TURNOVER
GUIDE
HELPDESK
Most of us are new to ClearVision, if you have questions, do not hesitate to call your field coordinator or
turnover coordinator for assistance. If they do not satisfactorily answer your question contact the
ClearVision Helpdesk at clearvisionsupport@clearwire.com NOTE: Patience must be taken when using
ClearVision. Wait for every Loading screen to clear before clicking anything on the screen.
INTRODUCTION
This document is intended to outline the process of turning over all documentation necessary for a general
contractor to claim a Construction Complete and receive a Site Acceptance from Clearwire. This
document is meant as a guide and not a contract document.
NAMING CONVENTIONS USED IN THIS GUIDE
<SiteID>
<Sector>
<ColorCode>
<Band>
<x>
The color code for that line R=Red (alpha), B-Blue (beta), Y=Yellow (gamma)
(i.e. R1 refers to the first line in Alpha)
Either TX or RX dependant on the band being swept
Picture number- in many cases you will have more than one image per image type
so you should use the same naming convention for the picture type but change the
picture number.
MPLS Complete
For a general contractor to claim MPLS Complete the following will be required:
Civil Complete
AC meter hot
T1 delivered
POTS line delivered
All MSP Deliverables must be uploaded within 24 hours after Civil completed and AC meter set.
MPLS cannot be claimed until the following have been uploaded into CV:
MPLS Checklist uploaded
MPLS Zip File uploaded into CV
Turnover Expectations
It is REQUIRED that a Turnover Coordinator be appointed by all GCs to coordinate all turnover
functions
If delays occur to meet the turnover deadlines, this will lead to payment delays and
potentially work removed from scope
Payments WILL be delayed for the following:
Missing forms or incorrect or missing photos
Incorrect naming convention
Missed deadlines
C: M7 NTP (MS093)
DO NOTHING WITH THIS FIELD. THE NTP WILL ALREADY BE
POSTED
C: M7 Signed Permit Card ( Due at MS160)
Post a signed copy of the building/electric permit card in this field.
Required for all sites.
NAMING CONVENTION: <SiteID>-SIGNED_PERMIT_CARD.PDF
C: M7 Construction Punchlist
GENERAL CONTRACTOR RESPONCIBLITY
FC to complete document and provided to GC to sign off and post
the completed
CONSTRUCTION_QUALITY_CONTROL_CHECKLIST.XLSX
Construction Punchlist Tab in this field. Required for all sites
NAMING CONVENTION: <SiteID>CONSTRUCTION_PUNCHLIST
PDF
C: M7 Tape Drop Form (Due at MS130)
Post the completed TAPE_DROP_FORM.PDF file in this field.
Required for all sites. NOTE: Towers require only one sector
column be filled out if all of the RAD centers are the same.
NAMING CONVENTION: <SiteID>-TAPE DROP.PDF
C: M7 Power Order Form
Post the completed Power Order Form in this field. Also send email notification to utilities@clearwire.com. Required for all nonsub-metered sites
NAMING CONVENTION: <SiteID>-POWER_ORDER_FORM.PDF
C: M7 Sweep Tests (Due at MS130)
Required for all sites. See Preparing Sweeps for Upload below.
NAMING CONVENTION: <SiteID-A>-SWEEPS.PDF
After logging into ClearVision, position pointer on the Information dropdown, click RDE
Forms-Sites
Click the
box opposite the document / test you want to upload.
The File Select dialog box will open, select file and click Open .
File will appear in selected field window
Click Apply (bottom right hand corner, just below Fields window).
Upload complete
NOTE: There is a dash - between <SiteID> and the name of the form for all of the
files listed below.
Unless otherwise stated, responsibility for posting the following documents lies with the
Contractor performing the work.
Rename images to correspond to the Naming Convention column in the table below.
If applicable, resize images to 1024x768 (no smaller pictures will be accepted (i.e. most
camera phone pics are too small)). Please see the Resizing Digital Images for an
explanation of how to easily resize digital images.
Zip file all photos into photo logs as show below:
<SiteID> - MPLS.zip
<SiteID> - CIVIL.zip
<SiteID> - RF.zip
Punch Items that are corrected shall also be documented through images. Zip file all
punch photos into photo logs as show below:
<SiteID> - PUNCH.zip
No zip file should exceed 3MB. If you need to make multiple photo logs for a package,
use a, b, c
M7-<SiteID> - CIVIL A.zip
M7-<SiteID> - CIVIL B.zip
Always remember, when in doubt take a picture. If there is pre-existing damage on site.
Notify your field coordinator and take pictures of the affected area.
