SINOHYDRO GROUP LIMITED
Doha ExpresswayPackage 6
East Industrial Road Interchanges at Intersection with Street 10 and Street 23
Contact No. C2011/085
Submittal Information
1. Document Number
EXW-P006-0000-GS-SHC-MT-00003
2. Description
Method Statement for Surveying and Setting Out
3. Pages
39
4. Revision
Rev.1
5. Reference Number
Nil
6. Country of Origin
Qatar
7. BOQ Ref.
1.05
8. Specification Ref.
QCS 2010, Section 1, Part 13 & 15
SINOHYDRO GROUP LIMITED
Doha ExpresswayPackage 6
East Industrial Road Interchanges at Intersection with Street 10 and Street 23
Contact No. C2011/085
Index
1. General Description of Package 6 Project
2. Purpose and Scope of Work
3. Specification and Standard
4. Abbreviations
5. Utilization of Existing Information
6. Manpower
7. Equipment
8. General Surveying Method
9. Process of Survey Works
10. Quality Assurance Procedure
11. Safety and Health Plan for survey works
12. Inspection & Testing
13. Appendix
Appendix 1. List of Survey Equipment (Used on P6 Site)
Appendix 2. Inspection for formation level/base slab/roof slab/backfilling surface of sheet
Appendix 3. Inspection for formation level/base slab/roof slab/backfilling surface drawing
Appendix 4. Setting Out for excavation sheet
SINOHYDRO GROUP LIMITED
Doha ExpresswayPackage 6
East Industrial Road Interchanges at Intersection with Street 10 and Street 23
Contact No. C2011/085
Appendix 5. Manhole/chamber inspection for base slab level sheet
Appendix 6. Inspection for level of the installed pipeline sheet
Appendix 7. Formwork checking for kerb blinding
Appendix 8 Survey data for compacted ground/sub-grade/sub-base
Appendix 9 Inspection for kerb stone sheet
Appendix 10 Inspection deviation drawing for kerb stone
Wastewater system
j)
12 May 2012
Page 1 of 35
5) Pipeline Works
6) Road Works
4 Abbreviations
The following abbreviations are used in this Plan.
GPS
GIS
QNG
QNHD
TGO
TBC
LGO
RTK
RFI
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 2 of 35
223366.897
383367.888
20.618
560080
223109.127
383197.218
22.054
560047
222681.230
383860.419
---------
560048
222940.056
384007.725
---------
560061
222591.112
384553.745
---------
560062
222327.402
384396.843
---------
Before starting survey works,every Qatar national benchmark will be checked. Accroding
checked result some benchmark not ues for this survey works.Benchmark of the above
table is the first class control point for the construction. Some new benchmark will be
established base on the condition of site survey during construction.
6 Manpower
Total 5 personnel are involved in this work. According to the site actual situation, It
increase suitably with the reduction surveyor. Details please see Table 2.
6.1
List of Personnel
Table 2
S/N
Name
Age
Work
Experience
Position
Wang Shaolin
49
30
Survey Manager
Zhang jisheng
43
20
Bao Yanjie
31
Qi Wanyi
25
Land Surveyor
Shen Jianchao
25
Land Surveyor
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 3 of 35
Survey Manager
Wang ShaoLin
Site SurveyChief
Zhang JiSheng
Office SurveyChief
Bao YanJie
Office Surveyor
Shen JianChao,Qi WanYi
7 Equipment
7.1 Survey Instrument
The following survey instrument should be involved in the site survey works.
a) GPS Receiver 2 unit
b) Total Station 1 unit
c) Electronic Level 1 unit
d) Automatic Level 1 unit
According to the actual site situation, It increase suitably with the reduction survey
instrument. Survey instrument should be regular get of calibration certificate.
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 4 of 35
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 5 of 35
12 May 2012
Page 6 of 35
Station.
Angle r is 30~ 150
Distance to a and b700 m
Distance of survey point Distance of BS.point
Accuracy of Check point 10 mm between 90~ 190from BS. Point
Points surveyed from a free station shall be placed in site or here the polygon
between the known points used for determine the free station point.
12 May 2012
Page 7 of 35
Setting-Out or
Inspection
Approved Shop
Drawings
Transfer Design
Coordinates to
GPS/Total Station
Uesing GPS,Total
Station or Leveling for
Setting-out/Inspection
Download GPS,Total
station or Leveling
survey raw data
Not OK
Not OK
Engineer Approved
And return to QA/QC
If the control / check survey shows that the result does not comply with the tolerance, the
responsible engineer in the construction or QA/QC group shall be informed immediately.
The result shall be submitted for the Engineer accept as soon as it have been completed.
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 8 of 35
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 9 of 35
data were measured on each points. With min. 20 minute interval or counter check. The
observation section were not less than 5 second and data were recorded .
