Вы находитесь на странице: 1из 297

PC-1 FORM

GOVERNMENT OF PAKISTAN

PLANNING COMMISSION

(Social Sector)

Water Supply Scheme

WATER SUPPLY SCHEME SADIQABAD , TEHSIL SADIQABAD DISTRICT


YAR KHAN

RAHIM

PC-I
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
WATER SUPPLY SCHEME
SADIQABAD , TEHSIL
SADIQABAD DISTRICT
RAHIM YAR KHAN
1

Name of Project:
WATER SUPPLY SCHEME
SADIQABAD , TEHSIL
SADIQABAD DISTRICT
RAHIM YAR KHAN

Location:

Tehsil

Sadiqabad

District:

Rahimyarkhan

Province

Punjab

Authority responsible for:


(i)

Sponsoring:

Government of Punjab.

(ii)

Execution:

P.H Engg: Department.

(iii)

Operation & Maintenance

TMA Sadiqabad

(iv)

Concerned Federal Ministry

Nil

(a) Plan Provisions:


Develoment under medium term development budgeting frame work to meet the millennium
goals , through block allocation for the year 2013-2014.
Project objectives & its relationship
with sectors objectives.
(i)
The project will provide drinking water facility to the inhabitants.
(ii)

The project will improve the health of the inhabitants.

(iii)

The project will improve the environmental condition.

HISTORY.
Sadiqabad was the town of Tehsil Ahmed Purr Lamma before 1928 but after that Tehsil headquarter was shifted to
Sadiqabad from Ahamd Pur Lamma since that it is working as headquarter Sadiqabad of District Rehim Yar Khan. It is
situated at a distance of 20 KM from Rehim Yar Khan towards west on KLP road and main track of Pakistan Railway.
Pakistan Railway track has divided Sadiqabad into two parts, one is Southern side and Northern side. The Southern side of
the town is called Mandi Town and Northern side is called old Sadiqabad. It grained importance due to production of food
grain, cotton and big mandi of agriculture products. FFC, Fatima fertilizer, sugar mills, hospital, degree college for boys &
girls, grain market etc are existed in Tehsil Sadiqabad. as per census 1998, the population of city is 144391 person. It
comprises of 29 No. union councils in whole Tehsil, 6 No falls in city are a and 23 No falls in rural area.

EXISTING FACILITIES.
1.
In 1962 a piped water supply system based on tubewells was provided. The water table started rising and with the
passage of time, sub soil water has become brackish. This scheme is abandoned and has completed its designed life.
2.
In 1963 Public Health Engineering Department proposed a water supply scheme based on canal source, which was
designed for a population of 20,000 souls at the rate of 20 gallons per head per day at a cost of Rs. 4,97,780/3.
The distribution pipelines were laid in the new town and in some parts of the old town. Later on the distribution
system was also provided to the adjoining abadies, these abadies actually were not included in the scope of the area to be
served, but there was no alternative except to share the water with these abadies because of the brackish nature of sub soil
water.
4.
Another Scheme was also framed by the Public Health Engineering Department for extension of water supply in
Mazhar Farid colony, which started functioning from 1975-76. It was also based on canal source to supply water for
population of 8600 persons at the rate of 20 gallons per head per day for approved cost of Rs. 10,59,000/- These schemes
based on canal water source are now abandoned.
5.
In 1983 a Comprehensive Water supply scheme Phase-I based on tubewell source (Chak No. 11/NP) for the
Zone-II i.e. northern side of Railway line including old town Mazhar Farid colony, Arian colony, Ilyas colony, new bus
stand, Mohallah Gharibabad etc. was designed. The tubewells of this scheme has been turned to brakish.This scheme was
administratively approved for this zone for 10 years of designed period i.e. upto 1991 and rising main for 20 years designed
period i.e. 2004. The scheme was designed @ 40 gallons/head/day and 16 hours of pumping. The main features of the
scheme are as under:1

Shallow tubewell of 0.85-cusec discharge along Jamal Din wali road.= 8 Nos.

A.C. pipe B-Class rising main 18 dia (from Tubewell to KLP road)= 18600 Rft

A.C. pipe B-Class rising main 10 dia (from KLP road Chowk to
Mazhar Farid colony water works)

= 2774 Rft.

4.

Pumping machinery 25 BHP, 140 ft head with discharge 0.85 cusec. = 8 sets.

5.

Yard piping.

1Job

Pumping chamber/pump house 8 dia.

= 8 No.

7.

Staff quarter (double room)

= 1 No.

8.

Staff quarter (single room)

= 1 No.

9.

Rising main (from KLP Chowk to Ghafoorabad ) 6dia AC pipe.

= 3000 Rft.

10.

Ground Storage Reservoir of 40 ft dia and 80000 gallons Capacity

= 1 No.

11.

Pumping machinery (40 BHP electric motor with centrifugal pump with
120 ft head)

= 2 sets.

12.

Pump House 30x12

= 1 No.

13.

Distribution system
16 dia A.C. pipe

= 1120 Rft.

12 dia A.C. pipe

= 2200 Rft.

8 dia A.C. pipe

= 1900 Rft.

6 dia A.C. pipe

= 2800 Rft.

4 dia PVC pipe

= 4800 Rft.

3 dia PVC pipe.

= 7600 Rft.

6.
In 1996 another scheme i.e. water supply scheme Sadiqabad Phase-II was started based on tubewell source for
population on southern side of Railway line. The scheme was administratively approved for Rs.607.39 Lac vide No. SO
(III) 1-24/94 dated 16.5.1996 The estimate was Technically sanctioned by the Chief Engineer (S) PHED Lahore vide No.
419/P&D dated 23.7.1996. The scope of work in this estimate was as under:1

Shallow tubewell of 1.00 cusec discharge.


(Ahmed Pur Lamma Distributory & Minor)

8 Nos.

2.

3.

Rising main.

20 dia A.C. pipe

32500 Rft.

18 dia A.C. pipe

2100 Rft

16 dia A.C. pipe

3000 Rft.

Pumping machinery
i)- 40 BHP, 200 ft head with a discharge of 1.00 cusec.

8 sets.

ii)-30 BHP, 100 ft head with a discharge of 1.50 cusec.


(At overhead bridge site)

= 2 sets.

4.

Yard piping

1 Job

Pump House 12x10

8 No.

30X24

2 No.

6.

Ground storage tank 46 dia.

1 No.

7.

Staff quarter two roomed.

2 No.

8.

Overhead Transmission line

1 Job

9.

Boundary wall.

587 Rft.

This scheme is operational now and serving population on southern side of Railway line.
7.
In 2005-06 another scheme was constructed in which 16 Nos tubewells of 0.5 Cusec discharge were installed
near Shahbaz Pur is completed and handed over to TMA Sadiqabad on 25/09/2008 and running satisfactory.This schemes
serves the population of old town Mazhar Farid colony, Arian colony, Ilyas colony, new bus stand and Mohallah Gharibabad
PROPOSAL:
It is proposed to install 10 Nos. tubewell having a discharge of 1 cusec Each along the bank of Fazal Wah distributry
flowing at a distance of 18 KM from Sadiqabad city. The proposed site falls in sweet zone. The discharge Fazal Wah
distributry is about 270 cusec at proposed site. The drinking water will be pumped through 20" i/d HDPE pipe to
intermediated pumping station at a distance of about 10 KM.Potable water from intermediate pumping station will be
pumped and supplied to the city area at various water works. Drinking water will be supplied by pumping to the abadies
provision of diesel generators has been made in the estimate to counter the electricity load shedding for continuous supply
of drinking water to the residents of the city. PC-1 /Rough cost estimate amounting to Rs. 711.538 million has been framed
in compliance of worthy CM Directive No CS(CD)CMS/12/OT-4/A/0154129 Dated 25-06-2012 and submitted for favor of
administrative approval from the competent forum
SCOPE OF WORK
i
ii
iii
iv
v

Survey and Investigation

10 Job

Tube well
(New=10)
Pump house 12'x12'
Pumping machinery
Rising main & Distribution System

10 Nos.
10 Nos.
10 Sets

500 mm dia HDPE pipe


450 mm dia HDPE pipe
400 mm dia HDPE pipe
355 mm dia HDPE pipe
12" dia PVC pipe
10" dia PVC pipe
8" dia PVC pipe
6" dia PVC pipe
4" dia PVC pipe
3" dia PVC pipe
vi
vii

Intermediate Pumping Station


GST

34000
22800
29386
1000
5420
500
7500
500
100
100

Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft

1 Job
4 Nos.

viii

ix
x

xi
xii
xiii
7

Pumping Machinery.for IPS/GST


(a) 4 cusecs,120 BHP,170' Head (IPS)
(b) 1 cusecs,30 BHP150' Head
(c) 1 cusecs,40 BHP,200' Head
(d) 3 cusecs100 BHP,200' Head
Staff Quarter
Over Head Reservoir
50000 Glns Capacity
100000 Glns Capacity
Transmission Line
Hypo chlorinator
Generator

5
2
1
2
4

sets
sets
sets
sets
Nos

2
1
18
10
6

Jobs
Jobs
Jobs
Nos.
Set

Rs.

Capital Cost Estimates

700.405 Millions.

Per Capita Cost


i) 2024

Rs

2314 /-

ii) 2034

Rs.

1716 /-

(i)

The estimate is prepared in


B1 annual 1st August
2014.To 31st January 2015

Component Year wise Physical activities


Item
Survey and Investigation
Tube well
Pump house 12'x12'
Pumping machinery
Rising main & Distribution System

500 mm dia HDPE pipe


450 mm dia HDPE pipe
400 mm dia HDPE pipe
355 mm dia HDPE pipe
12'' dia PVC pipe
10'' dia PVC pipe
8'' dia PVC pipe
6'' dia PVC pipe
4'' dia PVC pipe
3'' dia PVC pipe
Intermediate Pumping Station
GST
Pumping Machinery.for GST
(a) 4 cusecs,120 BHP,170' Head
(b) 1 cusecs,30 BHP,150' Head
(c) 1 cusecs,40 BHP,150' Head
(d) 3 cusecs,100 BHP,200' Head
Staff Quarter
Over Head Reservoir
a) 50000 Glns
a) 100000 Glns
Transmission Line
Hyphochlornator

Unit
10 Job
10 Nos.
10 Nos.
10 Sets

Year-I
100 %
100 %

Year-II

100
100

34000
29386
1000
5420
5420
500
7500
500
100
100
1
4

Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Job
Nos.

5
2
1
2
4

Sets
Sets
Sets
Sets
Job.

25
25
25
25
25

%
%
%
%
%

75
75
75
75
75

2
1
18
10

Nos.
Nos.
Nos.
Nos.

25 %
25 %
50 %

75
75
50
100

50 %

100
100
100
100
100
100
100
100
100
100
50
100

Generator
Components - Year wise Financial activities.

6 Sets

50 %

50

Unit

Year - I
Amount (Million)

Survey and Investigation

10 Job

0.574

Tube well

10 Nos.

6.997

Pump house 12'x12'

10 Nos.

Pumping machinery

10 Sets

Items

Year - II
Amount
(Million)
4.165

Million.

12.500

Rising main & Distribution System

500 mm dia HDPE pipe


450 mm dia HDPE pipe
400 mm dia HDPE pipe
355 mm dia HDPE pipe
12'' dia PVC pipe
10'' dia PVC pipe
8'' dia PVC pipe
6'' dia PVC pipe

34000 Rft
29386 Rft
29386 Rft
1000 Rft
5420 Rft

449.967

500 Rft
7500 Rft
500 Rft

4'' dia PVC pipe

100 Rft

3'' dia PVC pipe

100 Rft

Intermediate Pumping Station

1 Job

GST

4 Nos.

39.014

Million.

39.014

Million.

25.667

Pumping Machinery.for GST

(a) 4 cusecs,120 BHP,170' Head

5 Sets

2.500

Million.

7.500

(b) 1 cusecs,30 BHP,150' Head

2 Sets

0.550

Million.

1.650

(c) 1 cusecs,40 BHP,150' Head

1 Sets

0.313

Million.

0.938

(d) 1 cusecs,100 BHP,200' Head

2 Sets

0.850

Million.

2.550

0.536 Million.

1.607

Staff Quarter

4 Nos

OHR
a) 50000 Glns
a) 100000 Glns

2 Nos.

3.410

Million.

10.230

1 Nos.

2.834

Million.

8.501

Transmission Line

18 Job.

8.7267 Million.

8.727

Hyphochlornator

10 Nos.

Million.

0.450

11.050

Million.

11.050

77.35

Million.

584.515

Add 2% contingencies & petty establishment charges.

1.547

Million.

11.690

2 % Resident Supervision and design of scheme

1.547

Million.

11.690

1.25% for Compaign & Horticulture

0.967

Million.

7.306

Generator

6 Set
Total

G. Total Rs.
Say Rs.
8
A

Annual Operating Cost


Establishment
1 Operator/Chowkidar
Repair

33 No. for 12 Month @ Rs.

81.415 Million.
81.415 Million.

9000
P.Month

Rs.

615.202
615.202

3564000

Repair of Civil Work

ii

3
Repair of Pipe Line
3

iii

3 % of total cost of civil works


100 x
10828300

Rs.

324849

3 % of total cost of pipe lines.


100 x
307856045

Rs.

9235681.35

3 % of total cost of pipe lines.


100 x
29350000

Repair of Machinery
3

Rs.
Total

880500
14005030

Contingency
280101

Electric motorvertical turbine

14285131

Rs.

36247245

Rs.

54096376

1 Set

T/Well

10x35x8x0.746x365

IPS
GST 1,7,11
GST 3
GST 4

5x120x8x0.746x365
3x30x8x0.746x365
2x100x8x0.746x365
1x40x8x0.746x365
2788250 unit

Total A+B+C

Annual Operating and maintenance cost after


completion of the project.
9

Demand Supply

Financial Plan.

10

Project benefits & analysis

10

G. Total
Electric charges.

762412 unit
1306992
196049
435664
87133
13

unit
unit
unit
unit
P.Unit

Say
54096400
as per O & M cost

Attached

(i)

Financial

(ii)

Social

(iii)

Environmental

This project is social sector project and


is prepared on no loss no profit basis.
The project will provide drinking water facility
to the inhabitants,improve the health of inhabitants
and living standard of the people.
The environment will be cleaned after
completion of the project.

Social Sector benefits


Man Power employed during
execution and operation of the project
Engineer

1 Persons

Sub Engineer

2 Persons

Fore Man
Skilled
Un-Skilled

4 Persons
100 Persons
200 Persons

Salary per month


Engineer

Rs. 30000 each (P.Month)

Sub Engineer

Rs. 20000 each (P.Month)

Four Man
Skilled
Un-Skilled

Rs. 15000 each (P.Month)


Rs. 8000 each (P.Month)
Rs. 4000 each (P.Month)

(v)
11

12

Impact of delays on project


cost and viability.
Implementation of the Project
Starting Date.

Apr-14

Completion Date.

Jun-16

Nil

Management Structure &


Administrative arrangements for
implementation of the project.
1
2
3
4

Chief Engineer (S) Pb: PHE Department Lahore.


Superintending Engineer PHE Circle Bahawalpur
Excutive Engineer PHE Division Rahimyarkhan
Sub Divisional Officer PHE Sub Division Sadiqabad.

