Вы находитесь на странице: 1из 26

POWER FACTOR CONTROLLER

(PFC3) Part No: E000-21030.


(PFC3) Part No: E000-22090.
Installation and Adjustments Manual.









SAFETY PRECAUTIONS

Before operating the generating set, read the generating set
operation manual and this generator manual and become familiar
with it and the equipment.

SAFE AND EFFICIENT OPERATION CAN ONLY BE
ACHIEVED IF THE EQUIPMENT IS CORRECTLY
OPERATED AND MAINTAINED.

Many accidents occur because of failure to follow fundamental
rules and precautions.

ELECTRICAL SHOCK CAN CAUSE SEVERE
PERSONAL INJURY OR DEATH.

Ensure installation meets all applicable safety and local
electrical codes. Have all installations performed by a
qualified electrician.
Do not operate the generator with protective covers, access
covers or terminal box covers removed.

Disable engine starting circuits before carrying out
maintenance.

Disable closing circuits and/or place warning notices on any
circuit breakers normally used for connection to the mains or
other generators, to avoid accidental closure.

Observe all IMPORTANT, CAUTION, WARNING, and DANGER
notices, defined as:

Important ! Important refers to hazard or unsafe method or
practice which can result in product damage or
related equipment damage.

Caution ! Caution refers to hazard or unsafe method or
practice which can result in product damage
or personal injury.


Warning refers to a hazard or unsafe method
or practice which CAN result in severe
personal injury or possible death.





Danger refers to immediate hazards which
will result in severe personal injury or death.











Due to our policy of continuous improvement, details in this manual which were
correct at time of printing, may now be due for amendment. Information included
must therefore not be regarded as binding.

Front Cover Photograph
This photograph is representative only. Several variations are available within the
range of generators covered by this manual.



CONTENTS

SAFETY PRECAUTIONS IFC

SECTION 1 GENERAL DESCRIPTION 3

SECTION 2 PRINCIPLE OF OPERATION 4

2.1 Power Factor Control Mode 4
2.2 VAr Control Mode 4
2.3 Generator Current Limiting 4
2.4 Low Excitation Limiting 4
2.5 Voltage Matching Mode 6
2.6 Dead-Band or Dynamic Control Modes 6

SECTION 3 INSTALLATION 8

3.1 General 8
3.2 Generating Set Protection; General 8
3.3 Basic Operation - Power Factor
Control of Individual Generator(s) - Fig 6 8
3.3.1 Voltage Input ( E2 , E1 ) 8
3.3.2 Current Input ( S1 , S2 ) 8
3.3.3 AVR Control Output ( A1 , A2 ) 11
3.3.4 Circuit Breaker Input (CB1 , CB2 ) 11
3.4 Installing Options - Fig 8 11
3.4.1 Remote Power Factor (VAr) Adjustment - <1> 11
3.4.2 Remote Switching of Power Factor/VAr Mode - <2> 11
3.4.3 Generator Current Limiting - <3> 11
3.4.4 Excitation Voltage Limiting - <4> 11
3.4.5 Voltage Matching - <5> 11
3.5 PFC3 used for Power Factor Correction - Fig 9 11

SECTION 4 COMMISSIONING AND ADJUSTMENTS 15

4.1 Installations 15
4.2 Commissioning Basic System 15
4.2.1 Preliminary Adjustments 15
4.2.2 Droop Setting 16
4.2.3 PFC3 Setting 17
4.3 Commissioning Options 17
4.3.1 Voltage Matching Option 17
4.3.2 Current Limiting Option 18
4.3.3 Low Excitation Limiting Option 18
4.3.4 Dead-Band and Dynamic Control Options 19
4.4 Power Factor Correction 19

SECTION 5 USER ADJUSTABLE CONTROLS AND SELECTION LINKS 20

5.1 Light Emitting Diode (led) Indicators 20
5.2 Selection Links & Switches 20

SECTION 6 OPERATION 22

6.1 General 22
6.2 Combined Heat And Power Installations 22
6.3 Peak Lopping Installations 22
6.4 Power Factor Correction 22
6.5 Synchronous Motors 22
6.6 Overvoltage 22

SECTION 7 TROUBLE SHOOTING 23

SECTION 8 TECHNICAL SPECIFICATION 24














Newage International STRONGLY recommends that when a PFC3 is used
then "Loss of Excitation" tripping should also be used.






SECTION 1
GENERAL DESCRIPTION

The Power Factor Controller (PFC3) is designed to control the
power factor reactive current (VAr) of a generator whilst
running in parallel with the mains utility.

The PFC3 is also equipped with a voltage matching facility for
use with automatic synchronisation equipment. This dispenses
with the need for motorised potentiometers and allows a lower
cost synchroniser to be used.

The PFC3 can also be connected to provide power factor
correction of the incoming mains feeder by using the generator
to supply the reactive current. A current limiting facility is
provided to prevent generator overload.

The control loop within the PFC3 has two modes of operation
to allow for the best response matching of the prime-mover
governor and the generator voltage regulator. 'Dynamic
Control' is the preferred method providing continuous
correction and high accuracy. 'Deadband Control' provides an
alternative means which allows the power factor (or VAr) to
drift between presettable limits before any correction signal is
given. This method is employed where system stability may be
a problem.

The output of the PFC3 is internally limited to restrict the
maximum (or minimum) voltage of the generator under
abnormal operating conditions. This prevents the generator
from trying to match an unrealistic mains voltage and also
limits the consumer bus-bar voltage in the event of a mains
failure.

The PFC3 incorporates an excitation limiting circuit to prevent
the generator excitation from being driven to zero (or near
zero) when operating at leading power factor.

Due to its flexibility the PFC3 can be used in many different
single or multi-generator power schemes as shown in Fig 1a
through Fig 1d and the more unusual applications may not be
covered in this manual. If you are in any doubt as to the use of
the PFC3 in your application please contact your nearest
Newage International office for advice.
















































































SINGLE GENERATOR INSTALLATION
Fig. 1a Basic Power Factor Control

MULTIGENERATOR INSTALLATION
Fig. 1d Power Factor Correction

MULTIGENERATOR INSTALLATION
Fig. 1b Basic Power Factor Control

SINGLE GENERATOR INSTALLATION
Fig. 1c Power Factor Correction

SECTION 2
PRINCIPLE OF OPERATION

The following description makes reference to the block diagram
shown in Fig 2 ( Principle of Operation ).

