Вы находитесь на странице: 1из 60

CONTENTS

1.

OBJECTIVE

2.

TEST CODE

3.

TEST SCHEMATIC

4.

SELECTION OF INSTRUMENTS

5.

AGEING

6.

TOLERANCES

7.

FREQUENCY OF OBSERVATIONS

8.

DURATION OF TESTS

9.

ADVANCE PLANNING FOR THE TESTS

10.

PREPARING THE TG CYCLE FOR THE TESTS

11.

PRETEST SHUT DOWN ACTIVITIES

12.

INSTALLATION OF TEST INSTRUMENTS

13.

GENERAL GUIDE LINES

14.

INSTRUMENTS CALIBRATION AND CORRECTIONS

15.

ITEMS ESSENTIAL FOR AGREEMENT

16.

PROGRAMME OF TESTING

17.

PRESERVATION OF TEST FLOW ASSEMBLIES

18.

CONDITION AND CYCLE ISOLATION OF THE PLANT

19.

POST TEST ACTIVITIES

1.0

OBJECTIVE

The Performance Guarantee Tests on Khaperkheda Thermal Power Project, unit # 3 & 4 210 MW TG
shall be carried out to prove the Guaranteed Heat Rate and Output of the TG Set.
This Procedure has been prepared to carry out the tests at site as mentioned above for the following
conditions.
S.No.
A
01.

Guarantee Conditions

Guarantee Values

TG PACKAGE
Gen. Output at rated throttle pressure & temp with
condenser backpressure of 67 mm of Hg (abs) at
rated turbine parameters.

210 MW

02.
03.

Heat rate at 210 MW load. 30.5 deg C cooling water


temp. with 67 mm of Hg (abs) condenser back
pressure and 0% make up
Auxiliary power consumption
- Boiler feed pumps 2 x 50 %

B.

- Condensate pumps 1 x 100 %


- excitation system
Vapour exhaust fan
Vacuum pumps
Lube oil system
Generator seal oil system
OTHER BHEL

1939 .3 Kcal/Kwh

5320 Kw
Total Aux. Power

440 Kw

5950 Kw.
190 Kw

1260.7 Kw. Per

MANUFACTURED PACKAGES

Pump.

CW pump power (2 pumps)

Aux. Power Consumption of all aux. Mentioned above (sr. no. 3) will be measured during PG

test with 67 mm of Hg (abs) condenser backpressure and 0% make up. Excitation Power shall be
measured with plant instruments. HT Aux. Will be measured with DPM/Power Transducers and LT
Aux. Will be measured with clamp on meter.

2.0

TEST CODE

The HEAT RATE Tests shall be carried out in line with the recommendations of ASME PTC-6, 1976 Test
Code and in line with approved Document No. PE-4-183-100-211 Rev. 05 for method for computation
of Heat Rate.
3.0

TEST SCHEMATIC

The approved test scheme titled PERFORMANCE GUARANTEE TEST INSTRUMENTATION SCHEME, NO.
PE-3-183-100-210 REV. 02 shall be used.
4.0

SELECTION OF INSTRUMENTS

The instruments meeting accuracy requirements, as specified in ASME-PTC-6 1976 TEST CODE shall
be used.
Instruments selected and proposed to be used shall be as per the TG PG TEST INSTRUMENTATION
SCHEME/LIST which specifies the type of instruments and their ranges etc.
The brief details of the instruments to be used during the P.G. Test are

S.No.

PARAMETER TO BE

RANGE

MEASURED

MEASURING
INSTRUMENT

01.

Differential pressure

0-2.5 Kg/Sq. Cm

Transmitters

02.

Pressure

0-250 Kg/Sq. Cm

Transmitters

03.

Cond. Back Pressure

0-780 mm Hg.

Transmitters

03.

Temperature

0-300 Deg. C

PRT - 100

04.

Temperature

300-600 Deg. C

K Type T.C.

05.

Generator Power

0-1000 Watts.

Digital Power mete

0-5 Amps.
0-65 Volts.
06.

Speed

0-1000 rpm

Non contact type


Tachometer

5.0

AGEING

If the test is carried out after 4 months of the date of first commissioning, due to any reason what so
ever, the specific heat consumption shall be increased by following amounts for each month or part of
a month by which the period between the initial commissioning and the acceptance test exceeds 4
months.
0.01% for the following 8 months
0.06% for the period there after.
6.0

TOLERANCES

The tolerances on results shall be computed based on uncertainty/inaccuracy of the measuring


instruments used during PG test.
7.0

FREQUENCY OF OBSERVATIONS

It will be carried out as per ASME-PTC-6 which is briefly given below.


Heat rate and output test observations from indicating and differential measurement for primary flow
shall be made at intervals not greater than 1 minute. Other important measurements shall also be
made at not greater than 1-minute interval. Hot well and D/A levels shall be read at intervals not
exceeding 5 minutes.
8.0

DURATION OF TESTS

As per ASME-PTC-6, tests shall be carried out at a steady state run of minimum 2 hours duration.
However duration will be mutually decided, depending upon the conditions prevailing during
conductance of P.G. Tests, Minimum two test for heat rate at 100% MCR and one for output test shall
be conducted.
9.0

ADVANCE PLANNING FOR THE TEST

9.01 During the pretest unit commissioning/erection period, every effort shall be made by BHEL to
ensure the provision of all test tapping points as per test scheme. BHEL shall inform to MSEB in
advance for any missing point measurement which is not possible to be used due to unavoidable
reasons and mutually agreed upon. Minimum two tests for heat rate at 100% MCR and one for output
test shall be conducted.
9.02 Welded type thermowells shall be used by BHEL for temperature measurement on all critical
high temperature lines. These thermowells shall remain permanently installed on the pipe lines.
9.03 Screwed type thermowells shall be used in low pressure lines (pressure less than 40 ata) for
temperature measurement and shall be installed in the unit, just prior to the test. For these
thermowells, matching stub with suitable plug will be provided in the engineering stage itself. In case
these thermowells are found missing then these are to be obtained from the respective unit and
supplied & installed during erection stage itself.
9.04 All the pressure test tappings as mentioned in PG Test Instrumentation Scheme No. PE-3-193100-210 Rev. 02 are supplied with single or double root valves depending upon the pressure rating of
the pipe lines. They are supplied by BHEL piping centre in line with the erection drawings released for
construction. In case some of the pressure tappings are not available, the same shall be provided or
alternatively, either a T-off shall be taken from the operational tapping point or operational point

shall be used, as mutually agreed. Impulse pipe of suitable size shall be laid during pretest
preparations. The pressure lines will be strong enough to withstand any type of vibrations and will
have uniform gradient.
9.04a For Pressure and temperature tapping points in case not available/constraint in its use is
observed before the commencement, alternate operational points will be used after mutual
agreement.
9.05 Test CTs and PTs (MSEB scope) of 0.2 accuracy class are to be provided by BUS DUCT
supplier. The installation and/or test data for ratio and phase angle errors at different VA burdens and
power factors shall be provided by.
MSEB for accurate power calculations. Additionally test certificates giving the above
information, as submitted by the generator bus duct supplier shall also be arranged by MSEB.
9.06 CT terminals should be provided with termination arrangement for shorting or opening links.
Effects of connecting leads shall be neutralized in power calculations by measuring voltage drop
across PT terminals and measuring point.
9.07 It has to be checked during erection stage that no pipeline or installation etc. Fouls the test
tapping. Test temperature element are 450 mm along. Enough space should be available for each
tapping point so that the test temperature elements can be inserted without any difficulty. In case of
any obstruction an alternate test stub is to be provided as per point No. 9.02 & 9.03 if possible.
9.08
link.

Test CTs & PTs terminals to be brought to UCB panel. CT terminals be provided with shorting

10.0

PREPARING THE TG CYCLE FOR THE TEST

Efforts are to be made to ensure that all the TG systems/equipments are brought into service within
reasonable period of the first synchronisation and trial run should also be completed by this period.
Normally with the increase in running hours, salt deposits take place and also turbine clearances
change. This deteriorates the turbine performance and thus the test should be conducted preferably
within four months after first synchronisation.
The unit readiness for conducting the PG Tests is to be ensured as per the checklist.
10.01 To ensure that all LP & HP heaters are in normal operation and drips of these heaters are
cascaded properly as per the cycle. It is to be checked that there is no by passing of the drips either
to condenser or to deaerator and this is to be ensured for sufficient time before actual
commencement of the test.
10.02 To check that there should not be any leakage in the tubes of HP & LP heaters tubes.
10.03 To ensure the cleanliness of condenser tubes and to get the same cleaned if required during
the shut down prior to the tests.
10.04 To ensure that the machine is able to run on orie vacuum pump only. Further the vacuum
obtained with this running pump should preferably be nearer to the design value.
10.05 To ensure that pressure of Main Steam First Stage, Cold Reheat. Hot Reheat Extractions to
various heaters and condenser back pressure are near the design values at 210 MW load.
10.06 To ensure that the test flow assembly is available at site with all its matching flanges and
fasteners.
10.07 To ensure that the CW pressure drop across the inlet and outlet of the condenser is within the
design figure and there is no tube leakage in condenser. Conductivity and Oxygen content at
condenser hot well should also be within the prescribed limits.
10.08 To ensure the cleanliness of the E.S.V. and I.V. strainers. In case of the excessive pressure
drop, same should be cleaned.
10.09 To ensure that the unit is capable of attaining and maintaining the full load design parameters