5 Sub Engineer PHE Sub Division Sadiqabad.


13

14

Additional projects/decision required


Indicate additional projects / decision
required to optimize the investment
being undertaken on the project
Certificate

Nil
Certified that the project has been prepared on the
guidelines provided by the Planning Commission for
the preparation of PC-1 for the Social Sectors

Prepared By

Executive Engineer

Public Health Engg: Division


Rahimyarkhan

Checked By

Superintending Engineer
Public Health Engg: Circle
Bahawalpur

Approved By

Chairman P & D
Lahore

Year-II

%
%
%
%
%
%
%
%
%
%
%
%
%
%
%
%
%
%
%
%
%
%
%

661.869

696.617

bitants

URBAN WATER SUPPLY SCHEME SADIQABA


Detail of Generators

Sr No

Location

Capacity of Generator
(KVA)

Proposed No of Set

Tube Wells

120

5.00

Intermediate Pumping Station

300

1.00

Zone-3 (Stadium)

300

1.00

Total

7.00

URBAN WATER SUPPLY SCHEME SADIQ


General Abstract of Discharge of Machi
Total existing Dischrge
Total Design Discharge
Balance Discharge
Total proposed Discharge
Future Extension

Zone No

Name of
Area

Population

Existing No. of Sets

Total Existing
Discharge
(Cusec)

Model
Town

28708

2.0

1.64

4.00

2.36

Haq Town

35885

1.0

2.00

5.00

3.00

Stadium

72489

2.0

6.00

12.00

6.00

35885

4.0

6.00

5.00

24582

4.0

4.00

5.00

1.00

35527

4.0

4.00

5.00

1.00

31041

2.0

1.64

4.00

2.36

4
5
6
7

Main
Water
Works
Mazher
Fareed
Colony
Ghafoora
bad
Satellite
Town

Design
Balance
Discharge Dischrge
(Cusec)
(Cusec)

Muncipal
Town

48984

2.0

3.60

9.50

5.90

New Adda

25120

1.0

0.75

3.00

2.25

11

Tibba
Zahir peer

29520

2.0

1.64

4.00

2.36

24.0

31.27

56.50

26.23

Total

SUPPLY SCHEME SADIQABAD


ct of Discharge of Machinery
=

31.27

Cusec

56.50

Cusec

25.23

Cusec

9.00

Cusec

16.87

Cusec

Propose
Sets

Proposed
Dischrge(Cusec)

Discharge
in Future
Extension
(Cusec)

1.00

1.00

1.00

3.00

2.00

6.00
-

1.00

1.00

0.00

1.00

1.00

0.00
2.36
5.90
2.25
2.36

5.00

9.00

16.87

URBAN WATER SUPPLY SCHEME SADIQABAD


General Abstract of Storage
Total existing Storage Capacity

1250000

Gallons

Total Required Storage Capacity

Balance Storage Capacity

866536

Gallons

Total proposed Storage Capacity

600000

Gallons

Future Extension

266536

Gallons

2116536 Gallons

Existing
Storage

Balance
Total
Capacity
Required
Proposed Ground
Storage
Storage Tank (GST)
(Capacity
(Gallons)
in Gallons)
(Gallons)

Zone No

Name of
Area

Population

Existing GST
(Capacity in Gallons)

Exising Over
Head Reservoir
(OHR) (Capacity in
Gallons)

Model
Town

28708

(1 x 20000) = 20000

(1 x 40000) = 40000

60000

157896

100000

50000

Haq Town

35885

(2 x 100000) = 200000

200000

200000

Nil

Nil

Stadium

72489

(2 x 50000) = 100000

Nil

100000

398700

298700

200000

100000

35885

(5 x 20000)+(1x100000)
= 200000

(1 x 40000) = 40000

240000

197400

24582

(2 x 40000) = 80000

(1 x 40000) = 40000

120000

135200

Nil

35527

(1 x 100000) = 100000

100000

195400

100000

100000

31041

(2 x 20000) = 40000

(1 x 20000) = 20000

60000

170720

100000

50000

260000

269400

10000

20000

138200

120000

4
5
6
7

Main
Water
Works
Mazher
Fareed
Colony
Ghafoora
bad
Satellite
Town

Muncipal
Town

48984

(1 x 100000) + (1 x
80000)
+ (2 x 40000) = 260000

New Adda

25120

(1 x 20000 ) = 20000

Proposed
Over Head
Reservoir (OHR)

10
11
Total

Tibba
Qadirabad
Tibba
Zahir peer

18840

(2 x 25000 ) = 50000

50000

103620

53620

29520

Nil

Nil

Nil

150000

150000

1070000

180000

1250000

2116536

866536

50000
(1 x 50000) = 50000

400000

200000

Proposed
Storage
(Capacity
in Gallons)

Capacity
for future
extension
(Gallons)

50000

50000

Nil

Nil

300000

Nil

Nil

100000

50000

50000

10000

120000

50000

Nil

50000

100000

600000

266536

EXISTING WATER SUPPLY FACILITIES.


1.
Canal source water supply scheme was completed during 1963-64 on adam sohaba distributory which is
flowing in the city having discharge 250 cusecs.Now 6 cusec canal water is being supplied through main water
works to the residents of Mohalla Ghareebabad,Mohalla Faisalabad,Mohallah Kothian anf Mohalla Islam
pura.Residents of the city are not using canal water for their drinking purposes due to contamination.
2.
A water supply scheme comprising of 8 Nos tube wells having discharge 1 cusec each was completed
during 1996.These tube wells were installed along bank of Ahmed Wah minor flowing at a distance of 18 KM from
indus river.
3.
Another water supply scheme comprising of 16 Nos tube wells having discharge 0.5 cusec each was
completed during 2008.These tube wells were installed along bank of Ahmed Wah minor near Shahbazpur
4.
16 Cusec of drinking water is being supplied from tube well sources to city Sadiqabad. 6 Cusec canal
water is being supplied to city from main water works.
5.
It is further added that 55 Nos Tube wells having discharge 1 cusec each have been installed by FFC and
Fatima Fertilizer along the bank of Ahmed Wah Minor for use of their factories and employees.The drawl of under
ground water along the bank of Ahmed Wah minor is more as compared to recharging by seepage water.Area
falls in brackish zone deeper than 100 ft.There is apprehension to change the quality of water with the passage
of time due to drawl of under ground water more than recharging.
6.
However Indus river is flowing about 25 KM away from city Sadiqabad whereas Fazil Wah Minor having
discharge 270 cusecs is flowing about 18 KM from Sadiqabad.This water supply scheme has been proposed,
based on Tube Well source along the bank of Fazil Wah instead of Ahmed Wah because already about 71 cusecs
potable water is being drawn.Sufficient potable water is available as reported by the locals and already installed
irrigation tube wells by the farmers.
7.
Rising Main has been proposed for 10 years as further extraction of ground water from the area under
consideration is not recommended. Since the present tube wells are turning brackish due to extra extraction of
ground water reservoir available. To meet ultimate demand in future, further tube wells will be installed near River
Indus after detail study.

Sub Engineer

Sub Divisional Officer


Public Healt Engg: Sub Division
Sadiqabad

Executive Engineer
Public Health Engg: Division
Rahimyarkhan

aba distributory which is


through main water
Mohalla Islam
amination.

sec each was completed


a distance of 18 KM from

rge 0.5 cusec each was


near Shahbazpur

diqabad. 6 Cusec canal

een installed by FFC and


yees.The drawl of under
by seepage water.Area
f water with the passage

Fazil Wah Minor having


me has been proposed,
already about 71 cusecs
als and already installed

ater from the area under


ue to extra extraction of
ll be installed near River

Executive Engineer
ublic Health Engg: Division
Rahimyarkhan

ROUGH COST ESTIMATE

PROVINCE

PUNJAB

DEPARTMENT

HUD AND PHE DEPARTMENT

STATION

CITY SADIQABAD
TEHSIL SADIQABAD DISTT: R.Y.KHAN.

NAME OF WORK

WATER SUPPLY SCHEME


SADIQABAD

AMOUNT

696.617 Million

ROUGH COST ESTIMATE FOR WATER SUPPLY SCHEME


SADIQABAD TEHSIL SADIQABAD DISTT: RAHIMYARKHAN.
Reference

CM Directive No CS(CD)CMS/12/OT-4/A/0154129 Dated 25-06-2012

HISTORY AND REPORT:


Sadiqabad was the town of Tehsil Ahmed Purr Lamma before 1928 but after that Tehsil headquarter was shifted to
Sadiqabad from Ahmad Pur Lamma since that it is working as headquarter Sadiqabad of District Rehim Yar Khan.
It is situated at a distance of 20 KM from Rehim Yar Khan towards west on KLP road and main track of Pakistan
Railway. Pakistan Railway track has divided Sadiqabad into two parts, one is Southern side and Northern side.
The Southern side of the town is called Mandi Town and Northern side is called old Sadiqabad. It grained
importance due to production of food grain, cotton and big mandi of agriculture products. FFC, Fatima fertilizer,
sugar mills, hospital, degree college for boys & girls, grain market etc are existed in Tehsil Sadiqabad.
as per census 1998, the population of city is 144391 person. It comprises of 29 No. union councils in whole Tehsil,
6 No falls in city are a and 23 No falls in rural area.

EXISTING WATER SUPPLY FACILITIES.


1.
In 1962 a piped water supply system based on tubewells was provided. The water table started rising
and with the passage of time, sub soil water has become brackish. This scheme is abandoned and has completed
its designed life.
2.
In 1963 Public Health Engineering Department proposed a water supply scheme based on canal source,
which was designed for a population of 20,000 souls at the rate of 20 gallons per head per day at a cost of Rs.
4,97,780/3.
The distribution pipelines were laid in the new town and in some parts of the old town. Later on the
distribution system was also provided to the adjoining abadies, these abadies actually were not included in the
scope of the area to be served, but there was no alternative except to share the water with these abadies because
of the brackish nature of sub soil water.
4.
Another Scheme was also framed by the Public Health Engineering Department for extension of water
supply in Mazhar Farid colony, which started functioning from 1975-76. It was also based on canal source to
supply water for population of 8600 persons at the rate of 20 gallons per head per day for approved cost of Rs.
10,59,000/- These schemes based on canal water source are now abandoned.
5.
In 1983 a Comprehensive Water supply scheme Phase-I based on tubewell source (Chak No.
11/NP) for the Zone-II i.e. northern side of Railway line including old town Mazhar Farid colony, Arian colony, Ilyas
colony, new bus stand, Mohallah Gharibabad etc. was designed. The tubewells of this scheme has been turned to
brakish.This scheme was administratively approved for this zone for 10 years of designed period i.e. upto 1991
and rising main for 20 years designed period i.e. 2004. The scheme was designed @ 40 gallons/head/day and 16
hours of pumping. The main features of the scheme are as under:1

Shallow tubewell of 0.85-cusec discharge along Jamal Din wali road.= 8 Nos.

A.C. pipe B-Class rising main 18 dia (from Tubewell to KLP road)= 18600 Rft

A.C. pipe B-Class rising main 10 dia (from KLP road Chowk to
Mazhar Farid colony water works)

= 2774 Rft.

4.

Pumping machinery 25 BHP, 140 ft head with discharge 0.85 cusec. = 8 sets.

5.

Yard piping.

1Job

Pumping chamber/pump house 8 dia.

= 8 No.

7.

Staff quarter (double room)

= 1 No.

8.

Staff quarter (single room)

= 1 No.

9.

Rising main (from KLP Chowk to Ghafoorabad ) 6dia AC pipe.

= 3000 Rft.

10.

Ground Storage Reservoir of 40 ft dia and 80000 gallons Capacity

= 1 No.

11.

Pumping machinery (40 BHP electric motor with centrifugal pump with
120 ft head)

12.

Pump House 30x12

13.

Distribution system

= 2 sets.
= 1 No.
16 dia A.C. pipe

= 1120 Rft.

12 dia A.C. pipe

= 2200 Rft.

8 dia A.C. pipe

= 1900 Rft.

6 dia A.C. pipe

= 2800 Rft.

4 dia PVC pipe

= 4800 Rft.

3 dia PVC pipe.

= 7600 Rft.

6.
In 1996 another scheme i.e. water supply scheme Sadiqabad Phase-II was started based on tubewell
source for population on southern side of Railway line. The scheme was administratively approved for Rs.607.39
Lac vide No. SO (III) 1-24/94 dated 16.5.1996 The estimate was Technically sanctioned by the Chief Engineer (S)
PHED Lahore vide No. 419/P&D dated 23.7.1996. The scope of work in this estimate was as under:1

Shallow tubewell of 1.00 cusec discharge.

8 Nos.

(Ahmed Pur Lamma Distributory & Minor)


2.

3.

Rising main.

20 dia A.C. pipe

32500 Rft.

18 dia A.C. pipe

2100 Rft

16 dia A.C. pipe

3000 Rft.

Pumping machinery
i)- 40 BHP, 200 ft head with a discharge of 1.00 cusec.

8 sets.

ii)-30 BHP, 100 ft head with a discharge of 1.50 cusec.


(At overhead bridge site)

= 2 sets.

4.

Yard piping

1 Job

Pump House 12x10

8 No.

30X24

2 No.

6.

Ground storage tank 46 dia.

1 No.

7.

Staff quarter two roomed.

2 No.

8.

Overhead Transmission line

1 Job

9.

Boundary wall.

587 Rft.

This scheme is operational now and serving population on southern side of Railway line.
7.
In 2005-06 another scheme was constructed in which 16 Nos tubewells of 0.5 Cusec discharge were
installed near Shahbaz Pur is completed and handed over to TMA Sadiqabad on 25/09/2008 and running
satisfactory.This schemes serves the population of old town Mazhar Farid colony, Arian colony, Ilyas colony, new
bus stand and Mohallah Gharibabad
PROPOSAL
It is proposed to install 10 Nos. tubewell having a discharge of 1 cusec Each along the bank of Fazal Wah
distributry flowing at a distance of 18 KM from Sadiqabad city. The proposed site falls in sweet zone. The
discharge Fazal Wah distributry is about 270 cusec at proposed site. The drinking water will be pumped through
20" i/d HDPE Pipe to intermediate pumping station at a distance of about 10 KM.Potable water from intermediate
pumping station will be pumped and supplied to the city area at various water works. Drinking water will be
supplied by pumping to the abadies. Provision of diesel generators has been made in the estimate to counter the
electricity load shedding for continuous supply of drinking water to the residents of the city. PC-1 /Rough cost
estimate amounting to Rs. 71.538 million has been framed in compliance of worthy CM Directive No
CS(CD)CMS/12/OT-4/A/0154129 Dated 25-06-2012 and submitted for favour of administrative approval from the
competent forum.
DESIGN
Population as per census 1998 on Page-296
PROJECTED POPULATION
Growth Rate Per Year as per census on page -17
Add upto 2008 @ 3.22 of per annum
Add upto 2014 @ 3.22 of per annum
Add upto 2024 @ 3.22 of per annum
Add upto 2029 @ 3.22 of per annum
Add upto 2034 @ 3.22 of per annum
Area of Zone-1
Area of Zone-2
Area of Zone-3
Area of Zone-4
Area of Zone-5
Area of Zone-6
Area of Zone-7
Area of Zone-8
Area of Zone-9
Area of Zone-10

144391 Persons

=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=

3.22
190885
227764
301104
349582
405864
160
200
404
200
137
198
173
273
140
105

%
Persons
Persons
Persons
Persons
Persons
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.

Area of Zone-11
Area of Zone-12
Total served area
Density per acre as per 2024
Density per acre as per 2034
TUBEWELLS
Design period
Projected Population upto 2029
Consumption
Average daily demand
349582
Maximum daily demand
17479080
Proposed working hour
Discharge per hour
26218620
Total discharge required
Already avail able discharge by T/W Ahmadpur
Already avail able discharge by T/W Ahmadpur
Already avail able discharge by Canal source

8
16

301104
405864

x
x

Total
2262
2262

/
/

x
x

50
1.5

/
Or

18

1
0.5
Total

Balance required discharge


No of Tubewell

42.74

=
=
=
=
=

180
92
2262
133
179

=
=
=
=
=
=
=
=

15
349582
50
17479080
26218620
18
1456590
65

=
=
=
=

8.00
8.00
6.00
22

Acres.
Acres.
Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.
Cusec.
Cusec.

43 Cusec.

43 No,

Say
=
43 No.
It is proposed to install 10 No. tube well of 1 cusec each on Fazal Wah Distributory and balance 33 Nos will be
installed in future.
STRAINER FOR TUBE WELLS
Discharge
Proposed size of strainer
Proposed slot opening area of strainer
Entrance Velocity
Length of strainer =
1
3.143
Add 10% safety for socket.
Total length of strainer

x
x

12
0.05

x
x

100
12

=
=
=
=
=

1
12
10
0.05
63.64

Cusec
Inch
%
ft/sec
Feet.

