Вы находитесь на странице: 1из 39

www.bimtaskgroup.

org

p12

42nd

Spotlight on:
Hannah Mansell
& the BWF

Edition

@BIMgcs

p22

2014

Government
Construction Summit

p58 COBie

in the UK

WEEKLY NE WS LE TTE R

July 15th, 2014

View this weeks


Round the parish news

The Asset Information Model using BIM


Using PAS1192-3 to develop a bespoke digital AIM to support decision making

OIRs, AIRs and EIRs


Read more

This weeks feature story

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

DEPARTMENTAL ENGAGEMENT AND SUPPORT OFFICER ACTIVITIES (1)


Ministry of Justice (MoJ)
Richard Lane
Status meeting on 17 June. Work in progress
on training strategy & resources
Work in progress on next phase of adopter
projects and capturing lessons learned from
completed projects
Graeme Tappenden support in procurement
& integration of BIM Server. MOJ BIM Server

{ Philip Isgar }

{ Adam Matthews }
Highways Agency (HA)

{ Fiona Moore }

{ Richard Lane }

{ Anne Kemp }

Departmental Engagement
and Support Officers

Department of Health
ProCure 21+ (P21+)

Phil Jackson & Graeme Tappenden


Meeting with HA to review & update BIM
Strategy
On site meeting with M1 Junction 33 Team
reviewing BIM and data handover
Meeting of the HA BIM Project Board
Incorporation of BIM into the Capable Asset
Transformation theme of the Highways GoCo

Richard Lane & Howard Jeffrey

Defence Infrastructure
Organisation (DIO)

Article from Howard published in P21+ Newsletter


FM benefits document developed
Phase 1 early adopter reports in development

{ John Lorimer }

{ Graeme Tappenden }

Initial Phase 2 early adopter projects identified


Education Funding
Agency (EFA)
Richard Lane & Fiona Moore

Work is in progress on implementation strategy and process workstream.

{ Phil Jackson}

{ Howard Jeffrey }

Richard Lane & Fiona Moore

June has been a busy month for DIO, resulting in:


Executive Officer endorsement of the DIO BIM Strategy
Paper
Continued drafting of DIOs BIM Implementation Strategy in line with the 2016 BIM projects target
EIR Workshops that have resulted in the production of
a first draft DIO EIR
The selection of DIOs first BIM Trial Projects

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

DEPARTMENTAL ENGAGEMENT AND SUPPORT OFFICER ACTIVITIES (2)

Education Funding
Agency (EFA) and Training

Environment Agency (EA)


Phil Jackson & Graeme Tappenden

Richard Lane & Fiona Moore

{ Philip Isgar }

Work is in progress on implementation strategy and process workstream.

{ Adam Matthews }
{ Fiona Moore }

{ Richard Lane }

Local Government

{ Anne Kemp }

Departmental Engagement
and Support Officers

John Lorimer & Graeme Tappenden

Proposal pending to pass stewardship of LG BIM Regional


Champions & SIGs under National Association of Construction Frameworks NCAF. Police now becoming very
active. Interest rapidly building.

{ John Lorimer }

{ Phil Jackson}
{ Graeme Tappenden }

Training
Richard Lane

Project initiated to update the Learning


Outcomes Framework

Great progress in month. BIM Strategy pending


internal signoff. 9 Adopter Projects c800m+ & supplier SIG engaged. 6 supplier led workstream focus
groups established: EIR, COBie, MIDP, KPI, CDE &
Visualization Formats. Asset community engaged.

{ Howard Jeffrey }

Nuclear
Philip Isgar

Catch up meeting with John Clarke CEO - NDA


Meetings with Sellafield Ltd, Heads of Capability in Project Management,
Architecture and Computer Aided Engineering
Meetings with government departments, BIS, DECC and IUK Treasury
Organised speakers for Major Projects Association event on Nuclear New
Build Competency and Capacity
Strategic meetings with URS, Edf, Turner & Townsend and Capita
Supply Chain meetings with JCB, Amtech, Waldeck and Sitedesk
Established an accepted collaborative presentation to ICE - BIM 2014 a
nuclear Case Study
Attended Constructing Excellence NW BIM Group Meetings
A guest at Parsons Brinckerhoff (PB) Project of the Year Awards
At PB Launch of Digital Life Digital Legacy - Realising Digital Potential of Infrastructure Projects Infrastructure Projects

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

CORE TEAM MEMBER ACTIVITIES (1)

Mark Bew
Task Group Chair

Adam Matthews
EU & International Relations
MSBF enabling hierarchy

MSc summer School - Salford University


BIM review with Ordinance Survey Exec
Digital Built Britain Strategy Planning
Government Constructing Board
Tier 1 BIM2 Workshops
BIM4Manu Workshops
HS2 Strategy
Cyber Security Planning
dPoW entry mid design reviews
BSi - Greenwich County Council Smart City Standards Review

Training strategy meeting with Terry Stocks and BIM Academic


Forum to support international alignment on common BIM learning
outcomes.

International relations development with Asia-Pacific region, including


buildingSmart Australia and Singapore BCA to develop international
outreach programme for BIM Task Group in September & October.

Paris. Mark and Adam met with European BIM Group of public clients
to shape its medium-term programme and deliverables plan.

Attended the 1st session of ISO working group led by BSI to transition PAS1192 Part 2 to an ISO standard.
Update meetings with Mark, Terry and Barry Blackwell (Dept. for BIS)

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

CORE TEAM MEMBER ACTIVITIES (2)

Rob Manning
BIM Task Group

Terry Stocks
Delivery Director for Level 2 BIM

Part of the Construction News Awards 2014 Judging Panel.

Chaired meeting #2 of the BIM Stewardship Group

Attended the Government Construction Board (GCB) Meeting

Met with members of the BIM Task Group and Support Officers, as a
group and 1-2-1 to update on department BIM activities and progress

Took part in a meeting discussing Legacy Planning

Met with the Department for Transport and HS2

Presented BIM Level 2 to the South East BIM Hub at CICs offices

Chaired meeting #20 of the BIM Steering Group

Conducted a one day workshop for the CIC BIM Hub Champions on the use
of PAS 1192 Part 3.
Delivered a presentation on PAS 1192 Part 3 to the AGI BIM and Asset Management conference in Bristol.
Delivered presentations at the BIM4Manufacturers workshop. Presentations
addressed PAS 1192 Part 3 and the TSB BIM competition A digital tool for
building information management.
Contributed to question and answer sessions with the three bid leaders (BRE,
CIBSE and RIBA Enterprises) for the TSB BIM competition.
Delivered a presentation on Government Soft Landings to the AGM of the
Society of Electrical and Mechanical Engineers(SCEME) serving local government.
Attended the BSRIA Soft Landings User Group meeting.
Chaired a meeting of BSRIA Soft Landings leaders and the Government Soft
Landings Stewardship Group to explore opportunities to work more closely.
Delivered information on PAS 1192 Part 3, TSB BIM competition and GSL to
delegates at the Government Construction Summit.
Attended a CBx event A Soft Landings Approach delivered
by members of the BSRIA Soft Landings User Group at UCL
Energy Institute.

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

CORE TEAM MEMBER ACTIVITIES (3)

David Chairs the GCS


BIM panel session

David Philp
BIM Task Group Head of BIM

10

Chaired the BIM Panel session at Govt Construction Summit 2014


BIM Knowledge Hub at Govt Construction Summit 2014
Steering group meeting and update
Core team & departmental support meeting
Chaired launch of the Manufacturers Strategic BIM Forum
Practical delivery of IFC conference
SE BIM Hub level 3 presentation
Presentation at Greening Education conference
Presentation at ECTP, ENCORD, ENBRI conference - Brussels
Various BIM4 community meetings
UKCG conference and annual lunch
Media liaison
Assisted students in research and dissertation topics
Newsletter and development of new website
CN Awards 2014 task group presentation

Birthday wishes
Inaugural MSBF meeting
at BIS innovation centre

We would like to take this opportunity to send our wishes to Nikkie Basquine
of the BIM Task Group who celebrates a special birthday
all we can say is
she was born in the same year as her look alike Scarlett Johansson
or simply put half the age of Mark Bew and 5 years older than David Philp

11

INTERVIEW
INTERVIEW

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

BIM: PEOPLE MATTERS


14 QUESTIONS WITH
HANNAH MANSELL
In this edition we interview Hannah
Mansell, Technical Liaison Manager
with the British Woodworking Federation (BWF) and discuss the opportunities of digital workflows, data
needs and her parallel life as a cabinetmaker, artist and running a joinery businesses and her obsession
with all things timber!