Signals representing generator voltage and current are fed into
the PFC3 via isolation transformers and are used for various
tasks within the unit.

Two measuring circuits (the Active Current Transducer and the
Reactive Current Transducer) use both voltage and current
signals to produce internal dc references proportional to
generator kW and kVAr. The voltage input is also used to provide
internal power supplies and further internal circuits measure the
incoming voltage for voltage matching purposes.

The PFC3 is capable of operating in a variety of modes with
internal switching circuits routing the necessary control signals to
the main comparator/amplifier.

2.1 Power Factor Control Mode

In the 'Power Factor' mode of operation, the measured reactive
current is compared to a proportion of the measured active
current as set on the VAr/PF control potentiometer. If the
measured reactive current rises above the 'kW' signal, then the
PFC3 acts to reduce the internal set-point of the AVR (via
terminals A1 and A2) and brings the generated VAr (and hence
power factor) to the correct controlled level. If the measured
reactive current is lower than required then the reverse action
takes place. Under these conditions, closed-loop control of
generator power factor is achieved.

2.2 VAr Control Mode

In the 'VAr' mode of operation, the measured reactive current is
compared to a reference level derived from the setting on the
PF/VAR control potentiometer. If the measured reactive current
rises above this set-point, then the PFC3 acts to reduce the
internal set-point of the AVR (via terminals A1 and A2) and brings
the generated VAr to a controlled level. If the measured VAr is
lower than the demand then the reverse action takes place.
Under these conditions, closed-loop control of generated reactive
current is achieved.

The PFC3 incorporates circuits to provide a level of protection to
the generator not normally encountered in small/medium sized
installations.

2.3 Generator Current Limiting

Under normal circumstances the sizing of the generator set will
be such that the kW transfer to the mains (and hence the
generated VAr) will be limited by the engine and its fuel system.
In applications using the generator as power factor 'correction' of
the incoming mains this limiting does not apply and the level of
VAr demanded is a function of the feeder load. This can be many
times the rating of the generator set (particularly under fault
conditions) and must be protected against.

The PFC3 incorporates the necessary circuits to implement
generator current limiting. The output of a separate reactive
current measuring transducer is fed to the input of the main
comparator/amplifier in such a way as to override normal PF or
VAr control should excess current be detected. With this feature
connected, normal power factor (or VAr) control is provided
UNTIL the set current limit is reached, at which point the output to
the AVR restricts further increases in exported (or imported)
generator current. The level at which current limiting applies is set
using the appropriate circuit board control.

2.4 Low Excitation Limiting

In applications requiring the generator to operate at leading
power factor, the level of VAr imported may cause the generator
to reach an unstable region due to self excitation. This can result
in the loss of synchronisation and the associated large circulating
currents may cause circuit breakers to trip or even equipment
damage.

The PFC3 incorporates the necessary circuits to implement low
excitation limiting. The output of a separate excitation voltage
measuring transducer is fed to the input of the main comparator/
amplifier in such a way as to override normal PF or VAr control
should low excitation be detected. With this feature connected,
normal power factor (or VAr) control is provided UNTIL the set
low excitation limit is reached, at which point the output to the
AVR restricts further increases in imported generator current. The
level at which low excitation limiting applies is set using the
appropriate circuit board control. The circuit is automatically
disabled if left unconnected.

The PFC3 incorporates two more features which provide the user
with the choice of additional operating modes not normally
encountered in small/medium sized installations.






















































































































F
i
g
.

2

P
r
i
n
c
i
p
l
e

o
f

O
p
e
r
a
t
i
o
n



2.5 Voltage Matching Mode

The PFC3 is equipped with a second set of voltage input
terminals which are supplied (optionally) with a signal
representative of the load bus voltage. It is essential that this
signal is fully transformer isolated and is approximately 110Vac. If
enabled; and prior to the arrival of the closure signal from the
generator circuit breaker; the difference between the signals
representing the generator and bus voltages is fed to the input of
the main comparator/amplifier and adjusts the AVR set-point until
both signals match. The circuit is automatically disabled when the
generator circuit breaker closes. The table shown in Fig 3
explains the operation of the PFC3 when connected for voltage
matching.


E1/E2
SUPPLY
CB1/CB2
CONTACT
L1/L2
SUPPLY
OPERATING
MODE
ON OPEN
NON
PRESENT
AVR
CONTROL
ONLY
ON OPEN
APPROX
110V
VOLTAGE
MATCHING
MODE
ON CLOSED X
PF
CONTROL
MODE
OFF X X
AVR
CONTROL
ONLY


















2.6 Dead-Band or Dynamic Control Modes

The PFC3 can be set to operate in one of two control modes
dependent upon the requirements of the installation. In dynamic
mode, the output from the PFC3 continually adjusts the AVR set-
point in response to the smallest change in power factor (or
reactive current). In dead-band mode, the power factor (or
reactive current) is allowed to vary between user settable limits
before any adjustment is made. Dead-band mode results in a less
accurate control but can eliminate problems of stability caused by
interaction with engine governing systems.



VMAT
X = ANY POSITION
C
NORM
Links should be connected as shown
(Applies to PFC3 Part Numbers
E000-11030 & 21030 only)
Fig.3 Voltage Matching Mode

Fig 4 (Dead-band vs Dynamic) shows diagramatically the difference between dead-band and dynamic control modes and the effect
of the [ BAND ] control as seen on a typical power factor meter.

































Fig. 4 Dead-Band vs Dynamic

Fig 5 (Dead-band Control Action) further explains the operation of the PFC3 when set in dead-band control mode.































Fig. 5 Dead-Band Control Action

SECTION 3
INSTALLATION


DO NOT defeat or otherwise disable any
system interlocks whilst installing this
equipment.




To prevent personal injury or damage to
equipment, only qualified personnel should
install or operate this unit.



Important ! The use of Megger or High Potential test
equipment may result in damage to this unit.
Disconnect all leads before using such
equipment.

3.1 General

The Power Factor Controller PFC3 incorporates as standard
many features which enable it to be used in a wide range of
applications. These features may be used in any combination
depending upon the requirements of the end user.