Civil Zip
Civil Zip
NOTE: The images below are examples ONLY. They are not meant to be the perfect picture. My
comments appear to the left in red.
Example Photos
<SiteID> T1 Cable(#)
No Picture
Available
Civil Zip
Civil Zip
Civil Zip
Civil Zip
RF Zip
Example Photos
RF Zip
RF Zip
RF Zip
RF Zip
RF Zip
RF Zip
RF Zip
RF Zip
RF Zip
RF Zip
RF Zip
RF Zip
RF Zip
10.<left click>
11.<left click>
to exit.
The System Sweep Submission form v1.0 will display the result of a system sweep based on the
markers entered and give you a pass or fail based on the results. If you should have a line that is
failing you are call your field coordinator (FC) and begin to troubleshoot the issue with the FCs
guidance. Criteria for pass/fails are as follows:
Required Sweeps
At a minimum the following sweeps test will be required for each site constructed.
RF Antenna Sweeps
Sweep Labeling
XXXXXXX_X_MAIN1_RL_Antenna_only
XXXXXXX _X_ MAIN1_DTF_Load
XXXXXXX _X_ MAIN1_DTF_Short
XXXXXXX _X_ MAIN1_RL_Load (If main cable run is used)
XXXXXXX _X_ MAIN1_IL_Short
XXXXXXX _ X_MAIN1_System_RL_Antenna
XXXXXXX _X_DIV1_RL_Antenna_only
XXXXXXX _ X_DIV1_DTF_Load
XXXXXXX _ X_DIV1_DTF_Short
XXXXXXX _ X_DIV1_RL_Load (If main cable run is used)
XXXXXXX _ X_DIV1_IL_Short
XXXXXXX _ X_DIV1_System_RL_Antenna
XXXXXXX _X_MAIN2_RL_Antenna_only (3rd and 4th port)
XXXXXXX _X_DIV2_RL_Antenna_only (3rd and 4th port)
RF System Sweeps
VERTICAL AXIS
TOTAL SYSTEM
LIMIT LINE
SWEEP TITLE /
SAVE AS
2500-2700
M1 Peak
M2 Valley
M3 2630.5 MHZ (W07)
M4 2650.5 MHZ (W09)
M5 2683.5 MHZ (W12)
Auto Scale
Coax into the RF antenna
-15.5
<SiteID>-<ColorCode>_RS
Coax Jumpers
With LOAD
Return Loss limit set to -22dB
DTF with limit set to -30dB
Limit for connector portion = -30dB and Limit for cable portion = -45dB
Please adjust to autoscale if connectors are not visible in the plot. Otherwise
use 517 resolution.
DTF lengths should be 115% of actual jumper length
Example 6ft jumper should be 0ft to 7ft
With SHORT
DTF M1
IL (RL mode on equipment test)
GPS SYSTEM
1545-1600
120% of line length
M1 to peak of connector
M2 to peak of main line
Auto Scale
Surge arrestor, coax into a 50ohm load
-30
GPS_<SiteID>_DL
VERTICAL AXIS
TOTAL SYSTEM
LIMIT LINE
SWEEP TITLE /
SAVE AS
1545-1600
M1 to peak between M3 and M4
M2 to valley between M3 and M4
M3 = 1570
M4 = 1580
Auto Scale
Surge arrestor, coax into a short
None
GPS_<SiteID>_IS
1545-1600
120% of line length
M1 to peak
Auto Scale
Surge arrestor, coax into a short
None
GPS_<SiteID>_DS
All required files to be zipped into a single package and posted to M7 Sweep Test
.ZIP file format only
Files to Include in the ZIP Package
Anritsu Data files
Sweep Submission Form Named
<SiteID> Sweep Submission.xlsx
A Single PDF file that has all the sweeps loaded together named
<SiteID>_aswp.pdf
Package ZIP File to be named
<SiteID> - Sweeps.zip
Post completed ZIP-file to MS7 documents
After logging into Clearvision, position pointer on Information, left click RDE FormsSites
Digital Images
Prepare digital photos for upload as detailed above and post the
resulting ZIP files under Electronic Files in ClearVision.
NAMING CONVENTION: See details for preparing digital images
for upload above
Final Acceptance
Post a completed copy of FINAL_CLOSEOUT_FORM.PDF file
NAMING CONVENTION: <SiteID>-FINAL_CLOSEOUT_FORM.PDF
BLANK
DOCUMENTS
PLEASE NOTE, IF YOU ARE USING AN OLD VERSION OF A DOCUMENT THAT
DOES NOT APPEAR IN THIS SECTION IT WILL BE REJECTED