Вы находитесь на странице: 1из 42

Gran Telescopio de Canarias, S.A.

Instituto de Astrofsica de Canarias Centro Comn de Astrofsica de La Palma


Va Lctea s/n Cuesta de San Jos s/n
38200 - LA LAGUNA, TENERIFE, Islas Canarias 38712 BREA BAJA, LA PALMA, Islas Canarias
Tfno +34 922 315 031 Fax +34 922 315 032 Tfno +34 922 425 720 Fax +34 922 425 701

http://www.gtc.iac.es E-Mail: gtc@iac.es
















Cdigo : EXT/IDOM/2015-R
Edicin : 1.A
Fecha: 2014-05-19











GTC Dome Shutters Upgrade. Preliminary
Reliability Analysis



Cupula




Control de aprobacin
Recibido por:

Llus Cavaller Marques
Ingeniero de Desarrollos


Autorizado por:
Pedro lvarez Martn
Director
Fecha:2014-05-19
GTC Dome Shutters Upgrade Reliability Analysis

2015x1aa; 11/04/2014
3/42








GTC Dome Shutters Upgrade



PHASE II: RELIABILITY ANALYSIS
TECHNICAL REPORT



Doc. Number: 18242-TRE-012
Issue: 2 Date: 11/04/2014
Revision: - Date: -
Contract No: -

Name Signature Date
Written Nigel Bilbao 11/04/2014
Revised Asier Larringan 11/04/2014
Project Manager Celia Gmez 11/04/2014
Principal Gaizka Murga 11/04/2014

File: 18242-TRE-012-01_Reliability-Analysis.docx Pages: 42


GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
4/42

RECORD OF CHANGES


Issue Date Author Description
1.D 26/02/2014 Nigel Bilbao Draft version
1 28/02/2014 Nigel Bilbao First version
2 11/04/2014 Nigel Bilbao
Version after Review Meeting with
GRANTECAN

GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
5/42

ABBREVIATIONS


AD Applicable Document
GTC Gran Telescopio de Canarias
HPU Hydraulic Power Unit
MTTF Mean Time To Failure
MTBF Mean Time Between Failures
MTTR Mean Time To Repair
N/A Not Applicable
NC Not Compliant
ORM Observatorio de Roque de los Muchachos
PA Product Assurance
PHA Preliminary Hazards Analysis
RAMS Reliability, Availability, Maintainability and Safety
RBD Reliability Block Diagram
RD Reference Document
ROM Rough Order of Magnitude
SOW Statement of Work
TBC To Be Confirmed
TBD To Be Determined
TBR To Be Revised
UPS Uninterrupted Power System
VSD Variable Speed Drives
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
6/42

TABLE OF CONTENTS


1 SCOPE OF THE DOCUMENT ................................................................................................. 7
2 APPLICABLE AND REFERENCE DOCUMENTS ................................................................. 8
2.1 APPLICABLE DOCUMENTS .............................................................................................................................. 8
2.2 REFERENCE DOCUMENTS .............................................................................................................................. 8
3 INTRODUCTION ...................................................................................................................... 9
3.1 BACKGROUND .................................................................................................................................................. 9
3.2 OVERVIEW OF THE PROPOSED DESIGN ..................................................................................................... 10
3.3 DOCUMENT STRUCTURE ............................................................................................................................... 11
4 RELIABILITY ANALYSIS PROCEDURE ............................................................................... 12
4.1 INTRODUCTION .............................................................................................................................................. 12
4.2 RELIABILITY BLOCK DIAGRAMS ................................................................................................................. 12
4.3 DEFINITION OF FAILURE RATE .................................................................................................................... 13
4.4 REPAIRABLE AND NON-REPAIRABLE SYSTEMS ......................................................................................... 14
5 UPPER SHUTTER SYSTEM .................................................................................................... 16
5.1 INTRODUCTION .............................................................................................................................................. 16
5.2 CURRENT STATUS ........................................................................................................................................... 17
5.2.1 System representation ..................................................................................................................................... 17
5.2.2 Results ........................................................................................................................................................... 19
5.3 NEW STATUS ................................................................................................................................................... 21
5.3.1 System representation ..................................................................................................................................... 22
5.3.2 Results ........................................................................................................................................................... 24
5.4 RELIABILITY AND AVAILABILITY DIAGRAMS ............................................................................................. 25
6 LOWER SHUTTER SYSTEM .................................................................................................. 27
6.1 INTRODUCTION .............................................................................................................................................. 27
6.2 CURRENT STATUS ........................................................................................................................................... 28
6.2.1 System representation ..................................................................................................................................... 28
6.2.2 Results ........................................................................................................................................................... 30
6.3 NEW STATUS ................................................................................................................................................... 31
6.3.1 System representation ..................................................................................................................................... 32
6.3.2 Results ........................................................................................................................................................... 34
6.4 RELIABILITY AND AVAILABILITY DIAGRAMS ............................................................................................. 35
7 CONCLUSIONS ....................................................................................................................... 37
8 ADDITIONAL ANALYSES ...................................................................................................... 38
8.1 UPPER SHUTTER UPDATED NEW STATUS ................................................................................................... 38
8.2 LOWER SHUTTER UPDATED NEW STATUS ................................................................................................. 40

GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
7/42

1 SCOPE OF THE DOCUMENT

This document describes the Reliability Analysis performed for the proposed GTC Dome Shutters
Upgrade as compared to the current situation. The results from this analysis determine the current
and upgraded system availability and can be used for the definition of a preventive maintenance
plan.

Together with the Preliminary Design Report (18242-TRE-011-01), the Implementation Plan
(18242-PLA-013-01) and the Preliminary Cost Estimation (18242-LIS-014-01), this report
constitutes the Final Delivery Package for the Definition of the GTC Dome Shutters Upgrade
project.
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
8/42

2 APPLI CABLE AND REFERENCE
DOCUMENTS

2.1 APPLICABLE DOCUMENTS
Title Reference Iss. Date
AD 1
Statement of Work for the definition of
GTC Dome Shutters Upgrade
ESP/EDIF/0200-R 1.A 20/03/2013
AD 2 Current Status of the Dome Shutters RPT/EDIF/0386-R 1.A 18/03/2013