i.e. Main Steam pressure and temperature, Hot Reheat temperature and Condenser Back Pressure.
10.10 To ensure that all the local gauge glasses of the condenser, hot well deaerator and HP & LP
heaters are working and are clean and visible. There should not be any gauge glass leakage.
10.11 To ensure that there is adequate light to observe the levels at all places where the operators
will log the test readings.
10.12 A system tightness check i.e. Deaerator Drop Test shall be done by keeping the
interconnection on steam and load side isolated and also by closing the make-up inlet and by keeping
the CBD, EBD, SOOT Blowing and steam supply to fuel oil heating, atomisation etc. shut off. The
deaerator level is to be raised to the maximum permissible before this exercise. Fall in deaerator
level i.e. system losses are then to be observed and calculated. It is to be ensured that the unit is
able to run in the above condition for at least three hours. The problem if any, is to be rectified and
the efforts shall be made to bring down the system unaccounted leakage.
10.13 To ensure the availability of coal in sufficient quantity so that the machine may be loaded to
full load for any desired interval of time and the constancy of test conditions may be attained as per
ASME-PTC-6 code.
10.14 To ensure the tightness of the system, steam/feed & condensate drain line valves connected to
turbine flash tank for non passing as per the designed heat and mass balance diagram.
10.15 To ensure the availability of all tapping as per test scheme. This includes tapping points for
individual equipment performance which may not be required for contractual tests.
10.16 To ensure that the HP & LP Bypass valves to the condenser are not passing.
10.17 To ensure the availability of all the BFPs, CEPs, CWPs coal mills, ID, FDA PA fans etc. so that
there is no constraints in achieving and maintaining full load for at least 8 hrs. a day.
10.18 To ensure tightness of the vales as per the design heat & mass balance. For this purpose a
specific list of isolation of valves & systems bearing valve numbers shall be prepared in advance of
test.
11.0

PRETEST SHUT DOWN ACTIVITIES

After it is ensured that the unit is ready for the test, a suitable shut down shall have to be agreed
between BHEL and MSEB. BHEL shall then supply the calibrated test instruments, prior to the start of
the shut down. Major activities to be carried out during this shut down shall be as follows.
11.01 Mounting/installing missing screw type thermowells, test flow assembly, provision for T-off
and laying of
impulse pipe lines etc.
11.02 Providing any additional test tapping points if found necessary/applicable/missing.
11.03 Necessary arrangement/rectification for meeting the system requirements.
11.04 Necessary arrangement/rectification for meeting the requirement of system isolation i.e.
attending the defective/passing valves identified during the joint inspection before shut down. To this
effect, a list of valves to be kept closed during the test shall be jointly finalised with MSEB, prior to
the test and the system shall be isolated as per this list.
11.05 In case of prolonged operation, if necessary the internals of the turbine shall be checked for
its cleanliness.
11.06 The demagnetisation of test PTs and CTs will be carried out.
11.07 Mounting of temperature elements in identified hot areas and laying their cables.
11.08 Laying impulse pipe line (if not already laid) from the root valves in hot zones and terminating
with isolating valves. Their root valves to be kept open.

11.09 Condenser tube cleaning and condenser air tightness checks to be done and leakages to be got
attended.
12.0

INSTALLATION OF TEST INSTRUMENTS (ASME-PTC-6)

12.01 FLOW MEASURING DEVICES


In most of the places spool pieces are not provided in the pipelines, location is only indicated on the
isometric pipeline drawings. Spool pieces are to be made at site, in case the flow measuring
assemblies along with the matching flanges are supplied during erection stage itself. Otherwise, the
pipeline is to be cut as per the marked location and flanges along with flow assemblies are be
mounted during the shutdown. Flow measuring assembly device in any case is to be mounted during
the shutdown prior to the test so that these are not in use for longer duration prior to the test.
Flow measuring devices are to be mounted during the shut down prior to the test so that the same is
not in use for longer duration prior to the test.
Correct installation of flow assembly as per requirement is to be ensured and installation arranged by
BHEL in pretest shut down. It is preferable to check the impulse pipe line connections after
installation for any leakage/choking etc. by pressurising the flow measuring device to the extent
possible during the unit shut down itself. For flow orifice in the condensate line to deaerator, the
system can be checked by running the condensate pump. Problem noticed if any has to be attended
during the shut down itself.
12.02 TEMPERATURE MEASURING INSTRUMENTS
Chromel Alumel thermocouples and Platinum Resistance Thermometers elements will be used for
temperature measurements. After connecting extension leads (Compensating cable for TCs and lead
wires for PRTs), these elements will be mounted into thermowells as per the instrument allocation
list. Thermocouple wire is to be connected such that Chromel portion of the extension lead is
connected to Chromel part of the sensor. To identify this a positive sign has been marked on each
Chromel terminal.
Thermocouples, PRTs and transmitter out put shall be measured with precision Data Logger of
accuracy 0.03%.
12.03 PRESSURE MEASURING INSTRUMENTS
Impulse pipe lines are to be laid for the Pressure Transmitters.
Impulse pipe lines for the vacuum (negative pressure) measurement points should be laid such
that
transmitter is mounted above the tapping point. Thus the line should be laid upwards.
All the impulse lines should be rigid enough to avoid any vibration in the instrument.
For height correction in pressure measuring points the vertical distance from the center of the
transmitter to the tapping point is to be measured for each tag number and joint protocol to be
signed. The distance above the tapping point is taken as positive whereas same below the tapping
point is taken as negative for pressure correction.
The impulse pipe lines are to be flushed/purged sufficiently and steam to be allowed to condense
before mounting the transmitters.
A transmitter/gauges will be charged only before use, otherwise it should be kept isolated to avoid its
exposure to vacuum in case the unit trips.
12.04 POWER MEASURING INSTRUMENTS
CTs and PTs for P.G. Test use should be identified well in advance and locations of their terminals in
panels checked for connection of the power meters refer the generator schematic drawings.
The CTs and the PTs should be damagnetised during the shut down and it should be ensured that no
protection relay is connected in their circuit during the P.G. Test.

The lead resistance voltage drop in the circuit of PTs shall be measured along with MSEB
representative and protocol for the same made before starting the P.G. Test.
The digital power meter will be connected to the identified CTs and PTs terminals preferably in three
phase four wire mode.
12.05 LEVEL MEASUREMENT
Level measurements of all the storage tanks shall be noted by means of local gauge glass level
indicators equipped with metric scales. It shall be ensured before carrying out the test, that the level
indicators are in good working condition. Readings are to be recorded on the Data Sheet sample
enclosed.
Apart from it, the Control Room readings for levels of all storage tanks shall also be additionally
recorded for reference.
13.0

GENERAL GUIDE LIENS

13.01 All electrical instruments should be placed away from any magnetic field. Their proper leveling
should also be ensured.
13.02 If felt necessary, the mounting adjustable coupling can be removed and in that case T/Cs PRTs
should be properly tied and pressed downward with a piece of wire. Stub projections and sensor
stems, which are protruding out of thermowells should be covered with asbestos rope for providing
thermal insulation.
13.03 Demagnetisation of CTs.

Any of the following two methods may be employed.


13.03a Short circuit the secondary through a 3C ohms resistor of sufficient current capacity and
gradually increase the primary alternating current to full rated value. After this gradually reduce it to
zero.
13.03b With the primary open circuit, gradually increase the alternating current through the
secondary to 5/1Amp. After this gradually reduce it to zero. In case of voltage transformer case
should be taken to avoid short circuit of secondary.
13.04 All the instruments should be stored in a clean dry place nearer to unit under test, preferably
at Turbine Floor.
13.05 Tags giving Tag No., Serial No. and Service etc. should be provided at both tapping point end
and the instrument end.
13.06 All the Pressure Transmitters gauges/differential manometer/kenometer/U tube manometer
should be mounted in vertical position.
13.07 Depending upon the likelihood of completion of the above activities a date is finalised for the
conductance of P.G. Tests. BHEL representative shall then commission all the instruments and conduct
the tests jointly with MSEB under mutually agreed conditions.
14.0

INSTRUMENTS CALIBRATION AND CORRECTION

14.01 All the test instruments except Pressure Transmitters shall be duly calibrated at recognised
Test Houses.
14.02 The calibration certificates shall be furnished to MSEB before dispatching the instruments to
site.
14.03 Pressure Transmitters reading shall be additionally corrected for height corrections by
measuring the difference in levels between center of the transmitter & center of pipeline.
14.04 Pressure Transmitters shall be calibrated at site by BHEL Engineer before the conductance of
the tests in the presence of MSEB representative and the calibration certificates shall be jointly

signed.
14.05 Correction due to actual mercury density and actual barometric pressure shall also be applied
wherever applicable.
15.0

ITEMS ESSENTIAL FOR AGREEMENT

15.01 Nomination of coordinating Test Engineers from MSEB and BHEL.


15.02 The programme and the dates of the series of tests. In accordance with this programme, all
the test instruments shall be transported to site.
15.03 Suitable shut down required prior to test to carry out the preparatory activities.
15.04 Means for obtaining steady operating parameters at their rated values.
15.05 Deputation of adequate qualified personnel by MSEB to note down the test readings for which
exact number will be intimated to them well in advance.
15.06 Submission of drawings/information, as required and intimated by BHEL in advance for the non
BHEL scope of equipment.
15.07 Provision of T & P by customer like compressed air, welding sets, power supply etc.
15.08 Provision of illumination at all measuring junctions and working places by MSEB.
16.0

PROGRAMME OF TESTING

16.01 The completion of test preparations, mounting of instruments and isolation of thermal cycle
are to be checked before start of test.
16.02 The load is raised to rated capacity at rated parameters for taking a set of trial readings of all
instruments and for aquatinting the observers with the operation of instrument. All observers shall be
allotted with their respective junctions and shall note down the readings on the prescribed logsheets
to be supplied by BHEL.
16.03 The readings of the trial test are analysed. If the results differ much from the design values,
the case is to be investigated and rectification to be carried out wherever required. To this effect, it is
essential that the load is maintained at rated values. The mock test can be repeated until the results
are satisfactory. Then the time for test can be mutually decided.
16.04 During the trial test, it is checked that all the instruments are functioning/indicating properly
and verified wherever necessary. The pressure transmitters are isolated after the trial test.
16.05 The load is raised to rated capacity at rated parameters at least one hour before the start of
the test and the parameters shall be maintained constant throughout the test.
16.06 The system is isolated so that no unaccounted flow goes out of comes into cycle. The makeup
quantity shall be measured by noting down the various storage tanks levels at regular intervals of the
test.
16.07 Consistency of the load shall be accomplished by load limiter. Once the control valves have
been set, they shall be left undisturbed throughout the test.
16.08 The operations which shall not be carried out during the test which are to be isolated are for
the following which the isolations are to be carried out.

