Вы находитесь на странице: 1из 4

• PATTON REPORT NO.

3t

DESIGNED FOR FAILURE


01975 Patton Life Safety Systems, Inc.

Water, man's greatest ally on the fire front, suffered a most with fire department hose streams; an insurance inspector
severe setback in the 1890's when the National Fire Protection would show up at the scene the following day. He would
Association drew up a sprinkler system design standard. This immediately count the open sprinklers. When he got to the
deadly blow was dealt to water in two ways. 100th and final open head, he would then take that magic
First, the standard established a crazy quilt mix of rules number 15 (presuming 15 GPM should have come out of each
that made sprinklers so extremely costly that probably 98% of and every open head) and multiply by the 100 open heads.
the buildings constructed in this century have been Then he would promptly conclude that 1500 GPM was the
constructed without built-in fire protection. The prohibitions true required water flow for a "black-eyed pea canning plant."
against practical sprinkler systems is the primary underlying The next step in this scientific evaluation would be the
cause of our present awsome national fire loss. checking out of the water supply. He would find the highest
Secondly, the rules (which are mostly based on the law of sprinkler head was say 46 feet above the ground. Then he
averages) sometimes permitted such weak design of sprinkler would convert the elevation into being equivalent to 19.8 psi.
systems that a substantial percentage of the time that He would add to this the "magic number" of 15 psi (required
sprinklers were called upon to perform — they failed. at the top of the riser.) This adds to 34.8 psi. The next step
was to check out the water supply to see how many gallons
THE "FACTORY" SPRINKLERS actually had been available at 34.8 psi. Let us assume he found
out that the water mains would have delivered only 940 GPM
It all began when a sort of a "Factory" type of sprinkler
at 34.8 psi.
layout was selected as a "good, average, reliable" type of
Well! There was the problem, he would conclude! The
system. Sprinkler spacing was 10 feet by 10 feet, the orifice
sprinkler design required 1500 GPM (100 open sprinklers
was approximately 1/2 inch, and the water supply had to have
ti mes 15 GPM). But, his test showed only 940 GPM had been
approximately 15 psi at the top of the riser. No one attempted
available at the required pressure of 34.8 psi! The water supply
to determine:
was 560 gallons per minute short. NO WONDER IT FAILED!
a) Actual density of water discharge.
b) A real relationship between water density and fire THE SYSTEM FAILED—NOT THE WATER
loading (hazard). SUPPLY
c) The conditions which could produce excessive
But of course, the inspector's analysis was absurd. The
operation of sprinklers, thus water depletion at the
sprinkler system did not "FAIL" at that point where 63 heads
fire site and system failure.
were open and the 940 GPM that was available in the mains
Since no one really knew what they were doing in the
was all used up. No indeed! The sprinkler system FAILED
sprinkler design (except that they were using a system that
when 4 sprinklers opened directly above the fire and FAILED
somehow worked most of the time) soon enough the failures
to control the fire. At this point there was 940 GPM available
began to occur. The failures were inevitable because there was
to the sprinkler system — but the sprinkler system was not
no real method of judging the level of "hazard" and no real
capable of delivering even 60 gallons to the fire site. The
method of measuring "performance."
Of course, since there was a repeat of the same design delivery system (not the water supply) was so weak that less
over and over again, but under vastly differing conditions — than 10% of the water available could be delivered to the fire.
there was a percentage of "high hazard" risks that were "too So, the fire grew. Then more sprinklers opened. This
tough" and at the other end of the scale there were "low resulted in even less density at the fire site. Then more heads
hazard" properties being subjected to "overkill." opened. Of course, the density at the fire site dropped once
During this stage of sprinkler "non-design" apparently again. And so it went. The only thing significant about the
no one worried about the "overkill" problem, but a lot of 100th sprinkler opening was that was the point where the fire
people did worry about the "underkill" problem. Why? department gained control over the fire.
because factories were going up in smoke. The inspector believed that the system failed because more
than 63 heads opened. But he was wrong. The truth was that
MAGIC MATHEMATICS 63 heads opened because the system had already failed.

