Академический Документы
Профессиональный Документы
Культура Документы
DIRECTIONAL
DRILLING DESIGN
PROJECT 16
CIVE 609
Kwesi Wells
1406940
TABLE OF CONTENTS
1.0 Project Description............................................................................................... 2
2.0 Referenced Documents........................................................................................ 3
3.0 Design Criteria and Assumptions..........................................................................3
4.0 Design Methodology............................................................................................. 3
5.0 Rod by Rod Plan.................................................................................................... 4
6.0 DR Selection......................................................................................................... 6
7.0 Bore Construction Methodology........................................................................... 7
8.0 Drill Fluid Management........................................................................................ 8
9.0 Tooling selection................................................................................................... 9
10.0 Conclusion........................................................................................................ 10
11.0 References........................................................................................................ 10
11.0 Appendix.......................................................................................................... 11
LIST OF TABLE
ground level
Required clearance 1
120 m from pipe entry point 8m below
ground level
Required clearance 1
Table 1 Project Specifications and Guidelines
Recommendations
5-10
8-15
> 50
Actual Design
8
10
1026
(meters)
Radius of Curvature Exist
> 50
657
(meters)
Table 2: Angles and Radius of Curvature Guidelines
The rod by rod plan was then drafted using these exist and entry angles. A draft plot
is presented below in Figure 1.
200
400
600
800
1000
1200
1400
-5
-10
-15
DEPTH (FEET)
-20
-25
-30
-35
-40
L4=469.8 ft
L3=466.3 ft
DISTANCE (FEET)
6.0 DR Selection
With the bore angles confirmed, the next phase was to select the optimum pipe DR.
This design would incorporate three (3) key scenarios during the life cycle of the
pipe:
1. Operational Loads: Under deformed, collapsed, stable bore conditions
2. In-Service Loads: deformed, collapsed, stable bore conditions.
Under different operational loads the highest pressure occurred under risk of
collapse to a value of 180 kPa. This value minus the pressure associated with water
was used to model the earth pressure at 141.12 kPa. A summary of model outputs
are highlighted below in Table 3.0:
DR
Deflectio
Status1
n (%)
Collapse
Stat
Wall
Strength
us2
Compressi
(kPa)
7.3
9.0
11.5
13.0
Status3
ve Stress
(psi)
2.85
Pass
760
Pass
74.70
5.82
Pass
276
Pass
92.10
11.33
Fail
93
Fail
112.57
22.00
Fail
50
Fail
138.15
Table 3 Simulation Results for Operational Loads
Pass
Pass
Pass
Pass
Both DR 7.3 and 9.0 met the acceptable design thresholds under operational loads.
DR 11.5 and 13.0 failed under the deflection and collapse strength tests but passed
the wall compressive stress test. This was expected as this criteria rarely controls
the design outcome. The model was then run to calculate the performance of the
pipes under installation loads. This test was done considering no roller and no
ballast. All pipes pass the pullback load test as shown in Table 4.0:
Pipe DR
Maximum
Status1
Unconstrai
Status2
6
Pullback
ned
Stress (psi)
Collapse
Strength
7.3
9.0
11.5
13.0
1
2
(psi)
478.0
Pass
72.65
595.0
Pass
34.11
732.0
Pass
16.58
906.0
Pass
7.88
Table 4: Simulation Results for Installation Loads
Pass
Pass
Fail
Fail
Under installation loads DR 7.3 and 9.0 performed excellent in both scenarios. While
DR 11.5 and 13.0 both passed the pullback loads test but failed the unconstrained
collapse strength test. The final decision was to proceed with DR 9.0 since it would
be the easier pipe to work with and less costly. Further analysis would be done to
observe its performance under different construction methodologies.
All scenarios were run in the simulation to get the best methodology to be used for
installation. The results are presented below in Table 5 below:
Pipe
No Rollers
With Rollers
With Rollers
No Rollers
Sections
and No
and No
and Ballast
and with
Ballast (lbs)
Ballast (lbs)
(lbs)
Ballast (lbs)
TA
93,564
17,697
17,697
93,564
TB
129,544
75,066
41,466
95,945
TC
147,539
117,512
57,968
87,996
TD
158,133
148,118
69,748
79,763
Table 5 Results of Impact of Rollers and Ballast on Pullback loads for 30" Pipe DR 9
Using a construction methodology with roller and ballast the least amount of
pullback load on the pipe occurred. The ballast considered during design was water.