It is assumed that the AVR is ready wired to the generator as
specified in the appropriate machine wiring diagram.

In ALL applications of the PFC3, the AVR and generator MUST
be equipped with a standard Quadrature Droop Paralleling kit.
This is shown in all figures fitted in 'W' phase (the more normal
position). For exact details refer to the wiring diagrams supplied
with your generator.

The PFC3 should be located in a clean, vibration free
environment, typically on the back panel of a control cubicle. If
the unit is for machine mounting it will have been supplied without
metalwork and MUST be fitted on anti-vibration mounts equal to
those of the AVR.

All wiring should be carried out using cables rated at 6A/600V
(minimum 0.75mm sq : 20AWG). For details of the AVR wiring,
reference should be made to the wiring diagrams supplied with
your generator.

Different applications may demand the installation of one or more
of the optional features offered in the PFC3. Four typical
configurations are described in this manual.

Fig 6 - Basic Operation - Power Factor Control of Individual
Generators

Fig 7 - Replacing earlier VAr2 with the PFC3

Fig 8 - Maximum configuration - All Options Fitted

Fig 9 - PFC3 used for Power Factor Correction

IF IN DOUBT - REFER TO FACTORY
3.2 Generating Set Protection; General

Unless adequate protection is installed, engine control system
malfunction or poor set-up can cause engine over-load or reverse
power conditions resulting in damage to the engine.

Generator control system malfunction or poor set-up can cause
generator over-current or loss of synchronism (pole-slipping)
resulting in severe damage to the generator.

Generator Over-current Protection

It is the responsibility of the Generating Set Assembler to ensure
that adequate protection systems are installed to trip the
generator circuit breaker in the event of generator over-current.

Excitation Loss Protection

It is the responsibility of the Generating Set Assembler to ensure
that adequate protection systems are installed to trip the
generator circuit breaker in the event of loss of synchronism.
Newage International Ltd. can supply a suitable unit for linking
with the generator circuit breaker and control gear. Please refer to
factory for details.

Automatic Synchronisers

It is the responsibility of the Generating Set Assembler to ensure
that adequate protection systems are installed for Automatic
Synchronising of AC Generators.

The following Automatic Synchroniser settings are recommended
when using PFC3:-

Generator frequency mismatch 0.1 Hz
Voltage mismatch +/-3%
CB closing angle +/-10 degrees
Over/Under Voltage Protection

It is the responsibility of the Generating Set Assembler to ensure
hat adequate protection systems are installed to prevent damage
to the generator or connected equipment in the event of over or
under voltage caused by malfunction/poor set-up of the control
system.

3.3 Basic Operation - Power Factor Control of
Individual Generator(s) - Fig 6

This is the simplest configuration involving one or more
generators coupled to the mains bus.

3.3.1 Voltage Input ( E2 , E1 )

These are connected to the generator output terminals (normally
'U' phase and Neutral) and act as the power supply to the unit as
well as its sensing input. The maximum voltage allowed at these
terminals is 277Vac/60Hz. If local regulations demand supply
fuses, then these should be rated at 5A.

3.3.2 Current Input ( S1 , S2 )

These are connected to the generator current sensing C/T having
a secondary rating of 5A. This MUST be positioned in the correct
phase and with the correct polarity for successful operation of the
PFC3. See wiring diagrams for details of your particular machine.
If local regulations demand, then either lead S1 or S2 may be
grounded.



3.3.3 AVR Control Output ( A1 , A2 )

These are connected directly to the corresponding terminals on
the AVR. Should the cable length between the PFC3 and the
AVR exceed 5m (16ft) then it is advisable to use screened leads
with the cable screen connected to terminal A1.

Important ! Do NOT ground the screen at either end.

3.3.4 Circuit Breaker Input ( CB1 , CB2 )

Contact closure of these terminals switches the PFC3 into power
factor (or VAr) control operation. These two terminals would
normally be connected to a normally open auxiliary contact on the
generator circuit breaker.

In the case of multi-generator installations, where the generator
can run off-grid in parallel (island system), then a normally open
auxiliary contact from the incoming mains circuit
breaker/contactor MUST be connected in series with the 'E2'
supply to the PFC. The voltage matching facility will then NOT
operate in island operation. (See Fig 9).

Where the PFC3 is used to replace an earlier VAr-2 then the
alternative wiring as shown in Fig 7 can be used. This will
eliminate the need for any wiring changes when fitting the new
PFC3. 'Voltage matching' will NOT operate with this wiring
configuration.

3.4 Installing Options - Fig 8

If it is required to expand on the basic use of the PFC3 and to use
one or more of the built-in options then the following notes apply.

Note: The numbers in the <brackets> refer to the relevant feature
shown in Fig 8.

3.4.1 Remote Power Factor (VAr) Adjustment - <1>

Should front panel/remote adjustment of power factor or VAr be
required then a 10k ohm / 1W potentiometer may be connected to
terminals RX, RY and RZ as shown. The use of screened leads is
essential with the screen connected to the adjacent '0V' terminal.

Important ! Do NOT ground the screen at the potentiometer
end. Simply leave the screen unconnected and
insulated.

When fitted, the external potentiometer has complete control over
the PFC3 set-point and the on-board adjustment is no longer
effective.

3.4.2 Remote Switching of Power Factor/Var
Mode - <2>

Should front panel/remote selection of power factor or Var
operating modes be required then a single pole changeover
switch (rated at 1A/240V) may be connected to the terminals PF ,
C and VAR as shown. This will replace the link which is normally
fitted. The use of screened leads is essential with the screen
connected to the adjacent '0V' terminal.
Important ! Do NOT ground the screen at the switch end.
Simply leave the screen unconnected and
insulated.

3.4.3 Generator Current Limiting - <3>

Under certain operating conditions it is desirable to be able to
limit the maximum current delivered by the generator. Connect
the current transformer to the terminals 0V and ILIM as shown.
The current transformer should have a secondary current output
of 0.32A (class index 3.0) at 100% generator output and must be
positioned in the correct phase and with the correct polarity for
the successful operation of the PFC3. See loose leaf wiring
diagrams for details of your particular machine. Bar mounted
current transformers with the correct secondary rating and
mechanical fixings are available from Newage International.

