THICKNESS OF PILECAP (T) = 0.

70 m
CLEAR COVER = 0.075 m
WIDTH OF PILECAP (B) = 0.83 m
LENGTH OF PILECAP (L) = 2.83 m
WIDTH OF COLUMN (b) = 0.60 m
DEPTH OF COLUMN (d) = 0.30 m
f
ck
FOR PILECAP = 30 Mpa
f
y
FOR PILECAP = 415 Mpa
THICKNESS OF SOIL LAYER ABOVE PILECAP = 0.70 m
UNIT WEIGHT OF SOIL ABOVE PILECAP = 18.00 kN/m
3
CLEAR CANTILEVER FROM PILE = 0.15 m
DIAMETER OF PILES = 0.53 m
COLUMN F
y
(kN) F
x
(kN) F
z
(kN) M
x
(kN.m) M
z
(kN.m)
1 643.00 2.00 0.60 0.00 50.00
C
Y
0.7 X
Z
2.825
0.6
0.825 1 0.3 2
COLUMN
MOMENT DUE TO SHEAR AT PILECAP BASE (M
X
') 0.42 kN.m
MOMENT DUE TO SHEAR AT PILECAP BASE (M
Z
') -1.40 kN.m
TOTAL BENDING MOMENT (M
X
) 0.42 kN.m
TOTAL BENDING MOMENT (M
Z
) 48.60 kN.m
TOTAL VERTICAL UNFACTORED FORCE 713.15 kN
PILECAP DESIGN FOR 2 PILES WITH A SINGLE COLUMN
UNFACTORED REACTIONS AT COLUMN BASE
PILE NO. r
xi
(m) r
xi
2
1 1.000 1.00
2 1.000 1.00
r
xi
2
= 2.00
X
Z
0.6
0.4375
2.00
1.475
332 kN 381 kN
MAXIMUM ULTIMATE BENDING MOMENT (M
UZ
) = 250 kN.m
EFFECTIVE DEPTH ALONG-X DIRECTION = 0.619 m
EFFECTIVE DEPTH ALONG-Z DIRECTION = 0.607 m
X-DIRECTION
A
st
REQUIRED = 1155 mm
2
MIN. A
st
REQUIRED = 613 mm
2
DIA. OF MAIN BARS = 12 mm
DIA. OF DISTRIBUTION BARS = 8 mm
REQUIRED NOS. OF MAIN BARS = 10 mm
PROVIDED SPACING OF MAIN BARS = 5 mm
REQUIRED SPACING OF DISTRIBUTION BARS = 12 mm
PROVIDED SPACING OF DIST. BARS = 5 mm
Z-DIRECTION
MIN. A
st
REQUIRED = 728 mm
2
DIA. OF DISTRIBUTION BARS = 12 mm
REQUIRED SPACING OF MAIN BARS = 489 mm
PROVIDED SPACING OF DIST. BARS = 200 mm
332 kN 381 kN
2 1
FINAL FORCES
0.15
SECTION ALONG X
IN PILE (kN)
332
381
ONE-WAY SHEAR
ALONG-X
326 0.619 0.619 374
498 571
0.525 1.475 0.525
MAXIMUM ULTIMATE SHEAR AT CRITICAL SECTION (V
U
) = 374 kN
ULTIMATE SHEAR STRESS (
u
) = 0.73 N/mm
2
pt OF STEEL PROVIDED (%) = 2.96 %
SHEAR STRESS IN CONCRETE (
C
) = 0.96 N/mm
2
SHEAR STRESS RESISTED BY DIST. STEEL (
us
) = 0.25 N/mm
2
TOTAL SHEAR STRESS RESISTED BY SECTION = 1.20 N/mm
2
DESIGN FOR SHEAR IS NOT REQUIRED IN X-DIRECTION.
TWO-WAY SHEAR
ALONG-X
505 0.310 0.310 565
498 571
0.525 1.475 0.525
MAXIMUM ULTIMATE SHEAR AT CRITICAL SECTION (V
U
) = 565 kN
ULTIMATE SHEAR STRESS (
u
) = 0.28 N/mm
2
SHEAR STRESS IN CONCRETE (
C
) = 1.37 N/mm
2
k
s
.
c
= 1.37 N/mm
2
SECTION IS OK IN SHEAR.
SHEAR FORCE DISTRIBUTION
SHEAR FORCE DISTRIBUTION
CHECK FOR SHEAR
X-DIRECTION
A
st
REQUIRED = 1155 mm
2
15
MIN. A
st
REQUIRED = 613 mm
2
0.15 0.28
DIA. OF MAIN BARS = 12 mm 0.2 0.315
DIA. OF DISTRIBUTION BARS = 8 mm 0.25 0.35
NO OF BARS REQUIRED FOR MAIN STEEL = 10 0.5 0.46
NO OF BARS REQUIRED FOR DIST. STEEL = 12 0.75 0.54
REQUIRED SPACING OF MAIN BARS = 72 mm 1 0.6
REQUIRED SPACING OF DISTRIBUTION BARS = 60 mm 1.25 0.64
Z-DIRECTION 1.5 0.68
A
st
REQUIRED = 728 mm
2
1.75 0.71
MIN. A
st
REQUIRED = 728 mm
2
2 0.71
DIA. OF MAIN BARS = 12 mm 2.25 0.71
2.5 0.71
NO OF BARS REQUIRED FOR MAIN STEEL = 6 2.75 0.71
3 0.71
REQUIRED SPACING OF MAIN BARS = 489 mm
2.5
2.8
3.1
3.5
20 25 30
0.28 0.29 0.29
0.315 0.325 0.33
0.36 0.36 0.37
0.48 0.49 0.5 2.75 0.94
0.56 0.57 0.59 3 0.96
0.62 0.64 0.66 2.96 0.956703
0.67 0.7 0.71
0.72 0.74 0.76
0.75 0.78 0.8
0.79 0.82 0.84
0.81 0.85 0.88
0.82 0.88 0.91
0.82 0.9 0.94
0.82 0.92 0.96
15 2
20 3 5
25 4
30 5