Hi Hannah, can you tell us a little


about you and your background?
I have always been a really hands on,
artistic and creative person, who loves

12

13

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

making things from wood and initially


trained in furniture design and manufacture, alongside completing a traditional
cabinetmaking apprenticeship. Since
leaving university I have worked in
cabinetmaking and joinery businesses
of all sizes making everything in wood,
from the sublime to the ridiculous! I am
obsessed with timber; it is a truly magic
material, both to work with and to live
with.

Hannah
and her dog
Darcy
My work
is all about detail,
and attention to.
The digital exchange
of design
and contractual
agreement
has proved
a useful tool
in efficiently
manufacturing

Woof!

To develop technically, I completed a


Masters degree in Design Engineering
and have worked with both large and
small timber joinery and furniture manufacturers in product development and
R&D, process engineering, continuous
improvement and production management.
I currently work for the British Woodworking Federation as their Technical
Liaison Manager, dealing on a daily
basis with technical queries and regulations from our members and the public.
I also run my own business, specialising in the completely one off design and
manufacture of bespoke fine furniture
and art. Current projects on the books
are a sculpture from a 300 year old oak
tree, that fell over in the 2014 gales,
a design studio fit out and lounge furniture suite finished in two tone, high
gloss glitter paint...its varied, its exciting
and its creative.
My spare time is spent fitting out my
narrowboat... and yes, its all in wood, a
tribute to timber!

14

What can you tell us about the


British Woodworking Federation (BWF)
The British Woodworking Federation
(BWF) is the largest lobbying and business support organisation in our sector.
We offer advice, support and wood
industry information to our approaching
700 members as well as guidance for
customers who use or specify timber
products. We also provide voice for
the sector in the UK, influencing policy,
regulations and standards. We promote
the use of timber as a construction
material for internal and external joinery projects and celebrate its material
properties and the variety of uses that it
is suitable for. The BWF also manages
and accredits industry schemes including BWF CERTIFIRE for fire doors,
the BWF Stairs Scheme for timber
stairs and the Wood Windows Alliance.
These schemes have been set up to
improve industry standards and promote best practice for UK manufacturers who make quality, sustainable, safe
and beautiful timber joinery products.

What does your role as technical


liaison manager involve?
Every day is different.
This could really be attributed to the
variety of our membership, from one
person businesses, making one door a
week, right up to mass manufacturers
who ship thousands of timber doors

15

Newsletter, 42nd edition | July 15th 2014

and windows a week, we are in touch


daily with our members. The type of
technical assistance required is varied
but involves dealing with project specific technical queries relating to design
of product and current regulations, right
through to health and safety and legal
and contractual questions.
On a wider scale, my role at the BWF
means that I get involved in technical
committee meetings and projects such
as the implementation of BIM, Environmental Product Declaration (EPD) and
CE marking for our members products and providing technical advice
and assistance to our fire door, timber
stair and timber window accreditation
schemes.
A key aspect of my role is communication, tailoring both relevance and technical depth of knowledge appropriate to
the recipient.

How advanced are the BWF with


digital and or automated workflows?
Many joinery businesses are already
operating digital and automated systems integrating their design and manufacturing processes. The BWF have
been working with software companies and monitoring the developments
closely, assessing how they will impact
our members, industry and wider sec-

16

www.bimtaskgroup.org

tor. We have also been analysing the


opportunities that may be presented
to UK joinery manufacturers and the
UK construction industry and working
closely with industry experts to understand the risks and cost implications for
implementation. Our strategy is to be at
the forefront of providing useful information, guidance, resources and tools to
our members to enable them to adopt
new technologies within their business,
tailored to their particular business type
and scale.

What opportunity does BIM offer to


the BWF members?
Of course, there are the raw commercial opportunities of getting involved in
BIM enabled projects and being able to
efficiently provide accurate construction
data, liaising with project planners, architects and specifiers on a highly technical level. But if we look deeper and
refer back to the theory and rationale
for introducing BIM and other types of
digital workflows and relate them specifically to joinery manufacture, it represents a real opportunity to reduce waste
and cost from the manufacturing and
construction process, by getting it right,
first time. The products that our members manufacture are high performing,
technologically advanced, complicated
products that are manufactured under
strict factory control process to ensure

performance and conformance. Using


digital workflows provides the opportunity and physical platform to exchange
and communicate accurate product
data with all stakeholders throughout
the design and construction process
and ultimately the end user, ensuring
that the product performs during its
lifetime. This will also crucially enable
better protection of a specification,
limiting opportunity for quality products
to be value engineered out by inadequate alternatives this is a significant
problem for all construction product
manufacturers, but is perhaps most
significant for products such as Fire
Doors, which perform critical life safety
functions. This is really about providing
manufacturers a platform for making
their product information readily accessible... in a nutshell; traceability. It is
also hoped that installation, care and
maintenance instructions will be more
readily available, supporting longevity
and hence sustainability of products.

What are the challenges towards


BIM adoption in your community?

that the information is communicated


in needs to be simplistic without diluting the detail and easily accessible; by
this I mean that the systems in place
to manage BIM needs to be watertight
and easy to use. The more complex
it is the more we create a new tier of
unnecessary consultancy and cost
that could limit opportunities for certain
companies.
However, providing accurate product
data is nothing new for our members,
we actively encourage them to widely publish their technical data and
literature. In fact for our certification
schemes, the relevant documentation
to prove that a product will perform in
accordance to manufacturers claims is
integral at all levels of the design and
build process, from initial specification
and procurement, through to the strict
factory production control processes
in place and onwards to the care and
maintenance of the product throughout
its lifetime. After all, our members make
high performing, quality product, from
a material that is truly sustainable and
naturally beautiful; why wouldnt we
want to shout about it from the timber
trusses?

In principle nothing, but our membership is wide ranging in respect of size,


product and process and one of biggest
challenges that the sector faces is communicating the relevant product data to
the right person at different levels of the
project and build process. The format

17

Newsletter, 42nd edition | July 15th 2014

If we look deeper
and refer back
to the theory and rationale
for introducing BIM
and other types
of digital workflows
and relate them specifically
to joinery manufacture,
it represents a real opportunity
to reduce waste and cost
from the manufacturing
and construction process,
by getting it right, first time

18

www.bimtaskgroup.org

What sort of data is important to


your members?
For some time we have been maintaining an in depth dialogue with both
our members and other construction
industry experts, to disseminate what
type of data is going to be important to
be communicated through the construction process and then lifetime of timber
joinery products.
We see the type of data as being wide
ranging, from specific product dimensions and tolerances, right through
to the specification of individual components contained within the design,
installation detail and care and maintenance guidance. In addition we see it
as important that the product installed
can be linked back to the relevant
British Standards and regulations and
certification that it has been developed to perform and conform to. This
is particularly important when talking
about construction elements such as
fire doors and fire protected stairs or
highly performing thermally efficient
timber windows. These are finely developed products and every detail and
component of the design has been
engineered to ensure that it performs.
That is why we must ensure that the
format and type of information that is
held is accurate and properly managed. In implementing any project, it is
important to consider the implications

and possible risks associated of managing this type of information in the long
term. Also crucially Embodied Energy
is of increasing significance, accounting for 30-50% of a buildings overall
carbon cost, this is again data that can
be effectively managed through BIM to
support the right sustainable choices.