Important ! Do NOT ground either lead S1 or S2 of the
current limiting C/T circuit.

3.4.4 Excitation Voltage Limiting - <4>

Under certain operating conditions it is desirable to be able to
limit the minimum excitation voltage (and therefore excitation
current) to prevent generator pole slipping. All that is required to
enable this facility is to install two wires from X and XX (exciter
field + and -) on the generator to the terminals X and XX on the
PFC3. See loose leaf wiring diagrams for any additional details of
your particular machine.

Important ! Do NOT ground either lead X or XX. 3.4.5
Voltage Matching - <5>

Under certain operating conditions it is desirable to use the
voltage matching facility built into the PFC3. The inputs L1 and L2
have been designed to accept a standardised 110-120Vac supply
from the customers low, medium or high voltage bus. In ALL
cases the supply to the PFC3 MUST be isolated using a suitable
transformer but unlike the other unit inputs, the phasing is
unimportant. The input burden is typically 5VA.

Important ! Do NOT ground either lead L1 or L2.

3.5 PFC3 used for Power Factor Correction - Fig 9

It may be a requirement of certain applications to use the installed
generating capacity in conjunction with the PFC3 to 'correct the
power factor' of the incoming mains supply (at the consumers
incoming tie with the mains). In all cases it is necessary to protect
the generator against excessive current demand by fitting the
current limiting option.

The current limiting transformer(0.32A sec) MUST be fitted in the
generator output (as shown in Fig 9) and must be correctly
phased.

The power factor control current transformer (5A sec) MUST be
fitted in the incoming mains tie with the correct position and
phasing. This is usually 'U' phase but local variations may be 'A'
phase, L1 or cables 'red' in colour.

IF IN DOUBT - REFER TO FACTORY







F
i
g
.

6

P
o
w
e
r

F
a
c
t
o
r

C
o
n
t
r
o
l

o
f

I
n
d
i
v
i
d
u
a
l

G
e
n
e
r
a
t
o
r
s










































































































F
i
g
.

7

A
l
t
e
r
n
a
t
i
v
e

C
i
r
c
u
i
t

B
r
e
a
k
e
r

A
u
x
i
l
i
a
r
y

C
o
n
n
e
c
t
i
o
n








































































































F
i
g
.

8

P
o
w
e
r

F
a
c
t
o
r

C
o
n
t
r
o
l

A
l
l

O
p
t
i
o
n
s

F
i
t
t
e
d



























































































F
i
g
.

9

P
o
w
e
r

F
a
c
t
o
r

C
o
r
r
e
c
t
i
o
n

o
f

t
h
e

I
n
c
o
m
i
n
g

M
a
i
n
s

S
u
p
p
l
y







SECTION 4
COMMISSIONING AND ADJUSTMENTS

THERE ARE TWO VERSIONS OF PFC3
PFC3 E000-21030 has BLACK encapsulation
PFC3 E000-22090 is a GREEN board with clear encapsulation
Differences in features and commissioning are referred to where appropriate


To prevent personal injury or damage to
equipment, only qualified personnel should
install or operate this unit. During
commissioning the engineer will have access
to live components and terminals. Maximum
care should be taken when making
adjustments not to contact live parts. Refer to
the generator and switch-gear manufacturers
handbooks for other safety notices.


The following commissioning procedures
cover ONLY the features of the PFC3. They
DO NOT cover such matters as electrical
installation, phase sequence, switchgear or
engine controls.


Important ! The use of Megger or High Potential test
equipment may result in damage to this unit.
Disconnect all leads before using such
equipment.

4.1 Installations

ALL Installations:

- Follow section titled:
4.2 Commissioning Basic System

Installations making use of one or more of the optional
features:

Follow sections titled:
4.2 Commissioning Basic System and:
4.3 Commissioning Options

Installations configured for power factor correction:

Follow sections titled:
4.2 Commissioning Basic System and:
4.4 Power Factor Correction

4.2 Commissioning Basic System

The design of installations involving the paralleling of private
generators with the mains supply will be regulated by the local
generating authority. It is the responsibility of the commissioning
engineer to ensure that the necessary approval has been granted
before any paralleling operations are carried out.

The commissioning engineer should also be satisfied that all
system protection equipment is correctly installed, adjusted and
working and that ALL 'site' safety procedures have been
observed.

Before running the generator, the installing/ commissioning
engineer should ensure that all equipment is correctly installed
and that the generator set is safe to start. They should also have
studied the section on user adjustable controls and selection links
and should have become familiar with their function. If the

generator set controls are normally set to apply load automatically
then this feature should be inhibited or switched to 'manual'.

Important ! All paralleling operations must be carried out in
compliance with the generator set designers/
installers instructions. Newage International
take no responsibility for equipment damage
caused by incorrect paralleling operations.

Important ! During commissioning of the PFC3 any
connections to terminals RX, RY and RZ must
be removed.

Commissioning of the basic system is best carried out in three
parts:

1. Preliminary Adjustments.
2. Checking the Droop C/T polarity and setting.
3. Checking of the PFC3 C/T polarity and setting.

4.2.1 Preliminary Adjustments

Before starting the generator set the commissioning engineer
should first make sure that the user adjustable controls and
selection links on the PFC3 and certain AVR controls are set as
follows.

Note: CW = Clockwise Adjustment
CCW = Counter-Clockwise Adjustment




















Scaling as shown below

AVR controls Droop - Fully CW ( 100% )
Trim - Fully CCW ( 0% )







PFC3 controls PF/VAR - Midway ( 50% )
ILIM - Fully CCW ( 0% )
GAIN - Fully CCW
BAND - Fully CCW
XLIM - Fully CCW

Isolate voltage matching transformer if fitted.



























The Input Voltage Selection should be made appropriate for the
application (normally line-neutral voltage). Refer to wiring
diagrams supplied with your machine for further details.


















4.2.2 Droop Setting

Having checked that the generator is safe to run, the set
should be started and run up to nominal speed and the AVR
volts control adjusted to give an output voltage equal to that
of the installation mains.

Paralleling of the generator should now be carried out in
accordance with the set/installation designers instructions. At
this stage the commissioning engineer should take particular
notice of the generator output current.

