Вы находитесь на странице: 1из 26

CONTENTS

SL. NO.
DESCRIPTION
01. COLD START - UP
02. INTEGRATED START UP PROCEDURE COLD START UP
03. HOT AND WARM START UPS.
04. INTEGRATED START UP PROCEDURE WARM START UP
05. INTEGRATED START UP PROCEDURE HOT START UP.
06. START UP BY CURVES FOR ABSOLUTE COLD START WITH HP/LP BYPASS
SYSTEM.
07. START UP CURVES AFTER 48 HOURS SHAT DOWN WITH HP/LP BYPASS
SYSTEM.
08. START UP PROCEDURE AFTER 8 HOURS SHUT DOWN WITH HP/LP BYPASS
SYSTEM.
09. TECHNICAL DATA LIMIT CURVES FOR TURBINE VALVES WALL OF THE
CASING SHAFTS.
10. WARMING UP AND STARTING THE TURBINE TEMPERATURE CRITERIA.
11. TECHNICAL DATA REACTIVE CAPACITY CURVE FOR TURBO GENERATORS.

COLD START UP
(With Aux Ste am available )
A cold start up is by definition, one of which the maximum of HP casing and HP shaft is less than 150
0
C. This
normally means that the unit is shut down from the maximum load for more than five days. If machine is
started from ambient temperature (HPC/HP shaft temp approx. 40
0
C), heating up of casting is required. This
is accomplished by soaking the machine at 360 rpm at warming up steam parameters (40kg/cm
2
, 360
0
C), till
the TSE margin are satisfactory.
The rifle construction of the water wall combined with the boiler circulating water pumps permits very
high rate of pressure rising of boiler. An upper limit of 200
0
C/hr saturation temperature gradient can be
allowed, i.e. approximately the boiler pressure can be brought to 20 kg/cm
2
within an hour of cold start up.
But actual temperature gradient is limited by the thick walled Y piece provided in the main steam and HRH
lines. A main steam line heating is to be started as early as possible (at approx. 4 kg/cm
2
) as maximum
differential temperature allowed between inner (98%) and mid wall temperature (50%) is 40
0
C. So boiler
loading is accordingly regulated. It may be preferably to start only two CC pumps in order to minimise flashing
in down comers (and subsequent vibration) when the boiler water is in range of 85
0
C to 125
0
C. The third
pump should be started before drum pressure reaches 7 kg/cm
2
to minimise the temperature transients
experienced by the pump casing (this is to avoid fast load out back on the boiler in the event of any CC pump
tripping).
To get the rolling parameters, normally two elevation oil guns are taken with approx. 70 to 80t/hr
flow through HP-LP bypass. At that time M.S. parameters would be 40 kg/cm
2
and 360
0
C, HRH parameters
would be 12 kg/cm
2
and 360
0
C.
As soon as the turbine loading has started, HP/LP bypass closes and gets completely closed as the turbine
reaches the boiler load. First mill is put into operation around 10% of generator load. Second mill is put into
operation around 25% while third mill is at 40% of generator load. Fourth and fifth mills are put into operation
at 60% and 80% of generator load respectively. Sixth mill is taken to reach full generator load.
During loading the RH outlet steam temperature has to be kept as close as possible to SH outlet steam
temperature Burner tilt, SH spray, RH spray controls has to be adjusted accordingly. The turbine-loading rate
is decided by a selection circuit which compares the external load gradient, TSE margin and time dependant
gradient (set internally) and frequency influence.
INTEGRATED START-UP PROCEDURE
COLD START-UP
(AUXILIARY STEAM AVAILABLE)
REF. DRG NO. 20 BPE 691
STEP TIME UNIT CONDITION OPERATION NOTES
0 ..
Boiler pr. 0 kg/cm
2
(g)
and Ambient temperature
Charge Aux. Steam header
16 ata, 260
0
C, from existing
units.
-
- - -
Charge steam to fuel oil
pump house, atomising steam
and tracing steam deaerator
warming up.
All the steam tracing lines
and electrical tracings in
pump house & boiler to be
charged.
- - -
Start tank heating of LSHS
oil.
-
- - -
Start one LSHS pump on
recirculation as soon as the
sufficient oil temperature at
inlet is achieved.
-
- - -
Charge LSHS to boiler front
and keep it on long
recirculation, with heaters
control set on Auto to
maintain 110-129
0
C.
-
- - -
Fill water in drum upto
+200mm.
Ensure that the suction and
discharge valves of all the CC
pumps are open and the
pump suction and discharge
lines are vented.
- - -
Start Bearing cooling water
system pumps for Boiler,
Turbine and TG auxiliaries .
Check all circuits have
sufficient flow. Before
starting the pumps, the
emergency cooling water
tank level to be checked and
made normal.
- - -
Start instrument air
compressor and check that
all the lines to Boiler and TG
are charged.
Check that all circuits have
sufficient air pressure.
- - -
Start service air compressor
and fill the air receiver tanks
of SRAPH & PRAPH are filled.
-
- - -
Ensure that purge air to HEA
is open in all corners.
-
- - -
Line up Air and flue gas
circuits for startup.
Check dampers and gates
register position.
- - - ESP ready in all respects. -
- - -
Furnace bottom ash system
and seal through lined up.
-
- - -
FSSS panel ready in all
respects.
-
- - -
EAST panel ready in all
respects.
-
- - -
Excitation panel ready in all
respects.
-
- - -
Generator protection panel
ready in all respects.
-
- - -
Generator H
2
gas pressure is
4 kg/cm
2
Check purity of H
2
gas is
normal.
- - -
Generator stator water
system ready in all respects.
Check purity of generator
stator water is normal.
- - -
H
2
cooling water system
ready in all respects with SLC
on.
-
- - -
LP & HP chemical dozing
system is ready.
Check for level in Hydrazine,
Ammonia and phosphate
preparation tanks.
- - - SADC panel readiness.
Check for air pressure in all
the corners and elevations.
- - -
Power supply for all the
valves and dampers are ON.
Ensure Aux. air dampers and
modulating.
- - -
Supply for all auxiliaries of
SG, Turbine and Generator is
ensured.
-
- - -
Readiness of HP bypass panel
in all respects.
Ensure the oil unit is running
and all the bypass and spray
valves are closed.
- - - Start one of the CC pumps.
Ensure drum level is +200
mm, and the drum air vents
are closed.
- - - Start the second CC pump. Ensure drum level is normal.
- - - Start scanner air fan. -
- - -
Start both the secondary air
preheaters.
Ensure that all the inlet and
outlet air gas dampers are
open.
- - -
Start both the primary air
preheaters.
Ensure that the gas dampers
are closed.
- - -
Start one set of ID and FD
fans.
