Вы находитесь на странице: 1из 3

Generation of high voltages at power frequency is essential for testing the efficacy of insulation

of High Voltage Apparatus used in Power Systems. The generation and testing is carried out in a
laboratory, using High Voltage testing transformers. These testing transformers can either be
located indoor or outdoor.
Testing transformers are different from power transformers in a sense that they are not rated for
high power handling. They are designed to withstand frequent short circuits when the test object
fails or experiences flashover. Therefore, special methods are used, which are not applicable
when generating high voltage in high power applications.
The optimum rating of a single testing transformer unit is 300 kV. Beyond this level, the cost of
insulation rises rapidly and transportation becomes difficult. Cost of insulation for a single unit is
proportional to square of operating voltage. At higher test voltages a cascade arrangement of
several single unit transformers is used to generate high voltages for testing. Each of the units are
enclosed by large size metal rings to prevent corona
Cascade Arrangements of Transformers

Figure-1 --- High Voltage Cascade Transformer


The above figure shows a typical cascade arrangement of transformers used to obtain up to 300
kV from three units each rated at 100 kV. The low voltage winding is connected to the primary
of the first transformer, and this is connected to the transformer tank which is earthed. One end
of the high voltage winding is also earthed through the tank. The high voltage end and a tapping
near this end is taken out at the top of the transformer through a bushing, and excites the primary
of the second transformer. One end of this winding is connected to the tank of the second
transformer to maintain the tank at high voltage. The secondary of this transformer too has one

end connected to the tank and at the other end the next stage transformer is fed. This cascade
arrangement can be continued further, if a still higher voltage is required but not more than four
stages.
In the cascade arrangement shown, each transformer needs only to be insulated for 100 kV, and
hence the Transformer can be relatively small. If a 300 kV transformer had to be used instead,
the size would be massive. High voltage transformers for testing purposes are designed
purposely to have a poor regulation. This is to ensure that when the secondary of the transformer
is short circuited (as commonly it happens in flash-over tests of insulation), the current does not
increase to too high a value and to reduce the cost. The impedance of the transformer should be
generally less than 5% and must be capable of giving the short circuit current for one minute or
more depending on the design in practice, an additional series resistance (commonly a water
resistance) is also used in such cases to limit the current and prevent possible damage to the
transformer. What is shown in the cascade transformer arrangement is the basic principle
involved. The actual arrangement could be different for practical reasons. The number of stages
in this type of arrangement are usually two to four, but very often, three stages are adapted to
facilitate a three-phase operation so that can be obtained between the lines.
In addition to the normal windings, namely, the low voltage winding, high voltage winding and a
third winding known as meter windings is provided to measure the output voltage. Supply to the
units can be obtained from a motor-generator set or through an induction regulator for variation
of the output voltage. The rating of the primary or the low voltage windings is usually 230 or 400
V for small units up to 100 kVA. For larger outputs the rating of the low voltage winding may be
3.3 kV, 6.6kV or 11 kV.
Figure 1 shows the cascade transformer units in which the first transformer is at the ground
potential along with its tank. The second transformer is kept on insulators and maintained at a
potential of V2, the output voltage of the first unit above the ground. The high voltage winding
of the first unit is connected to the tank of the second unit. The low voltage winding of this unit
is supplied from the excitation winding of the first transformer, which is in series with the high
voltage winding of the first transformer at its high voltage end. The rating of the excitation
windings is almost identical to that of the primary or the low or the low voltage winding. The
high voltage connection from the first transformer winding and the excitation winding terminal
are taken through a bushing to the second transformer. In a similar manner, the third transformer
is kept on insulators above the ground at a potential of 2V2 and is supplied likewise from the
second transformer.
Typical Short circuit current for the High Voltage test is around 0.1 A for dry tests on solid and
liquid insulation. About 1 A may be necessary for wet test on large specimens.

Figure-2--Cascade Transformer unit with isolating transformer for excitation


T1,T2,T3- Cascade Transformer Units
lS1,lS2,lS3-Isolation Transformer units
C1,C2,C3-Capacitance Voltage dividers for h.v. measurement after first second and third stages

In figure Fig. 2, a second scheme for providing the excitation to the second and the third stages is
shown. Isolating transformers lS1,lS2,lS3 are 1:1 ratio transformers and are meant for supplying the
excitation for the second and the third stages at their tank potentials. Power supply to the
isolating transformers is also fed from the same a.c. input. This scheme is expensive and requires
more space. The advantage of this scheme is that the natural cooling is sufficient and the
transformers are light and compact. Transportation and assembly is easy. Also the construction is
identical for isolating transformers and the high voltage cascade units. Three phase connection in
delta or star is possible for the three units. Testing transformers of ratings up to 10 MVA are
cascade connected to give high voltages up to 2.25 MV are available for both indoor and outdoor
applications.
In order to reduce the size and cost of the insulation, sometimes transformers with a centre tap on
high voltage windings earthed or connected to the tank are used. This connection results in a
cheaper construction, and the high voltage insulation now needs to be designed for V2/2 , that of
second transformer at 5V2/2 , and that of the third transformer at 5V2/2
All the cascade transformer units which are meant for the supply of excitation to the next stage
have large leakage between the primary (or the low voltage winding) and the excitation
windings. Hence, they are invariably provided with compensating windings.

Вам также может понравиться