=
=

6.36 Feet.
70.00 Feet.

10

72.00 Feet.

RISING MAIN
Projected population upto 2034

Say

405864 Persons

Consumption per capita

Average day demand

20293209 Glns.

30439813 Glns.

Maximum day demand

20293209

1.5

Working Hour

Hourly Discharge

30439813

Already avail able discharge by T/W Ahmadpur


Already avail able discharge by T/W Fazal Wah
Already avail able discharge by Canal source

8
16

x
x

18

Discharge 2014

Discharge 10
years 2024

Discharge 15
years 2029

1691101 Glns.

75 Cusec

Say

75.00 Cusec

Total
Say

18 Hours

Or
1
0.5

Balance required discharge

50 GPCD.

=
=
=
=
=
=

Discharge 20
years 2034

Total Demand

42

Cusec

56

Cusec

65 Cusec

75

Cusec

Available 16+6+10

32

Cusec

32

Cusec

32 Cusec

32

Cusec

Balance

10

Cusec

24

Cusec

33 Cusec

43

Cusec

8.00
8.00
6.00
22
53

Cusec.
Cusec.
Cusec.
Cusec.
Cusec.

53 Cusec.

PUMPING MACHINERY FOR TUBE WELLS


Spring Level
Draw down
Seasonal variation
Difference of ground level
Loss in specials
Head loss in rising main(as per Hydrulic Statement)
Total
Say
BHP of Electric Motor
62.5
x

1
550

x
x

190
65

=
=
=
=
=
=
=
=

35.00
8.00
15.00
7.00
5.00
172
242.17
190.00

Feet.
Feet.
Feet.
Feet.
Feet.
Feet.
Feet.
Feet.

100

=
33.22 BHP.
Say
=
40 BHP.
So it is proposed to install 10 Sets of vertical turbine pumps capable to give a discharge of 1 cusec against a total
head of 190 ft: directly coupled with vertical AC Electric Motor of 40 BHP with 90 ft: column pipe assembly on tube
well.
DESIGN OF IPS
Discharge per hour
6 Hours storage capcity

450000

Proposed Capacity ofGST

20

No.

900000

22500

450000 Glns.

2700000 Glns.

Glns.

=
2,700,000 Glns.
=
2,700,000 Glns.
Say
=
900,000 Glns.
Volum of GST.
=
144,000 Cft.
Proposed No. of tanks.
=
1 No:
Capacity of tank.
=
144,000 Cft.
Proposed working depth of tank.
=
20 Ft.
Area of tank
144000 /
20
=
7,200.00 Sft.
Dia of tank=
7200
x4x7/22)^.5
=
95.75 Ft.
Say:
=
96.00 Ft.
It is proposed to construct 3 No Ground storage tank 96 ft. dia. with 20 ft. working depth and 3 ft: dead storage and 2
ft: Free Board. Total Depth of GST, is 25 Feet.
Total

PUMPING MACHINERY FOR IPS


Suction Level
Loss in specials
Difference of ground level
Head loss in rising main(as per Hydrulic Statement)
Total
Say
BHP of Electric Motor
62.5
x

4
550

x
x

170
65

=
=
=
=
=
=

25.00
5.00
7.00
67
103.70
170.00

Feet.
Feet.
Feet.
Feet.
Feet.
Feet.

100

=
118.88 BHP.
Say
=
120 BHP.
So it is proposed to install 5 Sets of vertical turbine pumps capable to give a discharge of 4 cusec against a total
head of 140 ft: directly coupled with vertical AC Electric Motor of 120 BHP with 25 ft: column pipe assembly on tube
well.
DESIGN OF ZONE -1
Area of Zone-1
Density per acre as per 2024
Density per acre as per 2034
Design period
Projected Population upto 2034
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

DESIGN OF OHR AND GST.

28708
1435420

x
x

50
1.5

2153130

/
Or
Say

18

=
=
=
=
=
=
=
=
=
=
=
=

160
133
179
20
28708
50
1435420
2153130
18
119618
5.32
5.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

Area of Zone-1
Design period
Density per acre as per 2024
Projected population upto 2034
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Available Capacity of OHR.
Available Capacity of GST.

=
=
=
=
=
=
=
=
1
1

No.
No.

40000
20000

Glns.
Glns.
Total

Balance Capacity for GST.


Say
Volum of GST.
Proposed No. of tanks.
Capacity of tank.
Proposed working depth of tank.
Area of tank
Dia of tank=

1000

16000 /
x4x7/22)^.5
Say:

16

It is proposed to construct 1 No Ground storage tank 36 ft. dia. with 16 ft. working depth
and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
Volum of GST.
Proposed No. of tanks.
Capacity of tank.
Proposed working depth of tank.
Area of tank
16000 /
16
Dia of tank=
1000
x4x7/22)^.5
Say:
It is proposed to construct 1 No Ground storage tank 25 ft. dia. with 16 ft. working depth
and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
MACHINERY FOR GST.
Design period
Density per acre asper 2024
Area served
Projected Population upto 2024
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

21298
1064910

x
x

50
1.5

1597365

/
Or
Say
2

18

Average daily demand


Available pumping set (0.82 cusecs,120' Head,20 BHP)

No

Nos

HEAD LOSSES.
Suctional Head
Loss in specials
Head loss pipe line i/c height of OHR(as per Hyd.Statement)
Total
Say
BHP of Electric Motor for 1.00 Cusec
62.5
x
1.00
550

x
x

150
60

=
=
=
=
=
=
=
=
=

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

40,000 Glns.
20,000 Glns.
60,000 Glns.
97,896
100,000
16,000
1
16,000
16
1,000.00
35.68
36.00

Glns.
Glns.
Cft.
No:
Cft.
Ft.
Sft.
Ft.
Ft.

and 1.50 ft: dead storage


=
16,000 Cft.
=
1 No:
=
16,000 Cft.
=
16 Ft.
=
1,000.00 Sft.
=
35.68 Ft.
=
36.00 Ft.
and 1.50 ft: dead storage

=
=
=
=
=
=
=
=
=
=
=
=
Say

Proposed No of Sets.

=
=
=

160
20
133
179
50
1435417
1578959
157896

=
=
=
=
=
=
=
=

10
133
160
21298
50
1064910
1597365
18
88743
3.94
4.00
1.64

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

2.36 Cusec.
2.00 Cusec.
1 No.
20.00
20.00
110
150.00
150.00

Feet.
Feet.
Feet.
Feet.
Feet.

100

=
28.41 BHP.
Say
=
30 BHP.
So it is proposed to install 1 Set of vertical turbine pumps capable to give a discharge of 1.00 cusec against a total
head of 150 Ft directly coupled with vertical AC Electric Motor of 30 BHP with 25 Ft: column pipe i/c assembly and I
No will be installed in future.
DESIGN OF ZONE -2
Area of Zone-2

200 Acres.

Density per acre as per 2024


Density per acre as per 2034
Design period
Projected Population upto 2034
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

35885
1794270

x
x

50
1.5

2691405

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-2
Design period
Density per acre as per 2024
Projected population upto 2034
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Say
available Capacity of GST.

No.

200000

Glns.
Total

Balance Capacity for GST.

Say

MACHINERY FOR GST.


Design period
Density per acre as per 2024
Area served
Projected Population upto 2024
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

26623
1331140

x
x

50
1.5

1996710

/
Or
Say

18

No

Average daily demand


Available pumping set (1 cusecs,200' head,40 BHP)

Say
=

1+1+1 Nos

72489
3624430

x
x

50
1.5

5436645

/
Or

18

Already available from cannal source

133
179
20
35885
50
1794270
2691405
18
149523
6.65
6.00

pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=

200
20
133
179
50
1794271
1973698
197370

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

197,400 Glns.

=
=

200,000 Glns.
200,000 Glns.

=
=

(2,600) Glns.
Nil Glns.

=
=
=
=
=
=
=
=
=
=
=

Balance
Proposed No of Sets in future extension.
DESIGN OF ZONE -3
Area of Zone-3
Density per acre as per 2024
Density per acre as per 2034
Design period
Projected Population upto 2034
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

=
=
=
=
=
=
=
=
=
=
=

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

2.00 Cusec.

=
=
=

3.00 Cusec.
3.00 Cusec.
3 No.

=
=
=
=
=
=
=
=
=
=
=
=

Balance
Say
DESIGN OF OHR AND GST.
Area of Zone-3
Design period

10
133
200
26623
50
1331140
1996710
18
110928
4.93
5.00

=
=

404
133
179
20
72489
50
3624430
5436645
18
302036
13.42
6.00
7.42
7.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.
Cusec.

404 Acres.
20 Year.

Density per acre as per 2024


Projected population upto 2034
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Say
Available Capacity of GST.

No.

50000

Glns.

Balance

=
=
=
=
=
=
=

133
179
50
3624428
3986871
398687
398,700

pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.
Glns.

100,000 Glns.

298,700 Glns.

=
=
=
=
=
=
=
=

200,000
32,000
1
32,000
16
2,000.00
50.46
50.00

It is proposed to construct 1 No OHR of 100000 Glns capacity.


Balance Capacity for GST.
Volum of GST.
Proposed No. of tanks.
Capacity of tank.
Proposed working depth of tank.
Area of tank
Dia of tank=

2000

32000 /
x4x7/22)^.5
Say:

16

Cft.
No:
Cft.
Ft.
Sft.
Ft.
Ft.

It is proposed to construct 1 No Ground storage tank 50 ft. dia. with 16 ft. working depth and 1.50 ft: dead storage
and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
MACHINERY FOR GST.
Design period
Density per acre as per 2024
Area served
Projected Population upto 2024
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

=
=
=
=
=
=
=
=
=
=
=

10
133
404
53778
50
2688900
4033350
18
224075
9.96
12.00

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

53778
2688900

x
x

50
1.5

4033350

/
Or
Say

18

Available pumping set (3 cusecs,200' head,100 BHP)

No

6.00 Cusec.

Proposed pumping set (2 cusecs,200' head,100 BHP)

No

6.00 Cusec.

Average daily demand

DESIGN OF ZONE -4
Area of Zone-4
Density per acre as per 2024
Density per acre as per 2034
Design period
Projected Population upto 2034
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

35885
1794270

x
x

50
1.5

2691405

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-4
Design period
Density per acre as per 2024
Projected population upto 2034
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Say

=
=
=
=
=
=
=
=
=
=
=
=

200
133
179
20
35885
50
1794270
2691405
18
149523
6.65
7.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=
=

200
20
179
35885
50
1794300
1973730
197373
197,400

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.
Glns.

available Capacity of OHR.


available Capacity of GST.

1
5

No.
No.

40000
20000

Glns.
Glns.

=
=

40,000 Glns.
100,000 Glns.

available Capacity of GST.

No.

100000

Glns.

100,000 Glns.

240,000 Glns.

Nil Glns.

Total
Balance Capacity for GST.
MACHINERY FOR GST.
Design period
Density per acre asper 2024
Area served
Projected Population upto 2024
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

26623
1331140

x
x

50
1.5

1996710

/
Or
Say
4

18

Average daily demand


Available pumping set (1.5 cusecs,200' Head,40 BHP)

No

Balance
DESIGN OF ZONE -5
Area of Zone-5
Density per acre as per 2024
Density per acre as per 2034
Design period
Projected Population upto 2034
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

24582
1229080

x
x

50
1.5

1843620

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-5
Design period
Density per acre as per 2034
Projected population upto 2034
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Say
Available Capacity of OHR.
Available Capacity of GST.

1
2

No.
No.

40000
40000

Glns.
Glns.
Total

Balance Capacity for GST.


Say
MACHINERY FOR GST.
Design period
Density per acre as per 2024
Area served
Projected Population upto 2024
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

18237
911831

x
x

50
1.5

1367746

/
Or
Say
4

18

Average daily demand


Available pumping set (1 cusecs,200' Head,40 BHP)

No

=
=
=
=
=
=
=
=
=
=
=
=

10
133
200
26623
50
1331140
1996710
18
110928
4.93
5.00
6.00

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

Nil

=
=
=
=
=
=
=
=
=
=
=
=

137
133
179
20
24582
50
1229080
1843620
18
102423
4.55
4.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=
=

137
20
179
24582
50
1229100
1352010
135201
135,200

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.
Glns.

=
=

40,000 Glns.
80,000 Glns.

120,000 Glns.

=
=

15,200 Glns.
Nil Glns.

=
=
=
=
=
=
=
=
=
=
=
=

10
133
137
18237
50
911831
1367746
18
75986
3.38
5.00
4.00

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

=
Say
=
So it is proposed to install 1 Sets of vertical turbine pumps capable to give a discharge of
1.00 cusec in future.
DESIGN OF ZONE -6
Area of Zone-6
Density per acre as per 2024
Density per acre as per 2034
Design period
Projected Population upto 2034
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

35527
1776330

x
x

50
1.5

2664495

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-6
Design period
Density per acre as per 2034
Projected population upto 2034
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Say
Available Capacity of GST.

No.

100000

Glns.
Total

Balance Capacity for GST.


Say
It is proposed to construct 1 No Ground storage tank of 100000 Glns capacity.
MACHINERY FOR GST.
Design period
Density per acre as per 2024
Area served
Projected Population upto 2024
Consumption
Average daily demand
26357
x
50
Maximum daily demand
1317828
x
1.5
Proposed working hour
Discharge per hour
1976743
/
18
Or
Average daily demand
Say
Available pumping set (1 cusecs,200' Head,40 BHP)
4
No

=
=
=
=
=
=
=
=
=
=
=
=

198
133
179
20
35527
50
1776330
2664495
18
148028
6.58
6.50

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=

198
20
179
35527
50
1776300
1953930
195393

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

195,400 Glns.

100,000 Glns.

100,000 Glns.

=
=

95,400 Glns.
100,000 Glns.

=
=
=
=
=
=
=
=
=
=
=
=

10
133
198
26357
50
1317828
1976743
18
109819
4.88
5.00
4.00

=
Say
=
So it is proposed to install 1 Sets of vertical turbine pumps capable to give a discharge of
1.00 cusec.
DESIGN OF ZONE -7
Area of Zone-7
Density per acre as per 2024
Density per acre as per 2034
Design period
Projected Population upto 2034
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

31041
1552040

x
x

50
1.5

2328060

/
Or

18

1.00 Cusec.
1.00 Cusec.

=
=
=
=
=
=
=
=
=
=
=

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

1.00 Cusec.
1.00 Cusec.

173
133
179
20
31041
50
1552040
2328060
18
129337
5.75

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.

Say

DESIGN OF OHR AND GST.


Area of Zone-7
Design period
Density per acre as per 2034
Projected population upto 2034
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Available Capacity of OHR.
Available Capacity of GST.

=
=
=
=
=
=
=
=
1
2

No.
No.

20000
20000

Glns.
Glns.
Total

=
=
=

5.00 Cusec.
173
20
179
31041
50
1552000
1707200
170720

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

20,000 Glns.
40,000 Glns.
60,000 Glns.

Balance Capacity for GST.

=
110,720 Glns.
=
60,000 Glns.
Volum of GST.
=
9,600 Cft.
Proposed No. of tanks.
=
1 No:
Capacity of tank.
=
9,600 Cft.
Proposed working depth of tank.
=
16 Ft.
Area of tank
9600 /
16
=
600.00 Sft.
Dia of tank=
600
x4x7/22)^.5
=
27.64 Ft.
Say:
=
28.00 Ft.
It is proposed to construct 1 No Ground storage tank 28 ft. dia. with 16 ft. working depth and 1.50 ft: dead storage
and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.Remaining will be constructed in future.
Say

MACHINERY FOR GST.


Design period
Density per acre as per 2024
Area served
Projected Population upto 2024
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

23029
1151440

x
x

50
1.5

1727160

/
Or
Say
2

18

Average daily demand


Available pumping set(0.82 cusecs,130' Head,40 BHP)

=
=
=
=
=
=
=
=
=
=
=
=

No
Say

Proposed No of Sets.

No

HEAD LOSSES.
Suctional Head
Loss in specials
Head loss pipe line i/c height of OHR(as per Hyd.Statement)
Total
Say
BHP of Electric Motor for 1.00 Cusec
62.5
x
1.00
550

x
x

150
60

=
=
=
=
=
=
=
=

48984
2449180

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

2.36 Cusec.
2.00 Cusec.
1 No.
20.00
20.00
110
150.00
150.00

Feet.
Feet.
Feet.
Feet.
Feet.

100

=
Say
=
So it is proposed to install 1 Set of vertical turbine pumps capable to give a discharge of 1.00
cusec against a total head of 150 Ft directly coupled with vertical AC Electric Motor of 30 BHP
with 15 Ft: column pipei/c assembly and 1 will be supplied in future.
DESIGN OF ZONE -8
Area of Zone-8
Density per acre as per 2024
Density per acre as per 2034
Design period
Projected Population upto 2034
Consumption
Average daily demand
Maximum daily demand

10
133
173
23029
50
1151440
1727160
18
95953
4.26
4.00
1.64

x
x

50
1.5

=
=
=
=
=
=
=
=

28.41 BHP.
30 BHP.

273
133
179
20
48984
50
2449180
3673770

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.