Adjust 30% air flow, and
furnace draft minus 5 to 10
mm WCL.
- - -
Charge steam coil preheater
concerned with the running
FD fans.
-
- - -
Initiate Boiler Purge
(duration 5 minutes).
After purge completion Boiler
trip valves will get reset.
- - - -
Also, after purge, adjust the
wind box dampers to get 30-
40 mm WCL. Wind box dp.
- - Lub oil system stopped.
Start one vapour extraction
fan, keep other fan standby.
Check oil level in MOT.
- - -
Line up lub oil cooler and
thrust bearing filter Start one
AOP.
Put on SLCs for other AOP
and EOP.
- - - -
Check out auto start of AOP
and EOP.
- -- -
Put lub oil temperature
controller on.
-
- - - Start one JOP.
Put on SLCs for other JOP
and DC-JOP.
- -- - -
Check out auto start of JOP
and DC-JOP.
- - -
Put off SLCs JOP 1, 2 & 3.
Stop running JOP.
-
- - - Open gate valve gearing.
Switch on SLC gate valve
gearing.
- - -
Start one JOP and switch on
SLCs for JOPs.
-
- - - M/c. comes on barring.
MOT level 50 mm oil temp.
45
0
C JOP header pr. 140
kg/cm
2
speed 80 100 rpm.
- - -
The sequential operation
narrated above on Lub oil
system stopped is
achieved by SGC mode.
If the programme gets
interrupted, the step and
criteria to be checked and to
be fulfilled for the programme
to proceed further.
- - M/c on barring.
Start centrifuge with both
heaters
-
- -
FRF system in stopped
condition.
Check FRF tank level. +200 mm.
- - -
Line up FRF cooler and duplex
filters in 32-bar system start
one CEP. Check auto start of
standby CEP.
-
- - -
Establish control fluid supply
to various services.
FRF tank level O (normal).
- - - Start one VEF. -
- - -
Start one recirculation pump
and include one Filters earth
and ultra fine.
-
- - -
Switch on FRF heater and
keep SLC ON for temperature
control, and control fluid
pumps.
FRF temperature 55
0
C.
- - - Switch ON control fluid SGC. -
- - FRF system, SGC is on.
The sequential operation
narrated above in FRF
system stopped condition is
achieved by SGC-FRF system
on starting programme mode.
If the programme gets
interrupted the step and
criteria to be checked and
fulfilled for the programme to
proceed further.
01 oo
Boiler ready for light up
and Turbine on Turning
gear.
Start 4 burners in AB
elevation with LSHS.
Check that SH & RH vents
are open.
- - - - SH & RH drains are open.
- - - -
MSVs closed and drains
before MSV open.
- - -
Regulate oil pressure to 8-10
kg/cm
2
.
Ensure atomising steam
pressure about 6 kg/cm
2
.
- - -
After 30 minutes, take
additional burners, so as to
ensure a drum metal
temperature raise of about
2
0
C/min.
Insert furnace probe and
ensure that the temperature
is below 535
0
C.
- - - -
Check drum level and give
blow down.
- - - -
Keep open the Eco.
recirculation valve when
there is no feeding to drum.
- - - Start motor driven feed pump
on recirculation.
Check deaerator level.
- - -
Charge the feed line upto
feed control station.
-
- - -
Charge heating steam to
deaerator from Aux. PRDS.
-
- - -
Start condensate pumps and
feed to deaerator as and
when required.
Check hotwell level.
-- - -
Start hotwell make up pumps
and feed hotwell as and
when required.
-
- - -
Aux. PRDS steam 15kg/cm
2
(g) 260
0
C
-
- - - CW system is charged. -
- - -
CW boxes to ensure
ventilating of water boxes.
-
- - -
Start one gland steam
exhauster fan.
-
- - -
Line up vacuum pumps and
start one by one Gradually
admit gland steam when
condenser vacuum reaches
0.2kg/cm
2
(g).
Ensure gland steam admission
temperature is always above
200
0
C.
- - -
Vacuum building can be done
through SGC vacuum on
starting programme mode,
gland steam exhauster has to
be started manually.
-
- -
Vacuum 0-9kg/cm
2
(g).
Open all drains connected to
flash tanks and flash boxes
connected to condenser.
-
-- - - Open HPBP warm up valves. -
- - - Switch on SLC drains. -
02 60'
Boiler pressure 2kg /cm
2
Close SH & RH header vents. -
- - -
Close SH & RH header drains.
-
- - - Open MSV by pass lines.
MS, HRH, & CRH lines will get
warmed up.
03 100
Boiler pressure 5kg /cm
2
.
Switch on automatic control
interface of LP bypass.
As soon as the fixed set
point reaches 12 kg/cm
2
, it
seizes.
- - - Open Main steam valves.
Automatic control interface
gets switched off when the
hot reheat steam pressure
reaches 13kg/cm
2
i.e. after
synchronisation.
- - - Open HP by pass. -
- - -
Start third C.C. pump when
boiler pressure reaches 9
kg/cm
2
.
-
- - -
Take additional guns in CD &
EF elevation.
Air heater soot blowing to be
carried out.
- - - Close HPBP warm up valves. -
A ROLLING THROUGH HYDRAULIC GOVERNOR
04 150
Boiler pressure:15 kg/cm
2
Temperature:180-200
0
C
HRH Pressure:8-12Kg/cm
2
Open HPESVs & IPESVs for
warming up by operating
starting device to
approximately 42%.
Check and ensure that speed
set point is zero and speeder
gear is 0% position.
- - - -
Ensure TSE influence is
switched on and available
margins are greater than =
30
0
K.
05 -300
M. S. Pr. 50 kg/cm
2
M.S. temp. 350
0
C
H. R. H. Pr. 12 kg/cm
2
HRH temp. : 350
0
C
Raise the speed set point of
EHC to 3200 rpm
If the oil system of EHC is
isolated at speed Gov. rack,
speed set point need not be
raised.
- - -
Gradually raise the starting
device to bring the speed to
360 rpm
Starting device position
approximately 56%.
- - Turbine ready for Rolling.
Hold the speed at 360 rpm
for about 35 to 40 mts.
Ensure closure of gate valve
gearing at 240 rpm. Monitor
bearing vibrations, shaft
vibrations, TSE margins,
bearing temperature &
Turbosupervisory readings at
360 rpm.
06 -360
M. S. Pr. 50
kg/cm
2
/350
0
C. Turbine
running at 360 rpm.
Raise the speed upto 2400
rpm through starting device
at the rate of 600 rpm.
Ensure tripping of JOP at 540
rpm.
- -
Raise further speed upto
3000 rpm through speeder
gear.
Starting device will be at
90%.