2.2 REFERENCE DOCUMENTS
Title Reference Iss. Date
RD 1 1
st
Progress Meeting Presentation 18242-PRE-001 1 11/10/2013
RD 2 1
st
Progress Report 18242-TRE-002 1 9/10/2013
RD 3 1
st
Progress Meeting Minutes 18242-MIN-003 1 16/10/2013
RD 4 Phase I: Analysis of Alternatives Report 18242-TRE-004 1 25/11/2013
RD 5 End of Phase I Meeting Presentation 18242-PRE-005 1 29/11/2013
RD 6 End of Phase I Meeting Minutes 18242-MIN-006 2 02/12/2013
RD 7 Phase II: Preliminary Cost Estimation 18242-LIS-014 2 11/04/2014
RD 8 Phase II: Implementation Plan 18242-PLA-013 2 11/04/2014
RD 9 Phase II: Preliminary Design Report 18242-TRE-011 2 11/04/2014
RD 10
The Complete Guide to Chain (http://chain-
guide.com)

RD 11
Michael Hess Replacing the K1 Dome
Shutter drive system
Proc. SPIE 6273-17
RD 12
Reliability, Maintainability and Risk, D. J.
Smith

RD 13
Reliability, Availability and Optimization,
Reliasoft System Analysis Reference


GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
9/42

3 I NTRODUCTI ON

3.1 BACKGROUND
The current shutter system of the GTC dome does not fully comply with the expected
requirements. The problems detected are essentially: a) a restricted range on main shutter opening,
which limits the telescope observation angle to 70 deg. above horizon; b) premature damage on
shutter bogies; c) the impossibility of deploying the windscreen, which has not been commissioned
yet; d) damages (cracks, corrosion, deformations) in the dome arch beams. These problems are
described by GRANTECAN in document AD 2.

GRANTECAN has launched this project consisting of: a) an analysis of alternatives aimed to
finding solutions to the current problems of the GTC dome shutters; b) selecting the best solution
in terms of performance, cost and implementation time and developing it up to a preliminary
design.

During the Phase I of this project the diagnostics developed by GRANTECAN was analysed and
completed and individual actions were identified aimed to solve each problem detected. In order to
evaluate the feasibility of these actions, they were combined into 3 particular packages, intended to
configure 3 potential solutions that were physically developed up to a conceptual design stage to
check and illustrate their applicability. A final trade-off analysis was developed to evaluate the pros
and cons of each solution. All this work is compiled in RD 4.

At the end of Phase I, GRANTECAN reviewed the delivered documentation and decided on the
solution out of the 3 proposed options which will be further developed up to a preliminary design
stage. The solution selected was the first alternative proposed (Option A), but modified to
include some additional actions:

Bogies design upgrade
Possibility of excluding the counterweight system
Prevision of emergency systems for the lower shutter operation

Option A consists in basically keeping the existing drive system typology but introducing a set of
incremental actions aimed to improve the current performance and solve the main problems. The
safety and reliability of each of the components (chains, motors, gearboxes) is increased as their
demanding loads will be lower than the allowable values. The actions include:

Replace current upper shutter chains by others with higher strength
Implement a counterweight system to reduce load at the last part of upper shutter travel
Improve load sharing between drives by a proper control system strategy.
Install a take-up system in chains to reduce the required preload
Install axial supplements in the guiding rails to reduce the rail runout
Replace motors and gearboxes of Lower shutter by others with higher power
Move the location of windscreen latching system to avoid overlapping
Reduce the windscreen weight
Replace current windscreen rollers cam followers for friction reduction
Modify the bottom profile of the windscreen guides
Monitor crack propagation, register a crack inventory and take actions according to the
propagation speed (grind-repair, crack arrest drilling, structural reinforcement)


GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
10/42

3.2 OVERVIEW OF THE PROPOSED DESIGN
The GTC Dome Shutters proposed modifications relevant to the present reliability analysis affect
to the drive system, control system and guiding system of both upper shutter and lower shutter.
Regarding the drive system, the upgraded design includes:
- Replacement of current roller chains by higher capacity chains, in both upper and lower
shutter
- In addition, for the lower shutter:
o replacement of main motors for higher power motors
o replacement of current gearboxes for double input gearboxes to include an
auxiliary gearmotor for redundancy, which will enable emergency operation in case
of failure of main motor.

Fig 3-1 Actions in shutters drive systems
The proposed redesign also includes an optional counterweight system, which would
contribute to reduce the loads in the last stage of the upper shutter travel.
For the guiding system, an improved bogie design is proposed with capability to absorb the rail
radial misalignment by means of a hydraulic equalization system. For each shutter, four
hydraulic equalization groups (each one including 5 bogies for the upper shutter and 2 bogies
for the lower shutter) have been defined.

Fig 3-2 Guiding system upgrade
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
11/42

Apart from the hydraulic actuator and the eccentric shaft for radial adjustment, the new bogie
design includes two radial wheels instead of one, for additional strength under the acting loads.
The shutters lateral guidance is also improved by means of axial correction supplements welded
to the rails.
For the control system, an optimized control strategy (Speed Trim Follower) is proposed
aimed to provide a better load sharing between drives. This configuration consists of:
the master drive is operated in speed regulation
the slave drives are operated in speed regulation with a speed trim that is function of
the difference between the master drive and each slave drive torque.
The equal load distribution between drives achieved with this new control strategy, together
with the replacement of drive chains and the improvement on shutter lateral guidance provided
by the axial correction supplements, can enable the operation of the upper shutter with only
three out of the four drives in emergency conditions.
More information about the Preliminary Design can be found in RD 9.


3.3 DOCUMENT STRUCTURE
The contents of this document are structured as follows:
The next chapter (Chapter 4) describes the general reliability analysis procedure: the concepts
of Mean Time Between Failures (MTBF) and Mean Time to Repair (MTTR), the assumptions
and exclusions of the present analysis, the representation in Reliability Block Diagrams (RBD),
the definition of the Failure rate and the classification of systems in Repairable and Non-
Repairable.
Chapter 5 and Chapter 6 contain the reliability assessment for the Upper Shutter and the Lower
Shutter respectively, applied to current status and new status (upgraded system). It includes the
system representation and the obtained results, together with final plots comparing the
availability and reliability in current and new status.
Finally, Chapter 7 summarizes the conclusions of this analysis.


GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
12/42

4 RELI ABI LI TY ANALYSI S PROCEDURE

4.1 INTRODUCTION
The aim of this analysis is to study the reliability of the GTC Dome Shutters proposed upgrade and
quantify the improvement with respect to the current. As part of this assessment, the mean time
between failures (MTBF) is obtained for the Upper and Lower Shutter

Once obtained the MTBF and determined the MTTR, the availability of each shutter, defined as
the probability that a repairable system will fulfil its specified function at a certain time, can be
determined as,

MTTR MTBF
MTBF
A
I
+
=


The down time (= 1-Availability) gives an idea of how much time the system is stopped comparing
to the total time.