There began a practice years ago that to a surprising degree CONFUSIONS CAST IN CONCRETE
still exists today. After a fire occurred in say a "black-eyed pea No self-respecting insurance inspector is going to walk away
canning plant" (for example) and an excessive number of from half a factory without making a "true and proper"
sprinklers opened (say 100), and the fire was finally controlled report.
Since the sprinkler design produced non-calculated densities even before they arrived, didn't they?
over an indeterminate area protecting undefined fire I would like to report that this sprinkler system "control"
potentials, there sure was nothing to be gained by analyzing of the rubber tire warehouse fire helped bring down the water
that piping system up in the roof. If you don't know what it's supply demand for the black-eyed pea canning factory, but
supposed to do to begin with, how are you going to equate it? things did not work that way. Water supply "failure" proved
Equate it to what? you needed more water, but if the system "worked" this only
But if you can count the heads, multiply by a magic proved the sprinkler system was a very reliable system when
number, produce a "required" water supply, and test the real properly fed by water.
water against the theoretical water need; then you really have
something — or so the inspectors reasoned.
SPRINKLER HYDRAULICS EXPLAINED
Having dtermined that a black-eyed pea canning plant The single most important thing to understand about
needed 1500 GPM, but in this case only had 940, the inspector sprinkler system design is that nearly all fires start off small.
would promptly file a report in triplicate to the home office. ( As with all rules, there are exceptions. But, once the
The actuaries, most of whom wouldn't have recognized a fundamentals are understood, then the exceptions can be
sprinkler head if it walked up and bit them, could then pump handled.)
the data into their computer systems of the day. The following The second thing to know about fire sprinkler systems is
Spring an executive committee of underwriters would meet that initially only one to four sprinklers open. These are the
and vote that a sprinkler system serving a black-eyed pea ones closest to the fire. (Again, there are some exceptions, but
canning factory would require a 2000 GPM water supply (note let's learn the fundamentals before going on to the unusual
the safety factor). If you had a black-eyed pea canning plant — problems.)
but didn't have 2000 GPM, you simply could not install an The third thing to know is that once the initial sprinklers
"approved" system. Of course, you could always install a new open, whether it be one or four, there will be no additional
water supply — and then install the sprinkler system, but this sprinklers that open unless there are special design or control
was not always practical. problems. There are two excellent reasons why a fire does not
No two thousand GPM, no sprinklers. Let it burn. As you open excessive heads.
can see, it was all very, very scientific. First, when the heated gases rise and strike the ceiling, and
flow outward, the temperature drops as the gases move away.
HALLELUJAH, WE'RE O.K. Heat is being dissipated rapidly (it is still a small fire), and
Of course, things didn't always work out so badly with the cooler air is mixing with the hot gases. So, a sprinkler eight
magic mathematics. Many times the sprinklers worked just feet from the fire is subjected to a higher temperature than
fine. For example, the very next day our brilliant inspector one fifteen feet away. The sprinkler subjected to the higher
might be off to visit a fire damaged tire warehouse. The night temperature will open first.
before, a fire had started in a stack of tires, and pretty soon A second reason why "close-in" heads open before
two sprinklers opened above the fire. "far-out" heads is because the velocity of the hot gas moving
Now, this warehouse had the magic 15 psi at the roof, by the "close-in" head is much greater. The velocity of a gas
which meant that there was about 7 psi at the orifices of the along the plane of the ceiling decreases as the ratio of the
opened sprinklers. The tire stack was delivered a water density square of the distance from "ceiling zero." Did you ever cool
of about 0.16 GPM/Sq. Ft., which was a nice density for a soup by blowing across the surface of a spoonful? Think of the
school — but not so nice for tire storage. So, with only a small close-in head being subject to a very hot wind; and the far-out