- - - -
Monitoring bearing
temperature and vibrations,
shaft vibrations, TSE margins
and Turbovisory readings,
Seal oil, Primary water and
gas temperatures &
Generator winding
temperature.
- - - -
Ensure trippinf of AOP at
2950 rpm.
- - - -
Speeder gear position will be
approximately at 50 to 60%.
07 370
MS Pr. 50 kg/cm
2
.
Temperature: 350
0
C
Turbine running at 3000
rpm.
Put AVR on Auto. -
- - - Close field breaker. -
- - -
Set manually the generator
voltage to grid voltage.
-
- - -
Synchronise the generator
with grid.
Pick up 50 MW load by
operating speeder gear.
-
- - - Increase HPBP set point.
Ensure closure of HPBP steam
valves & spray valves.
- - -
Close other drains, M.S. HRH,
keeping SLC drains on.
Drain pot drains of MS, CRH &
HRH and extraction steam
lines will operate as per the
actuation of level switches.
B - ROLLING THROUGH EHC.
04 150'
MS Pr.: 15 kg/cm
2
.
Temperature:180-200
0
C
HRH
Pressure:8to12kg/cm
2
.
Open HPESVs & IPESVs for
warming up by operating
starting device to
approximately 42%.
Check and ensure that TSE
influences is switched on and
available margins are greater
than 30
0
K.
- - - -
Check and ensure that speed
set point is zero and speeder
gear is 0% position.
05 300'
MS Pressure: 50 kg/cm
2
MS Temperature:350
0
C
HRH Pressure: 12kg/cm
2
HRH Temperature: 350
0
C.
Turbine Ready for rolling
Raise the starting device to
about 70%.
Check and ensure opening of
valves in HP/IP secondary
fluid lines to EHC at speed
control rack.
- - -
Raise the speed set point to
360 rpm and watch the
actual speed.
If tracking device is switched
ON, starting device position
will automatically track the
EHC position
- - -
Raise the speeder gear to
100%
- - -
Hold the speed at 360 rpm
for about 35 to 40 mts.
Ensure closure of gate valve
gearing at 240 rpm.
- - - -
Monitoring bearing vibrations,
bearing temperatures, shaft
vibrations, TSE margins and
Turbovisory readings.
06 360'
MS Pressure:50 kg/cm
2
MS Temperature:350
0
C
Raise the speed set point to
3000 rpm.
Ensure tripping of jacking oil
pump at 540 rpm.
- - Turbine speed: 360 rpm. -
The rate of acceleration will
be 600 to 850 rpm.
- - - -
Monitor bearing vibration and
temperatures, shaft
vibrations, Turbovisory
readings and TSE margins
- - - -
Monitor and control, SEAL oil
temperatures, Primary water
temp. Hydrogen gas
temperature and winding
temperature.
- - - -
Ensure tripping of AOP at
2950 rpm.
07 370'
MS Pressure: 50 kg/cm
2
MS Temperature: 350
0
C
Turbine speed: 3000 rpm.
Put AVR on auto, Close Field
Breaker.
-
Set manually generator
- - - voltage to grid voltage. -
- - -
Synchronise the generator
with grid.
Speed set point will raise
automatically by 8 rpm and
load will be picked upto
20MW.
- - -
Raise the speed set point
and pick up the load to 50
MW.
-
- - - Increase HPBP set point.
Ensure closure of HPBP steam
valves & spray valves.
- - -
Close other drains of MS,
CRH, HRH, keeping SLC drains
'ON'.
Drain pot drains of MS, CRH,
HRH and extraction steam
lines will operate as per the
actuation of level switches.
C - ROLLING THROUGH SGC - TURBINE.
04 150'
MS Pressure: 15 kg/cm
2
MS Temp.:180-200
0
C
HRH Pressure: 12 kg/cm
2
Switch on the start up
programme of SGC Turbine.
Ensure TSE influence is
switched on.


- - - -
If the programme interrupts
the particular step and
criteria to be checked and
corrected for the programme
to proceed further.
- - - -
All operations as explained
under EHC rolling will be
carried out by SHC Turbine
programme sequentially.
05 300'
MS Pressure: 50 kg/cm
2
MS Temperature: 350
0
C
HRH Pressure: 12 kg/cm
2
HRH Temp.: 350
0
C.
Turbine Ready for rolling
Turbine speed will be raised
to 360 rpm through SGC
Programme.
Ensure closure of gate valve
gearing at 240 rpm.
- - - -
Monitor bearing vibration,
bearing temperature, shaft
vibration, TSE margins and
Turbovisory readings.
- - - -
To achieve the programme as
per the starting curve, the
main steam temperature
should be maintained steadily
till loading upto 50 MW.
06 360'
MS Pressure: 50 kg/cm
2
MS Temperature: 350
0
C
Turbine running at 360
rpm.
Turbine speed will be raised
upto 3000rpm through SGC-
programme.
Ensure tripping of JOP at 540
rpm.
- - - -
Ensure tripping of AOP at
2950 rpm.
Monitor bearing temp and
vibrations, shaft vibrations,
TSE margins and turbovisory
- - - - readings seal oil, primary
water, Hydrogen gas and
Generator winding
temperatures.
07 370'
MS Pressure: 50 kg/cm
2
MS Temperature: 350
0
C
Turbine speed:3000rpm.
SGC programme will switch
ON field breaker, put AVR on
auto, synchronise and pick
up load upto 20 MW.
Ensure SGC start up
programme is completed.
- - -
Raise the speed set point
and pick up the load upto 50
MW.
- - - Increase HPBP set point.
Ensure closure of HPBP steam
valves and spray valves.
- - -
Close other drains of M.S.
CRH and HRH, keeping SLC
drains ON.
Drain pot drains of MS, CRH,
HRH extraction steam lines
will operate as per the
actuation of level switches.
08 390'
Load : 55 MW
M.S. : 54kg/cm
2
/350
0
C
HRH : 12 kg/cm
2
/340
0
C
Start seal air fan and PA fan
and take first mill in service.
Before starting P.A. fan,
ensure that air and gas
dampers of Primary Air
Preheaters are open.
- - - Charge ESP fields
Ensure Ash handling system
is ready.
- - -
Start the second set of ID &
FD fans.
Make ready SH & RH spray
systems.
- - - Cut in L.P. heaters 2 & 3.
Ensure switching on of load
controller above 60MW.
- - -
Cut out heating steam from
Aux. P.R.D.S. to Deaerator.
-
- - -
Peg Deaerator from CRH
steam gradually upto 2
kg/cm
2
.
-
- - - Cut in auto controllers. -
- -
Load : 55 MW
M.S. : 54kg/cm
2
/350
0
C
HRH : 12 kg/cm
2
/340
0
C
Charge Aux. PRDS station
from CRH. Cut in spray and
maintain a temperature of
250
0
C.
