Академический Документы
Профессиональный Документы
Культура Документы
Trying to understand what was going on, I increased the earth resistivity to 4.0e+10 @m just to see
what effect that would have. Well, the results were the same as obtained before. Now the only thing
I can conclude from here is that the program calculates the capacitance assuming perfect ground
outside the insulator layer. It doesn't matter what the ground resistivity is. So even when the soil is
a very pour conductor this parameter is the same as if it was a perfect conductor.
( ) ( )
1
(3)
where p
b
is the total probability of backflash over the 0 - 360 deg. range of power frequency
reference angles; I
s
(k) is the critical flashover current for the k
th
reference angle .
To find the critical surge current from ATP/MODELS run, the lightning surge source was
connected to the tower top via a systematic switch, stepped by small time intervals. The
value of sequence number of energization, KNT, was calculated in MODELS from the
closing instant of the switch, passed to MODELS. The surge current was then generated as a
function of the switch closing time, with the magnitude increased in steps until backflash
occurred in one phase. This was monitored in MODELS by passing the position of the
flashover switches.
This method assumes constant phase to tower flashover voltages in the three phases, and a
fixed surge front time for which a typical value of 2 micro seconds was used. In addition, it
uses a 13 type source, which is not ideal for lightning surge simulation.
In terms of ATP runs, the evaluation of equation (3) requires a number of passes
(energizations) equal to the product of the number of steps used in increasing the stroke
current in a pre-determined range times the number of steps used for scanning the range of
angle reference for the phase potentials. Assuming 20 for both , the number of passes is 400.
In addition each step for changing the phase angle requires a separate systematic run, hence
the full evaluation of (3) has to be done outside ATP.
3 Double Circuit HV/EHV Lines
The methods described above give reasonably good results for HV and EHV lines with tower
heights not exceeding approximately 35 meter, which would be the case with most single
circuit tower lines with horizontal configuration. For double circuit lines, and with the tower
height exceeding this value, field experience indicated that the simplified method may give
Technical Papers
EEUG News August 1997 41
overly optimistic or conservative results, depending on the simplifying assumptions made. If
compared with the ATP systematic method described above, the following additional factors
may be considered:
(a) The probabilistic distribution of the front time of the lightning surge current and the
shape of the rising part.
(b) The variation in the tower gap 50% flashover voltage in the three (or more) phases,
together with the dispersion of the flashover voltage around the 50% value.
(c) The different crossarm heights carrying the individual phases.
(d) The variation in the tower footing resistance.
(e) The effect of corona on increased coupling between shield and phase wires.
Including the variables considered in the systematic approach, the random variables and their
probability distribution considered, for the purpose of the example discussed in this paper,
are:
Lightning surge current log-normal distribution
Lightning surge rate of rise log-normal distribution
Phase potentials (reference angle) uniform distribution
Tower gap (insulator flashover) normal distribution
Tower footing resistance uniform distribution
The phase potentials are related to only one random variable , the phase rotation angle, while
the tower gap flashover voltages are considered to be independent in the three phases. This
gives a total seven independent probability distributions. To handle this problem with a
systematic approach, also referred to as method of enumeration, and if only five discrete steps
were considered for each variable, the total number of passes to be run would be 5
7
= 78125
passes. Apart from the excessive computer time, the effort in evaluation the results outside
ATP would be substantial, and/or a separate computer program would have to be used to do
it. It seems to be logical, therefore, to explore the benefits of a Monte Carlo type simulation.
EMTP is designed to perform normal (Gaussian) or uniform distribution of closing or
opening of circuit breaker poles either in a SYSTEMATIC manner or by random simulation
using STATISTICS with the Monte Carlo technique. The ATP Rule Book warns the user
against the potentially enormous number of energizations with the SYSTEMATIC option
depending on the step times used for breaker closing or opening.. The breaker opening or
closing logic is controlled internally by ATP, the user enters only the appropriate values for
stepping with SYSTEMATIC or with STATISTICS. For backflash simulation such
EMTP internal logic does not exist, and the user has to perform the random choice of the
magnitudes of probabilistic variables from TACS or MODELS. This involves, as a starting
point, the monitoring of the value KNT, the sequence number of the current energization
(pass). To eliminate the cumbersome way of calculating KNT as discussed in Section II, the
writer approached Dr. Meyer about the possibility of passing EMTP constants and variables
to TACS or MODELS, for use or even modification by the user. Changes were
implemented in both TACS and MODELS (by L.Dub), which gave MODELS a very
powerful additional capability to manipulate ATP variables from inside MODELS.
