SAP ERP Manufacturing - Production Planning (SAP PP): Introducing Flow, Part II Balancing a
Repetitive Line
SAP ERP Manufacturing - Production Planning (SAP PP): Introducing Flow, Part II Balancing a
Repetitive Line
Once all products are assigned to the Line Hierarchy, you can create a Line Balance for a short
term planning horizon of, lets say, 4 weeks. In that Line Balance, you copy the demand for
the next 4 weeks and calculate a takt time by which you need to run the model mix to fulfill
exactly that demand. This works in the following way: The system looks at the total demand for
all products in the model mix for the next 4 weeks and calculates a daily rate for the model mix,
which is necessary to meet the total demand over 4 weeks. Imagine you have 3 products - A, B
and C and a demand of 200, 400 and 100 pieces over the next week for these products. If there
are 20 working days in your next 4 weeks, you need to produce 10 As, 20 Bs and 5 Cs every day
to fulfill the demand over the next 4 weeks (according to EPEI heijunka leveling). Therefore you
need to produce 35 pieces on the line every day. If you have 7 hours available every day, you
need to produce 5 pieces per hour or introduce a piece into the line every 12 minutes this is
called the takt time. That, in turn, means that every work center has 12 minutes of work content
before it needs to move the product to the next work center.
In above example we have a maximum rate of 35 pieces per 7 hours and a model mix that
adheres to the maximum rate. Now we have to make sure that all operations in any work center
SAP ERP Manufacturing - Production Planning (SAP PP): Introducing Flow, Part II Balancing a
Repetitive Line
do not exceed the maximum allowable time in any work center the takt time. That, in essence,
is Line Balancing and may be carried out graphically in standard SAP.
In the Line Balance we can see that product 188 causes a takt violation with operation 0080 on
work center 65030TRY (note that work station 65030TRY has more work content available. This
is because we have more capacities available either more labor or more machine capacity). You
could now do either one of two things: either you increase the amount of machines used on work
center 65030TRY or you could move the operation to another work center, in the flow, that has
more work content available. Either way the takt violation is cured.
In any case, you have now calculated a takt time the speed by which the line must be run to
meet demand and you can now use takt-based scheduling to determine the sequence plan as
follows.
SAP ERP Manufacturing - Production Planning (SAP PP): Introducing Flow, Part II Balancing a
Repetitive Line
From here we can now perform a collective availability check, print the daily schedule or fill a
heijunka board on the shop floor. The schedule may also be connected with a Kanban control
cycle but that is stuff for another blog post
177 Views Tags: sequencing, heijunka, repetitive_manufacturing, repetitive_manufacturing;,