Ensure energizing of solenoid
in trimming device at and
above 100 MW load.
- - -
Peg Deaerator gradually to 4
kg/cm
2
.
Raise the pressure set point
of Deaerator pressure
controller gradually.
- - -
Cut in IInd mill and cut in
auto controllers.
-
- - -
Start withdrawing oil support
gradually.
Ensure fire ball scanner
healthiness
- - -
Control main steam and
reheat steam temperatures
by using spray if required.
-
10 440'
Load : 160 MW
M.S. : 90kg/cm
2
/380
0
C
HRH : 20 kg/cm
2
/380
0
C
Steam flow : 580t/hr.
Increase the wind box to
furnace differential pressure
to 100mm W.C. by adjusting
SADC.
-
- - - Charge H.P. heaters 5A, 5B,
6A and 6B.
-
- - - Put controllers on auto. -
- - -
Start first TDBFP & second
CEP.
-
- - -
Charge Deareator pegging
steam flow CRH to Extraction
around 200 MW load.
Ensure Deareator Pressure
controller remains as auto.
11 480'
Load : 250 MW
M.S. : 120kg/cm
2
/420
0
C
HRH : 26 kg/cm
2
/340
0
C
Steam flow : 820t/hr.
Cut in IIIrd mill and cut in
auto controllers.
-
- - - Start second P.A. Fan.
Before starting P.A. fan
ensure that air and gas
dampers of PAPHs are open.
12 510'
Load : 320 MW
M.S. : 125kg/cm
2
/350
0
C
HRH : 28-30
kg/cm
2
/340
0
C
Steam flow : 1040t/hr.
Cut in IVth mill and cut in
auto controllers.
-
- - - Cut of oil support completely.
Ensure healthiness of fire ball
scanners.
13 550'
Load : 405 MW
M.S. : 145kg/cm
2
/460
0
C
HRH : 33 kg/cm
2
/460
0
C
Steam flow : 1310 t/hr.
Cut in Vth mill and cut in
auto controllers.
-
- - -
Cut in second TD BFP and
switch off motor driven BFP.
-
14 590'
Load : 500 MW
M.S. : 170 kg/cm
2
/475
0
C
HRH : 40.5 kg/cm
2
/475
0
C
If full load is not reached cut
in VIth mill along with its
controllers. Increase the set
point of SH & RH spray
controllers such that rated
parametes are achieved
gradually.
-
15 670'
Load : 405 MW
M.S. : 145kg/cm
2
/460
0
C
HRH : 33 kg/cm
2
/460
0
C
Steam flow : 1310 t/hr.
- -

WARM AND HOT START UPS
(With Aux. Steam Available).
A warm start up is, by definition, one which the maximum of HP casing/HP shaft temperature is
between 150
0
C and 350
0
C. This normally means that the unit is shut down from the maximum load for one to
four days. Depending upon the absolute temperature of HP casing and HP shaft, steam parameters are
derived. A hot start up is by definition one which the maximum of HP casing/shaft temperature is more than
350
0
C. In this case to get the rolling parameters two mills are taken into service keeping HP, LP by pass in
operation. (Again the flow rate is restricted by the Y pieces constraints i.e., 40
0
C). In both the cases,
curves are given to derive the rolling parameters. In case when machine is rolled through EAST, curve
generators, calculate and give permissive for rolling.

INTEGRATED START-UP PROCEDURE
WARM START UP (AFTER 48 HOURS SHUT DOWN).
STEP
TIME IN
MINUTES
UNIT CONDITION OPERATION NOTES.
- -
One CC pump in operation
and scanner fan in
operation.
Motor operated BFP is run
as and when required to
maintain the drum level.
-
- -
Both SAPHs and PAPHs in
operation.
- -
- -
Turbine on bearing gear
with AOP, JOP and seal oil
pumps in operation.
- -
- -
Control fluid system ready
in all respects. One
circulating pump in
operation with one earth
filter and ultra fine filter in
circuit.
- -
- -
Generator gas system, seal
oil system and primary
water system in operation.
- -
- -
Bearing cooling water
system in operation.
- -
- -
HT and LT auxiliaries power
supply available.
- -
- -
HP bypass system ready in
all respects.
- -
- - ESP ready in all respects. - -
- -
EAST panels ready in all
respects.
- -
- -
Furnace bottom ash
system and seal trough
lined up.
- -
- -
Vacuum pumps lined up and
ready for operation.
- -
- -
Gland steam and leak
steam controllers are lined
up and ready for operation.
- -
- -
Generator protection panel
and exciter panels ready in
all respects.
- -
- -
Boiler drum pressure = 0
kg/cm
2
. SH
temperature between
130
0
C and 150
0
C.
1. Charge auxiliary steam
header from existing units.
Pr. 16ata temp. 260
0
C.
-
- - -
2. Charge steam to fuel oil
pump house, atomising
steam and tracing steam.
-
- - -
3. Start tank heating of
LSHS oil.
-
- - -
4. Start one LSHS pump on
recirculation as soon as
sufficient oil temp. at inlet is
achieved.
-
- - -
Start instrument oil
compressor and service air
compressors and check that
all lines to boiler and TG are
charged.
-
- - -
Charge LSHS pump to boiler
front and keep it on long
recirculation with heaters
control set on auto to
maintain 120
0
C.
-
- - -
Start circulating water pump
for condenser and deaerate
the condenser water boxes.
-
- - - Start second CC Pump.
Ensure running of motor
driven BFP continuously for
maintaining drum level.
- - -
Start one set of ID and FD
fans.
-
- - - Initiate boiler purge. -
- - -
Start one CEP and keep the
hot well make up in service.
-
- - -
Start one of the control fluid
pumps and keep the second
as auto standby.
-
- - -
Keep the control fluid
temperature control on
auto.
-
- - -
Line up main steam, CRH
and HRH steam lines for
charging by opening
respective line drains.
-
- - -
Line up FSSS panels in all
respects
-
- - -
Charge heating steam line to
Deaerator from Aux. PRDS.
-
01 oo
Boiler ready for light up and
turbine on turning gear.
Start 4 burners in AB
elevation with LSHS.
Check that SH & RH vents
are open.
- - - - SH & RH drains are open.
- - - -
MSVs closed and drains
before MSV open.
- - - -
Ensure atomising steam
pressure of about 6 kg/cm
2
- - - -
Ensure motor operated BFP
is in service.
- - -
Start Gland steam
Exhauster.
-
- - -
Start one by one vacuum
pumps.
-
Admit gland steam when Ensure gland steam
- - - vacuum reaches 0.2
kg/cm
2
.
admission temperature is
always above 200
0
C.
