PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 1 of 39
VOLUME-II
PART-C
CONTROL & INSTRUMENTATION
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 2 of 39
VOLUME-II, PART-C CONTROL & INSTRUMENTATION I N D E X CLAUSE NO. DESCRIPTION 1.00.00 INTRODUCTION 2.00.00 CONTROL & INSTRUMENTATION SYSTEM PHILOSOPHY 3.00.00 GENERAL TECHNICAL REQUIREMENTS 4.00.00 DATA SHEETS FOR FIELD INSTRUMENTS AND CABLES 5.00.00 UTILITIES 6.00.00 CODES AND STANDARDS 7.00.00 INSTRUMENT INSTALLATION ANNEXURE-1 DRIVE CONTROL INTERFACE
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 3 of 39
VOLUME-II, PART-C CONTROL & INSTRUMENTATION
1.00.00 INTRODUCTION
1.01.00 This specification is intended to cover all aspects of the design, engineering manufacture, assembly, testing & inspection at manufacturer's works, delivery at site and erection & commissioning of the complete Control & Instrumentation System of Air cooled Condensor (ACC) package for 1 x 300 MW coal based thermal power plant at village - Bandakhar, Tehsil - Pali, Korba district in state of Chhattisgarh.
1.02.00 The Control & Instrumentation for the unit shall comprise equipment described and specified in this section and other part/section of this specification document. In general only the major C & I systems and conceptual guideline for the plant C & I have been indicated. 1.03.00 It is not the intent or purpose of this specification to give details of every single item that might be required for completeness and/or proper integration of the overall system. The bidder shall be responsible for providing all materials, equipment and services, specified or otherwise which are required to fulfill the intent of ensuring functional completeness, safety of plant and personnel, operability, maintainability and reliability of the total work covered under this specification, during any stage of execution of the contract and the operating life of the plant; within the quoted price and without any further commercial implication to the Purchaser/Owner. 1.04.00 In the event of any conflict between the requirements of any two (2) clauses or documents forming a part of this contract the more stringent requirements shall supply unless otherwise confirmed by the Owner in writing. The decision of the Owner shall be final and binding in all such cases.
2.00.00 CONTROL & INSTRUMENTATION SYSTEM PHILOSOPHY
2.01.00 The Control & Instrumentation System shall mainly realize the following functions in order to assist the operator to perform safe start up/shutdown and normal/emergency operation of the plant. 1. Closed loop modulating control of parameters for optimized operation of turbine, boiler and balance of the plant. 2. Open loop control for automatic sequential operation, interlock and protection of various drives. 3. Continuous supervision of system parameters and equipment operating conditions
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 4 of 39
2.02.00 State-of-the-art-practices prevailing in the field of Control & Instrumentation shall be considered to ensure safe, efficient and smooth operation of the air cooled condenser with minimum interference of the operating personnel during normal working of the plant.
2.03.00 The system design shall be such that no single point failure will result in total system paralysis under any operational eventuality. Redundancy shall be provided at appropriate levels for critical control system functions.
2.04.00 In the event of loss of a major plant item, activities of binary and analog controls shall be coordinated to ensure that the plant is automatically brought to a safe holding condition consistent with maintaining maximum generation permissible under reduced plant availability. 2.05.00 The C & I System shall be configured to perform the following basic functions: -
a) Automatic sequencing of the start-up and shutdown of major equipment and auxiliaries including group/plant level start- up to minimize operators intervention under normal operating conditions. b) Regulation functions for various valves and dampers to achieve guaranteed performance and to achieve the most fuel-efficient operation. c) Protection of plant equipment and monitoring of equipment life.
d) Acquisition, display and archiving of plant data and generation of reports. 2.06.00 The entire operation of the air cooled condenser system will be through DCS from central control room.
Sequence control of ACC fan will be implemented in DCS. Bidder to optimise the % of VFD fans required for operation of the power plant meeting design performance and without under cooling for complete year operation at various temperatures. This system shall enable the operator for cold/warm/hot start- up and safe shutdown and carryout normal operation from control room.
Hotwell control & CEP minimum recirculation control will be implemented in DCS by CWPC.
The signals required for operation of ACC fans and associated valves will be cabled to DCS.
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 5 of 39
Bidder shall consider all necessary field instruments, cable supply, cable laying including cable trays and cable termination in DCS cabinet/DCS remote I/O cabinets(supplied by BTG Vendor).
Bidder shall prepare I/O list, ACC logics and graphic screens for implementation in DCS.
3.00.00 GENERAL TECHNICAL REQUIREMENTS
3.01.00 All equipment, system and associated accessories shall be from the latest proven product range of qualified manufacturers. All materials and equipment furnished for permanent installation shall conform to applicable local and international codes and standards Specifications and shall be new, unused and undamaged.
3.02.00 The equipment and systems shall be designed and constructed to meet specification requirements, and shall perform accurately and safety under the environmental and operating conditions described or implied in this specification without undue heating, vibration, wear, corrosion or other operating troubles during the continuous service life of the plant. It will be the responsibility of bidder to fully acquaint himself with the functional requirements and operating conditions for equipment, system/sub-system/ assemblies and accessories offered for this project. Additional features shall be provided where required to meet service conditions, functional/descriptive or parametric requirements for equipments/systems/assemblies/ accessories.
3.03.00 The design of the Control & Instrumentation system shall be such that isolation of any piece of defective equipment/accessories should be possible without shutting down the main equipment and should result in minimum disturbance to the process.
3.04.00 The design of control systems and related equipment shall adhere to the principle of fail safe operation at all system levels. Fail-safe Operation means that loss of signal, loss of power supply/air supply or failure of any component shall not cause a hazardous condition while at the same time prevent occurrence of false trips.
The following types of failure as a minimum shall be taken into account:
a) Failure of sensors or transmitters, producing high or low signal. b) Failure of controller during automatic operation. c) Loss of motive power to final control element actuators. d) Loss of control power. e) Loss of instrument air supply.
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 6 of 39
3.03.00 The instrument material specifications shall be consistent with the operating parameters like temperature, pressure, corrosion conditions and other process conditions. The instruments shall meet the brief technical requirements as specified elsewhere.
3.06.00 To ensure safe operation of C & I equipments located in hazardous areas, based on area classification requirement, transmitters shall be intrinsically safe and JB/Switch shall have ex-proof enclosures.
3.07.00 Safety earthing and C & I system earthing shall be separate. Safety earthing bus shall be connected to main plant earthing pit. Separate earth pits shall be provided for C&I system earthing (electronic earth) to achieve less than 0.5 ohm resistance to ground. Separate earthing shall be provided for intrinsically safe system.
3.08.00 All field mounted instruments shall have waterproof enclosures conforming to IP-65. All panels/cabinets shall have protection class IP-54 in ventilated areas and IP-42 in Air-conditioned area.
3.09.00 All field instruments shall be located in accessible/vibration free locations and clearly visible range for all readable instruments. Access platforms with ladders shall be provided for measuring instruments located at high or difficult places.
3.10.00 Separate cable trays shall be provided for control cables and instrumentation (signal) cables and separated from power cable trays by at least 600 mm.All cable entry points to instruments, junction boxes of panel shall be provided with suitable dust and watertight double compression type glands. All cables from field to junction box shall be through flexible conduit upto main tray/sub- tray.
