Вы находитесь на странице: 1из 8

Optimisation of Cut-Off Grade at Mount Isa Mines Limited’s

Enterprise Mine
J Poniewierski1, G MacSporran2 and I Sheppard3

ABSTRACT In most studies where the changes in cut-off grade with respect
to production rate are assessed, the derivation of the maximum
The practical application of Lane’s theory on optimum cut-off grade
policy has to date proved difficult for selective stoping in large-scale sustainable production rates for an underground orebody have by
underground mining. The key to determining an optimum cut-off grade is necessity required a number of simplifications. One such
the ability to rapidly perform complex mine layout designs combined simplification is to calculate the tonnes per vertical metre and
with rapid output of multiple potential schedules. This paper describes assume the mine production rate is limited by the vertical
aspects of the detailed investigation into estimating a practical static advance rate. There can be a large range of rates used and a
cut-off grade for the two main orebodies in Mount Isa Mine’s Enterprise typical one used in Western Australian gold mines is 30 to 50
Mine. vertical metres per annum (McCarthy, 1993). While useful in
Rule based automated scheduling software was used to evaluate conceptual studies, the validity of such simplifications is highly
thirteen different stoping layouts (including design infrastructure and dependent on the mining method used. For a large-scale multiple
capital development) of the Enterprise Mine’s two main orebodies, with level open stoping operation such as Mount Isa Mine’s Enterprise
over 200 schedules generated. The investigation illustrates the application Mine, an assumption of vertical depletion of an orebody bears no
of commercially available software to solve the problems of generating
resemblance to the actual mining operations.
multiple cut-off grade stope designs and achieving the otherwise
insurmountable task of rapidly generating and valuing multiple scenarios The need to make such assumptions has in the past been a
for each stoping layout. result of the complexity and time-consuming nature of designing
Each scenario was evaluated using modelled net cash flows of the an orebody at different cut-off grades and then manually
mining, concentrating and smelting operations of the company and scheduling each orebody design at different production rates.
calculating NPV. The cut-off grade for each orebody was selected based Iterative mine planning has therefore rarely been undertaken for
on the cut-off grade that achieved maximum NPV – with an appropriate optimising cut-off grade, although previous authors (Wheeler and
production rate. Rodrigues, 2002; Hall, 2000; Hall, 2002) have however
Underground mine scheduling is a complex task involving the highlighted the need for a comparative analysis at different
adherence to a number of simple scheduling rules and the balancing of cut-off grades and different production rates.
several competing drivers. The study also found that:
This paper describes aspects of the detailed investigation into
• while each scheduling rule itself is simple, the compounding estimating a best practical static cut-off grade for the two main
complexities of their interaction preclude manual scheduling from
being a realistic option.
orebodies in Mount Isa Mine’s Enterprise Mine – a deep
underground copper mine. The investigation was undertaken as
• there is a maximum sustainable rate of production possible for any
given stoping layout, and that the actual maximum production rate is
part of a major review for the copper business at Mt Isa.
also a function of the required number of years of sustainable The approach described shows the first step towards achieving
production. a practical application of the cut-off grade theory of Lane (1997)
• the optimal cut-off grade was different for each orebody – a in selective underground mining.
recognition of the impact of the different characteristics of each Commercially available software was used to generate
orebody. simplified stope layouts for various cut-off grades for each of the
two orebodies in the mine. The mine designs for these different
INTRODUCTION cut-off grades were then repeatedly scheduled at various target
production rates, again using commercially available software, in
The calculation of the optimum cut-off grade for any particular order to determine a suitable sustainable production rate for each
mine is a complex procedure involving a considerable amount of cut-off grade stoping layout. The resulting production tonnage
geological interpretation, mine design, scheduling, and economic and grade profiles were used as input into financial models of the
and financial modelling (Hall, 2000). At any given production mining, concentrating and smelting operations of the company.
rate there is generally a particular cut-off grade that will Based on the maximum Net Present Value obtainable, the ideal
maximise the Net Present Value (NPV) of the mine – a grade that cut-off grade for each orebody was thus determined.
will invariably be higher than the operating breakeven grade. As Further development of the software tools used for this study,
the production rate at a mine is changed, it is also generally to a point where they will allow the rapid automation of an
found that the cut-off grade will vary – a result of fixed capital optimum cut-off grade policy for underground mining should be
and fixed operating costs being spread over greater or lesser an industry goal.
tonnages. A significant concept that emerged from the study was that for
each orebody design, the complex interaction of individually
simple scheduling rules that account for the unique
1. MAusIMM, Business Analyst/Senior Mining Consultant, Runge Ltd, characteristics of each orebody, result in there being a maximum
GPO Box 2774, Brisbane Qld 4000. sustainable production rate for a given stoping layout design. To
E-mail: jponiewierski@runge.com.au
exceed that maximum sustainable production rate, major mine
2. MAusIMM, Formerly Mine Engineering Superintendent – 2002 design philosophy changes are required.
Copper Business Study, currently Senior Mining Engineer, SRK
Consulting, PO Box 943, West Perth WA 6872.
E-mail: gmacsporran@srk.com.au THE ENTERPRISE MINE
3. MAusIMM, Manager 2002 Copper Business Study, MIM – Copper Located in mineral-rich north west Queensland, Mount Isa Mines
Study Group, Mt Isa Mines Private Mail Bag, Mount Isa Qld 4825. (MIM) operates one of the world’s largest underground mining
E-mail: ikshep@isa.mim.com.au complexes, mining copper and lead-zinc-silver orebodies.

