Академический Документы
Профессиональный Документы
Культура Документы
SOLAR
COMPASS
July 2013 Edition
Market Dashboard
A snapshot of the
markets fundamentals
Latest Market Insights
An analysis of the policies,
projects, industry and finance
Key Question
Are tracking systems
viable in India?
Outlook
Projection for the
Indian solar PV market
DISCLAIMER
Contact
BRIDGE TO INDIA Pvt. Ltd.
N-117, Panchsheel Park
New Delhi 110017
India
contact@bridgetoindia.com
www.bridgetoindia.com
www.bridgetoindia.com/blog
www.IndiaSolarMarket.com
www.IndiaSolarHomes.com
Follow us on
BRIDGE TO INDIA,
2013
CONTENTS
1. Overview
01
2. Market Dashboard
02
02
02
03
3. Key Findings
4. Policies
06
06
08
09
5. Projects
10
10
12
14
6. Financing
16
7. Upstream Industry
17
19
8.1 Overview
19
19
20
21
22
23
24
26
8.9 Conclusion
26
9. Outlook
28
28
29
10. Annexure
32
LIST OF FIGURES
Figure 2-1: Market compass
02
Figure 2-2:
02
10
10
16
21
23
26
28
LIST OF TABLES
Table 4-1:
06
Table 8-1:
19
Table 8-2:
23
Table 8-3:
25
Table 8-4:
25
Table 8-5:
25
Table 8-6:
25
Table 8-7:
26
Table 9-1:
30
1. OVERVIEW
01
NA
S
E
EM
OW
IN
GI
GR
NG
E
R
U
NT
CE
MA
T
2. MARKET
DASHBOARD 2.1 MARKET COMPASS
Trend
PV
Lowest FiT
` 6.45/kWh
Interst Rate
13%
Average Capex
` 68 /W
$ 0.63/W*
$ 0.57/W*
$ 0.70/W*
$ 0.70/W*
BRIDGE TO INDIA, 2013
02
2.3 INSTALLED
CAPACITY IN INDIA
03
3. KEY FINDINGS
POLICY
1. I n the last quarter (April 2013 to
June 2013) we have seen several
state allocations in Andhra Pradesh
and Tamil Nadu drawing close to
signing of PPAs.
2. Bidding has also been completed
in the states of Punjab and Uttar
Pradesh.
3. MNRE has now decided to go ahead
with the allocations for 750 MW
based on VGF. The bidding process
for these allocations is expected to
begin in July 2013.
4. As an off-taker for NSM projects,
SECI will be considered as a less
bankable option than NVVN.
5. MNRE recently announced that
it plans to allocate mega-size
projects, i.e., projects larger than
500 MW. The primary objective
of these projects will be to
significantly bring down the tariffs.
6. In Tamil Nadu, originally, the 52
currently selected developers had
opted for a cumulative capacity of
293 MW. Out of this, 25 developers
opted to increase their allocated
capacity. This has led to a total
allocation of 690 MW.
FINANCING
PROJECTS
04
INDUSTRY ANALYSIS
1. The US has won the DCR case
against Canada, and Canada has
had to remove its DCR regulations.
This might have an impact on other
DCR policies, including in India.
2. As per the draft guidelines, the
allocations under the NSM will be
divided into two parts : projects with
a DCR and projects without a DCR.
3. Of the 2.5 GW capacity allocations
expected in 2013 across India,
including all state policies, only
about 500 MW under the NSM is
likely to have a DCR.
4. For anti-dumping duties, the last
day for stakeholders to submit
comments and counter briefs
was 23rd April 2013. An interim
order from the anti-dumping
investigations is expected soon.
OUTLOOK
1. A capacity of 1.7 GW has already
been installed in India and close
to 1.5 GW of PV is currently under
development.
2. There is a lot of momentum
building up for new capacity
additions in 2014, which could
easily exceed 2 GW.
