SPECIFICATIONS
DECEMBER 2012
TERRACON
FORT COLLINS, COLORADO
SECTION 01011
SECTION 01039
SECTION 01100
SECTION 01400
SECTION 01410
SECTION 01570
SECTION 02000
SECTION 02110
SECTION 02116
SECTION 02222
SECTION 02223
SECTION 02231
SECTION 02575
DIVISION 3 - CONCRETE
CONCRETE FORMWORK
CONCRETE REINFORCEMENT
CAST-IN-PLACE CONCRETE
SECTION 03100
SECTION 03200
SECTION 03300
SECTION 13205
FIGURES
COVER SHEET AND PROJECT VICINITY MAP
SITE FIGURE
NEW AST SITE FIGURE
NEW AST SURFACE CROSS SECTION
VINE STREET AST
FIGURE 1
FIGURE 2
FIGURE 3
FIGURE 4
FIGURE 5
10
SECTION 01011
SUMMARY OF PROJECT
1.
GENERAL
1.1. SECTION INCLUDES
A.
B.
The specifications for equipment and materials associated with the AST
systems allow for the submittal by the Contractor of proposed
alternates to the specifications that are required to be reviewed and
approved by the Engineer. All proposed equivalents or equals to the
specifications are required to be approved prior to the submittal of the
bids to the Owner. All proposed alternates to the specifications are
required to be submitted 10 calendar days prior to the bid submittal due
date. Approved alternates to the specifications will be issued as an
addendum to the project specifications prior to submittal of bid. No
proposed alternates to the specifications will be considered after
submittal of the bid.
B.
The Contractor shall provide all equipment and labor as may be required for removal and
disposal of the existing AST systems at the Road and Bridge Facility in Livermore, CO. This includes
demolition and removal of the following:
The existing Fuel Master fuel management system terminal shall be disconnected, removed,
relocated and installed at the new AST installation. The area will be backfilled and compacted as
specified.
The existing AST system will not be removed or demolished until the new AST
system is constructed, operationational, and permission is given by the Engineer
and Owner to remove the existing AST system.
2)
The Contractor shall provide all equipment and labor as may be required for the
complete installation of the new AST system at the Road and Bridge Facility in
Livermore, CO. This includes installation of one 6,000-gallon dual-compartment
AST (4,000-gallon diesel fuel and 2,000-gallon unleaded gasoline) system. The
AST system shall be delivered to the site factory assembled including skidmounted tank, pumping system, dispensers, piping, fill ports, sensor ports, overfill
prevention sumps, and dispensers. The installation also includes the following:
3)
Vine Street Shop Used Oil Above-Ground Storage Tank Removal and
Installation
The Contractor shall provide all equipment and labor as may be required for the
removal and disposal of the existing used oil AST at the Vine Street Shop in Fort
Collins, CO, cleaning of the existing gasoline 1,000-gallon AST at the Road and
Bridge Facility in Livermore, loading and transporation of the 1,000-gallon AST to
the Vine Street Shop, and complete installation of the 1,000 gallon tank as a used
oil AST at the Vine Street Shop in Fort Collins, Colorado. The installation also
includes the following:
Removal and demolition of the existing used oil AST located at the Vine
Street Shop
Cleaning of the 1,000-gallon AST located at the Livermore Shop
Loading and transfer of the 1,000-gallon AST to the Vine Street Shop
Installation of the 1,000-gallon AST and piping to the existing used oil
transfer lines
Miscellaneous equipment and materials for a complete used oil storage
system as shown on the Drawings
C.
D.
Project Sequence: The installation of the new used oil AST at the Vine Street
Shop shall be operational within two days of the existing used oil AST system
being shut down. At least two weeks notice shall be given to the Owner prior
to disconnecting and removal of the existing used oil AST system.
Section
Section
Section
Section
Section
Section
Section
Section
Section
Section
Section
Section
Section
Section
01011
01039
01100
01400
01410
01570
02000
02088
02110
02222
02223
02231
02575
13205
Summary of Project
Coordination
Health and Safety
Quality Control
Testing Laboratory Services
Traffic Control
Mobilization and Demobilization
Underground Storage Tank Removal
Demolition and Site Clearing
Excavation
Stabilization, Backfill and Compaction
Aggregate Base Course
Pavement Repair and Resurfacing
Above-Ground Storage Tank Installation
END OF SECTION
SECTION 01039
COORDINATION
1.
GENERAL
1.1. SECTION INCLUDES
A.
Coordination
2.
A.
B.
Coordinate removal and installation operations with Owner and Engineer such
that an operable fueling system is in place during all aspects of construction
activities.
C.
Coordinate space requirements with site personnel, and organize work area
efficiently so as not to interfere with site operations.
END OF SECTION
SECTION 01100
HEALTH AND SAFETY
1.
GENERAL
1.1. SECTION INCLUDES:
A.
This section covers requirements for health and safety procedures relating to
work in areas where petroleum hydrocarbon or solvent contamination is
encountered or is expected to be encountered.
1.2. SUBMITTALS
A.
