Академический Документы
Профессиональный Документы
Культура Документы
pressurisation
1.
Introduction
Air ingress in condenser, more than the design value, is not desirable. It decreases
the condenser vacuum. Efficiency of the machine reduces with increase of air
ingress. This article spells out the procedure of vacuum leak detection in KWU
steam turbines by steam pressurisation.
2.
ii)
iii)
iv)
etc.
v)
Excessive thermal loading of condenser due to leaking drain valves and
HP/LP by pass.
3.
iii)
iv)
v)
Steam pressurisation.
In KWU turbines, vacuum leak detection is done by filling water up to one metre
above the top row of condenser cooling water tubes (Fig. 1). This procedure is
called vacuum tightness test. During this test, CW side of the condenser is kept
completely empty.
In this procedure, however, leakage points one meter above the tube nest,
remain, undetected. Previously, "FREON GAS" detection instrument was employed
for the same. This instrument is currently not manufactured due to environmental
degradation by the Freon gas.
The following sections bring out the procedure of detecting leakage points in the
above-mentioned undetected area by steam pressurisation. The purpose of this
test is to check leakages in those areas, which will remain under vacuum even at a
load of 80 to 100% on the machine. This procedure is to be adopted during
commissioning as well.
Note: Helium gas leak detection equipment is under development.
4.
iii)
4.1
Preparation of Thermal Scheme, and readiness of Turbine and its Auxiliary
Equipment for Performing Steam Pressurisation
a)
b)
Close drain valves of alternate drains of HRH & CRH lines connection to unit
flash tank, if any.
c)
On Condenser
d)
On Ejectors/Vacuum Pump
e)
f)
On Turbine
g)
Keep leak-off valve in locked open condition, and switch off power supply to
its motor. Keep seal steam valve in closed position and ready for operation. Drain
line connection of seal steam header is to be diverted from condenser flash tank to
atmosphere.
h)
4.2
Manually open the steam supply valves supplying steam to the LP exhaust,
and raise the pressure slowly. It takes around 4 - 6 hours for the pressure to start
building up.
Vacuum line to speed control rack, LP by pass rack and vacuum pressure
switches rack
Repeat the steam pressurisation process after attending to the leakage points, till
no leaks are observed.
Note : Status of equipment should be as follows :
i)
ii)
iii)
iv)
v)
- Not in operation
- Not in operation
5.
Feedback/Additional Information
Turbine rotor may come to rest even if turning gear valve is open, as
pressure starts building up in the condenser steam space. This is expected.
It takes roughly 6-8 hrs for condenser to start getting pressurised to a value
of 0.2 kg/cm2 (g).
Proper illumination and approach are to be ensured for areas under test.
Insulation is to be removed.