Technical Papers
42 EEUG News August 1997
To demonstrate the new features and the use of Monte Carlo simulation in MODELS an
example data case was created for the backflash analysis discussed above. The main
features of this example data case, which will be available on the Fargo Server , are described
below.
4 A Sample Data Case for Backflash Analysis using MODELS
(a) Network and Tower Representation
The line used in the example was a double circuit steel tower construction for 345 kV,
barrel configuration with two overhead shield wires, but only one side of the tower
strung, similar to the arrangement used in the systematic approach described above.
Two 200 m half spans were represented on both sides of the tower assumed to be stricken
by lightning, with a three km section on the source side and ten km on the other side.
The circuit arrangement is shown in Figure 3. The line sections were modeled as
untransposed distributed parameter lines (K.C.Lee model) at 500 kHz. In an actual
engineering study the user may want to use the JMARTI setup but in the writers opinion
even a lossless line would give satisfactory results.
Figure 3 Circuit Arrangement in Data Case
The tower was modeled as a single phase distributed parameter line of four sections,
corresponding to the sections between crossarms and from the bottom crossarm to the
tower footing.
No steady state energization is used. A randomly selected angle for phase A is used to
calculate the instantaneous potentials of the three phases, which is then applied to the
phase wires at the source end in the time loop. As the line is longer than the simulation
time of 6s, there are no reflections from the line ends, which makes this approach a valid
equivalent to changing the phase angle in the phasor solution.
(b) Lightning Surge
For modeling the lightning surge current a simplified version of the Type 15 Bernd Stein
source was used generated in MODELS. The three variable parameters of the surge are
amplitude, front rate of rise and tail time to 50% amplitude. The tail time was fixed to 50
s, and the mean value of rate of rise was calculated as a function of the surge amplitude
[4]. Both the amplitude was assumed to have a log-normal distribution with a mean of
25kA, both the amplitude and a rate of rise were assumed to have a of 0.7. A typical
lightning surge current shape is shown in Figure 4.
Technical Papers
EEUG News August 1997 43
Figure 4 100 kA , 2/50 s surge
(d) Tower Gap Flashover
A uniform 50% impulse flashover voltage was assumed for the three phases equal to 1500
kVp, typical of 345 kV lines in North America. The probability distribution was assumed
to have a of 3%, with the three phases being probabilistically independent.
5 Monte Carlo Simulation Techniques in Models
Recent improvements to MODELS made it possible to run Monte Carlo simulation from
MODELS in a very efficient way. Two functions were added to MODELS which enabled
performing Monte Carlo simulations from MODELS for simultaneous simulation of several
independent random processes with different user defined probability distributions, and to
monitor the progress of the simulation. These two functions are: atp and deposit
The function atp is used to pass the value of an EMTP constant or variable to MODELS,
whereas the function deposit enables the user to modify an EMTP constant or variable and
pass it back to EMTP. This means that if an EMTP array is set aside for temporary storage,
variables can be passed from a trial (energization) KNT(i) to the next simulation trial
KNT(i+1). In the past, this could be done in an EMTP Monte Carlo simulation by a much
more laborious and slower way of using SPY. Highlights of the method are given below,
details can be found in the liberally annotated example data file BACKFL.DAT which will be
available from Prof. Morks site.
(a) Random Number Generation
The example data has six variables with independent probability distributions. It is
possible to use the consecutive throws of the same dice to generate the random numbers
for selecting the value of the variables in each trial. In the example, two random number
generators were used. One was the internal random number generator of MODELS, the
other was a user defined random number generator which was used to select the value of
the amplitude of the lightning surge current. This generator is seeded in the INIT group
by the user in the first pass. The x
i
value is stored in a selected EMTP array using the
deposit statement. For getting x
i+1
the atp function is used to recall x
i
and the user defined
random number generator calculates x
i+1
. The usefulness of having more than one
random number generator in the Monte Carlo simulation is beyond the scope of this
paper.
Technical Papers
44 EEUG News August 1997
(b) Keeping Track of Values and Events
With the atp and deposit statements it is possible to keep track of array values and events
(e.g. breaker operations) from the previous trials, which has not been possible with the
batch mode EMTP Monte Carlo simulation. In the backflash example at hand, the
variables to store and monitor, are points on the cumulative probability distribution curve
of a selected variable, and the number of backflashes which occurred.
