Академический Документы
Профессиональный Документы
Культура Документы
IN
HYDROPOWERGENERATION
http://www.cea.nic.in/best_practices_hydro.html
INTRODUCTION
1.
With a view to bring out a detailed document on the best practices and bench
marking covering various aspects of hydro power generation, the Central
Electricity Authority (CEA) constituted a committee under the Chairmanship
of Member (Hydro).
2.
3.
Chairman
Member
Member
Member
Member
Member
Member
Member
Member
Member-Secretary
4.
5.
iii)
iv)
v)
vi)
First meeting of the committee was held on 4th Oct. 2002 in the office of Sh.
B.K. Aggarwal, Member (Hydro), CEA at New Delhi wherein it was decided
to co-opt members from Central Water Commission, Irrigation Department,
Govt. of Maharashtra & Andhra Pradesh Generation Power Corporation Ltd.
also. The frame work of the document was also discussed in detail and it
was decided that a chapter on Best Practices in Operation & Maintenance
of Hydro Power Stations shall also be included. Views / suggestions /
supplementary information was desired from all the members of the
committee on the following chapters prepared by HE&TD / HE&RM Divisions
of CEA:(a)
(b)
(c)
After co-opting the members from various state entities, the composition of
the committee became as under:i)
ii)
iii)
iv)
v)
Chairman
Member-Secretary
Member
Member
Member
vi)
Member
Member
Member(Co-opted)
Member(Co-opted)
Member (Co-opted)
Member(Co-opted)
Member
Member
Member
6.
Second meeting of the Committee was held on 24th Oct, 2002 in CEA, New
Delhi wherein inputs received from NHPC, MSEB & KPCL were circulated
to all members of the committee for observations / views. Draft document
prepared on the basis of the material received from the members was
discussed in the third meeting of the committee held on 17th March, 2003 in
the office of Sh. V. S. Verma, Member (Hydro) CEA,
7.
iv)
The book was released by the erstwhile Honble Minister of Power in March
2004 and circulated to all Government power departments, Electricity Boards,
generation utilities & other organizations dealing with hydro power sector in
the country. The book has been widely received and suggestions for
modifications & enlargement of the scope were received from many quarters.
Sh. G. K. Pharlia, Member (Hydro), CEA also held a meeting with the
Committee members on 5th May, 2004 and suggested to bring out the latest
edition incorporating all the suggestions. Accordingly, an updated version
of the publication having revisions in the following chapters has been brought
out.
-
9.
It is hoped that the latest edition of the book will provide valuable guidance
to all persons working in various power utilities /organizations dealing with
hydro power sector in the country. Comments / suggestions to further improve
the book are welcome.
CHAPTER - 1
is the preliminary requirement that needs to be met by using state-ofthe-art scientific tools and techniques. The following chapter outlines
all the various necessary steps needed for this essential exercise.
1.1
INTRODUCTION
1.1.1
1.1.2
Besides, these DPRs need to get clearance from the Central Soil and
Material Research Station (CSMRS) from construction material aspects
and the Geological Survey of India (GSI) from geological aspects.
1.1.3
1.1.4
1.2
1.2.1
The following activities are carried out for the various alternatives
considered to justify the final choice of the location of different components
of the project :a)
b)
River surveys
Reservoir surveys
6
c)
d)
e)
f)
g)
The different activities of survey and investigations which are carried out
before preparing a Detailed Project Report are given in Sub-para 1.2.2.1
to 1.2.2.4.
Dam Site: Dam site area covering upto 500m upstream and 500 m
downstream of the dam axis (can also be finalized based on the
other important features like height of dam, location of diversion
portals, coffer dam and also the work area required on both the u/s
and d/s of the dam etc.) extending upto an elevation of top of dam +
1/4 of dam height depending upon the geological requirement and
slope stability vis-a-vis abutment stripping. The contour interval
should be 1m to 5m depending on the topographical characteristics
of the valley. The dam site survey should also include the area
required for diversion arrangement, intake structure, and other
appurtenant structures. The scale of the maps may vary from1:500
to 1:2000 depending upon the size of the area.
7
iii)
Survey for Power Channel: The width of the area considered for
contoured map/survey is 150m on either side of the center line of
the channel. The scale of the map should be 1:2000 to 1:5000.
iv) Survey for tunnel: The project area maps are used for initial
geological mapping and fixing of alignment of tunels, adits etc. in
consideration with the required rock cover. Later for detailed studies
and layout finalization 100 m to 400 m wide strip along the tunnel
alignment in a scale of 1:2000 to 1:5000 is considered. The
8
v)
vi) Project area map: The scale for the topographical map of the project
area is decided based upon the spread of the project area. If the
project area is spread upto 5 km, a scale of 1:5000 is adequate.