3.12.00 Bidder to provide necessary provision in HT motors for vibration sensor as per API 670
4.00.00 DATA SHEETS FOR FIELD INSTRUMENTS AND CABLES
4.01.00 PRESSURE GAUGE (PG)
01. Quantity : As per Service Requirement 02. Make : As per approved vendor list 03. Sensing Element : Bourdon Tube 04. MOC sensing & socket : AISI 316 SS 05. Movement material : AISI 304 SS 06. Case material : Stainless steel casing bayonet type. 07. Accuracy : 1.0% of span or better.
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 7 of 39
08. Dial size : 150mm 09. Adjustment : Micrometer screw of zero adjustment. Internal micro meter screw for range adjustment 10. Scale : Black lettering on white background in 270 arc 11. Window : Shatterproof toughened glass 12. Process connection : NPTM, Bottom entry 13. Element connection : Argon welding 14. Safety device : Blow out disc/Diaphragm at the back 15. Enclosure class : IP 65 16. Ambient temperature : 0 50 C 17. Over range protection : 130 % of max range by internal stop. 18. Nameplate : Tag number, service engraved in SS plate. 19. Application standard : IS 3624 / 1996 20. Accessories : a) Snubbers for pulsating fluid application b) Syphons for steam services c) For viscous & corrosive services, Remote Seal with Silicon Oil Filled diaphragm seal adapter flanges with nuts, bolts and gasket 4.02.00 PRESSURE SWITCH (PS)
01. Quantity : As per Service Requirement 02. Range & Set Pressure : As per Service Requirement 03. Make : As per approved vendor list 04. Type : Seal Diaphragm 05. Sensing element material : SS316 diaphragm 06. Case material : Die-cast aluminum with neoprene gaskets. 07. Performance : a) Accuracy1.0% b) Accuracy of setting indicator of 1.5% c) Repeatability 1% of span 08. Over range : 150% of maximum pressure 09. Switch configuration : Two (2) Nos. SPDT type
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 8 of 39
10. Switch type : Snap acting, shock & vibration proof 11. Switch rating : 240 V, 5A AC / 220 V, 0.5A DC 12. Ambient temperature : 0- 50C 13. Adjustability : a) Set point adjustable over span range b) Differential adjustable by 10% span 14. Cable Entry : 3/4" ET 15. Enclosure class : IP 65 16. Process connection : 1/2 NPT (M) bottom connected. 17. Name plate : Tag number, service engraved in SS tag plate 18. Accessories : a) Snubbers for pulsating fluid application b) For viscous & corrosive services, Remote Seal with Silicon Oil Filled diaphragm Seal adapter flanges with nuts, bolts and gasket 4.03.00 PRESSURE TRANSMITTER (PT)
01. Quantity : As per Service Requirement 02. Make : As per approved vendor list 03. Principle : Smart 04. Type : 2 Wire Microprocessor based Transmitter 05. Output signal : 4 20 mA DC with HART Protocol 06. Signal processing : Silicon solid state electronic circuitry 07. Measuring element : Diaphragm 08. Measuring element material : AISI 316 (Stainless steel) Diaphragm 09. Static pressure : 150% of maximum span continuously without affecting the calibration. 10. Operating voltage : 24 V DC 11. Ambient temperature : 0-50 C 12. Performance a) Accuracy : 0.1% of span or better b) Repeatability : 0.1% of span or better 13. Turn-down ratio : Minimum 40:1 14. Load impedance : 600 Ohm min at 24V DC 15. Response Time : 100 msec or better 16. Span / zero adjustment : Locally adjustable, non- interacting facility for
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 9 of 39
Elevation & Suppression by 100% 17. Enclosure class : IP-65 18. Output Indicator : LCD type in % and engineering unit. 19. Cable Entry : ET 20. Process Connection : NPT 21. Nameplate : Tag number, service engraved in SS tag plate. 22. Body : Forged Carbon steel (SS for DM Water). 23. Accessories : a) Universal mounting bracket suitable for 2 pipe and wall mounting. b) Condensate pot for Steam services. c) High tensile carbon steel U bolts. d) Installation accessories e) 2 way SS manifold, constructed from SS316 bar stock. f) Reverse polarity protection required.
4.04.00 DIFFERENTIAL PRESSURE SWITCH (DPS)
01. Quantity : As per Service Requirement 02. Make, Model : As per Approved Vendor List 03. Type : Sealed diaphragm, piston actuated type for high pressure & diaphragm bellow and torque tube for low pressure. 04. Sensing element material : AISI SS-316 diaphragm / piston. All other wetted part SS316. 05. Case material : Epoxy coated steel plate or die- cast aluminum alloy with neoprene gasket and clear glass where applicable. 06. Scale : Black graduation on white linear scale. 0 100% with red pointer for set point. 07. Performance : a) Accuracy1.0% b) Accuracy of setting Indicator of 1.5% 08. Over range : Static pressure on any one side, the other side being open to atmosphere.
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 10 of 39
09. Switch configuration : Two (2) Nos, SPDT type 10. Switch type : Snap acting, shock & vibration proof 11. Switch rating : 240 V, 5A AC / 220, 0.5A V DC 12. Ambient temperature : 0 - 50C 13. Adjustability : a) Set point adjustable over span range b) Differential adjustable by 10% span 14. Cable connection : 3/4" ET compression gland 15. Enclosure class : IP 65 16. Process connection : 1/2 NPT (M) bottom connected. 17. Name plate : Tag number, service engraved is SS tag plate 18. Accessories : a) Snubbers for pulsating fluid application b) Retention ring & screw for surface mounting c) 1/2" NPT 5-way valve SS- 316 manifold constructed from bar stock. d) 3/4" ET cable gland.