Vertical elevation checking method: One closed leveling line origins and terminates on the
national benchmark 560046, elevation is based leveling 570001 and 560046. Single
survey and middle thread reading method was adopted for the leveling survey, the
sequence of reading is back-front-front-back. The reading is saved to the five places of
decimal. Relevant specifications were followed in the progress of survey.
d) Tolerance
Horizontal : Points position 20mm+1ppm
Vertical : 4 L mm (where L is the distance leveled in kilometers).
e) Results Submit
<<Technical reports for checking survey of benchmarks>> shall be submitted for engineer
acceptance.
9.2 Earthworks
9.2.1 Setting-Out for Excavation
a) Used Instrument
Horizontal setting-out should be used RTK-GPS or Total Station.
b) Setting-out Method
The excavation coordinates for center line, boundary line and key points from the
approved shop drawing, are transfer into the GPS data collector or total station. The
setting out points shall be show at intervals of not more than 25m along the setting out line.
But also every key point must be staked out.
c) Tolerance
Setting-out points horizontal tolerance 50mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
9.2.2 Final Survey for Formation Level
a) Used Instrument
Horizontal checked should be used RTK-GPS or Total Station
Vertical checked should be used RTK-GPS, Total Station or Level Insrument.
b) Checking Methods
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 10 of 35
Formation level checked for pipeline: A point surveyed / checked every 10 m along the
centerlines.
Formation level checked for concrete works
Building: Max grid of 10m x 10m,and every key point must be checked.
c) Tolerance
Horizontal : 50mm, Vertical : - 150mm / +10mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
12 May 2012
Page 11 of 35
Vertical : 10mm.
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 12 of 35
12 May 2012
Page 13 of 35
transfered into total station, Site surveyor shall be setting-out manhole and chamber.
c) Tolerance
Horizontal : 20mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
9.4.2.2 Elevation Check for Base Slab
a) Used Instrument
Total station and level instrument should be adopted for this works.
b) Checking Method
Every manhole and chamber center points and boundary points are checked.
c) Tolerance
Storm Water Vertical : - 30mm / +10mm
Sewer Water Vertical : 10mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including checked drawing,
survey data and soft copy.
9.4.3 Manhole and Chamber Cover
Cover level checked after manhole and chamber completed.
a) Used Instrument
Total station and level instrument should be adopted for this works.
b) Checking Method
Every manhole and chamber cover center points shall be checking.
c) Tolerance
Vertical : 10mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including checked drawing,
survey data and soft copy.
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 14 of 35
a) Used Instrument
RTK-GPS and Total station should be adopted for this works.
b) Setting out method
Setting out method for pipeline work is to set out a point every 10m along the centerlines.
and key point must be staked out.
c) Tolerance
Wastewater pipeline: Horizontal tolerance: Pipe diameter 800mm: 20mm, 800mm:
30mm.
Storm pipeline: Horizontal tolerance : Pipe diameter 800mm: 20mm, 800mm:
30mm.
Irrigation pipeline: Horizontal tolerance : 100mm.
Potable Water pipeline: Horizontal tolerance : 100mm.
9.5.2 Wastewater Pipeline
Sewer pipeline elevation check after installation.
a) Used Instrument
Total station and level instrument should be adopted for this works.
b) Checking Method
Pipeline between two manhole or chamber is checked, Distance between point surveyed
shall not exceed 10 m along the centerlines.
c) Tolerance
Pipe diameter 800mm, Horizontal : 20mm, Vertical : 10mm.
Pipe diameter 800mm, Horizontal : 30mm, Vertical : 10mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
9.5.3 Storm Pipeline
Storm pipeline elevation check after installation.
a) Used Instrument
Total station and level instrument should be adopted for this works.
b) Checking Method
Checking method for storm pipelines is the same as checking method Sewer Pipelines.
c) Tolerance
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 15 of 35
12 May 2012
Page 16 of 35
a) Used Instrument
RTK-GPS should be adopted for this works.
b) Survey Method
Setting-out Method: Coordinates for centerline, boundary lines and key points from the
approved shop drawing, are transfered into GPS data collector. Center line and both
boundary lines shall be show at intervals of not more than 25m, and every key point must
be staked out.
OGL Survey Method: Each cross section not more than 25 m and every cross section for 5
point shall be survey. Every cross section survey width exceed road design width.
c) Tolerance
Setting-Out Horizontal : 20mm.
d) Results Submit
A RFI should be submitted for engineer acceptance, RFI including deviation drawing,
survey data and soft copy.
12 May 2012
Page 17 of 35
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 18 of 35
10.1.2 Responsibilities
Survey Manager shall fully take charge of survey work of the project, and implement the
regulations in quality assurance plan in the survey work and achieve survey result
conforming to the requirement of Project Specification.
Chief surveyor shall participate in the planning of survey technical design, and take
charge of on-site survey, calibration of survey instruments and checking of survey results.
Site surveyor team shall be responsible for conducting on-site survey works.
Office surveyor shall be responsible for the post-processing of data and preparation of
drawings.