Mine Planning and Equipment Selection Kalgoorlie, WA, 23 - 25 April 2003 531
J PONIEWIERSKI, G MacSPORRAN and I SHEPPARD

FIG 1 - Schematic cross-section of Enterprise Mine.

The MIM copper stream processes ore from the X41 Copper metres in plan and are extracted vertically to the full height of the
Mine and Enterprise Mine at Mount Isa and concentrate from orebody. The sublevel interval used is approximately 40 metres
MIM Holdings’ Ernest Henry Mine which lies about 40 km north which limits the length of blast holes. The mining method is
of Cloncurry. The Enterprise underground copper mine is the discussed in detail in numerous technical papers (Hall, 1992).
most recent copper ore source at Mount Isa and was developed
beneath existing operations at a cost of $A 370 million. It CUT-OFF GRADE THEORY APPLIED
commenced commercial production on 1 July 2000, and was
officially opened in August 2000. The accepted theory on optimum cut-off grade policy is that by
The Enterprise Mine is Australia’s deepest mine, with mining K Lane (1997). Practical application of Lane’s theory has
expected to a depth of 1800 metres below the surface. Ore from however proved difficult for selective stoping in underground
the mine has a head-grade of around four per cent copper. mining. The availability of automated scheduling software for
open pits has allowed significant advances in cut-off grade
The Enterprise Mine required construction of three major fixed
analysis in surface mining. However, difficulties in scheduling of
plant and equipment systems: a new ore handling system to
underground selective mining operations has deterred most
access the 3000 and 3500 orebodies, a refrigeration plant and a
operations from undertaking such an investigation of optimum
new paste fill plant. A schematic cross-section of the mine is
underground cut-off grades.
shown in Figure 1.
The Enterprise ore handling system consists of an underground The work presented in this paper is based on the assumption
jaw crusher, a conveyor connecting to the M62 internal shaft and that the corporate objective in cut-off grade selection is to
another conveyor connecting from the top of the M62 internal maximise the Net Present Value (NPV) of the mine, as is the case
shaft to the pre-existing U62 shaft and copper ore handling in the cut-off grade theory expounded by Lane. In many cases
system. The M62 internal shaft is 5.3 metres in diameter and 713 this is not the real objective of the corporation. Frequently
metres long. Its base lies approximately 1660 metres below the longest mine life, maximum Mineral Resource recovery or
surface. conversely achieving bottom quartile position on the industry
Virgin rock temperatures at Enterprise which reach more than cost curve, are cut-off grade selection objectives. These
60°C, along with the autocompression of ventilation air at the alternative objectives are not always openly admitted. They may
depth of mining, required installation of a major refrigeration be equally valid objectives alongside NPV for individual mine
plant. The refrigeration plant provides up to 22 MW of owners. Some Australian mining consulting firms have made
refrigerative cooling to condition the air entering the mine to comment on these issues over several years (Hall, 2000). In the
14°C. Four large ammonia compressors provide 540 L/s of cold study undertaken for the Enterprise Mine, NPV was chosen as
water to the bulk air cooler, where 580 kg/sec of downcast air the primary criteria for cut-off grade selection.
passes through large spray towers before being sent underground At a given point in the life of a mine and with a given future
via the R67 fresh air intake. production schedule, there is a particular cut-off grade that will
A major paste fill plant was also constructed for the Enterprise maximise the NPV. Lane has described three cut-off grade
mine. The paste fill plant is among the largest of its type in the equations that can be used to calculate the optimum cut-off grade
world and is designed to produce 450 dry tonnes of paste per for maximum NPV. The three equations are required to cover the
hour continuously as a 76 per cent solids-by-weight slurry. The three main operation scenarios possible:
paste is transported underground through two vertical boreholes, • marketing limited operations,
each 200 mm in diameter and 1100 m deep.
• treatment limited operations, and
The mining method utilised is sublevel open stoping (SLOS),
which has evolved over the last 70 years of operation, in the • mining limited operations.
copper and lead orebodies, to the present day design standards. In practice for long-term planning we are concerned with only
Stope dimensions for the Enterprise Mine are typically 35 by 35 two cases, the mining limited and the treatment limited cases.

