Академический Документы
Профессиональный Документы
Культура Документы
C O N T E N T S PA G E
Introduction.......................................................................- 7 -
2.0
Project development..........................................................- 9 -
2.1
Introduction..........................................................................- 9 -
2.2
Research...............................................................................- 9 -
2.3
Conceptual Design..............................................................- 18 -
2.4
2.5
2.6
Detailed Design...................................................................- 31 -
2.7
2.8
Final design.........................................................................- 36 -
2.9
3.0
Method Statements.........................................................- 38 -
3.1
3.2
3.3
3.4
4.0
4.1
4.2
4.3
Steel Reinforcement...........................................................- 47 -
4.4
Walkway components..........................................................- 48 -
5.0
Construction Processes...................................................- 49 -
6.0
Testing Procedures..........................................................- 51 -
6.1
6.2
Loading test........................................................................- 52 -
6.3
7.0
7.1
8.0
8.1
8.2
9.0
9.1
9.2
Inventory Analysis...............................................................- 64 -
10.0
Risk Assessment..............................................................- 67 -
10.1 Piling Risk Assessment.......................................................- 68 10.2 Steel fixing Risk Assessment..............................................- 69 10.3 Walkway Risk Assessment................................................ - 70 11.0
Cdm Regulations...........................................................- 71 -
11.1 Introduction........................................................................- 71 11.2 Risks assessed by CDM Regulations for Piling...................- 72 11.3 CDM Regulations for Working in Costal conditions/over water.73 11.4 Application of CDM regulations during Construction........- 75 12.0
12.1 Results of Risk Assessment.................................................- 80 12.2 Noise Mitigation for piling works.......................................- 80 12.3 Working over water Mitigation for piling works.................- 83 13.0
Environmental Assessment.............................................- 93 -
14.1 Environmental assessment Leopold Matrix........................- 94 14.2 Result..................................................................................- 94 14.3 Mitigation against Risk.......................................................- 95 15.0
16.0
17.0
Bill of Quantities...............................................................- 99 -
18.0
19.0
References......................................................................- 101 -
20.0
Appendix A : Drawings..............................................................
21.0
Appendix B : Calculations..........................................................
22.0
Appendix C : BillofQuantities&associatedworks.......................
L I S T O F TA B L E S
Table 1 : Matrix choice of Pile system to be used...........................- 19 Table 2 : Comparison of Brief with solutions...................................- 25 Table 3 : Comparison of prices with solutions................................- 26 Table 4 : Decision matrix.................................................................- 30 Table 5 : Frequency of functional checks (BSI, 2001)....................- 60 Table 6 : Embodied energy in materials..........................................- 64 Table 7 : Energy consumption during construction........................- 65 Table 8 : Energy consumption during Maintenance........................- 66 Table 9 : Piling Risk Assessment.....................................................- 68 Table 10 : Steel fixing Risk Assessment..........................................- 69 Table 11 Walkway Risk Assessment................................................- 70 Table 12 : Noise made due to piling with steel H Piles (BS1, 1992). - 81
Table 13 : Environmental assessment Leopold matrix....................- 94 Table 14 : Bill of Quantities...........................................................- 100 -
TA B L E O F F I G U R E S
Figure i : Map of Area during 1854 1901.....................................- 10 Figure ii : Map of Area during 1906 1939....................................- 10 Figure iii : Map of Area during 1924 1949...................................- 11 Figure iv : Map of Area during 1943 1995...................................- 11 Figure v : Aerial view of existing lifeboat station............................- 13 Figure vi : Detailed map of site location.........................................- 14 Figure vii Geology of Area...............................................................- 15 Figure viii : H-Pile System...............................................................- 20 Figure ix : Image illustrating a jack up Barge.................................- 50 Figure x : Bathing Waters................................................................- 10 Figure xi : Nature Reserves.............................................................- 10 Figure xiii : Sites of special scientific interest ...............................- 10 Figure xiii : Marine sensitive areas................................................- 10 -
SYNOPSIS
The objective of this report is the design and planning of the piling
foundations of a proposed R.N.L.I slipway lifeboat station at Selsey.
The lifeboat station is part of the redevelopment of old lifeboat
stations by the R.N.L.I.
and
material
specifications
including
performance
criteria,
1.0
INTRODUCTION
of
Quantities
and
material
specifications,
including
an
10
Volume 2 of the report covers the design of the slipway and the slab
arrangement to a proposed fully operating R.N.L.I slipway lifeboat
station at Selsey.