For project spread upto 10 km, normally a scale of 1:10,000 is
considered and for bigger area, a scale of 1:15,000 is adequate.
1.2.2.2 Engineering geological, geophysical, Seismological and
Construction material survey
(i)
General
These investigations are now considered as a fundamental
requirement of planning & design of large civil engineering structures
pertaining to hydroelectric Projects. All dam sites, power house
locations, tunnel alignments, major bridges etc. need to be thoroughly
explored before arriving at their techno-economic feasibility.
Subsurface exploration, comprising particularly of diamond core
drilling and exploratory drifts are the main stay of geological
investigations.
9
Surface investigations
After ascertaining the regional geology of the area the site specific
geological mapping is taken up by intensive surface traverses of
the project area and also with the aid of aerial photographs & satellite
imagery, for coverage of inaccessible area comprehensively.
Observations and measurements of the items such as nomenclature
and classification of rock, stratigraphy and geological structure,
properties of the ground are recorded and the data that is necessary
for knowledge of the general geological condition is gathered.
b)
c)
d)
e)
f)
(v)
Seismological Survey
Details of seismological events are collected from IMD, New Delhi
and site specific design earthquake parameters are evaluated either
by the institutes such as IIT, Roorkee or CWPRS, Pune, for working
out the site specific design earthquake parameters. These
parameters are further put up to National Committee on Seismic
Design Parameter for final approval before adopting the same in
detailed design of the project. Micro Earthquake studies are also
conducted for the assessment of seismicity of the area and
demarcation of the active faults in and around the project area,
depending upon the sensitivity & magnitude of the project.
(vi) Rock & Soil Mechanic Testing and Construction Material Survey
a)
Laboratory Testing
It is conducted to evaluate the engineering properties. Some of the
laboratory tests are
b)
Field Testing
These include the following
Rock stress determination using flat jack, over coring and hydro
fracturing
12
Laboratory and field tests for following materials are carried out
Rainfall
Gauge
Discharge
Sediments
Water quality
Evaporation
Availability of water for the benefits envisaged
Design flood for various structures
Environmental survey
Forest area involved
Likely displaced persons
13
1.3
1.3.1
Pre-Feasibility Stage
Feasibility Stage
Detailed Investigation (DPR) Stage
Construction Stage
Pre-Feasibility Stage
It is more of a desk study with limited field checks. Based on the 1 :50000
or 1 :25000 scale Survey of India toposheets, possible hydroelectric sites
are marked. These sites are examined by preliminary field traverses
wherein topography, broad geological aspects in terms of locating the
project components are looked into.
If required, broad assessment of the terrain at the likely site is also carried
out by geophysical survey to understand the sub surface condition of
the rocks.
1.3.2
Feasibility Stage
After selecting the site during Pre-feasibility stage, intensive field
traverses are under taken. Detailed survey like contour plans and sections
in 1: 1 000 to 1 :5000 scale are prepared for various important structures
such as dam, tunnels, powerhouse, etc. One or two alternate axis are
probed by detailed geophysical survey and a few drill holes to ascertain
depth and quality of bed rock besides carrying out broad geological
mapping & collection of regional geological information. The hydrometeorological data collection is also started during this stage. Based
on this data, lay-out of the project is prepared and its techno-economic
viability is established.
14
1.3.3
At least one drill hole shall be placed specifically for energy dissipation
arrangement immediately after the spillway. A provision of at least three
drill holes is generally kept separately for spillway in case it is a side
channel spillway, away from the main body of the dam. The location of
coffer dam in the river bed portions especially for the upstream one is
required to be probed by a drillhole to understand nature of overburden
material and bedrock depth. Similarly, for diversion tunnel also, a
provision of minimum three drill holes is kept with one each at the inlet &
outlet portals and the third one suitably placed on the tunnel alignment,
depending on the geological set-up and topographic considerations.
Exploratory drilling for water conductor tunnels (HRT/TRT) is carried out
to establish rock cover available above the proposed crown level of the
tunnel especially in low cover zones such as in the beds of stream and
to know the substrata along the proposed alignment of the tunnel. Drill
holes are proposed at the intake and portal sites at outlet and along
proposed alignment of the tunnel. These holes are drilled to the proposed
invert level of the tunnel. It would be desirable to probe the expected
tunneling media to the extent possible. But, in view of the high rock cover
above the tunnel alignment, normally drilling of holes down to tunnel
grade is a difficult task. Hence, majority of the tunnel forecast is based
on detailed geological map & projections. However, certain major weak
zones such as faults or thrusts etc should be probed by advance core
drilling during the tunneling activity to identify the exact condition and to
minimize geological uncertainties.
