RasGas Company Limited

Cranes and Lifting Gear Integrity Manual




Document No: T12-X03-002 Revision No: 2 Sheet: 109 of 139
Document Part: 000 RasGas Use Only Issue Date: 13-Sep-11
B.2.3 Onshore Critical Lift Plan Form - Table B-7 Onshore Critical Lift Plan Form

RASGAS ONSHORE CRITICAL LIFT PLAN
Job Description :
Location : Schedule Lift Date : Prepared Date :
Equipment Tag Number : WO # SD Job #
Basis for Critical Lift Classification:
Heavy Lift > 5.0 MT Hazardous Cargo / Materials Wind or Weather condition. Elevated Work using Personal W/Basket *
Multiple Cranes (Tandem Lift) used to Lift* Assessed Risk Medium, to High level risk *
Load over or near live Electrical Power, facility Hydro-carbon or process equipment ** Other s* _______________________________
* Review by Crane Specialist or TPA Lifting Inspector is required.
** If Lift is > 5.0 MT and over live facilities or occupied facilities- approval be Operation Supervisor and FIMs Program 10 Owner Designee is required.
1. Crane Details
Make : Model and Serial No: Current Inspection Validity :
2. Load Details
Load Description : Net Weight of Load (Kg or Tonnes):
(Specification of the Eqpt. to confirm the weight to be attached)
Load Elevation :
3. Calculation of Total Weight acting on the Crane
List of Lifting Tackles to be used Yes No N/A
Weight.(Kg or Ton)
Type of Equipment Size SWL Qty. Jib
Extension
Hook Block (Main)
Aux./Headache Ball
Rigging Tackles
Others
Gross Load Weight :
4. Lifting Requirements (Plot Plan, Rigging Sketch, and Method Statement shall be attached where required)
a. Required Boom Length : b. Max. Lifting Capacity at Configuration :
c. Max. Required Operating Radius : d. Percentage of Crane Capacity :
e. Lift will be: f. Outriggers :
g. Wind Speed allowed as per Crane Manufacture Specification:
(Allowable limit is 10.2m/sec. as per RG procedure.)
h. Ground/Site Condition: atisfactory i. Cra
5. Checklist
1. No. 2.
3.
(Calculation of ground bearing pressure exerting by the Crane and required additional protection shall be submitted where applicable)
4. Copy of current valid TPI certificate of Cranes, Lifting Gears & Lifting Equipment operators attached:

Lifting Plan Prepared By Lifting Plan Approved By
Lift Planner Name

Signature & Date

Name of Rigging & Lifting Supervisor or
Designated Custodian Department or FIMS
Program 10 Owner/Designee & Operation
Supervisor** ( See Basis Above)
Signature & Date

Reviewed By Crane Specialist (* See Basis for Critical Lift Section Above )
Name: Signature: Date:
Comments if any (Separate sheet can be attached if required):

RasGas Company Limited

Cranes and Lifting Gear Integrity Manual


Document No: T12-X03-002 Revision No: 2 Sheet: 110 of 139
Document Part: 000 RasGas Use Only Issue Date: 13-Sep-11
B.2.4 Onshore Nonstandard Lift Plan Form - Table B-8 Onshore Nonstandard Lift Plan Form

RASGAS ONSHORE NONSTANDARD LIFT PLAN
Job Description :
Location : Scheduled Lift Date : Prepared Date :
Eqpt. Tag Number : WO # SD Job #
Basis for Nonstandard Lift Classification:
Not classified as Critical, Gross load is less than 18 MT, Gross load is greater than 75% but less than 90% of Crane load
chart rating at lifting configuration.
1. Crane Details
Make :

Model and Serial No:

Current Inspection Validity
2. Load Details
Load Description :
Net Weight of Load (Kg or Tonnes):

(Specification of the Equipment to confirm the Wt. to be attached)
Load Elevation :
3. Calculation of Total Weight acting on the Crane
List of Lifting Tackles to be used Yes No N/A
Weight.
(Kg or Ton)
Type of Equipment Size SWL Qty. Jib
Extension
Hook Block (Main)
Aux./Headache Ball
Rigging Tackles
Others
Gross Load Weight :
4. Lifting Requirements (Plot Plan, Rigging Sketch, and Method Statement shall be attached where required)
i. Required Boom Length : j. Max. Lifting Capacity at Configuration :
k. Max. Required Operating Radius : l. Percentage of Crane Capacity :
m. Lift will be n. Outriggers :
o. Wind Speed allowed as per Crane Manufacture Specification:
(Allowable limit is 10.2m/sec. as per RG procedure)
p. Satisfactory i.
5. Checklist
5. No. 6.
7. No
(Calculation of ground bearing pressure exerting by the Crane and required additional protection shall be submitted where applicable)
8. Copy of current valid TPI certificate of Cranes, Lifting Gears & Lifting Equipment operators attached:

Lifting Plan Prepared By Lifting Plan Approved By
Lift Planner Name
Signature & Date

Name of Rigging and
Lifting Supervisor
Signature & Date

Comments if any (Separate sheet can be attached if required):