Вы находитесь на странице: 1из 6

ITEM

QUANTITY METHOD

OUTPUT

PLANT

LABOUR

Mobile Crane
and lorry

2 labours

DURAT
ION

REFERENCE

SUSPENDED
BEAM
First floor

Formwork &
strutting

659m2

Reinforcement

Sawn formwork as
described to concrete
works to sides and soffit of
suspended beams

Hot rolled steel


reinforcement to B.S 4449
(Mild steel, minimum
yield seels 250 N per
sq.mm) to concrete works
generally, including all
cutting, bonding and
placing

Bill 3.2 - Frame


7 days

Bill 3.2 - Frame


Mobile Crane
and lorry

2 labours

Concrete mixer

2 labours

14 days

7664Kg
Concreting

71m3

Vibrated reinforced
concrete Grade 30

Bill 3.2 - Frame


5 days

Second floor
Formwork &
strutting
659m2

Reinforcement

Sawn formwork as
Mobile Crane
described to concrete
and lorry
works to sides and soffit of
suspended beams

Hot rolled steel


reinforcement to B.S 4449
(Mild steel, minimum
yield seels 250 N per
sq.mm) to concrete works
generally, including all
cutting, bonding and
placing

2 labours

Bill 3.2 - Frame


7 days

Bill 3.2 - Frame


Mobile Crane
and lorry

2 labours

Concrete mixer

2 labours

14 days

7664Kg
Concreting

71m3

Vibrated reinforced
concrete Grade 30

Bill 3.2 - Frame


5 days

Roof Beam
Formwork &
strutting

279m2
Sawn formwork as
described to concrete
works to sides and soffit of
roof beams

Reinforcement

1412Kg

Concreting

Lorry mounted

28m3

Hot rolled steel


reinforcement to B.S 4449
(High yield 60, minimum
yield stress 46 N per
sq.mm) to concrete works
generally, including all
cutting, bonding and
placing to roof beams

mobile crane

2 labours

6 days
Bill 3.2 - Frame

Lorry mounted
mobile crane

2 labours

7 days

Bill 3.2 - Frame

Vibrated reinforced
concrete Grade 30
Lorry mounted
mobile crane

2 labours

Bill 3.2 - Frame


28 days

UPPER FLOOR
First floor
1070m2
Formwork

Use and waste of sawn


formwork to soffit of
suspended slab
Mobile Crane
and lorry

Reinforcement

Steel fabric for the


reinforcement of concrete
to B.S.4482 including
150mm laps, bending
fabric, notching round
obstructions and placing
position
491m2

Concreting

161m3

2 labours

14 days

BRC A8
Bill 3.3 Upper
floor

Bill 3.3 Upper


floor

Mobile Crane
and lorry

2 labours

14 days

Concrete mixer

2 labours

8 days

Vibrated reinforced
concrete Grade 30 as
described 150mm thick
suspended slab
Bill 3.3 Upper
floor

Second floor
1070m2
Formwork

Use and waste of sawn


formwork to soffit of
suspended slab
Mobile Crane
and lorry

Reinforcement

Steel fabric for the


reinforcement of concrete
to B.S.4482 including
150mm laps, bending
fabric, notching round
obstructions and placing
position
491m2

Concreting

161m3

2 labours

14 days

BRC A8
Bill 3.3 Upper
floor

Bill 3.3 Upper


floor

Mobile Crane
and lorry

2 labours

14 days

Concrete mixer

2 labours

8 days

Vibrated reinforced
concrete Grade 30 as
described 150mm thick
suspended slab
Bill 3.3 Upper
floor

ROOF
Flat roof
32m2

Class F1 formwork finish


to soffit roof slabs

Formwork

Reinforcement

Concreting

82m2

6m3

Steel fabric for the


reinforcement of concrete
to B.S.4482 (yield strength
of 485 N per sq.mm),
including 150mm laps,
bending fabric, notching
round obstructions
(measured net and no
allowance made for laps)

Ready-made
concrete

2 labours

5 days

Bill 3.3 Roof

Ready-made
concrete

2 labours

4 days

Bill 3.3 Roof

Ready-made
concrete

2 labours

28 days

Bill 3.3 Roof

Vibrated reinforced
concrete Grade 30 as
described roof slabs,
exceeding 100mm but not
exceeding 300mm thick

Вам также может понравиться