- - -
Vacuum building can be
done through SGC vacuum
on starting programme
mode. Gland steam
exhauster has to be started
manually.
-
- - -
Open all drains connected to
flash tanks and flash boxes
connected to condenser.
Ensure condenser vacuum
of 0.8 kg/cm
2
.
- - - Switch on SLC drains. -
- - -
Close SH & RH header vents
and drains.
Ensure boiler pressure is
2kg/cm
2
.
- - -
Open HPBP warming up
valves.
-
- - - Open MSV bypass lines. -
- - -
Switch Automatic control
interface of LP bypass.
As soon as the fixed set
point reaches 12kg/cm
2
, it
seizes.
- - - -
Automatic control interface
gets switched off when the
hot reheat steam pressure
reaches 13kg/cm
2
(i.e.)
after synchronisation.
- - -
Open Main steam stop
valves.
Ensure MS, CRH & HRH
lines get warmed up.
- - -
Open HP bypass and close
the HPBP warm up valves.
Ensure Boiler pressure is
5kg/cm
2
.
- - - Start third CC pump.
Ensure Boiler pressure is
9kg/cm
2
.
- - -
Put HP bypass controller on
auto and vary the set point
according to the gradient of
pipeline temperatures.
Ensure Boiler pressure is
10kg/cm
2
- - -
Put HP bypass spray control
on auto.
-
- - -
Take additional guns
according to the
requirement.
Air heater soot blowing to
be carried out.
A ROLLING THROUGH HYDRAULIC GOVERNOR.
02 180'
MS: 50 kg/cm
2
/365
0
C
HRH: 12 kg/cm
2
/325
0
C
By pass steam flow:
170t/hr.
Open HPESV and IPESV for
warming up by operating
starting device to approx.
42%
Check and ensure that
speed set point is zero and
speeder gear is 0%.
- - - -
Ensure TSE influence is
switched on and available
margins are greater than
30
0
K.
03 210'
MS: 60 kg/cm
2
/400
0
C
HRH: 12 kg/cm
2
/350
0
C
By pass steam flow:
200t/hr.
Raise the speed set point of
EHC to 3200 rpm.
If the oil system of EHC is
isolated at speed Gov.
rack, speed set point need
not be raised.
Gradually rise the starting
- - - device to bring the speed to
360 rpm.
Starting device position
approximately 56%.
- - -
Hold the speed at 360 rpm
for about 5 minutes.
Ensure closure of gate
valve gearing at 240 rpm.
- - - -
Monitor bearing vibrations,
shaft vibrations, TDE
margins, bearing temp. &
Turbovisory readings at
360rpm.
04 215' Turbine running at 360 rpm.
Raise the speed upto 2400
rpm through starting device
at the rate of 600 rpm.
Ensure tripping of JOP at
540 rpm.
- - -
Raise further speed upto
3000 rpm through speeder
gear.
Starting device will be at
90%.
- - - -
Monitor bearing temp &
vibrations, shaft vibrations,
TSE margins and
Turbovisory readings. Seal
oil, Primary water and gas
temperatures & Generator
winding temperature.
- - - -
Ensure tripping of AOP at
2950 rpm.
- - - -
Speeder gear position will
be approx. at 50 to 60 %.
05 220'
Turbine running at 3000
rpm
Put AVR on auto. -
- - - Close field breaker. -
- - -
Set manually the generator
voltage to grid voltage.
-
- - -
Synchronise the generator
with grid. Pick up 50 MW
load by operating speeder
gear.
-
- - - Increase HPBP set point.
Ensure closure of HPBP
steam valves & spray
valves.
- - -
Close other drains, M.S.
HRH, keeping SLC drains on.
Drain pot drains of MS,
CRH, and HRH and
extraction steam lines will
operate as per the
actuation of level
switches.
- - - -
Further load raising will be
done by operating the
speeder gear according to
the start up curve.
B ROLLING THROUGH EHC
02 180'
MS: 50 kg/cm
2
/365
0
C
HRH: 12 kg/cm
2
/325
0
C
By pass steam flow:
170t/hr.
Open HPESVs and IPESVs
for warming up by operating
starting device to approx.
42%.
Check and ensure that TSE
influence is switched on
and available margins are
greater than 30
0
K.
- - - -
Check and ensure that
speed set point is zero and
speeder gear is 0%.
MS: 60 kg/cm
2
/400
0
C
03 210'
HRH: 12 kg/cm
2
/350
0
C
By pass steam flow:
200t/hr.
Turbine ready for rolling.
Raise the starting device to
about 70%.
Check and ensure opening
of valves in HP/IP
secondary fluid lines to
EHC at speed control rack.
- - -
Raise the speed set point to
360 rpm and watch the
actual speed.
If tracking device is
switched on starting
device position will
automatically track the
EHC position
- - -
Raise the speeder gear to
100%.
Ensure closure of gate
valve gearing at 240 rpm.
- - -
Hold the speed at 360 rpm
for about 5 minutes.
Monitor bearing vibrations
bearing temperatures,
shaft vibrations, TSE
margins & turbovisory
readings.
04 215' Turbine running at 360rpm.
Raise the speed set point to
3000 rpm.
Ensure tripping of Jacking
oil pump at 340 rpm.
- - - -
Monitor bearing vibrations
and temps, shaft vibration,
turbovisory readings and
TSE margins.
- - - -
Ensure tripping of AOP at
2950 rpm.
05 225' Turbine speed: 3000 rpm.
Put AVR on auto close Field
breaker.
-
- - -
Set manually generator
voltage to grid voltage.
-
- - -
Synchronise the generator
with grid.
Speed set point will be
raise automatically by
about 8 rpm & load will be
picked upto 20 MW.
- - -
Raise the speed set point
and pick up the load to 50
MW.
-
- - - Increase HPBP set points.
Ensure closure of HPBP
steam valves and spray
valves.
- - -
Close other drains of MS,
CRH, and HRH keeping SLC
drains ON.
Drain pot drains of MS,
CRH, HRH and extraction
steam lines will operate as
per the actuation of level
switches.
C ROLLING THROUGH SGC TURBINE.
02 180'
MS: 50 kg/cm
2
/365
0
C
HRH: 12 kg/cm
2
/325
0
C
By pass steam flow:
170t/hr.
Switch on the start up
programme of SGC
Turbine.
Ensure TSE influence is
switched on.
- - - -
If the programme interrupts
the particular step and
criteria to be checked and
corrected for the
programme to proceed
further.
- - - -
All operations as explained
under EHC rolling will be
carried out by SGC
Turbine programme
sequentially.
03 210'
MS: 50 kg/cm
2
/365
0
C
HRH: 12 kg/cm
2
/325
0
C
By pass steam flow:
170t/hr.
Turbine ready for rolling.