A reliability analysis provides a quantitative measure of how close a proposed design comes to
meeting the design objectives and allows comparisons to be made between different designs (in this
case, current system and proposed redesign).

The assessment has been performed at a high level, i.e. potential failures of easily replaceable
components, such as electric elements of electric cabinets (relays, current supply, etc.) have not
been considered. This reliability analysis refers only to components whose MTTR is more than 4
hours. Also, it is assumed an uninterrupted power supply to the GTC dome in the Observatory (an
UPS would provide power in case of failure of the electrical supply)

4.2 RELIABILITY BLOCK DIAGRAMS

In order to determine the reliability of the systems, the different failure modes have been identified
and the system reliability as a function of component reliability has been studied, by means of
Reliability Block Diagrams.


Fig 4-1 Reliability Block Diagram (RBD) for a given system
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
13/42


In order to form a system reliability block diagram, the reliability-wise configuration of the
components must be determined. The RBD of a complex system can be formed by different
combinations of the following simple configurations:

- Series configuration: in a series configuration a failure of any component results in the
failure of the entire system
- Simple parallel configuration: in a simple parallel system, at least one of the units must
succeed for the system to succeed.
- K-out-of-n configuration: this type of configuration requires that at least k components
succeed out of the total n parallel components for the system to succeed.



Fig 4-2 Series, parallel and k-out-of-n configuration examples

4.3 DEFINITION OF FAILURE RATE
For the different components involved in the system the failure rate (t) - defined as the probability
of an item failing in the interval t to t+dt, given that it has survived until time t- is assigned.

) (
) (
) (
t R
t f
t =
where,
f(t) is the failure probability density function
R(t) is the reliability or probability of survival until a time t

Many mechanical and electrical components failure rate can be adjusted to a bathtub failure rate
function, which establishes that,

- the failures exhibited in the first part of the curve, where failure rate is decreasing, are
called early or infant mortality failures
- the middle portion is referred to as the useful life and it is assumed that failures exhibit a
constant failure rate
- the latter part of the curve describes the wear-out failures and it is assumed that failure rate
increases as the wear-out mechanisms accelerate


GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
14/42


Fig 4-3 Bathtub failure rate distribution, typical of many mechanical components

A constant value of (failure rate) has been considered for each component of the system. This
assumption involves that early failures would be mostly corrected during the commissioning of the
systems and wear-out failures would be minimized with an appropriate preventive maintenance
policy. Thus, reliability (R(t)) can be expressed as,

t
d
e e t R
t

=
0
) (
) (

The failure rate data for the different components have been obtained from the
FARADIP.THREE data bank [RD 12].



4.4 REPAIRABLE AND NON-REPAIRABLE SYSTEMS
Systems can be generally classified into non-repairable and repairable systems. Non-repairable
systems are those that do not get repaired when they fail. On the other hand, repairable systems are
those that get repaired when fail. This is done by repairing or replacing the failed components in
the system.

Considering a system as a non-repairable one, analytical methods can be applied, obtaining
parameters such as the followings:

- system failure probability density function (pdf)
- warranty periods
- system failure rate
- mean time to failure (MTTF)

If the systems are treated as repairable ones and a maintenance policy is established, similar results
can be determined by means of simulation, obtaining the following parameters:

- system availability
- mean time between failure (MTBF)

Depending on the preliminary results of the reliability analysis, actions on the most critical
component of each system in order to improve system reliability can be considered. This action is
focused following two approaches,
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
15/42


- fault avoidance, e.g. increase components reliability
- fault tolerance, e.g. consider component redundancy or k-out-of-n parallel configurations
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
16/42

5 UPPER SHUTTER SYSTEM

5.1 INTRODUCTION
The aim of this chapter 5 is to make a comparison between the current status and the new status of
the dome upper shutter system. For this purpose, taking into account the failure rates of the
different components that compose the upper shutter, the MTBF, the MTTR and the availability
will be obtained.

In the new status analysis, the optional counterweight system has not been considered. If this
system is finally installed, it will increase the reliability associated to the upgraded upper shutter.

The following figures show some of the different components and subsystems that have been taken
into account for the reliability analysis:


Fig 5-1 Upper shutter current status guiding system and drive mechanism


Fig 5-2 Upper shutter new status guiding system and drive mechanism

GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
17/42

5.2 CURRENT STATUS
The following figure represents the RBD of the current status of the upper shutter system:


Fig 5-3 Upper shutter system current status reliability block diagram

5.2.1 System representation
For the correct operation of the upper shutter mechanism, the control system, the drive system and
the guiding system must work correctly. Therefore the RBD for the dome upper shutter
mechanism is as follows:


Fig 5-4 Upper shutter mechanism representation
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
18/42


The control system controls the upper shutter drive system and is composed of a PLC (which
includes communication cards, power supplies, etc.) and a rectifier.



Fig 5-5 Upper shutter control system representation

As shown in Fig 5-1, the drive system is composed of four drives that two of them are in the
upper motor stations (upper part of the dome) and the other two are in the lower motor stations (at
the lower part of the dome). These drives are composed by some subsystems such as the frequency
converter (VSD), the motor, the brake, the encoder, the gearbox and the chain (see Fig 5-6). As it
can be seen in Table 5-1, some drives components have two MTTR (Mean Time To Repair) values
depending if the component belongs to an upper or a lower drive.





Fig 5-6 Upper shutter drive system representation

The guiding system, shown in Fig 5-1, is composed of twenty six bogies, which need to be
working for the correct movement of the dome upper shutter. In the same way, every wheel of the
bogie together with its corresponding bearing has to be working for its correct operation.


GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
19/42




Fig 5-7 Upper shutter guiding system representation

As it has been explained before, the system has been studied as a repairable system. The failure data
for each component, used as input for the system analysis, has been obtained from the
FARADIP.THREE data bank [RD 12], and are shown as follows:


Table 5-1. Component failure rate and MTTR used in the Upper Shutter System Current Status analysis

5.2.2 Results
The whole GTC Dome Shutters lifetime (50 years) has been considered. Up to 10000 different
failure scenarios have been simulated (with different combination of components failure along the
time). For each component, a MTTR (mean time to repair) value has been considered.

