, including isolation valves and
associated devices, shall be located in easily accessible locations for
maintenance, calibration and replacement. All maintenance, calibration
and replacement operations on a given device must be possible without
interruption of service to adjacent equipment.

c) Instrument mounting height shall 4 - 6 above equipment base or
platform.

d) Instrument tubing installation are designed in accordance with ANSI
B31.1 Power Piping.

6.02.00 Instrument Sensing Lines

a) All impulse pipe shall be of seamless type conforming to ANSI B36.10
for schedule numbers, sizes and dimensions etc

b) Minimum bending radius of instrument sensing lines 3 times the tube
diameter.

c) Instrument sensing lines are sloped in their horizontal runs, a minimum
of 1/2 per foot. In general, liquid and steam lines slope from their
process tap connection down to the instrument. In general, gas and
non-condensing vapor lines slope from their process tap connection
upto the instrument.

d) Instrument sensing lines shall be routed as directly as practicable from
the process root valve to the instrument. The length of instrument tubing
from the root valve to the instrument shall be limited to maximum of 12
meters for compressible fluids and 15 meters for non-compressible
fluids.

e) Instrument sensing lines are grouped together as much as possible to
benefit from the use of common support members and to present a
finished installation that is routed in a neat and orderly manner. Care is
exercised to assure that spacing between adjacent tubes in the same

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 34 of 39

group is maintained uniform and that tubes do not cross under or over
one another at any point. Changes in direction of tubing is done by the
use of tube bends and not tube fittings.

f) For connection to gauge or transmitter or switch compression tube
fittings will be used.

g) A single blow down valve or double blow down valves (if the process
root valves are doubled) shall be installed to the sensing lines of all
pressure transmitters that are tapped off liquid or steam process
systems. These valves shall be located at the instrument and may be
brought together to the header.

h) The maximum process temperature for all transmitters shall be limited to
80
o
C. To dissipate the excess heat, a maximum of 1 meter of tubing for
each 30
o
C of excess heat shall be installed to isolate the process media
from the instrument. An additional isolation valve shall be used at the
instrument for isolation on those instruments without valve manifolds.

6.03.00 Instrument Air Lines

a) Instrument air lines shall be of stainless steel..

b) Minimum bending radius of instrument air line tubing is 3 times the tube
diameter.

c) All branch lines from the instrument air line header are made from the
top of the air header and shall not be smaller than 1/2 inch. Branch lines
have a root valve at the process connection.

d) In areas with multiple air users, an instrument air manifold is used. The
branch from the air header to manifold is 1 inch, with a 1-inch isolation
valve at the manifold. The manifold consists of a 3 inch pipe with a caps,
3/8 inch air takeoff connections with 3/8 inch shutoff valves, and a 1/2
drain valve. A six and eight air user, manifold design, will be used.

6.04.00 Instrument Mounting

a) Instrument mounting shall be in accordance to standard hook-up details
and mounting details.

b) Spacing between multiple instruments mounted on the same support
shall be sufficient to allow ample clearance area in order to perform
service, maintenance, calibration and testing.

6.05.00 Instrument Wiring


SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 35 of 39

6.05.01 General
The two-wire system shall be employed for transmission of signals from
electronic transmitting instruments. Electronic instrument wiring shall be done
as per manufacturers standards and multicore cables shall be used wherever
practical. Special, screened, shielded or co-axial cables shall be used as
required and as such, these special cables shall be supplied by the
Contractor.

6.05.02 Conduit

Compensating and screened cable shall, in general, be installed in rigid
conduit. All special cable including compensating cables required for the plant
shall be included in Contractors scope.

6.05.03 Terminal Box

Except for thermocouple cables terminal/junction boxes shall be used for the
interconnection of control wiring and instrument signal wiring. Terminal boxes
of a type approved for area classification shall be provided for terminating
multicore control wiring. NEMA-3 standard type of better enclosures shall be
used for junction boxes. 20 % spare terminals shall be provided in the
junction box.

6.06.00 Wiring Practices

6.06.01 The signal cable shield shall not be used as a signal conductor. The signal
cable shall not be spliced. The cable shield shall be maintained at a fixed
potential with respect to the circuit being protected.

6.06.02 Low level signal cable shall be terminated with short untwisted length of wire,
which should have as minimum area as practicable to be exposed for
inductive pick-up. Low level signal cables should be separated (isolated) from
noisy & power circuits by practicable large distance. Signal cables should not
cross each others, if at all required, crossing shall be at right angles, and at a
large practical distance.

6.06.03 Instrument cubicle/panel wiring shall be such that minimum crossing of signal
cables are encountered. Instrument/device located in left (and right) hand
side of panel/cubicle should be terminated in left (& right) side terminal block
respectively so as to minimise intercrossing of wires in panel/cubicles.

6.06.04 Unused shielded conductors in a low level signal cable shall be single end
grounded at the opposite end.

6.06.05 Earthing plate for all electronic instruments shall be away from common
electrical earthing point. A signal circuit shall be grounded either at the
transmitter end or at the instrument end.


SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 36 of 39

6.06.06 All Cables to be terminated in Junction Box/Panel shall be through cable
glands.

6.06.07 All instrument cables like signal cable, communication cable, supply cable
should have separate color code and cables should be distinguished from
electrical cables. Signal cables and control cables should be put in cable trays
separate from that of power cables.

6.06.08 All cables should have traceability from field to JB and JB to DCS/Panel with
identification ferrules. The cabling should be documented properly so that it
can be useful for future maintenance.

7.00.00 DATA AND DOCUMENTS TO BE FURNISHED BY THE BIDDER ALONG
WITH BID

Bidder shall furnish all required information/data sheet/drawing/document
required to facilitate full appreciation of bid which shall include but not limited
to following :-

a) Proposed control philosophy along with Control system
configuration diagram.
a) Filled up Technical Particular Sheets/Schedules.
b) Details of C & I and PLC System offered
c) Tentative I/O counts
d) Details of hardwired controls and indication (if any).
e) List of deviation from Specification document.
f) Vendor list of instrumentation items.

DATA AND DOCUMENTS TO BE FURNISHED BY THE CONTRACTOR

a) Operational Philosophy.
b) Control system configuration diagram.
c) Description and write-up of control scheme and interlocking
system.

SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 37 of 39

d) Complete Local Control room layout drawings with foundation,
GA details of all panels, desks and consoles, wherever
applicable.
e) Interconnection cable schedule (ICS) and cable schedule
between instruments JBs & I/O cabinets.
f) Cabinet / Panel wiring diagrams and internal layout drawings
g) Cabinet / Panel terminal details
h) Wiring diagrams for panel, local panel, junction boxes,
actuators,etc
i) Proposed Graphics/Mimic displays and logs.
j) Control schemes/logic diagram.
k) Flow element and Control valve sizing calculations and
dimensional drawings.
l) Interconnection Diagram of different PLCs / C & I systems and
the DCS showing all hardware details.
m) Complete Instrument Schedule.
n) Junction Box Schedule
o) FAT procedure
p) Heat load, Power consumption and air consumption data
q) Calibration test & quality assurance test procedure and test
certificates.
r) Shop and site Test Records.
s) Manuals & technical literature for instruments/ equipments.
t) Instrument installation diagram showing all erection hardware.
u) Power supply arrangement for field mounted
instruments/panels/sub systems.
v) 'As built' status drawings.


SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 38 of 39

ANNEXURE-I-DRIVE CONTROL PHILOSOPHY

Drive Control Philosophy: Control philosophy for interfacing of MCC/SWGR./Actuator with
PLC/DCS is as follow:

a. Bi-directional drives (inching or open/close) -

All Motor operated valves/dampers are integral type. The following interface between
PLC and valve integral starter:

i. Potential free On-Off commands from PLC to integral starter.
ii. Speed output (For VFD Drives)

Feed backs from integral starter to PLC shall include:

i. Open limit switch feedback
ii. Close limit switch feedback
iii. Open torque switch feedback
iv. Close torque switch feedback
v. Integral Starter Disturbed (Loss of power/control supply, thermostat trip,
Thermal O/L, Torque open/close, Local/off/Remote S/S in Local or Off mode
etc.)
vi. Position Transmitter Feedback (For Inching Type drive)

b. Unidirectional LT Drives

LT drives like Pumps and Fans shall have the following interface with PLC and MCC:

i. Potential free On-Off commands from PLC to MCC.
ii. Speed output (For VFD Drives)

Feed backs from MCC to PLC shall include:

i. On/Running
ii. Off/stop
iii. Switchgear/MCC Disturbance (when Thermal O/L, control power supply fails,
MCC power supply is isolated, EPB OPTD, S/S not in Remote).
iv. Current Feedback for motor rated >30KW
v. Speed (For VFD drives)

c. Unidirectional HT Drives

HT Drives like pumps and fans shall have the following interface with PLC and MCC:

i. Potential free On-Off commands from DCS to MCC.
ii. Speed output (in case of VFD)



SPECFICATION FOR
AIR COOLED CONDENSER



PROJECT
1 x 300 MW COAL BASED THERMAL
POWER PLANT, CHHATTISGARH, INDIA
Doc. No. 11V02-201-SPC-M-0001, REV.R0
Date: 04-11-2011 VOL-II PART-C Page 39 of 39


Feed backs from MCC to PLC shall include:

i. On/Running
ii. Off/Stop
iii. Switchgear/MCC Disturbance (Overload relay operated, control supply fail,
Emergency LPBS operated)
iv. Switchgear/MCC Available (Breaker in service position, Switchgear in remote
& breaker spring charged, lockout relay reset)
v. Breaker in test position
vi. Current Feedback
vii. Speed Feedback (in case of VFD)

d. Solenoid Drives

Solenoid operated drives shall have the following interface with PLC:
i. Energize
ii. De-energize
iii. Open limit switch feedback
iv. Close limit switch feedback

e. Pneumatic Drive

Pneumatic operated drives shall have the following interface with PLC:

i. Command to I/P converter
ii. Position Transmitter Feedback
iii. Open limit switch feedback
iv. Close limit switch feedback
v. Command to solenoid valve (Wherever Applicable)

Вам также может понравиться