Introduction The technique of building bridge decks as balanced cantilevers about the piers provides an efficient and economic solution for medium and long span bridges. Balanced cantilever deck construction was introduced in the early 1950s and since has provided a spectacular way to build concrete box girder bridges with spans up to 300m using only minimal falsework and temporary works. With this technique the balanced cantilevers are formed by either casting the deck in-situ in short sections using form travellers or from precast segments lifted into place with cranes or gantries. The technique has also been extended into cable-stayed and arch bridge construction.
Principles With balanced cantilever construction the deck is usually built out simultaneously either side of a pier in a balanced manner. The technique may also be used with asymmetrically cantilevers with a prop or counterweight reducing the out-of-balance forces in the pier. Initially, the substructure, piers and abutments are built ready for the deck construction to begin. The section of deck above the pier is completed first, either by casting the concrete in-situ on falsework locally around the pier, or by placing a precast pier segment in position. Additional sections of deck are then cast in-situ or precast and placed in pairs on either end of the previously completed deck. Each new section of deck is supported by the prestressing cantilever tendons or reinforcement in the deck. The cantilevers are extended out in a balanced manner until the mid-span is reached. Cantilevers from adjacent piers are then joined together with an in-situ concrete stitch and prestressing tendons installed to make the deck continuous. At end spans adjacent to abutments, the end cantilever is extended out using temporary supports or falsework as indicated in the following figure. Finally, the remaining permanent prestressing tendons are installed to complete the bridge.
Balanced cantilever construction using form travellers for cast in-situ segments
The end spans are usually 60 ~65% of the length of the adjacent spans to provide a reasonable distribution of moments and forces along the bridge and to prevent uplift in the abutment bearings. With a constant depth deck the span to depth ratio is usually about 20, although on some projects this has been increased to over 30 for aesthetic or clearance reasons or reduced to 12 for economic reasons. For spans over 60m, the decks are usually haunched, with a reduced depth at mid-span to reduce the weight. For haunched decks the span to depth ratio at midspan is usually about 35 and at the pier about 16.
Construction
a) In-situ using form travellers The form travellers are supported off the previously completed length of deck, cantilevering out to support the formwork for the next section. The deck sections are usually cast in 4~5m lengths with the complete box section cast in a single pour. After each pour it is usual for a prestressing tendon to be installed through the top slab and anchored on the end face of the new segment to support it in place. Alternatively temporary prestressing bars or the permanent reinforcement in the box may be used to support several segments before the permanent cantilever prestressing tendons are installed. These cantilever tendons support the deck during the construction stages and provide the permanent prestress in the completed structure.
A typical cycle time for construction of an in-situ section of deck is 7 days. This has been reduced on some projects by precasting parts of the deck or by prefabricating the reinforcement cages.
b) Precast segments For longer bridge lengths, precast segmental construction provides a quicker and more economic solution. Each segment is precast in purpose built factories before being delivered to site and lifted in to position. Segments are placed by crane, lifting frame or gantry, with the segments fixed in position with epoxy glue and prestressing tendons. Segment lengths are typically up to 3.6m to suit highway transportation restraints and to limit lifting weights.
With precast segmental construction erection rates of up to 6 segments a day, 3 on each cantilever, have been achieved when matched with a suitable permanent works design. A typical cycle time for erecting a segment is 4 hours with a typical 60m span being erected within 7 days.
Casting segments in form traveller Precast segments being erected by crane
c) Stability Balanced cantilever construction is frequently adopted with integral piers to provide inherent stability to the deck. Where bearings are used, or with very slender piers, it may be necessary to support the deck with temporary props or a tie-down arrangement to provide sufficient stability during construction.
Design During the construction stages the design of the deck and substructure are checked to cater for the temporary works and other construction loads applied. The structure is checked for at least one segment out-of-balance to match the construction sequence. In addition, it is usual to consider an out-of-balance dead load, with the concrete 2.5% heavier on one side of the balanced cantilever, and wind loading on the deck including upward wind under one of the cantilevers. Differential horizontal wind loading on the two cantilevers may give rise to significant twisting of the pier which should also be checked.
Typical construction loadings include:
construction equipment (typically taken as 1 ~2T on the cantilever tip). construction live load (typically taken as 0.5 kN/m 2 ) applied to deck to give most adverse effect. for in-situ construction, weight of form traveller at the end of the cantilever, typically between 40 ~120T for spans between 50m and 200m for precast segmental construction, a segment lifting beam of up to 5T and a stressing platform of 6T applied at the ends of the deck. for precast segments erected with a lifting frame fixed to the deck, typically between 20~50T depending on the size and weight of the segment being lifted, applied to the end of the cantilever for precast segments erected with a gantry, typically 200~400T for spans between 50m and 120m distributed between the piers.
Balanced cantilever construction sequence causes a large redistribution of moments from the as-built to the long-term condition due to creep of the concrete. This affects both the dead load and the prestress forces. This is often beneficial as it helps balance the prestress tendon layout over the piers and in mid-span.
Concluding remarks Balanced cantilever construction produces economic and elegant structures. The reduction in temporary works and simplicity of construction frequently makes it the preferred solution for longer span lengths.
References HEWSON NR, Prestressed Concrete Bridges: Design and Construction. Thomas Telford, London, 2003 PODOLNY W AND MULLER J .M, Construction and Design of Prestressed Concrete Segmental Bridges. J ohn Wiley & Sons, New York, 1982. SCHLAICH J AND SCHEEF H, Concrete box-girder bridges. International Association for Bridge and Structural Engineering, Zurich, 1982.