The MTBF for each subsystem has been obtained, as well as the MTBF of the whole system.
Applying the formula explained in chapter 4.1, with the selected MTTR, the availability and MTTR
of every subsystem and the whole system have been obtained. These results are shown in the
following table:

Failure Rate
(per million hours)

(1/hours)
Component MTTF
(hours)
Component MTTF
(years)
Component MTTR
(hours)
Wheels 2 0.000002 5.00E+05 119.05 168
Bearings 2 0.000002 5.00E+05 119.05 168
VSD 5 0.000005 2.00E+05 47.62 4
Motor a.c. 5 0.000005 2.00E+05 47.62 Upper: 36 / Lower: 24
Brake 10 0.00001 1.00E+05 23.81 Upper: 12 / Lower: 8
Encoder 7 0.000007 1.43E+05 34.01 Upper: 36 / Lower: 24
Gearbox 20 0.00002 5.00E+04 11.90 Upper: 72 / Lower: 48
Chain 0.5 0.0000005 2.00E+06 476.19 24
PLC 40 0.00004 2.50E+04 5.95 4
Rectifier 4 0.000004 2.50E+05 59.52 24
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
20/42


Table 5-2. Upper Shutter System Current Status Reliability, Availability & MTTR analysis results.


MTBF
(hours)
MTBF
(years)
MTTR
(hours)
Availability
(%)
Bogie 2.49031E+05 59.29 167.99 99.93
Guiding System 9.59461E+03 2.28 167.93 98.28
Upper Drive 2.09829E+04 5.00 42.72 99.80
Lower Drive 2.09847E+04 5.00 28.73 99.86
Drive System 5.26684E+03 1.25 35.63 99.33
Control System 2.26503E+04 5.39 5.82 99.97
System 2.95969E+03 0.70 72.40 97.61
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
21/42

5.3 NEW STATUS
The following figure represents the RBD of the new status of the upper shutter system:


Fig 5-8 Upper shutter system new status reliability block diagram

GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
22/42

5.3.1 System representation
For the correct operation of the upper shutter mechanism, the control system, the drive system and
the guiding system must work correctly. Therefore the RBD for the dome upper shutter
mechanism is as follows:


Fig 5-9 Upper shutter mechanism representation

The control system controls the upper shutter drive system and is composed of a PLC (which
includes communication cards, power supplies, etc.) and a rectifier.



Fig 5-10 Upper shutter control system representation

As shown in Fig 5-2, the drive system is composed of four drives that two of them are at the top
of the shutter and the other two are at the lower part of the shutter. These drives are composed by
some subsystems such as the frequency converter (VSD), the motor, the brake, the encoder, the
gearbox and the chain (see Fig 5-11). As it can be seen in Table 5-3, some drives components have
two MTTR (Mean Time To Repair) values depending if the component belongs to an upper or a
lower drive. Considering the actions taken for the drive system upgrade (higher resistance chains,
improved control strategy) together with the lateral guidance correction, the new design enables the
operation with 3 out of 4 drives





Fig 5-11 Upper shutter drive system representation
DRIVE 1
DRIVE 2
DRIVE 3
DRIVE 4
3/4
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
23/42


The updated guiding system, shown in Fig 5-2, is composed of four hydraulic groups (5 bogies
per group). All hydraulic groups need to be properly working for the correct support of the dome
upper shutter. It has been assumed that inside each hydraulic group, a failure of one of the new
supporting bogies can be admitted. The new bogie system is composed of a hydraulic actuator and
a new bogie. Each bogie has two radial wheels with each corresponding bearing. None of them can
be damaged for a proper working of this bogie.







NEW BOGIE
SYSTEM 1
NEW BOGIE
SYSTEM 2
NEW BOGIE
SYSTEM 3
NEW BOGIE
SYSTEM 4
4/5
NEW BOGIE
SYSTEM 5
HYDRAULIC BOGIE GROUPS COMPOSITION
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
24/42

Fig 5-12 Upper shutter guiding system representation

As it has been explained before, the system has been studied as a repairable system. The failure data
for each component, used as input for the system analysis, has been obtained from the
FARADIP.THREE data bank [RD 12], and are shown as follows:


Table 5-3. Component failure rate and MTTR used in the Upper Shutter System New Status analysis

5.3.2 Results
The whole GTC Dome Shutters lifetime (50 years) has been considered. Up to 10000 different
failure scenarios have been simulated (with different combination of components failure along the
time). For each component, a MTTR (mean time to repair) value has been considered.

The MTBF for each subsystem has been obtained, as well as the MTBF of the whole system.
Applying the formula explained in chapter 4.1, with the selected MTTR, the availability and MTTR
of every subsystem and the whole system have been obtained. These results are shown in the
following table:


Table 5-4. Upper Shutter System New Status Reliability, Availability & MTTR analysis results.

Failure Rate
(per million hours)

(1/hours)
Component MTTF
(hours)
Component MTTF
(years)
Component MTTR
(hours)
Wheels 1 0.000001 1.00E+06 238.10 168
Bearings 1 0.000001 1.00E+06 238.10 168
Hydraulic Actuator 15 0.000015 6.67E+04 15.87 48
Hydraulic System 10 0.00001 1.00E+05 23.81 168
VSD 5 0.000005 2.00E+05 47.62 4
Motor a.c. 5 0.000005 2.00E+05 47.62 Upper: 36 / Lower: 24
Brake 10 0.00001 1.00E+05 23.81 Upper: 12 / Lower: 8
Encoder 7 0.000007 1.43E+05 34.01 Upper: 36 / Lower: 24
Gearbox 20 0.00002 5.00E+04 11.90 Upper: 72 / Lower: 48
Chain 0.5 0.0000005 2.00E+06 476.19 24
PLC 40 0.00004 2.50E+04 5.95 4
Rectifier 4 0.000004 2.50E+05 59.52 24
MTBF
(hours)
MTBF
(years)
MTTR
(hours)
Availability
(%)
Bogie 2.48382E+05 59.14 167.88 99.93
Bogie System 5.26788E+04 12.54 73.09 99.86
Hydraulic Bogie Group 1.98860E+06 473.48 35.81 100.00
Guiding System 8.27506E+04 19.70 145.20 99.82
Upper Drive 2.09829E+04 5.00 42.72 99.80
Lower Drive 2.09847E+04 5.00 28.73 99.86
Drive System 1.05209E+06 250.50 17.37 100.00
Control System 2.26503E+04 5.39 5.82 99.97
System 1.74524E+04 4.16 35.32 99.80
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
25/42

5.4 RELIABILITY AND AVAILABILITY DIAGRAMS
The next figures show the comparison of the reliability functions for current status and new status
of the upper shutter. Fig 5-13 time scale refers to the lifetime of 50 years. Fig 5-14 shows the first
part of the plots (ten initial years) for discernment of the difference in the curve shape.