3. A capacity of 750MW is expected
to be allocated under the NSM this
year. As the process is expected to
start in July 2013 with PPAs signed
only by October 2013, we do not
expect any capacity addition in the
next four quarters under the NSM.
05
4.1 NATIONAL
SOLAR MISSION
The draft guidelines for phase two
of the National Solar Mission (NSM)
were published by the Ministry of
New and Renewable Energy (MNRE)
on December 3rd 20121. According to
the draft policy, the MNRE wanted to
allocate 800 MW through a bundling
of power mechanism (as in phase one
of the NSM) and 750 MW through a
VGF2 mechanism. For a large part of
the first quarter (January to March
2013), the MNRE had been trying to
arrange for unallocated power from
the Ministry of Power (MoP) to carry
out the tariff based bidding component
of allocations based on bundling of
power3. However, as there is only a
limited amount of unallocated power
available and all states demand access
to this power, the MoP has been
unwilling to provide it. As a result, the
MNRE has now decided to go ahead
only with the allocations for just 750
MW based on VGF. The bidding process
for these allocations is expected to
begin in July 2013.
Schedule
Zero date
(expected in July 2013)
PPA signing
Financial closure
Commissioning
---------------------1
Draft policy document: Phase two of the National Solar Mission (NSM)
2
Refer to the October 2012 edition of the India Solar Compass
3
Refer to the January 2013 edition of the India Solar Compass
BRIDGE TO INDIA, 2013
06
4. POLICIES
07
08
4.3 ANDHRA
PRADESH SOLAR
POLICY
Like Tamil Nadu, Andhra Pradesh has
also planned an L1 process for the
final tariff determination but in Andhra
Pradeshs case, the lowest bid is to be
considered at the substation level as
compared to the state wise L1 in Tamil
Nadu. (This takes into account different
land costs and irradiation levels
across the state.) Based on this, 330
companies participated in the bidding
process and bid for a cumulative
capacity of 1,712 MW. However, in a
sudden change of process, after the
bidding process was complete, the
state last week announced that it could
only offer the overall L1 tariff across
the state instead of the substation
level L1 tariff. This meant that all
developers, irrespective of their project
size and location were offered the
same tariff. The L1 tariff was quoted by
SunBorne Energy for a 5 MW project
with ` 6.49 ( 0.10/$ 0.13)/kWh. The
states cabinet sub-committee on
power fixed this benchmark price at its
meeting on April 23rd 2013.
At this tariff, the state is now looking
to allocate a capacity of 350 MW. Of
this, seven companies with a capacity
of 53 MW have unconditionally agreed
to the terms and tariff and another
27 companies with a capacity of 297
MW have given their conditional
acceptance.
Andhra Pradesh also allowed
developers to re-negotiate the capacity.
However, unlike in Tamil Nadu, where
25 developers chose to increase
their allocation capacity, only three
developers chose to increase their
allocated capacity while six developers
chose to decrease their allocated
capacity (read the projects section of
this report for more analysis).
09
Figure 5-1: Grid connected solar projects installed in the previous quarter (April 1st to June 20th
2013)
Size - 125 MW
Technology - PV
Off-take - Captive RPO
Developer - Mahagenco
ANDHRA
PRADESH
Size - 20 MW
Technology - PV
Off-take--Third-party
Industrial sale
captive
Off-take
of power
Developer--EMMVEE
EMMVEE
Developer
Size - 50 MW
Technology - CSP
Off-take - NSM Phase 1, Batch
Developer - Godavari Green
Energy
MAHARASHTRA
RAJASTHAN
JHARKHAND
Figure 5-2: Grid connected solar projects installed in the previous quarters, that were not
covered in previous editions of the India Solar Compass
GUJARAT
Size - 2 MW
Technology - PV
access + RECs
Off-take -APPC/Open
REC Mechanism
Developer - Deepak Spinners
Size - 5 MW
Technology - PV
Off-take - State policy
Developer - Avatar Solar
Size - 0.5 MW
Technology - PV
access + RECs
Off-take -APPC/Open
REC Mechanism
Developer - M/S Gupta Sons
Size - 23 MW
Technology - PV
Off-take - State policy
Developer - Ujjawala Power
Private Limited
Size - 1 MW
Technology - PV
access + RECs
Off-take - APPC/Open
REC Mechanism
Developer - Omega Renk
Bearing
Island Electrification
TAMIL
NADU
TAMIL
NADU
UTTAR
PRADESH
Size - 5 MW
Technology - PV
Off-take - State RPO
Developer - NTPC
BRIDGE TO INDIA, 2013
Size - 1 MW
Technology - PV
Off-take - RPSSGP
Developer - Noel Media and
Advertising Pvt. Ltd.