(c) Termination of the Simulation
In principle, the simulation is terminated when the probability distribution of the resulting
event of interest becomes stable, i.e. it does no longer change with repeated trials,
meaning that the process converged. In the case of the backflash simulation this means
that the calculated value of the line tripout rate no longer changes with increasing number
of the trials. This simple concept could be difficult to implement when dealing with
events of a very low probability. The in depth theoretical treatment of this problem,
discussed in texts on the accuracy of Monte Carlo simulations, is beyond the scope of this
paper.
The backflash and hence the tripout rate is an event which depends of a usually very low
probability of the combination of high lightning surge current and the front time of the
surge. This probability for EHV lines is in the order of one percent. This means that the
monitored tripout rate, within an accuracy band, could appear to have converged and no
change occurs for a relatively large number of consecutive trials, before true convergence
was obtained. The approach tested was the monitoring of the convergence of the tripout
rate and the convergence of the obtained cumulative distribution of the lightning surge
amplitude. The convergence of the lightning surge amplitude was determined from the
monitoring of three points on the cumulative distribution curve in the 75 kA t 125 kA
range, using an accuracy defined for each of the three points. Convergence was deemed
to be obtained when both the tripout rate and the lightning surge distribution converged.
This approach was tested for large number of trials beyond the point of convergence, and
was found acceptable from the point of view of engineering accuracy, bearing in mind
the accuracy of the data for this type of analysis. When convergence is reached MODELS
sets NERG to KNT(i) +1, and the simulation is terminated. It should be noted, however,
that the method used only establishes a general concept of an automatic termination of the
Monte Carlo simulation. For other type of studies, and with the event or its probability
distribution having different sensitivities to the random variables, the method of testing
convergence would change.
(d) Optimization of Number of Trials and Individual Run Times
The total time required for the Monte Carlo simulation depends on the number of trials
(energizations) required to achieve convergence, and the run time TMAX used for a
single simulation.
The number of trials can be reduced if the range of simulation of the cumulative
distribution functions is restricted based on a knowledge by experience or by preliminary
calculations. An example using the surge amplitude log-normal distribution illustrates
Technical Papers
EEUG News August 1997 45
this. There is a minimum value of lightning surge current below which backflash will not
occur regardless of the steepness of the surge front. Assuming that this value for a given
line voltage class is 75 kA, only the >75 kA range of the distribution curve needs to be
simulated. For the log-normal distribution of lightning currents, the probability of a surge
amplitude being greater than 75 kA is 5.8%. This reduces the required number of trials to
approximately 5.8% compared to the simulation of the whole range. Because of the
random nature of the simulation this is not the exact reduction but it is a reasonable
estimate.
Another possibility to reduce the overall simulation time is to abort individual runs, once
it is recognized that the combination of values of random variables cannot cause a
backflash. This happens if the combination of surge amplitude and the steepness of the
surge front is such that from prior knowledge, backflash would not occur. If such a
condition is detected the deposit function is used to change the value of tmax to t+deltat.
The two methods described reduced the total simulation time for the backfl.dat example
by a factor of four.
6 Screen Display During Running
Once the simulation started, the user has lost control, as MODELS cannot be run in the SPY
mode. It is useful, however, particularly during the testing stage of the model, to observe on
the screen the progress of the simulation and some of the interim results of an individual run.
This information can be useful for debugging and/or improving and changing input data, and
provide some information for insulation coordination. The display is flashed on the screen
during each pass, generated by MODELS write statements, and is available in the .LIS file
for examination. In addition, by observing the display, the user may terminate the run for
data modifications. The screen display for monitoring random variables and backflash is
shown below.
KNT = 158
SURGE CURRENT 153 KA
SURGE FRONT 1.6 US
PHASE POTENTIALS PH. A, B, C
321, 56, 264 KV
TOWER GAP FLASHOVER PH. A, B, C
1578, 1670, 1524 KV
BACKFLASH IN PHASE C
TIME TO FLASHOVER 2.5 US
BACKFLASH COUNT = 5
TRIPOUT RATE 0.95/100 KM / YEAR
In the above listing the front time of the surge is calculated from the random steepness
assuming that the rate of rise is constant between zero and maximum amplitude. Phase
potentials are calculated from the random phase A reference angle. Tower gap flashover
voltages are calculated from the random variation around the 50% flashover value. Should
backflash occur, the timing of the backflash and the phase in which it occurred is recorded.