Contractor shall prepare and submit a Health and Safety Plan to the Engineer
prior to initiating work at the site, in accordance with applicable sections of
29CFR 1910.120 and 29 CFR 1926. Health and Safety Plan shall be
submitted to the Engineer at the Pre-Construction Conference meeting or no
later than 15 calendar days from the date of Notice to Proceed. The
Engineers receipt of such plans does not relieve the Contractor from the
responsibility to protect his/her personnel and subcontractor personnel.
B.
The Contractor shall prepare and submit copies of Health and Safety Plans
for Contractors associated personnel and subcontractors performing work at
the sites.
B.
Contractor engaged in project activity at the sites will comply with applicable
provisions of the Occupational Safety and Health Act of 1970, the safety and
health requirements set forth in Occupational Safety and Health
Administration regulation 29 CFR 1910.120, where applicable, and any
applicable state, city or local safety codes. The Contractor will be responsible
for supplying and utilizing necessary equipment required for safety
precautions for the Contractors and subcontractors employees engaged in
this project.
C.
The Contractor will assign a competent person to oversee work at the site,
and shall maintain an orderly and safe work area around demolition, cleaning
and excavation equipment to minimize the potential for accidents, including
2.
D.
E.
Contractor workers should use extra care when working in areas which
petroleum hydrocarbon contamination is encountered or is expected to be
encountered. Steel toe work boots, and hard hats should be worn at all
times. Workers are not to smoke, eat or chew tobacco while in the work area.
Workers should wash their hands, face and any exposed skin as soon as
possible upon leaving the work area.
F.
The Contractor shall monitor the work area using a combustible gas indicator
(CGI) and photoionization detector (PID). This monitoring equipment shall be
operated and calibrated in accordance with the manufacturers
recommendations. This monitoring is required when working in areas where
petroleum hydrocarbon or solvent contamination is encountered or is
expected to be encountered. Work activities shall cease and workers should
evacuate to the upwind side of the project site if combustible gas
concentrations in the work zone exceed 20% of lower explosive limit (LEL). If
sustained PID readings in the breathing zone of site personnel are greater
than or equal to the levels specified in the Contractors Health and Safety
Plan, as organic vapor in air, personnel will upgrade to NIOSH-approved
respiratory protection or evacuate to the upwind side of the work zone.
G.
MATERIALS
A.
Not used.
3.
EXECUTION
A.
Not used.
4.
and unit prices shall include all costs for all labor, materials and equipment
required to complete the work in accordance with the Plans and Specifications.
END OF SECTION
SECTION 01400
QUALITY CONTROL
1.
GENERAL
1.1. SECTION INCLUDES
A.
Related Sections
B.
C.
Tolerances
D.
References
E.
F.
G.
B.
C.
D.
Comply with specified standards as minimum quality for the Work except
where more stringent tolerances, codes, or specified requirements indicate
higher standards or more precise workmanship.
E.
1.4. TOLERANCES
A.
B.
C.
1.5. REFERENCES
A.
B.
C.
D.
B.
Observations, testing, and source quality control may occur on or off the
project site.
C.
E.
2.
END OF SECTION
SECTION 01410
TESTING LABORATORY SERVICES
1.
GENERAL
1.1. DESCRIPTION: This section describes requirements for testing laboratory
services used in connection with construction of the project.
1.2. SECTION INCLUDES
A.
Related Sections
B.
References
C.
D.
Engineers Responsibilities
E.
Contractors Responsibilities
F.
G.
1.4. REFERENCES
A.
B.
C.
ASTM D4561 - Practice for Quality Control Systems for an Inspection and
Testing Agency for Bituminous Paving Materials.
D.
ASTM E329 - Practice for Use in the Evaluation of Inspection and Testing
Agencies as Used in Construction.
E.
B.
C.
Quality control services include observations and tests and related actions
including reports performed by independent agencies, governing authorities,
and the Contractor.
2)
3)
4)
5)
6)
B.
C.
D.
2)
3)
4)
2.
A.
B.
C.
END OF SECTION
SECTION 01570
TRAFFIC CONTROL
1.
GENERAL
1.1. DESCRIPTION: Traffic control through the demolition and construction areas is
described in this subsection. The traffic control shall be the responsibility of the
Contractor. The Contractor is required submit a written plan to the Engineer and
Owner identifying propose methods and means for handling traffic control through
the work areas during the different stages of work prior to initiation of field work.
The Contractor is not allowed to start fieldwork if the Traffic Control Plan has not
been submitted. The review and comment of the Traffic Control Plan showing the
proposed method of handling and devices which shall be used to control traffic on
the project and shall in no way relieve the Contractor of liability for the safe
passage of traffic through the construction area.
1.2. SECTION INCLUDES
A.
Related Sections
B.
C.
Removal
D.
1.4. TRAFFIC SIGNS AND SIGNALS: Traffic signs and signals shall be in accordance
with the Manual on Uniform Traffic Control Devices and with applicable State and
local regulations.
A.
B.
C.
All traffic control devices shall be provided with all components necessary to
comprise a complete installation.
