No.

13011/ 2 /2011-CA-I
Government of India
Ministry of Coal
..
New Delhi, dated 2nd March, 2012
OFFICE MEMORANDUM

Subject:
Meeting held on 11.01.2012 & 12.01.2012 chaired by Additional
Secretary (Coal) to review the progress of allocated coal/lignite blocks and associated
end use projects.
..
The undersigned is directed to enclose herewith the minutes of the Review
Meeting held on 11.01.2012 & 12.01.2012 under the Chairpersonship of Additional
Secretary (Coal) to review the progress of allocated coal/lignite blocks and associated
end use projects for information and necessary action.

Sd/(Sandeep Gupta)
Under Secretary to the Govt. of India
To
1.
The Secretary, Ministry of Power, Shram Shakti Bhawan, New Delhi.
2.
The Secretary, Ministry of Steel, Udyog Bhawan, New Delhi.
3.
The Secretary, Ministry of Commerce & Industry, Deptt. of Industrial Policy &
Promotion (Cement-II Section), Udyog Bhawan, New Delhi
4.
The Secretary, Ministry of Environment & Forests, Paryavaran Bhawan, CGO
Complex, Lodi Road, New Delhi.
5.
The Chairman, Coal India Ltd., 10-Netaji Subhas Road, Kolkata.
6.
The Director (Technical), Coal India Ltd., 10-Netaji Subhas Road,] Kolkata
700 001.
7.
The Chairman, Neyveli Lignite Corporation Limited, Block -1 , Neyveli
Lignite, Tamil Nadu- 607 801.
8.
The Coal Controller, Coal Controller Organisation, 1-Council House Street,
Kolkata.
9.
The Chairman-cum-Managing Director, CMPDIL, Gondwana Place, Kanke
Road, Ranchi 834 008.
10.
The Chairman-cum-Managing Director, SCCL. Kothagudem Collieries P.O.,
Dist. Khammam, Andhra Pradesh.
11.
The Chief Secretary, Govt. of Orissa, Secretariat, Bhubaneswar 751 001
(through the Office of Resident Commissioner, Govt. of Orissa, Borodolai Marg,
Chanakypuri, New Delhi).
12.
The Chief Secretary, Govt. of Chhattisgarh, Secretariat, Raipur (through the
Office of Resident Commissioner, Govt. of Chhattisgarh, 7 Sarsar Patel Marg,
Chankapuri, New Delhi).
13. The Chief Secretary, Govt. of Maharashtra, Secretariat, Mumbai (through the
Office of Resident Commissioner, Govt. of Maharashtra, Maharashtra Sadan, Near
Mandi House, Copernicus Marg, New Delhi).
14.
The Chief Secretary, Govt. of Jharkhand, Secretariat, Ranchi. (through the
Office of Resident Commissioner, Govt. of Jharkhand, B 5/2, Jharkhand House,
Safdarjung Enclave, New Delhi).

15.
The Chief Secretary, Govt. of Rajasthan, Secretariat, Jaipur (through the Office
of Resident Commissioner, Govt. of Rajasthan, Bikaner House, Pandara Road, New
Delhi 110003).
16.
The Chief Secretary, Govt. of West Bengal, Secretariat, Kolkata (through the
Office of Resident Commissioner, Govt. of West Bengal, A-2, State Emporia Building,
Baba Kharak Singh Marg, New Delhi 110 001).
17.
The Chief Secretary, Govt. of Andhra Pradesh, Secretariat, Hyderabad. (through
the Office of Resident Commissioner, Govt. of Andhra Pradesh, 1- Ashoka Road, New
Delhi 110003).
18.
The Chief Secretary, Govt. of Madhya Pradesh, Secretariat, Bhopal (through the
Office of Resident Commissioner, Govt. of Madhya Pradesh, B-8, State Emp. Building,
Baba Kharak Singh Marg, New Delhi 110003).
19.
The Chief Secretary, Govt. of Gujarat, Secretariat, Gandhinagar ( through the
Office of Resident Commissioner, Govt. of Gujarat, A/6 State Emporia Bldg., Baba
Kharak Singh Marg, New Delhi-110001).
20.
The Chief Secretary, Govt. of Tamil Nadu, Secretariat Chennai. (through the
Offie of Resident Commissioner, Govt,. of Tamil Nadu, Tamil Nadu House, Kautilya
Marg, New Delhi 21).
22.
The Chief Secretary, Govt. of Arunachal Pradesh, Secretariat, Itanagar.

Sd/( Sandeep Gupta )


Under Secretary to the Govt. of India.
Copy to :
PS to Minister of Coal/PS to Minister of State for Coal
Sr.PPS to Secretary (Coal)/ PPS to Addl. Secretary (Coal)
JS (C) / JS(LA)/Economic Advisor
Dir (CA-I)/Director (Tech)
Director (Technical), NIC, Ministry of Coal for uploading the minutes in the official
Website of Ministry of Coal.

Minutes of the Meeting held on 11.01.2012. & 12.01.2012 at Scope Complex, Lodhi Road,
New Delhi Chaired by Additional Secretary (Coal) to review the progress of captive
blocks and the associated End Use Projects.
-----------------------------------------------------------------------------------------------------------------A meeting chaired by Additional Secretary (Coal) was held on 11th and 12th January,
2012 in Scope Complex, Lodhi Road, New Delhi to review the progress of development of
coal blocks allocated up to 31st Dec.2011 along with their associated end use projects.
List of participants is enclosed as Annexure.
At the outset, Chairperson welcomed all the officers representing different Ministries/
Departments of Central/ State Governments attending the meeting as well as different block
allocatees. Information was sought from each of the company representatives (block allocates)
on milestones achieved by them since the last review meeting held on 20th and 21st July,2010.
Committee also confirmed the minutes of last review meeting.
The status of allocated Coal Blocks was then reviewed. Out of a total of 218 Coal
blocks that have been allocated so far, 23 blocks have been deallocatted by Ministry of Coal till
Dec., 2011. The status of remaining coal blocks was reported as follows:
(i)
Net allocated coal blocks are 195
(ii)
39 blocks are allocated to Govt PSUs for commercial use. Out of these, some
blocks have been transferred to linked Power project for commercial use
within the State.
(iii)
Mining Plan approved for 126 coal blocks
(iv)
29 coal blocks have started coal production
(v)
3 coal blocks started coal production after the last review meeting.
(vi)
9 coal blocks have reached peak rated capacity of the mine.

Details of coal blocks allocated year wise are as follows:No of blocks to Govt. Companies
Year of
allocation

Till 2003
2004
2005
2006
2007
2008
2009
2010
2011(Dec.
2011)
Total:-

No of blocks to Private
Companies
De
Net
Gross alloca
allocated
Alloc
ted/
blocks as
atted surren
on date
dered
24
2
22
1
1
0
16
1
15
15
15
17
1
16
20
2
18
12
12
-

Gross
Allotted

De
allocated/
surrendered

Net
allocated
blocks as
on date

17
4
8
32
34
3
1
-

2
6
6
1
1
-

17
4
6
26
28
2
-

100

16

84

106

99

No of Blocks
to UMPP/for
Tariff based
bidding

Total Net
blocks for
the year

6
1
1
3
1

2
12

Chairperson expressed concern on overall progress of captive coal block/lignite blocks


specially for the blocks allotted prior to 2003 and 2004 and intimated the committee that Govt
is under tremendous pressure due to shortage of coal in the country and no further time can be
lost in the development of blocks to meet the demand and supply gap of domestic coal. She
also urged the State Governments to enhance their co-operation with the block allocatees in
order to clear the pending major milestones in time bound manner. She requested the State
Government to resolve law and order problems promptly and to extend necessary assistance for
deployment of security camps as per local requirement. Additional Chief Secretary,

39
4
21
47
45
21
15
1

195

Government of Jharkhand assured all necessary assistance for speedy disposal of pending
issues at the state level. The target of coal production of 36.15 Mill tonnes for 2011-12 (the
terminal year of XIth five year plan) and 39.2 Mill tonnes for 2012-13 (the initial year of XIIth
five year plan) needs to be achieved.
Joint Secretary (Coal) advised all the allocatees to push their projects for early
clearance of pending milestones. He also requested Ministry of Power to closely monitor the
upcoming power projects as well as coal projects allotted for power generation. He also
advised the owner of those coal blocks which were rejected earlier for forest clearance by
Ministry of Environment and Forest because of No Go Categorisation to pursue their forest
clearance proposal with the State Forest Departments for further consideration. Coal Controller
was directed to give information on opening of Escrow Accounts and approval of Mine
Closure Plan of captive coal blocks from the next review meeting.
General Recommendations of the Committee:During the review of the progress of coal & lignite block the major issues causing delay and
action points for reducing the delay in various clearances were identified. The decisions/issues
and recommendations are categorized as below:(a) Issues relating to Environment & Forestry Clearances:

The decision taken by GoM in its meeting held on July, 2011 has not percolated to
field level.