density falling on a very hot fire, the fire got a little hotter. head in cooler, and also more stagnant, air. So, the sprinklers
But, this was the highest density the system would ever directly over the initial small fire will open first. With only one
deliver. The next thing you know, three more sprinklers to four sprinklers open, the system water pressure is at its
opened, and the density at the fire dropped to 0.12 GPM/Sq. maximum. Any further opening of sprinklers will drop system
Ft. This didn't do the fire much good at all, so it flamed a pressure and reduce density at the fire.
little higher. And so, shortly, another five sprinklers opened. The conditions for automatic fire control are never going to
Of course, the density dropped again to 0.09 and the fire be better. The fire is at its earliest, most readily controllable
burned much fiercer. Well, surprise, surprise, another ten state. The density and pressure directly above the small fire is
sprinklers opened. Things were getting rather desperate now, at its maximum. If the system can't control the fire now — at
because the density was down to 0.05 and the fire was this point — conditions will deteriorate.
spreading fast. But, at this point the cavalry arrived in the
form of the Fire Department. They got their heavy streams
THE SECRET
working and because they arrived in time, quick control was
INGREDIENTS OF FIRE CONTROL
achieved. I call them "secret ingredients" because for more than 75
The inspector arrived the following day and true to form, years the insurance industry and the NFPA-13 sprinkler
he counted up 20 open sprinklers. Of course, he promptly committee has been able to ignore them. These ingredients
multiplied by 15 and determined that 300 GPM was the magic are:
number. So, this time he found that the sprinklers had 1 Initial density at the fire site.
"controlled" the fire with only 300 GPM, while the water 2. Initial pressure at the fire site.
supply was good for a thousand. "Great! This just goes to (The sad but true fact is that neither the insurance rules or
show what those sprinklers can really do when the water's the NFPA-13 rules consider "initial" density or "initial"
right", he advised the owner. This time the inspector was able pressure, the two most important factors of sprinkler design.
to report a "successful" sprinkler operation, and this too went This still holds true even today.)
into the tables confirming the validity of the system. His only If one to four sprinklers open, and the water is discharged
complaint was all that water thrown around by the fire over the fire, and then additional sprinklers open, it is certain
department because, after all the sprinklers had the fire licked that one or both of these undesirable conditions exists:
2
1. Inadequate water density delivered to the fire. 4. In the testing programs they "choked" down the
2. Inadequate cooling of the ceiling temperatures. valves to test for "minimum" pressure and densities.
The insurance industry, with its Mickey Mouse sprinkler Sure enough, by testing at low pressure and density,
engineering rules, virtually guarantees that one or both of the they would open all the sprinklers in three counties, and
above conditions will exist in a high percentage of the cases "prove" the need for huge water supplies and a hundred
where sprinklers are called upon for protection! open sprinklers.
The NFPA statistics indicate that the "standard" sprinkler 5. They built all this foolishness into the hydraulic
system FAILS nearly 4% of the time it is called upon to design standards.
operate, which is horrible enough — but, if we were to set the 6. Everytime a sprinklered factory burns down they've
failure point of sprinklers at that point where the FIFTH "proven" themselves "right."
sprinkler opens, then the failure rate would be nearly
TWENTY-FIVE PERCENT OF THE TIME! AN EXAMPLE
PRESSURE The FIA high piled stock tests is an example. In most of
The Australian sprinkler system out performs the American the tests the water supply was choked down to produce a low
system. Why? density. There are examples:
One reason is that all sprinkler systems in Australia are tied Series 1, Pile height 21', shredded paper in cardboard
into the fire department so a prompt and automatic response cartons
is guaranteed. The Australian fire department gets in early. Test 1 — density 0.20 GPM/Sq. Ft. — 12 sprinklers
But there's another reason and it is that pressure is opened