Proposed working hour


Discharge per hour

3673770

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-8
Design period
Density per acre as per 2034
Projected population upto 2034
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Say

=
=
=
=

18
204098
9.07
12.50

Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=

273
20
179
48984
50
2449200
2694120
269412

269,400 Glns.

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

Available Capacity of GST.

No.

100000

Glns.

100,000 Glns.

Available Capacity of GST.

No.

80000

Glns.

80,000 Glns.

Available Capacity of GST.

No.

40000

Glns.

80,000 Glns.

260,000 Glns.

=
=

9,400 Glns.
10,000 Glns.

Total
Balance Capacity for GST.
Say
It is proposed to construct 1 No Ground storage tank of 10000 Glns capacity in future.
MACHINERY FOR GST.
Design period
Density per acre asper 2024
Area served
Projected Population upto 2024
Consumption
Average daily demand
36340
x
50
Maximum daily demand
1817006
x
1.5
Proposed working hour
Discharge per hour
2725509
/
18
Or
Average daily demand
Say
Available pumping set(1.8 cusecs,200' Head,40 BHP)
2
No

=
=
=
=
=
=
=
=
=
=
=
=

=
Say
=
So it is proposed to install 3 Sets of vertical turbine pumps capable to give a discharge of
2.00 cusec in future.
DESIGN OF ZONE -9
Area of Zone-9
Density per acre as per 2024
Density per acre as per 2034
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

DESIGN OF OHR AND GST.


Area of Zone-9
Design period
Density per acre as per 2034
Projected population upto 2034
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR

25120
1255990

x
x

50
1.5

1883985

/
Or
Say

18

10
133
273
36340
50
1817006
2725509
18
151417
6.73
9.50
3.60

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

5.90 Cusec.
6.00 Cusec.

=
=
=
=
=
=
=
=
=
=
=
=

140
133
179
20
25120
50
1255990
1883985
18
104666
4.65
4.50

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=

140
20
179
25120
50
1256000
1381600
138160

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

Say
Available Capacity of GST.

No.

20000

Glns.
Total

Balance Capacity for GST.


Say
It is proposed to construct 1 No Ground storage tank of 120000 Glns capacity in future.
MACHINERY FOR GST.
Design period
Density per acre as per 2024
Area served
Projected Population upto 2024
Consumption
Average daily demand
18636
x
50
Maximum daily demand
931798
x
1.5
Proposed working hour
Discharge per hour
1397697
/
18
Or
Average daily demand
Say
Available pumping set(0.75 cusecs,150' Head,30 BHP)
1
No

138,200 Glns.

20,000 Glns.

20,000 Glns.

=
=

118,200 Glns.
120,000 Glns.

=
=
=
=
=
=
=
=
=
=
=
=

10
133
140
18636
50
931798
1397697
18
77650
3.45
3.00
0.75

=
Say
=
So it is proposed to install 3 Sets of vertical turbine pumps capable to give a discharge of
2.00 cusec in future.
DESIGN OF ZONE -10
Area of Zone-10
Density per acre as per 2024
Density per acre as per 2034
Design period
Projected Population upto 2034
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

18840
941990

x
x

50
1.5

1412985

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-10
Design period
Density per acre as per 2034
Projected population upto 2034
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Available Capacity of GST.

No.

25000

Glns.
Total

Balance Capacity .
Propsed
60000 Glns
It is proposed to construct 1 No OHR of 50000 Glns capacity.
DESIGN OF ZONE -11
Area of Zone-1
Density per acre as per 2024
Density per acre as per 2034
Design period
Projected Population upto 2034
Consumption
Average daily demand
Maximum daily demand
Proposed working hour

29520
1476000

x
x

Say

50
1.5

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

2.25 Cusec.
2.00 Cusec.

=
=
=
=
=
=
=
=
=
=
=
=

105
133
179
20
18840
50
941990
1412985
18
78499
3.49
3.40

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=

105
20
179
18840
50
942000
1036200
103620

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

=
=

50,000 Glns.
50,000 Glns.

=
=

53,620 Glns.
50,000 Glns.

=
=
=
=
=
=
=
=
=

180
121
164
20
29520
50
1476000
2214000
18

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.

Discharge per hour

2214000

/
Or
Say

18

=
=
=

DESIGN OF OHR AND GST.


Area of Zone-11
Design period
Density per acre as per 2034
Projected population upto 2034
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Proposed Capacity of GST.
Proposed Capacity of OHR.

1
1

No.
No.

100000
50000

=
=
=
=
=
=
=
=

180
20
164
29520
50
1476000
1623600
162360

Glns.
Glns.

=
=
=

100,000 Glns.
50,000 Glns.
150,000 Glns.

Say

=
=
=
=
=
=
=
=

100,000
16,000
1
16,000
16
1,000.00
35.68
36.00

Glns.
Cft.
No:
Cft.
Ft.
Sft.
Ft.
Ft.

=
=
=
=
=
=
=
=
=
=
=
=

10
121
180
21780
50
1089000
1633500
18
90750
4.03
4.00
1.64

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

Total

Volum of GST.
Proposed No. of tanks.
Capacity of tank.
Proposed working depth of tank.
Area of tank
Dia of tank=

16000 /
16
x4x7/22)^.5
Say:
It is proposed to construct 1 No OHR of 50000 Glns capacity &1 No Ground storage tank .
1000

MACHINERY FOR GST.


Design period
Density per acre as per 2024
Area served
Projected Population upto 2024
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

21780
1089000

x
x

50
1.5

1633500

/
Or
Say
2

18

Average daily demand


Available pumping set(0.82 cusecs,130' Head,40 BHP)

No
Say

Proposed No of Sets.

Nos

HEAD LOSSES.
Suctional Head
Loss in specials
Head loss pipe line i/c height of OHR(as per Hyd.Statement)
Total
Say
BHP of Electric Motor for 1.00 Cusec
62.5
x
2.00
550

x
x

160
60

=
=
=
=
=
=
=
=

15088

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

2.36 Cusec.
2.00 Cusec.
1 No.
20.00
5.00
0
25.00
160.00

Feet.
Feet.
Feet.
Feet.
Feet.

100

=
Say
=
So it is proposed to install 1 Set of vertical turbine pumps capable to give a discharge of 2.00
cusec against a total head of 160 Ft directly coupled with vertical AC Electric Motor of 60 BHP
with 25 Ft: column pipe i/c assembly in future.
DESIGN OF ZONE -12
Area of Zone-12
Density per acre as per 2024
Density per acre as per 2034
Design period
Projected Population upto 2034
Consumption
Average daily demand

123000 Glns.
5.47 Cusec.
9.00 Cusec.

50

=
=
=
=
=
=
=

60.61 BHP.
60 BHP.

92
121
164
20
15088
50
754400

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.

Maximum daily demand


Proposed working hour
Discharge per hour

754400

1.5

1131600

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-12
Design period
Density per acre as per 2034
Projected population upto 2034
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Available Capacity of GST

No.

10000

Glns.
Total

Balance Capacity for GST.


Say
Volum of GST.
Proposed No. of tanks.
Capacity of tank.
Proposed working depth of tank.
Area of tank
Dia of tank=

9600 /
16
x4x7/22)^.5
Say:
It is proposed to construct 1 No Ground storage tank of 60000 Glns capacity in future.
600

MACHINERY FOR GST.


Design period
Density per acre as per 2024
Area served
Projected Population upto 2024
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

11132
556600

x
x

50
1.5

834900

/
Or
Say
1

18

Average daily demand


Available pumping set(1 cusecs,160' Head,30 BHP)

No
Say

Proposed No of Sets.

1+1

Nos

HEAD LOSSES.
Suctional Head
Loss in specials
Head loss pipe line i/c height of OHR(as per Hyd.Statement)
Total
Say
BHP of Electric Motor for 1.00 Cusec
62.5
x
1.00
550

x
x

160
60

=
=
=
=
=

1131600
18
62867
2.79
3.00

=
=
=
=
=
=
=
=

92
20
164
15088
50
754400
829840
82984

=
=

20,000 Glns.
20,000 Glns.

=
=
=
=
=
=
=
=
=

62,984
60,000
9,600
1
9,600
16
600.00
27.64
28.00

Glns.
Glns.
Cft.
No:
Cft.
Ft.
Sft.
Ft.
Ft.

=
=
=
=
=
=
=
=
=
=
=
=

10
121
92
11132
50
556600
834900
18
46383
2.06
2.00
1.64

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

=
=
=
=
=
=
=
=

=
=
=
=
=

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

0.36 Cusec.
2.00 Cusec.
2 No.
20.00
20.00
110
150.00
160.00

Feet.
Feet.
Feet.
Feet.
Feet.

100

=
Say
=
2 Sets of vertical turbine pumps capable to give a discharge of 1.00 cusec will be installed in
future.

SCOPE OF WORK
The estimate consists of following scope.
1 Sub Work No.1
Survay & Investigation
2 Sub Work No.2
Tubewell 1 Cusec discharge
3 Sub Work No.3
Pump House 12'x12'
4 Sub Work No.4
Pumping Machinery For T/W
5 Sub Work No.5
Rising Main/Inter Connection

Glns.
Hours.
Glns.
Cusec.
Cusec.

10
10
10
10

Job
Nos
Nos
Sets

30.30 BHP.
30 BHP.

500 mm dia HDPE pipe


450 mm dia HDPE pipe
400 mm dia HDPE pipe
355 mm dia HDPE pipe
12'' dia PVC pipe
10'' dia PVC pipe
8'' dia PVC pipe
6'' dia PVC pipe
4'' dia PVC pipe
3'' dia PVC pipe
IPS
6 Sub Work No.6
G.S.T
7 Sub Work No.7
8 Sub Work No.8
Pumping Machinery.for

a)
b)
c)
d)

4 cusecs,100 BHP,140' Head (IPS)


1 cusecs,30 BHP,150' Head
1 cusecs,40 BHP,200' Head
3 cusecs,100 BHP,200' Head

=
=
=
=
=
=
=
=
=
=
=

34000
22800
29386
1000
5420
500
7500
500
100
100
1
4

Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
No
Nos

=
=
=
=
=

5
2
1
2
4

Sets
Sets
Sets
Nos
Nos

9 Sub Work No.9


Staff Qaurter
10 Sub Work No.10
OHR
a)
50000 Glns
=
2 Nos
a)
100000 Glns
=
1 Nos
11 Sub Work No.11
Transmission Line
=
18 Jobs
12 Sub Work No 12 Hyphochlornator
=
10 Nos
13 Sub Work No 13 Generator
=
6 Set
RATES
Rates provided in the estimate as per market for non schedule items and as per
market schedule ratesB1 Annual(1ST Feb 2014, TO 31ST JUly 2014)
SPECIFICATION
The Work will be completed according to PHE specification inforced at
the time of execution of work and upto entire satisfication of Engineer in Charge.
FUNDS
Total funds will be provided by the Govt: of Punjab .
TIME LIMIT
The work will take 3 years for completion if full funds will be provided by the Govt:
LAND
The land will be purchased for intermediate pumping station by PHE department/TMA
O & M COST
After completion of the scheme TMA Sadiqabad will be responsible for O & M
COST
Total cost of the estimate is work out to

Sub Engineer

696.617 Millions

Sub Divisional Officer


Public Healt Engg: Sub Division
Sadiqabad

Executive Engineer
Public Health Engg: Division
Rahimyarkhan

ONE PAGE NOTE


Name of Scheme

: WATER SUPPLY SCHEME SADIQABAD TEHSIL


SADIQABAD DISTT: RAHIMYARKHAN.

Status

: Minute has been issued and administrative approval still awaited.

A.A Cost

: 692.527 Million

T.S Cost
Design Population
Date of commencement
Allocation 2013-2014.
Total Expenditure Upto
11/05/2014

:
: 405864 Person
:
: 20 Million
:

CM Directive No CS(CD)CMS/12/OT4/A/0154129 Dated 25-06-2012

PHYSICAL ACHIEVEMENT
Sr.#

Description of Item

1
2
3
4
5

Survay & Investigation


Tubewell 1 Cusec discharge
Pump House 12'x12'
Pumping Machinery For T/W
Rising Main/Inter Connection
500 mm dia HDPE pipe
450 mm dia HDPE pipe
400 mm dia HDPE pipe
355 mm dia HDPE pipe
12'' dia PVC pipe
10'' dia PVC pipe
8'' dia PVC pipe
6'' dia PVC pipe
4'' dia PVC pipe
3'' dia PVC pipe
IPS
G.S.T
Pumping Machinery.for
4 cusecs,100 BHP,140' Head (IPS)
1 cusecs,30 BHP,150' Head
1 cusecs,40 BHP,200' Head
3 cusecs,100 BHP,200' Head
Staff Qaurter
OHR
50000 Glns
100000 Glns
Transmission Line
Hyphochlornator
Generator With Room

6
7
8

9
10

11
12
13

Quantity As Per Total Work Done till


A.A Estimate
to date

Balance Work
yet to be
Remarks
executed
-

10
10
10
10

Job
Nos
Nos
Sets

34000
22800
29386
1000
5420
500
7500
500
100
100
1
4

Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
No
Nos

5
2
1
2
4

Sets
Sets
Sets
Nos
Nos

2
1
18
10
6

Nos
Nos
Jobs
Nos
Set

AMMENDED ROUGH COST ESTIMATE

PROVINCE

PUNJAB

DEPARTMENT

HUD AND PHE DEPARTMENT

STATION

CITY SADIQABAD
TEHSIL SADIQABAD DISTT: R.Y.KHAN.

NAME OF WORK

WATER SUPPLY SCHEME


SADIQABAD

AMOUNT

700.405 Million

ROUGH COST ESTIMATE FOR WATER SUPPLY SCHEME


SADIQABAD TEHSIL SADIQABAD DISTT: RAHIMYARKHAN.
Reference

CM Directive No CS(CD)CMS/12/OT-4/A/0154129 Dated 25-062012

HISTORY AND REPORT:

Sadiqabad was the town of Tehsil Ahmed Purr Lamma before 1928 but after that Tehsil headquarter
was shifted to Sadiqabad from Ahamd Pur Lamma since that it is working as headquarter Sadiqabad
of District Rehim Yar Khan. It is situated at a distance of 20 KM from Rehim Yar Khan towards west
on KLP road and main track of Pakistan Railway. Pakistan Railway track has divided Sadiqabad into
two parts, one is Southern side and Northern side. The Southern side of the town is called Mandi
Town and Northern side is called old Sadiqabad. It grained importance due to production of food
grain, cotton and big mandi of agriculture products. FFC, Fatima fertilizer, sugar mills, hospital,
degree college for boys & girls, grain market etc are existed in Tehsil Sadiqabad.
as per census 1998, the population of city is 144391 person. It comprises of 29 No. union councils in
whole Tehsil, 6 No falls in city are a and 23 No falls in rural area.
EXISTING WATER SUPPLY FACILITIES.
1.
In 1962 a piped water supply system based on tubewells was provided. The water table
started rising and with the passage of time, sub soil water has become brackish. This scheme is
abandoned and has completed its designed life.
2.
In 1963 Public Health Engineering Department proposed a water supply scheme based on
canal source, which was designed for a population of 20,000 souls at the rate of 20 gallons per head
per day at a cost of Rs. 4,97,780/3.
The distribution pipelines were laid in the new town and in some parts of the old town. Later
on the distribution system was also provided to the adjoining abadies, these abadies actually were
not included in the scope of the area to be served, but there was no alternative except to share the
water with these abadies because of the brackish nature of sub soil water.
4.
Another Scheme was also framed by the Public Health Engineering Department for
extension of water supply in Mazhar Farid colony, which started functioning from 1975-76. It was also
based on canal source to supply water for population of 8600 persons at the rate of 20 gallons per
head per day for approved cost of Rs. 10,59,000/- These schemes based on canal water source are
now abandoned.
5.
In 1983 a Comprehensive Water supply scheme Phase-I based on tubewell source
(Chak No. 11/NP) for the Zone-II i.e. northern side of Railway line including old town Mazhar Farid
colony, Arian colony, Ilyas colony, new bus stand, Mohallah Gharibabad etc. was designed. The
tubewells of this scheme has been turned to brakish.This scheme was administratively approved for
this zone for 10 years of designed period i.e. upto 1991 and rising main for 20 years designed period
i.e. 2004. The scheme was designed @ 40 gallons/head/day and 16 hours of pumping. The main
features of the scheme are as under:1
Shallow tubewell of 0.85-cusec discharge along Jamal Din wali road.= 8 Nos.
2

A.C. pipe B-Class rising main 18 dia (from Tubewell to KLP road)= 18600 Rft

A.C. pipe B-Class rising main 10 dia (from KLP road Chowk to
Mazhar Farid colony water works)

= 2774 Rft.