If the generator current rises to an abnormally high level then
the generator circuit-breaker should be opened immediately
and the set stopped. In this event it is more than likely that
the droop C/T or its wiring is reversed. If this is the case then
the droop C/T connections to the AVR should be reversed
and the start-up and initial paralleling procedure repeated.
Do not confuse the AVR droop connections S1/S2 with the
PFC3 current transformer connections S1/S2.

After successful paralleling has been achieved, load should
be applied and increased to approximately 50%. At this point
the power factor should still be near unity. The voltage
across terminals S1 and S2 on the AVR should now be
measured (0.5 to 2.5Vac) and recorded for future reference.
The generator output current should be stable with only
minor variations reflecting small changes in the system
(mains) voltage.

The droop circuit polarity has now been verified and must
now be set to a level for the best operation of the PFC3.

Open the generator circuit breaker and stop the set before
proceeding.

The optimum position of the droop control can now be found by
using the following formula:


Potentiometer 0% = Fully Anti-Clockwise
Position 100% = Fully Clockwise

d = 0.25 for SX440 and MX341 AVRs
d = 1.00 for MX321 and SX421 AVRs

e.g If the measured voltage across S1 and S2 on the SX440 AVR
at half-load was 0.5V, then:


The AVR Droop potentiometer should therefore be set to the
midway position.

If the result of this calculation is greater than 100% then it
suggests that the droop C/T ratio is incorrectly rated (or fitted)
and the correct device should be obtained before proceeding
further.

The Droop equipment is now set.
Potentiometer
Position
(%) = X 100%
d
AVR S1 S2 voltage
Potentiometer
Position
(%) = X 100% = 50%
0.25
0.5


4.2.3 PFC3 Setting

Having set the AVR droop equipment the PFC3 can now be
commissioned as follows.

Important ! Make sure that the AVR Trim control is in the fully
counter-clockwise ( 0% ) position.

Start the generator, synchronise it with the mains supply and
apply load as described in the section on droop setting. At
this point the power factor should still be near unity.

The 'CB' LED on the PFC3 will indicate that the generator
circuit breaker is closed. Check that this is illuminated.

Measure the voltage across terminals S1 an S2 on the PFC3
(at half-load). This voltage should be between 50- 180mVac.
If this is not the case then it suggests that the PFC3 C/T is
incorrectly rated (or fitted) and should be replaced by the
correct unit before proceeding further.

Note: At this point the generator is under the control of
the AVR and droop transformer and the following
steps simply check the basic functions of the PFC3
before it is put into full operation.

Slowly adjust the PF/VAR control on the PFC3 to its fully
anti-clockwise position (maximum lag). If the generator
current rises to a high level as the adjustment is made, return
it to its central position immediately and re-check that the
AVR Trim control is in the fully anti-clockwise position.

After a delay of approximately 20 seconds measure the
voltage appearing across AVR terminals A2 and A1. This
should be between +2Vdc and +5Vdc (meter leads: positive
on A2, negative on A1). If the reading is of opposite polarity
(-2Vdc to -5Vdc) then stop the generator and check the
wiring between the PFC3 and the AVR (A1 and A2). If the
wiring is correct then simply reverse the connections S1 and
S2 to the PFC3.

Note: Certain 'third-party' current transformers do not
comply with standard marking conventions.

Re-start and parallel the generators, apply load and confirm
that the voltage across AVR terminals A2 and A1 is now of
the correct polarity.

Slowly adjust the PF/VAR control on the PFC3 to its fully
clockwise position (maximum lead) and measure the voltage
appearing across AVR terminals A2 and A1. This should be
between -2Vdc and -5Vdc (meter leads: positive on A2,
negative on A1).

Stop the generator and turn the PF/VAR control on the PFC3 to
the midway position. Turn the Trim control on the AVR to the fully
clockwise position.

The PFC3 is now ready for operation.
4.3 Commissioning Options

Before the generator and its PFC3 is put into full operation it will
also be necessary to set-up any of the optional features being
installed. The operation of the PFC3 and AVR will have already
been checked during the Commissioning of the basic system.

4.3.1 Voltage Matching Option

The Voltage Matching Transformer /Isolating Transformer (user
supplied) should be connected as shown in Fig 9. With the
system voltage and frequency at its nominal value, the secondary
voltage (applied to PFC3 terminals L1 and L2) should be
nominally 100Vac to 120Vac. The phasing of this signal is
unimportant.

Check that the voltage matching selection link is set to VMAT
E000 - 21030 (BLACK) only.

Turn the AVR Tim control fully anti-clockwise. Start the
generator and run-up to rated voltage and frequency. DO
NOT PARALLEL. Set the AVR volts control to give a
generator terminal voltage that is in the centre of the
expected Mains Utility Supply Voltage variation, e.g. If the
expected Supply Voltage variation is 380 - 440V then set the
generator terminal voltage to 410 volts.

If the expected Supply Voltage variation exceeds the rated
generator voltage stated on the nameplate, then stop the
generator and consult the factory before proceeding further.

Stop the generator and turn the AVR Trim control to the
midway position.

Start the generator and run-up to rated voltage and
frequency. DO NOT PARALLEL.

The VMAT LED should be illuminated E000 - 22090
(GREEN) only.

The PFC3 will now gradually adjust the generator voltage to
a new value which could be higher or lower than the bus
voltage. Return the generator voltage to the 'matched'
condition by slowly adjusting the BUSV control on the PFC3.
If the generator volts are 'High' (compared to the bus) then
the BUSV control should be adjusted slowly anticlockwise to
equalize the bus and the generator voltages. If the generator
volts are low then BUSV control should be adjusted
clockwise.

Note: The circuit may take several seconds to return the
generator voltage to the 'matched' condition. Due
allowance must be made for this delay whilst
making adjustments. For best results it is advisable
to adjust in small steps and wait for the response.

Stop the generator and turn the AVR Trim control to the fully
clockwise position.

The voltage matching option is now set.


4.3.2 Current Limiting Option

Current limiting should only be used when the PFC3 is connected
for Power Factor correction of the incoming main feeder.

If the generator has the MX321 AVR and separate current limiting
equipment fitted, this should be disabled by turning the ILIM
control on the AVR fully CLOCKWISE.