Fig 5-13 Upper shutter current and new status reliability diagrams (50 years)



Fig 5-14 Upper shutter current and new status reliability diagrams (10 years)

Next figure shows the system up/down periods along time for the upper shutter current status and
new status. The system availability is increased from 97.61% to 99.80%.
Control System
Drive System
Guiding System
System
Control System
Drive System
Guiding System
System
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
26/42


Fig 5-15 Upper shutter current and new status availability diagrams

GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
27/42

6 LOWER SHUTTER SYSTEM

6.1 INTRODUCTION
The aim of this chapter 6 is to make a comparison between the current status and the new status of
the dome lower shutter system. For this purpose, taking into account the failure rates of the
different components that compose the upper shutter, the MTBF, the MTTR and the availability
will be obtained.

For the lower shutter system reliability analysis, the windscreen potential failures have not been
considered for the analysis.

The following figures show some of the different components and subsystems that have been taken
into account for the reliability analysis:

Fig 6-1 Lower shutter current status guiding system and drive mechanism


Fig 6-2 Lower shutter new status guiding system and drive mechanism
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
28/42

6.2 CURRENT STATUS
The following figure represents the RBD of the current status of the lower shutter system:


Fig 6-3 Lower shutter system current status reliability block diagram

6.2.1 System representation
For the correct operation of the lower shutter mechanism, the control system, the drive system and
the guiding system must work correctly. Therefore the RBD for the dome lower shutter mechanism
is as follows:


Fig 6-4 Lower shutter mechanism representation

The control system controls the lower shutter drive system and is composed of a PLC (which
includes communication cards, power supplies, etc.) and a rectifier.

P
L
C
D
R
I
V
E

1
D
R
I
V
E

2
R
E
C
T
I
F
I
E
R
B
O
G
I
E

1
B
O
G
I
E

2
C
O
N
T
R
O
L

S
Y
S
T
E
M
D
R
I
V
E

S
Y
S
T
E
M
G
U
I
D
I
N
G
S
Y
S
T
E
M
V
S
D
M
O
T
O
R
G
E
A
R
B
O
X
C
H
A
I
N

1
B
R
A
K
E
E
N
C
O
D
E
R
D
R
I
V
E
S
C
O
M
P
O
S
I
T
I
O
N
W
H
E
E
L

1
B
E
A
R
I
N
G

1
B
O
G
I
E
S

C
O
M
P
O
S
I
T
I
O
N
B
O
G
I
E

1
0
C
H
A
I
N

2
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
29/42



Fig 6-5 Lower shutter control system representation

As shown in Fig 6-1, the drive system is composed of two drives that both of them are in the
upper motor stations (upper part of the dome). These drives are composed by some subsystems
such as the frequency converter (VSD), the motor, the brake, the encoder, the gearbox and two
chains (as a single motor moves the two chains, see Fig 6-6).




Fig 6-6 Lower shutter drive system representation

The guiding system, shown in Fig 6-1, is composed of ten bogies (5 at each side), which need to
be working for the correct support of the dome lower shutter. In the same way, every wheel of the
bogie together with its corresponding bearing has to be working for its correct operation.





Fig 6-7 Lower shutter guiding system representation
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
30/42


As it has been explained before, the system has been studied as a repairable system. The failure data
for each component, used as input for the system analysis, has been obtained from the
FARADIP.THREE data bank [RD 12], and are shown as follows:


Table 6-1. Component failure rate and MTTR used in the Lower Shutter System Current Status analysis

6.2.2 Results
The whole GTC Dome Shutters lifetime (50 years) has been considered. Up to 10000 different
failure scenarios have been simulated (with different combination of components failure along the
time). For each component, a MTTR (mean time to repair) value has been considered.

The MTBF for each subsystem has been obtained, as well as the MTBF of the whole system.
Applying the formula explained in chapter 4.1, with the selected MTTR, the availability and MTTR
of every subsystem and the whole system have been obtained. These results are shown in the
following table:


Table 6-2. Lower Shutter System Current Status Reliability, Availability & MTTR analysis results.


Failure Rate
(per million hours)

(1/hours)
Component MTTF
(hours)
Component MTTF
(years)
Component MTTR
(hours)
Wheels 2 0.000002 5.00E+05 119.05 168
Bearings 2 0.000002 5.00E+05 119.05 168
VSD 5 0.000005 2.00E+05 47.62 4
Motor a.c. 5 0.000005 2.00E+05 47.62 36
Brake 10 0.00001 1.00E+05 23.81 12
Encoder 7 0.000007 1.43E+05 34.01 36
Gearbox 20 0.00002 5.00E+04 11.90 72
Chain 1 0.5 0.0000005 2.00E+06 476.19 24
Chain 2 0.5 0.0000005 2.00E+06 476.19 24
PLC 40 0.00004 2.50E+04 5.95 4
Rectifier 4 0.000004 2.50E+05 59.52 24
MTBF
(hours)
MTBF
(years)
MTTR
(hours)
Availability
(%)
Bogie 2.49031E+05 59.29 167.99 99.93
Guiding System 2.50204E+04 5.96 167.94 99.33
Drive 2.08276E+04 4.96 42.54 99.80
Drive System 1.03862E+04 2.47 42.42 99.59
Control System 2.26503E+04 5.39 5.82 99.97
System 5.54270E+03 1.32 61.34 98.91
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
31/42