4.

Pumping machinery 25 BHP, 140 ft head with discharge 0.85 cusec. = 8 sets.

5.

Yard piping.

1Job

Pumping chamber/pump house 8 dia.

= 8 No.

7.

Staff quarter (double room)

= 1 No.

8.

Staff quarter (single room)

= 1 No.

9.

Rising main (from KLP Chowk to Ghafoorabad ) 6dia AC pipe.

10.

Ground Storage Reservoir of 40 ft dia and 80000 gallons Capacity = 1 No.

11.

Pumping machinery (40 BHP electric motor with centrifugal pump with

12.

120 ft head)

= 2 sets.

Pump House 30x12

= 1 No.

= 3000 Rft.

13.

Distribution system

16 dia A.C. pipe

= 1120 Rft.

12 dia A.C. pipe

= 2200 Rft.

8 dia A.C. pipe

= 1900 Rft.

6 dia A.C. pipe

= 2800 Rft.

4 dia PVC pipe

= 4800 Rft.

3 dia PVC pipe.

= 7600 Rft.

6.
In 1996 another scheme i.e. water supply scheme Sadiqabad Phase-II was started based
on tubewell source for population on southern side of Railway line. The scheme was administratively
approved for Rs.607.39 Lac vide No. SO (III) 1-24/94 dated 16.5.1996 The estimate was Technically
sanctioned by the Chief Engineer (S) PHED Lahore vide No. 419/P&D dated 23.7.1996. The scope of
work in this estimate was as under:1

Shallow tubewell of 1.00 cusec discharge.

8 Nos.

(Ahmed Pur Lamma Distributory & Minor)


2.

3.

Rising main.

20 dia A.C. pipe

32500 Rft.

18 dia A.C. pipe

2100 Rft

16 dia A.C. pipe

3000 Rft.

Pumping machinery
i)- 40 BHP, 200 ft head with a discharge of 1.00 cusec. 8 sets.
ii)-30 BHP, 100 ft head with a discharge of 1.50 cusec.
(At overhead bridge site)

= 2 sets.

4.

Yard piping

1 Job

Pump House
30X212x10

8 No.

2 No.

6.

Ground storage tank 46 dia.

1 No.

7.

Staff quarter two roomed.

2 No.

8.

Overhead Transmission line

1 Job

9.

Boundary wall.

587 Rft.

This scheme is operational now and serving population on southern side of Railway line.
7.
In 2005-06 another scheme was constructed in which 16 Nos tubewells of 0.5 Cusec
discharge were installed near Shahbaz Pur is completed and handed over to TMA Sadiqabad on
25/09/2008 and running satisfactory.This schemes serves the population of old town Mazhar Farid
colony, Arian colony, Ilyas colony, new bus stand and Mohallah Gharibabad
PROPOSAL
It is proposed to install 20 Nos. tubewell having a discharge of 1 cusec Each along the bank of Fazal
Wah distributry flowing at a distance of 18 KM from Sadiqabad city. The proposed site falls in sweet
zone. The discharge Fazal Wah distributry is about 270 cusec at proposed site. The drinking water
will be pumped through 28" i/d AC pipe B-Class to intermediated pumping station at a distance of
about 10 KM to control the head form intermediate pumping station will be pumped and supplied to
the city area at various water works. Drinking water will be supplied by pumping to the abadies
provision of diesel generators has been made in the estimate to counter the electrical load shedding
for continuous supply of drinking water to the residents of the city PC-1 /Rough cost estimate
amounting to Rs. 935.206 million has been framed in compliance of worthy CM Directive No
CS(CD)CMS/12/OT-4/A/0154129 Dated 25-06-2012 and submitted for favor of administrative
approval from the competent forum.
DESIGN
Population as per census 1998 on Page-296
PROJECTED POPULATION
Growth Rate Per Year as per census on page -17
Add upto 2008 @ 3.22 of per annum
Add upto 2013 @ 3.22 of per annum
Add upto 2023 @ 3.22 of per annum
Add upto 2028 @ 3.22 of per annum
Add upto 2033 @ 3.22 of per annum

144391 Persons

=
=
=
=
=
=

3.22
190885
227764
301104
349582
405864

%
Persons
Persons
Persons
Persons
Persons

Area of Zone-1
Area of Zone-2
Area of Zone-3
Area of Zone-4
Area of Zone-5
Area of Zone-6
Area of Zone-7
Area of Zone-8
Area of Zone-9
Area of Zone-10
Area of Zone-11
Area of Zone-12
Total served area
Density per acre as per 2023
Density per acre as per 2033
TUBEWELLS
Design period
Projected Population upto 2014
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

301104
405864

/
/

227764
11388190

x
x

50
1.5

17082285

/
Or

18

Already avail able discharge by T/W Ah 8


Already avail able discharge by T/W Faz 16
Already avail able discharge by Canal so

x
x

Total
2262
2262

1
0.5
Total

Balance required discharge


No of Tubewell

20.18

=
=
=
=
=
=
=
=
=
=
=
=
=
=
=

160
200
404
200
137
198
173
273
140
105
180
92
2262
133
179

=
=
=
=
=
=
=
=

15
227764
50
11388190
17082285
18
949016
42

=
=
=
=

8.00
8.00
6.00
22

Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.
Cusec.
Cusec.

20 Cusec.

20 No,

Say
=
42 No.
It is proposed to install 10 No. tube well of 1 cusec each on Fazal Wah Distributory to provide immediate
relief to public due to finicial constants.futher shortage will be met in phase-II.
Design period
=
15 Year.
Projected Population upto 2029
=
349582 Persons
Consumption
=
50 GPCD.
Average daily demand
349582
x
50
=
17479080 Glns.
Maximum daily demand
17479080
x
1.5
=
26218620 Glns.
Proposed working hour
=
18 Hours.
Discharge per hour
26218620
/
18
=
1456590 Glns.
Or
=
65 Cusec.
Already avail able discharge by T/W Ah 8
Already avail able discharge by T/W Faz 16
Already avail able discharge by Canal so

x
x

1
0.5
Total

Balance required discharge


No of Tubewell

42.74

=
=
=
=

8.00
8.00
6.00
22

Cusec.
Cusec.
Cusec.
Cusec.

43 Cusec.

43 No,

Say
=
42 No.
It is proposed to install 10 No. tube well of 1 cusec each on Fazal Wah Distributory and balance 31 Nos
will be installed in phase-II in future.
STRAINER FOR TUBE WELLS
Discharge

1 Cusec

Proposed size of strainer


Proposed slot opening area of strainer
Entrance Velocity
Length of strainer =
1 x
3.143 x
Add 10% safety for socket.
Total length of strainer

12
0.05

x
x

100
12

Say

=
=
=
=

12
10
0.05
63.64

Inch
%
ft/sec
Feet.

=
=

6.36 Feet.
70.00 Feet.

72.00 Feet.

x 10

RISING MAIN
Projected population upto 2034

Consumption per capita

Average day demand

15588450 Glns.

23382675 Glns.

Maximum day demand

15588450

1.5

Working Hour

Hourly Discharge

23382675

Already avail able discharge by T/W Ah 8


Already avail able discharge by T/W Faz 16
Already avail able discharge by Canal so

18

x
x

1299038 Glns.
58 Cusec

Say

58.00 Cusec

1
0.5

Say
Discharge 15
years 2029

18 Hours

Total

Discharge 10
years 2024

50 GPCD.

Or

Balance required discharge

Discharge 2014

311769 Persons

=
=
=
=
=
=

8.00
8.00
6.00
22
36

Cusec.
Cusec.
Cusec.
Cusec.
Cusec.

52.00 Cusec.

Discharge 20
years 2034

Total Demand

42

Cusec

49

Cusec

53 Cusec

58

Cusec

Available 16+6+10

32

Cusec

32

Cusec

32 Cusec

32

Cusec

Balance

10

Cusec

17

Cusec

21 Cusec

26

Cusec

DESIGN OF RISING MAIN


Discharge
Size of pipe
Velocity
PUMPING MACHINERY FOR TUBE WELLS

10 Cusec
20 Inch
4.58 Ft/sec

Spring Level
=
35.00 Feet.
Draw down
=
8.00 Feet.
Seasonal variation
=
15.00 Feet.
Difference of ground level
=
7.00 Feet.
Loss in specials
=
5.00 Feet.
Head loss in rising main and inter connections of tube wells(as per =
212 Feet.
Total
=
282.23 Feet.
Say
=
285.00 Feet.
BHP of Electric Motor
62.5
x
1
x
285
x
100
550
x
75
=
43.18 BHP.
Say
=
50 BHP.
So it is proposed to install 10 Sets of vertical turbine pumps capable to give a discharge of 1 cusec
against a total head of 285 ft: directly coupled with vertical AC Electric Motor of 50 BHP with 90 ft:
column pipe assembly on tube well.
DESIGN OF IPS
Discharge per hour
6 Hours storage capcity
Proposed Capacity ofGST

450000
3

20

*
No.

22500

450000 Glns.

2700000 Glns.

900000
Glns.
Total
Say

=
=
=

2,700,000 Glns.
2,700,000 Glns.
900,000 Glns.

Volum of GST.
Proposed No. of tanks.
Capacity of tank.
Proposed working depth of tank.
Area of tank
Dia of tank=

=
144,000 Cft.
=
1 No:
=
144,000 Cft.
=
20 Ft.
144000 /
20
=
7,200.00 Sft.
7200
x4x7/22)^.5
=
95.75 Ft.
Say:
=
96.00 Ft.
It is proposed to construct 3No Ground storage tank 96 ft. dia. with 24 ft. working depth and 1.50 ft: dead
storage and 1.0 ft: Free Board. Total Depth of GST, is 25 Feet.
PUMPING MACHINERY FOR IPS
Suction Level
Loss in specials
Difference of ground level
Head loss in rising main(as per Hydrulic Statement)
Total
Say
BHP of Electric Motor
62.5
x

4
550

x
x

170
65

=
=
=
=
=
=

25.00
5.00
7.00
67
103.70
170.00

Feet.
Feet.
Feet.
Feet.
Feet.
Feet.

100

=
118.88 BHP.
Say
=
120 BHP.
So it is proposed to install 6 Sets of vertical turbine pumps capable to give a discharge of 4 cusec
against a total head of 140 ft: directly coupled with vertical AC Electric Motor of 100 BHP with 25 ft:
column pipe assembly on tube well.
DESIGN OF ZONE -1
Area of Zone-1
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

28708
1435420

x
x

50
1.5

2153130

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-1
Design period
Density per acre as per 2023
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Available Capacity of OHR.
Available Capacity of GST.

1
1

No.
No.

20000
20000

Glns.
Glns.
Total

=
=
=
=
=
=
=
=
=
=
=
=

160
133
179
20
28708
50
1435420
2153130
18
119618
5.32
5.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=

160
20
133
179
50
1435417
1578959
157896

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

=
=
=

20,000 Glns.
20,000 Glns.
40,000 Glns.

Balance Capacity for GST.

=
117,896 Glns.
=
100,000 Glns.
Volum of GST.
=
16,000 Cft.
Proposed No. of tanks.
=
1 No:
Capacity of tank.
=
16,000 Cft.
Proposed working depth of tank.
=
16 Ft.
Area of tank
16000 /
16
=
1,000.00 Sft.
Dia of tank=
1000
x4x7/22)^.5
=
35.68 Ft.
Say:
=
36.00 Ft.
It is proposed to construct 1 No Ground storage tank 36 ft. dia. with 16 ft. working depth and 1.50 ft: dead
storage and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
Say

MACHINERY FOR GST.


Design period
Density per acre asper 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

21298
1064910

x
x

50
1.5

1597365

/
Or
Say
2

18

Average daily demand


Available pumping set (0.82 cusecs,120' Head,20 BHP)

=
=
=
=
=
=
=
=
=
=
=
=

No
Say

Proposed No of Sets.

1+1

HEAD LOSSES.
Suctional Head
Loss in specials
Head loss pipe line i/c height of OHR(as per Hyd.Statement)

No
s

Total
Say
BHP of Electric Motor for 1.00 Cusec
62.5
x
1.00
x
550
x

150
60

=
=
=
=
=
=
=
=

10
133
160
21298
50
1064910
1597365
18
88743
3.94
4.00
1.64

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

2.36 Cusec.
2.00 Cusec.
2 No.
20.00
20.00
110
150.00
150.00

Feet.
Feet.
Feet.
Feet.
Feet.

100

=
28.41 BHP.
Say
=
30 BHP.
So it is proposed to install 2 Sets of vertical turbine pumps capable to give a discharge of 1.00 cusec
against a total head of 150 Ft directly coupled with vertical AC Electric Motor of 30 BHP with 15 Ft:
column pipe i/c assembly
DESIGN OF ZONE -2
Area of Zone-2
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

35885
1794270

x
x

50
1.5

2691405

/
Or
Say

18

=
=
=
=
=
=
=
=
=
=
=
=

200
133
179
20
35885
50
1794270
2691405
18
149523
6.65
6.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

DESIGN OF OHR AND GST.


Area of Zone-2
Design period
Density per acre as per 2023
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR

available Capacity of GST.

No.

=
=
=
=
=
=
=
=

200
20
133
179
50
1794271
1973698
197370

Say

197,400 Glns.

200000
Glns.
Total

=
=

200,000 Glns.
200,000 Glns.

=
=

(2,600) Glns.
Nil Glns.

Balance Capacity for GST.


MACHINERY FOR GST.
Design period
Density per acre as per 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

Say

26623
1331140

x
x

50
1.5

1996710

/
Or
Say

18

No

Average daily demand


Available pumping set (1 cusecs,200' head,40 BHP)

=
=
=
=
=
=
=
=
=
=
=

Balance
Say
Proposed No of Sets in future extension.
DESIGN OF ZONE -3
Area of Zone-3
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
72489
Maximum daily demand
3624430
Proposed working hour
Discharge per hour
5436645

DESIGN OF OHR AND GST.


Area of Zone-3
Design period
Density per acre as per 2023
Projected population upto 2033
Consumption per capita

1+1+1 No
s

x
x

50
1.5

/
Or
Say

18

10
133
200
26623
50
1331140
1996710
18
110928
4.93
5.00

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

2.00 Cusec.

=
=
=

3.00 Cusec.
3.00 Cusec.
3 No.

=
=
=
=
=
=
=
=
=
=
=
=

404
133
179
20
72489
50
3624430
5436645
18
302036
13.42
7.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=

404
20
133
179
50

Acres.
Year.
pers/acre
Persons
GPCD.

Average day demand


Adding 10% for institutions
Take 1/10 of average day demand for OHR
Say
Available Capacity of GST.

No.

100000

Glns.

Balance
Balance Capacity for GST.
Volum of GST.
Proposed No. of tanks.
Capacity of tank.
Proposed working depth of tank.
Area of tank
Dia of tank=

Say

2000

32000 /
x4x7/22)^.5
Say:

16

=
=
=
=

3624428
3986871
398687
398,700

Glns.
Glns.
Glns.
Glns.

200,000 Glns.

198,700 Glns.

=
=
=
=
=
=
=
=

200,000
32,000
1
32,000
16
2,000.00
50.46
50.00

Cft.
No:
Cft.
Ft.
Sft.
Ft.
Ft.

It is proposed to construct 1 No Ground storage tank 50 ft. dia. with 16 ft. working depth and 1.50 ft: dead
storage and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
MACHINERY FOR GST.
Design period
Density per acre as per 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

=
=
=
=
=
=
=
=
=
=
=

10
133
404
53778
50
2688900
4033350
18
224075
9.96
10.00

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

53778
2688900

x
x

50
1.5

4033350

/
Or
Say

18

Available pumping set (3 cusecs,200' head,100 BHP)

No

6.00 Cusec.

Proposed pumping set (3 cusecs,200' head,100 BHP)

No

6.00 Cusec.

Average daily demand

DESIGN OF ZONE -4
Area of Zone-4
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

35885
1794270

x
x

50
1.5

2691405

/
Or
Say

18

=
=
=
=
=
=
=
=
=
=
=
=

200
133
179
20
35885
50
1794270
2691405
18
149523
6.65
7.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

DESIGN OF OHR AND GST.