Are BWF working with any of the


BIM4 groups to share knowledge?
The BWF is working closely with the
Construction Products Association,
National Specialist Contractors Council
and BIM for Manufacturers and Manufacturing working groups. We are
currently reviewing and developing
the Product Data Templates with other
UK construction industry experts from
many different sectors and material
backgrounds. What is important about
this exchange of knowledge and information is that by working together, a
system is being developed of gauging
not only what is currently best industry
practice and standard, but the often
highly charged and animated discussion throws up many questions about
what the what the future holds of the
construction industry, product development and product implementation.
My background in project management
means that I know the process of holding and exchanging accurate product
and construction data is a vital to a successful project. However, it is important

19

Newsletter, 42nd edition | July 15th 2014

to remember that this info needs to be


delivered in a manner that can be understood by all stakeholders in a construction process, whether this be the
lead architect, local authority planning
office, carpenter on site or the domestic end user. We need to ensure that
the tools and resources are in place to
deliver this info in a usable format and
that is why it is important to maintain
this dialogue throughout all the associated trades involved in the construction
process.

What are BWF looking to do in


order to help support their members
BIM mobilisation and implementation
journey?
The BWF are working on a range of
tools and resources that will assist in
the implementation of BIM into our
members businesses. From the very
practical tools such as Product Data
Templates to cater for the entire product
ranges of our members, to developing
a range of education resources that
can be rolled out in the businesses
with the objective of communicating
the importance of accurate product and
construction detail. We see education
throughout both the manufacturing and
construction sector as integral to the
adoption of BIM. Great things can be
achieved by making readily available
accurate and detailed product data, but

20

www.bimtaskgroup.org

only if it is managed well throughout the


entire construction process and lifetime
of a building by all stakeholders. Adopting BIM into a project and for any manufacturer involved in building is going
to mark a significant change to the UK
construction industry and the education
and training is the key to successful
implementation.

10

What will UK woodworking


manufacturing look like in a digital future?
The UK woodworking industry will be a
world leader in both the development
and manufacture of quality sustainable
products. We continue to look to the
future, in both the adoption of technology and digital exchange of prodcut
information. The woodworking sector
has experience, knowledge and skill
built up over hundreds of years, and we
cannot discount that. But we do need to
continue to look to the future, short and
long term and this is why it is so important to encourage schemes like apprenticeships, up skilling of your workforce
to ensure that we do have a sustainable
UK manufacturing future.

11

Do you think BIM could help


transform your sector?
There are many developments in product development, procurement, manufacturing theory and technology and
UK Building regulation that are driving
overall development in the UK timber
joinery industry. One thing is for sure;
UK joinery manufacturers have the
technical and manufacturing ability to
deliver quality product; BIM is a useful
initiative to drive improvement throughout the entire industry. As much as
our members products are made up
from many components that must work
in harmony with each other, so is a
building. BIM is encouraging dialogue
between all facets of the UK construction industry, and this can be a driver for
improvement and development, Together we are strong, now lets get out there,
manufacture, build and improve!

12

Back to you. Do you implement any digital workflows in your own


joinery business?
Dependant on project, I also liaise with
many different stakeholders on a project whether it is material suppliers,
clients or other building trades. My work
is all about detail, and attention to. The
digital exchange of design and contractual agreement has proved a useful tool

in efficiently manufacturing and ultimately producing successful projects to


budget and customer satisfaction.

13

Last wood and non non-wood


working books read?
It is the same book. Eucalyptus, by
Murray Bail; a book that I must have
read a hundred times! Its a beautiful
story with many other stories entwined
into it...and a educating read, each
chapter is named after a different species of eucalyptus tree...did you know
there are over 100?

14

What do you do with all that


sawdust?
All waste generated throughout the
production process is sorted by type
and recycled into the relevant waste
streams. Theres brass in muck. I have
a contract with a recycling company
and have eliminated waste disposal
costs from my business by recycling
or reusing everything. Packaging is
also a big consideration for me, both of
raw materials and delivery of finished
goods. I maintain a strong dialogue with
suppliers regarding packaging and the
disposal after. My training in lean manufacturing and continuous improvement
would not let me be any other way!

21

CONSTRUCTION SUMMIT

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

The BIM Task Group enjoyed another year at the Government Construction Summit and enjoyed the opportunity to share progress on
the programme since inception.
Mark Bew, Chair of the Task Group noted Great support and vision from Vince Cable, Paul Deighton and the political team
David Philp chaired a benefits of BIM panel session on the main stage more in the next edition ...

Dave Philp at the Knowledge Hub modelling the fastest route to the wash rooms

Dr Vince Cable describes how BIM will help create


smart and well-designed cities

22

are
eam prep
T
e
r
o
C
e
h
ew of t
ub
d Mark B
n
a
s
owledge h
k
c
n
o
k
t
S
M
I
y
B
r
r
e
e
T
to th
of visitors
h
s
u
r
a
r
fo

23

Newsletter, 42nd edition | July 15th 2014

Richard Lane Graeme Tappenden (Core Team) and


Karen Alford (EA) bonding over a MIDP

24

www.bimtaskgroup.org

ath

),K
re Team
o
C
M
I
B
g(
BSI)
Mannin
b
o
R
,
ndiak (
)
S
a
s
C
o
I
K
R
(
e
i
se
han
Alan Mu
nd Step
a
BIM
)
M
A
B
ent and
a(
m
e
g
a
n
Fontan
ma
ng asset
discussi

Rebecca Evans of E-Map


and bump visit the
Hub Congratulations
from all at the BIM
Task G r o u p

25

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

The Summit established how


the combined Government Construction Strategy (GCS) and
its components such as Project
Bank Accounts and BIM were
realising the efficiencies and reforms that were envisioned.
Indeed at the first summit the
BIM Task Group were hypothesising that Level 2 and the use
of open shareable asset information would lead to better value
for money, better carbon decisions and better outcomes.
Three years on we are cementing regular savings and the UK
BIM standards and processes
are recognised as the global
benchmark for industry digitisation.

26

27

AIM - PAS 1192:3:2014

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

The Asset Information Model


using BIM

Figure 1

PAS1192-2 and PAS1192-3

by: Rob Manning


BIS BIM Task Group

Introduction

In this article we look at how the approach outlined in docu m e n t PA S 11 9 2 P a r t 3 m i g h t b e u s e d b y a n o r g a n i s a t i o n t o


develop their bespoke digital Asset Information Model to
support decision making.

The publication of Publicly Available


Specification PAS 1192 Part 3 provides
a Specification for information management for the operational phase of
assets using building information modelling. It is a companion document to
PAS 1192 Part 2 which is a Specification for information for the capital /delivery phase of construction projects using
building information modelling. The
Part 3 document provides an approach
to creating an asset information model
to support the whole life of an asset
from create/acquire, through use/maintain and on to renew/dispose.
Here we are using PAS 1192 Part 3 to

28

explore how an organisation might go


about establishing a digital asset information model to provide information for
management.
Please note that hard copies of the
two companion documents are available through the BSI Bookshop (PAS
1192-2 LINK) and (PAS 1192-3 Link)
and free to download pdf versions were
made available on the BSI Bookshop
at the time of launch. The publication of
both documents makes it clear that one
of the main objectives of the application
of information modelling in the capital
delivery phase of an asset is to provide
information to support the longer term
activity of asset operation.

PAS1192-2 Information Management


in the Capital Phase
using BIM. February 2013

PAS1192-3 Information Management


in the Operational Phase
using BIM. March 2014

29

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

UK Government Digital Plan of Work


Figure 2

UK Government Digital Plan of Work

The Operation and End of life work


stage requires the organisation and
their design/construction team to focus
continuously on whole life considerations and in particular upon measuring
how well the delivered asset meets the
Strategy stage targets. Targets might
not be met for a number of reasons, for

example the targets may have been


wrongly set and the use of the asset
may have changed but it is important to
measure performance, recognise positive and negative impacts upon performance and to optimise performance.
These are the fundamental principles
of Soft Landings for the government
construction client.

Capital Delivery phase of an asset using BIM


Figure 3

Capital Project Information PAS1192-2 2013

In Figure 2 we introduce the work stages associated with the life cycle of an
asset. In 2012 the Business Innovation
Skills Building Information Modelling
(BIS BIM) Task Group worked with the
publishers of existing plans of work
to agree a standard set of work stages
that would be applied across all roles
and sectors associated with the creation and operation of assets in the built
environment. The aim was to agree
work stages that would be used across
all roles and sectors to reflect a consistent level of development of information
including non-geometric data, geomet-

30

ric data and documents. Note the significance of including Strategy and Operation and End of Life in the work stages.
These stages had not been strongly
recognised by previous plans of work.
At the Strategy work stage an organisation seeking to create a new asset
will be expected to define their required
outcomes in terms of the social, environmental and economic measures that
define sustainability. It is a stage that
is about the business defining required
economic, social and environmental
outcomes and setting measurable targets.