Soot Blowing
Continuous Blow Down.
Dusting of the Associated Boiler Unit.
Steam Supply to fuel Atomisation.
Fuel Heating and SCAPH
Chemical dozing.
Water and Steam Sampling etc.

16.09 PRDS control valve spindle cooling water, atmospheric valve gland sealing water flow shall be
adjusted for minimum flow.
16.10 Proper sealing water supply to vacuum system specially to atmospheric valve seals shall be
ensured.
16.11 All efforts shall be made to maintain the parameters constant throughout the test.
16.12 After the preparations have been completed, the test shall be started by synchronising the
watches of the observers with that of the control room.
16.13 The test readings shall be logged in the data logger and manual readings shall be noted down
in the prescribed log sheets in triplicate, which shall be signed by the observers and countersigned by
MSEB and BHEL at the end of the tests.
16.14 One set of the test readings shall be handed over to MSEB and two sets shall be retained by
BHEL for their analysis at their works.
16.15 Sensitivity of the condenser hot well level control shall be reduced or preferably the level be
controlled manually to avoid excessive fluctuation in the condensate flow to Dearator.
17.0

PRESERVATION OF TEST FLOW ASSEMBLIES

PG test low measuring assemblies for measurement of test flow are normally supplied directly to
site assembled condition in 2 halves. Flow measurement is an important measurement which effects
the PG Test results appreciably.
A minor dent on the sharp edge of the orifice or on its plain surface or on the inside surface of the
flow nozzle causes a large inaccuracy in flow measurement. Thus orifice plates/nozzles should never
be hung with a wire or a rope passing through their inner bore which may cause dent on them. Even
the adjoining pipe pieces encompassing the orifices/nozzles, which are normally machined from
inside, should be carefully handled during installation. In all cases these assemblies should be stored
in covered shed and protected from corrosion as any roughness on them may add to inaccuracy.
In view of above, it is needless to emphasize the importance of proper preservation of these
assemblies.
Also flow measuring assemblies received in assembled condition, should not be dismantled as it is
calibrated before supply. Dismantling may affect its calibration.
18.0

CONDITION AND CYCLE ISOLATION OF THE PLANT

Before starting the performance test the plant has to be in a good state. To be familiar with the plant
during operation and for finding out deficiencies, if any and for checking of all the measuring
instruments, customer has to allow pretests with the plant.
It is sufficient that the whole plant cycle is provided as presumed in the guarantee agreement. All
cross connections to other units must be closed and all drainages must be ensured absolutely tight.
Piping which are not utilized they have to be blanked off or it not possible they have to be checked
for tightness.
A special care will be used in isolating test cycle from any connection extraneous to the test, whether
inside or outside the unit. These shall be attended in case founding passing.
The following is the general list of the lines and the unit component that will be isolated or put out of
service during test. A specific list of isolation of valves & systems bearing valve numbers for each
valve shall be prepared in advance of the test which shall be used during performance testing.
All the LP turbine by pass
Make up line
Auxiliary steam header
Turbine sprays
Drain lines on stop intercept and control valves

Common units header not fed


Auxiliary boiler steam line
Steam to air Preheaters
Condensate chemical injection
Feedwater chemical injection
Steam generator vents
Steam generator soot blowers
Condensate and feed water flow by passing heaters
Heater drain by pass
Heater shell drains
Heater water box vents
Water lines for water washing the turbine
Steam Generator blowdowns
Emergency blow down valve
Main steam line to SSR
Dearator overflow line
The following lines will be throttled to a minimum
Dearator vents
The water sampling equipment flows will be measured by Weighing if any.
The water level in the feed water tank and in the condenser have to be watched and all changes to be
considered by making the quantity balance.
Before starting the performance test all items which could influence the result of the test have to be
brought into steady state. This has to be kept for the whole test.
19.0

POST TEST ACTIVITIES


A shut down of the unit is to be arranged for removing flow measuring assembly.

TG-PG TEST INSTRUMENTATION LIST


PRESSURE POINTS
Sr. No.

Tag

Service

Instrument

Accuracy

Range

No.
1

P201

MS BEF. STRAINER (L)

PR. TRANS.

0.1%

0-250Kg./Sq.Cm.

P202

HRH AFT. STRAINER (L)

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

P203

MS BEF. STRAINER (R)

PR. TRANS.

0.1%

0-250Kg./Sq.Cm.

P204

HRH AFT. STRAINER (R)

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

P205

1st STAGE PR.

PR. TRANS.

0.1%

0-250Kg./Sq.Cm.

P206

FFW AT ECO. INLET

PR. TRANS.

0.1%

0-250Kg./Sq.Cm.

P207

HP EXHAUST (TE)

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

P208

HRH TO IPT BEF. STRAINER

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

(L).
9

P209

CRH AFT. RH SPRAY (R).

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

10

P210

HRH TO IPT BEF. STRAINER

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

(R).
11

P211

CRH AFT. RH SPRAY (L).

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

12

P212

MS TO APRDS

PR. TRANS.

0.1%

0-250Kg./Sq.Cm.

13

P213

APRDS SPRAY

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

14

P214

EXTN. TO HPH-6 (HE)

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

15

P215

FW HPH-6 INLET

PR. TRANS.

0.1%

0-250Kg./Sq.Cm.

16

P216

FW HPH-6 OUTLET

PR. TRANS.

0.1%

0-250Kg./Sq.Cm.

17

P218

HPH-6 DRIP TO HPH-5

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

18

P219

EXTN. TO HPH-5 (TE)

PR. TRANS.

0.1%

0-25Kg./Sq.Cm.

19

P220

EXTN. TO HPH-5 (HE)

PR. TRANS.

0.1%

0-25Kg./Sq.Cm.

20

P221

FW HPH-5 INLET

PR. TRANS.

0.1%

0-250Kg./Sq.Cm.

21

P222

FW HPH-5 OUTLET

PR. TRANS.

0.1%

0-250Kg./Sq.Cm.

22

P223

HPH-5 SHELL PR.

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

23

P225

BFP-A DISCHARGE

PR. TRANS.

0.1%

0-250Kg./Sq.Cm.

24

P226

BFP-B DISCHARGE

PR. TRANS.

0.1%

0-250Kg./Sq.Cm.

25

P227

BFP-C DISCHARGE

PR. TRANS.

0.1%

0-250Kg./Sq.Cm.

26

P229

SH SPRAY PR.

PR. TRANS.

0.1%

0-250Kg./Sq.Cm.

27

P230

RH SPRAY PR.

PR. TRANS.

0.1%

0-250Kg./Sq.Cm.

28

P231

CRH BEF. RH SPRAY (L)

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

29

P232

CRH BEF. RH SPRAY (R)

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

Instrument

Accuracy

PRESSURE POINTS
Sr. No.

Tag No.

Service

Range

P102

IPT EXHAUST (L)

PR. TRANS.

0.1%

0-10Kg./Sq.Cm.

P104

IPT EXHAUST (R)

PR. TRANS.

0.1%

0-10Kg./Sq.Cm.

P105

LPT INLET (L)

PR. TRANS.

0.1%

0-10Kg./Sq.Cm.

P106

LPT INLET (R)

PR. TRANS.

0.1%

0-10Kg./Sq.Cm.

P107

EXTN. TO D/A (TE)

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

P108

EXTN. TO D/A (DE)

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

P109

D/A SHELL PR.

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

P110

BFP-A SUCTION

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

P111

HPH-5 DRIP TO D/A (HE)

PR. TRANS.

0.1%

0-60Kg./Sq.Cm.

10

P112

EXTN. TO LPH-3 (TE)

PR. TRANS.

0.1%

0-10Kg./Sq.Cm.

11

P113

EXTN. TO LPH-3 (HE)

PR. TRANS.

0.1%

0-10Kg./Sq.Cm.

12

P114

EXTN. TO LPH-2 (HE)

PR. TRANS.

0.1%

0-10Kg./Sq.Cm.

13

P115

EXTN. TO LPH-2 (HE)

PR. TRANS.

0.1%

0-10Kg./Sq.Cm.

14

P116

EXTN. TO LPH-1 (TE)

PR. TRANS.

0.1%

0-780mm. Hg.

15

P117

EXTN. TO LPH-1 (TE)

PR. TRANS.

0.1%

0-780mm. Hg.

16

P118

EXTN. TO LPH-1 (TE)

PR. TRANS.

0.1%

0-780mm. Hg.

17

P119

STEAM TO GSC

PR. TRANS.

0.1%

0-10Kg./Sq. Cm.

18

P120

LP BYPASS (R)

PR. TRANS.

0.1%

0-60Kg./Sq. Cm.

19

P121

LP BYPASS (L)

PR. TRANS.

0.1%

0-60Kg./Sq. Cm.

20

P122

CEP SUCTION

PR. TRANS.

0.1%

0-780mm. Hg.

