Академический Документы
Профессиональный Документы
Культура Документы
Enterprise Mine
J Poniewierski1, G MacSporran2 and I Sheppard3
ABSTRACT In most studies where the changes in cut-off grade with respect
to production rate are assessed, the derivation of the maximum
The practical application of Lane’s theory on optimum cut-off grade
policy has to date proved difficult for selective stoping in large-scale sustainable production rates for an underground orebody have by
underground mining. The key to determining an optimum cut-off grade is necessity required a number of simplifications. One such
the ability to rapidly perform complex mine layout designs combined simplification is to calculate the tonnes per vertical metre and
with rapid output of multiple potential schedules. This paper describes assume the mine production rate is limited by the vertical
aspects of the detailed investigation into estimating a practical static advance rate. There can be a large range of rates used and a
cut-off grade for the two main orebodies in Mount Isa Mine’s Enterprise typical one used in Western Australian gold mines is 30 to 50
Mine. vertical metres per annum (McCarthy, 1993). While useful in
Rule based automated scheduling software was used to evaluate conceptual studies, the validity of such simplifications is highly
thirteen different stoping layouts (including design infrastructure and dependent on the mining method used. For a large-scale multiple
capital development) of the Enterprise Mine’s two main orebodies, with level open stoping operation such as Mount Isa Mine’s Enterprise
over 200 schedules generated. The investigation illustrates the application Mine, an assumption of vertical depletion of an orebody bears no
of commercially available software to solve the problems of generating
resemblance to the actual mining operations.
multiple cut-off grade stope designs and achieving the otherwise
insurmountable task of rapidly generating and valuing multiple scenarios The need to make such assumptions has in the past been a
for each stoping layout. result of the complexity and time-consuming nature of designing
Each scenario was evaluated using modelled net cash flows of the an orebody at different cut-off grades and then manually
mining, concentrating and smelting operations of the company and scheduling each orebody design at different production rates.
calculating NPV. The cut-off grade for each orebody was selected based Iterative mine planning has therefore rarely been undertaken for
on the cut-off grade that achieved maximum NPV – with an appropriate optimising cut-off grade, although previous authors (Wheeler and
production rate. Rodrigues, 2002; Hall, 2000; Hall, 2002) have however
Underground mine scheduling is a complex task involving the highlighted the need for a comparative analysis at different
adherence to a number of simple scheduling rules and the balancing of cut-off grades and different production rates.
several competing drivers. The study also found that:
This paper describes aspects of the detailed investigation into
• while each scheduling rule itself is simple, the compounding estimating a best practical static cut-off grade for the two main
complexities of their interaction preclude manual scheduling from
being a realistic option.
orebodies in Mount Isa Mine’s Enterprise Mine – a deep
underground copper mine. The investigation was undertaken as
• there is a maximum sustainable rate of production possible for any
given stoping layout, and that the actual maximum production rate is
part of a major review for the copper business at Mt Isa.
also a function of the required number of years of sustainable The approach described shows the first step towards achieving
production. a practical application of the cut-off grade theory of Lane (1997)
• the optimal cut-off grade was different for each orebody – a in selective underground mining.
recognition of the impact of the different characteristics of each Commercially available software was used to generate
orebody. simplified stope layouts for various cut-off grades for each of the
two orebodies in the mine. The mine designs for these different
INTRODUCTION cut-off grades were then repeatedly scheduled at various target
production rates, again using commercially available software, in
The calculation of the optimum cut-off grade for any particular order to determine a suitable sustainable production rate for each
mine is a complex procedure involving a considerable amount of cut-off grade stoping layout. The resulting production tonnage
geological interpretation, mine design, scheduling, and economic and grade profiles were used as input into financial models of the
and financial modelling (Hall, 2000). At any given production mining, concentrating and smelting operations of the company.
rate there is generally a particular cut-off grade that will Based on the maximum Net Present Value obtainable, the ideal
maximise the Net Present Value (NPV) of the mine – a grade that cut-off grade for each orebody was thus determined.
will invariably be higher than the operating breakeven grade. As Further development of the software tools used for this study,
the production rate at a mine is changed, it is also generally to a point where they will allow the rapid automation of an
found that the cut-off grade will vary – a result of fixed capital optimum cut-off grade policy for underground mining should be
and fixed operating costs being spread over greater or lesser an industry goal.