11
2.0
PROJECT DEVELOPMENT
2.1 Introduction
This chapter illustrates the development of the foundation design for
the lifeboat station from the conceptual design stage up to the final
design. It shows the development of this particular aspect of the
scheme. It follows the general research which is detailed in the
Preliminary Engineering Report, and demonstrates the individual
research done about the foundations, construction problems, loading,
design development and choice of construction method.
2.2 Research
Much of the research was made at the conceptual stage, and is
contained in the preliminary report. Below is research that is
applicable
to
the
design
of
the
foundation,
thus
producing
12
13
Figure iii : Map of Area during 1924 1949, Courtesy of (Digimap Historic, 2006).
Figure iv : Map of Area during 1943 1995, Courtesy of (Digimap Historic, 2006).
As the maps above show, for the last 150 years this area has been very
sparsely populated, with no form of industry development. The area
has been dedicated as a lifeboat station for the last 150 years.
Therefore contamination of the area should be very little. Potential
14
contamination could come from fuel storage for the lifeboats; this will
be investigated in any future environmental assessment.
2.2.2 General information
Profile level :
Existing Station
Water level :
Low tide:
Tidal Range:
+ 0.21 m
+ 5.04 m
Access :
Not easy access and parking for the crew and the
emergency services.
16
Electricity supply
Water supply
17
There has been a station located in this area since the 1800s
therefore site conditions should not be a problem for any future
development.
18
Figure 3 illustrates the location of high and low water levels. This
shows that the lifeboat station location is more than adequate
concerning water levels. The tidal range at mean spring tides is
around 4.7 m at Selsey. In the central part of the Channel, the
maximum speed of tidal currents on mean spring tides is between
0.75 and 1.0 m/s. and can increase to 1.25 m/s. (English Nature,
2006).
19
This figure also explains that the main topsoil is sand and shingle.
Figure 4 demonstrates that Selsey is located within the London Clay
formation, which is made up of clay. Therefore the structural soil
properties of Clay will be used for the foundation design.
2.2.4 Design considerations based on research
Existing Station has piled foundations therefore it would be safe to
assume from the research that using piled foundations for the
proposed lifeboat station would be the most suitable option.
Long sloping beach signifies that the location of the lifeboat station
can moved. With change of location, the foundation design will
change, due to change in tide levels. This could increase or decrease
the sizes of the members.
20
6m of sand
30m of clay
Properties of Sand.
21
will be little or no
movement from swelling or shrinkage.
-
being hard to
-
predict
(Tomlinson, 2001).
22
The RNLI design brief states that lifeboat stations should have a 50
year design life. As Selsey is only 20 years old, it has not come to the
end of its design life. But due to the size of the existing station, lack of
facilities doesnt meet modern day standards, so renovation of the
existing structure is inappropriate.
Below are the key problem areas associated with the Selsey site and
potential solutions.
23
The
first
decision
made
was
to
use piled
foundations,
piled
The next problem encountered was which piling system to use, either
driven or bored piling. Due to the ground conditions of sand and clay,
it was decided that driven piles would be most suitable. They can be
readily carried above ground level especially in marine structures
(Tomlinson, 2001) which fits the specific needs of this project with an
added bonus of no spoil being created from the driving, thus not
altering the water environment.
Difficulty of design
Cost of plant
Speed of construction
Safety
2/7
2/6
2/5
5/9
3/7
3/5
4/4
5/9
24
Noise impact
Total
6/4
105
2/8
113
25
Precast Piles.
Steel H piles.
The decision was to use a steel tubular pile with concrete encased
within and reinforced with a steel H pile as the structural element.
H-Pile
Concrete
strength in
26
High tensile alloy steel piles will be used as they are suitable for
high impact forces from ships or waves in low temperature
conditions (Tomlinson, 2001).
27
Boat = 20 KN
Superstructure = 160 KN
TOTAL = 250 KN
PILE : = 600 mm
28
29
be
ascertained.
Using
supply
barges
as
means
of
Firstly a walkway will be constructed from the land to the site where
materials can be delivered straight to site. All materials will be stored
on land under high security. A mini crane platform will be constructed
Hemis Number 244742
30
adjacent to the site therefore lifting heavy materials around the site
with ease. Concerning the piling a spud leg piling rig system is to be
used to install the piles. This makes access relatively easy as the
pilling rig floats to its destination.