MOEF may be requested to issue guidelines as per the decision of the GoMs meeting
held on July,2011 to the regional/field offices of MOEF on Go/No Go issues.

In view of the decision of the GoM, cases which had stopped being processed due to
Go-No Go concept may be taken up by the block allottees again with the State Forest
Departments afresh and their pending applications may be processed by concerned
Forest Departments/MoEF without delay.

The block allocatees in the state of Jharkhand are facing a serious problem in forest
clearance issues at the State level as individual applicants are being asked to report on
the environmental impact on the entire forest belt in North Karanpura/Hazaribagh as a
whole. State Govt. representative was requested to take decision on forest clearance
proposals independently on a case to case basis. Impact on the forest belt as a whole
could be better assessed by State Forest Deptt.

Block allocatees should redefine boundaries in consultation with State Forest


department in the case of coal blocks falling in buffer zone or under National Tiger
Reserve Forest area and subsequently move forward for forest clearance to MOEF. In
case this is not possible Blocks may be de-allocated.

(b) Issues pertaining to State Governments:

State Government should adhere to the time schedule of 24 months or the time
schedule prescribed in allocation condition from the date of allocation for granting of
mining lease of captive coal blocks.

The block allocatees in the state of Orissa are facing a serious problem regarding land
acquisition and grant of mining lease due to the issue raised by Orissa Govt. for
supplying of 33% reject based free power to the State Govt. There is no clear cut
policy in this regard. Committee asked representative of Govt. of Orissa to issue
guidelines in the matter not to hold up clearances on this account till a policy is
formalized in consultation with Ministry of Power.

The block allocatees in the state of Jharkhand are facing a serious problem on law and
order issues. The representative of State was requested to look into the matter and to
ensure full security by deploying CRPF camp as and when requested.

Rehabilitation and Resettlement issue and issue of notification under section 4 of LA


Act, at the State Govt. level in case of land acquisition should be settled on priority
basis.

(c) Miscellaneous Policy Issues

As the block allocatees are facing serious problem regarding transfer of land from
subsidiary companies of CIL under CBA Act, Committee advised that subsidiary coal
companies of CIL should urgently transfer the land rights under CBA Act to State
Govt/ coal block allocatees. Necessary guidelines be issued, if necessary.

Decision on reduction of GR cost whenever required should be taken by CMPDIL in


consultation with Ministry of Coal on priority basis.

Transfer of surface right and mineral right of land acquired by subsidiary coal
companies of CIL to the block allocatees is sometimes a major cause of delay.
Committee urged Ministry of Coal to issue concrete guidelines in this regard.

Attention is needed for early settlement of bipartite agreement between subsidiary


coal companies and block allocates without delay.

Pending issues of Mine Plan approval and previous approval under section 5(1) of
MMDR Act in case of grant of mining lease on priority basis need to be cleared
expeditiously.

In a case from West Bengal, there is a problem due to overlapping of area for CBM
with coal block. Ministry of Petroleum and Natural Gas has accorded permission to
extract CBM from the allocated coal block and due to absence of any guidelines, the
coal block allocatees are unable to go ahead with the extraction of coal. Ministry of
Petroleum and Natural Gas may be requested to issue policy guidelines in order to
resolve the overlap issues.

Committee observed that some block owners are willfully delaying the achieving of
pending milestones of coal block and EUPs. Committee viewed it seriously and
recommended that deduction should be made from the Bank Guarantee corresponding
to slippage as per provisions contained in the allocation condition. In this regard
Ministry of Coal may consider framing policy guidelines regarding quantum of
deduction over period of delay.

Committee observed that every allocatee is required to open an Escrow Account with
Coal Controller for mine closure prior to opening of mines as per procedure laid down
in the guidelines of approved Mine Closure Plan. Compliance may be specifically
reported in the next review meeting.

(d) Other Issues

One coal block in the state of West Bengal is facing a serious problem due to
construction of Aerotropolis /airport project within the coal block areas. Construction
of Aerotropolis is going on the coal block area though the matter is subjudice before
the Honble Court. Committee recommended that the State Govt. may be advised to
immediately stop construction of Aerotropolis and to intimate the court accordingly.

In order to sort out the problem faced by block allocatees, close monitoring with the
concerned State Govt. and MoEF at the level of Ministry of Coal /Coal Controller may
be initiated. Regular meetings with Coal Controller/Ministry of Coal and representative
of State and Central Govt may be organized every 3 months. Forming a monitoring
sub-committee in this regard at the Ministry level may be considered.

Joint venture companies formed by the joint allocates are required to submit a
compliance status of Coal Block and associated EUPs of individual allocates to CCO
by 5th of the next month after every quarter. Block allocates were advised to submit the
progress reports and renewed BG to CCO without any lapse.

All the allocatees were advised that BG should be submitted by the JVC in case of
jointly allocated coal blocks. Individual submission of BGs will not be accepted.

The specific recommendations of the Review Committee regarding each coal block are as
follows:-

(I) The following 9 coal blocks have started coal production and have attained the
peak rated capacity.
Sl. No
1
2
3
4&5
6
7
8
9

Name of coal blocks


Talabira-I
Tara (East)
Tara (West)
Gotitoria (E&W)
Gare Palma IV/1
Gare Palma IV/5
Panchwara Central
Chotia*

Allotment year
1994
1996
1996
1996
1996
1996
2001
2003

Name of allocate /JV


INDAL/ HINDALCO
WBSEB/BECML
WBPDCL/BECML
BLA Industries
JSPL Ltd.
Monnet Ispat Ltd.
PSEB
Prakash Industries Ltd.

*The allocattee has been issued a show cause for deviation of conditions of allocation. The
matter is subjudice.

(II) The following 20 coal blocks have started coal production and have not attained
the peak rated capacity. The allocatees are advised to attain the peak rated
capacity as per the approved mining plan.
Sl. No
1
2-3
4
5
6-11
12
13
14
15
16
17
18
19
20.

Name of coal blocks


Sarshatali
GarePalma IV/2&3
Gare Palma IV/4
Namchik Namphuk
Baranj I-IV, Kiloni and
Manora Deep
Gare Palma IV/7
Barjore
Kathautia
Tasra
Barjora North
Belgaon
Parbatpur Central
Marki Mangli-I
Marki Mangli-III

Allotment year
1993
1998
1999
2003
2003

Name of allocatee /JV


CESC Ltd/ICML
Jindal Power Ltd.
Jayaswal Neco Ltd.
Arunachal PMDCL
KPCL

2000
2003
2003
1996
2005
2005
2005
2004
2005

RASL now SEML


WBPDCL/BECML
Usha Martin Ltd.
Steel Authority of India (IISCO)
DVC
Sunflag Iron & Steel Ltd.
Electro Steel Casting Ltd
B.S.Ispat Ltd.
Shree Virangana Steel Ltd.

(III)
From the reported progress, it is seen that production from the few coal
blocks will be started in the year 2011-2012 or the near future as per the
indicated schedule. It is the recommendation of the Committee that the
allocatees of these coal blocks be advised to start mining/ coal production in
2011-12 or as per the indicated schedule of production failing which
appropriate action will be initiated.
Sl. No.

Name of Coal Block

1.

Trans Damodar (Govt


Dispensation)

2.

Khagra Joydev

3.

Sial Ghogri

4-5.

Marki Mangli-II &


Marki Mangli-IV

Allocation
date/Target dt of
production
14.1.05/ March.09
03.03.05/ Mar.08
22.05.07 (revised to
22.8.07)/ Feb.12
6.09.05/ Mar.09

Name of Allocatee

WBMTDCL.
(Govt PSU)
DVC (Govt. PSU)
Prism Cement Ltd (Private).

Topworth Urja & Metals Ltd


(formally known as Shree
Virangana Steel Ltd)
(Private)
Utkal Coal Ltd (formerly
known as ICCL)

Utkal-C

29.5.98/ Nov.01

7-8

Parsa (East) &

25.06.07/ Sept.12

Kanta Basan
Panchwara North

10

Durgapur II/Taraimar

11

Gare Palma Sector-III

12

Fatehpur East

23.1.08/ Oct.13

13

Ganeshpur

28.5.09/ Nov.13

14-15

Sahapur (East)
&
Sahapur (West)

25.7.07/
April,14

NMDC

16

Bicharpur

25.7.07/
April,14

Madhya Pradesh State Mining


Corporation Ltd

17

Marki Zari Jamani Adkoli

2.8.06/ June,13

MSMCL

18

Andal East

3.7.09/ Apr.15

Bhusan Steel Ltd, Jai Balaji


Industries Ltd, Rashmi Cements
Ltd

Rajasthan Rajya Vidyut


Utpadan Ltd.

19.05.07/ Sept.12
26.04.05/ May.11

WBPDC Ltd.

6.11.07/Normative
date re fixed on
May,12
12.11.08/ May,12.