532 Kalgoorlie, WA, 23 - 25 April 2003 Mine Planning and Equipment Selection
OPTIMISATION OF CUT-OFF GRADE AT MOUNT ISA MINES LIMITED’S ENTERPRISE MINE

worked out. A continuously falling cut-off grade is the ideal. A


major issue for this concept for many mining operations is that
adopting a high cut-off grade early in the mine life may result in
sterilisation of Mineral Resource. Shortened mine life and loss of
Mineral Resource are the result. This is one of the reasons that
companies may not adopt maximum NPV as the selection
criteria for cut-off grade. Open pit mines can avoid the
sterilisation cost by stockpiling ‘low-grade’ ore. Underground
mines mostly do not have this option.
Additionally, the concept of changing cut-off grade every year
in large underground mines in order to develop the optimum
cut-off grade policy is often not practical. The skilled geology
and engineering resources to redesign every stope for a new
cut-off grade each year are simply not available in the average
mine. A practical solution is to select either a few cut-off grade
steps over the life of mine or only a single life of mine cut-off
grade that shows the best NPV solution. In the study presented
here the decision was made to estimate the first ‘step’ in the
cut-off grade for the mine. To estimate this first step a life of
mine design and schedule over a range of cut-off grades is
required.
Scheduling and selectivity are the two key issues to be solved
in determining the mining limited cut-off grade – NPV curve.
Underground mine scheduling is a complex task involving the
balancing of several competing drivers. The same problem
applies to selecting the volume of rock from amongst the Mineral
FIG 2 - Optimum cut-off grade with respect to mining limited and Resource that can be mined as Ore Reserve. When the selection
treatment limited grade-NPV curves. and scheduling needs to be done at many cut-off grades the
problem can seem just too big. As stated in the introduction,
Figure 2 shows an idealised concept of how these equations simplifying assumptions must be made to control the size of the
may apply. The mining limited curve shows that for an orebody problem. Too many or too crude assumptions however can
constrained only by its own mining rate, there will be a cut-off destroy the sensitivity of the orebody to the calculations
grade that gives the best NPV. Application of a treatment involved. The aim is to achieve the right balance between the
capacity limit introduces a second intersecting curve. Where the simplifying assumptions and the real world complexity.
curves intersect is the physical capacity balance point, where the For any one mine design there are many possible production
mining and treatment capacities are balanced. schedules. Each possible schedule will generate a different NPV
In Case 1 of Figure 2, the treatment capacity available is large result for the orebody. The more complex the stoping design the
and the peak of the mining limited curve is at a higher cut-off more variation on NPV between alternative schedules. In simple
grade than the intersection point. Hence the mining limited curve narrow single orebody mines the schedule choices are limited, so
defines the best cut-off grade and we can ignore the treatment the variation in NPV will be small. For complex geometry and
capacity limit. In Case 2 of Figure 2, the treatment capacity is
large orebodies the schedule choices are greater and the NPV
smaller. The intersection of the curves is at a higher cut-off grade
than the peak of the mining limited curve. In this case we have to results will have more variation.
consider the treatment capacity limit and the best cut-off grade is In this study sophisticated, but commercially available
the capacity balance point which is higher than for the simpler software was used to solve the issues of selectivity and
Case 1. The difference in the two solutions is the mathematically scheduling.
explained by Lane’s opportunity cost concept.
Other possible combinations of interaction between these CUT-OFF GRADE DETERMINATION TECHNIQUE
curves exist. But these simple cases explain the approach used in
the Enterprise Mine study described here. The reader is referred The steps taken to determine the cut-off grade for each orebody
to Lane (1997) for more detail. were in summary (MacSporran, 2002):
The Enterprise Mine cut-off grade study assumed that the
situation described in Case 1 of Figure 2 existed for the orebodies A. Selectivity solution
being reviewed. The Enterprise orebodies are the highest grade Create simple mine designs at each cut-off grade.
copper deposits on the lease and processing capacity is twice the
likely mining capacity. Hence the problem was simplified to 1. establish the range of cut-off grades of interest. Simple
establishing the nature of the mining limited curve. economic analysis showed the likely range;
It also needs to be noted that the above analysis is valid for 2. select StopeSizor™ Smallest Mining Unit (SMU)
only one point in time. A true optimised cut-off grade policy will parameters;
consider the change in NPV of the mine over time. Lane (1997)
describes how this cut-off grade policy can be estimated. The 3. establish stope modelling criteria;
software to simulate this optimum cut-off policy is available for 4. generate ‘psuedo Mineral Resource’;
open pit mines. The problem is more complex for selective
underground mining operations. 5. design stopes for each cut-off grade model;
A fundamental concept in the optimum cut-off grade policy 6. establish dilution criteria for stope models; and
theory is that cut-off grade for a mine should start high and then 7. design infrastructure and capital development required for
decline over time reflecting the fall in the mine’s NPV as it is each cut-off grade.