21

P123

CEP DISCHARGE

PR. TRANS.

0.1%

0-25Kg./Sq. Cm.

22

P124

CONDENSATE NEAR FE.

PR. TRANS.

0.1%

0-10Kg./Sq. Cm.

23

P125

APRDS AFT.

PR. TRANS.

0.1%

0-25Kg./Sq. Cm.

DESUPERHEATER
24

P126

25

P127

26

P128

27

P129

28

CW DIFF. PR. AT COND-A

DP. TRANS.

0.1%

0-2.5Kg./Sq. Cm.

CW DIFF. PR. AT COND-B

DP. TRANS.

0.1%

0-2.5Kg./Sq. Cm.

P130

CONDENSER VACUUM

PR. TRANS.

0.1%

0-780mm. Hg.

29

P131

CONDENSER VACUUM

PR. TRANS.

0.1%

0-780mm. Hg.

30

P132

CONDENSER VACUUM

PR. TRANS.

0.1%

0-780mm. Hg.

31

P133

CONDENSER VACUUM

PR. TRANS.

0.1%

0-780mm. Hg.

32

P134

CONDENSER VACUUM

PR. TRANS.

0.1%

0-780mm. Hg.

33

P135

CONDENSER VACUUM

PR. TRANS.

0.1%

0-780mm. Hg.

34

P136

BFP-B SUCTION

PR. TRANS.

0.1%

0-10Kg./Sq. Cm.

35

P139

CEP SUCTION

PR. TRANS.

0.1%

0-780mm. Hg.

36

P140

BFP-C SUCTION

PR. TRANS.

0.1%

0-10Kg./Sq. Cm.

37

P141

DC INLET

PR. TRANS.

0.1%

0-25Kg./Sq. Cm.

Instrument

Accuracy

FLOW POINTS
Sr. No.

Tag No.

Service

Range

F101A

MAIN CONDENSATE

DP. TRANS.

0.1%

0-2.5Kg./Sq.Cm.

F101B

MAIN CONDENSATE

DP. TRANS.

0.1%

0-2.5Kg./Sq.Cm.

F102A

RH SPRAY

DP. TRANS.

0.1%

0-2.5Kg./Sq.Cm.

F102B

RH SPRAY

DP. TRANS.

0.1%

0-2.5Kg./Sq.Cm.

F103A

SH SPRAY

DP. TRANS.

0.1%

0-2.5Kg./Sq.Cm.

F103B

RH SPRAY

DP. TRANS.

0.1%

0-2.5Kg./Sq.Cm.

Instrument

Accuracy

TEMPERATURE POINTS
Sr. No.

Tag No.

Service

Range

T101

MS BEF. STRAINER (L)

T/C

1/2 DIN

250-550 Deg. C

T102

MS BEF. STRAINER (L)

T/C

1/2 DIN

250-550 Deg. C

T103

MS BEF. STRAINER (R)

T/C

1/2 DIN

250-550 Deg. C

T104

MS BEF. STRAINER (R)

T/C

1/2 DIN

250-550 Deg. C

T105

CRH AFTER SPRAY (L)

T/C

1/2 DIN

250-550 Deg. C

T106

CRH AFTER SPRAY (R)

T/C

1/2 DIN

250-550 Deg. C

T107

EXTN TO HPH-6 (TE)

T/C

1/2 DIN

250-550 Deg. C

T108

EXTN TO HPH-6 (TE)

T/C

1/2 DIN

250-550 Deg. C

T109

HRH BEF. STRAINER (L)

T/C

1/2 DIN

250-550 Deg. C

10

T110

HRH BEF. STRAINER (L)

T/C

1/2 DIN

250-550 Deg. C

11

T111

HRH BEF. STRAINER (R)

T/C

1/2 DIN

250-550 Deg. C

12

T112

HRH BEF. STRAINER (R)

T/C

1/2 DIN

250-550 Deg. C

13

T114

IPT EXHAUST (L)

T/C

1/2 DIN

250-550 Deg. C

14

T116

IPT EXHAUST (R)

T/C

1/2 DIN

250-550 Deg. C

15

T117

LPT INLET (L)

T/C

1/2 DIN

250-550 Deg. C

16

T118

LPT INLET (L)

T/C

1/2 DIN

250-550 Deg. C

17

T119

LPT INLET (R)

T/C

1/2 DIN

250-550 Deg. C

18

T120

LPT INLET (R)

T/C

1/2 DIN

250-550 Deg. C

19

T121

MS TO APRDS

T/C

1/2 DIN

250-550 Deg. C

20

T122

SPRAY TO APRDS

PRT Pt-100

1/2 DIN

250-550 Deg. C

21

T123

EXTN. TO HPH-6 (HE)

T/C

1/2 DIN

250-550 Deg. C

22

T124

EXTN. TO HPH-6 (HE)

T/C

1/2 DIN

250-550 Deg. C

23

T125

FW HPH-6 INLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

24

T126

FW HPH-6 INLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

25

T127

FW HPH-6 OUTLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

26

T128

FW HPH-6 OUTLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

27

T131

HPH-6 DRIP TO HPH-5

PRT Pt-100

1/2 DIN

0-300 Deg. C

28

T132

HPH-6 DRIP TO HPH-5

PRT Pt-100

1/2 DIN

0-300 Deg. C

29

T133

EXTN. TO HPH-5 (HE)

T/C

1/2 DIN

250-550 Deg. C

30

T134

EXTN. TO HPH-5 (HE)

T/C

1/2 DIN

250-550 Deg. C

31

T135

EXTN. TO HPH-5 (HE)

T/C

1/2 DIN

250-550 Deg. C

32

T136

EXTN. TO HPH-5 (HE)

T/C

1/2 DIN

250-550 Deg. C

33

T137

FW INLET TO HPH-5

PRT Pt-100

1/2 DIN

0-300 Deg. C

34

T138

FW INLET TO HPH-5

PRT Pt-100

1/2 DIN

0-300 Deg. C

35

T139

FW HPH-5 OUTLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

36

T140

FW HPH-5 OUTLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

37

T141

EXTN. TO D/A (TE)

T/C

1/2 DIN

250-550 Deg. C

38

T142

EXTN. TO D/A (TE)

T/C

1/2 DIN

250-550 Deg. C

39

T143

EXTN. TO D/A (DE)

T/C

1/2 DIN

250-550 Deg. C

40

T144

EXTN. TO D/A (DE)

T/C

1/2 DIN

250-550 Deg. C

41

T145

FFW AT ECO. INLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

Instrument

Accuracy

TEMPERATURE POINTS
Sr. No.

Tag No.

Service

Range

46

T146

FFW AT ECO. INLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

47

T147

SH SPRAY

PRT Pt-100

1/2 DIN

0-300 Deg. C

48

T148

RH SPRAY

PRT Pt-100

1/2 DIN

0-300 Deg. C

49

T149

BFP-A DISCHARGE

PRT Pt-100

1/2 DIN

0-300 Deg. C

50

T150

BFP-B DISCHARGE

PRT Pt-100

1/2 DIN

0-300 Deg. C

51

T151

BFP-C DISCHARGE

PRT Pt-100

1/2 DIN

0-300 Deg. C

52

T152

HP BYPASS AFT.HPB VAL. (R)

T/C

1/2 DIN

250-550 Deg. C

53

T153

HP BYPASS AFT.HPB VAL. (L)

T/C

1/2 DIN

250-550 Deg. C

54

T154

CRH BEF. SPRAY (R)

T/C

1/2 DIN

250-550 Deg. C

55

T155

CRH BEF. SPRAY (R)

T/C

1/2 DIN

250-550 Deg. C

56

T156

CRH BEF. SPRAY (L)

T/C

1/2 DIN

250-550 Deg. C

57

T157

CRH BEF. SPRAY (L)

T/C

1/2 DIN

250-550 Deg. C

TEMPERATURE POINTS

Sr. No.

Tag No.

Service

Instrument

Accuracy

Range

T201

LPT EXHAUST (R) (TE)

PRT Pt-100

1/2 DIN

0-300 Deg. C

T202

LPT EXHAUST (L) (TE)

PRT Pt-100

1/2 DIN

0-300 Deg. C

T203

LPT EXHAUST (R) (COND.E)

PRT Pt-100

1/2 DIN

0-300 Deg. C

T204

LPT EXHAUST (L) (COND.E)

PRT Pt-100

1/2 DIN

0-300 Deg. C

T205

EXTN. TO LPH-3 (TE)

PRT Pt-100

1/2 DIN

0-300 Deg. C

T206

EXTN. TO LPH-3 (TE)

PRT Pt-100

1/2 DIN

0-300 Deg. C

T207

EXTN. TO LPH-3 (HE)

PRT Pt-100

1/2 DIN

0-300 Deg. C

T208

EXTN. TO LPH-3 (HE)

PRT Pt-100

1/2 DIN

0-300 Deg. C

T209

LPH-3 DRAIN TO LPH-2

PRT Pt-100

1/2 DIN

0-300 Deg. C

10

T210

LPH-3 DRAIN TO LPH-2

PRT Pt-100

1/2 DIN

0-300 Deg. C

11

T211

LPH-3 INLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

12

T212

LPH-3 OUTLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

13

T213

LPH-3 O/L D/S OF BP VALVE

PRT Pt-100

1/2 DIN

0-300 Deg. C

14

T214

EXTN. TO LPH-2 (TE)

PRT Pt-100

1/2 DIN

0-300 Deg. C

15

T216

EXTN. TO LPH-2 (HE)

PRT Pt-100

1/2 DIN

0-300 Deg. C

16

T217

EXTN. TO LPH-2 (HE)