D.
1.5. REMOVAL
2.
A.
Remove equipment and devices when no longer required and when approved
by Engineer.
B.
END OF SECTION
SECTION 02000
MOBILIZATION AND DEMOBILIZATION
1.
GENERAL
1.1. DESCRIPTION: Contractor shall mobilize and demobilize all personnel, materials
and equipment in an efficient manner to accomplish the Work.
1.2. SECTION INCLUDES
A.
Related Sections
B.
C.
2.
Obtain all necessary licenses and permits and pay all associated licensing
and construction fees prior to mobilizing to the site to ensure compliance with
all applicable Federal, State and local rules, laws and regulations including
Larimer County, Colorado Department of Labor and Employment, Division of
Oil and Public Safety and Livermore Fire Department.
SECTION 02110
DEMOLITION AND SITE CLEARING
1.
GENERAL
1.1. SECTION INCLUDES
A.
Related Sections
B.
Requirements
C.
Execution
D.
B.
1.3. REQUIREMENTS
2.
A.
Contractor is responsible for removal and proper off-site disposal of all trash
and debris associated with Work for this contract.
B.
EXECUTION
2.1. PROTECTION
A.
B.
Protect, repair and/or replace all fencing impacted by demolition and overexcavation.
C.
D.
2.2. CLEARING
A.
B.
Remove and replace paving, curbs, slabs, and fencing materials necessary to
accomplish Work.
C.
Control the amount of dust from demolition and over excavation and prevent
the spread of dust to adjacent properties. Use water sprinkling or other
method approved by the Engineer.
Remove portions of concrete curbs, slabs, and pavement at least two (2) feet
beyond the limits of disturbance.
B.
Strip surface materials and remove from site. Dispose of materials off site in
an appropriate manner in conformance with applicable Federal, State and
local regulations.
3.
A.
B.
SECTION 02116
ABOVE-GROUND STORAGE TANK REMOVAL
1.
GENERAL
1.1. DESCRIPTION: The Work included under this section consists of furnishing all
labor, materials, services, equipment and appliances required to properly remove,
close and dispose of the existing AST systems and associated ancillary
equipment, foundations, and containment structures at the Larimer County Fleet
Services Livermore Shop in Livermore, CO. This includes:
Removal and disposal of diesel fuel AST system including one AST
approximately 6-feet in diameter and 12-feet long, approximately 2,000gallons,
Removal and disposal of used oil AST located at the Vine Street Shop
including one AST approximately 4-feet in diameter and 11-feet long,
approximately 1,000 gallons;
Contractor is responsible for removal and disposal of all liquids and sludges inside
the tanks including diesel fuel, unleaded gasoline, used oil, water, solids, and/or
sludge. The existing Fuel Master fuel management system shall be relocated to
the new installation by the Contractor.
Contractor shall include allowance moneys in bid for over-excavation, loading,
waste characterization sampling and testing, waste disposal acceptance, loading,
transportation, and replacement/backfill material of up to 100 in-place cubic yards
of petroleum contaminated soil as directed by the Engineer.
1.2. SECTION INCLUDES
A.
Related Sections
B.
Performance Requirements
C.
Owner Occupancy
D.
Protection
E.
Utilities
F.
Qualifications
G.
Indemnification
H.
Execution
I.
B.
C.
D.
E.
The intent of the Work is to accomplish safe and legal removal and disposal of
complete above-ground storage tank systems including: tanks, product
piping, equipment, residual fluids and solids (diesel fuel, unleaded gasoline,
waste oil, water, and sludge), dispensers, fueling islands, concrete walls,
pads, contaminated soil (if present), import of backfill, compaction and
resurfacing of the excavation.
The Contractor shall furnish all labor,
materials, supplies, equipment, transportation, travel, and professional
services necessary.
B.
The Owner will occupy the sites during the entire period of AST removal
activities. The existing diesel and gasoline storage and dispensing system will
remain operational throughout the construction of the new AST facility at the
Livermore Shop site. The installation of the new used oil AST at the Vine
Street Shop shall be operational within two days of the existing used oil AST
system being shut down. At least two weeks notice shall be given to the
Owner prior to disconnecting and removal of the existing used oil AST
system. Contractor will cooperate fully with the Owner requirements during
the work to minimize conflicts and to facilitate Owners usage of the site.
1.6. PROTECTION
A. The Contractor shall adequately protect the work site, adjacent property and the
general public during all phases of the project. Contractor shall be responsible for
all damages or injury due to his action or negligence.
1.7. UTILITIES
A.
1.8. QUALIFICATIONS
A.
All work under this contract must be completed under the direction of
personnel experienced and licensed in inerting, removing, and disposing of
above-ground fuel storage tank systems.
1.9. INDEMNIFICATION
A.
2.
Contractor shall assume, indemnify and hold harmless the Engineer and
Larimer County for and from any and all liability, loss and expense (including
Workmens Compensation) resulting from loss of life or damage or injury to
persons or property (including employees of either of the parties hereto)
arising in whole or in part by reason of or in a way resulting from negligent
operations under this contract, whether such operations be by said
Contractor(s), or by any Subcontractor(s), or anyone directly or indirectly
employed by either of them.