31
ROOM
Option 1
Option 2
Boat room
Brief
Status
Crew room
27m <Area <
36m
Size
Option 3
34
32
Including a galley
Changing room
Area = 30m
Located at
ground level
Manager's
office
36 m
First
Floor
31
Area > 8m
Close to crew
room
Mechanics
Area = 15m
Storage
24
24
Area > 5m
Fuel storage
18
18
5m x 4m
Double access
door
Souvenir sales
outlet
10m < area <
30m
Access to
wheelchairs
General
24
24
Entrance
Toilets
1
1
20
35
1
0
31
First
Floor
12
15
12
24
32
21
6
10
22
1
21
13
m
m
1
1
32
22
Size
0
0
21
6
1
0
1
13
22
0
1
15
19
4
1
9
19
4
1 = it passes
Brief
0 = it doesnt
pass Brief
Spons Architects and Builders Price Book reveals the cost to build an
ambulance station is between 730 and 1,080 per square metre
(Langdon, D. 2006). The use of an ambulance station is only a guide as
the book did not have lifeboat stations as an option.
Cost of the
Option 1 (346
Option 2 (320
Option 3 (320
Option
From
Up to
m2 )
252, 580
373, 680
m2 )
233,600
345,600
m2)
233,600
345,600
33
At this preliminary stage, this doesnt take into account the slipway or
foundation and slab design, but just the structure of the actual
lifeboat station. But at this stage it gives some form of indication on
costing for each scheme even though they seem very low.
34
We decided to make a 2 floor station. The changing room and the crew
room are upstairs and a pathway will be created to link them together.
The ground floor is more basic with the souvenir shop, and the office
on a side and the mechanical storage rooms on the other.
Option 2
This solution has few differences: its a single storey station. The
office has a view on the sea which can be an advantage. The station is
compact; all rooms are close to the others. A disadvantage of this
solution is that it could require a higher surface of pilling; this means
a higher cost.
Option 3
35
During operation
36
General
Local Interest depends of the view walkers could get from and
in the station. It is useful for increasing donations.
37
Criterias - Magnitude(1-5)
Schemes
Solution
Solution
Solution
6 (x4) =
7 (x4) =
5 (x4) =
During Construction
Buildability
24
6 (x2) =
28
7 (x2) =
20
6 (x2) =
Time
12
5 (x4) =
14
7 (x4) =
12
7 (x4) =
Cost
20
28
28
6 (x5) =
9 (x5) =
5 (x5) =
During utilisation
practicability for people
30
8 (x4) =
45
6 (x4) =
25
5 (x4) =
Deliveries facilities
32
7 (x3) =
24
6 (x3) =
20
7 (x3) =
Comfort
21
18
21
8 (x3) =
6 (x3) =
7 (x3) =
General
Location
suitability/integration to site
24
6 (x2) =
18
8 (x2) =
21
4 (x2) =
Access
12
6 (x2) =
16
4 (x2) =
8
8 (x2) =
Local Interest
12
16
TOTAL
187
199
171
38
39
2.6
Detailed Design
The design of the piles is only possible when the load coming from the
main steel superstructure and floor construction are known. See
Volume 2, Volume 3 for more details.
40
41
With this now more simplified pile design, construction of the pile was
also made easier. Thus potentially needing less people and risks to
construct the pile foundation making it easier to adhere to any future
CDM regulations.
foundation,
calculation
began
on
the
piled
foundations.
Considerations made were the vertical loads, lateral loads, and uplift
resistance.
42
Using this spreadsheet, changes on the load had a small effect on the
design of the foundation. If a load increase and there is a need for a
bigger pile, the engineer has to just alter the length or choose the
next pile from the spreadsheet output. See appendix B.
43
Superstructure = 1000 kN
Lateral loads = 45 kN
All drawings were detailed to have these design criteria and can be
seen in appendix C.
44
45
Section Sizes
46
All of these elements have been drawn on the 302 & 303 drawing and
have been presented at the design seminar for assessment and
industrial advices.
Compare
47
48
3.0
M E T H O D S TAT E M E N T S
49
3.2.3 Methodology:
3.2.4 Preliminary Procedures:
An investigation of the ground should be carried out by competent
and experienced persons in accordance with BS 5930. Borings should
reach depths adequate to explore the nature of the soil both around
and beneath the proposed piles in accordance to BS 8004 and BS
6349 (Quality Risk).
50
Set out the steel pile location correctly on site, Risk of accuracy
of drawings, (Quality Risk).
Erect and install the bottom section of steel pile required size
into the ground by driving with the diesel hammer/drop hammer
(Environmental Risk).
51
Resume the above process until the pile has been driven to final
level according to the levels shown in the piling plans (Quality
Risk).
structures
during
construction,
the
following
52
53
Bring steel to site; unload into stock piles using a 25t crane, 2
labourers. Check for qualified crane driver, check crane load
capacity certificate and communication to the crane driver must
be maintained at all times.