Tunnel Portals are mapped using 1: 500 scale with 2m contour interval
instead of 1: 1 000. For Adits / Access Roads, Borrow Areas / Quarry
Sites all construction as well as access adits are mapped on 1 :2000
scale with 4m contour interval. Vulnerable areas on access roads are
also mapped on the above scale. As such, all geological maps are
updated in this stage. If there have been certain changes in the layout,
additional areas are covered.
For powerhouses, sub-surface exploration is carried out by holes drilled
at least 5m below the proposed level in order to assess the nature of the
16
rock for the foundation of the power house if rock cover is less. Similarly,
drill holes for ascertaining the geology of surge shaft and pressure shaft
etc. are also carried out.
Permeability tests should be conducted in all the drill holes selective
pits & trenches. Geological logging of Drill Holes, Drifts, Trenches & Pits
is carried out using 1:100 scale.
Groutability tests to assess the grout intake and reduction in permeability
values are generally done in this stage of investigation.
Generally the rock mechanic or soil tests are carried out in the DPR
stage for detailed design. Moreover, some of the detailed & expensive
tests like mortar bar test for construction material survey and insitu rock
stress measurements for design input are done at this stage.
The seismotectonic studies are pursued in detailed manner during this
stage for getting site specific earthquake parameters.
1.3.4
Construction Stage
Large scale foundation grade mapping for dam, progressive 3D
geological logging of ongoing tunnels, probe holes on the tunnel face
etc are carried out during this stage. Foundation grade geotechnical
mapping of earth & rockfill dam is done on 1 :500 scale and 3-D
geological logging of diversion tunnel is carried out on 1: 100 scale. For
Concrete Dam, Power House Excavation, Tunnel Excavations,
foundation grade geotechnical mapping and geological logging is done
on 1 :100 scale.
In case of underground works especially for tunnels, major identified
grey ares are probed by advance drilling or drifting to minimize geological
uncertainities.
1.4
1.4.1
1.4.2
analysis. The process of making maps by GIS is much more flexible than
traditional manual or automated cartography approaches. Existing maps
are digitized and computer compatible information are translated into
GIS.
Remote sensing using sensors such as cameras carried on aeroplanes,
GPS receivers, or other devices collect data in the form of images and
provide specialized capabilities for manipulating, analyzing, and
visualizing these images.
19
CHAPTER - 2
BEST PRACTICES IN PLANNING & APPRAISAL OF
HYDRO ELECTRIC PROJECTS
Planning
A.
PLANNING OF HE PROJECTS
2.1
INTRODUCTION
A hydro electric plant harnesses power from water flowing under pressure
through the prime mover known as water turbine. A Hydro Electric Project
may be conceived exclusively for power generation or power may be
one of the benefits along with flood control, irrigation etc. when it is termed
as Multipurpose Project.
The planning is very important component for the optimum development
of a hydro electric project in a river basin. A river valley can offer many
sites potentially attractive to the planners of hydro electric development.
Investigations at these sites can help eliminate certain number of them
and the optimum dimensions of dam, reservoir and powerhouse can be
worked out that could give the most economical scheme. Process of
selecting the best option depends upon the judgement and experience
of decision makers.
Hydro Electric Project forms an integral part of overall development of
water resources of the river basin. The hydro schemes also form part of
20
TYPES OF H. E. SCHEMES :
There are many types of hydro electric schemes. Based on the functions,
these may be classified as under :-
2.2.1
Run-of-River Schemes
Run-of-River schemes are the schemes either having pondage sufficient
Storage Schemes
These are the schemes having large storage capacity reservoir to store
excess water in monsoon months and to generate power in non-monsoon
months .
2.2.3
2.2.4
2.3
2.3.1
Storage Reservoir
It is an essential component of storage based hydro electric schemes.
Water available from the catchment area is stored in reservoir during
monsoon period so that it can be utilised to run the turbines for generating
electric power according to the requirements during lean flow period.
2.3.2
Dam
Dams are the civil structures built across the rivers for intercepting storage
of water and also to create head. These are also an important feature of
storage based hydroelectric schemes. Run of River scheme normally
have Weirs for diversion of river water.
2.3.3
Power House
Power House is a building housing the turbines, generator, control and
protection equipments etc. including auxiliaries for operating the
machines.
2.3.5
Tail race
Tail race carries the water discharged from the turbines to a suitable
point where it can be safely disposed off into the river in case of a
conventional hydro schemes. In case of a pumped storage schemes, it
carries water to tail pool or lower reservoir to be pumped back into the
upper reservoir.
2.3.6
Switchyard
Power generated by the generating units is pooled in the switchyard and
transmitted to load points. As far as possible, the switchyard is located
near to the Power House.