Mine Planning and Equipment Selection Kalgoorlie, WA, 23 - 25 April 2003 533
J PONIEWIERSKI, G MacSPORRAN and I SHEPPARD

B. Scheduling solutions The SMU represent a block size that assist in establishing shapes
for stope designs. In the case of the Enterprise Mine the SMU is
Generate life-of-mine schedules for each cut-off grade mine 30 mN by 30 mE by 10 mRL. The results of the StopeSizor
design. There are many possible schedules for a mine. The use of analysis were output in a form suitable for review in Microsoft
rule based semi automatic scheduling software allows the Excel. Figure 3 shows a typical cross-section (representing a
identification of the best schedule for a given cut-off grade. 30 m of Northing) for one of the orebodies. The value within
1. build XPAC Autoscheduler™ model for each design; each grid represents the grade (per cent copper) of the SMU
block.
2. run, interrogate and re-run XPAC Autoscheduler scenarios
until a maximum sustainable production rate is achieved; and
3. output XPAC Autoscheduler life-of-mine schedule details.

C. Simple economic calculations


Evaluate all cut-off grade design maximum rate schedules in a
cash flow model to determine maximum NPV cut-off grade,
involving:
1. establish costs and pricing/revenue assumptions;
2. establish a cash flows analysis model, including costing of
mining, concentrating and smelting operations – including
both fixed and variable capital and operating costs;
3. conduct a sensitivity analysis on the key assumptions;
4. Mineral Resource cut-off grade is selected as the grade that
gives the highest cumulative cash value; and FIG 3 - Typical cross-section of StopeSizor output in Excel.