Size - 1 MW
Technology - PV
access + RECs
Off-take - APPC/Open
REC Mechanism
Developer - Star Delta Transformers
ANDAMAN
ANDAMAN
& NICOBAR
& NICOBAR
MADHYA
PRADESH
Size - 1 MW
Technology - PV
Off-take - REC Mechanism
Developer - SWELECT Energy
Systems Limited
10
RAJASTHAN
Size - 2.5 MW
Technology - PV
access + RECs
Off-take - APPC/Open
REC Mechanism
Developer - BMD
Size - 3 MW
Technology - PV
access + RECs
Off-take - APPC/Open
REC Mechanism
Developer - KC (India)
Size - 1 MW
Technology - PV
access + RECs
Off-take - APPC/Open
REC Mechanism
Developer - Chartered Global
Financial Services
Size - 1 MW
Technology - PV
access + RECs
Off-take - APPC/Open
REC Mechanism
Developer - Dindyal Commodities
Size - 15 MW
Technology - PV
access + RECs
Off-take - APPC/Open
REC Mechanism
Developer - DJ Malpani
Size - 1.5 MW
Technology - PV
access + RECs
Off-take - APPC/Open
REC Mechanism
Developer - Impact Solar
Size - 10 MW
Technology - PV
access
+ RECs
Off-take - APPC/Open
NSM Phase
1, Batch
2
Developer - Jakson Power
(Allocation 1)
Size - 1 MW
Technology - PV
access + RECs
Off-take - APPC/Open
REC Mechanism
Developer - Raj Overseas
Size - 2 MW
Technology - PV
access + RECs
Off-take - APPC/Open
REC Mechanism
Developer - Rajasthan Patrika
Size - 2 MW
Technology - PV
access + RECs
Off-take - APPC/Open
REC Mechanism
Developer - Lahoti Overseas
Size - 10 MW
Technology - PV
access
+ RECs
Off-take - APPC/Open
NSM Phase
1, Batch
2
Developer - Sai Maithili Power
Company
Size - 10 MW
Technology - PV
access
+ RECs
Off-take - APPC/Open
NSM Phase
1, Batch
2
Developer - LEPL Projects
Size - 2 MW
Technology - PV
access + RECs
Off-take - APPC/Open
REC Mechanism
Developer - Sanjeev Prakashan
Size - 10 MW
Technology - PV
access
+ RECs
Off-take - APPC/Open
NSM Phase
1, Batch
2
Developer - Lexicon Vanijya
Size - 5 MW
Technology - PV
access
+ RECs
Off-take - APPC/Open
NSM Phase
1, Batch
2
Developer - Sunborne Energy
Services
Size - 10 MW
Technology - PV
access
+ RECs
Off-take - APPC/Open
NSM Phase
1, Batch
2
Developer - NVR Infrastructure
Size - 5 MW
Technology - PV
access
+ RECs
Off-take - APPC/Open
NSM Phase
1, Batch
2
Developer - Pokaran Solaire
Energy
Size - 10 MW
Technology - PV
access
+ RECs
Off-take - APPC/Open
NSM Phase
1, Batch
2
Developer - Symphony Vyapar
Size - 10 MW
Technology - PV
access
+ RECs
Off-take - APPC/Open
NSM Phase
1, Batch
2
Developer - Jakson Power
(Allocation 2)
Size - 1 MW
Technology - PV
access + RECs
Off-take - APPC/Open
REC Mechanism
Developer - Aman Home Appliance
Size - 1 MW
Technology - PV
access + RECs
Off-take - APPC/Open
REC Mechanism
Developer - Vinay Corporartion
---------------------5
Naxal, Naxalite and Naksalvadi are generic terms used to refer to various militant communist
groups operating in different parts of India under different organizational envelopes. They are
mostly concentrated in the eastern states of the mainland India (Chhattisgarh, Jharkhand, West
Bengal and Odisha).
