Implementation Options

Projects,Vision Operations->Setup->System->Implementation Options

Creating a Project

Normally when we are a create new project we will get the error
Issues while creating a new Project
Cannot copy a budget to a period which is out of the range of system defined
periods (e.g. PA period or GL period)"
Solution
While copying the template we need to take the Project Start Date as it is in the
Template Transaction Start Date then only it work
If you got any work plan related issue
Go to
Structures ->Click Details

Check the Work plan Structure

Partial Shared Structures: This scenario allows users to share the top level of the
WBS with the financial structure while allowing Project managers to build out

additional granularity for their workplan activities below the levels of the shared
activities. This scenario typically works very well when the top level of the WBS can
be easily shared by scheduled work and financial needs.
Non-Shared, Mapped Structures: This model applies when you have a scenario
wherein the workplan is structured very differently from how the financials of the
project are managed, but it is possible to map workplan activities (at any level of
the Workplan WBS) to activities in the financial WBS. This model enables the project
manager (PM) and the financial analyst to have independent control over their areas
of responsibility but still maintains the association between them. This allows for
improved interactivity between the two in terms of generating budgets and
forecasts based on workplans and also pulling workplan progress percent
complete into the financial structure in order to process revenue and billing based
on physical percent complete.
Shared Structures: This scenario allows users to share the complete WBS with the
financial structure.