Академический Документы
Профессиональный Документы
Культура Документы
R.E. OTT
Echometer Company
Consultant
F. COLLIER
A.L. PODIO
Abstract
With more and more emphasis on reducing the operating
costs for beam units, operators are examining several approaches to cut costs. One of the biggest costs in beam unit operations
is the electrical power cost.
Controlling pumping units to adjust to the optimum counterbalance will reduce the electrical bill. Several pumping untits
have been checked with a PC software program (POWER),
which allows the operator to determine how far out of balance
the units are and what it will take to properly balance them.
Properly balanced pumping units will result in electrical savings
both in demand and in consumption, thus reducing total electrical costs.
Examples from several fields are provided illustrating actual
power costs and the reduction in expenses that occurred.
Introduction
The first approach in determining whether the pumping unit
requires re-balancing or motor downsizing is to conduct a power
survey of the field. When the POWER software first became
available, it was used on several individual wells to determine if
the unit had an out of balance problem or the motor was too large.
The POWER program requires actual data. Two current and
three voltage probes are connected to the incoming electrical
lines. During two strokes of the pumping unit, power and current
data is stored in computer memory for interpretation. The power
data is converted to gear box torque and if out of balance condition is observed the program recommends the counterweight
adjustment required to achieve a better balance. The actual time to
measure these values is small, but all the data is necessary to
properly interpret the condition of the well. If the well is operated
with a pump-off controller, one must determine the condition of
the well for the majority of the run time, since pumping conditions
may vary widely from first coming on to just before pump-off.
The first small field surveyed consisted of 17 producing wells
in the Waddell Field, near Crane, Texas. Production depths ranged
from 2,635 m to 2,937 m (8,700 to 9,700 ft.) and all wells were
equipped with beam pump units. The Waddell field has a history
of high gas-oil ratios, which has caused some lifting problems in
the past. Incomplete pump fillage is not uncommon since, in some
cases, the tubing intake is located above the perforations, due to
the presence of liners and open-hole completions.
Direction of pumping unit rotation was checked to determine
the direction that resulted in lower electrical power consumption.
In some cases, changing the direction of rotation did help reduce
Special Edition 1999, Volume 38, No. 13
PAPER: 95-25
Well No.
Production
(O/W)
Monthly
Charge $
Out of Peak
Balance,
M in-lbs.
Torque
Power M in-lbs.
Avg.KW
POWER
Software
Move Weights
319
324
323
102
321
313
320
422
327
605
326
401
47/9
16/30
18/26
14/15
70/48
23/48
46/26
94/101
29/4
40/13
58/16
48/6
236.
106.
472.
146.
791.
348.
497.
443.
149.
176.
488.
227.
124.
82.
80.
75.
70.
66.
54.
48.
51.
40.
36.
38.
410
189.
389.
226.
379.
207.
327.
268.
210.
179.
450.
243.
17.5
2.9
25.2
8.3
20.9
9.7
13.8
13.3
8.6
10.4
13.6
15.5
Remove weight
Move all in 11.25
Move out 25.125
Move weights out
Move RJL in 38.25
Move wts in 13,375
Add heavier weights
Move in 8.5
Remove weights
Move out 2 weights
Move XJR in 9.5
Move 2-2ROs in
POC. Because of this, the electrical costs were higher, since the
wells do not require continuous pumping. Personnel changes
occurred during the increase in electrical costs and this probably
led to the lack of communication between the lease operators and
other field staff. There were also some POC electrical problems
that were not immediately repaired and, because of this, the
POCs were not effective in controlling the operation of the wells.
While this work was being done, questions arose as to whether
there was any Rule of Thumb for determining how far out of
balance a unit would have to be to require action being taken
based on potential cost savings. For API 456 units and smaller, if
the out of balance is less than 10 per cent of the unit rating, it is
probably not worth moving the weights. For units more than 10
per cent out of balance (torque values), it will be worthwhile to
reposition the weights. For API 640 units and larger, anything
over 50,000 in./lbs. is worth repositioning the weights. This Rule
of Thumb is not firm, but should give the operator some guidelines on when to start moving weights. This statement is based on
work done moving counterbalance weights when the units were
less than 10 per cent out of balance.
Second Phase
Because of the success of the work in the Waddell field, the
TorqueValues
Before*
After
Change
Before*
After
236.
221.
770.
146.
753.
349.
595.
553.
123.
188.
488.
221.
194.
188.
853.