BRIDGE TO INDIA, 2013
11
A capacity of 225 MW
had been allocated in
Madhya Pradesh in
May/June 2012.
A 50 MW Concentrated Solar
Power (CSP) project has also been
commissioned in Rajasthan in the last
quarter. This is the only CSP project
to have come up under the NSM
allocation till date. It takes Indias total
installed capacity for CSP to 55.5 MW.
Rajasthan
Karnataka is
experiencing excess
rainfall, projects that
have not begun the
construction work
early, might struggle
to commission on time.
Karnataka
Karnataka had allocated 60MW of solar
PV capacity in April 2012. The projects
were allocated to Essel Infrastructure
(10 MW), GKC Projects (10 MW), Helena
Power (10 MW), Jindal Aluminium(10
MW),SaiSudhir Energy (10 MW), United
Telecom (3 MW) and Welspun (7 MW).
Projects are to be commissioned no
later than October 2013. Given that the
deadline is right after the monsoons
and Karnataka is experiencing excess
BRIDGE TO INDIA, 2013
Tamil Nadu
In Tamil Nadu, 52 project developers
have been issued an LoI for setting up
a cumulative capacity of 690 MW under
the state solar policy. As mentioned
in the policies section, 25 developers
chose to increase their allocation
capacity from the earlier capacity that
they had bid for (read the policy section
12
In Tamil Nadu,
given the poor
bankability of the offtaker, most projects
are likely to be
financed by recourse.
Engineering,
Procurement and
Construction (EPC)
companies will get
very limited access
to project capacities
in Punjab as most of
the developers are
likely to do the EPC
work in-house.
Andhra Pradesh
In Andhra Pradesh, seven project
developers with a cumulative capacity
of 53 MW have unconditionally
accepted the tariff and terms of the
PPA. These projects are by developers
such as Enerparc from Germany (5
MW), SunBorne Energy (5 MW) and
Essel Mining and Industries (35 MW)
and a number of smaller, first time
project developers.
Apart from this, 27 projects with a
cumulative capacity of 297 MW have
conditionally accepted the terms
of agreement. These projects have
requested for a change in conditions
such as a change in location, an
increase or decrease in capacity and
in some cases, even an increase in
tariffs, if possible. It is expected that
some of these projects will not end up
signing the PPA. Five developers, who
account for eight projects out of these
27 projects, have previous project
development experience and, like
Tamil Nadu, the remaining developers
BRIDGE TO INDIA, 2013
Punjab
A capacity of 250 MW is likely to be
allocated under the Punjab policy to
27 developers. The average project
size per developer in the state is 13
MW but most projects are between
1 MW and 4 MW. Unlike Tamil Nadu
and Andhra Pradesh, a majority of the
capacity in Punjab is being developed
by experienced players such as
Welspun, Azure, Essel Infraprojects,
SolaireDirect, Moser Baer, Lanco and
Punj Lloyd. The tariffs in the state are
also financially more feasible: The
lowest tariff in the state is ` 7.20 (
0.11/$ 0.14)/kWh and the average tariff
across the selected projects is ` 8.22
( 0.13/$ 0.16)/kWh. These tariffs are
without any escalation and for a period
of 25 years.