12 May 2012
Page 19 of 35
10.2.3 Post-processing
Chief survey shall make further arrangements for data and documents review and check
relevant site record and calculation data. Drawer shall cooperate with each other and
make self-assessment. Survey team leader shall make final checking.
Survey superintendent shall be responsible for preparation of technical report, checking
of relevant survey record and data calculation.
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 20 of 35
management
system
will
cover
control
over
approval,
publishing,
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 21 of 35
Potential Danger
Control Measures
Inadequate
knowledge of
Project
requirements
Moving vehicles
/ Machinery
Personal injury
Injury to others
Ignorant to site
regulations
Road accident,
Personal injury, loss of
life, property and
equipment damages
Personal injury
Injury to Others
Struck by machinery
Hit by moving vehicle
Hit by moving truck
Fallen material
from high
Persons injured
Falls from
Height
Equipment damaged
Back Injury, Fractures,
Cuts, Bruises, Death
Reference
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 22 of 35
Safety vest
12 May 2012
Page 23 of 35
13 Appendix
Appendix.1 List of Survey Equipment (Used on P6 Site)
Appendix 2.Inspection for formation level /base slab/roof slab/backfilling surface of sheet
Appendix 3.Inspection for formation level /base slab/roof slab/backfilling surface drawing
Appendix 4.Setting out for excavation sheet
Appendix 5. Manhole/chamber inspection for base slab level sheet
Appendix 6 . Inspection for level of the installed pipeline sheet
Appendix 7.Formwork checking for kerb blinding
Appendix 8. Survey data for compacted ground/sub-grade/sub-base
Appendix 9. Inspection for kerb stone sheet
Appendix 10Inspection deviation drawing for kerb stone
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 24 of 35
Item
Manufacturer
Manufactures
Serial No
FOIF
T97212
R6
Trimble
4822153875
R6
Trimble
4822153857
DTM532
Nikon
032753
DINI12
Trimble
703163A
TBC
2.4
Trimble
TGO
1.63
Trimble
AutoCAD
2006/2010
Autodesk
Type
Model
Automatic
FOIF
Level
NAL-124
GPS
Receiver
Survey
GPS
Instrument
Receiver
Total Station
Electronic
Level
Survey
Calibration
Date
19-Mar-20
12
24-Dec-20
11
24-Dec-20
11
13-Mar-20
12
20-Feb-20
12
ExpireDate
Remarks
18-Sept-2012
23-Dec-2012
23-Dec-2012
12-Sept-2012
19-Aug-2012
Software
LGO
Nikon
Data
Transfer
Computer
LEICA
Nikon
unit 1
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 25 of 35
P.N
ELEVATION
DESIGN
ELEVATION
DEVIATION
P.N
EAST
NORTH
ELEVATION
STATION
BS
CHECK .BS
Surveyor:_________
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
Date:_________
12 May 2012
Page 26 of 35
4800.03
3300.00
3850.00
4799.97
1400.00
3850.00
Surveyor:_________
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
Date:_________
12 May 2012
Page 27 of 35
EAST
NORTH
ELEVATION
NORTH
ELEVATION
P.N
EAST
STATION
BS
CHECK .BS
Surveyor:_________
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
Date:_________
12 May 2012
Page 28 of 35
Manhole/CHAMBER
P/N
NORTH
ELEVATION
DESIGN COORDINATE
EAST
NORTH
ELEVATION
DEVIATION(mm)
EAST
NORTH
ELEVATION
EAST
NORTH
ELEVATION
STATION
BS
CHECK
POINTS
REFERENCE DRAWING:
Surveyor:_________
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
Date:_________
12 May 2012
Page 29 of 35
CHAINAGE
P/N
NORTH
ELEVATION
DESIGN
DEVIATION(mm)
ELEVATION
ELEVATION
EAST
NORTH
ELEVATION
STATION
B.S.
CHECK POINTS
REFERENCE DRAWING :
Surveyor:_________
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
Date:_________
12 May 2012
Page 30 of 35
Surveyor:
KERB
LEVEL
CH. __________)
CHECKED COORDINATES
POINT NO.
ELEVATION
DESIGN
LEVEL
DEVIATION LEVEL(MM)
Date:
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 31 of 35
SURVEY COORDINATE
AND LEVEL
EAST NORTH LEVEL
FINISHED
SUB-GRADE
ROAD
LEVEL(TOP)
LEVEL
DIVATION
LEVEL(mm)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
SURVEYOR:
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
DATE:
12 May 2012
Page 32 of 35
DESIGN
ELEVATION
NO.
FREE
ELEVATION
DEVIATION
ELEVATION(mm)
1
2
3
4
STATION
EAST
WEST
BS
CHECK BS
LEVELING BS
SURVEY INSTRUMENT:TOTAL STATION AND AUTO-LEVEL
SURVEYOR:
DATE:
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 33 of 35
Surveyor:__________
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
Date:____________
12 May 2012
Page 34 of 35
EXW-P006-0000-GS-SHC-MT-00003 Rev.1
12 May 2012
Page 35 of 35