Вы находитесь на странице: 1из 4

General Question Related to The Applications of Coiled Tubing

Unit
Coiled Tubing unit also called Endless Tubing Unit or Endless
Tension Unit.
1. Applications of Coiled Tubing Unit
Ans: applications of CTU are as follow:
Kick off
Spot acid
Wire line job : a wire is present inside the reel for performing the wire line jobs
Shooting or the perforations
Logging by CTU
Chemical pump
Completion by CTU
Drilling
Fishing job
Sand out and sand in
2. What features of CTU should be covered in our project
Ans: all features should be covered in the project
3. How many jobs performed by the CTU in Pakistan and the success ratio of performing
the jobs
Ans: the jobs performed by the CTU in Pakistan are as follow:
Nitrogen lifting or kick off job
Pumping of spot acid to the formation
Fishing job
Sand out or sand in
Drilling job performed in Zinn Baluchistan
4. Sir, we read research articles, manuals related to CTU, what relevant information we get
from them
Ans: yes get relevant information from them and also get further information regarding CTU
from visiting to the field.
5. We need the relevant data of the jobs performed by the CTU for our project can we have
the access of that data?
Ans: yes a relevant data can be obtained from the data book available on the field and get the
desired data.
6. Software use for taking the data for the jobs performs by CTU?
Ans: currently no software are using for performing the job.
7. Why we perform a job of coiled tubing unit on any well (reasons for performing the job)
Ans: The reasons for performing the job on any well are following:
For the flow of hydrocarbons by kick off the well or nitrogen lifting
For formation fracturing or cleaning the bore hole by pumping the chemicals
For drilling purposes
8. What problems mostly faced in the well and which appropriate jobs performed by the
CTU for those problems and what results we get after the performing of the jobs?
Ans: many problems faced by during performing the job and the solutions of those problems
are found during the performing of job.
9. In Pakistan can drilling occur with the help of CTU?
Ans: yes drilling took place by CTU in zinn Baluchistan
10. What will be the optimum cost of any job performing by the CTU?
Ans: a complete cost analysis took place and the final report of the cost for the job is sent to
the head office and also keeps the record at field also.
11. Alternative to CTU for any job perform by it1
Ans: for pumping of chemicals without CTU a drill string is used which is time consuming
no by performing the same job with CTU it is very easy to pump the chemicals at the
required depth.
Questions Related to the Components of CTU
Many manuals of different companies are available on net of CTU, what is the specification of
CTU of OGDCL and can we get that manual of CTU
Ans: we can get the specification of CTU operated by OGDCL from the field where unit is placed.

The basic components of CTU:
1-Coiled Tubing Reel
I. Types of reel and coiled
II. Material which made coil
Ans: alloy
III. Diameter and the entire length of coil
Ans: diameter 1.5 OD , length varies from
IV. Stress bearing capacity of coil
V. Either buckling occurs when run in hole the coil or not
VI. Maximum limit of sustaining the pressure
2-Injector Head
I. Specification
II. Working principle
III. Procedure of working
IV. How to installed injector head
V. How fluid injected into the coil by the injector head
VI. Is there any limitation of injector head?
3-Power Pack and Control Cabin
4-Pressure Control Equipment
5-Fluid injected or used for different performing of jobs
I. Which type of fluid injected for which type of job
II. Properties of fluid injected
III. At what pressure the fluid injected
IV. Fluid density, viscosity, specific gravity
V. Impact of fluid on the formation
VI. Is there any chance the injected fluid my also cause the formation damage or skin?

Refer the book of Schlumberger for study of components of CTU


Question related to Field Activity of CTU
1. How much time it takes for rig up
Ans: depend upon the type of job will be going to perform
General Discussion on CTU:
Argon welding done to join the coiled tubing joints and then observe carefully the join
after welding by X-ray and if 80% ok then consider that welding and use for performing
the jobs.
Tank in which fluid or any chemical stored for pumping purpose:
Unit in which we measured are cubic meter, bbl.
Pump the fluid at maximum 3000 psi
If using new coil then the pumping pressure extend up to 8000 psi
Chemical Pumping:
If chemical is to pump from the CTU then as the coil is run in the hole initially 25 bbl. Of fluid
injected in it then the further 16 bbl. Introduced in the coil then when reach at the desired depth
then for flush out the initially injected fluid from the coil 16bbl. Further fluid introduced into the
coil.
Installation of the submersible Pump:
The installation of submersible pump for the artificial lifting of hydrocarbons from the well bore
also take place by this CTU.