126.
781.
356.
605.
735.
87.
100.
262.
188.
-42.
-33.
+83.
-20.
+28.
+7.
+10.
+182.
-36.
-88.
-226.
-33.
301.
139.
388.
161.
316.
162.
344.
368.
178.
139.
404.
216.
306.
143.
429.
191.
297.
173.
349.
414.
180.
104
336.
196.
*The values reported here are from the resurvey of the field prior to moving weights
2
Days
KW
Demand
KWH
Used
Downtime
Days
Downtime
KWH
KWH w/o
Pump
Electric
Bill, $
$w/o
Pump
$/Day
w/o pump
28
28
28
31
30
549
576
559
547
543
314488
310092
347692
321419
280191
0
0
0
7
21
0
0
0
18799
56398
239291
234895
272495
256964
256021
15688.59
16046.21
16728.04
15849.78
14065.58
12068.43
13898.37
13165.93
12646.84
12351.67
431.02
496.37
470.21
407.96
411.72
Avg. 443.46
26May94 27Jun94
27Jun94 27Jul94
27Jul94 26Aug94
26Aug94 27Sep94
27Sep94 27Oct94
27Oct94 29Nov94
31
30
30
32
30
33
497
532
485
496
517
508
323456
268726
278387
303930
308138
331089
1.2
0
0
0
0
0
3134
0
0
0
0
0
243336
188158
197819
217991
227570
269049
14528.61
13659.94
13222.59
14031.25
14412.61
14846.52
11016.31
9921.84
9611.40
10276.22
10941.32
12985.96
355.36
330.73
320.38
321.13
354.71
393.51
Avg. 345.97
Note: Work was done in Mid-May 1994, to re-balance the counterweights
Well No.
Required
Counterweight
Adjustment
Power,
KWH
Peak Upstroke
Torque M-in lbs.
Peak Downstroke
Torque M-in lbs.
Balanced
M-in lbs.
18-26
25-5
19-14
19-17
18-21
23-15
18-14
19-18
23-11
25-3
MVB-1
AB-10
18-27
ABH-4
14-18
CBH-2
HSC-3
23-21
26-18
ABH-3
RPA-1
MVB-2
14-19
18-13
RPC-2
26-A9*
241 Out
212 Out
168 Out
125 Out
123 Out
114In
109In
108 Out
100In
99Out
87Out
86Out
73Out
70In
69Out
65In
60Out
59In
47Out
47Out
41Out
41Out
38Out
35Out
33Out
18In
10.1
6.6
6.4
11.3
8.7
17.2
7.5
16.7
7.5
11.0
9.5
14.2
7.0
11.4
7.5
3.7
10.1
14.5
13.8
8.5
4.9
3.4
9.3
7.4
7.7
6.0
324.
321.
384.
393.
459.
197.
213.
531.
154.
243.
360.
349.
171.
188.
227.
154.
192.
103.
240.
257.
238.
188.
98.
342.
212.
158.
20.
58.
132.
187.
216.
420.
391.
372.
315.
73.
202.
188.
79.
177.
185.
224.
282.
341.
307.
290.
437.
256.
160.
277.
270.
123.
118.
181.
97.
138.
160.
192.
2 18
200.
155.
135.
312.
184.
175.
117.
214.
148.
176.
131.
156.
277.
151.
189.
Parks field was surveyed. The Parks Field contains about 90 producing wells, most of which are on a beam pump. This field also
has a high gas-oil ratio. Table 4 presents the results of survey data
through listing only wells requiring some re-balancing.
Counterbalance weights were moved to reduce electrical costs.
At the north end of the Parks field there are a few wells either
with individual meters or with a small number of wells tied to a
single meter. The wells were re-balanced according to recommendations from the POWER software program which was used in
conjunction with a conventional dynamometer. Data was collected
for the electrical bills in these smaller installations as well as the
larger single field meter. The water injection station was also
included in the larger master meter, so it was deducted from the
base meter rate to try to determine any changes in power use in
the field.
Special Edition 1999, Volume 38, No. 13
Table 5 presents the data for the main area in the Parks field.
An average saving of $50/day was obtained as a result of the rebalancing project. Table 6 presents the single well data. The single
well data is not as conclusive, because changes at the well head
(i.e., run time, downtime, pump-off-control resetting) affect the
electrical readings for the month. Individual well problems are
explained in the notes at the bottom of Table 6.