BALCO

Goa Industrial Development


Corp Ltd.
JLD Yavatmal Energy, RKM
Powergen Ltd., Vandana
Vidyut , Visa Power, Green
Infrastructure
Tata Steel Ltd & Adhunik
Thermal Energy Ltd.

The progress of the following blocks was not found to be satisfactory but it is
seen that these blocks were delayed due to Go/No Go categorization, location in
wildlife corridors, allocation to PFC for UMPPs and overlapping of coal bearing
area with CBM/Aerotropolis project. Committee expressed concern over unsatisfactory
progress and advised the allocattees whose blocks were held up due to location in
No-Go area to pursue their forest diversion proposals since Go/No-Go concept has
been done away with. The Committee advised the other allocattees to pursue their
cases with the concerned authorities and get the requisite forest clearances
expedited.

(IV)

Sl. No.

Name of Coal Block

Allocation
date/Target dt of
production
14.08.2003/ Feb.07

1.

Tara

2-3.

Amelia &
Amelia North

12.1.06/ July,09

Madhya Pradesh State Mining


Corporation Ltd

Mahan

12.04.06/ Oct.09

Essar Power Ltd. & Hindalco


Industries Ltd

5-6

Paturia & Gidmuri

23.9.2004/ Mar.08

CSEB

Morga-I

02.08.06/ May,12

MPSMCL

Morga-II

02.08.06/ May,12

GMDC

Morga-III

25.7.07/ April,13

MPSMCL

10

Morga-IV

25.7.07/ April,13

MPSMCL

11

Vijay Central

12

Madanpur South

13-14

Nakia I & Nakia II

15

Madanpur North

13.1.06/ July,09

16

Sayang

6.11.07/ Aug.13

17

Rajgamar Dipside

14.10.11

18-19

Pindrakhi &
Puta Parogia

9.9.09/
March.13

01.11.2011 /May,15

13.1.06/ July,09

13.1.06 Refixed to
31.5.07/ Nov.10

Name of Allocatee

CMDC (Govt Disp.)

Coal India Ltd & SKS Ispat &


Power Ltd. Block allocated
recently in pursuance of a Court
Case.
Madanpur South Coal
Company Ltd (JVC of
Hindustan Zinc Ltd & Others)
Chhatiagarh Captive Coal
company Ltd (JVC of Ispat
Godavari & Others)
Madanpur North Coal
Company Ltd (JVC of
Ultratech Ltd and Others)
AES Chhatisgarh Energy Pvt
Ltd.
API Ispat & Powertech Pvt Ltd,
CG Sponge manufacturers
Consortium Coalfields Ltd
Akaltara Power Ltd (an SPV of
PRC)

20

Patal East

6.11.07/ Aug.13

Bhusan Power & Steel Ltd.

21

Mednirai

28.5.09/ Nov.12

Rungta Mines Ltd & Kohinoor


Steel Pvt Ltd.

22

Kerandari BC

An SPV of Power Finance


Corporation Ltd for JH UMPP

23

Mourya OC

20.7.07/ Feb.14 (zero


date revised as
7.08.09)
26.6.09/ Dec.12

24

Mara II Mahan

02.08.06/ May.12

25

Semaria Piparia

25.7.07/ Jan.12

NCT of Delhi, Delhi &


Haryana Power generation
Corp. Ltd.
MPSMCL

26

Mandla South

25.7.07/ Jan.12

-DO-

27

Rawanwara North

29.5.07/ Nov.11

SKS Ispat Ltd.

28

Brahmpuri

01.08.07/ July,11

Pusph Industries Ltd

29

Tandsi III & Tandsi III


Extension

30

Thesgora/Rudrapuri

31

Chatrasal

5.08.08/ Feb.13
21.11.08/ Nov.12
26.10.06 (zero
dt.Aug.07)/ Feb.11

Karanpura Energy Ltd.

MESCO Steel Ltd


Kamal Sponge Steel & Power
Ltd., Revati Cement Ltd.
M/s. Sasan Power Ltd (an SPV
of PFC for MP UMPP) has
been transferred to Reliance
Power Ltd.
Adani Power Ltd.

32

Lohara West Extention

6.11.07/ May.11

33

Bander

29.5.09/ Nov.13

34

Bhivkund

17.7.08/ April,14

35

Talabira-II & III

10.11.05/ May.09

MCL/NLC/Hindalco Industries
Ltd

36

Dulanga

25.1.06/ Sept.11

NTPC Ltd.

37

Manoharpur

25.7.07/ Jan.11

AMR Iron & Steel Ltd, Century


Textile Ltd and JK Cement s
Ltd
SPV of MAHAGENCO

OPGCL
38

Dipside Manoharpur

25.7.07/ April,13

39-40

Rampia
&
Dip side of Rampia

17.1.08/ Oct.13

-DOSterlite Energy Ltd., GMR


Energy Ltd, Arcelor Mittal
India Ltd, Lanco Group Ltd,
Navbharat Power Pvt Ltd,
Reliance Energy Ltd

13.9.06/ Mar.10

Power Finance Corporation Ltd

21.6.2010/ Nov.13

Sakshigopal Integrated Power


Company Ltd (SPV of 1st
additional Orissa UMPP)
Bankura DRI Mining Mfg. Pvt
Ltd.

41-43

Menakshi,

44

Meenakshi-B
&
Deep side Meenakshi
Bankui

45

Biharinath

46

Moira Madhujore

47-48

49

Kotre Basantpur
&
Panchmo
Parsa

50

Fatehpur

6.2.08/ Nov.13

SKS Ispat & Power Ltd &


Prakash Industries Ltd.

51

Bundu

25.4.06/ Oct.09

Rungta Mines Ltd.

52

Chakla

20.2.07/ Aug.10

Essar Power Generation Ltd.

53

Ashok Karkatta Central

6.11.07/ Aug.13

Essar Power Ltd.

54

Rohne

5.6.08/ Dec.11

55

Gare Palma IV/6

13.1.06/ July,09

56

Gare Palma IV/8

13.1.06/Jan.10

Jayaswal Neco Ltd.

57

Dongri Tal-II

2.8.06/ May,12

Madhya Pradesh State Mining


Corporation Ltd

58

Jogeswar & Khas


Jogeswar

11.4.08/ Oct.11

JSMDCL

20.2.07/ Feb.11
6.10.09/ April,13

11.8.05/ Feb.09

02.08.2006/ May,12

10

Ramswrup Lohh Udyog Ltd,


Adhunik Corporation Ltd,
Uttam Golva Steel Ltd, Howrah
Gases Ltd, Vikas Metal &
Power Ltd, ACC Ltd.
Tata Steel Ltd.

CSEB

JSW Steel Ltd., Bhusan Steel &


Power Ltd and Jai Balaji
Industries Ltd
JSPL & Nalwa Sponge Iron
Ltd.

(V) The progress of the following blocks was not found to be satisfactory. Committee expressed
concern over unsatisfactory progress and advised to expedite the development of the coal block and
be cautioned to be careful in future w.r.t the milestones stipulated. If they do not improve the
performance on the speedy development of the block further, action including deduction of BG/deallocation would be considered.
Sl.
No
.
1.

Name of Coal
Block

2.

Sitanala

9.4.07/ April,11

SAIL

Kosar
Dongergaon

20.2.07/ Feb11

Chaman Metallicks
Ltd.

ML & LA are pending. Mining lease


is pending with State Govt. Major
milestones are completed. Requested
for early grant of ML

Badam

3.11.03/ May.07

Tenughat Vidyut
Nigam Ltd.

5-6

Gangaramchak
&
Gangaramchak
Bhadulia

23.6.03/ Dec.06

WBPDC Ltd

FC & LA are pending.


Conditional ML granted. Stg-II forest
clearance is pending. Land acquisition
is pending with state Govt. Stg-II
compliance
submitted
to
Forest
Department in Sept.11. Amount for
Compensatory land deposited to land
revenue department. Mine is ready to
start production. Sec 11 notice issued.
FC, Stg-I, LA are pending.

Pakri Barwadih

Allocation
date/Target dt of
production
11.10.04/ April,08

Name of Allocatee

Status

NTPC Ltd.

LA is pending. Stg-II forest clearance


obtained. Mine Developer and Operator
(MDO) appointed. CHP operational.
Construction of railway line and R&R
projects are going in full swing. NTPC
discussed with MDO to raise coal
production up to 18MTPA. Exploration
is going on in the unexplored area. 600
acres of govt. land is there. Govt of
Jharkhand advised to conduct a meeting
with Revenue Department for land issue.
Company stated that coal evacuation
corridor completed and 13.5 Km
elevated coal conveyor works started.
ML & LA are pending. JVC formed
with Tata Steel and SAIL. (50-50
sharing basis). Assigned job to MDO for
coal mine development and supply of
coal steel plant. UG mine and incline
drivage. Degasification is required first
to develop seam. R/R issue is the major
problem to be sorted out.

Acquisition of forest land is


pending. Assured to start mining in
47 Ha non forest land. Forest
clearance is the main issue.

11

Utkal-B1

29.9.03/ Mar.07

Jindal Steel &


Power Ltd.