PRT Pt-100

1/2 DIN

0-300 Deg. C

17

T218

LPH-2 DRAIN TO LPH-1

PRT Pt-100

1/2 DIN

0-300 Deg. C

18

T219

LPH-2 DRAIN TO LPH-1

PRT Pt-100

1/2 DIN

0-300 Deg. C

19

T220

LPH-2 OUTLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

20

T221

LPH-2 INLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

21

T222

EXTN. TO LPH-1

PRT Pt-100

1/2 DIN

0-300 Deg. C

22

T223

LPH-1 DRAIN TO DC

PRT Pt-100

1/2 DIN

0-300 Deg. C

23

T224

LPH-1 DRAIN TO DC

PRT Pt-100

1/2 DIN

0-300 Deg. C

24

T225

LPH-1 OUTLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

25

T226

DC OUTLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

26

T227

LPH-1 INLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

27

T228

DC DRAIN TO FLASH BOX-3

PRT Pt-100

1/2 DIN

0-300 Deg. C

28

T229

DC DRAIN TO FLASH BOX-3

PRT Pt-100

1/2 DIN

0-300 Deg. C

29

T230

DC INLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

30

T232

STEAM TO GSC

PRT Pt-100

1/2 DIN

0-300 Deg. C

31

T233

GSC DRAIN TO FLASH BOX-

PRT Pt-100

1/2 DIN

0-300 Deg. C

3
32

T234

GSC INLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

33

T235

GSC OUTLET

PRT Pt-100

1/2 DIN

0-300 Deg. C

34

T236

CW INLET-A

PRT Pt-100

1/2 DIN

0-300 Deg. C

35

T237

CW INLET-A

PRT Pt-100

1/2 DIN

0-300 Deg. C

36

T238

CW OUTLET-A

PRT Pt-100

1/2 DIN

0-300 Deg. C

37

T239

CW OUTLET-A

PRT Pt-100

1/2 DIN

0-300 Deg. C

38

T240

CW OUTLET-A

PRT Pt-100

1/2 DIN

0-300 Deg. C

39

T241

CW OUTLET-A

PRT Pt-100

1/2 DIN

0-300 Deg. C

40

T242

CW OUTLET-A

PRT Pt-100

1/2 DIN

0-300 Deg. C

41

T243

CW OUTLET-A

PRT Pt-100

1/2 DIN

0-300 Deg. C

42

T247

CW INLET-B

PRT Pt-100

1/2 DIN

0-300 Deg. C

43

T248

CW INLET-B

PRT Pt-100

1/2 DIN

0-300 Deg. C

44

T249

CW OUTLET-B

PRT Pt-100

1/2 DIN

0-300 Deg. C

45

T250

CW OUTLET-B

PRT Pt-100

1/2 DIN

0-300 Deg. C

46

T251

CW OUTLET-B

PRT Pt-100

1/2 DIN

0-300 Deg. C

47

T252

CW OUTLET-B

PRT Pt-100

1/2 DIN

0-300 Deg. C

48

T253

CW OUTLET-B

PRT Pt-100

1/2 DIN

0-300 Deg. C

49

T254

CW OUTLET-B

PRT Pt-100

1/2 DIN

0-300 Deg. C

50

T258

CEP SUCTION

PRT Pt-100

1/2 DIN

0-300 Deg. C

51

T259

CEP DISCHARGE

PRT Pt-100

1/2 DIN

0-300 Deg. C

52

T260

COND. TO D/A NEAR FE

PRT Pt-100

1/2 DIN

0-300 Deg. C

53

T261

COND. TO D/A NEAR FE

PRT Pt-100

1/2 DIN

0-300 Deg. C

54

T262

COND. TO D/A (DE)

PRT Pt-100

1/2 DIN

0-300 Deg. C

55

T263

COND. TO D/A (DE)

PRT Pt-100

1/2 DIN

0-300 Deg. C

56

T264

D/A SHELL TEMP.

PRT Pt-100

1/2 DIN

0-300 Deg. C

57

T265

BFP-A SUCTION

PRT Pt-100

1/2 DIN

0-300 Deg. C

58

T266

BFP-A SUCTION

PRT Pt-100

1/2 DIN

0-300 Deg. C

59

T267

BFP-B SUCTION

PRT Pt-100

1/2 DIN

0-300 Deg. C

60

T268

BFP-B SUCTION

PRT Pt-100

1/2 DIN

0-300 Deg. C

61

T269

BFP-C SUCTION

PRT Pt-100

1/2 DIN

0-300 Deg. C

62

T270

HPH-5 DRIP TO D/A

PRT Pt-100

1/2 DIN

0-300 Deg. C

63

T271

HPH-5 DRIP TO D/A

PRT Pt-100

1/2 DIN

0-300 Deg. C

64

T272

APRDS AFT.

PRT Pt-100

1/2 DIN

0-300 Deg. C

DESUPERHEATER
65

T273

LP BYPASS (R)

T/C

1/2 DIN

250-550 Deg. C

66

T274

LP BYPASS (L)

T/C

1/2 DIN

250-550 Deg. C

67

T275

BFP-C SUCTION

PRT Pt-100

1/2 DIN

0-300 Deg. C

68

T276

CEP SUCTION

PRT Pt-100

1/2 DIN

0-300 Deg. C

69

T277

CEP SUCTION

PRT Pt-100

1/2 DIN

0-300 Deg. C

AUXILIARY POWER MEASUREMENT


Sr.

Tag No.

Service

Instrument

Accuracy

Range

No.
1

PAX-1

CWP-A discharge Pr.

PR. TRANS.

0.10%

0-10 Kg./Sq.Cm.

PAX-2

CWP-B discharge Pr.

PR. TRANS.

0.10%

0-10 Kg./Sq.Cm.

PAX-3

Booster pump suction Pr.

PR. TRANS.

0.10%

0-10 Kg./Sq.Cm.

PAX-4

BFP-A Suction Pr.

PR. TRANS.

0.10%

0-25 Kg./Sq.Cm.

PAX-5

BFP-A discharge Pr.

PR. TRANS.

0.10%

0-250 Kg./Sq.Cm.

PAX-6

BFP-A Suction flow

DP.TRANS.

0.10%

0-2.5 Kg./Sq.Cm.

PAX-7

Booster pump-B Suction Pr.

PR. TRANS.

0.10%

0-10 Kg./Sq.Cm.

PAX-8

BFP-B Suction Pr.

PR. TRANS.

0.10%

0-25 Kg./Sq.Cm.

PAX-9

BFP-B discharge Pr.

PR. TRANS.

0.10%

0-250 Kg./Sq.Cm.

10

PAX-10

BFP-B Suction flow

DP.TRANS.

0.10%

0-2.5 Kg./Sq.Cm.

11

PAX-11

CEP Suction Pressure

PR. TRANS.

0.10%

0-780 mm. Hg.

12

PAX-12

CEP discharge Pressure

PR. TRANS.

0.10%

0-60 Kg./Sq.Cm.

13

PAX-13

CEP discharge flow

DP.TRANS.

0.10%

0-2.5 Kg./Sq.Cm.

TAX-1

BFP-A Suction temp

RTD-100

1/2 DIN

0-300 Deg. C

TAX-2

BFP-B Suction temp

RTD-100

1/2 DIN

0-300 Deg. C

TAX-3

CEP discharge temp

RTD-100

1/2 DIN

0-300 Deg. C

P233

CW DISCH PR.

PR. TRANS.

0.10%

0-10 Kg./Sq.Cm.

P234

CW DISCH PR.

PR. TRANS.

0.10%

0-10 Kg./Sq.Cm.

F104

CONDENSATE FLOW (AUX.

DP. TRANS.

0.10%

0-2.5 Kg./Sq.Cm.

DP. TRANS.

0.10%

0-2.5 Kg./Sq.Cm.

POWER-PLANT ASSEMBLY)
2

F105

FEED FLOW (AUX. POWER BFP


SUC-PLANT ASSEMBLY)

ANNEXURES
1.

CORRECTION CURVES

1.1

HEAT RATE CORRECTION CURVES


MAIN STEAM PRESSURE
MAIN STEAM TEMP
REHEAT CIRCUIT PR. DROP
REHEAT STEAM TEMP.
CONDENSER PRESSURE

DRG No. PE-4-183-100-123


DRG No. PE-4-183-100-124
DRG No. PE-4-183-100-125
DRG No. PE-4-183-100-136

FINAL FEED WATER TEMP.

DRG No. PE-4-183-100-138

FREQUENCY

DRG No. PE-4-183-100-140

POWER FACTOR

DRG No. PE-4-183-100-142

SH SPRAY

DRG No. PE-4-183-100-144


DRG No. PE-4-183-100-137

OUTPUT CORRECTION CURVES


MAIN STEAM PRESSURE
MAIN STEAM TEMP.
REHEAT CIRCUIT PR. DROP
REHEAT STEAM TEMP

DRG No. PE-4-183-100-126


DRG No. PE-4-183-100-127
DRG No. PE-4-183-100-128
DRG No. PE-4-183-100-129

CONDENSER PRESSURE

DRG No. PE-4-183-100-130

RH SPRAY

DRG No. PE-4-183-100-135

FINAL FEED WATER TEMP.

DRG No. PE-4-183-100-139

FREQUENCY

DRG No. PE-4-183-100-141

POWER FACTOR

DRG No. PE-4-183-100-143

SH SPRAY
D/A LEVEL DROP (Ref. HRCC above)
1.3

DRG No. PE-4-183-100-122

RH SPRAY

D/A LEVEL DROP


1.2

DRG No. PE-4-183-100-121

HOTWELL CURVE HXE/SK/1029

DRG No. PE-4-183-100-145


DRG No. PE-4-183-100-137

1.4

D/A CURVE DRG No. 4-16310-00347

1.5

METHOD FOR COMPUTATION OF HEAT RATE


(DOCUMENT No. PE-4-183-100-211 REV 05)

2.0

CONNECTION BETWEEN PRESSURE SOURCE AND TRANSDUCER.