54
firstly sort and place the steel manually by a gang of steel fixers
and assisted by the 25t crane to place large amounts of steel.
Communication must be kept at all times with radio devices. In
this process the placing and storage of steel must be done
carefully. As high winds can easily affect the crane, it should not
be operated in high winds. The prevention of this can come in
the form of; Checking wind speeds and the weather report
before commencing the steel fixing - (Safety Risk, High Winds)
(BSI, 1997).
While fixing the steel, all personnel must wear lifejackets and a
rescue boat must be in operation at all times.
55
56
For the piling please refer to 3.2 the piling method statement which
states the correct procedures to follow.
For the steel erection please refer to Volume 3 for the Structural steel
erection procedures.
57
4.0
M AT E R I A L S P E C I F I C AT I O N
58
59
Memb
er
Bar
mar
k
Typ
e
and
size
Typ
e
10
11
12
13
14
15
16
17
18
19
20
21
No.
of
mbr
s
No.
of
bar
s in
eac
h
Tot
al
no.
F
1
0
1
2
1
2
1
0
1
2
1
2
1
2
1
2
3
2
1
0
1
2
1
2
1
2
1
2
1
2
1
2
1
2
1
2
1
2
1
2
1
2
Lengt
h of
each
bar
Sha
pe
cod
e
A*
mm
B*
mm
C*
mm
D*
mm
217
5
200
E/R*
mm
mm
600
0
600
0
342
5
187
5
187
5
48
6000
00
413
6000
00
644
3425
00
1875
00
78
1875
00
192
2100
51
12
5500
00
2000
00
1925
00
660
2175
21
244
5500
00
102
2050
00
16
3050
00
112
1600
00
33
5250
00
134
2025
00
56
5725
00
118
4975
00
240
2750
00
48
3800
41
600
24
2175
00
217
5
60
370
550
0
200
0
192
5
100
0
550
0
205
0
305
0
160
0
525
0
202
5
572
5
497
5
275
0
620
220
200
Rev
lett
er
22
23
1
0
3
2
14
2650
51
550
28
2000
11
650
720
The bar bending schedule above shows that the reinforcement bars
are High tensile bars and are indicated by the T. The total number of
each bar are also shown and the lengths. Concrete cover to all bars is
to
be
40mm,
to
prevent
corrosion
attack
of
the
rebar.
All
61
5.0
CONSTRUCTION PROCESSES
This section covers the detailed construction process for the pile
foundations of the lifeboat station structures. Prior to any piling
works, the site must first be set out by GPS surveying technology to
pinpoint the exact positions of the piles.
62
A transport barge hauls the piles to site, at this time the piles are
transported onto the spud leg. The piles are then to be driven to the
specified depths required and cut at the correct level. The Spud leg
then raises and moves to the next pile position and operates to the
same process as mention previously. Noise will be kept to a minimum
with the use of a muffler, thus reducing the noise levels of the impact
between the hammer and the pile.
Pile shoes are generally not required for H-piles and other plain rolled
steel sections. However, if the piles are to be subjected to
exceptionally hard driving, they may be strengthened at the bottom
end by cast steel plates, or by welding plates or angles, to increase
the thickness of the steel (BSI, 1986).
63
Steel plates are then welded onto the top of the pile and bolted to the
floor frame above. Once constructed cathodic protection is then
applied to the steel H-piles thus providing corrosion resistance. See
Section 10.1 for in depth detail on corrosion resistance. While all
these operations occur, a rescue boat is constantly in attendance, and
the application of the CDM regulations are in use.
64
6.0
TESTING PROCEDURES
ultimate
bearing
capacity
of
pile
may
be
calculated
65
pile
capacity,
and
can
usually
provide
additional
66
67
7.0
PERFORMANCE CRITERIA
68
Corrosion thus occurs at the anode but not at the cathode (unless the
metal of the cathode is attacked by alkali) (Davies, 2006).
A galvanic system.
Impressed-current system.
69
7.1.4 Performance
A DC. power source with automatic potential control will be used
when the environment conditions and the structure configuration and
service conditions induce large and frequent variations of the current
demand necessary to maintain polarization (BSI, 2001).
70
71
8.0
MAINTENANCE
to
be
provided.
Specialist
contractors
with
diving
and
All
inspectors
should
be
certified
for
underwater
Inspection.
Level I -
Level II -
72
pile
will
be
cleaned
at
designated
locations
then
damage.