31

Newsletter, 42nd edition | July 15th 2014

A lot of people may be familiar with Figure No 3 as an overview of using BIM


in the capital phase of asset delivery.
The process of capital delivery begins
on the right hand side in the operational
phase of the above diagram with the
organisation deciding that it needs to
create or refurbish an asset and that
decision of course is related to business need. The process then moves
anti-clockwise around the diagram. The
organisation will identify what information it already knows and what information it will want from the asset construction process to inform decisions
these will be called the Employers
Information Requirements. The Employers Information Requirements are
identified as the basis of construction/
refurbishment/de-commissioning contracts and as part of the procurement
process the organisation next seeks
an execution plan that demonstrates
that the supply chain can deliver what
is required. Following contract award a
delivery plan is produced by the supply
chain to identify from within their team
exactly who delivers what and when.
This is referred to as the Master Information Delivery Plan. It should be noted
that the TSB BIM Project A digital tool
for building information modelling (insert link) is being established to create
for all sectors a means of producing
both a default and a bespoke digital
Plan of Work using a Classification
system that will be applicable to all
construction sectors. The digital Plan of

32

www.bimtaskgroup.org

Work will effectively help to inform the


Master Information Delivery Plan. After
supply chain mobilisation the project
starts and information is exchanged
with the Employer at the agreed decision points.

Asset Management
Figure 4

Asset Management (Using PAS 55)

There are also likely to be many information exchanges between the design/
construction team at each of the work
stages. Digital documentation, graphical
data and non-graphical data are produced progressively in support of the
Employers decision points and eventually are transferred to the Employer
organisation at the end of Handover
and Close-out work stage.
The organisation has to decide what
happens to that digital information, how
it benefits them and how it fits with the
long term activity of asset management.

PAS1192-2:2013
Figure 4 introduces content from Publicly Available Specification(PAS) 551:2008 and PAS 55-2:2008. Part 1 sets
a standard for asset management. Part
2 provides guidelines for the application of PAS 55-1. Design companies,
construction companies and asset
operating companies might find it useful
to introduce awareness of these documents into their training programmes.

This diagram from PAS 55:1 identifies


the hierarchy of asset management. At
the apex of the triangle it shows the key
objective of supporting the purpose of
the business. It introduces the layers of
managing a diverse portfolio of assets
and of managing asset systems that
have an indefinite horizon of required
usage and each contribute to the overall goals of the organisation.

33

Newsletter, 42nd edition | July 15th 2014

As well as the layers dealing with strategic direction the diagram shows the
day-to-day activities and realities of
managing assets Create/acquire,
Use, Maintain and Renew/Dispose.
The diagram goes some way to showing that over the long-term of asset
management, the activities of Create/
Acquire and Renew/Dispose might be

www.bimtaskgroup.org

occur relatively infrequently.


Of course it is these Create/Acquire and
Renew/Dispose activities which require
the information management approach
identified in PAS 1192-2 whereas the
information management approach
identified in PAS 1192-3 applies to the
much longer term of whole life asset
management.

the short term construction/disposal


activities which are the subject of a lot
of publicity in the construction world are
really a means to the long-term end of
successfully operating a business supported by the practice of asset manage-

ment. The diagram illustrates the work


stages 0 (Strategy) to 6 (Handover and
Close-out) associated with PAS 1192-2
and the multiplicity of activities (n) that
occur during the much longer timescale
associated with work stage 7 (Operation and End of Life)

Operational phase of an asset using BIM

Figure 5

The Project Information Model in the asset life cycle?

Figure 6

Whole Life Information


PAS1192-3 2014

Figure 5 introduces the BS ISO 55000


series of documents which is now
published and sets an international
standard for asset management. At the
time of drafting PAS 1192 Part 3 the
new standards had not been published.

34

The information management approach


of PAS 1192 Parts 2 and 3 are shown
here surrounded by the standards of
asset management and the needs of
operational management for the business need. It is perhaps a reminder that

35

Newsletter, 42nd edition | July 15th 2014

How does information generated by the


day to day activities of asset management interface with the broader objectives of an asset information system?
The bottom left of Figure 6 shows
the broad principle of information exchanges from the multiple tiers of the
supply chain on a Create and Acquire
activity. These information exchanges
will be managed in keeping with PAS
1192-2. It also shows that there will
be similar information exchanges from
the supply chain on a Renew/Dispose
activity which will also be managed
in keeping with PAS 1192-2. The development of information in the above
activities is progressive and sequential

www.bimtaskgroup.org

in line with programmed work stages


to align with key decision points by the
Employer. The bottom centre of the
diagram shows the information exchanges associated with the Use and
Maintain activities and points out that
during these activities which last for
the greater part of the asset life cycle,
the information exchange points and
the decision points very rarely align so
there needs to be a way to store use
and maintain information so that the
most up-to-date information is available
to inform the decisions of corporate/organisation management when the need
arises. Figure 6 introduces the Asset
Information Model which can provide a
repository for information.

Asset Information Model Creating the case


Most organisations will probably say
that they have an asset information
model, after all they have probably
been managing assets for years. Their
models might be paper based, they
might be digitally based and they might
be a mixture of both. The models used
might either be managed by the organisation or they might be managed by a
supply chain provider. As asset portfolios become larger and more complex
and as the world becomes more digitally biased, organisations will no doubt
allocate more and more executive time

36

to consider the need for a re-structuring


of how they manage asset information
to information better decisions. Whatever method is used by the executive
team to analyse the performance of
their current model and to inform the
need for re-structuring the organisation,
it will almost certainly need to identify
benefits that it seeks to obtain from
using and owning a digital asset information model.
Before embarking on the journey of
producing the digital asset information

model an organisation will develop and


publish a business case. They will need
to identify the benefits that they plan
to obtain; how much time and money
will be needed to create a data and
file store; how much time and money
will need to allocated to identifying the
information that will be required; how
much time and money will be needed
to collect that data; what sort of people
and how many people will be needed
to conduct the work and provide governance; what sort of software tools will
be used to extract data from the asset
information model and create reports.
One of the first steps will be to identify
the potential benefits of creating a digital information model.
Some of the benefits might be as the
following;
Reduced costs due to the automated transfer of information from construction to operation. Less manual
input of information.
More complete information reducing management costs.
Fewer problems and costs during
early operation of a new or refurbished asset because of the availability of better information about the
asset.
The opportunity to reduce operation
and maintenance costs.
More focus on long term operational performance giving better in-

formed decisions about operational


expenditure and capital expenditure.
Reduced remedial costs during early operation brought about by fewer
construction defects.
Savings from life cycle decisions
informed by a single, integrated,
up-to-date source of information.
Better modelling of resilience and
risk of failure.
Improved expenditure
decisions enabled by information to support asset investment planning.
A source of data records from dynamic metering and condition sensors to identify poor energy performance, faults and risk of impending
failure.
The Organisation owns and retains
all their asset information for future
procurement.
The benefits to be sought are very personal to each organisation. Identifying
the anticipated benefits is the critical
stage of defining the required outcomes
that the asset information model is to
deliver. As with any project it is essential for the organisation to keep in mind
the outcomes that it requires and to
continuously monitor how well they are
met.

37

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

Below is an example from the list of potential benefits that we will follow through this text;

Organisation Information Requirements

To i m p r o v e e x p e n d i t u r e d e c i s i o n s e n a b l e d b y i n f o r m a t i o n t o
support asset investment planning.