3.0

CONNECTION BETWEEN VACUUM SOURCE AND TRANSMITTER

4.0

TEMP. MEASUREMENT USING T/Cs AND PRTs

5.0

CONNECTION DIAGRAM FOR DIGITAL POWER METER

6.0

DATA SHEET

7.0

HEAT BALANCE
DRG No. PE-3-183-100-101

8.0

MS FLOW Vs FIRST STAGE PRESSURE


DRG No. PE-4-183-100-131 (FOR INFORMATION CURVE)

DRG. NO. PE - 4 - 183 - 100 - 121

DRG. NO. PE - 4 - 183 - 100 - 122

DRG. NO. PE - 4 - 183 - 100 - 123

DRG. NO. PE - 4 - 183 - 100 - 124

DRG. NO. PE - 4 - 183 - 100 - 125

DRG. NO. PE - 4 - 183 - 100 -136

DRG. NO. PE - 4 - 183 - 100 - 138

DRG. NO. PE - 4 - 183 - 100 - 140

Drg. No. PE 4 - 183 - 100 - 142

DRG. NO. PE - 4 - 183 - 100 - 144

DRG. NO. PE - 4 - 183 - 100 - 137

DRG. NO. PE - 4 - 183 - 100 - 126

DRG. NO. PE - 4 - 183 - 100 - 127

DRG. NO. PE - 4 - 183 - 100 - 128

DRG. NO. PE - 4 - 183 - 100 - 129

DRG. NO. PE - 4 - 183 - 100 - 130

DRG. NO. PE - 4 - 183 - 100 - 135

DRG. NO. PE - 4 - 183 - 100 - 139

DRG. NO. PE - 4 - 183 - 100 - 141

DRG. NO. PE - 4 - 183 - 100 - 143

DRG. NO. PE - 4 - 183 - 100 - 145

Drg. No. 4 - 16310 - 00347

Doc. No. PE-4-183-100-211 REV 05

METHOD FOR THE COMPUTATION OF HEAT RATE


The measurements which are directly connected with computation of Heat Rate are shown in sheet 1
of this document. The other measurements required for the PG test are shown in the PG Test Scheme
(Drg. No. PE-3-183-100-210 REV. 02). The procedure for the computation of heat rate from the
measurements envisaged is as given below.
1.0

EXTRACTION STEAM FLOWS TO HP-HEATERS AND DEAERATOR


Steam extraction to HP-Heater and deaerator is evaluated from thermal balance.

HP-HEATER NO. 6
Z [H12 H7] = [M1+X+Y+Z-Mshs-MrhsMdea] (116-115) ............[A]
HP-HEATER NO. 5
Y.[H11-H8] + Z [117-118] = [M1+X+Y+Z- Mshs-mrhsMdea].(114-113) .. [B]
DEAERATOR
X.111+M1.H10+[Y+Z].119 = [M1+X+Y+Z].112 .................................[C]
Three unknown X, Y and Z can be calculated from equation [A], [B] & [C]
Feed water flow Mfw = M1 + X + Y + Z Mshs-Mrhs Mdea ............[D]
1) When there is an increase in the level f deaerator, -ve sign shall be used for Mdea
2) When there is a decrease in the level of deaerator, +ve sign shall be used for Mdea
Sum of storages [Msto] increases or decreased for the following tanks :a) Hotwell storage
NOTE :

b) Drum storage
c) Condensate make-up storage
d) Dearator storage
NOTE : For the above storages if there is a net increase in level, +ve sign is to be taken for Msto
and if there is a net decrease in level, -ve sign is to be taken for Msto to arrive at the unaccounted

losses to be reflected in the main steam flow [Mms].


= Mfw + MshsMstoMdrum .. [E]

Mms
NOTE :1.
2.

When there is increase in level of boiler drum, -ve sign shall be used for Mdrum
When there is decrease in level of boiler drum, +ve sign shall be used for Mdrum

Reheat steam flow Mrh = Mms + Mrhs Z Md .. (F)


M1
= Condensate flow to deaerator measured from flow measuring device F101 . Kg/hr
Md
= Gland leakages A, B and C from HP turbine to be computed (Mdi + Mdo) .kg/hr
Mdi
= Gland leakages A, B and C from HPT inlet side .. kg/hr
Mdo
= Gland leakages A, B and C from HPT outlet side .kg/hr
Msto
= Total increase/decrease of storage in system [from level gauges] during the test kg/hr
Mdea
= Change in deaerator storage during the test .. kg/hr
Mdrum = Change in boiler drum level during the test ......kg/hr
Mshs
= Super heater spray measured from flow measuring device F103 ...kg/hr
Mrhs
= Reheater spray quantity measured by flow measuring device F102 kg/hr
X
= Extraction steam flow to deaerator [calculated from thermal balances]
....kg/hr
Y
= Extraction steam flow to HPH-5 [calculated from thermal
balance] ....kg/hr
Z
= Extraction steam flow to HPH-6 [calculated from
thermal balance] ....kg/hr
H1
= Enthalpy of steam entering deaerator based on measurements P108 & T143, T144
...kcal/kg
H2

Enthalpy of feed water at deaerator outlet based on measurements


P110, T265, T266 & P136, T267, T268 & P140, T269, T275
...........................kcal/kg
H3
=
kcal/kg

Enthalpy of feed water at HPH5 inlet based on measurements P221 & T137, T138 .

H4
=
kcal/kg

Enthalpy of feed water at HPH-5 outlet based on measurements P222 & T139, T140

H5
= Enthalpy of feed water at HPH-6 inlet based on measurements P215 & T125, T126
.kcal/kg
H6
= Enthalpy of feed water at HPH-6 outlet based on measurements P216 & T127, T128
.kcal/kg
H7
= Enthalpy of HPH-6 drain based on measurements P218 & T131, T132
....................kcal/kg
H8
= Enthalpy of HPH-5 drain near heater based on measurements P111 & T270, T271
...kcal/kg
H10

Enthalpy of condensate entering deaerator


Based on measurements P124 & T262, T263 ...............kcal/kg

H11

Enthalpy of extraction steam entering HPH-5


Based on measurements P220 & T135, T136 ...............kcal/kg

H12

Enthalpy of extraction steam entering HPH-6


Based on measurements P214 & T123, T124 ...............kcal/kg

2.0

HEAT RATE :-

HR

Mms[HmsHffw]+Mrh[Hrho-Hrhi]+Mshs[Hffw-Hshs]+Mrhs[Hrhi-Hrhs]

--

--------------------------------------------------------------------------------------------------------------------............ [G]

Pnet.
HR
= Heat Rate
kcal/kwh
Mms
= Main steam flow at HPT inlet
[as calculated] .. kg/hr
Mrh
= Reheat steam flow [as
calculated] ......kg/hr
Hms
= Enthalpy of
steam before ESV based on measurements P201, P203 & T101 to T104 kcal/kg
Hffw
= Enthalpy of final feed water after HP-heaters based on measurements P206 & T145, T146
.. Kcal/kg
Hrho = Enthalpy of hot reheat steam before IV based on measurements P208, P210 & T109 to
T112 kcal/kg
Hrhi
= Enthalpy of cold reheat steam based on measurements P207 & T107 to T108 . Kcal/kg
Hshs
= Enthalpy of superheater spray based on any two of the measurements {P227, T151},
{P226, T150} and {P225, T149} depending upon working BFPs.
Hrhsi
= Enthalpy of CRH after mixing of RH spray based on measurements P209, T106 & P211,
T105 .. kcal/kg
Pnet = Pgen 63 (Towards integral auxiliaries) ..kw
Pgen = Power measured at Generator terminals .. kw

3.0

COMPUTATION OF TOTAL GLAND LEAKAGES :-

Steam leakage through the glands A, B and C is calculated using the formula given below

G = Steam leakage through the glands...............T/H.


P1= Pressure before the glands.......................ata
P2= Pressure after the glands......................ata
V1= Specific volume at inlet conditions to the glands..........cum/kg.

Data for design case is given below [Refer HBD No. PE-3-183-100-101 REV 02]
PARAMETER
HPT INLET END
G
3.051
P1
41.27
P2
6.835
V1
*0.0838
* Based on 41.27 ata & 816.0 kcal/kg.
** Based on 41.27 ata & 349.6 DEG C.

HPT OUTLET END


3.199
41.27
6.835
**0.0655

For design case P1, P2, V1 and G are known and hence K can be evaluated.
K values calculated for the design case are as given below :
a)
For gland leakage from HPT inlet end K = 0.1394
b)
For gland leakage from HPT outlet end K = 0.1292
For test case, by putting this value of K and the test values of P1, P2 and V1 and computation of G
can be done.
For the test case, the values of P1, P2 and V1 are determined as given below :

For HPT inlet end :

P1 is based on measurements P207


P2 is based on measurements P105 & P106
V1 is based on measurements P207 & TA

203 & T101 to T104.