EXECUTION
2.1. SAFETY PRECAUTIONS
A.
1)
Avoid all sources of ignition during liquids removal from the tank and
tank removal.
2)
3)
4)
After removing residual fluids, solids, and sludges from the tank and
before removing the tank, test tank atmosphere for explosive range with
a calibrated combustible gas indicator (CGI) instrument. The CGI shall
not read greater than 20% of the Lower Explosive Limit (LEL), and an
oxygen level as close to zero percent as practicable.
5)
At all times during the work, the Contractor shall have on site equipment
suitable for the detection of organic/combustible vapors.
6)
The Contractor shall have a Health and Safety Plan prepared prior to
initiation of the work. All field personnel and subcontractors shall have
read and signed the plan prior to conducting work on the project.
7)
Owner nor Engineer shall not be responsible for the approval of the Site
Safety Plan nor for Contractors safety.
8)
Contractor shall verify that all electrical sources to tanks, pumps, dispensers
and instruments have been de-energized and disconnected prior to
commencing work.
B.
C.
Piping: Prior to commencing removal, all fuel and used oil piping shall be
completely drained by the Contractor with all product being flushed and
drained back into the storage tanks. Under no circumstances, shall product
be allowed to drain from the piping into the surrounding ground areas.
D.
Pump Out: All remaining liquids, solids, and sludges inside ASTs shall be
completely removed by the Contractor and disposed of in accordance with
Federal and State regulations. Any material that is not considered recyclable
shall be disposed of in accordance with applicable federal and state laws at
Contractors expense. Copies of Bill of Lading and chain-of-custody for the
disposal of hazardous materials shall be submitted to the Engineer.
Contractor shall make allowances to remove and dispose of up to 500 gallons
of liquids, solids and/or sludges from the ASTs.
E.
Pumps: All vacuum and transfer pump motors and suction hoses shall be
grounded to the tank to prevent electrostatic ignition hazards.
Only
explosion-proof or air driven pumps shall be allowed at the site.
F.
Inerting:
1)
Before tank removal, the tank shall be rendered inert with the addition of
dry ice, compressed nitrogen gas or carbon dioxide gas. Flammable
vapors expelled from the tank during this process shall be vented a
minimum of 12 feet above grade and three (3) feet above adjacent roof
lines. The tank removals shall not proceed if atmospheric conditions will
prevent the dispersal and dilution of the vapors discharged from the
tank.
2)
Inerting with Dry Ice: The vapors in the tank may be inert by adding dry
ice in the amount of 1.5 pounds per 100 gallons (minimum) of tank
capacity. Dry ice shall be crushed and distributed evenly over the
greatest possible area on the tank bottom. Avoid skin contact with dry
ice. As dry ice evaporates, flammable vapors may surround the area.
Observe all safety precautions regarding flammable vapors.
3)
Ignition: Shut down all open flame and spark producing equipment
within vapor hazard area (50 feet from tank). Ban smoking. Remove all
non explosion proof electrical and internal combustion equipment.
Utilize only non sparking tools to be used on expose tank fittings.
Minimize static electricity by grounding all working equipment.
4)
During the inerting process, the oxygen level in the tank shall be
checked continuously with an oxygen and CGI meter. Achieve an
oxygen level as close to zero percent as practicable. When the process
is successfully completed, plug all openings, except for the vent line, and
commence tank removal.
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
Removal:
Upon removal and loading of the tank on an appropriate
transportation vehicle, the vehicle shall be removed immediately from the site.
The tank(s) shall not be stored at the site overnight after removal.
B.
Testing: Prior to shipping, test in and around tank with CGI to ensure that
flammable vapor concentration does not exceed safe levels for transportation.
C.
Labeling: Label as to vapor state, vapor inerting treatment and date. Also,
permanently label tank with 2-inch high letters as follows:
TANK HAS CONTAINED FLAMMABLE LIQUID
NOT GAS FREE
NOT SUITABLE FOR FOOD OR DRINKING WATER INTENDED
FOR ANIMAL OR HUMAN CONSUMPTION
3.
D.
E.
U.L. tank labels shall be removed from tank and returned to the Engineer for
filing.
F.
Disposal: Diesel fuel tank and piping removed as part of this project shall not
be sold for reuse. Final disposal shall be accomplished by cutting the tank
and piping for scrap metal, or discarding in an acceptable and approved solid
waste disposal facility. Unleaded fuel tank will be transferred to Vine Street
Shop.
G.
H.
Contractor shall not be allowed to disassemble or cut up tanks for scrap metal
on site.
include all costs for all labor, materials and equipment required to complete the
work in accordance with the Plans and Specifications.
END OF SECTION
SECTION 02222
EXCAVATION
1.
GENERAL
1.1. DESCRIPTION:
This section describes excavation of contaminated soil,
uncontaminated overburden, concrete pump islands and concrete drive pads.