tonnages. A significant concept that emerged from the study was that for
each orebody design, the complex interaction of individually
simple scheduling rules that account for the unique
1. MAusIMM, Business Analyst/Senior Mining Consultant, Runge Ltd, characteristics of each orebody, result in there being a maximum
GPO Box 2774, Brisbane Qld 4000. sustainable production rate for a given stoping layout design. To
E-mail: jponiewierski@runge.com.au
exceed that maximum sustainable production rate, major mine
2. MAusIMM, Formerly Mine Engineering Superintendent – 2002 design philosophy changes are required.
Copper Business Study, currently Senior Mining Engineer, SRK
Consulting, PO Box 943, West Perth WA 6872.
E-mail: gmacsporran@srk.com.au THE ENTERPRISE MINE
3. MAusIMM, Manager 2002 Copper Business Study, MIM – Copper Located in mineral-rich north west Queensland, Mount Isa Mines
Study Group, Mt Isa Mines Private Mail Bag, Mount Isa Qld 4825. (MIM) operates one of the world’s largest underground mining
E-mail: ikshep@isa.mim.com.au complexes, mining copper and lead-zinc-silver orebodies.
Mine Planning and Equipment Selection Kalgoorlie, WA, 23 - 25 April 2003 531
J PONIEWIERSKI, G MacSPORRAN and I SHEPPARD
The MIM copper stream processes ore from the X41 Copper metres in plan and are extracted vertically to the full height of the
Mine and Enterprise Mine at Mount Isa and concentrate from orebody. The sublevel interval used is approximately 40 metres
MIM Holdings’ Ernest Henry Mine which lies about 40 km north which limits the length of blast holes. The mining method is
of Cloncurry. The Enterprise underground copper mine is the discussed in detail in numerous technical papers (Hall, 1992).
most recent copper ore source at Mount Isa and was developed
beneath existing operations at a cost of $A 370 million. It CUT-OFF GRADE THEORY APPLIED
commenced commercial production on 1 July 2000, and was
officially opened in August 2000. The accepted theory on optimum cut-off grade policy is that by
The Enterprise Mine is Australia’s deepest mine, with mining K Lane (1997). Practical application of Lane’s theory has
expected to a depth of 1800 metres below the surface. Ore from however proved difficult for selective stoping in underground
the mine has a head-grade of around four per cent copper. mining. The availability of automated scheduling software for
open pits has allowed significant advances in cut-off grade
The Enterprise Mine required construction of three major fixed
analysis in surface mining. However, difficulties in scheduling of
plant and equipment systems: a new ore handling system to
underground selective mining operations has deterred most
access the 3000 and 3500 orebodies, a refrigeration plant and a
operations from undertaking such an investigation of optimum
new paste fill plant. A schematic cross-section of the mine is
underground cut-off grades.
shown in Figure 1.
The Enterprise ore handling system consists of an underground The work presented in this paper is based on the assumption
jaw crusher, a conveyor connecting to the M62 internal shaft and that the corporate objective in cut-off grade selection is to
another conveyor connecting from the top of the M62 internal maximise the Net Present Value (NPV) of the mine, as is the case
shaft to the pre-existing U62 shaft and copper ore handling in the cut-off grade theory expounded by Lane. In many cases
system. The M62 internal shaft is 5.3 metres in diameter and 713 this is not the real objective of the corporation. Frequently
metres long. Its base lies approximately 1660 metres below the longest mine life, maximum Mineral Resource recovery or
surface. conversely achieving bottom quartile position on the industry
Virgin rock temperatures at Enterprise which reach more than cost curve, are cut-off grade selection objectives. These
60°C, along with the autocompression of ventilation air at the alternative objectives are not always openly admitted. They may
depth of mining, required installation of a major refrigeration be equally valid objectives alongside NPV for individual mine
plant. The refrigeration plant provides up to 22 MW of owners. Some Australian mining consulting firms have made
refrigerative cooling to condition the air entering the mine to comment on these issues over several years (Hall, 2000). In the
14°C. Four large ammonia compressors provide 540 L/s of cold study undertaken for the Enterprise Mine, NPV was chosen as
water to the bulk air cooler, where 580 kg/sec of downcast air the primary criteria for cut-off grade selection.