The number of backflashes are accumulated and the tripout rate is calculated from the entered
data of isokeraunic level and tower dimensions. Further details are given in the
BACKFL.DAT data file.
In the BACKFLASH example, after the first 100 passes and then following blocks of 20
passes, the convergence of Monte Carlo simulation is checked. In the BACKFLASH
Technical Papers
46 EEUG News August 1997
example, this is done by checking the error between three points on the surge current
cumulative probability curve obtained by the simulation, against the theoretical values. If all
three errors are less than the specified errors, the run is terminated. This is run, or and the
error can be checked for more than one random variable if desired.
KNT = 121
CHECK PROGRESS NOW
TARGET CUMULATIVE PROBABILITIES
75, 100, 125 KA 5.8 2.4 1.1 %
CURRENT VALUES : 4.5 1.2 0.8 %
SURGE CURRENT 56 KA
SURGE FRONT 1.8 US
PHASE POTENTIALS PH. A, B, C 336 , 225, 111 KV
TWR GAP FLASHOVER PH. A, B, C 1618, 1673, 1603 KV
BACKFLASH COUNT = 3
TRIPOUT RATE 0.74 / 100 KM / YEAR
7 Conclusions
The paper shows an engineering example of utilizing some of the new features of the
MODELS language which were added recently. While the data demonstration data file
BACKFL.DAT is an example only rather than an engineering template for performing
lightning backflash studies, it is nevertheless a useful starting point for those who wish
develop Monte Carlo simulations for backflash studies, or other type of simulations such as
switching surge studies using random modeling of tower gap flashover voltages and lightning
arrester simulations. Further work is required to include a suitable corona model.
8 Acknowledgment
Acknowledgment is due to Ing. David Alvira of the Red Espana, Madrid. whose email
describing the SYSTEMATIC approach gave the incentive to the development presented, and
to Laurent Dube for his assistance in the implementation of the new MODELS features in the
data file.
9 References
[1] Transmission Line Reference Book 345 kV and above, EPRI, 1975
[2] David Alvira: Backflash Simulation for a 400 kV Double Circuit Line using
ATP/MODELS. ATP-EMTP List-server Email , January 1996.
[3] T. Yamada et al. : Experimental evaluation of UHV Tower Model for Lightning Surge
Analysis, IEEE Transmission and Power Delivery, Vol.10, No. 1, January 1995.
[4] R.B. Anderson, A.J. Erikson : Lightning Parameters for Engineering Application,
Technical Brochure, CIGRE, Electra, No.69, 1982.
[5] J.G. Anderson, Monte Carlo Computer Calculation of Transmission Line Lightning
Performance, Power Apparatus and Systems, Part III,Vol. 80, 1961.
[6] M.A. Sargent, Monte Carlo Simulation the Lightning Performance of Overhead
Shielding Networks of high Voltage Substations, IEEE Trans., Vol. PAS-91, 1972.
[7] IEEE Working Group Report: Estimating Lightning Performance of Transmission
Lines II - Updates and Analytical Models , IEEE Transactions on Power Delivery, Vol.8,
No.3, July 1993.
Technical Papers
EEUG News August 1997 47
Corona Modelling for Attenuation and Distortion of
Lightning Surges in Transmission Lines
Juan L. Ciudad, David Alvira, Fernando Soto Power System Studies Department
Red Elctrica de Espaa, S.A. , Spain P/ Conde de los Gaitanes, 177
La Moraleja, 28109 Madrid (Spain)
dalvira@ree.es
Abstract: Red Elctrica de Espaa, S.A. (REE) is interested in travelling wave attenuation
caused by corona, specially in lightning surges. Knowing how the overvoltage, produced by a
lightning strike, attenuates until it reaches the near substation, allows to evaluate the critical
lightning distance. In this paper it is shown a corona model for the Electromagnetic Transient
Program (EMTP/ATP) developed by REE, suitable for lightning surges. This model is based
on linearized charge-voltage cycles and on the division of the transmission line into sections.
After building the model, some validations are done.
Keywords: Corona, Lightning Surges, Attenuation, Distortion, EMTP.
1 Introduction
Two of the most important effects of corona in overhead transmission lines are the power loss
increase and the attenuation of travelling waves. This paper presents a model that can
simulate the attenuation of the amplitude and wave front of lightning type surges travelling in
a High Voltage transmission line.