5. Ore Reserve cut-off grade is selected as the grade that gives


the highest Net Present Value. The ‘lumped’ blocks that match or exceed the cut-off grade
being reviewed are tallied as part of the pseudo Mineral
Thirteen different stoping layouts were generated in the study Resource.
of the Enterprise Mine’s two main orebodies. For each stoping
layout at least eight and up to fifteen different production rate Designing stopes for each cut-off grade model
targets were investigated. Additionally, a number of ‘What If’
scenarios were reviewed to establish the sensitivity of the The conversion from a pseudo Mineral Resource to a pseudo Ore
production schedules to desired but flexible mining constraints. Reserve required stope models to be created for each cut-off
In total, over 200 schedules were generated. grade being reviewed. A consistent set of rules established to
This has allowed the mine to determine its Mineral Resource construct the stope models had to be followed at each cut-off
and Ore Reserve cut-off grades. These cut-off grades were grade. This was to ensure that the analysis was relative to the
optimised from those previously used and are now specific for change in grade and not the change in the stope model design.
each of the two Enterprise Mine orebodies – recognition of the The rules used in constructing stopes with a SMU of 30 m by
impact that the unique characteristics of each orebody has on the 30 m by 10 m were:
final cut-off grade decision. 1. smallest stope height is 30 m (three SMU blocks high);
A number of the steps taken to evaluate the cut-off grade will
be discussed in more detail in the following sections of the paper. 2. bands of low-grade blocks can be stoped but no more than
20 m (two blocks) thick; and
CREATING THE CUT-OFF GRADE 3. sill pillars between stopes must be 30 m (three blocks) thick.
DESIGN MODELS Since the stopes are effectively a series of regular blocks, the
stope models were constructed in Excel by aggregation of the
Establishing a range of cut-off grades to evaluate SMU blocks with grades above the designated cut-off. A typical
cross-section through one of the orebodies is shown in Figure 4,
The geological resource block model was used to establish a with the constructed stopes outlined for a cut-off grade in this
range of cut-off grades to be evaluated. The grade distribution of case of 1.7 per cent Cu. The SMU blocks greater than or equal to
this selection ensured that the expected optimum cut-off grade the cut-off grade (used to create the pseudo mineral resource) are
was between the minimum and maximum. To reduce the amount highlighted. The corresponding tonnage and grade for each stope
of work required, no more than five or six cut-off grades were were tallied below the ‘stope’ column lower in the Excel
selected for evaluation. spreadsheet.

Generating a ‘psuedo Mineral Resource’ Establishing the dilution criteria for stope models
A ‘pseudo Mineral Resource’ refers to material that is considered Two principal conversion factors by which mineral resources are
mine-able at the selected cut-off grade. To establish a pseudo modified to produce ore reserves are mining dilution and mining
Mineral Resource for each cut-off grade model, Snowden’s recovery (Stephenson and Vann, 1999).
StopeSizor software† was used (Thomas and Earl, 1999). This For this study the dilution for the stopes was based on
software filters the block model and ‘lumps’ the geology model estimates of the Equivalent Linear Overbreak/Sloughing (ELOS)
blocks together within a specified Smallest Mining Unit (SMU). for the stope crown and any fill walls exposed. The stope crown
generally has mineralised material, the grade of which was
† Refer to http://www.snowdenau.com/software.htm for further estimated by using the grade of the SMU block directly above
information. the stope crown. The fill material has an effective zero grade.

534 Kalgoorlie, WA, 23 - 25 April 2003 Mine Planning and Equipment Selection
OPTIMISATION OF CUT-OFF GRADE AT MOUNT ISA MINES LIMITED’S ENTERPRISE MINE

1. a description of each segment of the capital development


including length and appropriate development rates for that
segment;
2. a listing of the pre-requisite capital development segment(s)
for each segment of the capital development; and
3. a listing of the pre-requisite capital development segments
for each stope.
For the largest of the cut-off grade designs (the lowest cut-off
grade design), the number of capital development segments
(horizontal and vertical) was of the order of 100 individual
segments (in comparison to about 330 segments for the detailed
final design model).

SCHEDULING THE CUT-OFF GRADE DESIGNS


FIG 4 - Typical cross-section of lumped SMUs to create stope
designs at 1.7 per cent cut-off grade. Preliminary
The next major step in the cut-off grade analysis was to
determine the maximum sustainable production rate for each
The total effect of the Fill dilution is dependent on the number cut-off grade model. The schedule that best represents the likely
of exposed fill masses or the Sub Level Open Stope (SLOS) production rate is the one that has consistent sustainable
state. The sequence in which the stopes are mined dictates this production over the shortest period duration.
state. A series of dilution possibilities were therefore assigned to In order to complete the required scheduling tasks in an
each modelled stope – one for each possible number of fill appropriate time frame, manual scheduling of the cut-off grade
exposures. During the XPAC scheduling process, the appropriate designs was out of the question. A rigorous and automated
dilution value was then assigned dynamically, dependent upon scheduling method was required – one that could allow large
the fill exposure state at the time of stoping. numbers of schedules to be run quickly as well as obey the
scheduling rules for each orebody and enable evaluation of the
Designing infrastructure and capital development dynamic and static scheduling factors for each orebody.
for cut-off grade model Having had some earlier experience with the heuristic-
scheduling program XPAC Autoscheduler™ (Poniewierski,
The capital development requirements (level and decline) and 2002a, 2002b, 2002c)‡, this software was chosen by MIM as
infrastructure requirements (ore-passes, ventilation shafts and giving the best representation of achievable production and grade
raises, and trucking loops) were needed to be determined for profiles.
each cut-off grade design. This involved determining a detailed Thirteen different stoping layouts were generated as part of the
but conceptual level of design. The level of detail required (for study. For each stoping layout at least eight, and up to 15
use in the XPAC Autoscheduler model and in the cash flow different production rate targets were investigated. Additionally,
analyses) was such that three lists were required: a number of the specific layout production rate scenarios were
investigated for varying schedule objectives. In total,
approximately 200 schedules were generated and analysed
‡ Refer to http://www.runge.com.au for further information. within a two-week period following model construction
(Poniewierski, 2002d).