Non-destructive
tests
such
as
73
74
The procedures used and the results obtained shall be reviewed and
approved by cathodic protection personnel with adequate theoretical
and practical knowledge.
on
impressed
current
and
drainage
stations
is
75
8.2.3 Instrumentation
Instrumentation used for measurements shall be kept in good working
order and shall be subjected to periodical calibration and safety
checks (BSI, 2001).
76
9.0
L I F E C YC L E A N AY L S I S
Procurement of materials.
77
Waste
arising
from
demolition,
including
transport
to
destination.
Human energy.
Production
procurement
of
electricity,
of
gas
materials,
and
water
construction,
required
for
maintenance
and
Manufacture
and
maintenance
of
plant
and
machinery
(Ellingham 2006).
78
Mass
(kg)
Embodied
Energy
(MJ/kg)
Total
Embodied
Energy (GJ)
Steel
184,350
32
5899
nt
H piles
79
Plates
Bolts
Zinc Galvanized
167.16
38
6.352
88.2
38
3.35
Steel
Zinc Galvanized
TOTAL:
Steel
5908 GJ
= 184.605 tonnes
Emissions / unit
production of steel
Total emissions
= 184.605 x 1,750
= 323,058 kg CO2
= 323 tonnes CO2
Duration of
Energy
Use
Consumption
(hours)
305.36
305.36
305.36
(GJ)
193.47
32.97
193.47
Power
Machine
(kW)
Jack up Barge
Rescue Boat
Supply Barge
Hemis Number 244742
176
30
176
80
TOTAL:
419.91 GJ
81
9.2.5 Maintenance
For the maintenance, the continuous power usage over a 50 year
design period has been used.
Machine
Cathodic Protection
Power
Duration of Use
(kW)
(hours)
0.050
438000
TOTAL:
Energy
Consumption
(GJ)
78.84
78.84 GJ
The table illustrates that 78.84 gigajoules of energy will be used for
the protection (maintenance) of the piles.
82
The nature of this project suggests that the overall project is high in
risk, this partly due to working over water. Therefore Risks need to
assessed, identified, and mitigated to help prevent injury or fatality
over the course of the contract.
The following three pages lists the most common risks relevant to
piling, steel fixing and erection of the walkway, and preventative
control measures.
For each risk a contingency risk has been calculated with the financial
contingencies for each area shown below:
Piling:
59,500
Steel fixing:
59,500
Erection of Walkway:
35,000
Total:
This is added to the total cost for all piling activities.
83
Risk
Typical
Consequences
Probability/Impact
Control Measures
3/5
Implement rigorous
cdm training and safety
procedures &
equipment.
Task:
Personnel
falling in Water
Site
Fatality
Site
Fatality
2/5
Stability of
unconsolidated seabed
material must be
checked frequently.
Public
Environmental Fine
5/3
Less Probability of
environmental
fine.
2/3
3,750
Task:
Public
Environmental Risk
Environmental Fine
5/1
Less Probability of
environmental
fine.
1/1
750
Financial Cost:
Task:
Site
Quality Risk
Quality failure
3/2
Ensure regular
checking of materials
received and use a
reputable fabrication
yard with quality
approvals
Chances of quality
failure reduced
2/2
12,500
Financial Cost:
Task:
Site
Quality Risk
Quality failure
3/5
Less probability of
quality failure.
2,500
Financial Cost:
10.2
1.1
1/5
Environmental Risk
Financial Cost:
Load Testing
Less Probability of
fatality reduced
15,000
Task:
Quality
assurance of
fabrication
yard
1/5
Financial Cost:
Disposal of
waste Pile
arisings.
Less Probability of
fatality reduced
15,000
Task:
Noise
Probability/Impa
ct
Financial Cost:
Plant instability
over water
Typical
Consequences
after Control
Measures
84
1/5
Population at
Risk
Risk
Typical
Consequences
Probability/Impact
Control Measures
3/5
Implement rigorous
cdm training and safety
procedures &
equipment.
Task:
Working Over
Water
Site
Fatality
Site
Fatality
4/5
Public
1/5
Environmental Risk
Environmental Fine
5/1
Financial Cost:
Less Probability of
environmental
fine.
2/1
3,750
Task:
Site
Environmental Risk
Environmental Fine
4/1
Financial Cost:
Less probability of
environmental
damage
1/1
750
Task:
Site
Quality Risk
Quality Failure
3/2
Financial Cost:
Less probability of
quality failure.
2/2
12,500
Task:
Quality
assurance of
Reinforcement
Less Probability of
fatality reduced
15,000
Task:
Accuracy of
drawings
1/5
Financial Cost:
Lack of Steel
Storage Space
Less Probability of
fatality reduced
15,000
Task:
Disposal of
waste steel
Probability/Impa
ct
Financial Cost:
High Winds
Typical
Consequences
after Control
Measures
Site
Quality Risk
Quality failure
3/2
Financial Cost:
Less probability of
quality failure.