2.4
Site Identification
Survey & Investigation
Project Planning and Project Optimisation Studies for determination
of optimum Project Parameters
iv) Assessment of power & energy benefits
v) Economic Evaluation
vi) Preparation of Detailed Project Report
2.5
N year) is arranged in descending order and the (N+1) x 0.9 th year would
represent the 90 per cent dependable year. The 90 per cent dependable
year is thus, termed as the year in which the annual generation has the
probability of being equal to or exceed 90 per cent of the time on annual
basis during the expected period of operation of the scheme.
For example, if inflow data is available for a period of 20 years (N=20),
then,
90% Dependable year = ( 20+1)*0.9= 18.9 = 19th yr
2.6
2.6.1
2.6.2
work out firm power and 90% dependable energy generation benefits
corresponding to each of these scenario. The variation in the efficiency
of generating unit at heads lower and higher than rated head and
variations in tailrace level is also considered in computing energy
benefits, if available.
For selection of optimum FRL, the benefits (B) and the cost (C) for each
alternative are computed and Incremental Cost and Benefit Studies are
carried out to select optimum FRL from the consideration of maximization
of benefits.
2.6.4
Data Requirements
For carrying out Power Potential Studies, the requisite data is entered
into the Simulation model under the following categories.
a)
Configuration
Prior to carrying out simulations, the physical characteristics of the
development, its hydraulic links and down stream points of
discharges are to be defined.
b)
Hydrological Data
Hydrological Data consists of sequences of uncontrolled natural
inflows into the reservoirs.
c)
Evaporation Data
The month wise evaporation rate in the reservoir (in mm) is required
for simulation.
d)
Physical Characteristics
The physical dimensions of the reservoir constitutes the basis for
the determination of head on the Power Plant. Storage availability
has a direct impact on the possible degree of regularization. Area
capacity curve, minimum and maximum operating levels for reservoir
i.e. Full Reservoir Level (FRL) and Minimum Draw Down Level
(MDDL) are required for simulation.
Similarly for power house, the tailrace rating curve, turbine and
26
2.7
2.8
UNIT SIZE
The units size is determined depending upon the transportation
constraints, flexibility of operation and system considerations and
geological constraints like permissible cavern size in case of
underground power houses.
2.9
same is released during peak hours for generation by running the units
in generating mode. The capacity of upper/lower reservoirs, availability
of surplus off-peak energy, intended operating pattern of the pumped
storage scheme determines its installed capacity. The procedure for
optimization of the installed capacity and deciding the number of units is
same as applied for run-of-river schemes/ storage based schemes.
B.
2.10
2.10.1 Hydro electric projects are capital intensive involving high technology
and relatively long gestation period. Due to their complex nature, a large
amount of preparatory work is done by the project proponents before
detailed project report (DPR) is submitted to CEA for clearance.
Preparatory work covers detailed field investigations, planning,
assessment of benefits, design & engineering studies, detailed cost
estimates based on analysis, cost of inputs & equipment, identification
and tie up of inputs, project need, justification, economic and environment
studies, safety aspects etc.
2.10.2 The DPRs of Hydro Electric Projects are prepared as per the guidelines
issued by Government of India, Ministry of Irrigation (now MOWR) in
1980 and Guidelines for formulation of Project Reports for Power
Projects issued by CEA in October, 2002. The summary of guidelines
for formulation of power projects is given at Annex-I. Broad aspects to
be considered and covered in DPR include investigations, data collection
& analysis, selection of scheme of development, assessment of benefits,
project need & justification, design & engineering, environment & safety
aspects, tie-up of inputs, analysis of costs, cost estimates and financial
analysis etc.
2.10.3 Information on environmental aspects of the project are included in DPRs
as per the relevant performae/ guidelines of MOEF. As regards the forest
clearance, while the basic data (on the forest area) are included in the
report, action is taken separately to process the clearance through the
State Forest Department under Forest (Conservation) Act, 1980. The
28
2.11.1 Section 8 of Electricity Act, 2003 provides that any generating company
intending to set up a hydro generating station shall prepare and submit
to Authority for its concurrence a scheme estimated to involve a capital
expenditure exceeding such sum as may be fixed by Central Government
from time to time by notification.
2.11.2 At present the Central Government have fixed the following cost limits
for submission of DPRs for hydroelectric projects for concurrence of the
Authority:
i)
Rs 1000 Crores
ii)
Rs 2500 Crores
Rs 250 Crores
2.11.4 Section 10 (3) (a) of Electricity Act, 2003 provides that Every Generating
Company shall submit technical details regarding the generating station
to the Appropriate Commission and the Authority.
2.12
Appraisal of Schemes
In order to cut short the time in CEA clearance the revised procedure for
examination of project reports & its time frame for Hydro Projects have
been finalised and procedure have been made interactive. CEA has drawn
up a time bound procedure for processing of DPR so as to complete the
examination of DPR in a period of 3 months or less as per the time
schedules. This will be possible only when the project report is complete
with all the details and all the requisite clearances are available at the
time of submission/ registration of DPR in CEA. The project developers
are required to strictly adhere to the time schedules for furnishing
clarifications and attending to Standing Projects Appraisal Committee
and TEC meetings in CEA.