FIG 5 - Plan view of XPAC database stope outlines for three of the six cut-off grade designs used for one of the orebodies shaded for
contained copper metal tonnages.

Mine Planning and Equipment Selection Kalgoorlie, WA, 23 - 25 April 2003 535
J PONIEWIERSKI, G MacSPORRAN and I SHEPPARD

Building the XPAC Autoscheduler model • Stope production (‘stoping’).


• Pre-fill activities: representing the time delay from
Model database completion of stope production to commencement of
backfilling – effectively the time to prepare the stope for
In essence, XPAC Autoscheduler is a programmed suite of tools
filling – primarily fill-wall construction (particularly on the
(a ‘toolbox’) which quickly converts a spatially defined XPAC
extraction level).
database (a mine’s reserves) into a time-based database (ie the
definition of scheduling). Autoscheduler determines its own • Backfilling with paste fill.
mining sequence based on user specified targets, rules, • Backfill curing: representing the time to cure the cemented
constraints and objectives. The constraints and rules instruct fill of a stope before preliminary activities are allowed to
Autoscheduler on what it cannot select in a given situation, and occur in stopes adjacent to the filled stope.
the objectives guide Autoscheduler in the choice of the next
stope to schedule from the alternatives available. Specifying the spatial characteristics of each stope was an
The Autoscheduler model built for this study was based on an essential part of this model’s set up. This involved identifying the
XPAC database that contained details about each stope in the other stopes that were adjacent to each stope and whether each
deposit. The database was used to store a number of attributes for stope was accessible externally or only accessible via other
each stope – tonnes, grade (including those for different dilution stopes. This allowed the scheduling behaviour of the model to
alternatives), and factors such as LHD tram distance, stope honour three important spatial rules:
height, extraction level and ore-pass allocation. Programming • First Adjacent Stope Rule, ensuring that two adjacent stopes
scripts were used to calculate more complex attributes (eg
could not be mined simultaneously.
allowable production rates for each stope).
Figure 5 shows stope outline plans and their contained metal • Second Adjacent Stope Rule, which prevented two stopes
tonnages for the XPAC database layouts for three of the six being mined simultaneously if they exposed two sides of the
cut-off grades used for one of the orebodies. same filled stope.
• Accessibility Maintenance Rule, which prevented selection
Model logic of a stope for mining, if selection would prevent access to
other stopes in the orebody (development mining through fill
The logic built into the Autoscheduler model faithfully replicated not practised).
the majority of the logic that mine schedulers had used in the
past, and extended that logic when previously used Examples of other rules and constraints used to control the
simplifications were no longer needed owing to the computing scheduling behaviour included the following:
power available. • A capital development time constraint, which was used to
Many different activities must be performed during the course ensure that a stope did not become available until sufficient
of mining a stope. The Autoscheduler model built for this study time to perform the prerequisite development, had lapsed.
allowed for five sequential activities to be scheduled – replicating
• Use of variable stope-specific production profiles, which
the stoping life cycle for each stope. These five activities were:
modelled the production ramp-up to a maximum production
• Preliminary activities: being the ‘near’ fill development rate for an individual stope, followed by a production
mining, the cut-off slot raising and the production drilling of ramp-down. The maximum rates achievable were a function
the stope. The time for completion of these activities of the tramming distance to the assigned ore-pass.
obviously varies dependent upon the size of the stope.