Engineering, Procurement and
Construction (EPC) companies will
get very limited access to project
capacities in Punjab as most of the
developers are likely do the EPC work
in-house. Due to the high land costs in
the state, it is likely that most projects
13
14
15
62
60
58
56
54
52
50
48
46
44
42
40
Exchange
USDagainst
vs INRthe US dollar
Figure 6-1: A
weakening rate
Indian-rupee
Jul-13
Apr-13
Jan-13
Oct-12
Jul-12
Apr-12
Jan-12
Oct-11
Jul-11
INR/USD
Apr-11
Jan-11
6. FINANCING
16
7. UPSTREAM
INDUSTRY
The DCR will be
extended to thin film
modules for phase two
of the NSM.
17
18
8. KEY
8.2 CURRENT
QUESTION: 8.1 OVERVIEW
SCENARIO
systems for solar PV power
ARE TRACKING Tracking
plants generate more electricity than
Most projects in India use fixed-tilt
SYSTEMS fixed tilt systems during the early
structures with no tracking. Out
hours of the morning and during the
the total 1,746 MW installed in
VIABLE IN late afternoon. This excess generation ofIndia,
only approximately 80 MW
INDIA? leads to an increased yield and
are installed with tracking systems.
6
Location/
State
Project
size
(MW)
Module
type/
Supplier
Tracking
Tracker
technology supplier
Reliance
Solar/
Reliance Solar
Khimsar/
Rajasthan
0.032
Monocrystalline/
Reliance
Dual Axis
tracking
Degerenergie
Sripower/
Solarsis
Anantapur/
Andhra
Pradesh
0.375
CdTe/
Abound
Solar
Single axis
Horizontal
Smarttrak
Clover Solar/
Clover Solar
Baramati/
Maharashtra
0.82
Monocrystalline/
SunPower
Single axis
Horizontal
SunPower
Gildemeister/
SunCarrier
Omega
Bhopal/
Madhya
Pradesh
0.8
Crystalline
Vertical
SunSingle Axis Carrier
tracking
Omega
Mahindra Solar/
Mahindra Solar
Phalodi/
Rajasthan
Polycrystalline/
SunPower
Single axis
Horizontal
SunPower
Thin Film/
Nexpower
Single axis
Horizontal
SatecEnvir Engineering
Charanka/
Gujarat
Thin film/
First Solar
Vertical
IdeeSingle Axis matec
tracking
GmbH
Surendranagar/
Gujarat
9.2
Polycrystal- Vertical
Ideeline/ Trina, Single Axis matec
Solarfun
tracking
GmbH
19
Surfaces
Normal
South
Zenith
Intelligent tracking
is based on light
detection at a location.
The sensors align the
modules towards the
brightest spot in the
sky.
Astronomical tracking
is useful in locations
where the irradiation
remains constantly
high and skies are
more or less cloudless
throughout the year.
---------------------8
Azimuth is the compass direction from which sunlight is coming. At noon in northern hemisphere,
the sun is directly south and considered at azimuth angle = 0 degree
9
The angle from ground in the vertical plane at which modules are tilted
10
Castillo JE, Russo JM, Kostuk RK, Rosenberg GA; Thermal effects of the extended holographic
regions for holographic planar concentrator. J. Photon Energy accessed
11
The Alternative Energy eMagazine
BRIDGE TO INDIA, 2013
20
8.4 PV MODULE
TRACKER
TECHNOLOGIES
Single axis horizontal
tracking systems are
an optimum solution
for locations where
land area utilization
has to be optimized in
a project either due
to high land costs or
scarcity of land.
Fixed Tilt
The module mounting structures are
installed at a fixed inclination with
respect to the ground. The optimum
angle for fixed tilt installations
depends on the latitude of the location
and the season.
Module mounting structures in such
installations are the easiest to install
and are the most stable against
wind loads. They are also the the
most inexpensive type of installation
in terms of material costs, design,
fabrication and input labor costs.