The organisation will first identify what


information it needs in order to answer the operational decisions that it
will have to make. PAS 1192:3 refers
to these as Organisation Information
Requirements (OIRs). Having an asset
investment plan is an example.

calculate the financial and resource impact of deviating from


plans that might result in a
change in asset availability or
performance (e.g. what is the
financial impact of deferring the
maintenance of a specific generator by six months);

optimize asset management


strategy and optimize/prioritize its
asset management plan(s);

assess its overall financial performance;

Preparing for an Asset Information Model


Figure 7

Essential components to develop the model diagram

assess the financial benefits of


planned improvement activities;
determine the operational and
financial impact of asset unavailability or failure;
make life cycle cost comparisons
of alternative capital investments;
identify expiry of warranty period
and warranty;
determine the end of economic
life of assets/asset systems, e.g.
the point in time when the asset
related expenditure exceeds the
associated income;
determine the cost of specific
activities (activity based costing),
e.g. the total cost of maintaining
a specific asset(s)/asset system;

Figure 7 provides an overview of how the organisation can approach the development
of its information requirements and how the information relates to the Asset Information
Model (AIM) PAS 1192:3 and the Project Information Model (PIM) PAS 1192:2.

38

undertake the on-going identification, assessment and control of


asset related risks;
comply with statutory and regulatory obligations.
develop an asset investment plan
Above are some organisation information requirements that might help to
inform corporate/organisation decisions.
These will be specific to each organisation. Organisations can have different
needs for information. Identifying the
OIRs will require input from various departments within the organisation. Input
will be needed in particular from the
people involved in the strategic decision
making associated with the asset portfolio and asset systems.

obtain/calculate asset replacement values;


undertake financial analysis of
planned income and expenditure;

39

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

Asset Information Requirements


The next step will be to identify what
pieces of information are needed to
inform each OIR. PAS 1192:3 refers
to these pieces of information as Asset Information Requirements (AIRs).
Asset Information Requirements are
the detailed pieces of information about
the asset that when placed in context
can answer the questions raised in the
Organisation Information Requirements.
An OIR might be answered by a single
piece of information but it usually requires an aggregation of several pieces
of information about an asset. Continuing with our example it requires the
replacement cost, the life expectancy
and the business criticality of an asset
to inform the asset investment plan.

Information from the Create/Acquire Activity


To prepare the content required to
answer an Organisation Information
Requirement will often require the collection, aggregation and manipulation
of multiple pieces of asset information
the Asset Information Requirements.
A lot of these pieces of information will
be drawn from the activities of dayto-day asset management (Create/
Acquire, Use, Maintain and Renew/
Dispose) and to identify the required
information will need a lot of input from
people engaged on those activities.
There will be many Asset Information
Requirements and the organisation will
need to recognise the time and resource commitment required to identify
every piece of data that is required.

Employers Information Requirements


If there is a decision to construct a new
asset the organisation will need to identify which of the AIRs will need to be
identified as part of the Employers Information Requirements (EIRs) for the

40

Sources of Asset Information

new construction contract. In our example of creating an asset investment plan


we might ask for the life expectancy
and replacement cost to be identified as
part of the EIRs.

Figure 8

Some Asset Information is provided from construction Project


Information Models at Handover and Close-out

In the case of major works such as a


new construction/refurbishment a new
Project Information Model will be created and will feed in data to the Asset
Information Model. In creating the
Employers Information Requirements
for a new create and acquire project the
organisation will use some of the Asset
Information Requirements. That information will be delivered by the design
and construction team as they progress

through work stages 0 to 6. The information will be a mix of graphical data,


non-graphical data and documents and
will ultimately need to be retained in a
data store (data) and a file store (documents).
The asset information will be provided
to the Employer/Organisation during
and at the end of the Handover and
Close-out work stage (6).

41

Newsletter, 42nd edition | July 15th 2014

Listed below are some typical Asset


Information Requirements that might
be delivered from a Project Information
Model (PIM) at Handover and Close-out
(A Project Information Model is generated using BIM during the Create/Acquire
activity)
descriptions of assets, their functions and the asset system they
serve
locations of assets, possibly
using spatial referencing or geographical information systems
engineering data, design parameters, and engineering drawings
vendor data (details of the organisation that supplied the asset)
operating instructions
maintenance instructions
fault finding instructions

www.bimtaskgroup.org

commissioning dates and data

Information from the Use and Maintain


Activities

health and safety files

Figure 9

commissioning instructions

regular statutory test requirements

Other Asset Information Requirements are then provided during


operation of the asset

working life expectancy


of each asset

These will be written into the Employers Information Requirements at the


beginning of the PAS 1192:2 process.
Identifying these information requirements will require a lot of input from
the people responsible for the Use,
Maintain and Renew/Dispose activities
associated with asset management.
Notice that in following the
OIR to develop an asset
investment plan we have
identified the first Asset
Information Requirement to
have the;Working life
expectancy of each asset

Over the long-term operation of the


asset a lot of the asset information that
is needed to inform the Organisation
Information Requirement will come
from activities such as inheriting an
asset, maintenance, transfer of ownership, minor works, breakdowns, major

42

works and end-of-life works. There


will be multiple activities under these
main headings and they are regarded
as triggers that will require an update
of the Asset Information Model. It has
already been stated that the triggers do
not often deliver information to coincide

43

Newsletter, 42nd edition | July 15th 2014

with the organisation decision points


and rules have to be established with
regard to the required currency of data
and in that regard how frequently documents, graphical data and non-graphical data will be updated and who will do
updates.
Listed below are some typical pieces of
Asset Information that might be provided during operation of the asset;
the condition and duty of assets
condition and performance targets or standards

historical record of planned and


unplanned maintenance tasks
performed
details of historical asset failures,
causes and consequences (if
known)
operational data including performance characteristics and design
limits
details of emergency plans
including responsibilities and
contact details

key performance indicators

financial data including, where


available the cost of historical
and planned future maintenance
tasks

asset related standards, processes and procedures

asset related contractual information

access planning and work schedules

details of ownership and maintenance demarcation where assets


interface across a system or
network of assets

details of tasks to be carried out


work instructions together with
diagrams and reporting requirements, legal obligations and safety/environmental considerations
task risk assessments and control measures
criteria of non-conformance and
the actions to be taken
when assets were last maintained/inspected and when these
tasks are next due
list of overdue/outstanding tasks

44

www.bimtaskgroup.org

identities and levels


of spares held, inter-changeability specifications and storage
locations
cost of replacing each
asset
details of asset dependencies and interdependencies
the criticality of each
asset to the organisation

unique identification for


each asset

AIRs in operational
supply chain contracts
The asset information above will have
to be gathered to update the model during the long-term asset operation. The
need for this information will be written
into the contracts that are made with
asset operators and asset maintainers
and will be identified as Asset Information Requirements. As mentioned previously they are specific to each organisation and will need to identified by the
whole asset management team.
Notice that in response to
the OIR to develop an asset
investment plan we have
identified further Asset Information Requirements;

tion that together can contribute to the Organisation


Information Requirement
of having an Asset Investment Plan. By being able
to extract these pieces of
up-to-date information from
the data store in the Asset
Information Model the organisation can employ proprietary report writing tools
to produce an asset investment plan.
Information about Life
Expectancy + Criticality +
Details of asset dependencies and interdependencies + Replacement Cost+
Unique Identifier can be
analysed to create an Asset Investment Plan.

cost of replacing each


asset
details of asset dependencies and interdependencies
the criticality of each
asset to the organisation
unique identification
for each asset
We have identified various
pieces of asset informa-

45

Newsletter, 42nd edition | July 15th 2014

Figure 10

Identifying the internal sources and multiple supply chain tiers that
provide asset information

www.bimtaskgroup.org

Information from Outsourced Information


Models and direct Supplier Inputs
These are sources of data and file
based information, and they include;
External Asset Information Models
that might exist as computerised
management systems used by
suppliers for example a computer
aided maintenance management
system
Direct Supplier Inputs which could
reflect digital surveys, performance
evaluation results, component replacements, minor works.

Figure 10 is used here to emphasise the complexity of sourcing required data from the
organisations own internal sources and the multiple tiers of its supply chain.