FIG 6 - Report graph outlining the monthly achieved production based on an annual target rate showing periods of
‘no production’ and ‘low production’.

536 Kalgoorlie, WA, 23 - 25 April 2003 Mine Planning and Equipment Selection
OPTIMISATION OF CUT-OFF GRADE AT MOUNT ISA MINES LIMITED’S ENTERPRISE MINE

• Use of stope sequence dependencies in order to impose a


specific predecessor – successor sequence on certain stopes.
Dependencies were used to ensure compliance with the mine’s
pre-determined ventilation restrictions, rock mechanics
requirements and maintenance of tramming access corridors.
Each rule itself is simple, but their interaction quickly becomes
quite complex.

Determining maximum sustainable production


rates
The constructed XPAC Autoscheduler model for each cut-off
grade design was then scheduled at increasing production rates in
order to find the maximum sustainable production rate for that
cut-off grade design.
Various objectives with varying competing priorities were tried
for each schedule scenario in order to:
• maximise the sustainable production rate;
• maximise the time for which this production rate could be
achieved;
• maximise the copper grade earlier in the schedule;
• minimise any production sequence ‘tail’ resulting from single
stope pillar retreats; and
• minimise the number of total fill exposures for any individual
stope.
The model’s scheduling results were interrogated through the
use of graphs, tables and animations of the mining sequence.
Figure 6 provides an example of an XPAC report graph outlining
the monthly achieved production based on an annual target rate.
This figure shows the periods of ‘no production’ or ‘low
production’ caused through an attempt to produce from the
orebody at too high a rate. These ‘no production’/‘low
production’ periods occur when no stope is available for
production, due to combinations of the spatial constraints of the
stoping sequence and activity rate limits of the operation. This
highlights the fact that there is a maximum sustainable rate of
production possible for a stoping layout.
Schedules were repeatedly re-run with different objective
priorities and manual modifications to stope dependencies until a
satisfactory scenario that met the previous listed objectives was
achieved. Figure 7 shows the annual tonnage and grade
production profiles for three decreasing annual target rates. As
can be seen, the problem of choosing a suitable scenario
becomes one of deciding how many years at the sustainable
maximum rate is sufficient. In general a sustainable maximum
production rate of at least five years was deemed necessary. This FIG 7 - Annual tonnes and grade production profiles at three
period was believed to be a commensurate time frame with an decreasing annual tonnage target rates.
efficient use of a set mobile-equipment fleet size, and a time
frame in which further resources can be delineated by future
The analysis resulted in a Cumulative Cash Value (a zero
diamond drilling – with the expectation that the rate could then
discount rate assumption) and Net Present Value.
continue to be maintained.
Each of these values was plotted against the other cut-off grade
models and the ‘peak’ of these graphs represented the optimum
Output life-of-mine schedule details cut-off grade values. An example of such a curve for one of the
The main output required from the schedules, for use in the cash orebodies is shown in Figure 8. It was also found that the optimal
flow analyses were the tonnes and grade production profiles (in cut-off grade for each orebody was different from each other – a
time). Additional data required however included backfill recognition of the impact of the different characteristics of each
quantities schedule, capital development schedule, operating orebody.
development schedule, production-drilling schedule, and a The ‘peak’ of the cumulative cash value curve represents the
raise-boring schedule. cash breakeven cut-off grade for the orebody. Below this grade,
the total cash generated is lower and therefore some of the
OPTIMUM CUT-OFF GRADE DETERMINATION material being mined must be loss making (and therefore below
the break-even cut-off grade). Above this grade, the total cash
Each schedule created for each cut-off grade model and generated is lower as a result of potentially profitable material
production target rate was put through a cash flow analysis not being mined.
model, modelling the mining, concentrating and smelting This cut-off grade has been used as the ‘Mineral Resource’
operations of the company, with assumptions of prices and cut-off grade, as resources can be quoted if they have reasonable
exchange rates for revenue determination. expectation of economic extraction, ie if they are cash breakeven.

Mine Planning and Equipment Selection Kalgoorlie, WA, 23 - 25 April 2003 537
J PONIEWIERSKI, G MacSPORRAN and I SHEPPARD

This has allowed the Enterprise mine to determine its Mineral


Resource and Ore Reserve cut-off grades. These cut-off grades
were optimised from those previously used and are now specific
for each of the two Enterprise Mine orebodies – recognition of
the impact that the unique characteristics of each orebody has on
the final cut-off grade decision.