4.05.00 TEMPERATURE GAUGE (TG)
01. Quantity : As per Service Requirement 02. Range : As per Service Requirement 03. Make : As per approved vendor list 04. Type : Mercury filled, rigid stem type 05. Sensing element material : Bourdon AISI 316 SS 06. Movement material : AISI 304 SS 07. Bulb diameter and length : 11/70mm 08. Bulb material : AISI 316 09. Case material : Stainless steel casing bayonet type 10. Accuracy : 1.0% of full scale deflection or better. 11. Dial size : 150mm 12. Scale : Black lettering on white background in 270 Arc 13. Window : Shatterproof toughened glass 14. Process connection : 1/2"NPT (M) 15. Mounting : Surface 16. Enclosure class : IP 65 17. Over range protection : 130 % of max range by internal stop. 18. Zero Adjuster : Micro adjustable from front 19. Nameplate : Tag number, service engraved in
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 11 of 39
SS tag plate. 20. Compensation : Case compensation 21. Thermowell : a. Standard : ASME - PTC 19.3 b. Body MOC : Stainless Steel - Barstock c. Process Connection : M33 X 2 Screwed d. Element Connection : NPTF e. Extension length : As per Service Requirement f. Insertion Length U : As per Service Requirement 22. Accessories : a) Installation accessories as required. b) Adjustable nipple union nipple with thermo well connection
4.06.00 THERMOCOUPLES (T/C)
01. Quantity : As per Service Requirement 02. Range : As per Service Requirement 03. Make : As per approved vendor list 04. Type : Duplex, ungrounded 05. Element : Type-K (Chromel / Alumel). 16 AWG Wire 06. Protecting Tube: i) O.D : 8 mm (approx) ii) Material : 316 SS Seamless iii) Filling : Magnesium Oxide (Purity above 99.4%) iv) Length : As per Service Requirement 07. Response time : < 20 seconds for measurement. 08. Head i) Type : IP-65 universal screwed type ii) Material : Die cast aluminum or better iii) Terminal blocks : Nickel plated brass screw type/silver plated iv) Cable connection : 3/4" ET v) Process Connection : NPTF vi) Others : Terminal head cover with SS chain and suitable gasket. 09. Standard : ANSI MC 94.1 10. Thermowell : a. Standard : ASME - PTC 19.3 b. Body MOC : Stainless Steel - Barstock c. Process Connection : M33 X 2 Screwed d. Element Connection : NPTF e. Extension length : As per Service Requirement f. Insertion Length U : As per Service Requirement 11. Accessories : a) Adjustable nipple-union-
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 12 of 39
nipple with thermo well connection 12. Nameplate : Tag number, service engraved in SS tag plate
4.07.00 RESISTANCE TEMPERATURE DETECTOR (RTD)
01. Quantity : As per Service Requirement 02. Range : As per Service Requirement 03. Make : As per approved vendor list 04. Type : 3 wire, Duplex, ungrounded 05. Element : Pt-100 0.1/100 0hm at 0C, 06. Protecting Tube: i) O.D : 8 mm ii) Material : 316 SS Seamless iii) Filling : Magnesium Oxide (Purity above 99.4%) iv) Length : As per Service Requirement 07. Response time : < 20 seconds for measurement. 08. Head i) Type : IP-65 universal screwed type ii) Material : Die cast aluminum or better iii) Terminal blocks : Nickel plated brass screw type/silver plated iv) Cable Entry : ET v) Process Connection : NPTF vi) Others : Terminal head cover with SS chain and suitable gasket 09. Standard : Standard DIN 43760 10. Thermowell : a. Standard : ASME - PTC 19.3 b. Body MOC : Stainless Steel Bar stock c. Process Connection : M33 X 2 Screwed d. Element Connection : NPTF e. Extension length : As per Service Requirement f. Insertion Length U : As per Service Requirement 11. Accessories : a) Adjustable nipple-union- nipple with thermo well connection 12. Nameplate : Tag number, service engraved in SS tag plate
4.08.00 TEMPERATURE TRANSMITTER (TT)
01. Quantity : As per Service Requirement 02. Make : As per approved vendor list 03. Principle : Smart with HART Protocol 04. Type : 2 Wire
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 13 of 39
05. Input : Thermocouple / RTD 06. Range : As per Service Requirement 07. Output signal : 4 -20 mA DC with HART Protocol 08. Signal Processing circuitry : Microprocessor based solid state electronic 09. Output indicator : LCD type 10. Body : Die Cast aluminum 11. Operating Voltage : 24 V DC 12. Ambient Temperature : 0 50 C 13. Performance : a) Accuracy : 0.2% of span or better b) Repeatability : 0.05% of span or better c) Cold Junction Compensation : Built-in 14. Load impedance : 600 Ohm min at 24V DC 15. Span / zero adjustment : Locally adjustable, non- interacting 16. Calibration : As Per N.I.S.T Monograph 125 for T/C 16. Enclosure class : IP-65 17. Cable connection : 3/4 ET 18. Nameplate : Tag number, service engraved on metallic tag plate rigidly fixed to the body. 19. Accessories : a) Universal mounting bracket suitable for 2 pipe and wall mounting. b) High tensile carbon steel U bolts. 4.09.00 TEMPERATURE SWITCH (TS)
01. Type : Mercury filled in 02. Sensing element material : Bellow / Bourdon AISI SS-316 03. Bulb Material : AISI SS 316 04. Capillary : Stainless steel armored 05. Movement Material : AISI SS - 304 06. Case Material : Epoxy coated steel plate or die- cast aluminum alloy with neoprene gasket and clear glass where applicable conforming to IP65. 07. Scale : Black lettering n white background. 08. Over range protection : 120 % 09. Instrument connection : Bottom 10. Switch configuration : Two SPDT Lead wires (3+3 Nos.) are to be brought externally to the male connector wherein
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 14 of 39
the female pug Connector will be inserted to connect the control room cables for easy removal & re - calibration. 11. Switch rating : 240 V, 5A AC / 220, 0.5A V DC 12. Switch Type : Snap acting, shock & vibration proof 13. Adjustability : a) Internal Set point adjustable over span range b) Differential adjustable by 10% span (min) 14. Cable Connection : 3/4" ET compression gland
15. Compensation : a) Capillary compensation with invar wire throughout the capillary length. b) Case compensation 16. Performance i) Accuracy : 1.0% of full scale ii) Repeatability : < 0.5% of full scale iii) Response time : < 40 seconds with thermo well 17. Capillary length : 5 meters (local) /15 meters (local panel) 18. Name plate : Tag number, service engraved is SS tag plate 19. Accessories : a) Mounting accessories, b) 3/4' ET cable gland.
4.10.00 LEVEL GAUGE (LG) FLOAT & BOARD
01. Make : As per approved vendor list 02. Service : As per Service requirement 03. Type : Float & Board type 04. Float material : SS-304 / 316 05. Float Wire : SS-304 / 316 06. Tank Height : As per Tank Height 08. Range : As per Tank Height 09. Scale : 4 broad Aluminium (in inches) 10. Accuracy : 2% of FSD 11. Bolts and nuts : Rust proof alloy steel 12. Process a. Operating temperature: As per Service Requirement b. Operating Pressure : As per Service Requirement 13. Accessories : a) Counter flange, nuts & bolts, suitable gasket etc. b) Wire Rope, Nylon Roller,
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 15 of 39
Mounting brackets & all other required fittings.
4.11.00 LEVEL GAUGE WITH SWITCH FLOAT & BOARD
01. Make : As per approved vendor list 02. Service : As per Process 03. Type : Float & Board Gauge with Low Level Switch 04. Float & Wet material : SS-316 05. Float Wire : SS-316 06. Tank Height : As Required 07. Range : As Required 08. Scale : 4 broad Aluminium (in inches) 09. Accuracy : 2% of FSD 10. Bolts and nuts : Rust proof alloy steel 11. Process a. Operating Temp. : As per Service Requirement b. Operating Pressure : As per Service Requirement 12. Switch configuration : Micro, SPDT type (2 Nos.) 13. Switch type : Snap acting, 2 NO+ 2 NC 13. Switch rating : 240 V AC, 5A / 220, 0.5A V DC 14. Adjustability : Set point adjustable over span range 15. Cable connection : 3/4" ET 16. Enclosure class : IP 65 17. Accessories : a) Counter flange, nuts & bolts, suitable gasket etc. b) Wire Rope, Nylon Roller, Mounting brackets & all other required fittings.
