Академический Документы
Профессиональный Документы
Культура Документы
1.0 Introduction 3
2.1.5 TH Installation 5
5.0 Conclusion 10
Page 1 of 30
6.0 Appendixes 11-29
Figure 6.1.1 11
Figure 6.1.2 12
Figure 6.1.3 13
Figure 6.1.4 13
Figure 6.1.5 14
Figure 6.1.6 14
Figure 6.1.7 15
Figure 6.1.8 16
Figure 6.1.9 17
Figure 6.1.10 18
Figure 6.2.1 19
Figure 6.2.2 20
Figure 6.2.3 21
Figure 6.2.4 22
Figure 6.2.5 23
Figure 6.2.6 24
Figure 6.2.7 25
Figure 6.2.8 26
Figure 6.2.9 27
Figure 6.2.10 28
Figure 6.2.11 29
7.0 References 30
Page 2 of 30
1.0 Introduction
This report is on Subsea Completion, Workover, and processing in Nigerian Deep Waters, within
Nigeria, located in the Western part of Africa is one of the largest oil & Gas producers in Africa and
the Niger Delta coastal region has a greater reserve of the Oil & Gas. In Nigeria, the deepwater
Some of the Subsea completion carried out in this region was on dual bore completion System
using a Dual bore subsea production tree and equipments. The tree offers the means by which a
Workover is the performance of one or more of a variety of remedial operations on a producing well
to increase production such as deepening, plugging back, pulling and resetting liners, and squeeze
cementing. It could also mean the action and techniques of reentering the well and repairing the
Subsea processing of the produced oil and/or gas includes de-watering, or separating, the bulk of
the gas from the crude oil and sand particles using technology such as Subsea Multiphase flow
meters, Subsea Pump and compressors, Subsea separation and water reinjection etc.
Page 3 of 30
2.0 Subsea Completion – Tool & Equipments
The first step in preparing the well for completion is installing a completion guide base
(figure 6.1.1).
The TH (Figure 6.1.2) will be oriented and landed on the subsea wellhead provided
there is a landing shoulder, sealing area, and provision to lock the TH to the
wellhead. If no such provision exists in the wellhead, a tubing head with these
features will need to be installed for attaching a blowout preventer stack for pressure
Some control dimensions are necessary to set the TH and complete the well.
This tool locks the work string to the wellhead, via the TH and provides vertical
This is used to connect the TH and TH running tool to the riser running string
This system is used to lower the TH to the wellhead and provide access to the
This is used to verify that the TH is all the way down on its landing shoulder
2.1.5 TH Installation
The TH is run on its completion riser running assembly down through the
drilling riser and BOP stack which is landed and locked to the wellhead. The
TH is then tagged out on its landing shoulder with partial string weight. The TH
running assembly is then picked up a short distance so that the orientation pin
engages the helix on the orientation adapter joint and allows the TH and
running assembly to orient to the vertical slot in the adapter joint which is
preset to achieve the desired orientation of the production and annulus bore.
With the orientation pin still extended, the TH is set back down on the landing
shoulder with total string weight which will activate the TH seal assembly. The
the TH running tool. An overpull test will establish that the TH is locked to the
hydraulically unlocked from the TH and the TH running assembly is then pulled
This provide a means of cleaning out the upper portion of the wellhead prior to
Page 5 of 30
2.3 Lower Riser Package (LRP)/Emergency Disconnect Package (EDP)
in the production and annulus bores above the tree. The EDP provides the second
primary function which is a means to disconnect from the tree/LRP should the rig
experience excessive wave action and the riser system need to be disconnected from
the well.
Subsea Trees provides features including a hydraulic connector at the bottom to lock
the tree to the wellhead, seal pockets or stab sub receptacles in the bottom to
interface with the TH annulus, production and downhole tool connections, a flow line
connection system and hydraulic controls and accessories. Generally, all of the
valves in the tree are hydraulically controlled with manual overrides which are
adapted for actuation by an ROV. During the tree running operation, the valves are
hydraulically controlled from the control umbilical connected to the EDP/LRP. Later in
the operation when the tree cap is installed, the functions will be bridged over to the
control umbilical attached to the completion guide base so that the tree can be
controlled from the production platform location. It can be run with guideline or
guidelineless
Subsea trees could basically be classified as vertical trees (VXT) and horizontal trees
(HXT). It could also be classified as production and water / gas injection trees.
• In a VXT, the master valve is located directly above the TH, while in an HXT
the master valve is in the horizontal run adjacent to the wing valve
Page 6 of 30
• In a VXT, the TH and downhole tubing are run prior to installing the tree, while
in an HXT the TH is typically landed in the tree, and hence the TH and
the tree. The removal of an HXT normally requires prior removal of the TH and
completion string;
• VXT systems are run on a dual-bore completion riser (or a monobore riser with
bore selector located above the LRP). TH of HXT is run on casing tubular
joints.
In preparation for running the tree, the EDP/LRP will be locked to the top of the
tree at the surface in the moon pool. The hydraulic control umbilical is
connected to the top of the EDP. All hydraulics will be tested. The EDP, LRP
and tree will be picked up with the riser handling tool and hung off in the riser
spider. The tree is then lowered down to its required depth by adding riser
joints. The tree is now landed on the wellhead and locked to the wellhead by
activating the hydraulic lock function through the control umbilical to the tree
and valve functional. The surface joint is now installed bringing the riser
system through the rotary. The surface tree is made up and lowered onto the
top of the surface joint. The wireline plugs can now be pulled from the TH. The
well can now be completed and flow tested. The tree is now shut in
preparation for pulling the EDP/LRP/completion riser system. The surface tree
Page 7 of 30
from the tree and with the riser spider installed at the rotary; the
This is usually installed on the top of the tree to prevent marine growth on the
upper tree connection area and sealing bores, and may be either pressure-
running tool
try to increase production. Examples of workover jobs are deepening, plugging back, pulling
It also consists of the action and techniques of reentering the well and redoing or repairing
Some equipment/tools presently available for performing well entry and subsea
interventions include:
This is used to increase production rates, maximize total recovery, overcome flow
This involves removing most or all of the produced water from the well fluids,
This allows efficient single-phase pumping of the separated liquids and helps
corrosion.