REFERENCES
Hall, B E, 1992. Copper ore mining at Mount Isa Mines Limited, Mount
Isa, Qld, in Proceedings Underground Mass Mining Conference
1992, pp 173-177 (South African Institute of Mining and
Metallurgy: Johannesburg).
Hall, B, 2000. Practical cut-off grades for underground mining –
FIG 8 - Graph of cumulative cash value and Net Present Value for maximising value, or marginalising resources? Digging Deeper
cut-off grade designs modelled for one of the Enterprise Mine (AMC Newsletter), February.
orebodies. Hall, B, 2002. Cut-off Grades – Theory and Practice Workshop,
mineABILITY®, Townsville, 1 August.
Lane, K F, 1997. The Economic Definition of Ore, Second Edition
The cut-off grade at the peak of the NPV curve is a higher (Mining Journal Books: London).
cut-off grade than for the cumulative cash curve – a result of MacSporran, G, 2002. Enterprise Mine cut-off grade analysis and results,
influence of the opportunity costs (as per Lane’s theory). This is unpublished internal report to MIM 2002 Copper Business Study.
the grade used for Ore Reserve calculation and mine design. McCarthy, P L, 1993. Economics of Narrow Vein Mining, in Proceedings
A sensitivity analysis was also undertaken and indicated that Narrow Vein Mining Seminar 1993, pp 89-97 (The Australasian
the operating cost was the most sensitive parameter in selecting Institute of Mining and Metallurgy: Melbourne).
the optimum cut-off grade. The discount rate used in calculating Poniewierski, J, 2002a. 3000 Orebody XPAC Study – Results and Model
the NPV, the copper price and the exchange rate, while Description, unpublished internal report to MIM 2002 Copper
modifying the NPV and cumulative cash values, did not however Business Study – Report #4282 Runge Pty Ltd, January.
change the optimum cut-off grade selection. Poniewierski, J, 2002b. 2002 Copper Business Study– XPAC
Autoscheduler Model Refinements, unpublished internal report to
MIM 2002 Copper Business Study – Report #4327a Runge Pty Ltd,
CONCLUSION February.
The determination of an optimum cut-off grade in a large-scale Poniewierski, J, 2002c. 2002 Copper Business Study – 3500 Orebody
selective underground mine requires the ability to rapidly XPAC Scheduling, unpublished internal report to MIM 2002 Copper
Business Study – Report #4327b Runge Pty Ltd, February.
perform complex mine layout designs and multiple scheduling
Poniewierski, J, 2002d. 2002 Copper Business Study – XPAC Scheduling
runs. By establishing a simplistic but representative model of an
of Various Cut-off Grade Stope Layouts for Enterprise Mine,
orebody it is possible, with commercially available software, to unpublished internal report to MIM 2002 Copper Business Study –
make a defendable estimate of the ‘optimum’ cut-off grade to Report # 4327c, Runge Pty Ltd.
meet the business needs. In this study, such commercially Stephenson, P R and Vann, J, 1999. Common sense and good
available software was successfully used to generate multiple communication in mineral resource and ore reserve estimation, in
cut-off grade stope designs and to achieve the otherwise Proceedings Pacrim’99, pp 435 - 443 (The Australasian Institute of
insurmountable task of rapidly generating multiple scenario Mining and Metallurgy: Melbourne).
evaluations of these multiple stoping layouts. This task has been Thomas, G and Earl, A, 1999. The application of second-generation
achieved in a manner that honoured the real world rules and stope optimisation tools in underground cut-off grade analysis, in
complex trade-offs of a sublevel open stoping mining system. Proceedings Strategic Mine Planning Conference 1999, p 6 (The
The scheduling software also provided the mine management Australasian Institute of Mining and Metallurgy: Melbourne).
and operational personnel with a strong understanding of the Wheeler, A J and Rodrigues, R L, 2002. Cutoff-grade analysis at Fazenda
compounding complexities of the interaction between the Brasileiro: mine planning for declining gold prices, Trans Inst Min
Metall, 111, January – April, A(Min Tech):35-46.
orebody and the mining rules of the operation.

538 Kalgoorlie, WA, 23 - 25 April 2003 Mine Planning and Equipment Selection

Вам также может понравиться