46

There may well be outsourced information models that will both receive and
issue data to the organisations Asset
Information Model. A Computer Aided
Facilities Management (CAFM) system
used by a Facility Management provider will be the source of much of the
asset information such as information
about access planning and work schedules, a list of overdue/outstanding tasks
and details of historical asset failures,
causes and consequences. The CAFM
system will also be supplied with much
of the detail provided through a construction/refurbishment project such as

engineering data, design parameters,


operating instructions and fault finding
instructions.
It should be remembered of course that
the organisation may elect to be entirely
dependent upon such outsourced information models as their source of information. In so doing they will assess the
risk and reward associated with relying
upon a contracted provider. They will
consider various factors; the provider
may not have an understanding of the
strategic objectives, the provider may
have a time limited contract, employing
the provider in this way may reduce the
in-house cost of data management, the
ownership of data has to be established
etc
Other asset information might be
exchanged to and from work that is
commissioned either internally or with
other supply chain providers and would
include such things as digital surveys,
performance evaluation, component
replacements and minor works. These
are referred to as Direct Supplier Inputs.

47

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

Information from Integrated Organisation


(Enterprise) systems
document management systems
work/programme planning and
scheduling systems
materials management systems
spares inventory systems
purchasing systems
decision support systems eg
maintenance optimisation, capital
expenditure planning, whole-life
costing models

Dependent upon their Organisation


Information Requirements and the data
needed to inform those requirement the
organisation may need to link with Enterprise Systems such as those shown
in the table above. Decisions about
this potential linkage will very much
depend upon the Organisation Information Requirements and the needs of the
Asset Information System.

A simplified Asset Information Model


Figure 11

A simplified Asset Information Model

asset utilisation systems


performance reporting systems
geographical information systems
(GIS) and spatial analysis toolkits
(for the analysis of GIS data)
asset possession/shutdown/outage planning systems
SCADA (Supervisory Control and
Data Acquisition Systems)
condition monitoring systems
automation systems
knowledge management systems
staff location, scheduling and
despatch systems

48

This diagram is used to simply illustrate the types of information exchange and the basic
components that might contribute to an Asset Information Model.

49

Newsletter, 42nd edition | July 15th 2014

Governance of the Asset Information


andthe Common Data Environment (CDE)
Figure 12

Governance: Project Information Model CDE

www.bimtaskgroup.org

An information model is only as good as


the accuracy and currency of the information that is stored within it. The concept of the common data environment
(CDE) was introduced in BS 1192:2007.
The process of governance introduced
in BS 1192 is critical to delivering the
value of an information model.
Information is treated as Work in Progress until it is given approval to be
labelled as Shared information and
becomes accessible to selected team

members. When the information has


been verified and validated to confirm
that it meets the requirements of the
EIR/AIR it can be identified as Published data within the data store and
file store and can be used for report
writing and exchange with external
systems. When it is considered appropriate the information can be labelled
as Archive material and the asset files
and history are retained for knowledge,
regulatory and legal requirements.

Modified from
BS1192:2007

50

51

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

Governance of the Asset Information Model

Figure 14

Asset Information Model: Governance Reporting

Figure 13

Governance: Asset Information Model (CDE)

Ongoing input and output


documents and data
shared with Asset
Management and
Maintenance Team

Survey, Performance
Evaluation and other input
documents & data subject
to validation and
acceptance

Co-ordinated & validated


output documents & data
published for management
reporting and input to
portfolio and other external
partners or systems.

Asset document & data


history maintained
for knowledge, regulatory
and legal requirements, and
for historic asset information
management & reporting.

From PAS 1192-3

Level 2 Files Validated & Veried


with RAG Repor8ng before
publishing as Files and Data

This diagram re-affirms the importance


of the digital tool required to verify that
the information required by the AIR has
been delivered. By introducing acceptable limits for each piece of data the
tool can also validate that the informa-

tion provided is of the correct order of


magnitude. The TSB BIM Project A
digital tool for building information modelling is to develop a verification and
validation tool.

BS 1192:2007 was written with the design and construction process in mind.
PAS 1192:3 adopts the concept of the CDE from BS 1192:2007 and this diagram refers
to some of the asset management information to which it might be applied.

52

53

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

Roles associated with the management of


an Asset Information Model
This section looks at the human side of
data/information management. There is
a requirement to have in place people
who will manage the governance on a
day to day basis. The responsibility for
the strategic use of data and the processes of governance will need to be
vested in a senior appointee whose role
will be to ensure that the data available
is to the agreed standards of accuracy
and currency and that report writing
tools are extracting the correct data
to deliver the organisation information
requirements and answer the business
questions of the organisation executive
team.
allocation of roles, responsibilities
and authorities for the origination,
generation, capture, maintenance,
retention, transmission, access to,
assurance, archiving and disposal of
items of information;

What might the Asset Information look like?


Figure 15

An Asset Information Model

requirements for the storage of


information items according to
integrity, security and confidentiality
requirements;
retrieval and distribution of information to designated parties as
required by agreed schedules or
defined circumstances;
requirements for the archival of
designated information, for example
for the purpose of retaining audit records and knowledge preservation;
requirements for the disposal of
obsolete, unreliable or unwanted
information in accordance with the
organizations requirements and
security and privacy requirements;

PAS55/ISO5500
Standards Compliant

Dened Organisa-onal
Informa-on Requirements

Integrated Informa-on
Repor-ng

Project Supply
Informa3on

Enterprise
System
Integra0on

Service Supply
Informa2on

Asset Informa-on Model

definition of the content, meaning,


formats and medium for the representation, retention, transmission
and retrieval for each information
item;
requirements for information maintenance, including version control
and assurance activities;
requirements for the generation,
capture or importing of the identified
items of information;

54

Figure 15 provides an overview of an


asset information model and how it relates to the asset management system.
It is essential to emphasise that this is a
very adaptable concept and that this diagram does not reflect what is required
by every organisation. For example
this model could represent information

about a single asset or about multiple


assets. Another option would be that in
using report writing tools an organisation might choose to draw information
from just the published data or it might
choose to also draw upon information
from integrated enterprise systems.

55

Newsletter, 42nd edition | July 15th 2014

The model may be owned and managed by the organisation as their own
asset information model or they might
choose to apply the approach through
their supply chain provider of operation/
maintenance.
When the OIR/AIR (and any EIR) have
been identified and the structure and
use of the Asset Information Model has
been agreed the organisation will have
a functional brief which they can take
to their IT provider(s) so that they can
develop the model.

www.bimtaskgroup.org

A recognised classification system will


be essential to enable accurate data
extraction from the data/file store. The
TSB BIM Project A digital tool for
building information modelling is to
develop a classification system.
The needs of report writing will especially need to be reviewed to ensure
that any proprietary report writing tools
extract and aggregate the appropriate
data.

Conclusion
It is hoped that the guidance in PAS
1192 Part 3 will assist organisations
in considering the thought processes
and activities associated with establishing a digital Asset Information Model.
Starting with the need to identify costs
and benefits the document illustrates
the stages of identifying Organisation
Information Requirements and Asset
Information Requirements for asset
operation. It also introduces the need
to identify selected Asset Information
Requirements that will be identified as
Employers Information Requirements in
the event that a new asset construction
project is undertaken in keeping with

the principles of PAS 1192 Part 2. Finally the guidance looks at governance
and the principles of the Common Data
Environment before indicating what an
Asset Information Model might look like.
Adopting the guidance can place a
management team in a position whereby they can clearly specify their requirements to software developers.
The guidance is probably most useful to
those who wish to have an understanding of asset information management
without understanding the technical
detail about how the information is
made available to support management
decisions.

Acknowledgement to BSI Standards Ltd


and Mervyn Richards
for supporting illustrations

Rob Manning was the sponsor representative for the development of PAS 1192
Part 3. He developed the brief for the technical author, advised on steering group
contributors and signed off the publication.
The technical authors David Churcher, John Sands and Jo Harris from BSRIA
worked closely with Rob
and his BIM Task Group colleague Graeme Tappenden.
Significant and considerable contributions on both asset management and facility
management were
received from the steering group members
acknowledged in the published document.