Some installations allow module
output optimization in a certain
period of the year by adjusting the
tilt seasonally. The provision for
adjustment is present in the mounting
structures and the change in tilt can be
made manually on the site. Seasonal
tilt can give an approximate increase
in yield of 5% as compared to the
standard fixed tilt systems.
Fixed
ss
N
E
Singly-Axis-Trackers
N
E
- Dual-Axis-Trackers -
---------------------12
SolarGIS database
13
The drive could be mechanical (gears), electrical (motors) or hydraulic.
BRIDGE TO INDIA, 2013
21
According to SunPower
India, the use of
trackers has increased
the yield by 15% at
an increased initial
investment of 8% for
the project.
Dual-axis tracking
systems in higher
latitudes can lead to
an increase in yield of
35% to 40% over the
fixed tilt systems.
8.5 COMPARISON
OF VARIOUS
TRACKING
TECHNOLOGIES
---------------------14
As per communications with SunPower India representative. BRIDGE TO INDIA has not verified the
actual plant performance data.
15
SunCarrier Omega presentation
16
The figure is based on the claims of SunCarrier representatives and the actual plant data has not
been verified by BRIDGE TO INDIA
17
DEGERenergie brochure accessed here; Mecasolar, accessed here.
22
900
Fixed Tilt
800
Horizontal SAT
Vertical SAT
36%
700
23%
600
500
11%
400
Tracking systems
generate more
electricity than fixed
tilt systems in the early
hours of the morning
and in the evening or
late afternoon.
300
200
100
0
6
10
11
12
13
14
15
16
17
Table 8-2: Gain in yield for various axis tracking technologies for
a system size of 1 MW
Tracking Technology
% gain
Fixed tilt
5,967
Base case
6,642
11.3
7,370
23.5
An effective way to
determine if tracking
systems make
financial sense is to
compare Return of a
PV installation with
a tracking system to
without a tracking
system.
8.6 FACTORS
INFLUENCING
AN INVESTMENT
DECISION INTO
TRACKING
MECHANISMS
---------------------18
Values from PVSyst report
23
Any misalignment
while installing
the foundations for
trackers could lead
to additional costs in
maintenance over the
lifetime of the project.
8.7 FINANCIAL
ANALYSIS
Gujarat and Rajasthan have seen
maximum PV installations in the past
three years in India. Until now, most
projects in Rajasthan use fixed tilt
systems and have reported a CUF of
18%-20%23. For the purpose of this
analysis, a location at 20-degree
latitude having daily global irradiation
of 5.5 kWh/m2 and an average CUF of
19%24 has been considered.
Performance data of projects with
tracking systems in various projects
in India has been collected from
tracking system suppliers and the
performance data available from
government sources. As there is
very little data available for dual axis
tracking systems, the values used in
the analysis for dual axis trackers are
an approximation based on information
provided by experts in the solar
industry.
---------------------19
The drive mechanism could be electrical, mechanical or hydraulic
20
Ideematec GmbH
21
The drive mechanism of the tracker could be actuated electrically, mechanically or hydraulically.
22
Solar Pro, PV Trackers, Smith; Stephen, July 2011
23
MNRE,Net exported power-summary, Oct 2012-April 2013
24
Average CUF of a solar PV power plant in India using 14%efficiency C-Si modules
BRIDGE TO INDIA, 2013
24
Assumption
14
25
19
26
Tariff (INR/kWh)
6.60
27
Escalation (%)
70
0.8
29
5.72
30
70:30
13.00
Tracking technology
CUF of power
plant (%)32
Increase in
yield(%)
Fixed tilt
1.66
19
1.92
22
15
2.01
23
22
Dual axis
2.27
26
35
Tracking technology
Increase in cost34
(` per Wp)
11
18
12
Dual axis
30
20
Fixed tilt
Tracker type
Fixed
tilt
Single Axis
(Horizontal)
Single Axis
(Vertical)
Dual
Axis
19
22
23
25
4.5 37
5.0
6.0
7.0
CAPEX (` millions)
70
77
82
90
0.8
1.2
1.4
1.6
CUF (%)
Land Area35 (acres )36
38
25
Table 8-7: Variation of generation and EIRR with fixed tilt and
trackers39
Tracker type
Fixed tilt
Single Axis
(Horizontal)
Single Axis
(Vertical)
Dual Axis
14.5
15.0
14.2
14.9
EIRR (%)
BRIDGE TO INDIA, 2013
8.9 CONCLUSION
The increase in EIRR is marginal when
using horizontal single axis and dual
axis tracking systems. For vertical
single axis tracking systems, the EIRR
actually reduces for Indian conditions.