1.2. SECTION INCLUDES
A.
Related Sections
B.
Execution
C.
Payment
2.
A.
B.
C.
EXECUTION
2.1. EXCAVATION
A.
B.
Pump islands, foundations and concrete drive pads shall be removed and
disposed of off-site in accordance with all Federal, State and local
regulations.
C.
D.
F.
The Engineer may collect soil samples of excavated material for field
screening or laboratory analysis, for the purpose of assessing potential
contaminant concentrations. The Contractor shall provide soil samples of
excavated material to Engineer as requested.
G.
H.
I.
J.
1)
2)
3)
3.
A.
Contractor shall notify each utility owner and request utilities to be field
located by surface reference at least 48 hours prior to excavation. In the case
of a conflict, the proposed work may be modified, at the Engineer's discretion.
B.
C.
D.
SECTION 02223
STABILIZATION, BACKFILL, AND COMPACTION
1.
GENERAL
1.1. DESCRIPTION: This section describes preparation of subgrades; backfilling;
compacting; and finish grading for excavation areas.
1.2. SECTION INCLUDES
A.
Related Sections
B.
Materials
C.
Execution
D.
Payment
2.
A.
B.
C.
D.
E.
MATERIALS
2.1. STABILIZATION MATERIAL
A.
3.
Excavation backfill material shall be placed from the bottom of the excavation
to the bottom of the base course and/or pavement subgrade in accordance
with applicable sections of LCUASS Chapter 22.
EXECUTION
3.1. QUALITY ASSURANCE
A.
B.
2)
ASTM D4253 and D4254 - Standard Method of Test for Relative Density
of Cohesionless Soils.
3)
Density testing shall be performed in accordance with Section 01410 "Testing Laboratory Services".
2)
3)
Compaction tests for excavations shall be performed for each lift for
every 1,000 square feet of backfill area or per LCUASS Chapter 23,
Table 23-1 for areas/structures within jurisdiction of the local government
entity.
4)
If the Engineer determines that reliable and uniform results are produced
by the Contractors construction techniques, the frequency of testing may
be decreased by the Engineer.
B.
2)
3)
C.
D.
b)
Moisture Content
1)
2)
B.
C.
1)
D.
Methods and equipment which are appropriate for the backfill of material shall
be employed.
1)
4.
Other thickness may be used with the prior written approval of the
Engineer.
E.
F.
G.
Excess excavated materials and materials not suitable for backfill shall be
removed from the site, as directed by the Engineer.
SECTION 02231
AGGREGATE BASE COURSE
1.
GENERAL
1.1. SECTION INCLUDES
A.
Related Sections
B.
References
C.
Products
D.
Execution
E.
Payment
B.
C.
1.3. REFERENCES
A.
B.
ASTM D2922 - Test Methods for Density of Soil and Soil-Aggregate in Place
by Nuclear Methods (Shallow Depth).
C.
ASTM D3017 - Test Methods for Moisture Content of Soil and Soil-Aggregate
Mixtures.
1.4. SUBMITTALS
A.
2.
PRODUCTS
2.1. MATERIAL
A.
Aggregate base course for pavement subgrade shall consist of hard, durable
particles or fragments of stone or gravel crushed to the required sizes.
Material shall contain an appropriate quantity of sand or other finely-divided
mineral matter which conforms to the requirements of AASHTO M147, and to
Section 703.03, CDOT Standard Specification Class 5 or Class 6 aggregate
base course. In addition, the material must have an R-value of 72 or greater,
and must be moisture stable. When produced from gravel, not less than 60
percent by weight of the aggregate retained on a No. 4 sieve shall consist of
particles have at least one fractured face. Base material shall be free from
vegetable matter and lumps or balls of clay and when placed and compacted
will result in a firm, dense, unyielding foundation.
B.
Coarse aggregate shall show a loss of not more than 50 percent when tested
in accordance with AASHTO T96 Standard Method of Test for Abrasion of
Coarse Aggregate by use of the Los Angeles Machine.
C.
Only aggregate from the Local Entity approved sources shall be used.
Approval of sources will, at a minimum, consist of supplying documented
gradation, Atterberg limits, and R-value testing on an annual basis.
D.
Grading Requirements:
Percent Passing
Size
1
1
#4
#8
#200
3.
Class 5
100
95-100
30-70
3-15
Class 6
100
30-65
25-55
3-12
EXECUTION
3.1. EXAMINATION
A.
Verify substrate has been inspected, gradients and elevations are correct, and
dry.
B.
C.
3.3. TOLERANCES
A.
B.
B.
C.
D.
Frequency of Tests: One (1) in-place density test per 1,000 square feet or
portion thereof per lift placed per day or frequencies outlined in LCUASS
Chapter 23, Table 23-1 for areas/structures within jurisdiction of the local
government entity.
3.5. SCHEDULES
A. Compact placed aggregate materials to achieve 95 percent (95%) of the density
obtained by ASTM D698 and within plus or minus three percent (3%) of the
optimum moisture content indicated by that method, or as approved by the
Engineer.