6.3 NEW STATUS
The following figure represents the RBD of the new status of the lower shutter system:


Fig 6-8 Lower shutter system new status reliability block diagram

P
L
C
D
R
IV
E
1
D
R
IV
E
2
H
Y
D
R
A
U
L
IC

S
Y
S
T
E
M
R
E
C
T
IF
IE
R
C
O
N
T
R
O
L
S
Y
S
T
E
M
D
R
IV
E
S
Y
S
T
E
M
G
U
ID
IN
G
S
Y
S
T
E
M
V
S
D
M
A
IN

M
O
T
O
R
M
A
IN

G
E
A
R
B
O
X
C
H
A
IN
2
B
R
A
K
E
E
N
C
O
D
E
R
D
R
IV
E
S
C
O
M
P
O
S
IT
IO
N
N
E
W
B
O
G
IE

S
Y
S
T
E
M
1
N
E
W
B
O
G
IE

S
Y
S
T
E
M
2
N
E
W
B
O
G
IE

S
Y
S
T
E
M
1
N
E
W
B
O
G
IE

S
Y
S
T
E
M
2
H
Y
D
R
A
U
L
IC
B
O
G
IE
G
R
O
U
P
S
C
O
M
P
O
S
IT
IO
N
V
S
D
A
U
X
IL
IA
R
Y

M
O
T
O
R
B
R
A
K
E
E
N
C
O
D
E
R
A
U
X
IL
IA
R
Y

G
E
A
R
B
O
X
C
H
A
IN
1
H
Y
D
R
A
U
L
IC

A
C
T
U
A
T
O
R
W
H
E
E
L
1
B
E
A
R
IN
G
2
B
E
A
R
IN
G
1
W
H
E
E
L
2
N
E
W
B
O
G
IE
S
Y
S
T
E
M
S
C
O
M
P
O
S
IT
IO
N
N
E
W
B
O
G
IE
S
C
O
M
P
O
S
IT
IO
N
H
Y
D
R
A
U
L
IC
B
O
G
IE
G
R
O
U
P
1
N
E
W
B
O
G
IE

S
Y
S
T
E
M
3
N
E
W
B
O
G
IE

S
Y
S
T
E
M
4
H
Y
D
R
A
U
L
IC
B
O
G
IE
G
R
O
U
P
2
N
E
W
B
O
G
IE

S
Y
S
T
E
M
5
N
E
W
B
O
G
IE

S
Y
S
T
E
M
6
H
Y
D
R
A
U
L
IC
B
O
G
IE
G
R
O
U
P
3
N
E
W
B
O
G
IE

S
Y
S
T
E
M
7
N
E
W
B
O
G
IE

S
Y
S
T
E
M
8
H
Y
D
R
A
U
L
IC
B
O
G
IE
G
R
O
U
P
4
7
/8
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
32/42

6.3.1 System representation
For the correct operation of the lower shutter mechanism, the control system, the drive system and
the guiding system must work correctly. Therefore the RBD for the dome lower shutter mechanism
is as follows:


Fig 6-9 Lower shutter mechanism representation

The control system controls the lower shutter drive system and is composed of a PLC (which
includes communication cards, power supplies, etc.) and a rectifier.



Fig 6-10 Lower shutter control system representation

As shown in Fig 6-2, the drive system is composed of two drives located at the upper station.
Each drive moves two chains and includes a redundant auxiliary motor apart from the main motor
(see Fig 6-11)





Fig 6-11 Lower shutter drive system representation

GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
33/42

The guiding system, shown in Fig 6-2, is composed of eight bogies in four hydraulic groups (2
bogies per group). It has been assumed that one bogie out of the eight can fail without affecting to
the guiding system operation. The new bogie system is composed of a hydraulic actuator and a new
bogie. Each bogie has two radial wheels with each corresponding bearing






Fig 6-12 Lower shutter guiding system representation
HYDRAULIC
SYSTEM
NEW BOGIE
SYSTEM 1
NEW BOGIE
SYSTEM 2
HYDRAULIC BOGIE GROUP 1
NEW BOGIE
SYSTEM 3
NEW BOGIE
SYSTEM 4
HYDRAULIC BOGIE GROUP 2
NEW BOGIE
SYSTEM 5
NEW BOGIE
SYSTEM 6
HYDRAULIC BOGIE GROUP 3
NEW BOGIE
SYSTEM 7
NEW BOGIE
SYSTEM 8
HYDRAULIC BOGIE GROUP 4
7/8
NEW BOGIE
SYSTEM 1
NEW BOGIE
SYSTEM 2
HYDRAULIC BOGIE GROUPS COMPOSITION
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
34/42


As it has been explained before, the system has been studied as a repairable system. The failure data
for each component, used as input for the system analysis, has been obtained from the
FARADIP.THREE data bank [RD 12], and are shown as follows:


Table 6-3. Component failure rate and MTTR used in the Lower Shutter System New Status analysis

6.3.2 Results
The whole GTC Dome Shutters lifetime (50 years) has been considered. Up to 10000 different
failure scenarios have been simulated (with different combination of components failure along the
time). For each component, a MTTR (mean time to repair) value has been considered.

The MTBF for each subsystem has been obtained, as well as the MTBF of the whole system.
Applying the formula explained in chapter 4.1, with the selected MTTR, the availability and MTTR
of every subsystem and the whole system have been obtained. These results are shown in the
following table:


Table 6-4. Lower Shutter System New Status Reliability, Availability & MTTR analysis results.

Failure Rate
(per million hours)

(1/hours)
Component MTTF
(hours)
Component MTTF
(years)
Component MTTR
(hours)
Wheels 1 0.000001 1.00E+06 238.10 168
Bearings 1 0.000001 1.00E+06 238.10 168
Hydraulic Actuator 15 0.000015 6.67E+04 15.87 48
Hydraulic System 10 0.00001 1.00E+05 23.81 168
VSD 5 0.000005 2.00E+05 47.62 4
Motor a.c. 5 0.000005 2.00E+05 47.62 36
Brake 10 0.00001 1.00E+05 23.81 12
Encoder 7 0.000007 1.43E+05 34.01 36
Gearbox (main) 20 0.00002 5.00E+04 11.90 72
Gearbox (auxiliary) 20 0.00002 5.00E+04 11.90 72
Chain 1 0.5 0.0000005 2.00E+06 476.19 24
Chain 2 0.5 0.0000005 2.00E+06 476.19 24
PLC 40 0.00004 2.50E+04 5.95 4
Rectifier 4 0.000004 2.50E+05 59.52 24
MTBF
(hours)
MTBF
(years)
MTTR
(hours)
Availability
(%)
Bogie 2.48382E+05 59.14 167.88 99.93
Bogie System 5.26788E+04 12.54 73.09 99.86
Hydraulic Bogie Group 2.07920E+07 4950.48 36.96 100.00
Guiding System 8.71346E+04 20.75 150.80 99.83
Drive 4.75259E+04 11.32 69.44 99.85
Drive System 2.37007E+04 5.64 69.48 99.71
Control System 2.26503E+04 5.39 5.82 99.97
System 1.02011E+04 2.43 50.34 99.51
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
35/42

6.4 RELIABILITY AND AVAILABILITY DIAGRAMS
The next figures show the comparison of the reliability functions for current status and new status
of the upper shutter. Fig 6-13time scale refers to the lifetime of 50 years. Fig 6-14shows the first
part of the plots (ten initial years) for discernment of the difference in the curve shape.



