SEMESTER I: 2014
Homework #8 CONNECTIONS
Optional: Submit before Nov. 14 for a bonus credit of 2%!
Use E250 steel (fy=250 MPa and fu=410 MPa)
All loads are unfactored unless stated otherwise.
Calculate the theoretical spacing of M12 high strength [class 8.8] bolts in bearing for the built-up beam
(IXX = 39289 cm4) which is to carry a concentrated factored load of 250 kN in the middle of a span at
mid-span as shown in figure.
ISLC 200 @
20.61 Kg/m
250 kN
y = 184.7 mm
8m
ISMB 450
Prob.#2
Prob.#3
Prob.#4
ISWB 300
ISHT 100
140
100
100
An ISHB 400 @ 82.2 kg/m column supports a concentric axial load of 300 kN and a moment of 125 kN
m in the plane of the web. Design a base plate and its connection to the column shaft. Also design the
anchor bolts, if required.