4. MEASUREMENT AND PAYMENT
4.1. PAYMENT: Payment for all work described in this section shall be included in the
lump sum or unit prices in the Bid Schedule. The lump sum and unit prices shall
include all costs for all labor, materials and equipment required to complete the
work in accordance with the Plans and Specifications.
END OF SECTION
SECTION 02575
PAVEMENT REPAIR AND RESURFACING
1.
GENERAL
1.1. DESCRIPTION: Repair or replacement of surface obstructions which the
Contractor must remove, such as pavement, drives, curbs, gutters, and similar
surfaces, as required to perform the work is described in this Section. Contractor
has the option of protecting instead of removing and replacing obstructions that
interfere with the work.
1.2. SECTION INCLUDES
A.
Related Sections
B.
Materials
C.
Execution
D.
Payment
B.
1.5. SUBMITTALS
A.
2.
MATERIALS
2.1. AGGREGATE, ASPHALT AND CONCRETE
A. All materials, such as but not limited to aggregate, bituminous material, and concrete,
which are used in the repair of surface obstructions, shall conform to the LCUASS or
relevant specifications contained herein. In the event of a conflict between the LCUASS
and these specifications, the LCUASS shall take precedence.
3.
EXECUTION
3.1. ASPHALT AND CONCRETE, INCLUDING BASE AND GRAVEL SURFACING
A.
B.
Concrete curbing, pads and drive pads associated with the existing pump
islands will be compacted road base/gravel to meet adjacent surface grade.
C.
New aggregate road base surfacing and pavement shall be installed per
LCAUSS, Chapter 25.
D.
2)
3)
All finished restorative work shall be inspected after completion of site construction activities by the
Engineer. All finished restoration work shall be of equal or superior quality, condition and workmanship to
that of the original.
4.
PAYMENT
4.1. MEASUREMENT: Measurement for pavement repair and resurfacing will be
made by the Engineer using in-place quantities.
4.2. PAYMENT: Payment for all work described in this section shall be included in the
unit prices in the Bid Schedule. The unit prices shall include all costs for all labor,
materials, and equipment required to complete the work in accordance with the
Plans and Specifications. The Contractor is required to submit with each invoice
that includes offsite disposal of petroleum contaminated soils, copies of all waste
manifests associated with disposal being invoiced.
END OF SECTION
SECTION 03100
CONCRETE FORMWORK
1.
GENERAL
1.1. SECTION INCLUDES
A.
Related Sections
B.
References
C.
Design Requirements
D.
Quality Assurance
E.
Products
F.
Execution
G.
Payment
B.
1.3. REFERENCES
A.
B.
C.
PRODUCTS
2.1. WOOD FORM MATERIALS
A.
3.
A.
Form Release Agent: Colorless mineral oil which will not stain concrete, or
absorb moisture.
B.
EXECUTION
3.1. EXAMINATION
A.
B.
C.
B.
B.
Coordinate with work of other sections in forming and placing openings, slots,
reglets, recesses, sleeves, bolts, anchors, other inserts, and components of
other Work.
4.
Do not remove forms or bracing until concrete has gained sufficient strength
to carry its own weight and imposed loads.
END OF SECTION
SECTION 03200
CONCRETE REINFORCEMENT
1.
GENERAL.
1.1. SECTION INCLUDES
A.
Related Sections
B.
References
C.
Submittals
D.
Quality Assurance
E.
Coordination
F.
Products
G.
Execution
H.
B.
1.3. REFERENCES
A.
B.
C.
D.
1.4. SUBMITTALS
A.
Perform Work in accordance with CRSI 63, 65 and Manual of Practice, ACI
301, ACI SP-66, ACI 318.
1.6. COORDINATION
A.
2.
PRODUCTS
2.1. REINFORCEMENT
3.
A.
Welded Steel Wire Fabric: ASTM A185 Plain Type. A fiber additive is not
acceptable.
B.
Steel Reinforcing:
60,000 psi.
C.
Yield strength of
EXECUTION
3.1. PLACEMENT
A.
SECTION 03300
CAST-IN-PLACE CONCRETE
1.
GENERAL
1.1. SECTION INCLUDES
A.
Related Sections
B.
References
C.
Submittals
D.
Quality Assurance
E.
Field Samples
F.
Products
G.
Execution
H.
B.
1.3. REFERENCES
A.
B.
C.
D.
E.
F.
G.
1.4. SUBMITTALS
A.
B.
C.
PRODUCTS
2.1. CONCRETE MATERIALS
A.
B.
C.
Mix and deliver concrete in accordance with ASTM C94, Alternative No. 1.
B.
C.
Measurement
4,000 psi
58-66 percent by volume
34-42 percent by volume
0.50 by weight (mass)
3/4 inch
2-4 inches
5-8%
3.
D.
E.
Use set retarding admixtures during hot weather only when approved by
Engineer.
F.
Add air entraining agent to normal weight concrete mix for work exposed to
exterior.
G.
Alternate mix designs may be provided that meet the project specification
minimum compressive strength with proven performance and that meets local
government entity criteria for review and consideration for approval.