passes through large spray towers before being sent underground At a given point in the life of a mine and with a given future
via the R67 fresh air intake. production schedule, there is a particular cut-off grade that will
A major paste fill plant was also constructed for the Enterprise maximise the NPV. Lane has described three cut-off grade
mine. The paste fill plant is among the largest of its type in the equations that can be used to calculate the optimum cut-off grade
world and is designed to produce 450 dry tonnes of paste per for maximum NPV. The three equations are required to cover the
hour continuously as a 76 per cent solids-by-weight slurry. The three main operation scenarios possible:
paste is transported underground through two vertical boreholes, • marketing limited operations,
each 200 mm in diameter and 1100 m deep.
• treatment limited operations, and
The mining method utilised is sublevel open stoping (SLOS),
which has evolved over the last 70 years of operation, in the • mining limited operations.
copper and lead orebodies, to the present day design standards. In practice for long-term planning we are concerned with only
Stope dimensions for the Enterprise Mine are typically 35 by 35 two cases, the mining limited and the treatment limited cases.
532 Kalgoorlie, WA, 23 - 25 April 2003 Mine Planning and Equipment Selection
OPTIMISATION OF CUT-OFF GRADE AT MOUNT ISA MINES LIMITED’S ENTERPRISE MINE
Mine Planning and Equipment Selection Kalgoorlie, WA, 23 - 25 April 2003 533
J PONIEWIERSKI, G MacSPORRAN and I SHEPPARD
B. Scheduling solutions The SMU represent a block size that assist in establishing shapes
for stope designs. In the case of the Enterprise Mine the SMU is
Generate life-of-mine schedules for each cut-off grade mine 30 mN by 30 mE by 10 mRL. The results of the StopeSizor
design. There are many possible schedules for a mine. The use of analysis were output in a form suitable for review in Microsoft
rule based semi automatic scheduling software allows the Excel. Figure 3 shows a typical cross-section (representing a
identification of the best schedule for a given cut-off grade. 30 m of Northing) for one of the orebodies. The value within
1. build XPAC Autoscheduler™ model for each design; each grid represents the grade (per cent copper) of the SMU
block.
2. run, interrogate and re-run XPAC Autoscheduler scenarios
until a maximum sustainable production rate is achieved; and
3. output XPAC Autoscheduler life-of-mine schedule details.
Generating a ‘psuedo Mineral Resource’ Establishing the dilution criteria for stope models
A ‘pseudo Mineral Resource’ refers to material that is considered Two principal conversion factors by which mineral resources are
mine-able at the selected cut-off grade. To establish a pseudo modified to produce ore reserves are mining dilution and mining
Mineral Resource for each cut-off grade model, Snowden’s recovery (Stephenson and Vann, 1999).
StopeSizor software† was used (Thomas and Earl, 1999). This For this study the dilution for the stopes was based on
software filters the block model and ‘lumps’ the geology model estimates of the Equivalent Linear Overbreak/Sloughing (ELOS)
blocks together within a specified Smallest Mining Unit (SMU). for the stope crown and any fill walls exposed. The stope crown
generally has mineralised material, the grade of which was
† Refer to http://www.snowdenau.com/software.htm for further estimated by using the grade of the SMU block directly above
information. the stope crown. The fill material has an effective zero grade.
534 Kalgoorlie, WA, 23 - 25 April 2003 Mine Planning and Equipment Selection
OPTIMISATION OF CUT-OFF GRADE AT MOUNT ISA MINES LIMITED’S ENTERPRISE MINE
FIG 5 - Plan view of XPAC database stope outlines for three of the six cut-off grade designs used for one of the orebodies shaded for
contained copper metal tonnages.
Mine Planning and Equipment Selection Kalgoorlie, WA, 23 - 25 April 2003 535
J PONIEWIERSKI, G MacSPORRAN and I SHEPPARD
FIG 6 - Report graph outlining the monthly achieved production based on an annual target rate showing periods of
‘no production’ and ‘low production’.