ML & LA are pending. Grant of ML


is held up for the issue of 33% free
power to be provided to Govt. of
Odhisa. 225 Ha land are with the
company. All clearances obtained
except ML.

Jamkhani

12.11.03/ Nov.08

Bhushan Steel &


Power Ltd.

Tokisud North

Previous approval, FC, ML & LA are


pending. Shifting of villagers have been
started. LA to be completed by Feb.12.
Land will be in possession by April
2012. Public Hearing (PH) for LA done
in 3 villages. ML is in final stage and
will reach MoC shortly. R&R is in
progress
FC(Stg-II), ML & LA are pending. Land
acquisiton: - Diversion of forest land is
involved. Part of the land acquired
through direct negotiation and balance
land will be handed over by March.
2012. Mining operation will be
commenced on pvt land. Govt land
acquisition is pending with Govt. of
Jharkhand. Revised Mining plan with
capacity 2.5 MTPA submitted to MoC.
PPA to be signed in April, 2013.
Previous approval of ML, FC(Stg-II),
ML, LA are pending.
Brinda-Sasai Block
Company informed that application for
prior approval ML forwarded by State
Govt to MoC and will be obtained
shortly. Land is sufficient to start
mining.
Meral Block
State Govt. forwarded application for
prior approval of ML to MOC in Dec.11
which is pending at MoC and will be
obtained shortly. Meral has no forest
land. Land is available. 300 ha land
acquired. Delay due to change of EUP
location.

7.1.02/ July,05

GVK Power
(Govindwal Sahib)
Ltd

1012

i) Brinda
ii) Sasai
iii) Meral

26.05.05/ Nov.08

Abhijeet
Infrastructure Ltd

13

Majra

29.10.03/ April,07

Gondwana Ispat
Ltd.

FC(Stage-II), LA are pending.


Company informed that every thing
is ready except forest clearance. 6-8
months will require to get Stg-II
clearance. 150 Acres land acquired.

14

Mandakini-A

9.1.08/ July,11

Monnet Ispat &


Energy Ltd, Tata
Power Ltd, Jindal
Photo Ltd.

Previous approval, FC, ML,LA are


pending. ML application to be
forwarded to MoC by March,12.
Payment for land will be completed by
Feb.,12. FC proposal will be prepared
soon. Canal & Nalla diversion is
required. 800 acres are forest land. 20
Lakh paid as land cost.

12

15

Ardhagram

6.12.07/ June,11

Sova Ispat Ltd &


Jai Balaji Sponge
Ltd.

16

Talaipalli

25.1.2006/ Mar.12

NTPC Ltd.

17

Sondiha

25.7.07/ April,13

CMDCL

18

Kesla North

5.8.08/ Feb.13

Rathi Udyog Ltd.

19

Rajgamar
Dipside (South of
Phulakdih nala)

3.6.09/Dec.13

Monnet Ispat &


Energy Ltd,
Topworth Steel
Ltd,

20

Gondulpara

13.1.06/ July,09

TVNL + DVC

21

Amarkunda
Murgadangal

17.1.08/ Oct.13

JSPL & Gagan


Sponge Iron Ltd

13

FC(Stg-I), ML & LA are pending.


Block is under option_III. Sova Ispat &
Jai Balaji Industries having share 85% 15%.Transfer of land from ECL to the
company is the major issue. Tripartite
agreement with ECL is still pending.
Resettlement cost paid to
local
authorities. Company requested to early
grant of NOC by ECL .
FC (Stg-I), EMP & LA are pending.
Company stated that 40,000 mts drilling
completed. FC proposal is pending with
PCCF, Govt of Chattisgarh . Expected to
reach MoEF in Jan. 2012.
NTPC
formed JVC with SCCL to develop the
block.
FC/EMP clearance , ML & LA are
pending. Mining plan and Mine closure
plan
approved.
Forest
proposal
submitted to State Govt. as per schedule.
ML grant, FC/EMP, LA are pending.
Public hearing completed. Land
surveyed. 80-90 % land notified under
CBA Act. SECL have to transfer land
to State Govt. ML application is not yet
forwarded to MOC for 5(1) approval.
Company requested MOC to convey
joint meeting with Govt of CG. Land
transfer issue to be sorted out with
SECL. Requested to shift zero date for
development.
MP approval, FC/EMP, ML LA are
pending. Forest application submitted.
70 % land is with SECL. Transfer of
land from SECL to State Govt is the
main issue. Joint survey of land is being
carried out and is expected to be
completed in Jan.12. Forest Diversion
Proposal prepared.
EMP/FC, ML & LA are pending. No Go
issue cleared in Sept. 2011.Public
hearing for EMP to be conducted in
Feb.12. Mining lease application is
pending with State Govt.
RE block. Company stated that illegal
mining is going on. 3 contractors
appointed. Law and Order problem is
there. Company requested to the State
Govt to deploy CRPF camp in the area.
Land acquisition is the main issue. 2000
MW Power Plant of Gagan Sponge and
JSPL to be set up jointly . Company
intimated that for generation of 2000
MW power plant, 400 MT coal reserves
are required.

22

Suliyari Belwar

25.7.07/ April,14

Andhra Pradesh
Mining Dev
Corporation Ltd.

23

Marki Bakra

25.7.07/ April,14

MPSMCL

24

Mandla North

17.9.07/ March.12

Jaipraksh
Associates Ltd

25

Bikram

12.08.08/ Feb.13

Birla Corporation
Ltd.

26

Urtan North

12.1.09/ April, 14

JSPL & Monnet


Ispat & Energy
Ltd.

27

Warora

28

Khappa
Extension

29

Bijahan

30

Radhikapur
(West)

RE Block. Mining Plan to be ready


by April,13. 220 Ha is forest land.
Exploration in non forest land
completed. Exploration in Ph-II
forest land not yet done. Drilling
ready. R&R activity is in progress.
MP approval, FC, EMP, ML & LA
are pending. MP approval is pending
with MoC since Dec.11. ML is
pending with State Govt.
Previous approval, ML, FC, EMP,
LA are pending. MOEF presentation
made on Oct 2011. UG mine
through Board and Pillar method.
Land purchased. Prior approval of
ML is pending with MoC.
Previous approval, ML, FC, EMP,
LA are pending. Forest application
is pending with CCF. Acquisition of
compensatory land is main problem.
Public Hearing for EMP by Feb.12.
MP approval, Previous approval,
ML,
EMP, LA are pending.
Company stated that MP and MCP
submitted to MOC in Oct 2011 &
July 2011 respectively. TOR
approved. No forest land is
involved. 20 acres land is required.
80 mt seam depth. UG block will
take time to develop.

20.7.07/ Jan.12

MSMCL

MP approval, EMP, ML & LA are


pending. No forest land in Phase-I
mining. MP presentation done in Dec
2011. TOR for EMP obtained.
Application U/S 4(1) of LA Act made.
JVC formed with Gupta Coal Co. Ltd
with 51%(MSMCL) : 49%(GCC)
sharing basis. JVC will produce coal.

29.5.09/ Nov.13

Sunflag Iron &


Steel Ltd &
Topworth Steel
Ltd.

FC(Stg-I),EMP, ML & LA are


pending. Forest Diversion Proposal
submitted. Defense land is within
the block area and is required to be
diverted.

13.1.06/ Nov.10

M/s. Bhushan Steel


& Power Ltd &
Mahavir Ferro
Alloys Ltd.

25.4.06
(reallocated on
21.12.09)/ June,13

Rungta Mines Ltd,


OCL India Ltd and
Ocean Ispat Ltd

FC, EMP, ML & LA are pending. Govt


of Odhisa has advised to hold the block
development due to law and order
problem and has advised to start
Jamkhani block first.
Previous approval, FC, EMP, ML, LA
are pending. TOR filed. EMP is
expected by 2012. Polluted area (CEPI).
ML application is pending with Director
(Mines).IIDCO to submit project cost
for irrigation project.

14

31

Ramchandi
Promotional
Block

27.2.09/ Nov.14

Jindal Steel &


Power Ltd.

32

North of
Arkhapal

27.2.09/Nov.14

Strategic Energy
Tech. System Ltd.

RE block.
40,000-45,000 mts drilling is required.
Depends on viability of reserves.
Applied for exploration license.1200 Ha
land. 33% rejecst based free power
issue is there. Middings generated to be
used in JSPL plant.
RE block.
DFO has cleared forest proposal for
drilling. PL is not yet granted. Coal
quantity to be ascertained for
gasification. 10 Sq. km. area is under
proved category.

(VI)

The progress of the following blocks was not found to be satisfactory. The Committee
expressed concern over the progress and recommended that the allocatees be served with show-cause
notice to explain why the block should not be de-allocated .

Sl. Name of Coal


No. Block
1

2-3

Tubed

(i)

Chinora

Allocation
date/Target dt of
production
1.08.07/ Feb.11

Name of
Allocatee

Status

Hindalco
Industries & Tata
Power Ltd.