The marginal increase in EIRR does
not justify the additional costs and
risk involved in adopting tracking
technology at the current cost for
tracking in India.
Installing tracking systems for utility
scale projects requires a more detailed
technical and financial due-diligence.
Given the stringent deadlines for PV
projects in most policies, developers
find it convenient to avoid tracking
systems and opt for fixed tilt systems.
15.6
15.4
Equity IRR
15.2
15
14.8
14.6
14.4
14.2
14
13.8
26
A more competitive
price for tracking
technology is required
for the tracker market
to pick up and become
relevant in India.
27
9. OUTLOOK
400
300
200
100
0
Q3-2013
Q4-2013
Q1-2014
Q1-2014
NSM
Rajasthan
50
Madhya Pradesh
50
155
25
Karnataka
40
20
0
250
Tamil Nadu
50
Andhra Pradesh
80
Punjab
100
Uttar Pradesh
Others
Total
0
30
0
50
0
80
50
100
80
245
175
630
9.1 COMING
QUARTER
The coming quarter (July 2013
to September 2013) is expected
to see around 80 MW of projects
500
BRIDGE TO INDIA, 2013
A capacity of 1.7 GW
has already been
installed in India and
close to 1.5 GW of PV
is currently under
development.
700
---------------------40
The permission granted by the state agency in the form of an accreditation certificate that allows
the developers to sell renewable power to the state and be eligible to avail RECs.
BRIDGE TO INDIA, 2013
28
Andhra Pradesh
Only developers with
recourse are expected
to get finance without
delays in Tamil Nadu.
Maharashtras power
distribution company,
Brihan Mumbai
Electric Supply and
Transport Undertaking
(BEST), has signed
an agreement with
Welspun to set up
a 20 MW project to
supply solar power
to meet its RPO .
9.2 LONG-TERM
OUTLOOK
29
Policy
Initially
announced
capacity allocation (as
of January
2013)
Current scenario
(as of June 2013)
750 MW likely to
be allocated in the
next few months
0 MW
300 MW
Andhra
Pradesh
1,000 MW
80 MW
Some projects
are expected to
be commissioned
before the
deadline as
there is a fiscal
incentive for
commissioning
before the
deadline
Rajasthan
100 MW
A capacity of 75
MW has been
allocated
50 MW
These projects
are expected to
be commissioned
within the
deadline
Uttar
Pradesh
200 MW
Financial bids
received for 135
MW. No clarity
on whether LOIs
will be issued
as, due to an
undersubscribed
tender, some of
the tariffs quoted
are very high
50 MW
Some experienced
developers
are expected
to be able to
commission the
projects a couple
of months before
the deadline
Punjab
500 MW
100 MW
Some experienced
developers
are expected
to be able to
commission the
projects a couple
of months before
the deadline
30
40 MW was
expected
as per the
policy
An allocation for
130 MW is under
process
0 MW
31
Karnataka
32
33
34
EARN
AND SAVE
THROUGH
SOLAR
OUR PROPOSITION
OUR MODEL
CONTACT US
Akhilesh Magal
akhilesh.magal@bridgetoindia.
com
BRIDGE TO INDIA, 2013
35
36
Contact
contact@bridgetoindia.com
www.bridgetoindia.com
Follow us on facebook.com/
bridgetoindia
www.bridgetoindia.com/blog
37