EXECUTION
3.1. EXAMINATION
A.
B.
Verify that anchors, seats, plates, reinforcement and other items to be cast
into concrete are accurately placed, positioned securely, and will not cause
hardship in placing concrete.
Place concrete in accordance with ACI 304, ACI 301 and ACI 318.
B.
The surface of the concrete at all joints shall be thoroughly cleaned and all
loose material removed prior to placing adjoining concrete. Reference ACI
301.
C.
D.
Ensure reinforcement, inserts and embedded parts are not disturbed during
concrete placement.
E.
F.
G.
Use expansion joint material between new and existing pavement. Place
contraction joints at a maximum of 18 feet apart in new concrete pavement
per Portland Cement Association recommendations.
H.
B.
Field observation and testing will be performed in accordance with ACI 301
and under provisions of Section 01410.
B.
Provide free access to Work and cooperate with appointed testing firm.
C.
Submit proposed mix design to observation and testing firm for review seven
days prior to commencement of Work.
D.
E.
Four concrete test cylinders will be taken for every 75 or less cubic yards of
concrete placed, with a minimum of four concrete test cylinders taken per
pour.
F.
One additional test cylinder will be taken during cold weather concreting,
cured on job site under same conditions as concrete it represents.
G.
One slump test will be taken for each set of test cylinders taken; and air
content as applicable.
4.
A.
B.
C.
Do not patch, fill, touch-up, repair, or replace exposed concrete except upon
express direction of Engineer for each individual area.
4.1. PAYMENT: Payment for all work described in this section shall be included in the
lump sum or unit prices in the Bid Schedule. Those prices shall include all costs
for all labor, materials and equipment required to complete the work in
accordance with the Plans and Specifications.
END OF SECTION
SECTION 13205
ABOVE-GROUND STORAGE TANK INSTALLATION
1.
GENERAL
1.1. DESCRIPTION: The Work included under this section consists of furnishing all
labor, materials, services, equipment and appliances required to properly install
one 6,000-gallon dual-compartment double-walled AST (4,000-gallon diesel fuel
and 2,000-gallon unleaded gasoline) and dispensing systems. The AST systems
shall be delivered to the site as complete factory pre-fabricated systems including
skid-mounted tank, pumping system, piping, fill ports, sensor ports, overfill
prevention sumps, leak detection, secondary containment, and dispensers. The
installation also includes the following:
Protective bollards
Electrical service
Related Sections
B.
Performance Requirements
C.
Owner Occupancy
D.
Protection
E.
Utilities
F.
Qualifications
G.
Indemnification
H.
Products
I.
Execution
J.
Payment
B.
C.
B.
The Automatic Tank Gauging System shall be provided as an option for the
Owner to have installed as part of the system installation. The Contractor
shall provide a complete turnkey installation with or without the Automatic
Tank Gauging System.
C.
The Owner will occupy the site during the entire period of tank installation
activities. The existing diesel and gasoline storage and dispensing system at
the Livermore Shop will remain operational throughout the construction of
new facility. The installation of the new used oil AST at the Vine Street Shop
shall be operational within two days of the existing used oil AST system being
shut down. At least two weeks notice shall be given to the Owner prior to
disconnecting and removal of the existing used oil AST system. Contractor
will cooperate fully with the Owner during the work to minimize conflicts and
to facilitate Owners usage of the site.
1.6. PROTECTION
A.
The Contractor shall adequately protect the work site, adjacent property and
the general public during all phases of the project. Contractor shall be
responsible for all damages or injury due to his action or negligence.
1.7. UTILITIES
A.
1.8. QUALIFICATIONS
A.
All work under this contract must be completed under the direction of
personnel experienced and registered in the installation of above-ground fuel
storage systems in the State of Colorado.
1.9. INDEMNIFICATION
A.
2.
Contractor shall assume, indemnify and hold harmless the Engineer and the
Owner for and from any and all liability, loss and expense (including
Workmens Compensation) resulting from loss of life or damage or injury to
persons or property (including employees of either of the parties hereto)
arising in whole or in part by reason of or in a way resulting from negligent
operations under this contract, whether such operations be by said
Contractor(s), or by any Subcontractor(s), or anyone directly or indirectly
employed by either of them.
PRODUCTS
2.1. Above-Ground Storage Tank: Tank shall be skid-mounted, above-ground fuel storage
tank systems furnished as a complete factory prefabricated system. One dualcompartment AST for diesel fuel and unleaded gasoline services will be installed
per the specifications and drawings. Components of the tank package shall be as
follows:
A.
B.
C.
Vents:
Both normal pressure relief and emergency vents shall be
independent of each other and shall be designed and constructed as per
NFPA 30.
D.
E.
F.
Tank structure in its entirety shall have a 30-year warranty to include primary
and secondary tank, concrete pad, and any exterior coating, cladding, or
finish material.
G.
H.
I.
J.
2.2. Pumps
A.
Gasoline system will include a Red Jacket submersible turbine pumps-1/3 hp,
60 HZ, single phase with added wiring for auxiliary equipment, or Engineer
approved equivalent.