increased in the system above the check valve (with a small Test 3 — density 0.40 GPM/Sq. Ft. — 4 sprinklers
pump to prevent false alarms due to water surge). The opened
sprinkler system is made into a "pressure tank." Even though Series 1, Pile height 21', 2 lb. Polystyrene in each
that initial burst of high pressure discharge may last only for cardboard carton
30 or 60 seconds, it will drop ceiling temperature RIGHT Test 4 — 0.4 GPM/Sq. Ft. — 26 sprinklers opened
NOW! Extra heads won't open — and water density at the fire Test 7 — 0.6 GPM/Sq. Ft. — 6 sprinklers opened
site is maximized. The British experience with small pressure Note the very dramatic ability to reduce the number of
tanks confirms this also. open sprinklers with a higher density.
Why don't we use high pressure on sprinkler systems in the But did FIA conduct many 0.6 GPM/Sq. Ft. tests, or even
U.S.? Well, the policy of the insurers, including the two higher density tests? No. Only one test run at a density above
insurance industry testing laboratories, have worked against it. 0.40 GPM/Sq. Ft.
Look at the U.L. or F.M. pump listings. With very few The FIA moved right into the fairy tale of:
exceptions the only "approved" pumps are 500 GPM and a) low density design
greater. The installed cost of a fire pump is $10,000 to b) open most the heads in the building
$15,000 and up. There is no way to install a low cost high c) put Lake Michigan on a tower
pressure pump on a sprinkler system. The price is too high for For example, at the time of the tests I worked for the
90% of the buildings that need protection. Distilling Industry, and the FIA recommendations (which
And, even more devastating, the sprinkler design rules do eventually became "legal" recommendations) also covered 21
not recognize the advantages of high pressure. An "almost foot high "alcohols in bottles." The FIA recommended system
certain to fail" sprinkler layout (the pressure will drop to 7 psi for a "high hazard" whiskey cased goods warehouse would
at the orifice with only two heads open) is given equal status have a density of 0.45 GPM/Sq. Ft. over 6000 to 12,000 Sq.
with a high pressure system. Ft. (depending on "conditions"). This, in effect, was designing
for up to 120 open sprinklers and a water supply of up to
DENSITY 6000 GPM.
Since most "standard" sprinkler systems installed in the Later, we in the Distilling Industry went into Factory
U.S. produce an "unknown" density the statistical correlation Mutual laboratories, and tested this 21 foot high storage of
between "density", "fire loading", and "failure" is almost whiskey in bottles in cartons, applied a 0.6 GPM/Sq. Ft. and
non-existant. Mickey Mouse engineering has deprived us of controlled this fire with 4 (yes, just 4) sprinklers using only
good performance data. 190 GPM. Fantastic wasn't it? The regulations said 6000 GPM,
But it is sad to relate, even in recent years when "hydraulic we did it with 200 GPM.
design" was being applied to sprinklers, the old fairy tales were But I considered 0.6 GPM/Sq. Ft. to be marginal and
still fouling up the designs and the performance data. The wanted to test at 0.8 density to get a quicker "kill" — but this
inspector who counted 100 open heads in the black-eyed pea plan met with very strong opposition from insurance executives
canning factory is still setting the design parameters for even who advised my superiors against it. fought like hell to get
the "highly protected risk" rated properties today. 0.6) One of their objections was that such densities are
Historically, here is what has happened: "impractical", but this only proved how little they knew
1. Mickey Mouse engineering produced sprinkler systems about sprinkler design because it is possible to design for an
that were low pressure, low density and guaranteed to initial density of 0.8 GPM/Sq. Ft. or even 1.5 GPM/Sq. Ft.
fail. while at the same time knocking 40% to 50% off the cost of
2. The sprinkler systems did fail and the opening of 25, the protection.
50, 100 and even 200 sprinklers were not that unusual. So, much of the sprinkler testing in recent years, including
3. The insurers became convinced that from 1000 to the high rack tests, were creating new fairy tales rather than
5000 GPM was needed for a "good" supply, and they dispelling the old fairy tales. I will wager that 90% of the
keyed their testing to very low densities over very large sprinklers in use today will deliver less than 10% of the water
areas. available to the fire site.

