Project: Throgs Neck Bridge

Contract: TN-50
Job No. 106
Turnbuckles EE Cruz Heavy Construction
9/21/2014 8:50 PM
Pier Stringer
North/S
outh
East/
West
Qty Installed Repair Type Transverse Restrainers
Pier 10 S5 N - 1
Pier 10 S6 N - 1
Pier 10 S8 N - 1
Pier 10 S9 N - 1
Pier 10 S11 N - 1
Pier 10 S12 N - 1
Pier 10 S2 S E 1 Existing 'T'
" " " W 1 Y Existing 'T'
Pier 10 S7 S E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 10 S10 S E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 10 S14 S E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 9 S2 N E 1 Existing 'T'
" " " W 1 Existing 'T'
Pier 9 S5 N E 1 B Existing 'T'
" " " W 1 B Existing 'T'
Pier 9 S7 N E 1 B Existing 'T'
" " " W 1 Y Existing 'T'
Pier 9 S10 N E 1 B Existing 'T'
" " " W 1 Y Existing 'T'
Pier 9 S14 N E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 9 S4 S E 1 Existing 'T'
" " " W 1 Existing 'T'
Pier 9 S7 S E 1 Existing 'T'
" " " W 1 Existing 'T'
Pier 9 S11 S E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 9 S14 S E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 9 S18 S E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 8 S2 N E 1 Y Existing 'T'
" " " W 1 B Existing 'T'
Pier 8 S6 N E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 8 S10 N E 1 Y Existing 'T'
" " " W 1 B Existing 'T'
Pier 8 S14 N E 1 C Existing 'T'
" " " W 1 Y Existing 'T'
Pier 8 S18 N E 1 Existing 'T'
" " " W 1 Existing 'T'
New 'T'
New 'T'
New 'T' A
A
A
\\vboxsrv\conversion_tmp\scratch_2\245005411.xls.ms_office 1 of 4
Project: Throgs Neck Bridge
Contract: TN-50
Job No. 106
Turnbuckles EE Cruz Heavy Construction
9/21/2014 8:50 PM
Pier Stringer
North/S
outh
East/
West
Qty Installed Repair Type Transverse Restrainers
New 'T' A
Pier 8 S2 S E 1 C Existing 'T'
" " " W 1 Y Existing 'T'
Pier 8 S6 S E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 8 S9 S E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 8 S13 S E 1 C Existing 'T'
" " " W 1
Existing 'T'
Pier 7 S4 N E 1 Y Existing 'T'
" " " W 1 C Existing 'T'
Pier 7 S6 N E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 7 S9 N E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 7 S13 N E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 7 S2 S E 1 C Existing 'T'
" " " W 1 Y Existing 'T'
Pier 7 S5 S E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 7 S8 S E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 7 S11 S E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 6 S2 N E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 6 S3 N - 1
Pier 6 S4 N - 1
Pier 6 S5 N E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 6 S8 N E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 6 S9 N - 1
Pier 6 S10 N - 1
Pier 6 S11 N E 1 Existing 'T'
" " " W 1 Y Existing 'T'
Pier 6 S2 S E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 6 S3 S - 1
Pier 6 S4 S - 1
Pier 6 S5 S E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 6 S8 S E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
Pier 6 S9 S - 1
Pier 6 S10 S - 1
Pier 6 S11 S E 1 Y Existing 'T'
" " " W 1 Y Existing 'T'
92 56 Total
New 'T'
New 'T' A
New 'T'
A New 'T'
\\vboxsrv\conversion_tmp\scratch_2\245005411.xls.ms_office 2 of 4
Project: Throgs Neck Bridge
Contract: TN-50
Job No. 106
Turnbuckles EE Cruz Heavy Construction
9/21/2014 8:50 PM
Photo # Issues
16
16
17 Existing 'T' needs smaller pin. 1-3/8" (EEC).
IIW has not installed to date.
IIW has not installed to date.
13 Existing 'T' needs to be raised.
Existing 'T' needs to be raised.
14 Existing 'T" needs to be raised.
15 Existing 'T' does not align AND needs to be raised
IIW has not installed to date.
IIW has not installed to date.
Existing 'T' needs smaller pin. 1-3/8" pin. EEC
Existing 'T' needs smaller pin. 1-3/8" pin. EEC
9,10,11,12
Existing 'T' does not align. Needs to be raised. IIW to use a
smaller existing 'T' on site to FIT on top of the pier (15" 'T').
Use a 6" turnbuckle. Use a smaller 1-3/8" diameter pin.
7 Existing 'T' needs to be raised ~5".
6 Existing 'T' does not align.
IIW has not installed to date.
IIW has not installed to date.
NEW 'T' needs to be raised ~3". Anchor bolt holes have been
drilled. TYP
NEW 'T' needs to be raised ~3". Anchor bolt holes have been
drilled. TYP
NEW 'T' needs to be raised ~3". Anchor bolt holes have been
drilled. TYP
\\vboxsrv\conversion_tmp\scratch_2\245005411.xls.ms_office 3 of 4
Project: Throgs Neck Bridge
Contract: TN-50
Job No. 106
Turnbuckles EE Cruz Heavy Construction
9/21/2014 8:50 PM
Photo # Issues
NEW 'T' needs to be raised ~3". Anchor bolt holes have been
drilled. TYP
8
Re-install an existing 'T'. Holes have been drilled. Does not
need raised
Existing hole diameter is 1-1/2". Purchase 1-3/8" pin. 'T'
does not align. Relocate to new alignment.
Existing hole diameter is 1-1/2". Purchase 1-3/8" pin. Use 6"
turnbuckle
Existing hole diameter is 1-1/2". Purchase 1-3/8" pin. 'T'
does not align. Relocate to new alignment.
5
Existing hole diameter is 1-1/2". Purchase 1-3/8" pin. 'T'
does not align. Relocate to new alignment.
4 Raise Pad 3". Holes have been drilled by CC.
4 Raise Pad 3". Holes have been drilled by CC.
3
Need to core drill holes for new 'T'.
Corcon needs to move cable to drill holes.
No existing restrainer 'T". Replace with one on site.
Raise Pad 3". Holes have been drilled by CC.
Raise Pad 3". Holes have been drilled by CC.
2 Need to core drill holes for new 'T'.
2 Corcon needs to move cable to drill holes.
1