Previous approval, FC(Stg-I), ML, LA


are pending. 206 Ha non forest land is
with DFO. Stg-I forest clearance is
expected by Aug.12. Section 4(1) to be
cleared by end of Jan.12. 4-6 months are
required for completion of land
acquisition. NOC has been given by DC.
EUP of Hindalco:740 acres Pvt land acquired. Govt land
by March.12. About 1000 acres land to
be acquired by May.12. Construction
work has not been started.

8.10.03/ Oct.06

Field Mining &


Ispat Ltd.

16.8.99/ Feb.03

Monnet Ispat &


Energy Ltd.

Previous approval, ML & LA


pending. No forest land is involved.
Company informed that there is a
court case hence subjudice. Prior
approval of ML is pending with
MoC. Financial closure of EUP not
completed. Land for EUP purchased.
No significant progress of coal
blocks and EUP.
ML & LA are pending.
ML approval has not been issued.
MIEL conveyed consent to Govt of
Orissa in July.11 for putting up
washery and reject based power
plant. 33 % reject based free power to

(ii)
Warora
Southern Part

Utkal B2

state Govt is the main issue. R/R is in


progress.

15

Gare Palma
Sector -I

02.08.06/ May,12

CMDC

Gare Palma
Sector-II

02.08.06/ May,12

TNEB & MSMCL

Shankar
Pur/Bhatgaon II
& Extn

25.7.07/ Jan.11

CMDCL

Durgapur
II/Sariya

6.11.07/ May,11

DB Power Ltd.

Sugia Closed
mine

30.1.06/ July,09

JSMDCL

16

RE Block. Prospecting license obtained.


Field works completed 2 months before
completion of prospecting. Prospecting
to be completed by March, 2012.
Boundary dispute with JSPL exists.
Company informed that 3 yrs will be
required to start production after
completion of GR.
RE block. Company informed that MDO
(Lanco Infratech Ltd) appointed in
Feb.2011 and exploration works
awarded to MECL in April,2011.Total
no of boreholes required to be
completed 160- 171. 24-30 boreholes at
the depth of 70,000 mts already
completed. Company expects to
complete 2,74,000 mts drilling by
March.12. Drilling is almost completed.
Mining Plan will be ready by June,12.
Company informed that Phase-I mining
in non forest area will be commence 1st
and then in phase-II mining in forest
area. Coal evacuation from pit head to
Power plant by rail siding. OB removal
land identified. Coal block area is large
(2.20 Sq. KM). Company requested to
change Zero date. Land for 2000 MW
power plant identified. CIDC is
authorized to acquire land. Order to
prepare Coal Mining plan on available
data placed. Boundary defined in
Nov.2011. Rail link is not yet ready.
FC(Stg-I), EMP, ML & LA are pending.
Company stated that Mining Plan &
Mine Closure plan are approved. State
Govt is delaying in submiting EMP
report to MOEF. Forest application is
expected to be submitted to Govt of CG
by end of March.2012. Land acquisition
is almost complete.
FC, EMP, ML & LA are pending.
Company informed that ML will be
executed after Env. Clearance. Land
acquisition completion is expected by
Dec.12.
FC, LA & ML are pending.
Process for Selection of MDO is going
on. EIA approved. Stg-I forest clearance
is pending. JVP not yet selected.

10

Utkal-D

19.12.03/ June,07

OMDC (Govt
Disp.)

11

Utkal-E

27.8.04/ Feb.08

12

Bhaskarpara

21.11.08/
May,12

13

Rauta Closed
mine

30.1.06/ Oct.11

JSMDCL

14

Burakhap small
patch

30.1.06/ Oct.11

JSMDCL

15

Gomia (deep UG
mine)

2.8.06/ May.13

MMTC Ltd.

16

Prindra-DebipurKhaowatand

2.8.06/ May.12

JSMDC

17

Latehar

2.8.06/ May.12

JSMDCL

18

Saria Koiyatand

02.08.06/ May.12

BRKBN Ltd.

19

Raj Bar E & D

02.08.06/ May,12

TVNL

20

Urma Paharitola

25.7.07/ April, 13

JSEB &
BSMDCL

RE block. MDO not yet selected.

21

Patratu

25.7.07/ April,13

JSMDCL

RE block. GR preparation is going on.


Floted tender for selection of JVP. Big
coking coal block. Land schedule is with
Ramgarh Distt office.

NALCO

Electrotherm
(India) Ltd,
Grasim Industries
Ltd

17

FC (Stg-II), ML are pending.


Company informed that earlier JVC
was formed between OMDC (26%
share) and Sainik Finance (74%
Share) which was not permissible.
OMDC
board
resolved
the
shareholding and changed the
shareholding pattern in 51:49 ratio
and also
resolved major pending
issues. Company requested MoC to
engage MCL to raise coal.
FC(Stg-I), ML, LA are pending.
Company stated that 98.4 crores
have been spent. Required amount
for 526 Ha for pvt land paid to Govt.
of Odhisa. 169 Ha forest land
acquired.
Previous approval, FC, EMP ML & LA
are pending. Requested MOC to grant
previous approval of ML. Forest
clearance is the main issue. Company
informed that State Govt. cancelled PH
resulting in delay in stage-I clearance.
Land is under SECL and is to be
transferred to State Govt.
RE block. After getting GR, company
will start other pre-mining activities.
RE block. GSI prepared GR and to
submit shortly. After getting GR,
company will start other pre-mining
activities.
RE block. PL took 2 years time. Tender
for additional 12 boreholes completed.
No progress.
RE block. GR to be submitted to Govt
of JH. FDP will be prepared shortly.
Tech. bid opened. No other progress.
RE block. Regional GR purchased.
CMPDIL stopped drilling work. Land
schedule submitted.
RE block. Subjudice before the court.
Monnet Ispat Ltd is petitioner. Earlier
MDO selection process cancelled. No
Progress. CCO intimated that they have
not submitted status report to CCO
every quarter.
RE block. Drilling completed. MP
preparation is returned by CMPDIL.

22

Rabodih OCP

25.7.07/ Jan.11

JSMDCL

23

Bramhadih

26.2.96/ Aug.99

24

Lalgarh North

8.7.05/ Jan.09

Castron Mining
Ltd.(formerly
Castron Tech.
Ltd.)
Domco Pvt Ltd

25

North Dhadu

13.1.06/ July,09

26

Jitpur

20.2.07/ Aug.10

27

Seregarha

9.1.08/ Oct.13

28

Mahuagarhi

9.1.08/Oct.13

Remarks on progress. MP approval, FC,


EMP, ML & LA are pending. GR
available. EIA preparation is processed.
Draft Mining plan prepared. 745 acres
area is under forest land.
Abandoned U/G coking coal mine.
Company requested to treat coke plant
as EUP and to wash coal and to make it
coke. PRC is 1.5 LTPA
MP approval, FC/EMP/ ML & LA are
pending. No progress. 2 Mining plans
have been submitted to MOC. 65 acres
land purchased. Company intimated that
6 months will be required for FC/EMP
after MP approval. Financial closure for
EUP has not been completed.
FC, EMP, ML LA are pending.
ML application submitted. 220 acres
land acquired. Modified/revised mining
plan submitted to MOC in Oct.2011.
Forest clearance application submitted.
Dump area problem is there. Approval
of revised mining plan is the main issue.

Electro
Steel
Casting
Ltd,
Jharkhand
Ispat
Pvt Ltd, Pawanjay
Steel & Power
Ltd,
Adhunik
Alloys & Power
Ltd.
JSPL
FC (Sgt-I), ML, LA are pending.
Queries raised by State Govt. has been
replied. Mine Closure plan approved.
Forest clearance application made in
2008. Stg-I clearance is pending at State
level. Process to set up End use power
plant of 2x600 MW is going on. Land
and water tied up. MOU signed with
State Govt. 139 ha forest land for which
money has been deposited.65 acres are
tenancy land and 365 acres Pvt land.
Requisite amount deposited for Govt
and Pvt land. Location of EUP is 10-20
Kms away from pit head.
Arcelor Mittal
RE block. Company informed that 50%
India Ltd & GVK drilling completed. M/s. Naresh Kr &
Power (G.Sahib)
Co is the drilling agency.PL signed in
Ltd.
March 2011. Difficult in setting up of
steel plant.
CESC Ltd & Jas
RE block. Company informed that TOR
Infrastructure Ltd
received. Drilling is continuing. Assured
to expedite exploration. Law and order
is main issue to be resolved.

18

29

Choritand Tailaya

14.5.08/ Nov.11

Rungta Mines Ltd


& Sunflag Iron &
Steel Ltd

30

Macherkunda

5.8.08/ Feb.13

Bihar Sponge Iron


Co Ltd.

31

Rajhara North
(Central &
Eastern)

20.11.08/ Nov.11

Mukund Ltd, Vini


Iron & Steel
Udyog Ltd.