Appraisal of Schemes shall be in following parts i)
ii)
2.12.1 Three Stage Clearance for Central Sector Hydro Electric Schemes
Three-stage development procedure for Central Sector Hydro Electric
Schemes shall be as follows:
(a) Cost Estimates for Stage-I Activities
The report shall contain the justification for taking up the proposed
scheme for survey & investigation.
The activities under Stage-I shall be completed within one year from
the date of sanction.
The report shall also specify downstream benefits, if any. The report
shall contain the chapters on Introduction, Salient features, Scheme
Cost, Hydrology, Power Optimization Studies, Geology and
Construction Material, Design of Civil Engineering structures, Hydro
Mechanical Equipment, Power Plant- Electrical and Mechanical
Equipment, Environmental aspects, Infrastructure facilities,
Construction Methodology, Equipment Planning and Construction
Schedule, Economic Evaluation.
The report shall also contain the Vicinity Map, Scheme Layout plan,
Geological Plan of Scheme, Index Plan of Borrow Area, Diversion
Structure Plan, Diversion Structure - Longitudinal Section, Water
Conductor system - Longitudinal Section, Power House General
Arrangement & Cross Section, Construction Schedule.
32
Hydro-meteorological observations
Submission of DPR to the Authority (CEA) and obtaining its TechnoEconomic Clearance.
of design flood, silt studies for estimation of life of the project etc.
ii)
iii)
iv) Inter-State/ International Aspects: CWC also examines interState/ inter-national aspects related with a hydroelectric project in
consultation with Ministry of Water Resources, if considered
necessary and provides necessary suggestions to CEA.
v)
36
ii)
iii)
37
2.12.2.4
2.12.2.5
38
2.12.2.6
2.12.2.7
2.15
Acquisition of land
Finalization of Power Purchase Agreement
Financial Closure
ii) The above transfer of TEC shall be subject to furnishing the following
by the new agency within ONE YEAR of the transfer of TEC.
a)
b)
c)
2.15.2
b)
c)
d)
e)
2.15.3.
Authority shall have the right to revoke the transfer of TEC, if any of the
conditions stipulated in para 1 & 2 above are not fulfilled.
2.16
44
Annexure-I
SUMMARY OF GUIDELINES FOR FORMULATION OF PROJECT
REPORTS OF HYDRO ELECTRIC POWER PROJECTS
1.
INTRODUCTION
Hydro Power Schemes are broadly classified as run-of-river schemes
and storage schemes. The Detailed Project Report (DPR) for these
works should be formulated by the State Electricity Boards (SEBs),
Public Sector Undertakings, Private Sector/ Joint Sector Utilities/
Companies who intend taking up the projects for implementation and
forward to CEA for techno-economic concurrence. DPR for
hydroelectric schemes would be submitted to CEA, while DPRs for
multi-purpose project would be submitted to Central Water Commission.
Submission of the Schemes shall be as follows (i) Three stage
clearance for Central Sector Hydro Electric Schemes (Cost estimates
for Stage I activities, Feasibility Report (FR) for assessing commercial
viability, Cost estimates for Stage II activities) (ii) Appraisal of
Hydroelectric Schemes for concurrence (Detailed Project Report).
2.
3.
FINANCIAL LIMITS
Government of India has fixed Rs 1000 crores in relation to hydroelectric
generating stations prepared by a Generating company selected
through a process of competitive bidding by competent Government or
Governments, Rs 2500 crores for generating stations where tariff for
sale of electricity is determined by CERC/ SERC, Rs 20,000 crores for
a generating company not owned by Government for supply to more
than one state and approved in accordance with a scheme proposed
by a committee authorized by Central Government and Rs. 250 crores
for other hydro-electric schemes, as sum of capital expenditure
exceeding which the scheme shall be submitted to Central Electricity
Authority for its concurrence. However, all hydroelectric schemes
utilizing waters of inter-state rivers shall be submitted to CEA for its
concurrence.
5.
46
47
Sl. Activity
No.
1.
Time
(Days)
2.
Distribution of DPR
3.
4.
21
5.
6.
10
7.
8.
9.
10
Total
90
The Check List-A is for checking of legal and other major clearances
at the time of receipt/registration of DPR. If the requirements as per
Check List-A are not met, the proposal would not be accepted for
processing in CEA. If the requirements as per Check List-A are met,
the proposal would be examined for meeting the requirement as per
Check List-B. The Check List-B is for checking of the completeness of
the DPR. If the requirements as per Check List-B are not there, the
proposal would be returned.