12,500
85
2/2
Risk
Typical
Consequences
Probability/Impac
t
Control Measures
3/5
Implement rigorous
training and regular
checking of harnesses
and lifting platforms
Task:
Working at
Height
Fatality
Chance of fatality
reduced
1/5
15,000
Financial Cost:
Task:
All
Environmental Risk
Reduced working
time
Chances of
unforeseen
circumstances
reduced
1/4
Chances of quality
failure reduced
2/2
7,500
Financial Cost:
Task:
Quality
assurance of
fabrication
yard
Probability/Impa
ct
Site
High winds
Typical
Consequences
after Control
Measures
Site
Quality Risk
Quality failure
3/2
12,500
Financial Cost:
86
1 1 . 0 C D M R E G U L AT I O N S
11.1 Introduction
The Construction (Design and Management) CDM Regulations 2004
aim to reduce the risk of accidents and occupational ill health arising
from construction work. It ensures that construction health and safety
risks are avoided, mitigated or managed throughout every stage of the
project and involving all parties, client, designer, contractor and subcontractor (Gilbertson, 2004).
87
Plant instability
Inadequate working platform for
equipment - considerations such
as:
Bearing capacity, stability, and
variability of marine conditions.
Plant and Machinery
Lifting, slewing and pitching of
casings, piles and reinforcement
cages.
Movement of piling rigs, Delivery
of materials.
88
Working environment
Noise, vibration, exhaust fumes,
trips,
open bores/excavations, impact
from
spoil falling off auger.
Services
Buried
underground
and
including
gas,
overhead
services
electricity, water
and drainage by drilling, driving,
impact, vibration, settlement.
Health hazards
Contact
with
contaminated
arising /groundwater.
Dust
and
irritation
from
materials (eg
Bentonite and cement).
(CDM Regulations, 2004)
11.3 Risks assessed by CDM Regulations for Working in Costal
conditions/over water.
89
by
plant
or
slewed
90
of
accessible
welfare
provisions
due
to
exposed/remote location.
Contaminated water:
- Water borne diseases
- Chemicals contamination
Immersion
Cold water shock.
Hypothermia.
Fatigue.
Drowning.
Moving Water
River currents, scour
Tidal movements.
Flood water.
Unsafe Temporary Structures
Unconsolidated seabed material.
Seabed Changes.
Temporary
Storage
e.g.
rock
dump.
91
11.4.1
Supervision.
and
communication
between
the
design
and
11.4.2
Pre-Site Preparations.
11.4.3
Storage of materials.
92
11.4.4
11.4.5
Floating barriers and warning lights must be provided around the site
to avoid any possibility of injury or damage by boats sailing past and
colliding with the marine structures. All visitors to the site must sign
in on arrival at the site office, and sign out on departure in case of an
emergency takes place on site.
11.4.6
93
All
11.4.7
Rescue boats
11.4.8
94
must be present on site. All employees must be familiar with first aid
procedures.
11.4.9
Emergency Procedures
should
be
familiar
with
these
procedures
before
11.4.10
Environmental issues
Contamination from fuel for plant and equipment to the local water
environment must be avoided at all cost. Therefore measures must be
put in place to avid this. Extra care must be placed when pouring
concrete at sea, spillage must be avoided. All waste must be bought to
shore and disposed of satisfactory.
11.4.11
95
11.4.12
Demolition
during
the
dismantling
of
the
structure.
The
post-
96
1 2 . 0 K E Y M I T I G AT I O N M E A S U R E S
Legislative background.
97
12.2.2
Project programme.
12.2.3
Hours of working.
98
12.2.4
Level of Noise.
Table 12 : Noise made due to piling with steel H Piles (BS1, 1992)
The table above illustrates the noise created by steel H piling (BSI,
1992). It is anticipated that the piling will eject an approximate figure
of 127 db.
12.2.5
Driven piles.
99
12.2.6
100
Weather conditions.
12.3.2
Ground Conditions.
Ground conditions, sea and waterway bed and water levels can be
very variable and change on a daily basis. This is obvious where the
location is subject to tidal influence (Construction Confederation,
2004) however, the use of a spud leg barge will effectively make the
ground conditions obsolete.
12.3.3
101
possible. Consider emergency access and egress from the site in times
of storm and known or predictable sea or waterway bed changes
(Construction Confederation, 2004).
12.3.4
Harnesses.
12.3.5
102
12.3.6
Lifting equipment.
wind
speeds.
