The document discusses problem management processes and procedures. The primary objectives are to prevent problems and reduce the impact of incidents. For major incidents or those with high customer impact, a root cause analysis must be conducted and documented in a ticket within 3 or 8 business days respectively. The root cause analysis aims to identify the root cause and define solutions. Quality gates are in place to review the documentation and ensure issues are addressed. Target times are also set for finalizing the root cause analysis and implementing sustainable solutions.
The document discusses problem management processes and procedures. The primary objectives are to prevent problems and reduce the impact of incidents. For major incidents or those with high customer impact, a root cause analysis must be conducted and documented in a ticket within 3 or 8 business days respectively. The root cause analysis aims to identify the root cause and define solutions. Quality gates are in place to review the documentation and ensure issues are addressed. Target times are also set for finalizing the root cause analysis and implementing sustainable solutions.
The document discusses problem management processes and procedures. The primary objectives are to prevent problems and reduce the impact of incidents. For major incidents or those with high customer impact, a root cause analysis must be conducted and documented in a ticket within 3 or 8 business days respectively. The root cause analysis aims to identify the root cause and define solutions. Quality gates are in place to review the documentation and ensure issues are addressed. Target times are also set for finalizing the root cause analysis and implementing sustainable solutions.
The primary objectives of Problem Management are to prevent Problems and
resulting Incidents from happening, to eliminate recurring Incidents and to
minimize the impact of Incidents that cannot be prevented. In order to reach the Problem Management process objectives it is important to consequently analyze all process and technical aspects of Major Incidents and Incidents with high Customer Business Impact (CBI), as well as to perform regular Incident analyses to identify trends.
Reactive Problem Management including Major Incidents MI (INM with confirmed CBI critical) Incidents with CBI high Multiple Incidents (reoccurring Incidents) Customer feedback (if covered in the contract) PRM based on input from other processes (i.e.: Changes with close code not successful) Workarounds (an existing Workaround has to be substituted by a sustainable solution)
For every INM with CBI critical or high it is mandatory to open a PRM Ticket. For INM critical and high all actions have to be recorded in the RCA- document! This will be done in parallel to opening and tracking of the PRM Ticket by a Lead Problem Manager. The RCA has to be prepared in cooperation with SOCs, OPM and SDM.
Proactive Problem Management: Triggers for proactive PRM have to be considered by the CSS GxUs and LBUs themselves. Every employee has the obligation, based on monthly INM analysis, to start pro-active PRM. PROBLEM MANAGEMENT (PRM) PROBLEM MANAGEMENT PROcEss TRiGGER fOR PRM TickETs
Version: 2.1 Released Classification: INTERNAL Approved at/valid from: 08.04.2014 Approved by: CSS Quality Improvement Luis Pavez Author: Marek Kastelovic (CSS unit process manager) Area of validity: Delivery / CSS
Please note: Previous versions (handouts /flyers) will be obsolete with this document!
GxU has nominated defined PRM process contacts that can be addressed by dedicated mailboxes: GCU A&F & DPDHL: Mailbox: FMB_GCU_AF_GBO_GPQ Mailbox: FMB PRM Postfach GO DPWN GCU AMER: Mailbox: DL TSNA GQPT DESC LIM GCU APAC: Mailbox: FMB TS GDM SGA PbM GCU MPHS: Mailbox: CSS_QPS@t-systems.com GCU SHELL: Mailbox: FMB-TS-GDM-SGA-PbM@t-systems.com GCU TelCo : Mailbox: Telekomit.Leadproblem@telekom.de GDU DPS: Mailbox: QPSM-PM@t-systems.com GDU SAP: Mailbox: GDU-SAP-CPRM@t-systems.com
Reference process of TSI PRM https://tsi-myworkroom.telekom.de/livelink_en/livelink/open/49451394 CSS Work instruction PI (PRM): https://tsi-myworkroom-de.telekom.de/livelink_de/livelink/open/74771182
Major process KPI 2014: (Reporting within CSS Quality Cockpit) Root cause rate in time RCRit critical Target 2014: min. 75% Problem solution rate in time critical Target 2014: min 90% Root cause rate in time RCRit high Target 2014: min. 65% Problem solution rate in time high Target 2014: min 90%
fURThER dOcUMENTATiON PRM TickET OPENiNG PRM PRiORiTizATiON
The tickets are handled in Service Center Cosima (will be followed by SM9 in July). In the module Problem you can use Open New Problem and start the relevant template. According to the Procedural Guideline CSS the following rules apply:
Latest 1 BD after close (critical / high) of the INM, Problem Management needs to be started. (PRM ticket has to be created and related to INM ticket ) The standard RCA template has to be used in specified cases and the content needs to be harmonized with the related PRM ticket.