The Current Limiting Transformer should be connected as shown
in Fig 8 (feature 3). The phasing of this C/T is important.

For power factor correction applications it is usual to have two
current transformers (C/T's) fitted in the generator terminal box,
one with a 5 Amp secondary and one with a 330 mA secondary.
There will also be a 5 Amp secondary CT fitted to the Mains
Utility incoming feeder.

The 5 Amp Generator mounted CT is used for normal
Commissioning and Generator Power Factor Control. This will be
unused in Power Factor Correction operation and provision
should be made for connection of a shorting link to prevent an
open CT secondary.

The 330mA Generator mounted CT is used for measuring
generator reactive current for the I Limit feature.

The 5 Amp CT connected to the Mains Utility incoming feeder is
the one used in service for Power Factor correction. This CT
could be carrying site current and provision should be made for
the connection of a shorting link to prevent an open CT
secondary.

1. With the generator stationary connect the generator mounted
5 Amp CT to the PFC3 S1 S2 terminals, observing polarity.
Generator wiring diagrams will show the full details.

2. Connect the Generator mounted 330mA I Limit CT to the
PFC3 connections 0V / ILIM, S1 to ILIM, S2 to 0V. Generator
wiring diagrams will show the full details.

3. Turn the PFC ILIM potentiometer fully anti-clockwise.

4. Set PF / VAR selector to PF.

5. Parallel generator to mains network and run at maximum kW
set-point rating.

6. Adjust the PFC3 to give a generator PF of 0.9 lagging.

7. Calculate the operating Per Unit Reactive Current (PURC)
against generator rating :-










8. Measure TP2 voltage between 0V and TP2, meter neg (-) on
OV. This should be between +2 and +4V dc. For the location
of TP2, see the label drawing on the PFC3 access cover
plate or PFC3 manual.

9. Calculate required setting of TP2 voltage :-
[ (1 - PURC) X (TP2 voltage + 0.3) ] - 0.3

10. Turn ILIM slowly clockwise. TP2 voltage should reduce in
value. If it rises then stop generator and reverse the S1 S2
connections to the PFC3 0V and ILIM terminals. Retest from
line 5.

11. Adjust ILIM until TP2 = Required voltage as calculated in line
9.

12. Stop the generator and remove the generator CT
connections S1 S2 on the PFC3 and terminate the generator
CT wires with a suitable shorting link.

13. Connect the mains feeder CT S1 / S2 cables to the PFC3
(observing polarity) and remove the mains feeder CT
shorting link.

14. Turn the PFC3 PF / VAR setting potentiometer to the centre
position.

15. Start the generator and parallel to the mains network.

16. Set the generator to the required operating kW.

17. Adjust the desired mains power factor using the PF /VAR
setting potentiometer on the PFC3.

18. Set-up is now complete.

4.3.3 Low Excitation Limiting Option

Low Excitation Limiting should only be used when the generator
is to be operated at leading power factor.

The Excitation Limiting input (X and XX) should be connected in
parallel with the generator exciter field winding as shown, in Fig 8
(feature 4). The two exciter field connections (X and XX) will
normally be found at the auxiliary terminal block within the
generator. If these terminals do not exist, a suitable connection
block can be obtained from Newage International.

Connect a digital multimeter as follows:

Negative Input to 0V (any of four) on the PFC3
Positive Input to Test Point TP4 on the PFC3
Set to measure on the 20Vdc scale

Set the voltage matching selection link to NORM.
Start the generator and run-up to rated voltage and
frequency. DO NOT PARALLEL.
Using the graph shown in Fig 11, adjust the low excitation
limit control XLIM to set the voltage on the test point as
indicated.
Stop the generator and set the voltage matching selection
link to its original position.

The low excitation limiting option is now set.















Fig. 10
Fig. 11 Low Excitation Limit Setting


4.3.4 Dead-Band and Dynamic Control Options

For the majority of applications, dynamic control is recommended
as this is the more accurate and has the fastest response time of
the two operating modes. However, if instability is encountered,
then dead-band control may provide the necessary flexibility
within the generator control loop to overcome this undesirable
effect.

In dynamic mode, correction signals are continually fed to the
AVR in order to maintain the set power factor. In dead-band
control, the power factor is allowed to 'drift' within pre-set limits
before any corrective action is taken. Allowing the loop to 'open'
in this way provides for a less accurate control but much
improved stability.

In dead-band control mode the correction signals take the form of
pulses which change in width as the error (deviation from
setpoint) changes.

The three controls which alter the overall performance of the
PFC3 in dead-band mode are as follows:

[ BAND ] Adjusts the Dead-band width in dead-band mode
and allows the PF (or VAr) to drift between wider
limits before AVR set-point adjustments are made.

[ CLK ] Sets the rate at which AVR adjustments are made
(in dead-band mode only).

[ GAIN ] Makes the controller more or less sensitive to
deviation from the set-point (in dead-band mode
only) by altering the size of each adjustment.

For more information on the above adjustments see the section
on User Adjustable Controls and Selection Links.

If dead-band mode is selected it is strongly recommended that
the Gain and Band are set fully counter-clockwise (lowest gain,
widest band). These controls can then be adjusted from their
initial positions by trial and error to find the optimum setting.

As an aid to setting, red light emitting diodes (LEDS) indicate
increase (INC) and decrease (DEC) excitation signals. The clock
(CLK) indicates the rate of error correction signals and is pre-set
at the factory at approximately one per second.

4.4 Power Factor Correction

With the generator operated as a power factor correction system
it will be possible to overload the generator windings with a PFC3
setting of near unity power factor WITHOUT overloading the
engine/prime-mover. In this situation the generator has to supply
the necessary reactive current to the load in order to correct the
mains supply power factor to that set on the PFC3. The generator
output current is therefore independent of the governor setting
(kW) and/or the power factor setting on the PFC3.

Before the generator is put into operation in this mode the Current
Limiting option MUST be installed and commissioned (see
section 4.3.2).
The commissioning engineer should also attempt to establish the
nature of the site load. Since the generator will be expected to
supply all or part of the reactive component of load current, any
condition which would result in the generator operating at leading
power factor must be treated with care. Operating the generator
at leading power factor will cause the excitation to be reduced to
a level where loss of synchronisation may occur. This may cause
protective equipment to operate and the loss of the correcting
influence of the generator or, in extreme cases, equipment
damage.