Particular
attention
is
required
when
12.3.7
Site tidiness.
103
12.3.8
Inter-vessel transfer.
104
12.3.9
Emergency planning/preparedness.
provision
of
access
to
key
emergency
services
such
as
105
12.3.10
Rescue procedure.
A set routine for getting persons to hospital whether for checkup through immersion in water (possibly polluted), or for
treatment as the result of injury (Construction Confederation,
2004).
12.3.11
Safety Helmets.
106
12.3.12
Footwear.
Safety footwear with non-slip soles should be worn. Rubber and thigh
boots should be avoided, where possible, as, once filled with water
they act as deadweight and could drag the wearer under water
(Construction Confederation, 2004).
12.3.13
undertaken
and
the
protective
clothing
being
worn
12.3.14
107
long enough to allow for the state of the tide, height of working place
above water, or for the person being carried downstream by a current.
They may be constructed of either cork with canvas covering, or of
polyurethane foam with a rigid PVC cover. Both types are effective in
salt or fresh water (Construction Confederation, 2004).
Daily checks should be made to ensure that lifebuoys and rescue lines
are still in their proper place and that no repair work is required as a
result of vandalism or other interference.
108
12.3.15
Grab lines.
12.3.16
Rescue/safety boats.
109
provide the most benefit. Their very existence may put the safety boat
operatives in an unsafe environment (Construction Confederation,
2004).
Boats should be fitted with grab lines and carry at least one approved
lifebuoy,
boathook,
baler,
anchor
and
suitable
warp.
Two-way
110
13.0
Consultancy/Design Costs
Therefore = 76688.48
13.1.2
Construction Costs
From the Bill of Quantities in appendix C, the total cost for the piling
works is (not including Class A and B items) = 230065.45
This figure does not include all site mobilisation, labour, supervision
or plant costs which are all included in the overall Bill of Quantities in
appendix C of this report.
The
financial
contingency,
that
was
obtained
from
the
risk
111
Therefore this gives a total cost for the piling works= 289,565.45
13.1.3
Maintenance Costs
13.1.4
Demolition Costs
112
13.1.5
The total cost of the structure, over the 50 year design life =
531,489,59
113
1 4 . 0 E N V I R O N M E N TA L A SS E S S M E N T
114
Figure
xiii
Marine
Noise
Marine Life
Environme
ntal
Impacts
Erosion Risks
Water Quality
Visual
Landscape
Total
Pre
Construction
1
5
2
4
1
3
1
5
1
1
22
Signifca
nce
Project Activites
Constructio
maintenanc
Operation
n
e
4
1
2
5
5
5
3
0
2
4
4
4
1
1
1
3
3
3
5
2
2
5
5
5
4
2
1
1
1
1
64
21
36
115
Demolitio
n
4
5
4
4
1
3
3
5
1
1
55
Tot
al
60
44
15
65
9
14.2 Result
This
table illustrates
of
water during
Control measures must therefore deal with such issues as the leakage
of diesel fuel, particularly when refuelling of vessels is taking place.
Similarly, the design and provision of 'failsafe' fuel storage and
delivery systems using double skinned containers with automatic shut
off valves that are difficult to defeat is important. Pollution events
have occurred when the fuel delivery system has allowed the lever of
the dispensing gun to be tied in the open position. This occurs when
the amounts of fuel being dispensed, or the speed of the refuelling
116
Washout facilities for concrete pumps and mixer trucks along with
safe storage, mixing and use of bentonite are other high risk
situations that demand careful consideration and action.
117
The time ratios used to produce the program have been adapted from:
SPONS, 2007
This book has been used in order to obtain the practical rates as
possible. Following are the details of each tasks duration using 1
plant gang and 1 labour gang each time Assume 40 working hours per
week.
Slipway:
207.8m / 25m
8.3 days
Lifeboat:
645.6m / 25m
25.83 days
Walkway
101m / 25m
4.04 days
39 days
118
For all take off sheets, gantt chart and resource allocation. Please see
Appendix C.
1 6 . 0 T A K E O F F S H E E T R E S U LT S
SECOND DIVISION
THIRD DIVISION
Qty
Un
it
Ref
2
.
3
.
Depth
4
.
20-30m
125
B23
4
4
.
Samples
2
.
From Boreholes
1
.
Open Tube
nr
B42
1
5
.
5
.
1
.
1
.
1
.
3
.
Permeability
Standard
Penetration
10
nr
10
nr
6
.
6
.
Instrumental
Observations
Instrumental
Observations
3
.
3
.