The option of the ballast can be changed if desired but calculations would be
reworked to ensure compliance with best practices. A recommendation is being
made to execute the installation with the assistance of rollers and ballast
Diameter (Inches)
8
18
28
38
42
The drill speed would be set at 60 feet per hour. This would allow sufficient time for
the cutting to be removed and a reasonable pump capacity to be achieved. Total
volume of fluid to be removed is estimated 900 m 3. Pump capacity required to
remove the soil is estimated at 678 L/min. All fluid would be stored in ten 100 m 3 on
the project site.
calculated to 197.25 kPa. This is lower than the overburden pressure of 224 kPa.
Fracture during the drilling campaign most likely be avoided.
Recommended Rig
Maximum Limits
Specifications
100,000
1100 psi
870
80,000
677
(L/min)
Table 6: Drill Rig Recommended Specifications
A special request would have to be made since most of the medium rigs are
outfitted with 20 feet rods and 3- 4 inches drill rods. Since the project calls for 10
feet rods and 1.625. A special outfitting would have to be done to match the
project requirements. A recommended drill rig for the job is a Vermeer D100x140
15. This rig would be able to meet the project requirements. This medium rig must
be used in association with rollers and ballast or only ballast only. If these aids are
not going to be used a larger rig would be needed.
Supereamers design model should be used as this would allow exceptional mixing
action. This type of reamer could be used on Vermeer D100x140. No integration
problems should occur. Also required reaming sizes are available on the market. A
barrel reamer should be used at the hole diameter. This would assist in swabbing
out the hole.
For this borehole project, a recommendation is being made for the drill fluid
composition.
1.
2.
3.
4.
Bentonite Based
Soda Ash Add if the pH of the makeup water is between 8-9
No SAG to enhance the capability of the fluid ( lb per 100 gallons)
Quick TROL LV to enhance the filter cake building ability of the fluid ( lbs
per 100 gallons)
This is just a base recommendation for initiate drill fluid mix. As the project
progresses, adjustments should be made to achieve the desired results.
10.0 Conclusion
The project could be executed within 15 days using a product pipe of 30 OD at DR
9. A medium rig could be used with the assistance of rollers and ballasts to achieve
this bore. This would reduce the installation cost. The design should be peer
reviewed before final approval is construction commences. All owners of buried
pipelines should be informed of the impending works. This would gather information
about exact location of pipelines and any obstacles encountered during their
projects. Environmental and safety regulations should be followed during the works.
11.0 References
American Society Testing Materials (ASTM).1999 Standard Guide for Use of MaxiHorizontal Directional Drilling for Placement of Polyethylene Pipe of Conduit under
Obstacles, Including River Crossings. F1962-11, West Conshohocken, Pa.
Plastics-Pipe Institute Handbook (2014) Horizontal Direction Drilling, Chapter 12,
Irving Texas
10
11.0 Appendix
ROD BY ROD CORDINATES FOR ENTIRE BOREPATH
11
Rod
Number
Angle
Radians
0.000
1.000
2.000
3.000
4.000
5.000
6.000
7.000
8.000
9.000
10.000
11.000
12.000
13.000
14.000
15.000
16.000
17.000
18.000
19.000
20.000
21.000
22.000
23.000
24.000
25.000
26.000
27.000
28.000
29.000
30.000
31.000
32.000
33.000
34.000
35.000
36.000
37.000
38.000
39.000
40.000
41.000
42.000
43.000
44.000
45.000
46.000
47.000
48.000
49.000
10.000
9.737
9.474
9.211
8.948
8.684
8.421
8.158
7.895
7.632
7.369
7.106
6.843
6.579
6.316
6.053
5.790
5.527
5.264
5.001
4.738
4.474
4.211
3.948
3.685
3.422
3.159