Turbine speed will be raised
to 360 rpm through SGC-
Programme.
Ensure closure of gate
valve gearing at 240 rpm.
- - - -
Monitor bearing vibration,
bearing temp, shaft
vibration, TSE margins and
Turbovisory readings.
- - - -
To achieve the programme
as per the starting curve,
the main steam
temperature should be
maintained steadily till
loading upto 50 MW.
04 215'
MS: 60 kg/cm
2
/400
0
C
Turbine running at 360 rpm.

Turbine speed will be raised
upto 3000 rpm through SGC
Programme.
Ensure tripping of JOP at
540 rpm. Ensure tripping
of A.O.P. at 2950 rpm.
- - - -
Monitor bearing temp &
vibrations, shaft vibrations,
TSE margin and turbovisory
readings, seal oil, primary
water, Hydrogen gas and
Generator winding
temperatures.
05 225'
MS: 60 kg/cm
2
/400
0
C
Turbine speed: 3000 rpm.

SGC programme will switch
ON field breaker, put AVR on
auto, synchronise and pick
up load upto 20 MW.
Ensure SGC Start up
programme is completed.
- - -
Raise the speed set point
and pick up load upto 50
MW.
-
- - - Increase HPBP set point
Ensure closure of HPBP
steam valves and spray
valves.
- - -
Close other drains of M.S.,
CRH and HRH, keeping SLC
drains ON.
Drain pot drains of M.S.,
CRH, HRH and Extraction
steam lines will operate as
per the actuator of level
switches.
06 230'
Load: 60 MW
MS: 60 kg/cm
2
/410
0
C
HRH: 14 kg/cm
2
/360
0
C
Cut in L.P. heaters 2 and 3.
Ensure switching on of load
controller at 60 MW.
- - -
Cut out heating steam from
Aux. PRDS to Deaerator.
-
- - -
Peg Deaerator from CRH
steam gradually upto 2
kg/cm
2
.
-
- - - Cut in all auto controllers. -
- - -
Start seal air fan and P.A.
fan
Before starting P.A. fan,
ensure that air and gas
dampers of Primary Air
Preheaters are open.
- - -
Cut in further oil guns for
raising parameters.
-
07 245'
Load: 110 MW
MS: 80 kg/cm
2
/420
0
C
HRH: 19 kg/cm
2
/380
0
C
Main steam flow: 470t/hr.
Trimming device is in OFF.
Cut in 1st coal mill and cut
in Auto controllers.
Make ready SH & RH spray
system.
- - - Charge ESP Fields.
Ensure Ash handling
system is ready.
- - -
Charge Aux. PRDS station
from CRH. Cut in spray and
maintain a temperature of
250
0
C.
-
- - -
Peg Deaerator gradually
upto 4 kg/cm
2
.
Raise the pressure set
point of Deaerator pressure
controller gradually
- - -
Cut in H.P. heaters and put
the level controls on auto.
-
- - -
Start first TD BFP and
second CEP around a load of
170 MW.
-
- - -
Increase the windbox to
furnace diff. pressure to
100mm. W.C. by adjusting
SADC.
-
08 270'
Load: 200 MW
MS: 100 kg/cm
2
/435
0
C
HRH: 19 kg/cm
2
/400
0
C
Main steam flow: 750t/hr.
Cut in IInd mill and cut in
auto controllers.
-
- - -
Start withdrawing oil
support gradually.
Ensure healthiness of fire
ball scanners.
- - -
Control main steam and
reheat steam temperature
by using spray if required.
-
- - -
Change Deaerator pegging
steam from CRH to
Extraction steam.
Ensure Deaerator pressure
controller remains on auto.
- - -
Cut in IIIrd mill and cut in
auto controllers.
-
- - - Start second P.A. fan.
Before starting P.A. fan
ensure that air and gas
dampers of PAPH are open.
09 300'
Load: 320 MW
MS: 125 kg/cm
2
/450
0
C
HRH: 30 kg/cm
2
/430
0
C
Cut in IVth mill and cut in
auto controllers.
-
Main steam flow: 1080t/hr.
- - -
Cut off oil support
completely.
Ensure healthiness of fire
ball scanners.
- - -
Cut in Vth coal mill and cut
in auto controllers.
-
- - -
Start second TDBFP and
switch off motor driven BFP.
-
- - -
Cut in VIth coal mill and cut
in auto controllers.
-
10 340'
Load: 500 MW
MS: 170 kg/cm
2
/480
0
C
HRH: 40.5 kg/cm
2
/480
0
C
Main steam flow: 1620t/hr.
Check all parameters at full
load and ensure them within
limits.
-
- - -
Increase the set point of SH
& RH spray controllers such
that rated parameters are
achieved.
-
11 420'
Load: 500 MW
MS: 170 kg/cm
2
/535
0
C
HRH: 40.5 kg/cm
2
/535
0
C
Main steam flow: 1570t/hr.
- -

INTEGRATED START UP PROCEDURE
HOT START UP (AFTER 8 HOURS SHUT DOWN)
STEP
TIME IN
MINUTES.
UNIT CONDITION OPERATION NOTES.
- -
Two CC pumps in operation
and scanner fan in
operation.
Motor operated BFP is run
as and when required to
maintain the drum level. If
necessary BFP should be
kept running continuously.
-
- -
Both SAPHs and PAPHs in
operation.
- -
- -
Turbine on barring gear
with AOP, JOP and seal oil
pumps in operation.
- -
- -
Control fluid pump in
operation. One circulating
pump in operation with one
earth filter and ultra fine
filter in circuit.
- -
- -
Generator gas system, seal
oil system and primary
water system in operation.
- -
- -
Bearing cooling water
system in operation.
- -
- -
Condenser circulating
- -
water system in operation.
- -
Service air and instrument
air compressors in
operation.
- -
- -
One condensate pump in
operation and hot well
make up in service.
- -
- -
Aux. steam header charged
from existing units (16ata
260
0
C).
- -
- -
LSHS pump in operation on
long recirculation upto
boiler front with heaters
control set on
- -
- -
HP bypass system ready in
all respects.
- -
- -
LP & HP and chemical
dosing system ready.
- -
- -
ESP panels ready in all
respects.
- -
- -
EAST panels ready in all
respects.
- -
- -
Furnace bottom ash
system and seal trough
lined up.
- -
- -
Vacuum pumps lined up and
ready for operation.
- -
- -
Gland steam and leak
steam controllers are lined
up and ready for operation.
- -
- -
Generator protection panel
and exciter panels ready in
all respects.
- -
- -
FSSS panel ready in all
respects.
- -
- -
Boiler drum Pr. 75 kg/cm
2
SH. Temp. between 415
0
C
and 430
0
C.