Entering surges due to lightning is a cause of failures in substations. For this reason it is very
important to estimate the amount of dangerous surges that can enter a substation through the
different transmission lines. Several factors are important in this kind of studies (conductors,
grounding, shield wires, corona, surge arresters, ...).
There are several types of corona models in the bibliography, many of them are single-phase
ones. On the other hand when using EMTP/ATP some size limits must be taken into account.
As the transmission line is divided into sections (pieces of some metres long), if a long travel
distance is studied size limits (number of knots) may be exceeded using a three-phase corona
model.
In this paper a simple and easy to use single-phase model is presented, that simulates the
attenuation and distortion of lightning surges amplitude and wave front, due to corona. There
are more sophisticated models involving corona dynamics [5], [6], [7], and employing
complicated algorithms that are useful when a very precise wave form is needed.
Technical Papers
48 EEUG News August 1997
2 Corona Model Description
The corona effect is produced by the air ionization around the conductor caused by the
voltage gradient raise in the conductor . This causes a charge increase in the conductor
surface and allows the air surrounding the conductor to become a conductor path.
The charge increase in the conductor surface is widely studied. Many charge-voltage cycles
measures are available, involving several surges types and conductor bundles [1], [4].
These measured cycles must be linearized in order to program them, figure 1 shows how this
process is done. Three different slopes are considered for the charge increasing part of the
cycle, one before the corona inception voltage and two for the ionization phase. Only one
zone is set for the corona decay. As it is easily followed, each slope means a capacitance
value for the transmission line.
Q
D
0
o
V V
1
V
C
o
1
C
C
2
C
Ccor1
Ccor2
A
B
Fig. 1 - Charge-Voltage cycle linearized. C
0
= geometric capacitance of the conductor; V
0
=
corona threshold; C
cor1
, C
cor2
= linearized capacitances; C
1
, C
2
= incremental capacitances.
2.1 Before corona inception:
The corona becomes present when the overvoltage in the conductor exceeds the corona
inception voltage. As in zone OA in figure 1, the conductor voltage is under the corona
threshold (V
0
), the corona phenomenon is not considered and only the geometric capacitance
of the line is important. This means that no additional capacitance value is used in that case.
2.2 Ionization phase:
When the voltage exceeds the corona threshold (V
0
), the corona effect must be included. Two
different zones are considered in the ionization phase. The division is made by a voltage
value (V
1
), which depends on the cycle selected for each simulation. The first zone is for
voltages below this fixed value (here we use C
cor1
) and the second one for higher voltages
(C
cor2
). This means that two different slopes for the linearized cycle are considered and so two
capacitance values are used, one for each zone.
2.3 Corona decay:
The slope of the cycle in the decay phase, corresponds to a capacitance value which is more
or less equal or slightly higher than the geometric one, so is acceptable to consider only the
Technical Papers
EEUG News August 1997 49
geometric capacitance for this zone. This simplification obtains great improvement in speed
and coding without significant error.
2.4 Parameter determining:
All the parameters values (C
cor1
, C
cor2
, V
0
, V
1
), are calculated using measured cycles. These
cycles are obtained for different conductor bundles and overvoltages (front time and
amplitude) [1]. This allows us to simulate every particular case precisely, even without using
any dynamic model.
3 Simulation Method
Simulations are made using the Electromagnetic Transient Program (EMTP/ATP). The line is
divided into several pieces in which the corona model is included. The lightning overvoltage
is simulated using a MODELS controlled source (type 60) in one side of the line. The source
equation is refereed in section 4 of this paper.
Different equations govern the charge increase in each cycle zone. In zone OA (figure 1) the
voltage is under V
0
, so the equation is:
q u C =
0
(1)
If voltage enters zone AB (V
0
<
u < V
1
), it should be used:
q u C u V C C
cor
= +
0 0 1 0
( ) ( ) (2)
And in zone BC (u > V
1
):
q u C u V C C u V C C
cor cor cor
= + +
0 0 1 0 1 2 1
( ) ( ) ( ) ( ) (3)
For the corona decay the same equation of zone OA is used.
All these are included in EMTP/ATP simulations as can be seen in figure 2. The transmission
line is divided into pieces and the circuit in figure 2 is added in each piece. Of course if any
line model is used, the reactance and geometric capacitance of the line are not necessary and
can be suppressed.