56

57

BS1192-4:2014 COBie

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

BS 1192- 4 - Collaborative
production of information - Part 4:
Fulfilling employers information
exchange requirements using
COBie
by: Nick Nisbet
AEC3 UK Ltd Owner

COBie (Construction Operations Building information exchange) is a standard format for sharing facilities information. It is designed to ensure that the client gets all the
information needed to own and operate the facility in a reliable form.
Informally one can think of COBie as a
well-appointed suitcase that allows us
to move information from the project
team across to the client team. The
sides of our suit case are transparent:
anyone can see the what is and isnt
yet included: we see slots for all our
essentials and lots of free space for our
loose items.
So what are the essentials: its the project, site and the facility itself, the list of
visit-able spaces and locations (forget

58

the cupboards), and a list of the manageable components (forget the reinforcement). These spaces are grouped
into floors and locations, and into zones
such as occupancy and activities. The
components are organised by their
specification (type) and by their functions (systems). Each of these needs
a name, description and classification,
and a note of who and when they were
added.
These can then be supplemented with

additional loose items such as attributes, document references, contact


details, maintenance instructions, and
cost and carbon impacts.
The COBie for all working group has
run through a series of infrastructure
scenarios, from simple stations through
detailed track and motorway handover
right up to progressive handover of a
whole new line. We have found that the
COBie can do the job: in fact
COBie helped resolve some of the
casual ambiguities that creep into conventional practice. Some specifics such
as the use of Linear Referencing Meth-

ods, turned out to be not so different


to building practice such as the use of
grids in large spaces.
But the importance of COBie lies in
its efficiency: neither the client nor the
designers/contractors need waste time
designing suitcases but instead can
focus packing the correct information. If
you want a packing list, then the Employers Information Requirements (EIR)
and the forthcoming digital Plan of Work
(dPoW) will give the detail. But given
the base asset register, the content of
COBie is driven by real purposes such
as using or maintaining or operating or
monitoring or repurposing the facility.

59

Newsletter, 42nd edition | July 15th 2014

Like any good suitcase, you dont


always have to fill it all at once: COBie
has proved invaluable for client briefing
and schedules of accommodation, later
it can contain the Room (and Zone)
Data Sheets (RDS). As a progress
report, COBie can be used to convey
to and from the client the state of his
facility. Product manufacturers often

www.bimtaskgroup.org

offer COBie in preference over proprietary 3D objects, especially if their products are less likely to be modelled or
selected in early stages . So although
COBies primary purpose is to deliver
handover information, it can offer the
whole UK facilities industry a step into
a world of containerised information
transport.

It is a required deliverable by 2016 in


central government projects where information must flow into portfolio, asset
planning and facility maintenance tools.
Already private clients are seeing the
same value. Applications such as Revit,
Xbim, Solibri and AEC3 are offering
tools that help the supply side. Suggestions for generating, comparing and
checking COBie are openly available
(www.bimtaksgroup.org/labs). On the
receiving side UK CAFM tools are now
catching up with US applications and
offering COBie support.
Is COBie too difficult (like long-division
as one critic claimed)? Hopefully not for
a mature and accurate industry moving
into a data-rich era. Use a calculator!
Is it too simple (IFC-lite) ? COBie
is 100% convertible with IFC and is
entirely usable on every computer and
smart device, so it is likely to be around
for a while yet.
Where can one learn to speak
COBie? There are a number of 10-minute movies on YouTube (search COBie
east). Theres lots of free examples on
the buildingSMART Alliance and BIM
task group websites (search
COBie-UK-2012) and shortly there will
be the full British Standard:
Last November a working group of the
BSI construction information committee began collarating on a standard
description of the UK use of COBie.

60

The outcome is named BS 1192-4


- Collaborative production of information - Part 4: Fulfilling employers
information exchange requirements
using COBie Code of practice and
the draft for public comment has been
available since the end of May for review and comment. It will remain open
till the end of July, when the group will
reconvene to assess the feedback and
make any final adjustments.
Anyone familiar with the earlier
COBie-UK-2012, and the training
material available on YouTube will recognise the core content. But have we
succeeded in introducing the ideas behind COBie and making them relevant
to both buildings and infrastructure, and
both new and existing assets? Have
we struck the right balance between
prescriptive requirements and the use
of EIR (Employers Information Requirements)? Have we kept the door open
wide enough for the forthcoming digital
Plan of Works ?
If you want a sneak preview, and want
to check it over, go to http://drafts.
bsigroup.com [LINK}
and search for BS1192 or click
through to http://drafts.bsigroup.com/
Home/Details/53020 [LINK] . We currently rank as the second most popular
draft, could you help push us into the
number one slot (and improve the document at the same time)?

61

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

The publication of BS1192-4:2014 will be a key milestone


in the Level 2 BIM programme forming one the key seven artefacts
that underpins this stage of maturity.
COBie UK provides us with a consistent and verifiable means
of sharing and transporting structured information
across the asset life-cycle it also supports our digital queries
and transactions with early interim data deliveries being used
to monitor the business case for the facility or infrastructure
and to help plan for taking ownership.
Beyond delivery from a use case perspective the completed COBie file
supports the management of the asset and provides a vehicle
to take data
created during the project information modelling
into the Computer Assisted Facilities Management (CAFM) system.
The BIM Task Group would like to take this opportunity to thank
all those involved in the creation of the standard
including BSI, The COBie4All working group and especially Nick Nisbet

62

- David Philp, BIM Task Group

63

CIBSE BIM SURVEY

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

The 3rd Annual CIBSE


BIM Survey
by: Prof Tim Dwyer
University College London (UCL)
The 3rd annual CIBSE BIM Steering Group encourages participants from all aspects of the building process to reflect
on their experiences of BIM through a survey throughout
June, July and August, 2015 at http://bit.ly/CIBSEBIM2014.

This is aimed both at the aspiring, as


well as the experienced, BIM user so
that the results can help lead the development of protocols, tools, applications,
education and training by CIBSE and
the wider construction and software
world to ensure that the deployment of
BIM truly improves the building process.
Previous surveys have indicated that
the building services profession is
already more active in employing the
richer features of BIM than others
in the construction process but have
identified clear areas of need for the
whole industry. Earlier surveys, including those by BIM4FM and the CIBSE
FM Group indicated that majority of
FMs, owners and occupiers see that
BIM will become increasingly important

64

in day-to-day working practices in the


near future. And so in the new survey
respondents will find questions that are
specifically aimed at discovering aspects of BIM application that are relevant to post-occupation building operation and maintenance.

classification system to enable widespread adoption of Level 2 BIM across


the built environment. This is one of 3
TSB projects across the sector that is
assessing opportunities for accessible
BIM tools.
The inter-institutional website
www.BIMTalk.co.uk is also a tangible
output of the work of CIBSE and other
institutions that resulted from the demands voiced in previous surveys - it
provides a non-commercial resource
for those who wish to learn more about
BIM.
One of the challenges identified by the
surveys has been for designers and
operators to obtain reliable product data
that can quickly be incorporated into
BIM environments. CIBSE have led an
initiative to develop the Product Data
Templates (PDTs) that allow manufacturers to make their product information

readily available, with relative simplicity


in a spreadsheet format, that can then
be used by many potential users in their
BIM models.
The survey results will be published in
the autumn on www.BIMTalk.co.uk
and in the CIBSE Journal.