Area of Zone-4
Design period
Density per acre as per 2023
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR

=
=
=
=
=
=
=
=
=

Say
available Capacity of OHR.
available Capacity of GST.

1
1

No.
No.

40000
20000

Glns.
Glns.
Total

Balance Capacity for GST.


Say
Volum of GST.
Proposed No. of tanks.
Capacity of tank.
Proposed working depth of tank.
Area of tank
Dia of tank=

1000

16000 /
x4x7/22)^.5
Say:

16

200
20
179
35885
50
1794300
1973730
197373
197,400

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.
Glns.

=
=

40,000 Glns.
20,000 Glns.

60,000 Glns.

=
=
=
=
=
=
=
=
=

137,400
100,000
16,000
1
16,000
16
1,000.00
35.68
36.00

Glns.
Glns.
Cft.
No:
Cft.
Ft.
Sft.
Ft.
Ft.

It is proposed to construct 1 No Ground storage tank 36 ft. dia. with 16 ft. working depth and 1.50 ft: dead
storage and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
MACHINERY FOR GST.
Design period
=
10 Year.
Density per acre asper 2023
=
133 pers/acre
Area served
=
200 Acres.
Projected Population upto 2023
=
26623 Persons
Consumption
=
50 GPCD.
Average daily demand
26623
x
50
=
1331140 Glns.
Maximum daily demand
1331140
x
1.5
=
1996710 Glns.
Proposed working hour
=
18 Hours.
Discharge per hour
1996710
/
18
=
110928 Glns.
Or
=
4.93 Cusec.
Average daily demand
Say
=
5.00 Cusec.
Available pumping set (1 cusecs,200' Head,40 BHP)
4
No
=
4.00 Cusec.
Say
Proposed No of Sets.

1+1

HEAD LOSSES.
Suctional Head
Loss in specials
Head loss pipe line i/c height of OHR(as per Hyd.Statement)

No
s

Total
Say

=
=
=
=
=
=
=
=

1.00 Cusec.
2.00 Cusec.
2 No.
20.00
20.00
157
197.00
200.00

Feet.
Feet.
Feet.
Feet.
Feet.

BHP of Electric Motor for 1.00 Cusec


62.5
x
1.00
x
550
x

200
60

100

Say
So it is proposed to install 2 Sets of vertical turbine pumps capable to give a
discharge of 1.00 cusec against a total head of 200 Ft directly coupled with
vertical AC Electric Motor of 40 BHP with 15 Ft: column pipei/c assembly

DESIGN OF ZONE -5
Area of Zone-5
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

24582
1229080

x
x

50
1.5

1843620

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-5
Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Say
Available Capacity of OHR.
Available Capacity of GST.

1
2

No.
No.

40000
40000

Glns.
Glns.
Total

Balance Capacity for GST.


Say
MACHINERY FOR GST.
Design period
Density per acre as per 2023
Area served
Projected Population upto 2023
Consumption

=
=

37.88 BHP.
40 BHP.

=
=
=
=
=
=
=
=
=
=
=
=

137
133
179
20
24582
50
1229080
1843620
18
102423
4.55
4.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=
=

137
20
179
24582
50
1229100
1352010
135201
135,200

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.
Glns.

=
=

40,000 Glns.
80,000 Glns.

120,000 Glns.

=
=

15,200 Glns.
Nil Glns.

=
=
=
=
=

10
133
137
18237
50

Year.
pers/acre
Acres.
Persons
GPCD.

Average daily demand


Maximum daily demand
Proposed working hour
Discharge per hour

18237
911831

x
x

50
1.5

1367746

/
Or
Say
4

18

Average daily demand


Available pumping set (1 cusecs,200' Head,40 BHP)

=
=
=
=
=
=
=

No

Say
So it is proposed to install 1 Sets of vertical turbine pumps capable to give a
discharge of 1.00 cusec in future.
DESIGN OF ZONE -6
Area of Zone-6
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

35527
1776330

x
x

50
1.5

2664495

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-6
Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Say
Available Capacity of GST.

No.

100000
Total

Balance Capacity for GST.

Glns.

=
=

911831
1367746
18
75986
3.38
5.00
4.00

Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

1.00 Cusec.
1.00 Cusec.

=
=
=
=
=
=
=
=
=
=
=
=

198
133
179
20
35527
50
1776330
2664495
18
148028
6.58
6.50

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=

198
20
179
35527
50
1776300
1953930
195393

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

195,400 Glns.

100,000 Glns.

100,000 Glns.

=
95,400
Say
=
100,000
It is proposed to construct 1 No Ground storage tank of 100000 Glns capacity in future.
MACHINERY FOR GST.
Design period
=
10
Density per acre as per 2023
=
133
Area served
=
198
Projected Population upto 2023
=
26357

Glns.
Glns.

Year.
pers/acre
Acres.
Persons

Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

26357
1317828

x
x

50
1.5

1976743

/
Or
Say
4

18

Average daily demand


Available pumping set (1 cusecs,200' Head,40 BHP)

=
=
=
=
=
=
=
=

No

Say
So it is proposed to install 1 Sets of vertical turbine pumps capable to give a
discharge of 1.00 cusec in future.
DESIGN OF ZONE -7
Area of Zone-7
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

31041
1552040

x
x

50
1.5

2328060

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-7
Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Available Capacity of OHR.
Available Capacity of GST.

1
2

No.
No.

20000
20000

Glns.
Glns.
Total

Balance Capacity for GST.


Say
Volum of GST.
Proposed No. of tanks.
Capacity of tank.
Proposed working depth of tank.
Area of tank
Dia of tank=

1000

16000 /
x4x7/22)^.5
Say:

16

=
=

50
1317828
1976743
18
109819
4.88
5.00
4.00

GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

1.00 Cusec.
1.00 Cusec.

=
=
=
=
=
=
=
=
=
=
=
=

173
133
179
20
31041
50
1552040
2328060
18
129337
5.75
5.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=

173
20
179
31041
50
1552000
1707200
170720

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

=
=
=
=
=
=
=
=
=
=
=
=

20,000 Glns.
40,000 Glns.
60,000 Glns.
110,720
100,000
16,000
1
16,000
16
1,000.00
35.68
36.00

Glns.
Glns.
Cft.
No:
Cft.
Ft.
Sft.
Ft.
Ft.

It is proposed to construct 1 No Ground storage tank 50 ft. dia. with 16 ft. working depth and 1.50 ft: dead
storage and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
MACHINERY FOR GST.
Design period
Density per acre as per 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

23029
1151440

x
x

50
1.5

1727160

/
Or
Say
2

18

Average daily demand


Available pumping set(0.82 cusecs,130' Head,40 BHP)

=
=
=
=
=
=
=
=
=
=
=
=

No
Say

Proposed No of Sets.

1+1

HEAD LOSSES.
Suctional Head
Loss in specials
Head loss pipe line i/c height of OHR(as per Hyd.Statement)

No
s

Total
Say
BHP of Electric Motor for 1.00 Cusec
62.5
x
1.00
x
550
x

150
60

=
=
=
=
=

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

2.36 Cusec.
2.00 Cusec.
2 No.
20.00
20.00
110
150.00
150.00

Feet.
Feet.
Feet.
Feet.
Feet.

100

Say
So it is proposed to install 2 Sets of vertical turbine pumps capable to give a
discharge of 1.00 cusec against a total head of 150 Ft directly coupled with
vertical AC Electric Motor of 30 BHP with 15 Ft: column pipei/c assembly
DESIGN OF ZONE -8
Area of Zone-8
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

=
=
=

10
133
173
23029
50
1151440
1727160
18
95953
4.26
4.00
1.64

48984
2449180

x
x

50
1.5

3673770

/
Or
Say

18

=
=

=
=
=
=
=
=
=
=
=
=
=
=

28.41 BHP.
30 BHP.

273
133
179
20
48984
50
2449180
3673770
18
204098
9.07
12.50

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

DESIGN OF OHR AND GST.


Area of Zone-8
Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Say

=
=
=
=
=
=
=
=

273
20
179
48984
50
2449200
2694120
269412

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

269,400 Glns.

Available Capacity of GST.

No.

100000

Glns.

100,000 Glns.

Available Capacity of GST.

No.

80000

Glns.

80,000 Glns.

Available Capacity of GST.

No.

40000

Glns.

80,000 Glns.

260,000 Glns.

Total
Balance Capacity for GST.

=
9,400 Glns.
Say
=
10,000 Glns.
It is proposed to construct 1 No Ground storage tank of 10000 Glns capacity in future.
MACHINERY FOR GST.
Design period
=
10 Year.
Density per acre asper 2023
=
133 pers/acre
Area served
=
273 Acres.
Projected Population upto 2023
=
36340 Persons
Consumption
=
50 GPCD.
Average daily demand
36340
x
50
=
1817006 Glns.
Maximum daily demand
1817006
x
1.5
=
2725509 Glns.
Proposed working hour
=
18 Hours.
Discharge per hour
2725509
/
18
=
151417 Glns.
Or
=
6.73 Cusec.
Average daily demand
Say
=
9.50 Cusec.
Available pumping set(1.8 cusecs,200' Head,40 BHP)
2
No
=
3.60 Cusec.
Say
So it is proposed to install 3 Sets of vertical turbine pumps capable to give a
discharge of 2.00 cusec in future.
DESIGN OF ZONE -9
Area of Zone-9
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

25120
1255990

x
x

50
1.5

1883985

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-9
Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR

=
=

5.90 Cusec.
6.00 Cusec.

=
=
=
=
=
=
=
=
=
=
=
=

140
133
179
20
25120
50
1255990
1883985
18
104666
4.65
4.50

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=

140
20
179
25120
50
1256000
1381600
138160

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

Say

138,200 Glns.

Available Capacity of GST.

No.

20000

Glns.
Total

20,000 Glns.

20,000 Glns.

Balance Capacity for GST.

=
118,200
Say
=
120,000
It is proposed to construct 1 No Ground storage tank of 120000 Glns capacity in future.
MACHINERY FOR GST.
Design period
=
10
Density per acre as per 2023
=
133
Area served
=
140
Projected Population upto 2023
=
18636
Consumption
=
50
Average daily demand
18636
x
50
=
931798
Maximum daily demand
931798
x
1.5
=
1397697
Proposed working hour
=
18
Discharge per hour
1397697
/
18
=
77650
Or
=
3.45
Average daily demand
Say
=
3.00
Available pumping set(0.75 cusecs,150' Head,30 BHP)
1
No
=
0.75
Say
So it is proposed to install 3 Sets of vertical turbine pumps capable to give a
discharge of 2.00 cusec in future.
DESIGN OF ZONE -10
Area of Zone-10
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

18840
941990

x
x

50
1.5

1412985

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-10
Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Available Capacity of GST.

No.

20000

Glns.
Total

Balance Capacity for GST.


Volum of GST.
Proposed No. of tanks.
Capacity of tank.
Proposed working depth of tank.
Area of tank
Dia of tank=

Propsed

60000 Glns

500

8000 /
x4x7/22)^.5
Say:

Say

16

=
=

Glns.
Glns.

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

2.25 Cusec.
2.00 Cusec.

=
=
=
=
=
=
=
=
=
=
=
=

105
133
179
20
18840
50
941990
1412985
18
78499
3.49
3.40

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=

105
20
179
18840
50
942000
1036200
103620

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

=
=

40,000 Glns.
40,000 Glns.

=
=
=
=
=
=
=
=
=

63,620
50,000
8,000
1
8,000
16
500.00
25.23
25.00

Glns.
Glns.
Cft.
No:
Cft.
Ft.
Sft.
Ft.
Ft.

It is proposed to construct 1 No Ground storage tank 28 ft. dia. with 16 ft. working depth and 1.50 ft: dead
storage and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
MACHINERY FOR GST.
Design period
Density per acre as per 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

21831
1091530

x
x

50
1.5

1637295

/
Or
Say
2

18

Average daily demand


Available pumping set(0.82 cusecs,130' Head,40 BHP)

=
=
=
=
=
=
=
=
=
=
=
=

No
Say

Proposed No of Sets.

1+1

HEAD LOSSES.
Suctional Head
Loss in specials
Head loss pipe line i/c height of OHR(as per Hyd.Statement)

No
s

Total
Say
BHP of Electric Motor for 1.00 Cusec
62.5
x
1.00
x
550
x

150
60

29520
1476000

x
x

50
1.5

2214000

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-11
Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/6 of average day demand for OHR
Proposed Capacity of GST.

No.

100000
Glns.
Total
Say

Volum of GST.

=
=
=
=
=

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

2.36 Cusec.
2.00 Cusec.
2 No.
20.00
20.00
110
150.00
150.00

Feet.
Feet.
Feet.
Feet.
Feet.

100

Say
So it is proposed to install 2 Sets of vertical turbine pumps capable to give a
discharge of 1.00 cusec against a total head of 150 Ft directly coupled with
vertical AC Electric Motor of 30 BHP with 15 Ft: column pipei/c assembly
DESIGN OF ZONE -11
Area of Zone-1
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

=
=
=

10
133
164
21831
50
1091530
1637295
18
90961
4.04
4.00
1.64

=
=

28.41 BHP.
30 BHP.

=
=
=
=
=
=
=
=
=
=
=
=

180
121
164
20
29520
50
1476000
2214000
18
123000
5.47
9.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=

180
20
164
29520
50
1476000
1623600
162360

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

=
=

200,000 Glns.
200,000 Glns.

=
=

200,000 Glns.
32,000 Cft.

Proposed No. of tanks.


Capacity of tank.
Proposed working depth of tank.
Area of tank
Dia of tank=

=
1 No:
=
32,000 Cft.
=
16 Ft.
32000 /
16
=
2,000.00 Sft.
2000
x4x7/22)^.5
=
50.46 Ft.
Say:
=
50.00 Ft.
It is proposed to construct 1 No Ground storage tank 50 ft. dia. with 16 ft. working depth and 1.50 ft: dead
storage and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
MACHINERY FOR GST.
Design period
Density per acre as per 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

21780
1089000

x
x

50
1.5

1633500

/
Or
Say
2

18

Average daily demand


Available pumping set(0.82 cusecs,130' Head,40 BHP)

=
=
=
=
=
=
=
=
=
=
=
=

No
Say

Proposed No of Sets.

1+1

HEAD LOSSES.
Suctional Head
Loss in specials
Head loss pipe line i/c height of OHR(as per Hyd.Statement)

No
s

Total
Say
BHP of Electric Motor for 1.00 Cusec
62.5
x
1.00
x
550
x

160
60

DESIGN OF OHR AND GST.


Area of Zone-12
Design period
Density per acre as per 2033

=
=
=
=
=

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

2.36 Cusec.
2.00 Cusec.
2 No.
20.00
5.00
0
25.00
160.00

Feet.
Feet.
Feet.
Feet.
Feet.

100

Say
So it is proposed to install 2 Sets of vertical turbine pumps capable to give a
discharge of 1.00 cusec against a total head of 160 Ft directly coupled with
vertical AC Electric Motor of 30 BHP with 15 Ft: column pipei/c assembly

DESIGN OF ZONE -12


Area of Zone-12
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

=
=
=

10
121
180
21780
50
1089000
1633500
18
90750
4.03
4.00
1.64

15088
754400

x
x

50
1.5

1131600

/
Or
Say

18

=
=

=
=
=
=
=
=
=
=
=
=
=
=
=
=
=

30.30 BHP.
30 BHP.

92
121
164
20
15088
50
754400
1131600
18
62867
2.79
3.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

92 Acres.
20 Year.
164 pers/acre

Projected population upto 2033


Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Available Capacity of GST

No.

10000

Glns.
Total

=
=
=
=
=

15088
50
754400
829840
82984

Persons
GPCD.
Glns.
Glns.
Glns.

=
=

20,000 Glns.
20,000 Glns.

Balance Capacity for GST.