32

Tadicherla-I

06.12.05/ Dec.08

Andhra Pradesh
Power Generation
Co. Ltd.

33

Nerad
Malegaon

13.1.06/ Jan.10

Gupta Metallics &


Gupta Washeries
Ltd.

34

Gondkhari

21.11.08/ Nov.12

35

Dahegaon
Makardhokra
IV

17.6.09/ Dec.13

3637

Mahanadi &
Machakata

6.2.06/ Dec.11

Maharastra
Seamless
Ltd,
Dharial
Infrastructure Ltd
&
Kesoram
Industries Ltd
IST Steel & Power
Ltd, Gujarat
Ambuja Cements
Ltd & Lafarg
India Ltd.
MSEB & GSEB

19

Previous approval, ML, FC, EMP LA


are pending.
ML application is pending with State
Govt since March 2010. TOR obtained
in May 2011 Forest application made in
2010. Forest area density calculated.
Forest proposal presently lying with
ADC, Bokaro. NOC for diversion of
Jungle-jhari obtained. Law and Order
problem is there. 100 Ha land acquired
under CA scheme. Land and forest
clearance is the main issue to be sorted
out.EUP of SISL is operational (350
cuM BF)
ML, FC, EMP LA are pending.
Transfer of land by CCL to company is
a
long pending issue. CMPDIL
informed that GR cost not yet submitted.
395 Ha land has been given to BSIL out
of total 600 Ha. Explored block.
MP approval, EMP, ML & LA are
pending. CCL to transfer land. Lack of
support from CCL. Employment
problem at the mine area. No forest land
involved. EMP study conducted by
MOEF. TOR approved. Requested
MOC to for change of Option to develop
the block
Vini said that 100 crs spent for 87 acres
land. Mukund will pay BG after
finalization of Option-II.
FC(Stg-I), EMP, ML & LA are pending.
APGENCO decided to transfer the
project to SCCL. Land issue settled.
EMP application submitted in Dec 10.
52 Ha forest land involved. Diversion of
Forest land proposal submitted to State
Forest Department.
Grant of previous approval, EMP, ML,
LA are pending. Main issue is grant

of previous approval for


Lease. 65% land acquired.

Mining

EMP, ML & LA are pending


ML is pending with Govt of
Maharashtra. No forest land is involved.

MP approval, FC/EMP, ML & LA are


pending. ML returned to State Mines
Department on Dec 2011. Applied for
forest clearance in Nov 2011.

FC Stg-I), EMP, ML & LA are


pending. Previous approval obtained
recently. PH for EMP is not yet
completed. Villagers resistance and
land acquisition is the main issue.

38

Naugaon Telisahi

2.8.06/ May.12

OMC &
APMDCL

3940

Chendipada &
Chendipada-II

25.7.07/ Jan11
(Chendipada)
Apr.13
(Chendipada-II)

UPRVUNL
CMDC
MPGCL

41

Baitarni West

25.7.07/ Jan.11

KSEB, OHPGCL
& GPCL

42

Mandakini-B

25.7.07/ April,13

43

Naini

25.7.07/ April, 13

Assam State
Mineral Dev Corp.
Ltd, Meghalaya
State Mineral Dev
Corp. Ltd, Tamil
Nadu Electricity
Board & Orissa
Mining Corp. Ltd
GMDC, PIPDCL

44

Utkal-A &
Gopalprasad

29.11.05/ May.09

MCL/JSW/JTPL/J
indal Stainless
Ltd/ Shyam
Metallics Pvt Ltd

45

New Patrapara

13.1.06/ July,09
(revised to
15.12.2010)

Bhushan Steel Ltd


(Formerly known
as Bhushan Steel
& Strips Ltd) & 5
Others.

20

RE block. Drilling completed. GR


prepared. MP preparation awarded to
CMPDIL. Interaction with two states
(Odhisa & Andhra Pradesh) are the
main issue. Requested MCL to form
JVC.
Previous approval, FC, EMP ML & LA
are pending.

TOR issued. 53.4 crs paid to IDCO.


Issue of 4(1) notification is pending.
PL for Chendipada-II block will be
applied in 3-4 months. Land
Acquisition not yet started. Forest
Diversion Proposal submitted. If
clearances are fast-tracked, coal
production is expected by 2014. Sec
(4) & (11) will require 1 year time.
FC, EMP, ML & LA are pending.
Explored by CMPDIL in 2008.
Administrative approval of Govt of
Odhisa will be obtained soon. Land is
the main problem. Selection of
Chairman of JVC is in process. OPGCL
& KSEB will jointly set up power plant
at Orissa.
FC, ML, LA are pending.
RE block. Permission of DFO for 5 no.
of boreholes obtained. PL is yet to be
obtained. 33 % rejects based free power
to state Govt is the main issue. MP
approval pending. Board to take
decision with State Govt over land
issue. Land acquisition not yet started.
RE block. GR Prepared on indicated
data in Dec 2011. CMPDIL will
prepare draft MP within 5-6 months.
Land notification issued. EUP of
PIPDCL: Pit head power plant. 90 acres
land acquired. GMDC to sort out the
issue of location of EUP immediately.
FC(Stg-I), EMP, LA are pending.
Company stated that Stg-I FC is
expected by June 2012 and Stg-II
within 3-4 months thereafter. 240 Ha
land acquired and balance land will be
acquired in a phased manner. EMP will
be granted 3-4 months after forest
clearance. MCL is facilitating all the
clearance process.

MP approval, FC, EMP, ML & LA


are pending. SC raised some queries
on MP approval but reply is yet to
be received. Govt. of Odhisa &
CMPDIL
will
look
into
transportation issue. No area for OB
dump.

46

Radhikapur
(East)

7.2.06/ Aug.09

Tata Sponge Iron


Ltd, Scaw
Industries Pvt
Ltd, SPS Sponge
Ltd.

FC, EMP, ML & LA are pending.


MOEF recommended EC in Dec
2011. Gram Sabha cleared FC. 75
crs disbursed for Land acquisition.
50% disbursed in 2 villages. Land
Acquisition is presently on hold.
Land allocated for R&R project.
EUP is operational.

47

Ichapur

2.8.06/ May.12

WBMDTC Ltd.

48

Kulti

2.8.06/ May.12

WBMDTC Ltd.

49

Jaganathpur-A

20.7.07/ Dec.14

WBMDTC Ltd.

MP approval, FC/EMP, ML & LA are


pending.
GR prepared in Dec 2011. Mining plan
will be submitted soon. Production as
per schedule.
Exploration completed and GR to be
completed by Jan 2012. MP to be
submitted after GR preparation.
MP approval, FC, EMP, ML & LA are
pending. TOR for EMP received.
Presentation of MP before screening
committee done.

50

Jaganathpur-B

20.7.07/ Dec.14

WBMDTC Ltd.

51

Sitarampur

27.12.07/ Sept.14

WBMDTC Ltd.

52

Gourangdih ABC

10.7.09/ Jan13

Himachal EMTA
Power Ltd & JSW
Steel Ltd

5354

Moher & Moher


Amlori Extension

13.09.06 (zero
dt.Aug.07)/ Feb.11

M/s. Sasan Power


Ltd (an SPV of
PFC for MP
UMPP) has been
transferred to
Reliance Power
Ltd.

21

MP approval, FC/EMP ML & LA


are pending.
Presentation for MP done. MoC
asked some clarifications which will
be sub mitted by Feb 2012.
No forest land is involved.
Drilling completed.
GR to be prepared soon. Preparation
of MP is in process. All activities
will be after MP approval.
FC, EMP, ML & LA are pending.
FC application finalized. Selection of
MDO will require 2 months. MP
approved with 2.5 mtpa mine capacity.
No significant progress achieved.
Quarterly EUP report not being
submitted to CCO.
LA is pending. Land acquisition is the
main issue.

55

Moitra

13.5.05/ Nov.08

56

Lohari

24.8.05/ Aug.08

57

Chitarpur

58

Dumri (explored)

Jayaswal Neco
Ltd.

2.09.05/ March.09

13.1.06/ July,09

FC (Stg-I), ML & LA are pending.


Moitra is a coking coal block. Company
informed that forest application made in
2005 and is still pending. Forest
clearance is the main hurdle to develop
the project. Representative from Govt.
of Jharkhand stated that forest proposal
forwarded to MOEF by State in Sept.
2011. Govt of Jharkhand stated that
forest issue is pending with MoEF.
Satelite maps (DGPS maps) to be
submitted. Company deposited 8 crores
towards purchase of land to State Govt.
Mining lease will not be granted unless
grant of forest clearance.
Usha Martin Ltd.
Previous approval, FC, ML & LA are
pending. CCL transferred acquired land
to company in 2009.Land problem is
there.89 Ha land is jungle-Jhari. Land
acquisition pending. The process of
Previous approval of ML to start by end
of 2011-12.
Corporate Ispat
ML, FC (Stg-I), LA are pending.
Ltd
Company informed that FC (Stg-I) is
expected by March. 2012. 600 acres
land acquired and is in physical
possession. Washery is there.
Neelachal Iron & FC, ML LA are pending. Previous
Steel
Ltd
& approval obtained. Stg-I is pending with
Bajrang Ispat Pvt MOEF. CHP is commissioned. Entire
Ltd.
EUP plant is ready.