If the proposal is found to be meeting the requirements as per Check
List-A and Check List-B, it would be further processed and clarifications/
additional information, if necessary, may be sought. If the clarifications/
additional information needed by CEA are not received within the time
stipulated by CEA, the proposal will be deemed as returned.
For such proposals deemed as returned, project authorities would be
required to submit the proposals afresh and the case would be
processed afresh.
7.
CONTENTS OF DPR
Detailed Project Report for hydro electric schemes submitted in the
CEA for techno-economic clearance should cover the following
information:
Cost Estimate for the proposals, Interest during construction & Tariff,
etc.
7.1
SALIENT FEATURES
Detailed salient features of the project i.e. Location, Hydrology and
climate, Dam, Reservoir, Spillway, Submergence, Diversion/Head
Race Tunnel, Sediment chamber, Surge shaft, Penstock, Power house,
Tailrace, Switchyard, Power benefits etc. should be mentioned.
7.2
7.3
7.6
Completed cost , Present Day Cost (for SEBs) and both for
Generating Companies in Public Sector as per CEA formats.
j)
Tariff Notification
Equity Participation
Change of name of implementing agency
General / Specific conditions
b)
c)
d)
e)
f)
g)
Completed cost, Present Day Cost (for SEBs) and both for
Generating Companies in Public Sector as per CEA formats.
h)
i)
j)
k)
l)
Planning
54
ii)
iii)
iv)
v)
Hydrology
vi)
x)
xi)
xii) Estimates
xiii) B.C. Ratio & Revenue.
xiv) Ecological aspects & Soil Conservation (if needed).
B
1002
1002
1003
1004
b)
c)
d)
e)
f)
15.
56
16
As per the Tariff Notification of Govt. of India dated 30th March, 1992
(as amended from time to time), the actual capital expenditure
incurred on completion of the project shall be the criterion for fixation
of tariff. Where the actual expenditure exceeds the approved project
cost, the excess as approved by the Authority shall be deemed to
be the actual capital expenditure for the purpose of determining
the tariff. Provided that such excess expenditure is not attributable
to the generating company or supplier of contractors.
17
58
CHAPTER - 5
BEST PRACTICES IN CONSTRUCTION MONITORING OF
HYDRO ELECTRIC PROJECTS
5.1
Objectives of Monitoring:
The following are the main objectives of monitoring mechanism:
5.2.1
Completion Period:
This covers determination of period of construction project as a whole
and firm up the completion dates of each of the project components. The
determination of completion period depends on the following factors :i) Location of the project.
ii) Number of major components.
iii) The most critical item of each of the components.
Evaluation of the working cycle time for all other activities considered
as parallel activities.
The cycle time for men and machinery to be properly evaluated taking
into consideration Job & Management Factors.
5.3
Computerization:
The various practices enlisted above can be computerized to yield better
practices.
i)
ii) The daily, weekly and monthly reports are computed and analyzed
for lacunae and better results both at field level and Corporate offices.
5.4
Monitoring Mechanism:
The best practice at field at the end of the day is assessing the work
done during the last 24 hours, with various constraints and determining
the work for the next 24 hours envisaging constraints and thus providing
for optimum utilization of all men and machinery available.
Classify the project under one of the Job factors and one of the
Management factors. This would yield a single value of Job &
Management factor, which is used to compute the expected progress.
To keep a proper track of the progress, schedules are prepared for the
complete project (Level-I schedule which is the Master Control Network)
as well as for their individual components of works (Level-II schedules).
Further detailing of activities is done if required which gives a Level-III
schedule, generally in form of bar charts. The Level-I network therefore
enables one to gauge the overall position of works vis--vis the plans, at
any point of time.
5.5
The Schedules:
The Project Management consists of four major parts- Planning,
Organization, Execution and Control. Monitoring system carries out the
control part, i.e. controlling the activities of project so that they proceed
according to the plan and accomplish the required target in time.
Monitoring basically involves acting on feedback to avert any hindrance
203
affecting or likely to affect the activities. The yardstick for how the activities
should proceed is the schedule, while the feedback is the progress report,
i.e. the targeted and actual achievements up to any point of time. In other
words, it is a comparison of what significant milestone has been actually
achieved at a given point of time and when it was due. The primary tools
of monitoring are therefore, the schedules and the milestones derived
from it.
Hydroelectric projects, or for that matter any big project has large number
of interlinked activities, some of which are more important than the rest.