=
62,984 Glns.
=
60,000 Glns.
Volum of GST.
=
9,600 Cft.
Proposed No. of tanks.
=
1 No:
Capacity of tank.
=
9,600 Cft.
Proposed working depth of tank.
=
16 Ft.
Area of tank
9600 /
16
=
600.00 Sft.
Dia of tank=
600
x4x7/22)^.5
=
27.64 Ft.
Say:
=
28.00 Ft.
It is proposed to construct 1 No Ground storage tank 28 ft. dia. with 16 ft. working depth and 1.50 ft: dead
storage and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
Say

MACHINERY FOR GST.


Design period
Density per acre as per 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

11132
556600

x
x

50
1.5

834900

/
Or
Say
1

18

Average daily demand


Available pumping set(1 cusecs,160' Head,30 BHP)

=
=
=
=
=
=
=
=
=
=
=
=

No
Say

Proposed No of Sets.

1+1

HEAD LOSSES.
Suctional Head
Loss in specials
Head loss pipe line i/c height of OHR(as per Hyd.Statement)

No
s

Total
Say
BHP of Electric Motor for 1.00 Cusec
62.5
x
1.00
x
550
x

160
60

=
=
=
=
=

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

0.36 Cusec.
2.00 Cusec.
2 No.
20.00
20.00
110
150.00
160.00

Feet.
Feet.
Feet.
Feet.
Feet.

100

Say
So it is proposed to install 2 Sets of vertical turbine pumps capable to give a
discharge of 1.00 cusec against a total head of 150 Ft directly coupled with
vertical AC Electric Motor of 30 BHP with 15 Ft: column pipei/c assembly

SCOPE OF WORK
The estimate consists of following scope.
1 Sub Work No.1 Survay & Investigation
=
2 Sub Work No.2 Tubewell 1 Cusec discharge =
3 Sub Work No.3 Pump House 12'x12'
=
4 Sub Work No.4 Pumping Machinery
=

=
=
=

10
121
92
11132
50
556600
834900
18
46383
2.06
2.00
1.64

10
10
10
10

Job
Nos
Nos
Sets

=
=

30.30 BHP.
30 BHP.

5 Sub Work No.5 Rising Main/Inter Connectio


20" dia HDPE pipe
18" dia HDPE pipe
16" dia HDPE pipe
14" dia HDPE pipe
12" dia PVC pipe
10" dia PVC pipe
8" dia PVC pipe
6" dia PVC pipe
4" dia PVC pipe
3" dia PVC pipe
6 Sub Work No.6 IPS
7 Sub Work No.7 G.S.T
8 Sub Work No.8 Pumping Machinery.for

a)
b)
c)
d)

4 cusecs,120 BHP,170' Head


(IPS)
1 cusecs,30 BHP,150' Head
1 cusecs,40 BHP,200' Head
3 cusecs,100 BHP,200' Head

=
=
=
=
=
=
=
=
=
=
=
=
=

34000
22800
29386
1000
5420
500
7500
500
100
100
1
4

Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
No
Nos

=
=
=
=
=

5
2
1
2
4

Sets
Sets
Sets
Nos
Nos

9 Sub Work No.9 Staff Quarter


10 Sub Work No.1 OHR
a)
50000 Glns
=
2 Nos
a)
100000 Glns
=
1 Nos
11 Sub Work No.1 Transmission Line
=
18 Jobs
12 Sub Work No Hyphochlornator
=
10 Nos
13 Sub Work No Generator
=
6 Set
RATES
Rates provided in the estimate as per market for non schedule items and as per
market schedule rates(1ST AUGUST, 2013 TO 31ST JANUARY, 2014)
SPECIFICATION
The Work will be completed according to PHE specification inforced at
the time of execution of work and upto entire satisfication of Engineer in Charge.
FUNDS
Total funds will be provided by the Govt: of Punjab .
TIME LIMIT
The work will take 2 years for completion if full funds will be provided by the Govt:
LAND
The land will be purchased for intermediate pumping station by PHE department/TMA
O & M COST
After completion of the scheme TMA Sadiqabad will be responsible for O & M
COST
Total cost of the estimate is work ou 696.617 Millions

Sub Engineer

Sub Divisional Officer


Public Healt Engg: Sub Division
Sadiqabad

Executive Engineer
Public Health Engg: Division
Rahimyarkhan

ROUGH COST ESTIMATE FOR WATER SUPPLY SCHEME


SADIQABAD TEHSIL SADIQABAD DISTT: RAHIMYARKHAN.
GENERAL ABSTRACT OF COST
1 Sub Work No. 1. Survey and Investigation Ground water
2 Sub Work No .2 T Wells
3 Sub Work No. 3 Pump House 12x12

10
10
10

Job
Nos.
Nos.

Rs.
Rs.
Rs.

574000 /6997000 /4165000 /-

4 Sub Work No. 4

Pumping Machinery.for tubewell

10

Sets.

Rs.

12500000 /-

5 Sub Work No. 5

Rising Main:& Distribution system


34000
22800
29386
1000
5420
500
7500
500
100
100
1
4

Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Job
Nos.

Rs.
Rs.

78027400 /25667100 /-

5
2
1
2
4

Sets.
Sets.
Sets.
Sets.
Nos.

Rs.
Rs.
Rs.
Rs.
Rs.

10000000
2200000
1250000
3400000
2143200

6
7
8

9
10

500 mm dia HDPE pipe


450 mm dia HDPE pipe
400 mm dia HDPE pipe
355 mm dia HDPE pipe
12'' dia PVC pipe
10'' dia PVC pipe
8'' dia PVC pipe
6'' dia PVC pipe
4'' dia PVC pipe
3'' dia PVC pipe
Sub Work No.6 Intermediate Pumping Station
Sub Work No. 7 G.S.T
Sub Work No. 8 Pumping Machinery.For IPS/GST
a)
4 cusecs,120 BHP,170' Head (IPS)
b)
1 cusecs,30 BHP,150' Head
c)
1 cusecs,40 BHP,200' Head
d)
3 cusecs,100 BHP,200' Head
Sub Work No. 9 Staff Quarter
Sub Work No 10 Over Head Reservoir

449966500

/////-

a)

50000 Glns Capacity

Nos.

Rs.

13640000 /-

b)

100000 Glns Capacity

1
18

Nos.

Rs.

11335000 /-

Nos.

Rs.

17453400 /-

10

Nos.

Rs.

450000 /-

Set

11 Sub Work No 11 Transmission Line


12 Sub Work No 12 Hyphochlornator
13 Sub Work No 13 Generator

Rs.

22100000 /-

Total:

Rs.

661868600 /-

G.Total:-

Rs.
Rs.
Rs.
Rs.

13237372
13237372
8273358
696616702

Rs.

696.617
Million

Add 2% Contingencies & petty establishment


charges
2 % Resident Supervision and Design of scheme
1.25 % For awarness Compaign & Horticultural provision

Say:-

Sub Engineer

Sub Divisional Officer


Public Health Engg: Sub Division
Sadiqabad

Superintending Engineer
Public Health Engg: Circle
Bahawalpur

DEO\Sajid Imran SDK

Executive Engineer
Public Health Engg: Division
Rahimyarkhan

////-

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

14.943
-4.090

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

18" dia AC pipe


14" dia AC pipe
14" dia AC pipe
14" dia AC pipe
12" dia AC pipe
10" dia ACpipe
10" dia ACpipe
10" dia ACpipe
8" dia AC pipe
6" dia PVC pipe

DEO\Sajid Imran SDK

ROUGH COST ESTIMATE

PROVINCE

PUNJAB

DEPARTMENT

HUD AND PHE DEPARTMENT

STATION

CITY SADIQABAD
TEHSIL SADIQABAD DISTT: R.Y.KHAN.

NAME OF WORK

WATER SUPPLY SCHEME


SADIQABAD

AMOUNT

696.617 Million

ROUGH COST ESTIMATE FOR WATER SUPPLY SCHEME


SADIQABAD TEHSIL SADIQABAD DISTT: RAHIMYARKHAN.
Reference

CM Directive No CS(CD)CMS/12/OT-4/A/0154129 Dated 25-06-2012

HISTORY AND REPORT:


Sadiqabad was the town of Tehsil Ahmed Purr Lamma before 1928 but after that Tehsil headquarter was shifted to
Sadiqabad from Ahamd Pur Lamma since that it is working as headquarter Sadiqabad of District Rehim Yar Khan.
It is situated at a distance of 20 KM from Rehim Yar Khan towards west on KLP road and main track of Pakistan
Railway. Pakistan Railway track has divided Sadiqabad into two parts, one is Southern side and Northern side.
The Southern side of the town is called Mandi Town and Northern side is called old Sadiqabad. It grained
importance due to production of food grain, cotton and big mandi of agriculture products. FFC, Fatima fertilizer,
sugar mills, hospital, degree college for boys & girls, grain market etc are existed in Tehsil Sadiqabad.
as per census 1998, the population of city is 144391 person. It comprises of 29 No. union councils in whole Tehsil,
6 No falls in city are a and 23 No falls in rural area.

EXISTING WATER SUPPLY FACILITIES.


1.
In 1962 a piped water supply system based on tubewells was provided. The water table started rising
and with the passage of time, sub soil water has become brackish. This scheme is abandoned and has completed
its designed life.
2.
In 1963 Public Health Engineering Department proposed a water supply scheme based on canal source,
which was designed for a population of 20,000 souls at the rate of 20 gallons per head per day at a cost of Rs.
4,97,780/3.
The distribution pipelines were laid in the new town and in some parts of the old town. Later on the
distribution system was also provided to the adjoining abadies, these abadies actually were not included in the
scope of the area to be served, but there was no alternative except to share the water with these abadies because
of the brackish nature of sub soil water.
4.
Another Scheme was also framed by the Public Health Engineering Department for extension of water
supply in Mazhar Farid colony, which started functioning from 1975-76. It was also based on canal source to
supply water for population of 8600 persons at the rate of 20 gallons per head per day for approved cost of Rs.
10,59,000/- These schemes based on canal water source are now abandoned.
5.
In 1983 a Comprehensive Water supply scheme Phase-I based on tubewell source (Chak No.
11/NP) for the Zone-II i.e. northern side of Railway line including old town Mazhar Farid colony, Arian colony, Ilyas
colony, new bus stand, Mohallah Gharibabad etc. was designed. The tubewells of this scheme has been turned to
brakish.This scheme was administratively approved for this zone for 10 years of designed period i.e. upto 1991
and rising main for 20 years designed period i.e. 2004. The scheme was designed @ 40 gallons/head/day and 16
hours of pumping. The main features of the scheme are as under:1

Shallow tubewell of 0.85-cusec discharge along Jamal Din wali road.= 8 Nos.

A.C. pipe B-Class rising main 18 dia (from Tubewell to KLP road)= 18600 Rft

A.C. pipe B-Class rising main 10 dia (from KLP road Chowk to
Mazhar Farid colony water works)

= 2774 Rft.

4.

Pumping machinery 25 BHP, 140 ft head with discharge 0.85 cusec. = 8 sets.

5.

Yard piping.

Pumping chamber/pump house 8 dia.

= 8 No.

7.

Staff quarter (double room)

= 1 No.

8.

Staff quarter (single room)

= 1 No.

1Job

9.

Rising main (from KLP Chowk to Ghafoorabad ) 6dia AC pipe.

= 3000 Rft.

10.

Ground Storage Reservoir of 40 ft dia and 80000 gallons Capacity

= 1 No.

11.

Pumping machinery (40 BHP electric motor with centrifugal pump with

12.

120 ft head)

= 2 sets.

Pump House 30x12

= 1 No.

13.

Distribution system

16 dia A.C. pipe

= 1120 Rft.

12 dia A.C. pipe

= 2200 Rft.

8 dia A.C. pipe

= 1900 Rft.

6 dia A.C. pipe

= 2800 Rft.

4 dia PVC pipe

= 4800 Rft.

3 dia PVC pipe.

= 7600 Rft.

6.
In 1996 another scheme i.e. water supply scheme Sadiqabad Phase-II was started based on tubewell
source for population on southern side of Railway line. The scheme was administratively approved for Rs.607.39
Lac vide No. SO (III) 1-24/94 dated 16.5.1996 The estimate was Technically sanctioned by the Chief Engineer (S)
PHED Lahore vide No. 419/P&D dated 23.7.1996. The scope of work in this estimate was as under:1

Shallow tubewell of 1.00 cusec discharge.

8 Nos.

(Ahmed Pur Lamma Distributory & Minor)


2.

3.

Rising main.

20 dia A.C. pipe

32500 Rft.

18 dia A.C. pipe

2100 Rft

16 dia A.C. pipe

3000 Rft.

Pumping machinery
i)- 40 BHP, 200 ft head with a discharge of 1.00 cusec.

8 sets.

ii)-30 BHP, 100 ft head with a discharge of 1.50 cusec.


(At overhead bridge site)

= 2 sets.

4.

Yard piping

1 Job

Pump House 12x10

8 No.

6.

Ground storage tank 46 dia.

7.

Staff quarter two roomed.

2 No.

8.

Overhead Transmission line

1 Job

9.

Boundary wall.

587 Rft.

30X24

2 No.
1 No.

This scheme is operational now and serving population on southern side of Railway line.
7.
In 2005-06 another scheme was constructed in which 16 Nos tubewells of 0.5 Cusec discharge were
installed near Shahbaz Pur is completed and handed over to TMA Sadiqabad on 25/09/2008 and running
satisfactory.This schemes serves the population of old town Mazhar Farid colony, Arian colony, Ilyas colony, new
bus stand and Mohallah Gharibabad
PROPOSAL
It is proposed to install 20 Nos. tubewell having a discharge of 1 cusec Each along the bank of Fazal Wah
distributry flowing at a distance of 18 KM from Sadiqabad city. The proposed site falls in sweet zone. The
discharge Fazal Wah distributry is about 270 cusec at proposed site. The drinking water will be pumped through
28" i/d AC pipe C-Class to intermediated pumping station at a distance of about 10 KM to control the head form
intermediate pumping station will be pumped and supplied to the city area at various water works. Drinking water
will be supplied by pumping to the abadies provision of diesel generators has been made in the estimate to
counter the electrical load shedding for continuous supply of drinking water to the residents of the city PC-1
/Rough cost estimate amounting to Rs.
million has been framed in compliance of worthy CM
Directive No CS(CD)CMS/12/OT-4/A/0154129 Dated 25-06-2012 and submitted for favor of administrative
approval from the competent forum.
DESIGN
Population as per census 1998 on Page-296
PROJECTED POPULATION
Growth Rate Per Year as per census on page -17
Add upto 2008 @ 3.22 of per annum
Add upto 2013 @ 3.22 of per annum
Add upto 2023 @ 3.22 of per annum
Add upto 2028 @ 3.22 of per annum
Add upto 2033 @ 3.22 of per annum

144391 Persons

=
=
=
=
=
=

3.22
190885
221617
292978
340148
394911

%
Persons
Persons
Persons
Persons
Persons

Area of Zone-1
Area of Zone-2
Area of Zone-3
Area of Zone-4
Area of Zone-5
Area of Zone-6
Area of Zone-7
Area of Zone-8
Area of Zone-9
Area of Zone-10
Area of Zone-11
Area of Zone-12
Total served area
Density per acre as per 2023
Density per acre as per 2033
TUBEWELLS
Design period
Projected Population upto 2028
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

292978
394911

Already avail able discharge by T/W Ahmadpur


Already avail able discharge by T/W Fazal Wah
Already avail able discharge by Canal source

Total
2415
2415

/
/

340148
17007380

x
x

50
1.5

25511070

/
Or

18

8
16

x
x

1
0.5
Total

Balance required discharge


No of Tubewell

41.99

=
=
=
=
=
=
=
=
=
=
=
=
=
=
=

160
200
404
200
80
198
173
383
240
105
180
92
2415
121
164

=
=
=
=
=
=
=
=

15
340148
50
17007380
25511070
18
1417282
63

=
=
=
=

8.00
8.00
5.00
21

Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.
Cusec.
Cusec.

42 Cusec.

42 No,

Say
=
42 No.
It is proposed to install 20 No. tube well of 1 cusec each on Fazal Wah Distributory and balance 22 Nos will be
installed in future.
STRAINER FOR TUBE WELLS
Discharge
Proposed size of strainer
Proposed slot opening area of strainer
Entrance Velocity
Length of strainer =
1
3.143
Add 10% safety for socket.
Total length of strainer

x
x

12
0.05

x
x

100
12

Say

=
=
=
=
=

1
12
10
0.05
63.64

Cusec
Inch
%
ft/sec
Feet.