Where these conditions are likely to exist it is recommended that
the Low Excitation Limiting option be used (see section 4.3.3).
Use of Excitation Loss equipment is also strongly recommended
for all installations where industrial ac generators run in parallel
with the mains supply (see section 3.2).







SECTION 5
USER ADJUSTABLE CONTROLS AND SELECTION LINKS

Refer to Figs 12 and 13 for the location of adjustments and
selection links.

Important ! Any control marked with an 'R' followed by a
number is NOT a user adjustable control. Do
NOT adjust unless instructed by Newage
International to do so.

Important ! Make sure you fully understand the function of
each control and link before making any
adjustments.

Note: W = Clockwise Adjustment
CCW = Counter-Clockwise Adjustment

[PF/VAR] Is the main Power Factor or Reactive Current
setting control dependent upon which mode of
operation the PFC3 is selected for.

PF mode CCW = Lag
Midway = Unity Power Factor
CW = Lead

VAr modeCCW = Export (generate) VAr
Midway = Minimum VAr
CW = Import (absorb) VAr

[ STAB ] Adjusts the effective 'damping' within the PFC3

CW = Fully damped (most stable)
CCW = Minimum damping

[ BAND ] Adjusts the Dead-band width in dead-band mode
and allows the PF (or VAr) to drift between wider
limits before AVR set-point adjustments are made.

CW = Narrow Band
CCW = Wide Band

[ CLK ] Sets the rate at which AVR adjustments are made
(in dead-band mode only).

CW = Faster Rate
CCW = Slower Rate

[ GAIN ] Makes the controller more or less sensitive to
deviation from the set-point (in dead-band mode
only) by altering the size of each adjustment.

CW = Large Adjustments made
CCW = Small Adjustments made

[ ILIM ] When this option is wired/enabled, adjusts the level
at which generator current limiting takes place.

CW = Decreases the current level
CCW = Increases the current level

[ BUSV ] When this option is wired/enabled, adjusts the
relative proportion of bus volts applied to the main
comparator/amplifier to make allowances for
different user supplied isolation transformers.

CW = Increases generator voltage
CCW = Decreases generator voltage

[ XLIM ] When this option is wired/enabled, adjusts the
lowest level of excitation permissable when
operating at leading power factor.

CW = Raises the low excitation limit
CCW = Lowers the low excitation limit

The remaining controls are set and sealed at the factory:

TP1 - TP6 are used for special setting up procedures.

5.1 Light Emitting Diode (led) Indicators

( CB ) Indicates closure of terminals CB1 and CB2 and
that the PFC3 is operating in power factor (or VAr)
mode.

(VMAT) To indicate presence of voltage matching signal.
E000 - 22090 (GREEN)

( CLK ) To indicate the rate of correction signals when
operating in dead-band mode.

( INC ) To indicate when the PFC3 is increasing the AVR
set-point in dead-band mode.

( DEC ) To indicate when the PFC3 is decreasing the AVR set-
point in dead-band mode.

5.2 Selection Links & Switches

{ PF - C - VAR } Power Factor or VAr modes

{ NORM - C - VMAT } Normal or Voltage Matching modes
E000 - 21030 (BLACK)

{ 1 = DYN 2 = DBD } Dead-Band or Dynamic modes
E000 - 22090 (GREEN)

{ DBD - C - DYN } Dead-Band or Dynamic modes
E000 - 21030 (BLACK)

{ C - 220 - 240 - 277 } Input Voltage Selection
E000 - 21030 (BLACK)

{ 115 - C - 220 Input Voltage Selection
240 - C -277 } E000 - 22090 (GREEN)













































































Fig. 12 PFC3 User Adjustable Controls and Selection Links Part
number E000 - 21030 (BLACK)
Fig. 13 PFC3 User Adjustable Controls and Selection Links
Part number E000 - 22090 (GREEN)


SECTION 6
OPERATION

6.1 General

Important ! Before putting the generator into full operation
the Trim control on the AVR MUST be set to the
fully clockwise position.

Under normal circumstances the operation of the PFC3 is fully
automatic and once commissioned the unit should continue to
operate without further attention.

Once commissioning is complete it will only be necessary to set
the operational power factor on the PF/VAR control on the PFC3.
The actual operating point of the power factor controller will be
determined by the application and the following notes are for
guidance only.

6.2 Combined Heat And Power Installations

Installations where the generator is operated at a kW rating
dependent upon the 'heat' demand from the site.

Normal PFC3 setting would be 1.0pf to 0.8pf lag to optimise the
utilisation of the generator rating but care must be taken not to
export unacceptable levels of VAr to the mains supply.

6.3 Peak Lopping Installations

Installations where the generator is used to supply all the site
load in excess of a maximum set by the mains provider.

Normally the PFC3 would be set to generate at a power factor
equal to the site load average and at a fixed power level
(maximum rating of the set) in order to reduce the incoming
demand on the mains to a minimum.

6.4 Power Factor Correction

The generator is used to provide the site VAr necessary to
maintain the power factor of the incoming mains supply within
fixed limits.

Normal PFC3 setting would be 1.0pf to 0.8pf lag to optimise the
power factor of the incoming supply, care must be taken that the
generator rating is not exceeded. The current limiting feature of
the PFC3 MUST be used in this situation.

6.5 Synchronous Motors
Using an a.c generator as a synchronous motor will demand a
setting of 1.0pf to 0.9pf on the PFC3.

Important ! Users of ac generators as synchronous motors
must provide the necessary equipment and/or
procedure for starting e.g pony motor.

When using an ac generator (equipped with a PFC3) as a
synchronous motor, the wiring required is identical to that of
generator applications. There is NO requirement to reverse C/T
or any other phase sensitive connections.
6.6 Overvoltage

If at any time during generator operation, the terminal voltage
exceeds the rated generator voltage stated on the nameplate,
then stop the generator and consult the factory.





SECTION 7
TROUBLE SHOOTING

Under normal circumstances the operation of the PFC3 is fully
automatic and once commissioned the unit should continue to
operate without further attention. Should the system fail in
service, the troubleshooting chart shown in Fig 14 will be helpful
in identifying the cause.