L
Cgom
D
U
1
1
+
-
Ccor1-Cgom
1
D
U
2
2
Ccor2-Ccor1
2
R
+
-
c
c
Fig. 2 - Transient corona model circuit.
Technical Papers
50 EEUG News August 1997
Diodes D
1
and D
2
are voltage controlled. In zone OA of the cycle both of them are off, but
with voltages over the corona threshold, in zone AB, D
1
is turned on and in zone BC both are
active.
4 Validations
The model has been compared with the wave presented by Gary in [1]. In figure 3 and 4 the
measured oscilograms of 995 kV and 850 kV positive polarity overvoltages are presented.
The source used in the simulation corresponded to the equation:
u t U e e sin t
ch
t t
( ) ( . . ( . ))
. .
= +
0 988 1064 12 3 70
0 123 4 1
(4)
Where Uch is 995 kV or 850 kV respectively.
The parameters used in the simulations are those of a Spanish 220 kV line, very similar to the
one used by Gary [1] (25.38 mm conductor diameter, 7.5 m between phases, ...).
Figure 5 and 6 shows the results obtained in the simulations with EMTP/ATP. Numeric
oscillation have been found during the energization of the capacitors that build up the corona
model. The effort has been dedicated to match amplitude and front of wave, instead of
eliminating completely the oscillations.
As can be seen in the results amplitude differences between simulation and measured
oscilograms are from 3.5% to 6%. The wave front is simulated with less than 1 s error.
Fig. 3
Fig. 4
Technical Papers
EEUG News August 1997 51
.8100 .6300 .4500 .2700 .0900
MICROSECONDS x 10** 1
Umax=+995 kV
1
1
2
2
3
3
3
4
.8000
.6000
.4000
.2000
0.0
Voltage (V) x 10**6
Fig. 5 1) 1 km distance, 2) 3 km distance, 3) 7 km distance.
.9000 .7000 .5000 .3000 .1000
MICROSECONDS x 10** 1
Umax=+850 kV
1
1
2
2
3
3
.7500
.5625
.3750
.1875
0.0
Voltage (V) x 10**6
Fig. 6 1) 1 km distance, 2) 3 km distance, 3) 7 km distance.
Technical Papers
52 EEUG News August 1997
5 Conclusions
A single-phase corona model suitable for the lightning surges studies using EMTP/ATP has
been developed. With this model the amplitude and front of wave of a surge after a few
kilometres, can be calculated.
This model can be easily used to define an influence zone on the substation, when the BIL
(Basic Insulation Level) in the substation has a value lower than the surges that can be found
in the line (due to a high BIL in the line). The strokes that hit the line in the influence zone
are the ones that can reach the substation. Knowing the length of this zone, it can be
calculated the number of surges that reach the substation.
6 References.
[1] Gary C., Cristescu D., Dragan G.: Attenuation and Distortion of Travelling Waves
Caused by Transient Corona, CIGRE Report, Study Committee 33: Overvoltages
and Insulation Co-ordination, 1989.
[2] Correia de Barros M.T., Dub L., Almeida M.E.: Including a Transmission Line
with Corona in ATP Using MODELS, EMTP European users Group Meeting,
Denmark, April 1994.
[3] Carneiro Jr S., Mart J.R.: Evaluation of Corona and Line Models in
Electromagnetic Transient Simulations, IEEE Transaction on Power Delivery,
Vol. 6, No. 1, January 1991.
[4] Maruvada P.S., Menemenlis H., Malewski R.: Corona Characteristics of
Conductor Bundles under Impulse Voltages, IEEE Trans. Vol.PAS - 96,
pp. 102-115. Jan./Feb. 1977.
[5] Huang W.G., Semlyen A.: Computation of Electro-Magnetic Transients on
Three-Phase Transmission Lines with Corona and Frequency Dependent
Parameters, IEEE Transaction on Power Delivery, Vol. PWRD-2, No. 3, July 1987.
[6] Kudyan H.M., Shih C.H.: A Nonlinear Circuit Model for Transmission Lines in
Corona, IEEE Transaction on Power Apparatus and Systems, Vol. PAS-100, No. 3,
March 1981.
[7] De Jesus C., Correira de Barros M.T.: Modelling of Corona Dynamics for Surge
Propagation Studies, IEEE Transaction on Power Delivery, Vol. 9, No.3, July 1994.