LIGNITE BLOCKS
(I)

The following lignite blocks have started coal production. The Committee advised the
allocattees of the lignite blocks which have not attained the peak rated capacity to attain
the same as per the approved mining plan at the earliest.
Name of Allocatee/JV
Sl.
No

Name of lignite blocks

Year of allotment

1.

Giral

1994 (Lease granted)

Sonari

28.8.2004

3.

Kapurdih

13.11.2006

4.

Matasuk

26.7.2002

RSMML

5.

Mata-No- Madh

Gujarat Mineral Dev Corp.


Ltd. (GMDCL)

6.

Panandhro

16.5.2001(lease granted for


1314 Ha) & 31.5.2006
(Lease granted for 437 Ha)
21.7.1973 (Lease granted
for 1151 Ha) & 26.6.1988
(Lease granted for 568 Ha)

2.

22

Rajasthan State Mines &


Minerals Ltd (RSMML)
RSMML
RSMML

GMDCL

7.

Tadkeswar

5.12.2001

GMDCL

8.

Surka (North)

5.12.2001

GMDCL

9.

Rajpardi (G19 & G19


Extn) or Amod

5.12.2001

10.

Vastan

July,1996 (Lease granted)

GIPCL

11.

Khadsaliya

Not available

GHCL

12.

Gurha East

1.7.2005

13.

Mongrol Valia

9.3.2000

GMDCL

V.S.Lignite Power Pvt Ltd.


(No one attended the
meeting)
GIPCL

The progress of the following blocks was not found to be satisfactory. Committee expressed

(II)

concern over unsatisfactory progress and advised to expedite the development of the lignite block
and be cautioned to be careful in future w.r.t the milestones stipulated. If they do not improve the
performance on the speedy development of the block further, action including deduction of
BG/de-allocation would be considered
Sl.
No.

Name of Lignite Block

Allocation date

Name of Allocatee

1.

Kaparion Ki Dhani

7.2.2007

DCM Sriram Consolidated Pvt


Ltd

2.

Gurha West

1.7.2005

RSMML

3.

Jalipa

13.11.2006

RSMML

4-5.

Shivkar Kurla
&
Sacha Sauda

13.11.2006

RSMML

The progress of the following lignite blocks was found to be cause of concern. Committee

(III)

expressed concern over the progress and recommended that the allocatees be served with showcause notice to explain why the block should not be de-allocated .

(IV)

Sl.
No.

Name of Lignite Block

Allocation date

Name of Allocatee

1.

Mokhala

14.7.2003

RSMML

2.

Merta Road

7.02..2007

NSL Power & Infratech Pvt Ltd.

Regarding the progress of the following blocks, the Committee noted the position as
stated by the allocatees and advised accordingly.

23

Sl.
No.

Name of Lignite
Block

1.

Mandal Charan

2-3

Allocation
date

Name of
Allocate

Status/ View of the Committee

7.2.2007

Indure Pvt Ltd.

Khadsaliya-II
&
Surka-III

6.9.2005

GIPCL

4.

Akrimota

Not
available

GMDC

5.

Indwar

7.2.2007

Nandlal
Enterprises Pvt
Ltd.

6.

Nimbri Chandawatan

7.2.2007

Binani Cements
Ltd.

It was stated that the block was not


found to be viable after drilling 38
boreholes and the allocatee requested
to allocate an alternate block. The
Committee advised to take up the
issue of an alternate block with MoC
separately.
It was stated that the Surka-III block
was not found to be viable. The
Committee advised to file an
application to MoC for surrendering
the block and approach CCO to
calculate the revised BG after
surrendering the Surka-III block.
Committee also advised MoC to
expedite the prio approval of ML for
Khadsaliya-II block.
It was stated that activities are
pending due to Supreme Courts order
and the block also falls in the Tiger
corridor and GMDC has requested for
an alternate block. The Committee
advised to take up the issue of an
alternate block with MoC separately.
It was stated that the reserves in the
block are very less and requested to
revise the BG as per the revised
reserves. The Committee advised
MoC to sort out the issue.
It was stated that MoEF has referred
the issue of wetland area in the block
to ISRO for some clarifications. The
Committee advised the allocatee to
pursue the issue with MoEF.

Meeting ended with the vote of thanks to the chair.

--------------

24

Names of representatives of Ministry of Coal who attended the Review meeting held
on 11.01.2012 and 12.01.2012
Sl.No.
1
2.
3
4
5.
6.

Name & Designation


Ms Zohra Chatterji, Additional Secretary.. In the Chair
Shri A.K. Bhalla, Joint Secretary
Shri P.S. S. Reddy, Director
Shri D.N. Prasad, Director (Technical)
Shri Sandeep Gupta, Under Secretary
Shri V.S. Rana, Under Secretary

25

Names of representatives of Central/State Government/PSUs who attended the Review


meeting held on 11.01.2012 and 12.01.2012
Sl.No.
1
2
3
4
5
6
7
8
9
10

11
12
13
14
15

Name & Designation


Sh B.N. Basu,
Sh. V. Appa Rao, Director
Sh R. Kandasamy, Director (P&P),
NLC Ltd
Sh. K.B. Nair, Under Secretary
Dr.S. Mazumdar
Sh. G. Dhar, CGM
Sh A.K. Sarkar, Addl. Chief
Secretary
Dr. K.V.V.S. Gautam, GM (Expl
Service), CMPDI
Sh. A, Acharya, Coal Controller
Sh Romit Mutsuddi, Executive
Director,
WBIDC
&
M.D.,
WBMDTC Ltd
Sh. K.B. Nair, Under Secretary
Sh Vipin Saxena, Sr. Resident
Commissioner
Sh. N.C. Mohanty, Adviser (Coal),
Govt. of Odisha
Sh. J.P. Prakash, Principle Secretary,
Government of Meghalaya
Sh. B.N. Basu, DT(CRD), CMPDI

26

Ministry/Deptt/Organsiation
Director (Technical), CMPDI
Ministry of Power
Neyveli Lignite Corporation Ltd
Ministry of Steel
General Manager (Geology), CIL
Coal India Limited
Government of Jharkhand
CMPDI
Office of Coal Controller, Kolkatta
Commerce and Industries Department,
Government of West Bengal
Ministry of Steel
Government of Orissa
Government of Odiha
Government of Meghalaya
CMPDI

Names of representatives of coal/lignite blocks allocates who attended the Review


meeting held on 11.01.2012
Sl.No. Name
Company
1
Sh A.K.Makadia
GMDC
2
Sh P.J. Jain
GUVNL (erstwhile GEB)
3
Sh B.M. Verma
ESSAR Power
4
Sh Deepak Kamra
D B Power
5
Sh Pankaj Bhardwaj
D B Power
6
Sh Partha Mazumdar
NTPC
7
Sh Dilip Kumar Das
Corporate Ispat Alloys
8
Sh Gyan Chand Agrawal
Pawanjay Steel and Power Ltd.
9
Sh. R.B. Mathur
Mahatamil Collieries Co. Ltd
10
Sh N. Singh
Madanpur (N)
11
Sh Malay Kar
Abhijeet Infrastructure Ltd.
12
Sh.A.K. Srivastava
-do13
Sh. M.B. Mathur
Jayaswal Neeco Ltd
14
Sh A.P. Lohiya
Ultratech Cement
15
Sh Krishan Kumar Garg
Anjani Steels Ltd.
16
Sh P.K. Mishra
Electrosteel Castings Ltd
17
Sh Rajesh Goverdhan
CMDC
18
Sh P.S. Yadav
CMDC
19
Sh P.C. Hembram
Power Finance Corporation
20
Sh B.K. Bhatia
BALCO
21
Sh G.K. Chhanghani
Sarda Energy
22
Sh. K.K. Tiwari
Gare IV/7
23
Sh G.K. Chhanghani
Madanpur South Coal Block
24
Sh A. Kuhar
TVNL
25
Sh R. Ranjan
TVNL
26
Sh R.K. Gaur
RRVUNL
27
Sh R.K. Mattoo
-do28
Sh M.P. Singh
Arcelar Mittal
29
Sh P.S.
-do30
Sh S. Roy Choudhury
-do31
Sh MMS Khadi
Fathepur
32
Sh N.M. Mishra
NTPC
33
Sh S.N. Goyal
NTPc
34
Sh B.D. Garg
BSIL
35
Sh Dinesh Anand
Bihar Sponge Iron
36
Sh Rajesh Sharma
Jindal Steel and Power Ltd
37
Sh D.N Abrol
-do38
Sh Neeraj Semwal
Goa IDC
39
Sh K K Shrivastava
Chhattisgarh Captive Coal Mining Ltd.
40
Sh Alok Trivedi
-do41
Sh A K Prasad
SKS Ispat and Power Ltd
42
Sh M Rama Rao
MTCL
43
Sh Sanjeev Anand
ESSAR Power Ltd
44
Sh BCK Reddy
GVK Power Ltd
45
Sh Anjani Kumar
Karanpura Energy Ltd
46
Sh Ajay Vishnoi
S K S Ispat and Power Ltd
47
Sh R.K. Kapur
Usha Martin Ltd
48
Sh Mubarik Khan
Hindustan Zinc Ltd
49
Sh Alok Choudhari
Chhattisgarh Steel and Power Ltd
27