4.12.00 LEVEL SWITCH RF TYPE
01. Quantity : As per Service Requirement 02. Service : Coal Bunker 03. Height : As per Service Requirement 04. Make/Model : As per approved vendor list 05. Type : RF type 06. Mounting : Side mounted 07. Supply voltage : 230 V AC 08. Contact type : Snap acting, 2 NO+ 2 NC 09. Contact rating : 240 V AC, 5A / 220 V, 0.5A DC 10. Adjustability : Set point adjustable over span range 11. Performance :
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 16 of 39
a. Accuracy : 5% of FSR b. Dead band : 2% of FSR 12. Cable connection : 3/4" ET 13. Response time : less than 1 sec 14. Sensing element : SS 316 14. Coat guard shield : SS 316 15. Insulation : PTFE
4.13.00 RADAR LEVEL TRANSMITTER
01. a) Type : Guided wave Radar type transmitter b) Probe : Coaxial c) Probe material : SS 316 / SS 316L 02. Calibration Range : As per application 03. Process medium : As per application 04. Process temperature : As per application 05. Static pressure : Capable of working in vacuum also 06. Power supply : Range to be specified by the bid (loop power Available =24V DC) 07. Reverse polarity protection : Required 08. Output : 4 to 20 mA, 2Wire & HART 09. Accuracy : 10mm or better 10. Stability : As per process application 11. Communication : Communication / configuration shall be possible either through integral key pad and display or through hand communicator. If integral key pad is not available, one number hand held communicator common for all the transmitters shall be supplied 12. Load limitation : Max 600 ohm at 24V 13. Span & Zero : Adjustable 14. Flange Mounting : Yes 15. Environmental protection : IP 66 or better 16. Process connection : Traditional flange with - 18 NPT on flange with process adapters 17. Electronic housing : Aluminum alloy 18. Electrical connection : Preferably : 14 NPT with gland
4.14.00 ULTRASONIC LEVEL TRANSMITTER
01. Type of transmitter : Non contact Microprocessor based 2 wire type, HART protocol
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 17 of 39
Compatible 02. Output Signal : Galvanically isolated 4 20 mA DC along with superimposed digital signal (HART protocol) 03. Sensor Accuracy : 0.5% of calibrated span 04. Sensor Repeatability : 3 mm or better 05. Power Supply : 18 - 36V DC 06. Temperature Compensation : To be provided within transducer 07. Configuration : Sensor and electronic unit are separate. Electronic unit all be possible to mount on the accessible location near the transducer. All cables, weather proof fittings for connection between transducer and electronic unit. 08. Housing : IP 55 with durable corrosion resistant Epoxy coating 09. Calibration : Through HART communicator
10. Zero and Span adjustment : Continuous, Tamper proof, Remote as well as manual adjustability. Provision to calibrate the instrument without any level in the tank or sump etc. 11. Sensor Material : Corrosion resistant application to suit the individual 12. False signal tolerance : Facility to be provided. Shall have adjustable damping circuitry. 13. Range : To be decided during detail Engineering, with a facility to take care of frequency attenuation due to different obstructions (Surface, vapor) 14. Display : Minimum 4 character display with integral key pad, access protected features. 15. Diagnostics : Loss of echo alarm 16. Load impedance : 500 minimum or as per vendor spec. 17. Electrical connection : Plug and socket 18. Accessories : Canopy for protection sunlight and Rain Mounting hardwares
4.15.00 DISPLACER TYPE LEVEL TRANSMITTER
01. Type : Smart
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 18 of 39
02. Float movement : Vertical 03. Stages of operation : Continuous 04. Material a) Displacer/Float : AISI 316 SS/304 S b) Wire rope, sleeve pipe: AISI 304 SS/316 SS c) Torque tube : AISI 304 SS/316 SS/ Inconel 05. Transmission : 2-wire 06. Output Signal : 4-20 mA Protocol HART 07. Signal processing : Solid-state electronic circuitry 08. Static/overload pressure : Maximum static pressure without permanent deformation or loss of accuracy. 09. Turn-down ratio : 100: 1 minimum 10. Zero & Span : Easily accessible (local zero & span adjustment and non- interactive type) 11. Zero Suppression / elevation : i) Suppression = 150 % of span (min.) ii) Elevation = 50 % of span (min.). 12. Enclosure class : IP-65 (explosion proof for NEC class-1) 13. Body/Cage : Forged Carbon Steel or Stainless Steel depending upon fluid condition 14. Output Indicator : LCD type 15. Output Ripple : < 0.25% of span 16. Operating voltage : 16 48 V DC 17. Nameplate : Tag number and service engraved in SS tag plate 18. Ambient Temperature : 0 - 50C 19. Load Impedance : 600 Ohms at 24 Volts (minimum) 20. Process connection : 50 NB ANSI RF Companion flange with nuts, bolts and gaskets 21. Performance a) Accuracy : 0.5 % of span or better b) Repeatability : 0.05 % of span or better c) Sensitivity : 0.1 % of span or better d) Hysteresis : 0.05 5 of span or better e) Temperature : < 0.5 % of span / 50C regardless of rate of calibration change. f) Power supply effect : 0.005 % / volt 22. Accessories : i) ANSI RF Counter Flange; rating as per process pressure.
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 19 of 39
Necessary nuts, bolts, gaskets etc. ii) Vent and drain plugs iii) Stilling chamber v) 3/4" ET cable gland 23. Preferred Features : a) Test plug connection and cutout terminal physically separated from other electronics. b) Electronic Damping facility (adjustable)
4.16.00 DP TRANSMITTER (LT & FT)
01. Quantity : As per Service Requirement 02. Make : As per approved vendor list 03. Principle : Smart with HART Protocol 04. Type : 2 Wire Microprocessor based Transmitter 05. Output signal : 4 20 mA DC with HART Protocol 06. Signal processing : Silicon solid state electronic circuitry 07. Measuring element : Diaphragm 08. Measuring element material : AISI 316 (Stainless steel) Diaphragm 09. Static pressure : 150% of maximum span continuously without affecting the calibration. 10. Operating voltage : 24 V DC 11. Ambient temperature : 0-50 C 12. Performance a) Accuracy : 0.05% of span or better b) Repeatability : 0.05% of span or better 13. Turn-down ratio : 100:1 14. Load impedance : 600 Ohm min at 24V DC 15. Response Time : 100 msec or better 16. Span / zero adjustment : Locally adjustable, non- interacting facility for Elevation & Suppression by 100% 17. Enclosure class : IP-65 18. Output Indicator : LCD type in % and engineering unit. 19. Cable Entry : ET 20. Process Connection : NPT 21. Nameplate : Tag number, service engraved in SS tag plate. 22. Accessories : a) Universal mounting
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 20 of 39
bracket suitable for 2 pipe and wall mounting. b) High tensile carbon steel U bolts. c) Installation accessories d) Condensate Pot for steam service e) 5 - way SS manifold, constructed from SS316 bar stock. f) Reverse polarity protection required.
