Вы находитесь на странице: 1из 6

Report No:

KAZ POWER PLANT


INSPECTION TEST REPORT

Date:

Checks and Tests of Instruments for Pre-Commissioning


Subcontractor:
Reference QCP No:

QCP phase:

Test Notification n:

Notification Date:

Equipment: Type: HV-MV SWITCHBOARD

Equipment Tag:

Equipment Designation:

System Tag:

Manufacturer:

Model:

Data Sheet No:

Drawing No.:

Operating Voltage

[kV]

Rated Frequency

[kV]

Max insulation Voltage

[kV]

Rated Voltage

Checks and Tests Description of Switchboards


1

[kV]

N/A

Preliminary checks
Verify the check sheet (ITR-EW-03-A) of Mechanical Completion is completed and signed
Check availability of Vendors instructions.
Check cleaning and conservation status
Verify the check sheet of Mechanical Completion (end assembly) of electric motor and associated auxiliary
equipment is completed and signed.

Electrical measurement
Insulation Resistance Tests (Bus Bar System)
Test Voltage
Phase to earth
Result

L1 L2,3 +E

L2 L1,3 +E

L3 L1,2 +E

L1L2+ L3,E

L2L3+ L1,E

L1L3+ L2,E

Phase to phase
Result

Test equipment

Note: 1) Close all circuit breakers an apply the AC voltage for a period of 1 minute to the tested phase
2): Perform insulation resistance tests after the AC Voltage test. Compare the value obtained with the value measured before the
AC Voltage test, described in ITR-EW-04A ( construction phase if any)
Perform the AC applied voltage test
Test Phases
Result

L1L2,3 +E

L2L1,3+E

L3L1,2+E

Note: 3) The AC voltage test shall be reduced to 85% in accordance with the requirements of IEC 60439, in cases where the switchgear
has been subjected to such tests earlier.

P.1/5

Report No:

KAZ POWER PLANT


INSPECTION TEST REPORT

Date:

Checks and Tests of Instruments for Pre-Commissioning


Subcontractor:

Checks and Tests Description of Switchboards

N/A

Conductivity Test

Circuit designation
From

Circuit designation Busbar conductivity, m


To

L1

L2

L3

Ducter

Note (*) Ducter (DLRO-Digital Low Resistance Ohmmeter) is an instrument to measure low values of resistance.
Conductivity measurements shall be carried out between adjacent outgoers or adjacent outgoer and incomers in order to verify
the entire busbar path including 'droppers/risers'.
For identical connections the measured values shall not differ by more than 20% from each other.

Test equipment data


Manufacturer

Remarks:

P.2/5

Model

Serial No.

Type

Range

Eng. Unit

KAZ POWER PLANT


INSPECTION TEST REPORT

Report No:
Date:

Checks and Tests of Instruments for Pre-Commissioning


Subcontractor:

Equipment: Type: HV-MV SWITCHBOARD(*)

Equipment Tag:

Equipment Designation:

System Tag:

Manufacturer:

Model:

Data Sheet No:

Drawing No.:

Checks and Tests Description of each Switchgears


1

Preliminary checks
Bus-coupler breaker insertion / draw-out
Manual isolators closing and opening checks
Check of isolator locking devices
Check of breaker springs manual charging
Check of breaker opening and closing by electrical commands
Check of breaker interlocks and trip signals
Voltage transformers wiring check
Check internal wiring and cabling system

Current Transformers wiring check

Metering Instruments check (if any)


Make sure that protection relays are checked
Check of breaker status remote signals

Functionality check and test


Confirm that auxiliary service work properly
Confirm that electrical interlocks operate correctly
Confirm that all instrument, alarm and trip device operate correctly
Confirm that remote control circuits operate correctly
Check that the primary and secondary injection tests on all protective circuits prove that the relays and tripping
circuits operate correctly

P.3/5

N/A

Report No:

KAZ POWER PLANT


INSPECTION TEST REPORT

Date:

Checks and Tests of Instruments for Pre-Commissioning


Subcontractor:
Check that the ratio and polarity test on all current and voltage transformers with primary injection has been
performed correctly
Perform the calibration of direct relay
Confirm that phase rotation is correct
Check that anti-condensation heater operate correctly
All checks recommended by the supplier have been performed.
Record defects in the punch list report

Checks and Tests Description of each Switchgears


3

N/A

Electrical measurement
Measure insulation resistance of circuit breakers before AC applied voltage test (secondary side only).
A01
Result

U2V2

U2W2

V2W2

Note(*): Fill this form for each switchgears inside the switchboard
Note 1): Short-circuit non-tested windings and connect them to earthing network. Apply the Megger voltage for a period of 1 minute
between the tested winding and the earthing network.
Perform the AC applied voltage test
Tested phase
Result

L1L2,3 +E

L2L1,3+E

L3L1,2+E

Note2): Close all circuit breakers an apply the AC voltage for a period of 1 minute to the tested phase
Measure insulation resistance of circuit breakers after AC applied voltage test
A01
Result

U2V2

U2W2

Earthing System
Check the condition of the earthing bar and connections
Measure continuity between earthing bar of switchboard to main earth

P.4/5

V2W2

N/A

Report No:

KAZ POWER PLANT


INSPECTION TEST REPORT

Date:

Checks and Tests of Instruments for Pre-Commissioning


Subcontractor:

Test equipment data


Manufacturer

Remarks:

P.5/5

Model

Serial No.

Type

Range

Eng. Unit

Report No:

KAZ POWER PLANT


INSPECTION TEST REPORT

Date:

Checks and Tests of Instruments for Pre-Commissioning


Subcontractor:

P= Positive; N = Negative; N/A = Not Applicable;


Conform
INSPECTORS
Name:
Signature:
Date:

P.6/5

Not Conform
SUBCONTRACTOR

CONTRACTOR

CLIENT

AUTHORITY (if any)

Вам также может понравиться