It is therefore, necessary to have a plan that gives a birds eye view of
how the whole project work will proceed and which activities are more
important than others, requiring special attention. Such a schedule is
termed Master Control Network or Level-I schedule, which is basically
a schedule based on Critical Path Method (CPM), and shows only the
major activities with their interdependence, start/end dates, allowable
delays (floats) and criticalities. The critical path in a schedule is the longest
chain of successive related activities without any float i.e. allowable delay
and therefore decides the total completion period of the project. Obviously,
there has to be at least one such path but there may be more than one
also. Critical path, by definition, has no float and therefore any delay in
critical activities results in the delay in completion of the project as a
whole. The activities lying on the critical path therefore have to be paid
special attention. Level-II schedule is more detailed, component-wise,
while Level-III is of still lower level, generally in form of bar chart and
indicates quantitative monthly or weekly targets. Level-I, II and III
schedules essentially have to be in conformity.
The Project work is required to proceed as per these schedules and
feedback on the progress given from site to the monitoring office is
compared with these schedules to gauge the deviations and pace of
progress.
The Master Control Network (Level-I Schedule) also shows the desired
completion dates of some important activities. A list of such milestones
is prepared and actual achievement compared with it. For monitoring at
204
highest level, say ministers level, even Level-I schedule is a bit too
detailed and cumbersome. In this situation, milestones i.e. completion
of an important activity, like excavation or concreting of tunnel, dam etc.,
is the best tool. A list of important milestones is derived from the Level-I
schedule. Achievement of each milestone by its due date simply means
that the work is progressing as planned. This saves the high level
management from trivialities. The Ministry of Programme Implementation
& Statistics monitors all major projects in the country, hydroelectric
projects included, through list of milestones.
5.5.1
5.6
Contract Management:
Since most of the works are done through large contracts, the
management of contracts is very vital for the progress. After award the
contracts are operated by the site officials. Major components of the
project involve large civil and electrical works and supplies and have to
be executed in parts and mostly through contracts. Works are broken
down into various contract packages according to the quantum of work,
205
Financial Control:
Adequate financial control is exercised on the project works at the
appropriate levels by suitable financing and accounting system. Normally
Finance & Accounts (F&A) Wing exercises the financial control, i.e. the
arrangement and control of funds in accordance with the approved cost
estimate of the project. The project furnishes in advance the detailed
budget proposals for each approaching year, which is approved and
accordingly the funds are provided to the projects through monthly bank
withdrawal limits at the local bank at site. In case the expenditure
overshoots the prescribed limits, the cost has to be revised and necessary
approval for the Revised Cost Estimate (RCE) is sought from the
Government.
The project is required to be completed within the approved cost that
was envisaged at the detailed estimate stage of the project. During the
execution stage, attempts are made to maintain the expenditure incurred
on each work within the provision kept for that work. All financial controls
are enforced both at the project level and at the Corporate Office level to
ensure this vital aspect by constant monitoring. However, sometimes due
to unforeseen or unavoidable reasons, the cost overshoots the prescribed
limit inspite of best efforts to contain it. In such circumstances the estimate
has to be revised and a fresh approval needs to be obtained by following
206
due procedures for the same which includes severe scrutiny by the Govt.
at various levels.
5.8
211
CHAPTER - 6
BEST PRACTICES IN OPERATION & MAINTENANCE OF
HYDRO POWER STATIONS
6.1
MAINTENANCE PRACTICE
Some of the practices to be adopted at hydro power stations for
maintenance of certain main plant are broadly given below.
6.2.1
6.2.2
Cavitation & erosion at top portion due to rushing of air during fill up.
The inspection schedule for the durability of anticorrosive paints used.
Replacement schedule for various vulnerable parts such as bends,
open conduits etc.
Due to humidity open conduit deteriorates from outside. As such
inspection & cleaning to be carried out from time to time at regular
intervals.
Anticorrosive-painting schedules followed.
Timely Operation & Maintenance of the cranes & hoists.
Healthiness of control & protection for isolating gates/valves & for
cranes/hoists.
Maintenance of trash-rack/intake gate filter.
Maintenance of communication systems, availability of power supply,
equipment for emergency operations, approach roads etc.
New Turbine Runner of Unit No. 3 of Burla Power House of Hirakud Power
System being replaced for RIM & U Works.
results. Low heat input welding can also be tried at some of the locations
to some extent.
An effective system for monitoring of silt content (quantity and size in
PPM) may be installed & commissioned by each power station and silt
content may be monitored continuously on the basis of which action to
mitigate the damaging effect to under water parts may be initiated
reducing the down time of units / station.
Best efficiency microprocessor based digital PID speed governors
provide fast response. Periodical maintenance of speed governors
alongwith all associated mechanical, electrical, electronics component
should be carried out. The control circuit should be neatly dressed with
identification marks. The electronic components and cards should be
carefully maintained at appropriate temperature level to achieve desired
performance. Periodical calibration and testing of transducers, meters
216
Governor
6.2.3
6.2.4
Inspection of the CTs, PTs and bus bars for over heating, temperature
rise etc.
Inspection of circuits for protection & control circuits & mock trials of
the fire fighting system alongwith evacuation system. Checking weight
loss of the CO2 cylinders and replenish as per recommendations of
OEM.