TA is calculated on the basis of P207 and enthalpy corresponding to P201 and

For HPT outlet end : P1 is based on measurements P207


P2 is based on measurements P105 to P108
V1 is based on measurements P207 & T107 to T108
4.0

NOTE :

1.
The heat rate is guaranteed with 0% make-up and hence no make-up will be supplied to the
condenser during the performance guarantee test. Under these conditions the storage in the
deaerator feed storage tank is utilised towards the leakage losses and the measured heat rate shall
be corrected using the correction curve viz. Change in heat rate vs. change in storage of feed water
storage tank.
2.
In case the temperature measured at the HP turbine exhaust (measurements T107 to T108) is
less than the temperature of extraction steam at HP Heater No. 6 inlet (measurements T123, T124)
then leakage through the HP bypass valve is suspected. The leakage shall be estimated as given
below :
Mhpb

[Mms Md] [H12 Hrhi]


_______________________
[Hms Hrhi]

where Mhpb = Quantity of steam leakage through the HP bypass valve . T/HR
The quantity of steam entering the HP turbine [Mms1] shall be corrected for the leakage through the
HP bypass as given below and shall be used in the equation (G) instead of Mms.
Mms1 = Mms Mhpbp
5.0

GUARANTEE CONDITIONS.

1.

Guaranteed Heat Rate at 100% load = 1939.3 Kcal/Kwhr.


(Ref HBD No. PE-3-183-100-101 REV 01 titled 210 MW 0% MU 0.0911 ata Back Pr).

2.
Instrument uncertainly shall be computed with accuracy classes of various instruments to be
used during the P.G. test in accordance with the document titled Guidance for evaluation of
measuring uncertainly in performance test of steam turbine A report by ASME Performance test
code committee G
3.
If the test is carried out after four months of the date of first commissioning, due to any
reason whatsoever, the specific heat consumption shall be increased by following amounts for each
month or part of a month by which the period between the initial commissioning and the acceptance
test exceeds 4 months.
0.10% for the following 8 months
0.06% for the period thereafter
4.

The pressure drop between MS strainer and ESV & between ESV and HPT in the MS line and

between HRH strainer and IV & between IV & IPT in HRH line have not been considered in the heat
balance calculations since same is to be accounted in the respective system piping pressure drops.
The actual pressure drops shall be estimated during the PG test based on layout envisaged and the
calculated steam flows and necessary corrections applied on the measured pressures.
6.0
A.

LIST OF CORRECTION CURVES


HEAT RATE CORRECTION CURVES FOR :

i. Main steam pressure.


ii. Main steam temperature.
iii. Reheat steam temperature.
iv. Reheat circuit pressure drop.
v. Back pressure.
vi. Reheat Spray/Superheater Spray.
vii. Change in feed water storage in Deaerator FW storage tank.
viii. Final feed water Temperature.
ix. Power factor.
x. Frequency.
B.

OUTPUT CORRECTION CURVES FOR :

i.
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
x.

Main steam pressure.


Main steam temperature.
Reheat steam temperature.
Reheat circuit pressure drop.
Back pressure.
Reheat Spray/Superheater Spray.
Change in feed water storage in Deaerator FW storage tank.
Final feed water temperature.
Power factor.
Frequency.

CONNECTION BETWEEN PRESSURE SOURCE AND TRANSDUCER.

CONNECTION BETWEEN VACUUM SOURCE AND TRANSMITTER.

TEMPERATURE MEASUREMENT USING T/Cs & PRTs.

CONNECTION DIAGRAM FOR DIGITAL POWER METER

HEAT BALANCE Drg. No. PE-3-183-100-101

Drg. No.: PE-4-183-100-131

P ROC EDU RE F OR SITE P ERF ORM ANC E G U ARANTEE TEST OF BF P


PROJECT

2 x 210

CUSTOMER

MSEB

UNITS 3 & 4

1.0

KHAPERKHEDA TPS

INTENT :
The intent of the site test is to prove the auxiliary power consumption of the Boiler Feed Pump
set measured at the input terminals of the BFP drive motor at guaranteed parameters.

2.0

GUARANTEE PARAMETERS :
The guaranteed parameters of the pump are given at cl.no. 9.0

3.0

TEST SET UP :
The schematic arrangement for the test is illustrated in page no. 6.

4.0

MEASURING POINTS :
a)

FLOW :
The Feed water flow of the Boiler Feed Pump is measured using the plant flow nozzle
and test differential pressure transmitter.

b)

HEAD :
The head measurement is done by test pressure transmitters in Booster pump suctions,
BFP suction and BFP discharge.

c)

TEMPERATURE :
The temperature measurement is done by test RTD.

d)

SPEED :
The speed measurement is carried out by non-contact type digital tachometer.

c)

POWER :
The power input at the motor terminals shall be measured by test watt transducers
which shall be connected to C.T's and P.Ts provided in the switchgear.

5.0

PERFORMANCE TOLERANCES :
An overall tolerance of 3.5% will be used while comparing measured power with the
guarantee power due to measurement uncertainties on flow, head and power. This is as per
Table-7 of BS-5316, Class C.

6.0
6.1

TEST METHODOLOGY :
The test instruments listed at cl.no. 10.0 will be connected as per the test scheme. All
transducers will be connected to a data logger.

6.2

Preliminary test shall be conducted for checking up of instruments.

6.3

After stabilisation, the test will be conducted for about 1 hour and readings will be recorded at
5 minute intervals in the data logger. The data logger print out of the readings thus recorded
shall be signed by Customer and BHEL Representatives. During the test, the customer shall try
to maintain the flow through the BFP within

3% of the flow at guarantee point, for recording

the various parameters.


6.4
7.0

Two tests will be conducted on each pump set.


CALCULATION PROCEDURE :
The auxiliary power consumption for BFP set is valid for a given set of guarantee parameters
of BFP suction flow and the feed water temperature. In case the BFP is operated at a point
different from the guaranteed parameters, the input power would be computed using the
standard formulae relating Q, H and Efficiency, and the auxiliary power consumed at motor
terminals is derived after considering the motor efficiency, pump efficiency and hydraulic

coupling losses corresponding to test flow, with reference to design curves of BFP and Booster
pump. Evaluation is done by averaging the test results of the two test carried out on each
pump.
8.0

AUXILIARY POWER GUARANTEE :


BFP parameters corresponding to Auxiliary Power guarantee :
(MRC Flow, 0% MU, 0.0911 ata back pr.)
Suction Flow (m3/hr)

343.9 (per BFP)

Dynamic head (mlc)

1890 (BFP + BP)

Temperature (C)

159.50

Specific Wt. (kg/m3)

907.77

Motor input power (kW)

2660 (per BFP)

Total Auxiliary Power (kW)

5320

NOTE : Auxiliary power is guaranteed with ZERO interstage flow i.e. interstage valve in
closed condition.
9.0

LIST OF INSTRUMENTS :

-----------------------------------------------------------------------------------PARAMETER TYPE AND RANGE OF

TAG NO. ACCURACY

Booster
Pump
Suction Pr.

Pressure Transmitter 010kg/sq.cm.

PT1

0.1%

BFP suction
Pressure

Pressure Transmitter 030kg/sq.cm.

PT2

0.1%

BFP
discharge
Pressure

Pressure Transmitter 0300kg/sq.cm.

PT3

0.1%

BFP suction
Flow

Diffl. Pr. Transmitter


(Range will be selected
based on flow nozzle
data)

DPT

0.1%

TE

1/3 DIN

Optical non-contact
Digital Tachometer.

1 RPM

Booster
Optical non-contact
Pump Speed Digital Tachometer.

1 RPM

Motor input
Power.

0.25%

BFP Suction
RTD 0 - 200C
Temperature
BFP speed

Watt transducer

REMARKS

------------------------------------------------------------------------------------

10.0

SAMPLE CALCULATIONS :
During the site test, pump parameters like flow, head and speed may be different from those
guaranteed. The following illustrates sample calculation for new auxiliary power based on site
test parameters.

A.

Site tested data :


Feed water temp.

150 C

Sp. wt. of feed water

916.9 kg/m3 from standards

Flow

345 t/hr

Booster pump suction pressure

p1 kg/cm2

BFP suction pressure

p2 kg/cm2

BFP discharge pressure

p3 kg/cm2

Booster pump speed

1510 rpm

BFP speed

4800 rpm

Power input to motor terminals

2770 kW

From the above data :


Flow

B.

345/0.9169

376.27 m3/hr

Booster pump head

{(p2 - p1) x 10} / 0.9169

say 105 mlc

BFP head

{(p3 p2) x 10} / 0.9169

say 1952 mlc

Estimated auxiliary power based on tested data :


i.

Booster Pump :
Tested flow corrected to design speed = (1485/1510)x376.27=370 m3/hr
Efficiency at corrected flow from design curve = 77%
916.9 x 376.27 x 105
Power input to pump = ------------------------

128 kW

102 x 3600 x 0.77


ii.

Boiler Feed Pump:


Tested flow corrected to design speed = (5075/4800)x376.27=398m3/hr
Efficiency at corrected flow from design curve = 81%
916.9 x 376.27 x 1952
Power input to pump = -------------------------102 x 3600 x 0.81

iii.

Hydraulic Coupling :

= 2264 kW

Mechanical losses

100 kW (Approximate)

HC Prim. speed BFP Test speed


Slip losses

= ---------------------------------------- x Input power

(speed dependent)

BFP Test speed

5998 4800
=

------------------- x 2264

= 188 kW.

4800
Total losses in Hydraulic Coupling = 100 + 188
iv.

C.

= 288 kW

Total input power = (i) + (ii) + (iii) = 128+2264+288 = 2680 kW


Motor efficiency from motor design curve

95 %

Power input at Motor terminals

2680/0.95

2821 kW

Auxiliary Power measured at site :


Auxiliary power measured at test speed

D.

2770 kW

Auxiliary power at motor terminals measured at site (C) will be compared to the estimated
auxiliary power (B-iv).
In case the measured power is higher than the calculated power, the difference of the two will
be treated as excess auxiliary power consumption.

RECORD OF REVISIONS
Rev.
No.