One area of interest in this work is the measurement of the
power factor for each well. Low power factors usually suggest
room for improvement in the electrical design/installation and this
was confirmed by the data. However, trying to obtain large
improvements in the power factor is not easy. Each well was optimized with the best electrical installation available (without completely changing out equipment) and large improvements in the
power factor were not always achieved. Decreasing motor sizes
3
Days
KWH
Adjusted
$Adjusted
$/Day
30
29
32
31
439600.
425909.
447158.
459658.
246568.
239311.
241257.
260192.
13694.68
13259.23
13600.04
13781.35
7692.92
7442.57
7334.21
7805.76
256.43
256.64
229.19
251.80
Avg. 248.52
12Aug94 14Jul94
14Sep94 12Aug94
13Oct94 14Sep94
14Nov94 13Oct94
15Dec94 14Nov94
29
33
29
32
31
412300.
471520.
420234.
478343.
486449.
225702.
232653.
187004.
195258.
174825.*
12517.91
13957.08
12783.55
14301.63
14574.75
6861.34
6886.53
5684.92
5838.21
5244.75
236.60
208.68
196.03
182.44
169.19
Avg.198.59
Days
KWH
Adjusted
$/Kilowatt
$/Day
30
29
32
31
29
16172.
16290.
21542.
19007.
18891.
16172.
16290.
21542.
19007.
18891.
1404.74
1479.76
1549.88
1520.65
1402.63
0.0869
0.0908
0.0719
0.0800
0.0742
46.82
51.03
48.43
49.05
46.82
Avg. 48.74
14Sep94 12Aug94
13Oct94 14Sep94
14Nov94 13Oct94
15Dec94 14Nov94
33
29
32
31
20509.
18173.
19655.
17532.
20509.
18173.
19655.
19532.*
1420.49
1366.75
1465.78
1348.94
0.0693
0.0752
0.0746
0.0769
43.04
47.13
45.81
43.51
Avg. 44.87
* 1. The AB Harrington #2 well was shut in for two weeks in early December
2. Data summed is from wells where counterbalance weights were moved (five wells adjusted, seven were not)
3. Work was done in August 1994 to re-balance the counterweights
Future Work
Most of the wells in West Texas are sized for larger than actual
pumping conditions. When the waterflood hits we have to be
able to pump it off! was a common statement years ago when
selecting both motor size as well as pumping unit size.
Consequently, there are many pumping units in West Texas that
are over-designed both for lifting capacity and motor size.
As a result of this work, an evaluation of the economics of
downsizing motors has been initiated. The approach is to carefully
measure the pre-KWH consumption and KW demand prior to
downsizing the motor, make the motor change, and then carefully
measure the results of this work. A well was selected in the
Russell Ranch field to do this experiment. A multi-channel electrical meter was installed on the well prior to downsizing the motor,
to determine the KWH per month, KW demand, and power factor.
A 72 hp unit is working on the well. The POWER software indicated a 30 hp motor would be sufficient to produce the well.
Once the results of this well are known, the plan was initiated
to select a small group of candidate wells for motor downsizing
4
Conclusions
The conclusion of these investigations are:
A. The utilization of the POWER software can help reduce
electrical costs.
Journal of Canadian Petroleum Technology
Acknowledgement
We would like to thank Mobil E & P U.S. for permission to
publish this paper. Thanks also are extended to Larry Logan and
James Wolf of Mobil for conducting many of the surveys.
Authors Biographies
James McCoy graduated from the
University of Oklahoma with a B.S. in
petroleum engineering and from Penn State
University with a M.S. in petroleum and
natural gas engineering. He is president of
Echometer Company, is a member of the
Petroleum Society and the Society of
Petroleum Engineers, and was the 1994
recipient of the Southwestern Petroleum
Short Course Slonneger Award.
Bill Drake graduated from the University
of Texas at Arlington with a B.S. in electrical engineering. He is an engineer for
Echometer Company and a member of the
Society of Petroleum Engineers.
REFERENCES
1. MCCOY, J.N., COLLIER, F.B., and PODIO, A.L., Application of
Real-time Measurement of Motor Power to Determination of Beam
Pump Efficiency; Southwestern Petroleum Short Course, Lubbock,
TX, 1994.
2. MCCOY, J.N., PODIO, A.L., JENNINGS, J., and DRAKE B.,
Motor Power, Current and Torque Analysis to Improve Efficiency of
Beam Pumps; Southwestern Short Course, Lubbock, TX, 1993.