6.2.5
Emergency D. G. Set
6.2.6
Other P. H. Equipment
220
CHAPTER - 6
BEST PRACTICES IN OPERATION & MAINTENANCE OF
HYDRO POWER STATIONS
6.1
MAINTENANCE PRACTICE
Some of the practices to be adopted at hydro power stations for
maintenance of certain main plant are broadly given below.
6.2.1
6.2.2
Cavitation & erosion at top portion due to rushing of air during fill up.
The inspection schedule for the durability of anticorrosive paints used.
Replacement schedule for various vulnerable parts such as bends,
open conduits etc.
Due to humidity open conduit deteriorates from outside. As such
inspection & cleaning to be carried out from time to time at regular
intervals.
Anticorrosive-painting schedules followed.
Timely Operation & Maintenance of the cranes & hoists.
Healthiness of control & protection for isolating gates/valves & for
cranes/hoists.
Maintenance of trash-rack/intake gate filter.
Maintenance of communication systems, availability of power supply,
equipment for emergency operations, approach roads etc.
New Turbine Runner of Unit No. 3 of Burla Power House of Hirakud Power
System being replaced for RIM & U Works.
results. Low heat input welding can also be tried at some of the locations
to some extent.
An effective system for monitoring of silt content (quantity and size in
PPM) may be installed & commissioned by each power station and silt
content may be monitored continuously on the basis of which action to
mitigate the damaging effect to under water parts may be initiated
reducing the down time of units / station.
Best efficiency microprocessor based digital PID speed governors
provide fast response. Periodical maintenance of speed governors
alongwith all associated mechanical, electrical, electronics component
should be carried out. The control circuit should be neatly dressed with
identification marks. The electronic components and cards should be
carefully maintained at appropriate temperature level to achieve desired
performance. Periodical calibration and testing of transducers, meters
216
Governor
6.2.3
6.2.4
Inspection of the CTs, PTs and bus bars for over heating, temperature
rise etc.
Inspection of circuits for protection & control circuits & mock trials of
the fire fighting system alongwith evacuation system. Checking weight
loss of the CO2 cylinders and replenish as per recommendations of
OEM.
6.2.5
Emergency D. G. Set
6.2.6
Other P. H. Equipment
220
CHAPTER - 7
RENOVATION AND MODERNISATION AND UPRATING OF
HYDRO POWER STATIONS
7.1
7.2
7.3
7.4
Visual examination
On line diagnostics
Review of operational history
Review of plant documents
Discussions with plant authorities and O&M staff on the health of the
equipments
Identification of critical components
7.6
225
CHAPTER - 8
MONITORING OF R&M SCHEMES
INTRODUCTION :
8.1.1
8.1.2
8.1.3
This committee may have the financial powers to place orders and take
all policy decisions. This will cut short the delays in taking decisions
and thereby help in reducing time and cost over runs. The committee
shall also periodically review the progress of R&M works for timely
completion.
8.2
PROCUREMENT OF SPARES
Due to fast changing technologies especially in the field of electronics/
control & Instrumentation, the system gets obsolete frequently. As a result
the power stations have to go for replacement of the system resulting in
extra financial burden. To overcome the problem, power stations should
procure sufficient initial spares. Also it may be clearly mentioned in the
contract that in the event of manufactures going out of production of certain
items, shall inform the users well in advance so that sufficient spares
could be procured by them and they should also submit details of
drawings for its manufacture.
8.4
TURNKEY ORDERS
Wherever possible orders on turnkey basis may be placed so as to have
single point responsibility on the bidder.
8.5
8.6
8.7
228
CONCLUSION
The book has been prepared to provide guidelines to the Planners,
Consultants, Power Utilities & other organizations in the country who are
associated in one or more aspects of Survey & investigation, Planning,
Designs, Construction, Operation & Maintenance, Renovation,
Modernisation and Uprating and Monitoring for projects under
construction and under operation. International practices, Indian
Practices and Expected Benchmarking for various parameters of Hydro
Power Generation have also been included in the document. It is hoped
that the guidelines / suggestions contained in the report will help in
improving overall performance, achieve higher level of equipment
availability, help in improving the morale & dedication of the staff of all
such Indian organizations serving in the field of hydro generation in the
country.
The material given in the document has been contributed by the
members of the Committee & suggestions for improvement received from
various officials of the organizations in the hydro power generation &
reflect the practices followed by their respective organizations.
Since it is an attempt to compile & disseminate such information to
all users in the country, contents of the document, suggestions about
the best practices and bench marking in various areas of hydro
power generation by the various utilities to enrich the document
are earnestly sought. Interaction with the Chairman & MemberSecretary of the Committee and feedback regarding the contents
would be also welcome.
229