4.17.00 ROTAMETER
01. Quantity : As per Service Requirement 02. Type : Online Reading 03. Process Parameter : As per Service Requirement 04. Accuracy : 1% of FSD 05. Scale : Graduated-Engraved Black lettering on white background, in m/hr 06. Body : SS-316 07. Tube : Borosilicate glass 08. Float : SS-316 09. Stopper : SS-316 10. Gland packing : PTFE 11. End connection size/Type : As per Service / Flanged to ANSI B16.5 CL150 12. Pressure drop : As per Requirement 13. Range : As per Requirement
4.18.00 FLOW ORIFICE
01. Quantity : As per Service Requirement 02. Service : Feed Water 03. Design Standard : BS- 1042 04. Flow element & type : Orifice / Concentric 05. Flow element material : SS 316 06. Flow element thickness : 3mm minimum 07. Pipe material : SA 106 GR B 08. Flange Material : SA 106 GR B 09. Type of tapping : Corner tapping 10. Number of tapings : Two pairs
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 21 of 39
11. Beta ratio : 0.4 to 0.7 12. Pressure loss (meter max) : 0.7 Kg/Cm2 13. Process Parameter : As per Table 14. Service : Feed Water 15. Flow Rate (Nor/ Max.) TPH : As per Service Requirement 16. Pressure (Kg/Cm 2 ) : As per Service Requirement 17. Temperature C : As per Service Requirement 18. Density : 1 19. Pipe Size / MOC : As per Service Requirement 20. End Connection : As per Service Requirement 21. Accessories : SS316 Flanges, 1/2" root valves (Globe), 1/2" Nipple (2 nos. of Root valves if upstream pressure >40 Kg/cm2) Note: The following Drawing / Document shall be submitted along with each instrument. GA drawing Data Sheet Flow orifice sizing calculation Flow Vs Differential pressure curve
4.19.00 FLOW NOZZLE
01. Quantity : As per Service Requirement 02. Service : As per Service Requirement 03. Design Standard : BS-1042 04. Flow element & type : Flow Nozzle/ Long Radius 05. Flow element material : Alloy Steel 06. Pipe material : SA 335 P22 07. Pipe size : As per Service Requirement 08. End connection : Butt Weld 09. Type of tapping : D and D/2 10. Number of tapings : Two pairs 11. Beta ratio : 0.5 to 0.7 12. Pressure loss (meter max) : 0.4 Kg/Cm2 13. Service : As Required 14. Flow Rate : As per Service Requirement 15. Flow Rate (Nor/ Max.) TPH : As per Service Requirement 16. Pressure (Kg/Cm 2 ) : As per Service Requirement 17. Temperature C : As per Service Requirement 18. Density : As per Service 19. Pipe Size / MOC : As per Service Requirement 20. End Connection : Butt Weld 21. Accessories : 1/2" root valves (Globe), 1/2" Nipple Test: The Following test shall be carried out along with supply of instrument:
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 22 of 39
100% Radio graphic. Hydro test. Calibration test. IBR test Certificate. Note: Drawing/ Document shall be submitted along with supply of instrument: Fabrication & assembly drawing Data Sheet Flow Nozzle sizing Calculation Flow Vs Differential pressure curve
4.20.00 FLOW SWITCHES (FS)
01. Type : Flapper 02. Material of sensing element : PP / Die Cast Aluminum, stoved, enameled With anticorrosive paint 03. Flow range and surge ratio : Later 04. Accuracy : 1 % 05. Contacts type, rating : Two (2) Nos, SPDT type with snap action 06. Enclosure class : IP 65 07. Connection Instrument/ : As per process requirements / NPT (F) Conduit 08. Accessories : Isolation valve, drain and vent plug on external cage, Bolt/Nut and gaskets.
4.21.00 MASS FLOW METER
A. Sensor 01. Measuring principle : Coriolis Mass flow. 02. Primary Element : Flow tube of 316 SS or better 03. Heating Arrangement : Integral with Flow Element 04. Temp. control for heating : To be provided 05. Process connection : ANSI RF Flanged and rating as per process required. 06. Drain : Self-draining facility 07. Accessories : Counter flanges, mounting nuts, bolts, gaskets etc. B. Transmitter 01. Measured quantities : Mass Flow rate, Total Mass Flow, Density, Temperature as minimum 02. Input Signal Processing : Digital processing 03. Display : Digital Display (LCD).
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 23 of 39
04. Output : 2 Nos. isolated output of 4-20mA DC selectable from four measured quantities. 05. Load : <750 ohms 06. Power supply : 240V AC, 50 HZ. 07. Turn Down : 100:1 08. Accuracy : 0.2% of measured value 09. Ambient Temperature : 85 10. Repeatability : 0.05% 11. Housing : IP 65(Explosion proof for NEC Class-1) 12. Hazardous duty version : FM Standards. 13. Nameplate : Tag number, service engraved in SS tag plate 14. Accessories : a) As required for field mounting b) Handheld configurator c) Mounting U-bolts, nuts, prefab cable etc. d) ET cable gland.
4.22.00 MOTORISED VALVES
01. Quantity : As per Service Requirement 02. Valve service : Main Steam 03. Valve type : Gate Valve 04. Pipe size inlet / outlet : 250NB Sch 140 / 250NB Sch 140 05. Pipe MOC : SA-335 P22 06. Guiding : Later 07. Type of connection : Flanged 08. Material i) Valve body : Later ii) Stem : ANSI -316 SS iii) Seat rings : ANSI -316 SS iv) Plug : ANSI -316 SS v) Bonnet gasket : Later 09. Port size : Later 10. Plug type : Later 11. Plug characteristic : Later 12. Differential pressure : Later 13. Maximum flow capacity : a. Normal Flow in TPH : As per Service b. Maximum Flow in TPH: As per Service c. Operating Temp in O C : As per Service d. Up steam Operating Pressure in Kg/cm 2 :
As per Service e. Down steam Operating Pressure in Kg/cm 2 :
As per Service
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 24 of 39
14. Valve stem packing : Later 15. Type of actuator : Motor operated 16. Actuator make / model : Later 17. Signal range : Later 18. Integral Bypass Valve : 25NB Motorized Integral Valve with All accessories 19. Accessories included : Electric motors, Position limit switches & Torque limit switches, Hand wheel, gear train, mechanical position indicator, internal wiring, integral starters and terminal block etc., 20. Noise ratio : < 85 db 21. Leakage class : Class IV 22. Minimum clearance required : As per standard for maintenance purposes 23. Integral Bypass Valve : 25NB Motorized Integral Gate Valve with all accessories 24. Make : As per approved vendor list.
4.23.00 CONTROL VALVE
01. Quantity : As per Service Requirement 02. Make : As per Approved Vendor List 03. Valve service : Later 04. Valve type & size : As per process requirement 05. Valve co-efficient : Later 06. Connection size inlet / outlet : As per process parameter 07. Guiding : Later 08. Type of connection : Later 09. Material i) Valve body : Later ii) Stem : ANSI -316 SS iii) Seat rings : ANSI -316 SS iv) Plug : ANSI -316 SS v) Bonnet gasket : Later 10. Port size : Later 11. Plug type : Later 12. Plug characteristic : Later 13. Differential pressure : Later 14. Maximum flow capacity : Later 15. Valve stem packing : Later 16. Type of actuator : Pneumatic actuator 17. Actuator make & model : Later 18. Signal range : Later 19. Action on air failure : Fail to open or fail to close in a
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 25 of 39
direction safe for the process 20. Accessories included : Hand wheel, Limit switches, I/P Converter, air lock relay, position transmitter and JB etc. 21. Noise ratio : < 85 db 22. Leakage class : IV 23. Min. clearance required : As per standard for maintenance purposes 24. Process Parameters: a) Process Pressure : Later b) Process Temperature : Later c) Process Flow : Later d) Line Size : Later
4.24.00 SOLENOID VALVE
01. Operating Principle : Electromagnetic (noiseless) Latch / release coil shall be used in the required application where the safety is to be ensured. 02. Coil voltage rating : 240 V AC /110V AC / 24 V DC / 48 V DC / 220 V DC (As required). 03. Ways : 3 ways (NO + NC) [General], other Depending on requirement 04. Port size : 1/2" NPT / as per site requirement 05. Body : SS Bar Stock 06. Trim : AISI SS-316 07. Manual operator : In built 08. Duty : Suitable for continuous energization 09. Sealing : Airtight and leak proof 10. Ambient temperature : 0 - 50 O C 11. Fluid temperature : 0-150 O C or as per application 12. Coil enclosure : Stainless Steel 13. Insulation : Class-H 14. Coil casing : IP-65 (Explosion proof for NEC Class-1) 15. Mounting : On pipe or on panel 16. Cable connection : 3/4" ET Compression gland 17. Accessories : Mounting brackets, nuts and bolts 18. Pressure Rating : As per application 19. Special feature : i) Temperature operated fuse at explosion proof
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 26 of 39
enclosure. ii) Solenoid valve directly integral to actuator body shall have NAMOOR interface.