2.896
2.633
2.369
2.106
1.843
1.580
1.317
1.054
0.791
0.528
0.264
0.001
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.175
0.170
0.165
0.161
0.156
0.152
0.147
0.142
0.138
0.133
0.129
0.124
0.119
0.115
0.110
0.106
0.101
0.096
0.092
0.087
0.083
0.078
0.074
0.069
0.064
0.060
0.055
0.051
0.046
0.041
0.037
0.032
0.028
0.023
0.018
0.014
0.009
0.005
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
X
Coordinate
s
9.848
19.704
29.568
39.439
49.317
59.202
69.095
78.993
88.899
98.810
108.727
118.651
128.579
138.514
148.453
158.397
168.346
178.300
188.257
198.219
208.185
218.155
228.128
238.104
248.083
258.065
268.050
278.037
288.027
298.018
308.012
318.006
328.003
338.000
347.998
357.997
367.997
377.997
387.997
397.997
407.997
417.997
427.997
437.997
447.997
457.997
467.997
477.997
487.997
497.997
Y
Coordinate
s
-1.736
-3.428
-5.074
-6.674
-8.230
-9.740
-11.204
-12.623
-13.997
-15.325
-16.607
-17.844
-19.036
-20.181
-21.282
-22.336
-23.345
-24.308
-25.226
-26.097
-26.923
-27.703
-28.438
-29.126
-29.769
-30.366
-30.917
-31.422
-31.881
-32.295
-32.662
-32.984
-33.260
-33.489
-33.673
-33.811
-33.903
-33.950
-33.950
-33.950
-33.950
-33.950
-33.950
-33.950
-33.950
-33.950
-33.950
-33.950
-33.950
-33.950
Table
7: Drill
Rig
12
Recommended Specifications
INPUT DATA
Bore Specs
Pipe Surface Length
(m)
Depth of Cover (m)
Outside Diameter
(inch)
Drill Rod OD (inches)
Drill Rod L (inches)
Meters
400
Feet
1312
10
30
393.7
0.762
1.625
10
0.041275
Angles
Bore Exit Angle (Alpha)
Bore Entry Angle (Beta)
Degrees
8
10
Radians
0.13963
0.17453
OUTPUT DATA
Radius of Curvature
Pipe Entry (m) Rin
Pipe Exit (m) Rout
1025.876984
656.56127
Pipe Sections
L2 - Entry
L4 - Exit
L3 - Horizontal
Total
CALCUATTIONS
Lengths (m)
143.24
114.59
142.17
400.00
BORE
PLAN
Lengths (feet)
469.8
375.9
466.3
1312.00
13
1.00
20.00
16.83
19.84
10.00
999.74
30.34
6.00
4.00
9.81
10.00
28200.00
2.00
0.58
0.45
9.00
39.23
180.35
141.12
42.00
1.07
0.70
1.15
0.32
0.59
122.92
39.23
180.35
122.92
0.00
0.00
40.06
276.18
14
INPUTS VARIABLES
OD (inches)
DR
Earth Pressure (kPa)
Modulus of Elasticity (psi)
Modulus of Elasticity (Mpa)
Water Density (lbs/ft3)
Poisson Ratio
Radius of Curvature - Pipe Entry (m)
Radius of Curvature - Pipe Exit (m)
30.000
9.000
141.121
28200
194.432
62.400
0.450
1025.877
656.561
9.807
15
141.12
30
9
3.333333333
2947.381121
Outputs
Wall Compressive Stress (psi)
Allowable Compressive Stress (psi)
92.10566004
1150
16
Inputs Variables
L1 (m)
L2 (m)
L3 (m)
L4 (m)
Depth of Cover (m)
OD (inches)
DR
Bore Exit Angle
(Alpha)
Bore Entry Angle
(Beta)
Va (no rollers)
Va (rollers)
Vb
Water Density
(lbs/in3)
Pi
S.G of Pipe , Ya
S.G of Mud Slurry ,
Yb
S.G of Ballast Fluid
(water) , Yc
Conversions and
Constants
Wa (lbf/in)
9.635902902
Wa (lbf/ft)
115.6308348
No Ballast
Wb (lbs/in)
Wb (lbs/ft)
28.6743786
344.0925432
13.22414161
158.6896994
Outputs
Ta
Tb
Tc
Td
0.0000098
1
No Rollers + No
Ballast
93563.41
129543.48
147538.41
158132.07
1.6862830
08
Rollers +
No Ballast
17696.22
75065.76
117511.46
148117.02
Rollers +
Ballast
17696.22
41465.85
57968.11
69747.57
No Rollers
+ Ballast
93563.41
95943.57
87995.05
79762.63
17
Hydrokinetic Force
Tk (lbf)
3393.36
3393.36
3393.36
3393.36
14.7105
10
28200
2
0.58
0.251455
Tensile Factor Fr
0.851777
70721
0.001953
34.1195
21.33023
18
400
80
2.5
Reaming Sequence
(inches)
8
18
28
38
42
893.9478895
132
6.772332496
60
10
0.67723325
Drill Pass
1
Total (min)
Total (hr)
Total (days)
Drill Time
1312
6560
109.3333333
9.111111111
0.2032
0.4572
0.7112
0.9652
1.0668
Volume of Soil
(m3)
12.97339341
52.70441072
93.24626512
133.7881195
64.86696704
357.5791558
677.2332496
100
8.939478895
19
677.2332
1066.8
762
Va (m/s)
0.025781
dP/dL (kPa/m)
Length (m)
Circulation Pressure (kPa)
0.125251
400
50.10058
147.15
197.2506
224
180.3494
20