Line up main steam, CRH
and HRH steam lines for
charging by opening
respective line drains.
Ensure MSV is closed.
- - -
Start one gland steam
exhauster.
-
- - -
Start one by one vacuum
pumps.
-
- - -
Admit gland steam when
vacuum reaches 0.2
kg/cm
2
.
Ensure gland steam
admission temperature is
always above 200
0
C.
- - -
Vacuum building can be
done through SGC vacuum
on starting programme
mode. Gland steam
exhauster has to be started
manually.
-
- - -
Open all drains connected to
flash tanks and flash boxes
connected to condenser.
Ensure condenser vacuum
of 0.8 kg/cm
2
.
- - -
Ensure condenser vacuum of
0.8 kg/cm
2
.
-
- - -
Open HPBP warming up
valves.
-
- - -
Switch Automatic control
interface of LP bypass.
As soon as the fixed set
point reaches 12 kg/cm
2
, it
seizes.
- - - -
Automatic control interface
gets switched off when the
hot reheat steam pressure
reaches 13 kg/cm
2
(i.e.)
after synchronisation.
- - - Start third CC pump.
Ensure differential temp. is
within permissible limits.
- - - -
Ensure running of motor
driven BFP continuously for
maintaining drum level.
- - - Start both ID & FD fans -
- - - Initiate boiler purge. -
- - -
Charge heating steam line to
Deaerator from Aux. PRDS.
-
01 oo
Boiler ready for light up and
turbine on turning gear.
Start 4 burners in AB
elevation with LSHS.
Ensure atomising steam
pressure of about 6kg/cm
2
.
Drum Pr. 75 kg/cm
2

SH. Temp. 415
0
C and
430
0
C.
-
Ensure motor operated BFP
is in service.
- - - Open drains before MSV. -
- - - Open MSV by pass lines. -
- - -
Open Main steam stop
valves.
Ensure MS, CRH, HRH lines
got warmed up.
- - -
Open HP bypass and close
the HPBP warm up valves.
-
- - -
Put HP bypass controllers on
auto and vary the set point
according to the gradient of
pipeline temperatures.
-
- - -
Put HP bypass spray control
on auto.
-
- - -
Take additional guns
according to the
requirement.
Air heater soot blowing to
be carried out.
- - -
Start both P.A. fans and
seal air fans.
Before starting P.A. Fans
ensure that air and gas
dampers of Primary air
preheaters are open.
- - -
Line up milling system for
starting.
-
A ROLLING THROUGH HYDRAULIC GOVERNOR
02 40'
MS: 85 kg/cm
2
/485
0
C
HRH: 12 kg/cm
2
/440
0
C
Bypass steam flow:
280t/hr.
Cut in first coal mill & cut in
auto controllers.
Make ready SH and RH
spray system.
- - - Charge ESP fields.
Ensure Ash handling
system is ready.
- - -
Increase the windbox to
furnace diff. Pressure to
100mm W.C. by adjusting
S.A.D.C.
-
Cut in second mill and cut in
- - - auto controllers. -
- - -
Peg the deaerator from CRH
gradually upto 2 kg/cm
2
.
-
- - -
Open HPESVs and IPESVs
for warming up by operating
starting device to
approximately 42%.
Check and ensure that
speed set point is zero and
speeder gear is at 0%.
- - - -
Ensure TSE influence is
switched on and available
margins are greater than
30
0
K.
03 50'
MS Pressure: 85 kg/cm
2
MS Temperature: 500
0
C
HRH Pressure: 12 kg/cm
2
HRH Temperature: 450
0
C.
Bypass steam flow:
360t/hr.
Turbine Ready for rolling
Raise the speed set point of
EHC to 3200 rpm.
If the oil of EHC is isolated
at speed Gov. rack, speed
set point need not be
raised.
- - -
Gradually raise the starting
device to bring the speed to
360 rpm
Starting device position
approximately 56%.
- - - -
Ensure closure of gate
valve gearing at 240 rpm.
- - - -
Monitoring bearing
vibrations, shaft vibrations,
TSE margins, bearing temp
& Turbovisory readings at
360 rpm.
04 52' Turbine running at 360rpm.
Raise speed upto 2400 rpm
through starting device at
the rate of 600 rpm.
Ensure tripping of JOP at
540 rpm.
- - -
Raise further speed upto
300 rpm through speeder
gear.
Starting device will be at
90%.
- - - -
Monitor bearing temp and
vibrations, shaft vibrations,
TSE margins and
turbovisory readings. Seal
oil Primary water and gas
temperatures and
Generator winding
temperature.
- - - -
Ensure tripping of AOP at
2950 rpm.
- - - -
Speeder gear position will
be approximately at 50 to
60%.
05 56' Turbine running at 3000rpm Put AVR on auto. -
- - - Close field breaker. -
- - -
Set manually the generator
voltage to grid voltage.
-
- - -
Synchronise the Generator
with grid. Pick up 50 MW
load by operating speeder
-
gear.
- - - Increase HPBP set point.
Ensure closure of HPBP
steam valves & spray
valves.
- - -
Close other drains, M.S.
CRH, HRH, keeping SLC
drains on.
Drain pot drains of MS,
CRH, and HRH and
extraction steam lines will
operate as per the
actuation of level
switches.
- - - -
Further load raising will be
done by operating the
speeder gear according to
the start up curve.
B ROLLING THROUGH EHC
02 40'
MS Pressure: 85 kg/cm
2
MS Temperature: 485
0
C
HRH Pressure: 12 kg/cm
2
HRH Temperature: 440
0
C.
Bypass steam flow:
280t/hr.
Cut in first coal mill & cut in
auto controllers.
Make ready SH & RH spray
systems.
- - - Charge ESP fields.
Ensure Ash handling
system is ready.
- - -
Increase the windbox to
furnace diff. Pressure to
100mm W.C. by adjusting
S.A.D.C.
-
- - -
Cut in second mill and cut in
auto controllers.
-
- - -
Peg the deareator from CRH
gradually upto 2 kg/cm
2
.
-
- - -
Open HPESVs and IPESVs
for warming up by operating
starting device to
approximately 42%.
Check and ensure that
speed set point is zero and
speeder gear is at 0%.
- - - -
Ensure TSE influence is
switched on and available
margins are greater than
30
0
K.
03 50'
MS Pressure: 85 kg/cm
2
MS Temperature: 500
0
C
HRH Pressure: 12 kg/cm
2
HRH Temperature: 450
0
C.
Turbine Ready for rolling.
Bypass steam flow:
360t/hr.
Raise the starting device to
about 70%.
Check and ensure opening
of valves in HP/IP
secondary fluid lines to
EHC at speed control rack.
- - -
Raise the speed set point to
360 rpm and watch the
actual speed.