Installations
42
nr
Readings
42
nr
Moisture
Content
nr
Classification
1
.
2
.
Triaxial Cell
nr
B71
1
B74
2
Engineer
Chartered
B83
7
.
7
.
Laboratory Tests
1
.
4
.
Professional Services
Laboratory Tests
Settlement Gauges
Settlement Gauges
Classification
119
1
.
4
.
25
B51
1
B51
3
B63
1
B63
4
Reinforcement
Reinforcement
Reinforcement
2
.
2
.
2
.
Deformed high
Yield Bars
Deformed high
Yield Bars
Deformed high
Yield Bars
3
.
4
.
8
.
10 mm
1.3
12 mm
9.5
32 mm
0.2
G52
3
G52
4
G52
5
10.
7
M42
1
10.
7
M62
200
nr
M64
4
Galvanizing
65
M86
Cathodic Protection
42
nr
M87
48
N14
65
O34
Fabrication of other
members
2
.
Beams
1
.
6
.
2
.
Permanent erection
6
.
4
.
HSFG general
grade
8
.
8
.
6
.
7
.
4
.
Straight on
plan
24-30mm
4
.
Handrails
CLASS O : TIMBER
3
.
Hardwood decking
Hemis Number 244742
4
.
25 - 50 mm
120
CLASS P : PILES
7
.
5
.
166
.6
P75
956
Q51
5
42
nr
Q84
42
nr
Q85
8
.
8
.
Pile tests
Pile tests
1
.
4
.
5
.
Non destructive
Integrity
Inclinometer
Readings
5
.
depth driven
The next sheet shows a Bill of Quantities for the materials to be used
in the construction of the piling foundation, construction of walkway
and reinforcement in the slab.
121
Total ()
957,471.48
6,488.73
Class E: EARTHWORKS
25,166.40
48,044.35
226,451.19
57,910.00
6,065.80
Class P: PILES
150,900.55
146,627.60
6,961.50
Class V: PAINTING
3,196.20
13,443.36
305,500.00
BILL TOTAL
1,954,227.16
Mechanical and Electrical - 30% of the station without slipway and walkway
GRAND TOTAL
138,697.76
2,092,924.91
Contingency @ 5%
104,646.25
2,197,571.16
122
19.0 REFERENCES
website:
http://www.sbe.napier.ac.uk/projects/piledesign/guide/chapter1.htm
BSI. (1992). BS 5228-4: 1992 Part 4: Code of practice for noise and
vibration control applicable to piling operations. London: BSI
123
Architect
website
on
124
March
3,
2007
from:
http://www.canadianarchitect.com/asf/perspectives_
sustainibility/
measures_of_sustainablity/measures_of_sustainablity_embodied.htm
/technologyaccelerator/life-
cycle_energy_and_emissions.htm
125
on
March
12,
2007
from
http://www.english-
nature.org.uk/science/natural/NA_HAbDetails.asp?Name
=Folkestone+to+Selsey+Bill&N=108&H=65&S=&R=
Ellingham,
J.
(2006).
November
28th,
2006,
Individual
from
Report.
University
Retrieved
of
Retrieved
Portsmouth,
Civil
agents.
Retrieved
April
20,
2007,
from:
http://www.ciria.org/acatalog/c602.pdf
Engineering
website
on
March
3,
2007
http://www.fes.co.uk/services/GeophysicsPileTesting/intro.asp
126
Haven Ports (2007) Jackup Barge Hire Retrieved from Haven Ports
website:
http://www.havenports.co.uk/plant_hire/marine_plant_hire/jack_up_ba
rge.php
Jufri, S.A.R. & Wellman R.J. (1996) 'Civil Engineering Construction IV',
The Hong Kong Polytechnic University.
Live Local (2007). Live search. Retrieved from Live local website on
March 3, 2007 from http://maps.live.com/
website
on
March
3,
2007
from:
http://www.greenhouse.gov.au/yourhome/technical/fs31.htm
127
website
on
May
3,
2007
from
http://www.pilecapinc.com/inspection.htm
Retrieved
February,
23,
2007
from:
http://scopac.org.uk/maps/sediment.pdf
SCOPAC,
(2007).
Maps.
Retrieved
26th
February
2007
from
http://www.scopac.org.uk/maps.html
128
April
20,
2007,
from:
http://www.engineerlive.com/asiapacific-engineer/healthsafety/2185/ultrasonic-thickness-gauges-help-avoid-equipmentfailure.thtml
129
130
2 0 . 0 A P P E N D I X A : D R AW I N G S
131
2 1 . 0 A P P E N D I X B : C A L C U L AT I O N S
132
133