Вы находитесь на странице: 1из 4

Delay and

completion

 What is practical completion?


 Consequences of practical
completion
 Options as to delay
 The defects liability period and
obligations
employer in the building contract
Delayed completion
Introduction as being essential for practical
The date set in the building contract as completion to take place have been
This guide will consider the date for completion of the new satisfied; and
development is less than one month
what is practical away. The employer visits the site with
> the health and safety file and all “as
built” information and operating
completion and the his contract administrator. While
and maintenance information have
various parts of the development are
consequences of practical almost complete, other parts of the
been provided to the employer.
completion either development will clearly not be ready
The impact of practical completion
by the completion date, the date the
happening or not before employer has arranged to take The date of practical completion acts
examining the options if possession and move into the new as a trigger for a number of different
building. and important events. It signifies the
practical completion is commencement of the defects liability
delayed as well as What are the options? period (or, as it is now increasingly
being called, the “rectification period”).
discussing obligations The employer should immediately ask This is the period during which the
to sit down with his contract
arising during, and at the administrator and discuss the options
contractor has an obligation to remedy
any (originally latent) defects which
end of, the defects liability open to him. However to begin with,
may emerge. Generally speaking, it is
the employer will want to know:
period? a 12 month period, which allows the
> Why is the development not going employer to operate the building
to be ready on time? through all the seasons and gives time
for defects to emerge.
> Whose fault is the delay?
The date of practical completion also
> Is the contractor entitled to an fixes the date for the release of the
extension of time? first half of the retention. It also starts
> What remedies are available? the timetable for agreeing the final
account.
Practical completion Equally important, on practical
While the phrase “practical completion, the insurance obligations
completion” and other similar phrases, under the contract cease. The
such as “substantial completion”, are employer must have insurance for the
often used in construction contracts, building as from that date.
many do not in fact define what it is. The date of practical completion also
In order for the development to be normally signifies the start of the
practically complete, there must be no limitation period for any claims against
patent defects. However, the contract the contractor under the building
administrator does have discretion to contract.
certify practical completion if there are
very minor items of work left to Liquidated damages
complete and the development as a If the works are not practically
whole is capable of being fully used by complete by the completion date, as
the employer. extended by any extension of time to
Some of the newer standard forms of which the contractor is properly
contract (e.g. JCT Major Project Form) entitled, the employer is entitled,
have defined practical completion as subject to the requisite contractual
taking place when the development is notices being served, to deduct
complete for all practical purposes liquidated damages from any sums
and, in particular: otherwise due to the contractor. Such
liquidated damages are calculated at
> the relevant statutory requirements the rate set out in the building contract
have been complied with by the from the completion date, as extended,
contractor and any necessary until such time as the contractor
consents or approvals obtained; achieves practical completion. The
> none of the minor outstanding relevant contractual notices which act
works affect the use of the building; as a pre-condition to liquidated
damages can include; a certificate on
> any stipulations identified by the
non-completion being issued by the snagging list) is in fact attached to the second and final part of the retention.
contract administrator; the employer certificate of practical completion,
The final certificate cannot be issued
notifying the contractor that it may those minor defects should be
prior to the issuing of the certificate of
exercise its right to levy liquidated remedied at the start of the DLP within
making good.
damages; and the employer issuing a a reasonable time from practical
valid withholding notice. completion.
Defects appearing after the
Liquidated damages provide an During the DLP and if the employer so Certificate of Making Good has been
exclusive remedy in respect of the instructs, the contractor has an issued
contractor’s delay. obligation to remedy any (originally
latent) defects which may emerge, at Strictly speaking, the contract
its own cost. As noted already, it is administrator cannot issue the
Partial possession
generally a 12 month period. contractor with an instruction to make
Even if the building contract does not good any defects which appear after
contain a provision for sectional issue of the certificate of making good.
The end of the Defects Liability Period
completion of that part of the works However, if the final certificate has not
which is very near to completion, the Very shortly before the expiry of the yet been issued, an adjustment as to
employer can, if he wishes and if the DLP, the contract administrator should the amount payable to the contractor
contractor consents, take partial inspect the works and draw up a can be made.
possession of that part of the building schedule setting out, in some detail,
The employer should check the terms
which will, in the very near future, be any defects which are apparent.
of the building contract to ascertain
partially complete.
the contractual effect of the final
What options are there as to the
However, taking possession of part, certificate and in particular whether it
defects identified?
before the whole development is is conclusive and if so, as to what?
complete, does have its disadvantages. The contract administrator can As a last resort (and assuming that the
These include that, notwithstanding instruct the contractor to make good
final certificate does not act as a bar),
there may still be some patent defects, the defects within a reasonable time,
the employer may have no alternative
practical completion of the part of at no cost to the employer.
but to issue proceedings in relation to
which early possession is taken will be
Alternatively, the contractor can be the losses which it will suffer, as a
deemed to have occurred and all the
instructed not to remedy the defects. result of the defects. The issuing of
consequences of practical completion
The employer would then make an proceedings is outside the scope of
will follow in respect of that part. This
appropriate deduction in respect of the this guide.
will lead, for example, to there being
two defects liability periods (one for costs that it will incur in having the
the part of the development for which defects remedied by others. However Conclusion
early possession is taken and the other the employer may be restricted to
So while practical completion and the
for the remainder of the development). recovering no more than the costs that
DLP are the final hurdles, it is
Equally, the employer will have to the contractor would have itself
incurred, had it been asked to remedy important that care is taken to ensure
insure that part of the development in that the project does not stumble at
respect of which possession is taken. the defects. This is in line with the
this late stage when the finishing post
In addition, the amount of liquidated duty to mitigate.
is in sight.
damages to which the employer is The contract administrator does not
entitled in respect of the non- have to wait until the end of the DLP. It
completed part and in respect of which can issue instructions during the DLP
possession is not taken, will be to remedy any defects which emerge
reduced accordingly. during the DLP. For further information, please contact
James Levy
However, with the agreement of the
contractor, it may be possible to Once the defects have been made Tel: 020 7074 8074
overcome some of the problems good
Email: james.levy@lewissilkin.com
arising out of the employer taking Once the defects have been made good
partial possession. If agreement is and assuming that the contractor was
possible, a supplemental agreement is actually instructed to make good the
recommended, varying the terms of defects, the contract administrator
the original building contract. must issue a notice to that effect, for
example, the certificate of making
Defects Liability Period (“DLP”) good.
At practical completion, there are not
meant to be any patent defects. The Consequences of issuing the
DLP is about remedying defects which Certificate of Making Good.
“appear” during that period. However, The issuing of the certificate of making
if a schedule of minor defects (a good will result in the release of the
© July 2007

Вам также может понравиться