The call from previous surveys for


co-ordinated industry wide activity has
seen some movement in recent months
with the early stage Technology Strategy Board (TSB) projects that are developing a digital tool for building information modelling. CIBSE are co-ordinating
the C8 collaboration of APM, BIFM,
CIBSE, CIOB, ICE, IStructE, RIBA and
RICS to investigate the development of
id3 (eye-dee-cubed) - a web-based tool
to deliver the digital Plan of Work and

65

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

Overview of CIBSE BIM Survey 2013 findings

A c k n o w l e d g e m e n t t o B I M Ta l k w e b s i t e [ L I N K ] f o r s u p p o r t i n g i l l u s t r a t i o n s

66

67

Construction News Supplement

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

This is a reprint of Construction News, full supplement can be found on BIM Task Group website [LINK]

Make the next


INTRODUCTION
From new horizons for QS firms
to FM cost benefits to European
conformity, the opportunities are
there if you know where to look.
It has been just over three years
since the government published
its construction strategy, which
can be credited as a major driver
of BIM adoption having set a
deadline for public sector projects
to hit Level 2 from 2016 onwards.
While government was keen to
use it to cut the cost of building
and running its estate, having such
a huge client mandate its use
meant BIM was bound to spread.
The Royal Institution of

CONTENTS
Page 4
RICS on why BIM should be seen as
an opportunity rather than a threat
to the role of the quantity surveyor

Page 8
Bam FM has been finding out just
how beneficial the technology can
be for facilities management firms

Page 12
Bentley Systems on why there is
still one area of infrastructure that
remains untapped for Level 2 BIM

Page 16
How Atkins has been able to roll out
Level 1 consistently and effectively
across a diverse and global business

Editor Damon Schnmann


Editorial Chloe Stothart
Production Andy Rennison

cnplus.co.uk/special-reports

68

step

Chartered Surveyors survey at its


latest BIM conference showed
relatively small growth in the
number of delegates who had
worked on a BIM project in the
past year compared with the poll
at the 2013 event (see p4). But a
significant number believed it
was imperative to invest in BIM
technology in the next 12 months.
Director of built environment
Alan Muse says the recession may
have slowed uptake but that firms
should invest in it now to improve
efficiency as conditions improve.
He also describes the impact of
the BIM-induced changes that
quantity surveyors will face once
the industry advances to Level 3.
While some have feared that
automated cost generation in BIM
will reduce the role of the QS and
force them to cut their fees, he
sees opportunities for new,
valuable areas of work.
Another aspect lauded by
advocates but relatively untested
is BIM's use in aiding FM. Bam FM
decided to discover the costs and
benefits for itself by using BIM to
manage and maintain a school
(see p8). The results point to the
potential to cut costs, particularly
in buildings run under private
finance initiative deals.
New BIM frontiers are also clear
in plans to make it work better for
roads, rail and energy. COBie, the
data transfer mechanism which
features in the UK governments
BIM standards and others, works
well for buildings at present, but
less so for linear infrastructure

infrastructure that goes from one


place to another, such as a road.
A group within the UK BIM
Task Group is tweaking COBie to
make it suitable for all sorts of
projects (see p12).
Another fresh avenue for BIM
use is being explored by Atkins,
which has reached Level 1
worldwide unusual for such a
large company (see p16). It was
exploring this standard before the
UK government created a
mandate. Among lessons learned
was that introducing BIM is like

New frontiers are


clear in plans to
make BIM work
better for roads,
rail and energy
making any other major business
change: it is about planning and
getting people to embrace it,
rather than simply technology.
Taking BIM beyond national
borders is not confined to big firms.
Several European countries have
got together informally to share
BIM knowledge (see right). Getting
nations using BIM in as consistent
a fashion as possible should make
it easier for contractors to bid for
work across the continent.
While discussions are at an
early stage, perhaps this could be
the opening of new frontiers for
the firms at the BIM vanguard.

Continent seeks
collaboration to
broaden BIM use
INTERNATIONAL
A group of European countries is
exploring potential collaboration
to introduce BIM more widely in
public works across the continent.
Public clients from 15 states
Austria, Denmark, Estonia,
Finland, France, Germany, Iceland,
Ireland, Italy, Netherlands,
Norway, Portugal, Slovakia,
Sweden and the UK want to
share their knowledge about BIM.
The countries are looking at
ways to improve consistency
between states while allowing for
local flexibility. Greater consistency
in standards and getting more
countries using it would also be of
benefit to contractors.
UK BIM Task Group head of EU
and international relations Adam
Matthews says the EU BIM
working group is exploring the
possible working together for the
wider introduction of BIM into
Europes public works projects
and that it was early days for the
group, with no firm commitments.
The talks follow two EU BIM
conferences and the introduction
of BIM to the European Public
Procurement Directive, which
will encourage BIM in European
public projects. The directive
will be implemented across all
28 member states by mid-2016.
BIM Supplement 2014 | 3

69

Q&A WITH BIM DOCTOR

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

This is a reprint of Q&A session with BIM doctor, Sarah Davidson, on June 11th, publish on www.building.co.uk website

For full transcript visit www.building.co.uk [LINK]

70

71

ANNOUNCEMENTS

Newsletter, 42nd edition | July 15th 2014

www.bimtaskgroup.org

ICE BIM for Infrastructure - A new training course


that embeds the Governments Learning Outcomes
Framework
Developed and reviewed by members of the BIM Action Group
of the Institution of Civil Engineers (ICE), this training course
takes the delegate through each aspect of BIM: data, application, contractual and insurance.

Why attend?
Embeds the Governments Learning
Outcomes Framework
Demystifies BIM, allowing you to
understand the challenges and benefits of implementing BIM across the
project portfolio
Delivers clarity on how to integrate
and apply BIM to engineering, design, construction and asset management
Includes questionnaires following
each session to test your learning
and align with the objectives of the
programme

What will you learn during the programme?


Through a combination of specialised
tuition, facilitated workshops and group
exercises, this two day programme will
address in detail:
The power of BIM over the whole life
cycle of assets, across the portfolio
How BIM successfully integrates the
built environment both buildings
and infrastructure

72

How the BIM phenomenon fits into


the delivery of engineering, design,
construction and asset management
in practice
The impacts and benefits of BIM to
the engineering profession and to
the built environment
The practical steps of implementing
BIM

Who is this programme intended for?


This programme is ideal for all those
looking to consolidate their learning and
refresh their knowledge of BIM, in order
to align with the Governments Learning
Outcomes Framework. Delegates will
include:




Senior Management
Project Managers / Project Directors
Engineers
Technicians
Graduates / Apprentices

Tutors

Anne Kemp

Philip Jackson

Anne is Director
of Strategy and
Development for
Atkins Limited
and Chair of the
ICE BIM Action
Group. She also
has responsibility for BIM Strategy and Development
across the UK.

Phil is a core
member of the
BIM Task Group
and Chair of the
ICE Information
Systems Panel.
He is an acknowledged leader in
the deployment of information technology in infrastructure design, construction
and operational management.

BSc (Hons), CEng, FICE, FRSA

BSc, PHD, FRICS, FRGS

Anne is currently advising the BIM


Strategy at Eight20 (at the Thames Water Alliance) and has just completed her
term serving on the UK BIM Task Group
as a Delivery Officer for Highways
Agency and Environment Agency.

Whilst he is a Civil Engineer by training,


his background and experience has
encompassed most aspects of the construction industry from buildings through
infrastructure to asset management.

Availability and pricing


All public sector employees are entitled to a 10%

discount* on the full course fee:

Normal fee: 645 per delegate for the full 2 day programme
Discounted fee: 580.50 per delegate for the full 2 day programme
- Includes supplementary learning material
- Excludes VAT
Dates for 2014 are now available and can be found here: [LINK]
For enquiries, contact:
e: Jessica.necchi@thomastelford.com
p:+44(0)20 7665 2498

*How to claim your discount and discount terms:


Register online or contact us directly using the details above and quote promotional
code PUBSEC14
The discount code can be used once per delegate
Offer applies to bookings onto 2014 classroom courses only. Expiry 19/10/2014

73

ANNOUNCEMENTS

Newsletter, 42nd edition | July 15th 2014

South West BIM Hub networking event


On a very sunny 12th June the South West Bim Hub hosted
a networking event jointly with the Association of Women in
P r o p e r t y.

www.bimtaskgroup.org

Hub Events
SOUTH WEST

South West Hub Events

This was a well received event with a mix of 40 construction


and property professionals who enjoyed a light BIM chat with
their glass of Pimms.
Their next social will be BIM on a boat.

PIMMS photos of Elizabeth Kavanagh


(SW BIM Hub champion)
and Rachel Bell

74

75

YOUR
CONTRIBUTION

W e r e

L i s t e n i n g !

Wed love to hear from


you. To help us tailor
the newsletter content
for you let us tell your
BIM story, hear your suggestions for articles, your
forthcoming events, pictures or indeed any feedback or questions on the
programme.
Additionally dont forget our blog section on the task
group website; we would be delighted to receive your
contribution.
Contact us info@bimtaskgroup.org
Monika Orzeszak, Deputy Editor

Вам также может понравиться