4.2 Pressure-boosting
production above natural flow conditions by adding energy to the system. Some
• Submersible pumps
Page 9 of 30
• Seabed multiphase pumps
5.0 Conclusion
Deepwater exploration in this region has been very challenging technically and difficult as a
result of the water depth involved. Also, it has been a very expensive venture.
abandonment) have been able to give the major producers success in exploring the Oil &
Gas deposits in these difficult reserves in this region. New and innovative technological
like lighter weight and increased water depth for the Subsea equipments/tools. This will help
access and explore those difficult reserves in this region, which in the past prove difficult to
Page 10 of 30
6.0 Appendixes
Figure 6.1.1: Running Completion Guide Base using the Running Tool
Page 11 of 30
LOCK DOWN RING
ACTUATOR IN SET DOWNHOLE PRESSURE
POSITION AND TEMPERATURE LINE
ANNULUS
BORE
DOWNHOLE
DOWNHOLE SAFETY PRESSURE
VALVE LINE AND PRODUCTION
TEMPERATURE BORE
LINE
DOWNHOLE SAFETY
TUBING HANGER VALVE LINE
SEAL ASSEMBLY
IN SET POSITION
PRODUCTION
BORE PLUG
PROFILE
ANNULUS BORE
PLUG PROFILE
INDICATOR
PIN
GROOVED
SHEAR PIN
PRODUCTION BORE TUBING HANGER SEAL
ANNULUS BORE ASSEMBLY
RETAINER RING IN RUNNING
POSITION
METAL TO
METAL SEAL
Page 12 of 30
IMPRESSION BLOCK
4-1/2” IF BOX RETAINER SLEEVE
CONNECTION
RETAINER NUT
IMPRESSION BLOCK
LEAD
ASSEMBLY
IMPRESSION
BLOCK
ORIENTAION LINE
SOCKET SET
SCREW
LANDING JOINT
LANDING HEAD
INDICATOR ROD
ALLIGNMENT KEY
RETAINER RING
RETAINER RING
RISER
ANNULUS CLAMP
BORE
PRODUCTION BORE
ALIGNMENT RING
RETAINER RING
Page 13 of 30
4-1/2” IF BOX
DEBRIS SHIELD
WASHING JETS
STAB PLATE
TREE MANDREL
ALIGNMENT PIN
TREE GUIDE FRAME
FLOWLINE
ANODE
FLOWLINE DEBRIS
COVER
DX CONNECTOR
FLOWLINE
CONNECTOR
Page 14 of 30
ANNULUS BOX
CONNECTION
PRODUCTION
RISER PIN
CONNECTION
ALIGNMENT RING
STANDARD
PRODUCTION
RISER
CONNECTION
ALIGNMENT RING
ANNULUS BORE
RISER CLAMP
PRODUCTION BORE
Page 15 of 30
Typical Tree Cap (TC)
Page 16 of 30
Typical Tree Cap (TC) Running Tool
Tool
Page 17 of 30
Figure 6.1.10: Lower Riser Package (LRP)
Page 18 of 30
6.2 Stacked up Completion & Processing Tools/Equipments in running mode
ORIENTATION PIN IN
RETRACTED MODE
Page 19 of 30
ORIENTATION PIN IN ORIENTATION ADAPTER JOINT (OAJ
EXTENDED MODE IN ROTATION MODE
TUBING HANGER
Page 20 of 30
ORIENTATION PIN FULLY ORIENTATION ADAPTER JOINT (OAJ
STROKED OUT
Page 21 of 30
WELLHEAD HOUSING
Page 22 of 30
TUBING HANGER RUNNING
TOOL UNLOCKED FROM
TUBING HANGER
WELLHEAD HOUSING
Page 23 of 30
ORIENTATION PIN IN
EXTENDED MODE
Page 24 of 30
EMERGENCY DISCONNECTION
PACKAGE (EDP)
LOWER RISER
PACKAGE (LRP)
TREE
WELLHEAD HOUSING
Figure 6.2.7Figure
Overview
2.7 of Tree Landed
on Wellhead
Page 25 of 30
TREE
TREE CONNECTOR
LOCKING PROFILE
WELLHEAD HOUSING
LOCKING PROFILE
WELLHEAD HOUSING
Page 26 of 30
GUIDELINES
EMERGENCY
DISCONNECTION
PACKAGE (EDP)
LOWER RISER
PACKAGE (LRP)
TREE
Page 27 of 30
GUIDELINES
TREE CAP
RUNNING TOOL
TREE CAP
GUIDE POST
TREE CAP
TREE
Page 28 of 30
Figure 6.2.11 Subsea Processing Systems Overview
Page 29 of 30
7.0 References
[1] ISO 13628-1 (2nd Edition, 2005); Petroleum and natural gas industries — Design and
[2] ISO 13628-7 (2nd Edition, 2005); Petroleum and natural gas industries — Design and
operation of subsea production systems (Part 7: Completion & Workover Risers) [Accessed
December, 2009]
[3] Dril-Quip Inc (1996). Offshore Drillings & Completions Training Manuals; Pages 253 – 295
Page 30 of 30