If tracking device is
switched on starting
device position will
automatically track the
EHC position.
Raise the speeder gear to Ensure closure of gate
- - - 100%. valve gearing at 240 rpm.
- - -
Hold the speed at 360 rpm
for about 5 minutes.
Monitor bearing vibrations,
bearing temperatures,
shaft vibrations, TSE
margins and turbovisory
readings.
04 52' Turbine reading at 360 rpm.
Raise the speed set point to
300 rpm.
Ensure tripping of Jacking
oil pump at 540 rpm.
- - - -
The rate of acceleration
will be 600 to 800 rpm
2
.
- - - -
Monitor bearing vibrations
and temperatures, shaft
vibration, turbovisory
readings and TSE margins.
- - - -
Monitor and control, seal
oil temperatures, primary
water temperature.
Hydrogen gas temperature
and winding temperature.
- - - -
Ensure tripping of AOP at
2950 rpm.
05 56' Turbine speed: 3000 rpm.
Put AVR on auto Close field
breaker.
-
- - -
Set Manually generator
voltage to grid voltage.
-
- - -
Synchronise the generator
with grid.
Speed set point will be
raised automatically by
about 8 rpm and load will
be picked upto 20 MW.
- - -
Synchronise the generator
with grid.
-
- - - Increase HPBP set point.
Ensure closure of HPBP
steam valves and spray
valves.
- - -
Close other drains of MS.
CRH and HRH, keeping SLC
drains ON.
Drain pot drains of MS,
CRH, HRH and extraction
steam lines will operate as
per the actuation of level
switches.
C ROLLING THROUGH SGC TURBINE.
02 40'
MS: 85 kg/cm
2
/485
0
C
HRH: 12kg/cm
2
.
Bypass steam flow:
280t/hr.
Cut in first coal mill & cut in
auto controllers.
Make ready SH & RH spray
systems.
- - - Charge ESP fields.
Ensure Ash handling
system is ready.
- - -
Increase the windbox to
furnace diff. Pressure to
100mm W.C. by adjusting
S.A.D.C.
-
- - -
Cut in second mill and cut in
auto controllers.
-
- - -
Peg the deaerator from CRH
gradually upto 2 kg/cm
2
.
-
- - -
Switch on the start up
programme of SGC-Turbine.
Ensure TSE influence is
switched ON.
If the programme
- - - -
interrupts, the particular
step and criteria to be
checked and corrected for
the programme to proceed
further.
- - - -
All operations as explained
under EHC rolling will be
carried out by SGC-Turbine
programme sequentially.
03 50'
Turbine ready for rolling.
MS: 85 kg/cm
2
/500
0
C
HRH: 12kg/cm
2
/450
0
C
Bypass steam flow:
360t/hr.
Turbine speed will be raised
to 360 rpm through SGC-
programme.
Ensure closure of gate
valve gearing at 240 rpm.
- - - -
Monitor bearing vibration,
bearing temperature, shaft
vibration, TSE margins and
Turbovisory readings.
- - - -
To achieve the programme
as per the start up curve,
the main steam
temperature should be
maintained steadily till
loading of 50 MW.
04 52' Turbine reading at 360 rpm.
Turbine speed will be raised
upto 3000 rpm through SGC-
programme.
Ensure tripping of JOP at
540 rpm.
- - - -
Ensure tripping of AOP at
2950 rpm.
- - - -
Monitor bearing
temperature and
vibrations, shaft vibrations,
TSE margins, Turbovisory
readings, seal oil, primary
water, Hydrogen gas and
Generator winding
temperatures.
05 56'
Turbine speed: 3000 rpm.
MS: 85 kg/cm
2
/500
0
C
HRH: 12kg/cm
2
/450
0
C
Bypass steam flow:
360t/hr.
SGC Programme will switch
ON field breaker, put AVR on
auto synchronise and pick
up load upto 20 MW.
Ensure SGC-start up
programme is completed.
- - -
Raise the speed set point
and pick up load upto 50
MW.
-
- - - Increase HPBP set point.
Ensure closure of HPBP
steam valves & spray
valves.
- - -
Close other drains of M.S,
CRH and HRH, keeping SLC
drains ON.
Drain pot drains of MS,
CRH, HRH and Extraction
steam lines will operate as
per the actuation of level
switches.
06 60'
LOAD: 60 MW.
MS: 85 kg/cm
2
/500
0
C Cut in L.P. heaters 2 and 3.
Ensure switching on of load
controller at 60 MW.
HRH: 16kg/cm
2
/470
0
C
- - -
Cut out heating steam from
Aux. PRDS to Deaerator.
-
- - -
Raise the generator pressure
from 2kg/cm
2
to 4kg/cm
2
.
Raise the pressure set
point of Deaerator pressure
controller.
- - - Cut in auto controller. -
- - -
Start withdrawing oil
support gradually.
Ensure healthiness of fire
ball scanners.
07 65'
LOAD: 150 MW.
MS: 100 kg/cm
2
/500
0
C
HRH: 20kg/cm
2
/480
0
C
Main steam flow: 1620t/hr.
Trimming device is in OFF.
Charge Aux. PRDS station
from CRH. Cut in spray and
maintain a temperature of
250
0
C.
-
- - -
Cut in H.P. heaters and put
the level controls on auto.
-
- - -
Start first TD BFP and
second CEP around a load of
170 MW.
-
- - -
Control main steam and
reheat steam temperature
by using spray if required.
-
- - -
Change deaerator pegging
steam from CRH to
Extraction steam.
Ensure Deaeator pressure
controller remains on auto.
- - -
Cut in IIIrd mill and cut in
auto controllers.
-
08 70'
LOAD: 230 MW.
MS: 120 kg/cm
2
/500
0
C
HRH: 20kg/cm
2
/495
0
C
Main steam flow: 820t/hr.
Cut in IVth mill and cut in
auto controllers.
-
- - -
Cut off oil support
completely.
Ensure healthiness of fire
ball scanners.
- - -
Cut in Vth coal mill and cut
in auto controllers.
-
- - -
Start second TD BFP and
switch off motor driven BFP.
-
- - -
Cut in VIth coal mill and cut
in auto controllers.
-
09 86'
LOAD: 500 MW.
MS: 170 kg/cm
2
/500
0
C
HRH: 40.5kg/cm
2
/500
0
C
Main steam flow: 1620t/hr.
Check all parameters at full
load and ensure them within
limits.
-
- - -
Increase the set point of SH
& RH spray controllers such
that rated parameters are
achieved.
-
LOAD: 500 MW.
10 135'
MS: 170 kg/cm
2
/500
0
C
HRH: 40.5 kg/cm
2
/480
0
C
Main steam flow: 1570
t/hr.
- -

********************

Вам также может понравиться