All steps and information regarding the PRM handling process are documented in the tab Details. After saving you can find them in tab Activities. In the tab Activities you can find tool related messages as well as messages about status and changes, i.e. automatic warnings and alerts. In case of INM (critical/high) additionally the RCA template has to be used. The Lead Problem Manager is responsible for steering the RCA. The processing of the RCA (template) is documented and tracked in the Main Reporting List/Root Cause Overview (MRL/RCO) and Solution Tracking List (STL) (GPRM for critical / GQPP for high) PRM TickET PROcEssiNG PATTERN ANALysis PRM TickET PROcEssiNG TiMEs By PRiORiTy
1. Successful handover of all necessary information from LIM to responsible LPRM (draft of the RCA document). 2. Start Problem Management/RCA for closed INM 3. Validation of final CBI with respective SDM/OPM 4. Steer the Problem Management process with aim to deliver all required requisites in due dates. 5. Fill the individual RCA sections according the inputs from respective stakeholders (Production, OPM, SDM) 6. Answer all questions which raised during Problem Management Process 7. Describe the root cause from the management perspective 8. Document all the information into MRL/RCO list 9. Deliver the RCA with root cause to FMB_CSS_ProblemManagement 10. Define the solutions, based on the all technical and procedural findings 11. Define the owner of each measure 12. Define target time for each measure 13.Document the measure into Solution Tracking List 14. Fill all the mandatory fields within the RCA document = 100% 15. Deliver final RCA to FMB_CSS_ProblemManagement 16. Successful Quality Gate will be performed by CSS 17. Send the approved final RCA document to GPRM team for QG2 18. Send the final RCA to the whole Distribution List. 19. Prepare Lessons Learned Document and deliver it to the production lines.
The most important factors to avoid RCA rejection: Ensure clear root cause and customer business impact description Ensure the correct classification of CBI and customer impact time Ensure that RCA document will not miss any of mandatory field Ensure that the GPRM team will receive the final RCA document in time Ensure knowledge sharing with other, in future, possibly affected lines
Based on the CSS Ticket Report each GxU/LBU is responsible for identification of possible INM tickets for PRM/RCA. A validation of correct values of CBI needs to be done, possibly a steering of setting the values is needed, if the tickets are not monitored by the Ticket Marshalls (EMEA + SHELL). Problem Management and Root Cause Analysis has to be started latest 1 Business Day after INM closure and all information needs to be returned to the CSS PRM mailbox. After finalization of the RCA the content and the PRM ticket should be harmonized and the Line Process Manager takes over as a Quality Gate. Further, after finalization of the analysis and setup of dedicated measures a BestGuide (known error database) entry has to be created for technical solutions. The BestGuide-ID has to be stored into the related PRM ticket. https://websso.t-systems.com/bestguide/bg/gv_view.php
The PRM ticket can only be closed after all measures are implemented successfully!
All documentation has to be done in a way, that people not closely involved into the technical discussion can generally understand the content and status of the Problem solving
TiMEfRAME fOR ROOT cAUsE ANALysis hOw TO sUccEssfULLy PROcEEd wiThiN RcA Process Steps Prioritization Problem Logging Problem Investigation & Diagnosis Know Error Logging & Investigation Known Error Resolution Problem Review & Closure Major Problem 3 BD 7 BD 30 BD (single case) / 60 BD (multiple case) Warning70% Warning70% Warning70% high 8 BD 7 BD 40 BD (single case) / 70 BD (multiple case) Warning70% Warning70% Warning70% medium 15 BD 10 BD 70 BD Warning70% Warning70% Warning70% low 20 BD 10 BD 70 BD Warning70% Warning70% Warning70% RcA PROcEssiNG Based on Management Request for customer or areas with an increase trend of Incidents Tickets (critical/high/medium) the CSS PRM Team prepare a pattern analysis to identified major findings according to the documented Incidents. Normally the CSS PRM Team analyzed all ticket in the last Three months. Result will be presented to CSS responsible for affected account or organization. QUALiTy GATEs RcA - css Based on documented root cause Analysis for critical and high Incidents,, PRM GQD checked the quality of documentation and addressed finding to CSS PRM House, Our CSS PRM Team checked the addressed findings and define proposal to solve the issues and addressed this into the CSS PRM Community. A weekly Report is established within CSS TiMEfRAME fOR fiNALizATiON Of ROOT cAUsE ANALysis TiMEfRAME fOR sUsTAiNABLE sOLUTiON CBI Critical Incidents (Major Incidents & eCrids & Early Warning ) Inputs GPRM Morning Call / CSS Daily Ticker Target time for delivering of RCA document with root cause 3 BDs Documentation of root cause in tool (SC-Cosima / SM9) Documentation of correctly described root cause in GPRM Main reporting list Send the RCA with defined root cause to FMB_CSS_Problemmanagement Quality gate 1 is done by GPRM based on the inputs in GPRM MRL. CBI High Incidents Inputs GPRM Morning Call / CSS Daily Ticker /GPRM INM Daily Journal Target time for delivering of RCA document with root cause 8 BDs Documentation of root cause in tool (SC-Cosima / SM9) Documentation of correctly described root cause in the RCO list Send the RCA with defined root cause to FMB_CSS_Problemmanagement Quality gate 1 is done by GPRM based on the inputs in RCO list.
Target times for finalization of the RCA document Critical: 7 BDs to deliver final RCA document High: 7 BDs to deliver final RCA document
Define solution measures, measure owners, due date for each measure Document the measures into the Solution Tracking List RCA mandatory fields filled on 100% Send the final RCA to CSS PRM Management (FMB_CSS_Problemmanagement) Quality Gate for CSS QG Send the approved RCA (with CSS QG) to GPRM team for QG2
Critical: single solution / multiple solutions = 30BDs/60BDs High: single solution / multiple solutions = 40BDs/70BDs Single solution is realization of the single measure on one affected Configuration Item. Multiple solutions is a multiple realization of the measure/measures on the multiple Configuration items.
All defined and agreed measures are handed over and stored into the Solution Tracking List (STL) and are tracked centrally. Valid reasons for an adaptation date in STL : Waiting for change approval Waiting for supplier contribution Waiting for customer contribution/ approval