536 Kalgoorlie, WA, 23 - 25 April 2003 Mine Planning and Equipment Selection
OPTIMISATION OF CUT-OFF GRADE AT MOUNT ISA MINES LIMITED’S ENTERPRISE MINE
Mine Planning and Equipment Selection Kalgoorlie, WA, 23 - 25 April 2003 537
J PONIEWIERSKI, G MacSPORRAN and I SHEPPARD
REFERENCES
Hall, B E, 1992. Copper ore mining at Mount Isa Mines Limited, Mount
Isa, Qld, in Proceedings Underground Mass Mining Conference
1992, pp 173-177 (South African Institute of Mining and
Metallurgy: Johannesburg).
Hall, B, 2000. Practical cut-off grades for underground mining –
FIG 8 - Graph of cumulative cash value and Net Present Value for maximising value, or marginalising resources? Digging Deeper
cut-off grade designs modelled for one of the Enterprise Mine (AMC Newsletter), February.
orebodies. Hall, B, 2002. Cut-off Grades – Theory and Practice Workshop,
mineABILITY®, Townsville, 1 August.
Lane, K F, 1997. The Economic Definition of Ore, Second Edition
The cut-off grade at the peak of the NPV curve is a higher (Mining Journal Books: London).
cut-off grade than for the cumulative cash curve – a result of MacSporran, G, 2002. Enterprise Mine cut-off grade analysis and results,
influence of the opportunity costs (as per Lane’s theory). This is unpublished internal report to MIM 2002 Copper Business Study.
the grade used for Ore Reserve calculation and mine design. McCarthy, P L, 1993. Economics of Narrow Vein Mining, in Proceedings
A sensitivity analysis was also undertaken and indicated that Narrow Vein Mining Seminar 1993, pp 89-97 (The Australasian
the operating cost was the most sensitive parameter in selecting Institute of Mining and Metallurgy: Melbourne).
the optimum cut-off grade. The discount rate used in calculating Poniewierski, J, 2002a. 3000 Orebody XPAC Study – Results and Model
the NPV, the copper price and the exchange rate, while Description, unpublished internal report to MIM 2002 Copper
modifying the NPV and cumulative cash values, did not however Business Study – Report #4282 Runge Pty Ltd, January.
change the optimum cut-off grade selection. Poniewierski, J, 2002b. 2002 Copper Business Study– XPAC
Autoscheduler Model Refinements, unpublished internal report to
MIM 2002 Copper Business Study – Report #4327a Runge Pty Ltd,
CONCLUSION February.
The determination of an optimum cut-off grade in a large-scale Poniewierski, J, 2002c. 2002 Copper Business Study – 3500 Orebody
selective underground mine requires the ability to rapidly XPAC Scheduling, unpublished internal report to MIM 2002 Copper
Business Study – Report #4327b Runge Pty Ltd, February.
perform complex mine layout designs and multiple scheduling
Poniewierski, J, 2002d. 2002 Copper Business Study – XPAC Scheduling
runs. By establishing a simplistic but representative model of an
of Various Cut-off Grade Stope Layouts for Enterprise Mine,
orebody it is possible, with commercially available software, to unpublished internal report to MIM 2002 Copper Business Study –
make a defendable estimate of the ‘optimum’ cut-off grade to Report # 4327c, Runge Pty Ltd.
meet the business needs. In this study, such commercially Stephenson, P R and Vann, J, 1999. Common sense and good
available software was successfully used to generate multiple communication in mineral resource and ore reserve estimation, in
cut-off grade stope designs and to achieve the otherwise Proceedings Pacrim’99, pp 435 - 443 (The Australasian Institute of
insurmountable task of rapidly generating multiple scenario Mining and Metallurgy: Melbourne).
evaluations of these multiple stoping layouts. This task has been Thomas, G and Earl, A, 1999. The application of second-generation
achieved in a manner that honoured the real world rules and stope optimisation tools in underground cut-off grade analysis, in
complex trade-offs of a sublevel open stoping mining system. Proceedings Strategic Mine Planning Conference 1999, p 6 (The
The scheduling software also provided the mine management Australasian Institute of Mining and Metallurgy: Melbourne).
and operational personnel with a strong understanding of the Wheeler, A J and Rodrigues, R L, 2002. Cutoff-grade analysis at Fazenda
compounding complexities of the interaction between the Brasileiro: mine planning for declining gold prices, Trans Inst Min
Metall, 111, January – April, A(Min Tech):35-46.
orebody and the mining rules of the operation.
538 Kalgoorlie, WA, 23 - 25 April 2003 Mine Planning and Equipment Selection