Mains Utility Supply Voltage Variations

In some areas, large voltage variations can take place causing
malfunction of the generator control system.

As stated in section 3.2, it is the responsibility of the Generating
et Assembler to install adequate protection to safeguard the
generator.

If satisfactory operation cannot be achieved then is would be
advisable to carry out a Mains Utility Supply Voltage survey over
a minimum period of 24 hours, recording the absolute maximum
and minimum RMS voltages and also the largest step change.
Consult the factory for advice.

The user is reminded of the following information relating to the
paralleling of generators.

The active power output (kW) of the set is controlled entirely
by the engine governor and NOT by the generator AVR.
Problems concerning kW fluctuations etc. are almost
certainly to do with the engine fuel system and/or frequency
control.

The reactive power output (kVAr) of the set is controlled
entirely by the excitation system of the generator (i.e the
AVR). Problems concerning reactive current (circulation/
fluctuation etc.) are almost certainly to do with the generator
AVR and its associated equipment.

Spares & Service

A full technical advice and on-site service facility is available from
our Service Department at Stamford or through our subsidiary
Companies.

When ordering parts the machine Serial Number or Machine
Identity Number and type should be quoted, together with the part
description. The Serial Number is printed on the nameplate and
the Machine Identity Number on two labels inside the terminal
box.

Orders and enquiries for parts should be addressed to:

Newage International Ltd.,
Nupart Department,
P O Box 17, Barnack Road,
Stamford, Lincolnshire
PE9 2NB, England.

Telephone: 44 (0) 1780 484000
Cables Newage Stamford
Telex: 32268
Fax: 44 (0) 1780 766074

or any of our subsidiary companies listed on the back cover.



SECTION 8
TECHNICAL SPECIFICATION


Input voltage (50-60Hz) 115 range 110-125v ac Applies to PFC E000 - 22090 (GREEN)
220 range 200-230v ac 5VA
240 range 231-250v ac
277 range 251-290v ac (60 Hz only)

Input current PF/VAR sensing 5A CT 2.5VA
Current Limit 330mA CT 2.5VA

Voltage matching input 110v ac 10%
5 vA nominal

Low excitation limit input 150 V dc Max

AVR control range (A1 A2) 3 volts dc

Power Factor setting range (PF) 0.7 lag to 0.7 lead (see note 1)

Remote PF setting potentiometer value 10K ohms 1 watt

Reactive current setting range (VAR) generate/absorb 0-100% gen. current (see note 1)

Low excitation limit range 2-8 volts dc

Current limit range 70-100% gen. current

Control accuracy VAR 5% (see note 2)
Power Factor 0.05 pf
Voltage matching 2%

Reponse time constant 4 seconds

Generator output voltage limiting range 5% to 15%

Environmental Vibration 20-100 Hz 50 mm/s
100-2 kHz 3.3 g
Relative humidity 0-60 C 95%
Operating temperature -40 to +70 C
Storage temperature -55 to +80 C

Note 1: Refer to generator lag/lead performance data sheets for permissible operating conditions.

Note 2: Control accuracy may drift if the CT secondary current falls below 0.5 Amps.




REGISTERED OFFICE AND ADDRESS
NEWAGE INTERNATIONAL LIMITED, PO BOX 17, BARNACK ROAD, STAMFORD
LINCOLNSHIRE, PE9 2NB ENGLAND
Tel: +44 (0) 1780 484 000
Fax:+44 (0) 1780 484 100
Website: www.newage-avkseg.com


STAMFORD POWER GENERATION WORLDWIDE


AUSTRALIA NEWAGE ENGINEERS PTY. LIMITED
PO Box 6027,
Baulkham Hills Business Centre,
Baulkham Hills NSW 2153
Tel: (61) 2 9680 2299
Fax: (61) 2 9680 1545
MEXICO NEWAGE Mexico
Stamford Mexico S de RL de CV
Av. Circuito Mexico No. 185
Parque Industrial 3 Naciones
San Luis Potosi, SLP
C.P. 78395
Tel: (00) 48 26 84 00
Fax: (00) 48 26 84 05

CHINA

WUXI NEWAGE ALTERNATORS LIMITED
Plot 49-A, Xiang Jiang Road
Wuxi High Technical Industrial Dev.Zone
Wuxi, Jiangsu 214028
PR of China
Tel.: (86) 51 027 63313
Fax: (86) 51 052 17673

NORWAY

NEWAGE NORGE A/S
kern Naeringspark, Kabeigt 5
Postboks 28,
kern, 0508 Oslo
Tel: Oslo (47) 22 97 44 44
Fax: (47) 22 97 44 45

GERMANY

AvK DEUTSCHLAND GmbH & Co. KG
Niederlassung Dreieich
Benzstrasse 47-49
63303 Dreieich
Tel: (49) 61 03 50 39 0
Fax: (49) 61 03 50 39 40

SINGAPORE

NEWAGE ASIA PACIFIC PTE LIMITED
10 Toh Guan Road #05-03
TT International Tradepark
Singapore 608838
Tel: (65) 794 3730
Fax: (65) 898 9065

INDIA

C.G. NEWAGE ELECTRICAL LIMITED
C33 Midc,
Ahmednagar 414111,
Maharashtra
Tel: (91) 241 778 224
Fax: (91) 241 777 494

SPAIN

STAMFORD IBERICA SA
Poligono Industrial ''Los Linares
Avda.de Fuenlabrada, 38
E-28970 HUMANES DE MADRID
Tel: (34) 91 498 2000
Fax : (34) 91 498 2124

ITALY

NEWAGE ITALIA SrI
Via Triboniano,
20156 Milan
Tel: (39) 02 380 00714
Fax: (39) 02 380 03664

U.S.A.

Newage AVKSEG-Americas
7928 University Avenue NE
Fridley, MN 55432
Tel : (1) 800 367 2764
Fax: (1) 800 863 9243

JAPAN

NEWAGE INTERNATIONAL JAPAN
8-5- 302 Kashima
Hachioji-shi
Tokyo, 192-03
Telefon: (81) 426 77 2881
Fax (81) 426 77 2884









'STAMFORD' is a registered trademark of Newage International Ltd.
2003 Newage International


TD_PFC MAN.GB_09.03_01_GB

Вам также может понравиться