50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81

Sh Amil Kumar Curi


Sh Anuraj Bansal
Sh D.K. Jain
Sh Vijay Surjan
Sh Amarjeet Vish
Sh Kamal Ghosh
Sh R.V. Mathe
-doSh Shashank Jaiswal
Sh S.K. Moitra
Sh R.N. Singh
Sh Sudhi Kapur
Sh A.K. Mukherjee
Sh Ashok Sharma
Sh S.C. Wahie
Sh Gagan Pant
Sh Prashant Lahane
Sh Amitabh S. Mudgal
Sh Anuj Kumar
Sh Arun K Shukla
Sh Rahul Tiwari
Sh A.K. Singh
Sh S.M. Devraj
Sh Deepak Kumar
Sh V. Ravikumar
Sh T.K. Natta
Sh Arvind Kumara
Sh A.K. Tooley
Sh S.B. Chakravarty
Sh S.K. Puri
Sh A.R. Sharma
Sh M E Ahmed

82
83
84
85
86
87
88
89
90
91
92
93
94
95

Sh Subhash Jetly
Sh Chanakya Chaudhary
Sh Vijay Kachroo
Sh. R.P. Goyal
Sh B Akla
Sh Shashi Kant N Mehta
Sh V.R. Kochar
Nandita Singh
Sh Aditya Verma
Sh R.N. Choubey
Sh Viren K Mital
Sh C.S. Moorthi
Sh Arindam Mukherjee
Sh Amitabh Chatterjee

MSP Steel & Power Ltd


Sunflag Iron & Steel Co Ltd
Rungta Mines Limited
Rathi Udyog Ltd
Castron Mining Ltd.
-doVandana Energy & Steel (P) Ltd
Vandana Vidhyut Ltd
Jindal Power Ltd
JLD Yavatmal
MMTC
MMTC
NIPL (Dumri)
DOMCO
Bhushan Power & Steel Ltd
API Ispat & Powertech Pvt Ltd
CG Consortium Coalfields Pvt Ltd
Monnet Ispat & Energy Ltd
Vinni Iron and Steel Udyog Ltd
JSMDC
Bhaskarpara Coal Co. Ltd
Grasim Cement & Electrotherm (I) Ltd
VISA Power Ltd
-doCESC Ltd.
-doSAIL
Pachwara North of WBPDCL
TVNL
PSPCL
EMTA Coal
Joint Commissioner, Govt of Bihar for
BRKVNL
Adhunik Alloys & Power Ltd
Tata Steel
Tailaya UMPP, Jharkhand
Bhushan Power & Steel Ltd
MMTC
MMTC
Tata Power
-do-doMukund Ltd
-do-doRohne Coal Co Ltd, JSW Steel Ltd
Rohne Coal Co. Ltd. JBNL

28

Names of representatives of coal/lignite blocks allocates who attended the Review


meeting held on 12.01.2012
Sl.No. Name (S/Sh)
Company
1
Rajesh Sharma
Jindal Steel and Power Limited
2
Lalit Joshi
Bhushan Steel Ltd
3
D.K. Jain
Rungta Mines Ltd
4
N.N. Mishra
NTPC
5
Y Rajeshwra Reddy
APMDC
6
Sanjeev Anand
ESSAR Power Ltd
7
D.P. Selvan
NMDC Ltd
8
Soumya P Patnaik
NALCO
9
Arvind Pujari
Revati Cements P Ltd, Kamal Spong Steel
& Power
10
A.K. Saxena
B S Ispat Ltd
11
D. Ramakrishnan
TANGEDCO (OMC, AMDC, MMDC)
12
N.C. Mohanty
-do13
K.C. Sarangi
-do14
V.K. Jain
Wani Coalfields Pvt Ltd, Nagpur
15
Ashok Mudhra
-do16
Anil Deshmukh
-do17
P.Y. Tembhas
MSMC Warora Collieries Ltd
18
-doAdkali Natural Resources
19
R. Nagarjuna
Karnataka Power Corporation Ltd
20
T.C. Sharma
NCT of Delhi and HPGCL
21
S.K. Goswami
Kerala State Electricity Board
22
G. Sreeniwasan
-do23
S.P. Rath
-do24
Atul Jain
Pushp Steel and Mining Pvt Ltd
25
M.S. Sandhu
Jaiprakash Associates Ltd
26
S.N. Chawla
-do27
R.L.Mattoo
Adani Power Ltd
28
J.K. Pohwa
VISA Steel Ltd
29
Kapil Dhagat
Bhushan Steel Ltd
30
V.K. Kaul
-do31
S.R. Singh
UCM Coal Company Ltd
32
C.K. Bansal
Ambuja Cement Ltd
33
Kamlesh Sharma
-do34
Gaurav Gupta
-do35
Alok Gupta
-do36
S.K. Mitra
Sree Veerangana Steel Ltd
37
J. Ravindranath
Prism Cement Ltd
38
Ashwani Kumar
Sasan Power Ltd
39
M.A. Khan
Orissa Sponge Iron & Steel Ltd
40
D.S. Ahlawat
YCCPL (Jt venture of Govt of Haryana and
Delhi
41
S.K. Mandal
MPSMCL
42
D.K. Mitra
Bank DRI Mining
43
Ajay Vishnoi
SKS Ispat Ltd
44
A.K. Prasad
-do45
H.S. Rajore
Chinora & Warora
46
Amrendra Kumar
MCL & JVMNH Shakti Ltd
47
Harsha Vardha
Rajasthan States Mines and Minerals Ltd
29

48
49
50
51
52
53
54
55
56
57

Dr. K Shirod Brahma


S.K. Kar
R.B. Mathur
D.K. Sahni
Rajeev Lala
R.C. Bagla
V. Chadha
P.K. Dave
Sanbjeev Gor
Executive Director

58
59

-do
A.K. Gupta

60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96

Lalit Beniwal
S.C. Khera
M.B. Mathur
A.K. Giri
M.A.N. Srivastava
B.S. Sinha
Radhakrishan K.S.
S.S. Puri
N.K. Purohit
A.K. Makadia
Deepak Lal
Prem P Srivastava
-doS.K. Goswami
S.K. Gupta
S.S. Dang
S.C. Jain
S.C. Wahie
P. Girish
Amitabh S. Mudgal
M.K. Sinha
Sanjay Jain
Amitabh Chatterjee
Devinder Arora
Deepti Singh
K. Kasturi
Sanjay Mkupawat
A.K. Thakur
U. Chatterjee
R.K. Agarwal
Robin Bose
Piyush Srivastava
Punit Gupta
Dr. V. Madri
Abani P Mishra
A.K. Samal
K.P. Agrawal

Orissa Power Generation Corporation


-doLANCO Infratech
Utkal Coal Ltd
-doBander Coal Company (P) Ltd
-do-do-doMAHAGENCO, MGCL (Macchakatta coal
block)
MAHAGENCO, MGCL (Bhivkund block)
Kesoram Industries Ltd, Maharashtra
Seamless Ltd, Dhariwal Infrastructure (P)
Ltd
Sova Ispat Ltd
Mideast Integrated Steel Ltd
Bander Coal Mining Pvt Ltd
Chaman Metaliks
Narbharam Power and Steel Ltd
Howrah Gases Ltd
DSCL
MESCO
GIPCL
GMDC, PIPDIC
Indure Pvt Ltd
OIPL
SIPCL
GPCL
Sunflag Iron and Steel Ltd
Birla Corporation Ltd
Shri Mahavir Ferro Alloys Ltd
Bhushan Power and Steel Ltd
Jindal Phot
Monnet Ispat
-doOcean Ispat Pvt Ltd
Jaibalaji Industries Ltd
Areclar Mittal India
-doACC Ltd
Adhunik Corporation Ltd.
MJSJ Coal Ltd.
Tata Sponge
Concast
Binani Cement Ltd
SETSPL (North of Arkhapa and Srirampur)
Jindal India Thermal Power Ltd
Lanco Babandh Power Ltd
GMR Kamalanga
-doRSMML/BLMCL
30

97
98
99
100
101
102

Pradeep Mittal
Subhash Jetly
A.K. Tooley
R. Bose
A.C. Sharma
M.S. Cheema

Rampia Block, Orissa


Adhunik Metaliks Ltd
Bengal Emta
WBPDCL
HPPCL (HEPL)
JSW Steel Limited

******

31