4.25.00 ELECTRO-PNEUMATIC CONVERTER (I/P)
01. Quantity : As per Service Requirement 02. Make : As per approved vendor list. 3. Type : Electro-Pneumatic Input 4. Input : 4-20 mA DC 5. Output : 0.2 to 1.0 kg/cm 6. Direct/reverse action : Provided 7. Enclosure class : IP 65 8. Mounting : Field (Pipe& wall) mounting 9. Air filter regulator : Sintered bronze, 5 Microns, 10Kg/cm 10. Output gauge : Provided 11. Connections : ET / NPT (Electrical/ Pneumatic) 4.26.00 AIR FILTER REGULATOR
01. Quantity : As per Service Requirement 02. Make : As per Approved Vendor List 03. Filter element : Sintered Bronze 04. Filter size : 5 microns 05. Input air : 10.0 Kg/Sq.cm (maximum) 06. Output : Adjustable from 0- 2.0 Kg / cm or 0 7.0 Kg/Sq.cm (continuous) as applicable. 07. Effect of supply : Maximum 0.002 Kg/Sq. cm for a change pressure variation in supply pressure of Kg / Sq.cm 08. Bowl material : Metallic cover around high Temperature Area / clear transparent polycarbonate with metallic cover for ordinary applications. 09. Accessories : 2" dial size output pressure gauge 10. Desirable feature : No perceptible drop of pressure on opening the drain port. 4.27.00 JUNCTION BOX
01. Quantity : As per Service Requirement 02. Make : As per Approved Vendor list 03. Type : Flame proof/weather proof
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 27 of 39
04. Enclosure : IP-65 05. Material : Die cast aluminum with protective coating 06. Cable entry : Bottom 07. Cable glands : Double compression type Nickel plated brass with PVC hoods. 08. Mounting : Outdoor 09. No. of terminals : As required with standardization 10. Terminals : Phoenix/Wagon 11. Grounding : Two terminals for body and shield ground 12. Door : Hinged, lockable type.
4.28.00 POSITIONER
01. Stroke Adjustment : Shall be possible. 02. Gauges : Supply, signal, output 03. Travel time of valve : < 10 seconds 04. Hysteresis : 0.5% of F.S. 05. Linearity : 1.0% of F.S. 06. Dead Band : 0.5% of F.S.
4.29.00 LIMIT SWITCH (LS)
01. Type : Dust proof momentary spring return 02. Operating head : Adjustable roller Lever (32-82.5 mm) with 19 mm Dia and 8 mm Dia Vide metal Roller. 03. Accuracy and differential : 0.2% of full scale 04. Differentialfixed/ adjustable : Adjustable 05. Contact Arrangement : SNAP Action 06. Number of contacts : 2 Normally Open (NO) & 2 Normally Closed (NC) 07. Contact rating : 5A, 240V/0.25A, 220V DC 08. Outlet Pressure gauge range : 50 mm diameter Range (0 -10) 09. Operating temperature range : Later 10. Cable Entry : 3/4" Double compression cable gland 11. Enclosure class : IP 65 13. Accessories : Isolation valve, drain and vent plug on external cage
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 28 of 39
4.30.00 Control &Instrumentation Cables
4.30.01 600V GRADE SINGLE PAIR TWISTED INSTRUMENTATION SIGNAL CABLE
CONSTRUCTION
a) Conductor: Each core shall be seven stranded annealed copper electrolyte grade conductor of cross section 1.0 mm2 generally complying to IS-8130.
b) Insulation: Each core shall be provided with extruded HR PVC conforming to IS:5831 Type 'C'. Insulation thickness shall be >=0.8 mm and shall conform to relevant IS/other standard. Color of insulation shall be white and black in a pair.
c) Twist: Every 2 core shall be twisted to form a pair and number of twist shall be 20 twist per meter.
d) Shielding: The individual pair shall be shielded. Shield shall be Aluminium backed by Mylar tape bonded together side down helically applied with either side 25% overlap and 100% coverage. Minimum shield thickness shall be 0.05mm Drain wire shall be 0.5 sq mm multi stranded bare tinned annealed copper conductor. The drain wire shall be in continuous contact with aluminium side of the shield.
e) Inner sheath: Cables shall be provided with extruded HR PVC inner sheath as per IS 5831 type ST1. The color shall be black and minimum thickness shall be >= 0.4 mm. f) Armouring: Armouring applied over inner sheath shall be of galvanised steel wire 1.4 mm dia as per IS 1554 part I and IS 3975.
g) Overall sheathing: The cable shall be sheathed with extruded HR PVC type ST1 as per IS 5831 Color of sheath be Black. Thickness of the sheath shall be as per IS 1554 Part. I and >= 1.24 mm. FRLS PVC outer sheath shall be provided.
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 29 of 39
4.30.02 600V GRADE MULTIPAIR TWISTED INSTRUMENTATION SIGNAL CABLES
GENERAL
Multi pair twisted instrumentation cables shall be same as Single pair shielded cable.
Following additional features shall be applicable: -
a) Conductor: Each core shall be seven stranded annealed copper electrolyte grade conductor of cross section 0.75 mm2 generally complying to IS-8130.
b) Shielding: In addition to individual shielding of pair, overall shielding shall be provided. Overall shield shall be Aluminium backed mylar tape helically applied with metallic side down either side 25% overlap and 100% coverage. Shield thickness shall be 0.075 mm. Drain wire shall be similar to individual pair drain wire and shall be in continuous contact with the Aluminium side of the overall shield.
b) Twist: Overall twist of all pair shall be as per manufacturer standard
c) Pair-Identification : Pairs shall be identified by printing pair numbers by black indelible ink on the white core at interval not more than 250 mm. Conductor insulation shall be black and white for each pair.
4.30.03 600V GRADE SINGLE TRIAD SHIELDED CABLE
600V grade single triad cable shall be same as Single pair shielded cable.
4.30.04 600 GRADE MULTI TRIAD SHIELDED CABLE
600V grade multi triad cable shall be same as Multi triad shielded cable.
