Вы находитесь на странице: 1из 6

SLEDs/PLETs

FMC offers a complete range of sled systems including PLETs (Pipeline End Terminations), PLEMs (Pipeline End
Manifolds) and In-line Sleds to meet virtually all manifold project requirements. Sled designs include options
for first-end, second-end or midline installations from vessels with J-lay, S-lay or reeled capabilities. In
addition, sleds range in complexity from a single hub with manual isolation valve to multiple hubs with
actuated valves, chemical injection, pig launching capabilities and more.

Single and Dual Flowlines


Insulated / Non-Insulated
Multiple Hubs
Piggable
Thermal Expansion Capability
Skirted / Piled

Diverless technique adapted for


deepwater repairs, future tie-ins
09/01/2012

Email
Print

0
Facebook

0
Twitter

0
LinkedIn

0
Share

Grip and Seal rectifies GoM hurricane damage


Edgar Keijser
Gerald Douglas
Oil States Industries
Virtually all deepwater field developments depend upon pipelines. Failure of a pipeline due to corrosion, defect, or an
external event can lead to loss of production and, in the worst case, pollution.
Pipelines can fail for a variety of reasons, and the type and extent of damage and water depth in which this occurs will
define the manner in which the repair can be handled.

ROV-installed clamp.
Isolated pipeline damage is characterized by a small hole or crack and is most often a result of localized corrosion; a
defect in a pipeline weld that went undetected during installation; a metallurgical defect; or impact from a dropped item.
In general, a clamp that firmly encapsulates the pipeline and provides a reliable seal around the damaged area should be
adequate for the repair.
Extensive pipeline damage can result from an unfortunate incident during pipelay operations or an event during the life of
a field for instance dragging of anchors, mudslides, upheaval buckling, or pipe walking. In most cases, the pipeline
cannot be lifted back to the surface, and the damaged pipeline section has to be removed and replaced subsea with an "on
bottom" repair spool piece.

Diverless connector deployed.


Localized pipeline corrosion can be repaired by installing a high-integrity pressure vessel around the pipe at the damaged
location. Typically this is accomplished using a Grip and Seal split-sleeve type clamp whereby two clamp halves are
joined together by studs and nuts. These clamps incorporate tension bowls and slips that grip the pipe at both ends of the
clamp, transferring the thrust loads through the clamp body. The slips ensure a smooth circumferential distributed load on
the pipeline.
Longitudinal face seals and circumferential seals (typically made from purpose-built elastomeric materials) are energized
by the studs to ensure a perfect seal around the damaged area. In shallow waters, over 3,000 split sleeve clamps have been
installed worldwide, in diameters ranging from 3-48 in. (7.6 cm--1.2 m), and pressure ratings from ANSI 600 to API
10,000. Several of these clamps have been in service for over 25 years.

Dual Grip and Seal connector showing the "grips" and seals at each side of the
connector.
To repair pipelines in deepwater, ROV-installable and operable versions of split-sleeve type clamps have been developed.
Alignment saddles are normally incorporated for landing and positioning of the clamp on the pipeline. The design of the
body bolts allows for tightening by a standard work-class ROV using a low torque or impact-type wrench, or integrated
hydraulic stud tensioners. Following activation by the ROV of the hydraulic pressure, the connector mechanically locks so
that hydraulic pressure does not have to be maintained. Standard diverless Grip and Seal type split-sleeve clamps have

been manufactured for pipe sizes from 8-44 in. (20.3 cm--1.12 m) OD and ratings of ANSI 900 to 2500, and have been
installed in water depths up to 7,000 ft (2,133 m).
When a pipeline is damaged severely and or deformed over a certain length, the affected section must be removed and
replaced. If the pipeline cannot be lifted back to the surface, an "on bottom" pipeline repair has to be performed. A spool
piece repair (pipe replacement) necessitates cutting of the pipeline in order to remove the damaged section, with the
replacement section connected to the pipeline on the seafloor. While hyperbaric welding can be used to connect the spool
piece directly to the pipe in shallow water within the range of diver operations, this technique can be extremely costly.

Horizontal piggable midline tie-in sled.