B.
Diesel system will include a Red Jacket submersible turbine pumps-3/4 hp, 60
HZ, single phase with added wiring for auxiliary equipment, or Engineer
approved equivalent.
2.3. Dispenser:
A.
B.
The on-road diesel system shall include Dresser-Wayne Reliance G6200 two
hose dispenser or Engineer approved equivalent.
C.
Gasoline and diesel systems shall include an Engineer approved pulser and
high hose retractor.
2.4. Nozzles: Utilize existing dispensers, Husky 1-GS automatic shut-off nozzle or
Engineer approved equivalent. Nozzles will be connected to hoses with a minimum
length of 20 feet with OPW 66 REC reconnectable breakaway.
2.5. Liquid Level Gauge: System shall include visual liquid level gauge at the tank for
product volume as supplied by Morrison Clock Gauge Model 818 or Engineer
approved equivalent.
2.6. Fill Port: Fill ports will include 2-inch male quick disconnect fitting with spill
containment sump of minimum seven gallons with integral reservoir and manual
flow back drain system. Fill ports to be located at the north side of the tank. Fill
ports must be located within spill containment box so that connections made to fill
port will be within the spill containment sump. Manual shut off valves and one way
valves will be located in each fill port pipe adjacent to the spill containment sump.
Each fill port pipe and cap will be painted appropriate color as follows;
Overfill prevention shall be provided by installing a mechanical overfill prevention valve within
the AST fill opening, OPW61 fSTOP three inch cylinder float or Engineer approved equivalent.
2.7. Automatic Tank Gauging System (ATG): Tank monitoring system for inventory
management, overfill protection, and leak detection as supplied by Veeder Root
Model TLS-300C or Engineer approved equivalent shall be installed. ATG system
to be included as an option for installation. Owner will evaluate including the ATG
system option.
A.
B.
C.
D.
Overfill alarm with audible alarm at AST Veeder Root No. 790091-001 and
790095-001
2.8. Emergency Shut-off: An emergency shut off switch shall be located north of the AST
on the south side of the existing site building, as shown in the drawings, greater
than 20 feet from the ASTs, and no further than 75 feet. A 20-pound ABC fire
extinguisher in a weather resistant box shall be mounted adjacent to the emergency
shut-off switch. Audible overfill alarm with light and alarm acknowledge unit shall
also be located adjacent to emergency shut-off switch.
2.9. Foundation Slab: Slab shall be designed in accordance with tank manufacturers
specifications and criteria as shown on the attached foundation figure
2.10. Card Reader: The Fuel Master fuel management system and island terminal will be
relocated from the existing AST system, to the south side of the new AST system
and face south, as shown in the drawings. Contractor will install all conduits for
installation of wiring to install relocated Fuel Master fuel management system.
2.11. Card Reader Cabinet: The Fuel Master fuel management system terminal will
require the installation of a new cabinet/shelter. The cabinet shall be constructed of
metal, include a motion activated light, and powder coated in color to match the
AST. The approximate cabinet dimension is shown on Drawing 3, attached, or
engineer approved equal.
2.12. Relocation of the Fuel Master fuel management system: Contractor is required to
install electrical power and conduits as required for installation and hookup of
relocated Fuel Master fuel management system.
2.13. Site Lighting Two yard lights with poles are to be installed for the Livermore Shop.
Yard lights will be located on the east and west ends of the new AST, as shown in
the drawings. Motion detectors are to be installed on lights with adjustable timers to
be approved by Engineer and Owner, approximately 10 minutes.
3.
EXECUTION
3.1. TANK INSTALLATION
A.
B.
C.
requirements for record keeping. All materials shall be turned over to the
Owners authorized representative at the time of start up and training portion
of project.
D.
2)
3)
4)
5)
6)
WITH
WHEEL
B.
Sign shall be white letters two inches tall on brilliant red background. Metal
base material shall be pre-drilled with three holes each edge prior to painting
process. Sign shall be warranted against fading or chipping for a minimum of
five years from date of installation.
C.
3.3. TESTING
A.
B.
3.4. WARRANTIES
A.
3.5. START UP
A. Contractor shall advise Engineer and Owner of intended start-up date.
Contractor shall provide training of on-site personnel in complete system
operation and all aspects of accessories and facilities relating to the tank
installation. Contractor shall notify Engineer and Owner a minimum of 72
hours prior to intended start up.
3.6. HOUSE-KEEPING
A.
At all times the premises shall be kept clean and neat. No debris shall be
allowed to remain on site overnight at any time during the project. At the
completion of the project all debris shall be removed from the site as part of
this contract. All surrounding earth work shall be left in natural or improved
condition to match surrounding terrain as per site plan for this location.
4.
PAYMENT
4.1. PAYMENT: Payment for all work described in this section shall be included in the
lump sum or unit prices in the Bid Schedule. The lump sum and unit prices shall
include all costs for all labor, materials and equipment required to complete the
work in accordance with the Plans and Specifications.
END OF SECTION