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 30 of 39
4.30.05 1100V GRADE 2 CORE CONTROL CABLE
CONSTRUCTION
a) Conductor: Each core shall be seven stranded annealed tinned copper conductor of cross section 1.5 mm2 generally complying to IS 8130.
b) Insulation: Each core shall be provided with extruded HR PVC insulation conforming to IS 5831 Type 'C'. Insulation thickness shall be >= 0.8 mm. Color of core insulation shall be black with core numbers printed in white indelible ink at max. 150mm apart on each conductor.
c) Inner sheath: Cables shall be provided with extruded HR PVC inner sheath as per IS 5831 type ST1. The color shall be black. Thickness of sheath shall be >= 0.3 mm.
d) Armouring : Armouring applied over inner sheath shall be of galvanised steel wire 1.4 mm dia. as per IS 1554 part I and IS 3975.
e) Overall : The cable shall be sheathed with extruded HR PVC sheathing type ST1 as per IS 5831. Colour of sheath shall be black. Thickness of the sheath shall be >= 1.24 mm as per IS 1554 part-I. FRLS PVC outer sheath shall be provided.
4.30.06 1100V GRADE Multi core control cables
Multi core control cables shall be same as two core control cable except for the following features. a) Conductor: Each core shall be seven stranded annealed tinned copper conductor of cross section 0.75 mm2 generally complying to IS 8130.
The core identification can be done by numbers. In that case, the insulation of cores shall be of same color and number sequentially sorting with number 1 for inner layer. The number shall be printed in Hindu Arabic numerals on the outer surface of the cores. (All the numbers shall be of same color which shall contrast with the color of the insulation. The numerals shall be 1 eligible. Bidder may alternately offer color coded conductors).
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 31 of 39
4.30.07 Fibre Optic Cable (Mono type)
i. Cable Type : Mono-mode with minimum 4 fibers ii. Wavelength band optimized : 850nm / 1300nm / 1550nm iii. Mode field diameter : 9-10m + 10% of nominal value iv. Cladding diameter : 125m + 3 Non-concentricity core / Cladding : not more than 2m Non-circularity of cladding : not more than 3m vii. Cut-off wavelength : 1200nm viii. Attenuation : 1. less than 0.3-0.4 dB/km at 1300nm 2. less than 0.15-0.25 dB/km at 1550nm Fibre optic cables shall be Rodent proof type and shall be laid through 30 mm dia HDPE conduit
4.30.08 Fibre Optic Cable (Multi type)
i. Cable Type : Multi-mode with minimum 4 fibers ii. Core / cladding diameter : 62.5 / 125 m iii. Jacketing Material : Halogen Free, Flame Retardant, Low Toxicity iv. Attenuation @ 850 nm : Length (m) x 0.0035 db/m+2db maximum v. Outside Diameter : 8.10 mm (0.324 in) vi. Minimum Bend Radius : 12.5 cm (5 in) vii. Minimum Bend Radius : 7.5 cm (3 in) (Long term) viii. Cable Assembly : Tensile Load for attenuation increase <0.5 db: 300 N (66 lb) maximum ix. Tensile Load at Installation : 1776 N (400 lb) max. x. Connector Tensile Load MIC : 133 N (30lb) xi. Minimum Crush Resistance : 46 N /cm (250 lb /in) Fibre optic cables shall be Rodent proof type and will be laid through 30 mm dia HDPE conduit
5.00.00 CODES & STANDARDS
5.01.00 GENERAL
5.02.00 All equipment, systems and works covered under the Bidders scope shall comply with all statutory regulations and safety codes as applicable internationally and in locality where the equipment will be installed.
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 32 of 39
5.03.00 The Bidders scope of supply shall include some items such as thermowells, control valves and other in-line devices for main steam, feedwater system, falling under the purview of Indian Boiler Regulation (IBR) Act. It shall be the responsibility of the Bidder to obtain the necessary approval of the concerned Inspecting Authority/Chief Inspector of Boilers for the design and design calculations, manufacturing and erection procedures as called for under the Indian Boiler Regulations Act. 5.04.00 The design, manufacture, inspection, testing and erection of the equipment covered under this Specification shall conform to the standards and codes (latest editions) including but not be limited to those mentioned below. Contractor shall refer to the latest revision of all codes and standards.
Bidder shall however, follow sound Engg. practice throughout.
Temperature Measurement -ASME PTC 19.3 ANSI MC 96.1 IEC 751, IEC584.2 BS 1401 IS 2806
Pressure Measurement -ASME PTC 19.2 IEC 381 IS 3624
Flow Measurement -ASME PTC 19.5 BS 1042/ ISO 5167
Control Valves - ISA S 75.01-75.05 ANSI B16.34 ANSI B16.10
Sampling System -ASME PTC 19.11 ASTM D1198 ASTM A 269
Enclosures -IEC 529 IEC 79 (Hazardous) IS 2147/IS 13947
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 33 of 39
Cables - IEEE 383 BS 6746 IS 5831 BS 5308 BS 6346 IS 10810 IS 1554 BS 6360 IS 694 IS 8130 BS 6500
6.00.00 INSTRUMENT INSTALLATION
6.01.00 General a) Instrument process tubing and instrument air tubing to be designed in accordance with the instrument installation drawings.
b) All instruments, process connections, including isolation valves and associated devices, shall be located in easily accessible locations for maintenance, calibration and replacement. All maintenance, calibration and replacement operations on a given device must be possible without interruption of service to adjacent equipment.
c) Instrument mounting height shall 4 - 6 above equipment base or platform.
d) Instrument tubing installation are designed in accordance with ANSI B31.1 Power Piping.
6.02.00 Instrument Sensing Lines
a) All impulse pipe shall be of seamless type conforming to ANSI B36.10 for schedule numbers, sizes and dimensions etc
b) Minimum bending radius of instrument sensing lines 3 times the tube diameter.
c) Instrument sensing lines are sloped in their horizontal runs, a minimum of 1/2 per foot. In general, liquid and steam lines slope from their process tap connection down to the instrument. In general, gas and non-condensing vapor lines slope from their process tap connection upto the instrument.
d) Instrument sensing lines shall be routed as directly as practicable from the process root valve to the instrument. The length of instrument tubing from the root valve to the instrument shall be limited to maximum of 12 meters for compressible fluids and 15 meters for non-compressible fluids.
e) Instrument sensing lines are grouped together as much as possible to benefit from the use of common support members and to present a finished installation that is routed in a neat and orderly manner. Care is exercised to assure that spacing between adjacent tubes in the same
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 34 of 39
group is maintained uniform and that tubes do not cross under or over one another at any point. Changes in direction of tubing is done by the use of tube bends and not tube fittings.
f) For connection to gauge or transmitter or switch compression tube fittings will be used.
g) A single blow down valve or double blow down valves (if the process root valves are doubled) shall be installed to the sensing lines of all pressure transmitters that are tapped off liquid or steam process systems. These valves shall be located at the instrument and may be brought together to the header.
h) The maximum process temperature for all transmitters shall be limited to 80 o C. To dissipate the excess heat, a maximum of 1 meter of tubing for each 30 o C of excess heat shall be installed to isolate the process media from the instrument. An additional isolation valve shall be used at the instrument for isolation on those instruments without valve manifolds.
6.03.00 Instrument Air Lines
a) Instrument air lines shall be of stainless steel..
b) Minimum bending radius of instrument air line tubing is 3 times the tube diameter.
c) All branch lines from the instrument air line header are made from the top of the air header and shall not be smaller than 1/2 inch. Branch lines have a root valve at the process connection.
d) In areas with multiple air users, an instrument air manifold is used. The branch from the air header to manifold is 1 inch, with a 1-inch isolation valve at the manifold. The manifold consists of a 3 inch pipe with a caps, 3/8 inch air takeoff connections with 3/8 inch shutoff valves, and a 1/2 drain valve. A six and eight air user, manifold design, will be used.