Fig 6-13 Lower shutter current and new status reliability diagrams (50 years)



Fig 6-14 Lower shutter current and new status reliability diagrams (10 years)

Next figure shows the system up/down periods along time for the upper shutter current status and
new status. The system availability is increased from 98.91% to 99.51%.

Control System
Drive System
Guiding System
System
Control System
Drive System
Guiding System
System
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
36/42


Fig 6-15 Lower shutter current and new status availability diagrams

GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
37/42

7 CONCLUSI ONS
The next tables summarize the final results obtained from the reliability assessment:


Table 7-1. Upper Shutter System comparison between current and new status


Table 7-2. Lower Shutter System comparison between current and new status

In both Upper and Lower Shutter systems, the improvement in the MTBF value is considerable
when comparing the results obtained for the proposed redesign (new status) with the current
installed system (current status).

For the upper shutter, the MTBF of the overall system is increased by a factor of 6, from a current
value of less than 1 year to a new value of more than 4 years. Especially relevant is the increase in
the availability of the drive system, mainly achieved by the possibility of operating with 3 out of the
4 drives. Also, a significant improvement in the MTBF is achieved for the guiding system.

In the case of the lower shutter, the current MTBF is higher than in the upper shutter (1.32 years
instead of 0.7 years), basically because the drive system is currently capable of operating with a
higher safety factor. However, this applies only to the lower shutter individual operation as
currently the lower shutter drives (motors and chains) have not enough capacity to deploy the
windscreen. The proposed actions for the drive system include higher capacity motors and chains
in order to enable windscreen deployment. There would be also an emergency system to guarantee
shutter operation in case of failure of one motor (auxiliary redundant motor in each drive), what
contributes to increase the drive system reliability. Apart from that, and similarly to the upper
shutter, the improved guiding system increases considerably the MTBF with respect to the current
bogies. The combination of these factors increases the MTBF for the lower shutter overall system
from 1.32 years to 2.43 years.

Current Status
MTBF (years)
New Status
MTBF (years)
Upper Shutter System 0.70 4.16
Guiding System 2.28 19.70
Drive System 1.25 250.50
Control System 5.39 5.39
Current Status
MTBF (years)
New Status
MTBF (years)
Lower Shutter System 1.32 2.43
Guiding System 5.96 20.75
Drive System 2.47 5.64
Control System 5.39 5.39
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
38/42

8 ADDI TI ONAL ANALYSES

During the meeting with GRANTECAN on 6
th
March, 2014, the following actions were agreed:

1. The necessity of referring the reliability study in terms of failures that avoid closing the
shutter system. In this sense, some malfunctions previously considered as failures (as in
the case of the bogies hydraulic system) have been reviewed as they will not affect to the
emergency closing of the shutter system.

2. The review of the drive system modelling: it was pointed out the necessity of representing
a gearbox and chain failure as critical failures which could entail to a stop of the system.
The probability of occurrence of this kind of failures is lower than a simple failure of the
gearbox which can or not bring to a stop of the system (example: the gearbox may not be
able to transmit torque however it is capable to rotate, allowing to be dragged by the rest of
the driving system). Therefore, the failure rate of the gearbox has been reduced down to 5
failures per million working hours.

3. Clarify if the MTBF refer to the operational time or real time. This issue is answered in the
next section. It refers to operational time, which for main components is around 1
hour/day. However, a few subsystems such as the power source of the control system has
a longer operational period, so during this study the operational time has been maintained
in 12 hours/day.

4. Indication of potential improvements in the control system aimed to increase its reliability.
The possibility of including some redundant components is outlined in next section.

This chapter includes the response to the previous actions and corresponding update of the results
of the reliability analysis.

8.1 UPPER SHUTTER UPDATED NEW STATUS
In order to account for the scenario stated in Action 2 of previous section, the Drive System has
been changed from the study shown in chapter 5.3. An additional block called Transmission,
which accounts for the chain and gearbox failure rates (set in series), has been added in series.

Following the request by GRANTECAN, an increase in the reliability of the Control System
(Action 4 of previous section) is proposed by duplicating the power source and the communication
card obtaining an increase in the reliability of the PLC. The new failure rate has been defined as 20
failures per million working hours.

The failure data for each component, used as input for the system analysis are shown as follows:

GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
39/42


Table 8-1. Component failure rate and MTTR used in the Upper Shutter System Updated New Status analysis

The whole GTC Dome Shutters lifetime (50 years) has been considered. Up to 10000 different
failure scenarios have been simulated (with different combination of components failure along the
time). For each component, a MTTR (mean time to repair) value has been considered.

The MTBF for each subsystem has been obtained, as well as the MTBF of the whole system.
Applying the formula explained in chapter 4.1, with the selected MTTR, the availability and MTTR
of every subsystem and the whole system have been obtained. These results are shown in the
following table:


Table 8-2. Upper Shutter System Updated New Status Reliability, Availability & MTTR analysis results.

Even though the operational time of most of the components of the guiding system, transmission
and driving system is around 1 hour/day, during this study the operational time per day has been
maintain in 12 hours/day as it should keep in mind that few subsystems such as the power source
of the control system has that operational period (Action 3 of previous section).

Thus, in case of reading the MTBF of the guiding, transmission and driving system, it is most
convenient to use the hours values and from them generate the corresponding number is years.

Failure Rate
(per million
hours)

(1/hours)
Component
MTTF (hours)
Component
MTTF (years)
Component MTTR
(hours)
Wheels 1 0,000001 1,00E+06 238,10 168
Bearings 1 0,000001 1,00E+06 238,10 168
Hydraulic Actuator 15 0,000015 6,67E+04 15,87 48
Hydraulic System 10 0,00001 1,00E+05 23,81 168
VSD 5 0,000005 2,00E+05 47,62 4
Motor a.c. 5 0,000005 2,00E+05 47,62 Upper: 36 / Lower: 24
Brake 10 0,00001 1,00E+05 23,81 Upper: 12 / Lower: 8
Encoder 7 0,000007 1,43E+05 34,01 Upper: 36 / Lower: 24
Gearbox 5 0,000005 2,00E+05 47,62 Upper: 72 / Lower: 48
Chain 0,5 0,0000005 2,00E+06 476,19 24
PLC 20 0,00002 5,00E+04 11,90 4
Rectifier 4 0,000004 2,50E+05 59,52 24
MTBF
(hours)
MTBF
(years)
MTTR
(hours)
Availability
(%)
Bogie 2,48382E+05 59,14 167,88 99,93
Bogie System 5,26788E+04 12,54 73,09 99,86
Hydraulic Bogie Group1,98860E+06 473,48 35,81 100,00
Guiding System 8,27506E+04 19,70 145,20 99,82
Transmission 4,53367E+04 10,79 56,89 99,87
Upper Drive 3,68824E+04 8,78 21,21 99,94
Lower Drive 3,68601E+04 8,78 14,39 99,96
Drive System 4,50226E+04 10,72 56,28 99,88
Control System 4,13818E+04 9,85 7,32 99,98
System 1,71494E+04 4,08 54,71 99,68
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
40/42

Finally, in order to obtain the system reliability in terms of unfeasibility to close the upper shutter
system (Action 1), the simulation has been repeated by assuming that the failures of the hydraulic
actuators and the hydraulic group (hydraulic system) do not cause system failure, i.e., by removing
these components from the guiding system reliability blocks.