3
APPARENT REFORM Next came another hooker. We proved (my God, i
obvious) that walls contain the heat. A fire in one room w
In 1971 and 1972 we outflanked the "sprinkler experts" set off one or more sprinklers in the room on fire — but it w
with our Life Safety System concepts. Ironically, many of the not open sprinklers in another room three doors down t
"experts" concluded that the "new" concepts of design hallway. The only possible way to do this would be for t
(actually, I had laid all the ideas on the insurers years ago) sprinklers to FAIL — and if the sprinklers in the first roe
were O.K. for "saving life" but would not qualify for FAIL — what good are the sprinklers three rooms away goi
"property protection." But this was fuzzy thinking on two to do when the fire burns its way over there?
counts: But, of course, the guys who write the NFPA sprinkler rul
1) How do you "save life" and also burn down the seem to be a special breed, and now they've got the rules s
building? up for 3000 Sq. Ft. of open sprinklers, even if there's
2) The concepts applied were originally developed in separate rooms.
tests involving "high hazard" fire risks. They want a "safety factor" you may say. But do they g
But, since we were producing a new sprinkler design one? Let's assume 20 small hotel rooms, with 20 baths and
standard (BOCA-100) and since the experts wanted to kill this closets, and a hallway all comprising 3000 Sq. Ft. This requir
standard before it got off the ground, miraculous changes perhaps 70 sprinklers. Now, hydraulically, if the most dista
came about in NFPA-13. After NFPA-13 was revised (by 60% sprinkler is set to "minimum" pressure 7 psi (very weak) ti
according to the estimates of one member), appropriate average "standard" head is going to actually dischar
experts appeared at the BOCA hearings to advise that probably 20 GPM (not 15) which means the pipes and pum
"BOCA-100 wasn't needed any more — NFPA-13 now did it have to be sized for 1,400 GPM. The NFPA rules have creatf
all." a monster.
Well, I felt in my heart that this sudden change in NFPA-13 But, we can't possibly design such a ridiculous system f
was more smoke screen than reform, but only time would tell most of the light hazard properties. What's the alternativ
for sure. Only one. Choke down each and every sprinkler head. With a
Now, with BOCA-100 available, and the experts apparently inch orifice each sprinkler will discharge one-fourth the wat
resigned to it, the smoke screen is lifting and it seems the more of the standard sprinkler. Now, we are down to 350 GPM ov
things change with NFPA, the more they are the same. the 3000 Sq. Ft., which is still very excessive, but tolerable.
But what have we done to ourselves? We have met ti
DESIGN FOR FAILURE NFPA rules. But to do it we have choked down the water f
the first few heads that open to the point where syste
One of the things we did with our research and the BOCA FAILURE becomes a strong possibility. And, if the system
rules was we tested out densities for light hazard properties the room fails (because of throttled density) and the fire do
and found that a density of 0.025 GPM/Sq. Ft. was adequate leave the room, why the game is surely lost because the syste
for control (British tests also confirmed this). So, believing has been weakened all about.
that the safety factor should be added at the fire site (not at As always, the experts will prove themselves right I
the other side of the building) we threw in a 4 to 1 safety burning down the place. The inspector will be in the next d.
factor, made the minimum design density 0.1 GPM/Sq. Ft., and say, — "See, we knew that 70 heads could open all along
and the design area 800 Sq. Ft. minimum (generally 4 How right they were. By their engineering, a hundred op
sprinklers in the light hazard property). heads is far too few.
The NFPA-13 group promptly followed our lead and took This "design for failure" is not only now being built in
0.1 density as a minimum for light hazard hydraulics (even "calculated" light hazard properties — it has already be
though the "cookbook": system will not produce it). But then built into the ordinary and extra hazard calculated syster
they "Mickey Moused" it by throwing in twice the area (1500 throughout the country.
Sq. Ft.) thinking that "double the area" is a safety factor (it The thing that frightens me most of all is that those rn.
isn't). But, not being content with this misreading, they who write the rules of sprinkler design — our "experts" if yi
immediately went to 3000 Sq. Ft. as a minimum area for will — know so little about what they are doing — that they
"combustible construction" (what's this got to do with it?). not even comprehend their errors. They go blithly forwar
This quadrupling of the area of sprinkler operation was applied supremely confident in their fairy tales, causing untc
even if the interior sheathing of the walls and ceiling was damage, destroying lives, and making a mockery of fire safe
gypsum wallboard. — and we all must suffer for it.

PATTON LIFE SAFETY SYSTEMS, INC.


6075 Cleveland Avenue
Columbus, Ohio 43229

Вам также может понравиться