6.04.00 Instrument Mounting
a) Instrument mounting shall be in accordance to standard hook-up details and mounting details.
b) Spacing between multiple instruments mounted on the same support shall be sufficient to allow ample clearance area in order to perform service, maintenance, calibration and testing.
6.05.00 Instrument Wiring
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 35 of 39
6.05.01 General The two-wire system shall be employed for transmission of signals from electronic transmitting instruments. Electronic instrument wiring shall be done as per manufacturers standards and multicore cables shall be used wherever practical. Special, screened, shielded or co-axial cables shall be used as required and as such, these special cables shall be supplied by the Contractor.
6.05.02 Conduit
Compensating and screened cable shall, in general, be installed in rigid conduit. All special cable including compensating cables required for the plant shall be included in Contractors scope.
6.05.03 Terminal Box
Except for thermocouple cables terminal/junction boxes shall be used for the interconnection of control wiring and instrument signal wiring. Terminal boxes of a type approved for area classification shall be provided for terminating multicore control wiring. NEMA-3 standard type of better enclosures shall be used for junction boxes. 20 % spare terminals shall be provided in the junction box.
6.06.00 Wiring Practices
6.06.01 The signal cable shield shall not be used as a signal conductor. The signal cable shall not be spliced. The cable shield shall be maintained at a fixed potential with respect to the circuit being protected.
6.06.02 Low level signal cable shall be terminated with short untwisted length of wire, which should have as minimum area as practicable to be exposed for inductive pick-up. Low level signal cables should be separated (isolated) from noisy & power circuits by practicable large distance. Signal cables should not cross each others, if at all required, crossing shall be at right angles, and at a large practical distance.
6.06.03 Instrument cubicle/panel wiring shall be such that minimum crossing of signal cables are encountered. Instrument/device located in left (and right) hand side of panel/cubicle should be terminated in left (& right) side terminal block respectively so as to minimise intercrossing of wires in panel/cubicles.
6.06.04 Unused shielded conductors in a low level signal cable shall be single end grounded at the opposite end.
6.06.05 Earthing plate for all electronic instruments shall be away from common electrical earthing point. A signal circuit shall be grounded either at the transmitter end or at the instrument end.
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 36 of 39
6.06.06 All Cables to be terminated in Junction Box/Panel shall be through cable glands.
6.06.07 All instrument cables like signal cable, communication cable, supply cable should have separate color code and cables should be distinguished from electrical cables. Signal cables and control cables should be put in cable trays separate from that of power cables.
6.06.08 All cables should have traceability from field to JB and JB to DCS/Panel with identification ferrules. The cabling should be documented properly so that it can be useful for future maintenance.
7.00.00 DATA AND DOCUMENTS TO BE FURNISHED BY THE BIDDER ALONG WITH BID
Bidder shall furnish all required information/data sheet/drawing/document required to facilitate full appreciation of bid which shall include but not limited to following :-
a) Proposed control philosophy along with Control system configuration diagram. a) Filled up Technical Particular Sheets/Schedules. b) Details of C & I and PLC System offered c) Tentative I/O counts d) Details of hardwired controls and indication (if any). e) List of deviation from Specification document. f) Vendor list of instrumentation items.
DATA AND DOCUMENTS TO BE FURNISHED BY THE CONTRACTOR
a) Operational Philosophy. b) Control system configuration diagram. c) Description and write-up of control scheme and interlocking system.
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 37 of 39
d) Complete Local Control room layout drawings with foundation, GA details of all panels, desks and consoles, wherever applicable. e) Interconnection cable schedule (ICS) and cable schedule between instruments JBs & I/O cabinets. f) Cabinet / Panel wiring diagrams and internal layout drawings g) Cabinet / Panel terminal details h) Wiring diagrams for panel, local panel, junction boxes, actuators,etc i) Proposed Graphics/Mimic displays and logs. j) Control schemes/logic diagram. k) Flow element and Control valve sizing calculations and dimensional drawings. l) Interconnection Diagram of different PLCs / C & I systems and the DCS showing all hardware details. m) Complete Instrument Schedule. n) Junction Box Schedule o) FAT procedure p) Heat load, Power consumption and air consumption data q) Calibration test & quality assurance test procedure and test certificates. r) Shop and site Test Records. s) Manuals & technical literature for instruments/ equipments. t) Instrument installation diagram showing all erection hardware. u) Power supply arrangement for field mounted instruments/panels/sub systems. v) 'As built' status drawings.
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 38 of 39
ANNEXURE-I-DRIVE CONTROL PHILOSOPHY
Drive Control Philosophy: Control philosophy for interfacing of MCC/SWGR./Actuator with PLC/DCS is as follow:
a. Bi-directional drives (inching or open/close) -
All Motor operated valves/dampers are integral type. The following interface between PLC and valve integral starter:
i. Potential free On-Off commands from PLC to integral starter. ii. Speed output (For VFD Drives)
Feed backs from integral starter to PLC shall include:
i. Open limit switch feedback ii. Close limit switch feedback iii. Open torque switch feedback iv. Close torque switch feedback v. Integral Starter Disturbed (Loss of power/control supply, thermostat trip, Thermal O/L, Torque open/close, Local/off/Remote S/S in Local or Off mode etc.) vi. Position Transmitter Feedback (For Inching Type drive)
b. Unidirectional LT Drives
LT drives like Pumps and Fans shall have the following interface with PLC and MCC:
i. Potential free On-Off commands from PLC to MCC. ii. Speed output (For VFD Drives)
Feed backs from MCC to PLC shall include:
i. On/Running ii. Off/stop iii. Switchgear/MCC Disturbance (when Thermal O/L, control power supply fails, MCC power supply is isolated, EPB OPTD, S/S not in Remote). iv. Current Feedback for motor rated >30KW v. Speed (For VFD drives)
c. Unidirectional HT Drives
HT Drives like pumps and fans shall have the following interface with PLC and MCC:
i. Potential free On-Off commands from DCS to MCC. ii. Speed output (in case of VFD)
SPECFICATION FOR AIR COOLED CONDENSER
PROJECT 1 x 300 MW COAL BASED THERMAL POWER PLANT, CHHATTISGARH, INDIA Doc. No. 11V02-201-SPC-M-0001, REV.R0 Date: 04-11-2011 VOL-II PART-C Page 39 of 39
Feed backs from MCC to PLC shall include:
i. On/Running ii. Off/Stop iii. Switchgear/MCC Disturbance (Overload relay operated, control supply fail, Emergency LPBS operated) iv. Switchgear/MCC Available (Breaker in service position, Switchgear in remote & breaker spring charged, lockout relay reset) v. Breaker in test position vi. Current Feedback vii. Speed Feedback (in case of VFD)
d. Solenoid Drives
Solenoid operated drives shall have the following interface with PLC: i. Energize ii. De-energize iii. Open limit switch feedback iv. Close limit switch feedback
e. Pneumatic Drive
Pneumatic operated drives shall have the following interface with PLC:
i. Command to I/P converter ii. Position Transmitter Feedback iii. Open limit switch feedback iv. Close limit switch feedback v. Command to solenoid valve (Wherever Applicable)