Where it is economically viable to use divers, a bolted flanged connection method is generally employed. After the
damaged pipeline section has been cut and removed, a standard flange is attached to each pipeline end in order to connect
the repair spool piece to the pipeline. For a permanent connection, Grip and Seal connectors are most often used to
structurally attach to and seal against the outside of the existing pipe. Wedge-shaped slip segments, positioned radially
inside the body of the connector, are most commonly applied to attach the connector to the pipeline and are often self
energizing; the higher the tension or compression force, the tighter the grip on the pipeline.
The sealing system generally consists of one or two stacks of circumferential elastomeric packers. When axially
compressed by the bolts, the elastomeric packer flows radially inward against the pipe OD and outwardly against the
connector body. To facilitate subsea installation, end-gap adjustments (up to one pipe diameter) can be incorporated in
connectors. This provides flexibility in positioning of the repair spool piece prior to fixing the connector on the pipeline.
When the damaged pipeline section is removed, divers will stab the end connectors over each pipe end. When spool piece
metrology has been performed, the repair spool piece can be fabricated and lowered subsea. Divers will position the repair
spool piece and bolt each spool piece flange to the mechanical connector flange. Finally, the pipeline end connector bolts
are actuated to Grip and Seal on the pipe end. Thousands of these mechanical pipe end connectors have been installed by
divers, on new construction projects and for pipeline repairs, in sizes ranging from 2--48 in. (5 cm1.22 m), and a wide
variety of pressure ratings.
Deepwater pipelines are now routinely tied in and connected subsea using ROVs and remotely operated pipeline
connection systems. Diverless mechanical pipeline connectors are most frequently used to tie in new spool pieces. The
mechanical connector system comprises a male hub connection structure on which the female hub connector assembly is
connected. For a deepwater on-bottom repair, where the damaged pipeline section has to be cut and removed, the
challenge is to attach a male hub connection structure to each pipeline end in order to install and connect the repair spool
piece subsea.
Following a survey of the damaged section of the pipeline, the pipeline is raised using the diverless pipe lift frames, after
which the damaged section is cut out and removed. The diverless Grip and Seal connector with the male hub connection
structure is deployed using a temporary installation (gantry) frame and fitted on a support frame. The support base plate
provides stability and is equipped with mud mats to allow for soft seabed conditions.
The temporary installation (gantry) frame is operated by the ROV and used to stab the connector over the pipeline end.
After installation and testing of the connector, the pipeline is laid back on the seabed using the diverless pipeline lift frame
and the pipeline end connector fixed in the cradle on the support frame. The temporary lift frame is then removed and the
operation repeated for the other pipeline end. The repair spool piece can now be measured, fabricated, and shipped to site
and installed in line with normal installation procedures, following which the repair is complete.
Various iterations of the systems described above have been designed and fabricated for operators in the Gulf of Mexico.
All the systems went through various phases of testing prior to acceptance by the clients and stored onshore, ready for use
when required. Following damage caused by the Katrina and Rita hurricanes, systems were deployed for repairs of Shell's
Mars and Entreprise's Typhoon pipelines.

Further design advances led to the development of a second generation system ideally suited to situations where the repair
spool piece is relatively short, and where the seabed is sufficiently flat. More importantly, the amount of steel work left on
the seabed after the repair is greatly reduced.
The (single) diverless Grip and Seal connector is modified to form a dual Grip and Seal connector whereby the end of the
repair spool piece and the pipeline end are contained within one connector housing. A dual Grip and Seal connector is
fitted to each end of the repair spool pieces and equipped with an ROV-operable telescopic action. When the repair spool
piece is positioned on the seabed and aligned with the pipeline ends via the diverless pipeline lift frames, the connector is
stabbed over the pipeline end using the telescopic device, allowing the connector to Grip and Seal around both the
pipeline end and spool piece end. Dual Grip and Seal connectors have been manufactured for various oil companies in
sizes ranging from 6 to 24-in. (15.2-61 cm). They were selected for Total's Girassol 12-in. (30.5-cm) diverless pipeline
repair in deepwater Angolan block 17, performed at the end of 2009.
The most effective and economical method of adapting deepwater pipelines to allow for future subsea tie-ins involves use
of "midline tie-in sleds" modular units that consist of flowline piping; a connection structure for a future diverless
pipeline connection; a block valve to isolate the future tie-in line; a piggable Y fitting to combine the trunkline with the
future tie-in line; and mud mats.
The sled is welded into the pipeline like an ordinary joint of pipe and is designed to be easily installed via S-lay or J-lay.
In a later stage, the new pipeline is installed close to the existing pipeline and the new tie-in is performed using a jumper,
fitted with standard diverless pipeline connectors, and connected to the midline tie-in sled at one end on the existing
pipeline and the pipeline end termination (PLET) of the new line.
A pipeline network is generally designed upfront with midline tie-in sleds built in to the pipeline system and installed
during the pipelay operations, to facilitate connection of future pipelines into the existing pipeline network. However,
during the Mars pipeline repairs, Shell took the opportunity to fit out the repair spoolpiece with a future tie-in hub. The
same applies for the Typhoon repair where a future tie-in point was incorporated in the repair connection structure.
Shell's Perdido field is in the Alaminos Canyon block 857 in the Gulf of Mexico, in 7,800 ft (2,377 m) of water. The field
is in an area with little export infrastructure: to install an export line all the way to shore would be extremely costly and a
major challenge due to the difficult seabed conditions. The closest existing offtake system was the ExxonMobil Hoover
Offshore Oil Pipeline System (HOOPs). Shell obtained approval from ExxonMobil to tie the Perdido export pipeline into
HOOPS, even though there was no connection link available in the HOOPS line, and any pipeline shut down would have
to be kept to a minimum. But based on its experience with the Mars on-bottom diverless pipeline repairs, Shell decided, as
an industry "first," to use the same pipeline repair principle for the Perdido tie-in.
The operation entailed:

Cutting and removing a 28-ft (8.5-m) long section from the HOOPS pipeline
Using a Grip and Seal connector, attaching a single pipeline connection hub on the upstream end of the pipeline
Using a Grip and Seal connector, attaching a dual pipeline connection hub (including a piggable Y) to the
downstream part of the pipeline
Installing a jumper on the two HOOPS hubs in order to ensure flow through the existing HOOPS pipeline.

A pipeline connection hub is now available for the future Perdido export line tie-in. The system went through various
rigorous onshore SITs and shallow water tests which resulted in a successful subsea installation, in 4,500 ft (1,372 m)
water depth, using multiple ROVs, with the shutdown of the HOOPS pipeline limited to 17 days. The Perdido export line
was subsequently connected to the connection hub on the HOOPS pipeline tie-in assembly.

Acknowledgment
Based on a paper presented at the Offshore West Africa 2012 conference in Abuja, Nigeria, Jan. 25, 2012.

Вам также может понравиться