The update results, including also the previous modifications, are included in the next table.


Table 8-3. Upper Shutter System Updated New Status, in terms of failures that avoid closing the shutter. Reliability,
Availability & MTTR analysis results.
The reliability of the guiding system in this case increases significantly, as a result of considering
that it will be still operative in case of failure of the hydraulic system. It is important to remark that
under these circumstances the guiding system performance will not be optimal and it should be
avoided to operate it regularly in these conditions. However, an emergency closing of the dome
shutters would be possible.

8.2 LOWER SHUTTER UPDATED NEW STATUS
Following the same criteria explained in the previous section (resulting from Actions 2 and 4), an
updated study of the Lower shutter system has been carried out.

The failure data for each component, used as input for the system analysis are shown as follows:


Table 8-4. Component failure rate and MTTR used in the Lower Shutter System Updated New Status analysis
MTBF
(hours)
MTBF
(years)
MTTR
(hours)
Availability
(%)
Bogie 2.48382E+05 59.14 167.88 99.93
Bogie System = Bogie 2.48382E+05 59.14 167.88 99.93
(Hydraulic)Bogie Group 1.84210E+07 4385.95 78.83 100.00
Guiding System 4.59510E+06 1094.07 85.80 100.00
Transmission 4.53367E+04 10.79 56.89 99.87
Upper Drive 3.68824E+04 8.78 21.21 99.94
Lower Drive 3.68601E+04 8.78 14.39 99.96
Drive System 4.50226E+04 10.72 56.28 99.88
Control System 4.13818E+04 9.85 7.32 99.98
System 2.15494E+04 5.13 31.11 99.86
Failure Rate
(per million
hours)

(1/hours)
Component
MTTF (hours)
Component
MTTF (years)
Component MTTR
(hours)
Wheels 1 0,000001 1,00E+06 238,10 168
Bearings 1 0,000001 1,00E+06 238,10 168
Hydraulic Actuator 15 0,000015 6,67E+04 15,87 48
Hydraulic System 10 0,00001 1,00E+05 23,81 168
VSD 5 0,000005 2,00E+05 47,62 4
Motor a.c. 5 0,000005 2,00E+05 47,62 36
Brake 10 0,00001 1,00E+05 23,81 12
Encoder 7 0,000007 1,43E+05 34,01 36
Gearbox (main) 5 0,000005 2,00E+05 47,62 72
Gearbox (auxiliary) 5 0,000005 2,00E+05 47,62 72
Chain 1 0,5 0,0000005 2,00E+06 476,19 24
Chain 2 0,5 0,0000005 2,00E+06 476,19 24
PLC 20 0,00002 5,00E+04 11,90 4
Rectifier 4 0,000004 2,50E+05 59,52 24
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
41/42



The whole GTC Dome Shutters lifetime (50 years) has been considered. Up to 10000 different
failure scenarios have been simulated (with different combination of components failure along the
time). For each component, a MTTR (mean time to repair) value has been considered.

The MTBF for each subsystem has been obtained, as well as the MTBF of the whole system.
Applying the formula explained in chapter 4.1, with the selected MTTR, the availability and MTTR
of every subsystem and the whole system have been obtained. These results are shown in the
following table:


Table 8-5. Lower Shutter System Updated New Status Reliability, Availability & MTTR analysis results.

Even though the operational time of most of the components of the guiding system, transmission
and driving system is around 1 hour/day, during this study the operational time per day has been
maintain in 12 hours/day as it should keep in mind that few subsystems such as the power source
of the control system has that operational period (Action 3).

Thus, in case of reading the MTBF of the guiding, transmission and driving system, it is most
convenient to use the hours values and from them generate the corresponding number is years.

Analogously, the system reliability in terms of unfeasibility to close the lower shutter system (Action
1) has been obtained. The results are collected in the next table.


Table 8-6. Lower Shutter System Updated New Status, in terms of failures that avoid closing the shutter. Reliability,
Availability & MTTR analysis results.
Similarly to the upper shutter, the reliability of the guiding system increases significantly, as a result
of considering that it will be still operative in case of failure of the hydraulic system. In this case the
MTBF
(hours)
MTBF
(years)
MTTR
(hours)
Availability
(%)
Bogie 2,48382E+05 59,14 167,88 99,93
Bogie System 5,26788E+04 12,54 73,09 99,86
Hydraulic Bogie Group2,07920E+07 4950,48 36,96 100,00
Guiding System 8,71346E+04 20,75 150,80 99,83
Drive 1,66339E+05 39,60 63,66 99,96
Drive System 8,37553E+04 19,94 63,66 99,92
Control System 4,13818E+04 9,85 7,32 99,98
System 2,09424E+04 4,99 56,29 99,73
MTBF
(hours)
MTBF
(years)
MTTR
(hours)
Availability
(%)
Bogie 2.48382E+05 59.14 167.88 99.93
Bogie System = Bogie 2.48382E+05 59.14 167.88 99.93
(Hydraulic)Bogie Group 3.00000E+08 71428.57 68.20 100.00
Guiding System 6.30622E+06 1501.48 84.64 100.00
Drive 1.66339E+05 39.60 63.66 99.96
Drive System 8.37553E+04 19.94 63.66 99.92
Control System 4.13818E+04 9.85 7.32 99.98
System 2.76513E+04 6.58 26.53 99.90
GTC Dome Shutters Upgrade Reliability Analysis



2015x1aa; 11/04/2014
42/42

guiding system performance will not be optimal and it should be avoided to operate it regularly in
these conditions. However, an emergency closing of the lower shutter would be possible.

Вам также может понравиться