Project: Development of Palm Deira Client: NAKHEEL
Main Contractor: ZSML MEP Contractor: BBAE
METHOD STATEMENT O !NSTALLAT!ON O !NS"LAT!ON ON D"CT#O$K !NSTALLAT!ON O !NS"LAT!ON ON D"CT #O$K %&' SCOPE O #O$K To define the method of installing closed cell elastomeric insulations of 48-98 Kg/m3 on duct works to ASTM C34 (&' $ESPONS!B!L!T) !efore commencement of an" installation acti#it"$ the following %rocedures are re&uired to 'e carried out( )(* All materials used must ha#e an a%%ro#ed material su'mittal( )() All works shall 'e installed as %er a%%ro#ed construction drawings( )(3 All works shall 'e installed in a neat and tid" fashion( *&' DESC$!PT!ON O #O$K *&% Preparation #or+ ,- BBAE !efore the commencement of an" ducting installation the following works are to 'e carried out( 3(*(* Check ductwork to 'e installed as indicated on a%%ro#ed construction drawings( 3(*() Check materials to 'e used ha#e an a%%ro#ed material su'mittal( 3(*(3 Check work area is clean and safe( *&( !n.tallation Proce/0re +uct work installation using closed cell elastomeric ru''er insulation of *9mm thick 3()(* Clean the surface of duct( 3()() A%%l" foster adhesi#e 8*-*, or e&ui#alent a%%ro#ed( 3()(3 -i. stuck %ins/ +"rod"ne$ where steel %ins are used$ as in the sam%le cut ends close to the surface and seal with A 3, . 3, S0-T to co#er with 1, . 1, Alu 2 3lass ta%e( 3()(4 -i. Aerofle. of 48-98 K3/m3 +ensit" ha#ing thickness *9mm as re&uired( 3()( Seal the longitudinal 4oints with self-adhesi#e ta%e of 1) mm wide( 3()(5 6einforce the longitudinal ta%e seal with cross ta%ing at 5,,mm centers with *, mm o#erla% on either side( 1&' LABO"$2 PLANT 3 MATE$!AL $E4"!$EMENTS 4(* The material shall 'e of a%%ro#ed Manufacturer as %er the material su'mittal( 4() Skilled technicians$ in sufficient num'ers$ shall carr" out the installation( 4(3 The workmanshi% shall 'e maintained at all times( 5&' S"PE$6!S!ON A$$AN7EMENTS (* A constant su%er#ision '" the foreman and su%er#isor shall 'e carried out in order to control the work and the workmanshi%( () 7.%erienced su%er#isors shall 'e a%%ointed to carr" out the work smoothl" and to ha#e the full control of the la'our( 8&' TEMPO$A$) #O$KS TO BE DES!7NATED AND !NSTALLED& 8/A 9&' HEALTH AND SAET) $E4"!$EMENT 9&% 7nsure work area is clean and tid"( 9&( 7nsure the work Area is well #entilated( 9&* All em%lo"ees shall ado%t safe working %ractices( 9&1 Safet" e&ui%ment 9e.am%le :ard :ats$ Safet" Shoes$ Co#eralls$ 3lo#es$ 3oggles when necessar" etc(; to 'e worn at all times( :&' EN6!$ONMENTAL $E4"!$EMENTS 8(* A safet" officer shall ensure that the la'our has a good working en#ironment$ a ha<ard free en#ironment( 8() The en#ironmental changes and the climatic e.tremes shall 'e recorded and necessar" ste%s shall 'e taken '" the site safet"$ in order to %re#ent an" incident due to climatic e.tremes( ;&' SEC"$!T) A$$AN7EMENTS 8/A