Date

Revision Details

Revised Approved
By
By

01

26.12.2000 Revised as per MSEB ltr. No. 3084 dt.


21.10.2000

02

12.01.2001

Parameters revised to 0% MU as per


PEM ltr. dt. 11.01.2001

PROCEDURE FOR SITE PERFORMANCE GUARANTEE TEST OF CEP

Project
Customer

1.0

KHAPERKHEDA TPS, UNIT III & IV


:

MSEB

INTENT :
The intent of the site test is to prove the auxiliary power consumption of the Condensate
Extraction Pump set measured at the input terminals of the CEP drive motor at guarantee
parameters.

2.0

GUARANTEE PARAMETERS :
The guarantee parameters of BFP set are given at cl. No. 8.0

3.0

TEST SET UP :
The schematic arrangement for the test is illustrated at page no. 5

4.0

MEASURING POINTS :
a.

FLOW :
The condensate water flow of the Condensate Extraction Pump is measured using
test Differential Pressure Transmitter across orifice in down stream of
gland steam condenser.
b.
HEAD :
The head measurement is done by test pressure transmitters in Pump suction and
discharge
branches.
c.
TEMPERATURE :
The temperature measurement is done by test RTD.
d.
SPEED :
The speed measurement is carried out by tachometer.
e.
POWER :
The power input at the motor terminals shall be measured by test Wattmeter/
transducers by
connecting these wattmeter/transducers to C.Ts and P.Ts provided in the switchgear.
5.0

PERFORMANCE TOLERANCES :

0.1
An overall tolerance of 3.5% will be used while comparing measured power with the guarantee
power due to measurement uncertainties on flow, head and power. This is as per Table-7 of BS-5316,
Class C.
6.0
6.1
will

TEST METHODOLOGY :
The test instruments listed at cl.no. 9.0 will be connected as per the test scheme. Transducers

be connected to a data logger.


6.2

Preliminary test shall be conducted for checking the instruments.

6.3
After stabilisation, the test will be conducted for about 1 hour and readings will be recorded at
(5) five
minute intervals in the data logger. The data logger print out of the readings thus recorded
shall be
signed by Customer and BHEL Representatives. During the test, the customer shall try to
maintain the
flow through the BFP within 3% of the flow at guarantee point, for recording the various
parameters.
6.4
7.0

Two tests will be conducted on each pump set.


CALCULATION PROCEDURE :
The auxiliary power consumption for CEP set is valid for a given set of guarantee
parameters of CEP discharge flow and the temperature. In case the CEP is operated at a
point different from the guaranteed parameters, the input power would be computed
using the standard formulae relating Q, H and Efficiency, and the auxiliary power
consumed at motor terminals is derived after considering the pump efficiency and motor
efficiency corresponding to test flow from the design curves. Evaluation is done by
averaging the test results of the two tests carried out on each pump. Sample calculations
are given at cl.no. 10.0.

8.0

AUXILIARY POWER GUARANTEE :


Condensate Extraction Pump parameters for Auxiliary Power Guarantee :
(MRC Flow, 0% MU, 0.0911 ata back pr.)

9.0

Flow (m3/hr)
Dynamic head (mlc)
Temperature (C)

:
:
:

498.5
219 (From Test Curve)
43.6

Specific Wt. (kg/m3)


Motor input power (kW)
Pump speed (rpm)

:
:
:

990
440
1485

LIST OF INSTRUMENTS :

-----------------------------------------------------------------------------------------------Parameter
Accuracy

Type & range of

Tag No.

------------------------------------------------------------------------------------------------Suction Pressure

Pressure transducer -1 to +1
kg/sq.cm.

PT1

0.1%

Discharge Pressure

Pressure transducer 0 - 40
kg/sq.cm.

PT2

0.1%

Flow

Diffl. Pr. transmitter (Range will be


selected before the test based on
the flow orifice data sheet).

DPT

0.1%

Temperature

RTD

TE

1/3 DIN

Speed

Optical non-contact digital


tachometer.

1 rpm

Power

Watt transducer

0.25%

-----------------------------------------------------------------------------------------------10.0

SAMPLE CALCULATIONS :
During the site test, pump parameters like flow, head and speed may be different from
those guaranteed. The following illustrates sample calculation for correcting the site
tested parameters to the design speed.
A.

Site test data :

Speed

: 1513 rpm.

Discharge temp.

: 43C (sp. wt. to be taken from standard)

Flow

: 540 m3/hr (TPH / sp. wt. at 43C)

Pump dynamic head

Power input at motor


terminals

: 456 kW.

B.

Estimated auxiliary power based on tested data :


Flow corrected to design speed = 148/1513) X 540 = 530m3/hr.

1.

Dynamic head corrected to design speed = (1485/1513)2

2.

C.

3.

Pump efficiency at 530 m3/hr from design curve = 76%

4.

Power input to pump =

530 x 218.68 x 990


------------------------ = 411.15 kW
3600 x 102 x 0.76

5.

Power input to motor =

Pump input power


-----------------------Motor efficiency

411.15
= ---------- = 435 kW
0.945

Auxiliary power measured at site :

1.
2.
D.

{(Disch. pr.- Suction pr.) x 10} / sp. wt. = say


227 mlc

Aux. power at tested speed of 1513 rpm = 456kW.


Aux. power corrected to design speed = (1485/1513)3 x 456 = 431.149
kW.

Evaluation:
Site measured auxiliary power at motor terminals, corrected to pump design
speed (C2) will be compared to the estimated auxiliary power (B5).
In case the measured power corrected to design speed is higher than the
calculated power, the difference of the two will be treated as excess auxiliary

power consumption.

RECORD OF REVISIONS

Rev.

Date

No.
01

Revision Details

26.12.2000

Revised

Approved

By

By

Revised as per MSEB ltr. No. 3084


dt. 21.10.2000.

02

12.01.2001

Parameters revised to 0% MU as per


PEM ltr. dt. 11.01.2001.

PROCEDURE FOR SITE PERFORMANCE GUARANTEE TEST OF CWP


PROJECT

IV

CUSTOMER
1.0

:
:

2 X 210 MW KHAPERKHEDA TPS UNIT III &


MSEB

INTENT :
The intent of the site test is to prove the auxiliary power consumption of the Cooling water
Pump set measured at the input terminals of the CWP drive motor at guarantee points.

2.0

GUARANTEE PARAMETERS :
The guaranteed parameters shall be as per Annexure-I.

3.0

TEST SET UP :
The schematic arrangement for the test shall be as per Annexure- III for CWP Set.

4.0

MEASURING POINTS :
a)

DISCHARGE PRESSURE :
Discharge Pressure measurement is done by a calibrated pressure gauge.

b)

STATIC HEIGHT :
Static height of the pump discharge pressure gauge from the surface of the water line
in the sump shall be measured as below.
1.
Measure the height of pump discharge pressure gauge centre line from
the
operating floor level, Say "Z1".
2.
Measure the depth of water surface from the operating floor level, say
"Z2".
Static Height = (Z1 + Z2).

c)

SPEED :
The speed measurement is carried out by non-contact type digital tachometer.

c)

POWER :
The power input at the motor terminals shall be measured by test Watt Meters.

5.0

PERFORMANCE TOLERANCES :
An overall tolerance of 1.5% will be used while comparing measured power with the
guaranteed power due to measurement uncertainties on head and power.

6.0

CALCULATION PROCEDURE :
The auxiliary power consumption for CWP Set is valid for a given set of guaranteed
parameters of CWP Discharge flow and bowl head.
In case the CWP is operated at a point different from the guaranteed parameters, the input
power would be computed using the standard formula relating Q,H and Efficiency. And the
auxiliary power consumed at motor terminals is derived after considering pump efficiency and
motor efficiency corresponding to designed flow, with reference to tested curves of CWP.
Refer Annexure IV for sample calculations.
ANNEXURE 1
AUXILIARY POWER GUARANTEE

Project

Customer

2 x 210 MW Khaperkheda units 3 & 4


:

MSEB

CWP parameters corresponding to Auxiliary Power guarantee

Flow (cum/hr)

13600

Bowl head (m)

28.5

Motor input power (kw)

1260.7

ANNEXURE II
LIST OF INSTRUMENTS
Parameter

Type and range

Tag
Accuracy Remarks
No.

Static height Measuring Tape

MT

--

Discharge
pressure

Pressure gauge 07kg/sq.cm

PG

0.1%

Speed

Optical non-contact
Digital tachometer

1 RPM

Power

Watt Meter

0.25%

ANNEXURE IV
COMPUTATION OF POWER INPUT TO CWP MOTOR
(SAMPLE CALCULATIONS)

1.

Pump discharge pressure (P1)

2.

Height of discharge pr. Gauge

center line from operating floor (Z1)


3.

2.2 Kg/sq.cm (g)

1.0 m

5.0 m

Depth of water surface in the sump


from operating floor (Z2)

4.

Bowl Head (Hb)


Where, V

(P1x10)+Z1+Z2+(V2/2g)+hr

= Velocity of water in discharge pipe.


V2/2g

= 0.18 m (for a flow of 13600 m3 /hr)

hf

= Friction loss in pump column pipe

hf

= 0.5 m (committed value)

HL

= 22.0 + 1.0 + 5.0 + 0.18 + 0.5


= 28.68 m

5.

Flow corresponding to Hb (28.68 m)


m3/hr

13600

6.

Bowl efficiency

89%

7.

Power input to pump bowl

(refer tested curve)

1000 x 13600 x 28.68


--------------------102 x 3600 x 0.89

=
8. a
b

1193.5 kW

Thrust bearing loss

9 KW

Transmission loss

KW
=
9.

Total loss (a + b)
12 kW

Pump shaft input power

1193.5 + 12

1205.5 kW

10.

Motor efficiency

96.0%

11.

Motor input power

1205.5/0.96

1255.73 kW

Вам также может понравиться