=
=

6.36 Feet.
70.00 Feet.

10

72.00 Feet.

RISING MAIN
Projected population upto 2033

394911 Persons

Consumption per capita

Average day demand

19745571 Glns.

29618357 Glns.

Maximum day demand

19745571

1.5

Working Hour
Hourly Discharge

=
29618357

18

50 GPCD.

18 Hours
1645464 Glns.

Already avail able discharge by T/W Ahmadpur


Already avail able discharge by T/W Fazal Wah
Already avail able discharge by Canal source

8
16

x
x

Or

73 Cusec

Say

73.00 Cusec

1
0.5
Total

Balance required discharge


Say
Discharge 10
years 2023

Discharge 2013

Discharge 15
years 2028

=
=
=
=
=
=

8.00
8.00
5.00
21
52

Cusec.
Cusec.
Cusec.
Cusec.
Cusec.

52.00 Cusec.

Discharge 20
years 2033

Total Demand

41

Cusec

54

Cusec

63 Cusec

73

Cusec

Available 16+5+20

41

Cusec

41

Cusec

41 Cusec

41

Cusec

Balance

Cusec

13

Cusec

22 Cusec

32

Cusec

PUMPING MACHINERY FOR TUBE WELLS


Spring Level
Draw down
Seasonal variation
Loss in specials
Head loss in rising main(as per Hydrulic Statement)
Total
Say
BHP of Electric Motor
62.5
x

1
550

x
x

160
65

=
=
=
=
=
=
=

35.00
8.00
20.00
5.00
23
91.27
160.00

Feet.
Feet.
Feet.
Feet.
Feet.
Feet.
Feet.

100

=
27.97 BHP.
Say
=
30 BHP.
So it is proposed to install 20 Sets of vertical turbine pumps capable to give a discharge of 1 cusec against a total
head of 160 ft: directly coupled with vertical AC Electric Motor of 30 BHP with 90 ft: column pipe assembly on tube
well.
DESIGN OF IPS
RISING MAIN
Projected population upto 2033

73 Persons

Consumption per capita

50 GPCD.

Average day demand

3673 Glns.

5509 Glns.

Maximum day demand

3673

1.5

Working Hour
Hourly Discharge

=
5509

Already avail able discharge by T/W Ahmadpur


Already avail able discharge by T/W Fazal Wah
Already avail able discharge by Canal source

8
16

x
x

18

=
=

0 Cusec

Say

73.00 Cusec

Total
Say
Area of Sadiqabad
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033

306 Glns.

Or
1
0.5

Balance required discharge

18 Hours

=
=
=
=
=
=
=
=
=
=
=

8.00
8.00
5.00
21
-21

Cusec.
Cusec.
Cusec.
Cusec.
Cusec.

52.00 Cusec.
2415
121
164
20
394911

Acres.
pers/acre
pers/acre
Year.
Persons

Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

394911
19745570

x
x

50
1.5

29618355

/
Or

18

=
=
=
=
=
=

50
19745570
29618355
18
1645464
73

GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.

DESIGN OF GST.
Area of Sadiqabad
Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/6 of average day demand for OHR

=
2415 Acres.
=
20 Year.
=
164 pers/acre
=
394911 Persons
=
50 GPCD.
=
19745600 Glns.
=
21720160 Glns.
=
3620027 Glns.
Say
=
400,000 Glns.
Proposed Capacity ofGST
2
No.
200000
Glns.
=
400,000 Glns.
Total
=
400,000 Glns.
Say
=
200,000 Glns.
Volum of GST.
=
32,000 Cft.
Proposed No. of tanks.
=
1 No:
Capacity of tank.
=
32,000 Cft.
Proposed working depth of tank.
=
16 Ft.
Area of tank
32000 /
16
=
2,000.00 Sft.
Dia of tank=
2000
x4x7/22)^.5
=
50.46 Ft.
Say:
=
50.00 Ft.
It is proposed to construct 1 No Ground storage tank 50ft. dia. with 16 ft. working depth and 1.50 ft: dead storage
and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
PUMPING MACHINERY FOR IPS
Suction Level
Loss in specials
Head loss in rising main(as per Hydrulic Statement)
Total
Say
BHP of Electric Motor
62.5
x

3
550

x
x

110
65

=
=
=
=
=

20.00
5.00
83
108.00
110.00

Feet.
Feet.
Feet.
Feet.
Feet.

100

=
57.69 BHP.
Say
=
60 BHP.
So it is proposed to install 7 Sets of vertical turbine pumps capable to give a discharge of 1 cusec against a total
head of 110 ft: directly coupled with vertical AC Electric Motor of 60 BHP with 20 ft: column pipe assembly on tube
well.
DESIGN OF ZONE -1
Area of Zone-1
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

DESIGN OF OHR AND GST.


Area of Zone-1

394911
19745570

x
x

50
1.5

29618355

/
Or
Say

18

=
=
=
=
=
=
=
=
=
=
=
=
=

160
121
164
20
394911
50
19745570
29618355
18
1645464
73.13
5.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

160 Acres.

Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Available Capacity of OHR.
Available Capacity of GST.

=
=
=
=
=
=
=
1
1

No.
No.

20000
20000

Glns.
Glns.
Total

=
=
=

20
121
394911
50
19745600
21720160
2172016

Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

20,000 Glns.
20,000 Glns.
40,000 Glns.

Balance Capacity for GST.

=
2,132,016 Glns.
=
100,000 Glns.
Volum of GST.
=
16,000 Cft.
Proposed No. of tanks.
=
1 No:
Capacity of tank.
=
16,000 Cft.
Proposed working depth of tank.
=
16 Ft.
Area of tank
16000 /
16
=
1,000.00 Sft.
Dia of tank=
1000
x4x7/22)^.5
=
35.68 Ft.
Say:
=
36.00 Ft.
It is proposed to construct 1 No Ground storage tank 36 ft. dia. with 16 ft. working depth and 1.50 ft: dead storage
and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
Say

MACHINERY FOR GST.


Design period
Density per acre asper 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

19360
968000

x
x

50
1.5

1452000

/
Or
Say
2

18

Average daily demand


Available pumping set (0.82 cusecs,120' Head,20 BHP)

=
=
=
=
=
=
=
=
=
=
=
=

No
Say

Proposed No of Sets.

1+1

Nos

HEAD LOSSES.
Suctional Head
Loss in specials
Head loss pipe line i/c height of OHR(as per Hyd.Statement)
Total
Say
BHP of Electric Motor for 1.00 Cusec
62.5
x
1.00
550

x
x

150
60

=
=
=
=
=
=
=
=

10
121
160
19360
50
968000
1452000
18
80667
3.59
4.00
1.64

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

2.36 Cusec.
2.00 Cusec.
2 No.
20.00
20.00
110
150.00
150.00

Feet.
Feet.
Feet.
Feet.
Feet.

100

=
28.41 BHP.
Say
=
30 BHP.
So it is proposed to install 2 Sets of vertical turbine pumps capable to give a discharge of 1.00 cusec against a total
head of 150 Ft directly coupled with vertical AC Electric Motor of 30 BHP with 15 Ft: column pipe i/c assembly
DESIGN OF ZONE -2
Area of Zone-2
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033

=
=
=
=
=

200
121
164
20
32705

Acres.
pers/acre
pers/acre
Year.
Persons

Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

32705
1635240

x
x

50
1.5

2452860

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-2
Design period
Density per acre as per 2023
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Say
available Capacity of GST.

No.

200000

Glns.
Total

Balance Capacity for GST.


MACHINERY FOR GST.
Design period
Density per acre as per 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

Say

24263
1213160

x
x

50
1.5

1819740

/
Or
Say

18

No

Average daily demand


Available pumping set (1 cusecs,200' head,40 BHP)

Balance
Say
Proposed No of Sets in future extension.
DESIGN OF ZONE -3
Area of Zone-3
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

DESIGN OF OHR AND GST.


Area of Zone-3

1+1+1 Nos

66064
3303190

x
x

50
1.5

4954785

/
Or
Say

18

=
=
=
=
=
=
=

50
1635240
2452860
18
136270
6.06
6.50

GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=

200
20
121
164
50
1635244
1798768
179877

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

179,900 Glns.

=
=

200,000 Glns.
200,000 Glns.

=
=

(20,100) Glns.
Nil Glns.

=
=
=
=
=
=
=
=
=
=
=

10
121
200
24263
50
1213160
1819740
18
101097
4.49
5.00

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

2.00 Cusec.

=
=
=

3.00 Cusec.
3.00 Cusec.
3 No.

=
=
=
=
=
=
=
=
=
=
=
=
=

404
121
164
20
66064
50
3303190
4954785
18
275266
12.23
15.28

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

404 Acres.

Design period
Density per acre as per 2023
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR

=
=
=
=
=
=
=
=

Say
Available Capacity of GST.

No.

1000000

Glns.

Balance
Balance Capacity for GST.
Volum of GST.
Proposed No. of tanks.
Capacity of tank.
Proposed working depth of tank.
Area of tank
Dia of tank=

Say

2000

32000 /
x4x7/22)^.5
Say:

16

20
121
164
50
3303193
3633512
363351
363,400

Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.
Glns.

2,000,000 Glns.

(1,636,600) Glns.

=
=
=
=
=
=
=
=

200,000
32,000
1
32,000
16
2,000.00
50.46
50.00

Cft.
No:
Cft.
Ft.
Sft.
Ft.
Ft.

It is proposed to construct 1 No Ground storage tank 36 ft. dia. with 16 ft. working depth and 1.50 ft: dead storage
and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
MACHINERY FOR GST.
Design period
Density per acre as per 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

=
=
=
=
=
=
=
=
=
=
=

10
121
404
49012
50
2450580
3675870
18
204215
9.08
5.00

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

49012
2450580

x
x

50
1.5

3675870

/
Or
Say

18

Available pumping set (3 cusecs,200' head,100 BHP)

No

6.00 Cusec.

Proposed pumping set (3 cusecs,200' head,100 BHP)

No

6.00 Cusec.

Average daily demand

DESIGN OF ZONE -4
Area of Zone-4
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

DESIGN OF OHR AND GST.


Area of Zone-4
Design period
Density per acre as per 2023

32705
1635240

x
x

50
1.5

2452860

/
Or
Say

18

=
=
=
=
=
=
=
=
=
=
=
=
=
=
=

200
121
164
20
32705
50
1635240
2452860
18
136270
6.06
7.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

200 Acres.
20 Year.
164 pers/acre

Projected population upto 2033


Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR

=
=
=
=
=
=

Say
available Capacity of OHR.
available Capacity of GST.

1
1

No.
No.

40000
20000

Glns.
Glns.
Total

Balance Capacity for GST.


Say
Volum of GST.
Proposed No. of tanks.
Capacity of tank.
Proposed working depth of tank.
Area of tank
Dia of tank=

1000

16000 /
x4x7/22)^.5
Say:

16

32705
50
1635200
1798720
179872
179,900

Persons
GPCD.
Glns.
Glns.
Glns.
Glns.

=
=

40,000 Glns.
20,000 Glns.

60,000 Glns.

=
=
=
=
=
=
=
=
=

119,900
100,000
16,000
1
16,000
16
1,000.00
35.68
36.00

Glns.
Glns.
Cft.
No:
Cft.
Ft.
Sft.
Ft.
Ft.

It is proposed to construct 1 No Ground storage tank 36 ft. dia. with 16 ft. working depth and 1.50 ft: dead storage
and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
MACHINERY FOR GST.
Design period
=
10 Year.
Density per acre asper 2023
=
121 pers/acre
Area served
=
200 Acres.
Projected Population upto 2023
=
24263 Persons
Consumption
=
50 GPCD.
Average daily demand
24263
x
50
=
1213160 Glns.
Maximum daily demand
1213160
x
1.5
=
1819740 Glns.
Proposed working hour
=
18 Hours.
Discharge per hour
1819740
/
18
=
101097 Glns.
Or
=
4.49 Cusec.
Average daily demand
Say
=
5.00 Cusec.
Available pumping set (1 cusecs,200' Head,40 BHP)
4
No
=
4.00 Cusec.
Say
Proposed No of Sets.

1+1

Nos

HEAD LOSSES.
Suctional Head
Loss in specials
Head loss pipe line i/c height of OHR(as per Hyd.Statement)
Total
Say
BHP of Electric Motor for 1.00 Cusec
62.5
x
1.00
550

x
x

200
60

=
=
=
=
=
=
=
=

20.00
20.00
157
197.00
200.00

Feet.
Feet.
Feet.
Feet.
Feet.

100

=
Say
=
So it is proposed to install 2 Sets of vertical turbine pumps capable to give a discharge of
1.00 cusec against a total head of 200 Ft directly coupled with vertical AC Electric Motor of 40
BHP with 15 Ft: column pipei/c assembly
DESIGN OF ZONE -5
Area of Zone-5
Density per acre as per 2023
Density per acre as per 2033

1.00 Cusec.
2.00 Cusec.
2 No.

=
=
=

37.88 BHP.
40 BHP.

80 Acres.
121 pers/acre
164 pers/acre

Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

13082
654100

x
x

50
1.5

981150

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-5
Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Say
Available Capacity of OHR.
Available Capacity of GST.

1
2

No.
No.

40000
40000

Glns.
Glns.
Total

Balance Capacity for GST.


Say
It is proposed to construct 1 No Ground storage tank of 100000 Glns capacity in future.
MACHINERY FOR GST.
Design period
Density per acre as per 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
9705
x
50
Maximum daily demand
485264
x
1.5
Proposed working hour
Discharge per hour
727896
/
18
Or
Average daily demand
Say
Available pumping set (1 cusecs,200' Head,40 BHP)
4
No

=
=
=
=
=
=
=
=
=

20
13082
50
654100
981150
18
54508
2.42
7.00

Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=
=

80
20
164
13082
50
654100
719510
71951
72,000

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.
Glns.

=
=

40,000 Glns.
80,000 Glns.

120,000 Glns.

=
=

(48,000) Glns.
100,000 Glns.

=
=
=
=
=
=
=
=
=
=
=
=

=
Say
=
So it is proposed to install 1 Sets of vertical turbine pumps capable to give a discharge of
1.00 cusec in future.
DESIGN OF ZONE -6
Area of Zone-6
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

32378
1618890

x
x

50
1.5

2428335

/
Or
Say

18

=
=
=
=
=
=
=
=
=
=
=
=

10
121
80
9705
50
485264
727896
18
40439
1.80
5.00
4.00

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

1.00 Cusec.
1.00 Cusec.

198
121
164
20
32378
50
1618890
2428335
18
134908
6.00
6.50

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

DESIGN OF OHR AND GST.


Area of Zone-6
Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Say
Available Capacity of GST.

No.

100000

Glns.
Total

Balance Capacity for GST.


Say
It is proposed to construct 1 No Ground storage tank of 100000 Glns capacity in future.
MACHINERY FOR GST.
Design period
Density per acre as per 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
24021
x
50
Maximum daily demand
1201029
x
1.5
Proposed working hour
Discharge per hour
1801543
/
18
Or
Average daily demand
Say
Available pumping set (1 cusecs,200' Head,40 BHP)
4
No

=
=
=
=
=
=
=
=

198
20
164
32378
50
1618900
1780790
178079

178,100 Glns.

100,000 Glns.

100,000 Glns.

=
=

78,100 Glns.
100,000 Glns.

=
=
=
=
=
=
=
=
=
=
=
=

10
121
198
24021
50
1201029
1801543
18
100086
4.45
5.00
4.00

=
Say
=
So it is proposed to install 1 Sets of vertical turbine pumps capable to give a discharge of
1.00 cusec in future.
DESIGN OF ZONE -7
Area of Zone-7
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

DESIGN OF OHR AND GST.


Area of Zone-7
Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR

28290
1414490

x
x

50
1.5

2121735

/
Or
Say

18

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

1.00 Cusec.
1.00 Cusec.

=
=
=
=
=
=
=
=
=
=
=
=

173
121
164
20
28290
50
1414490
2121735
18
117874
5.24
9.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=

173
20
164
28290
50
1414500
1555950
155595

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

Available Capacity of OHR.


Available Capacity of GST.

1
2

No.
No.

20000
20000

Glns.
Glns.
Total

=
=
=

20,000 Glns.
40,000 Glns.
60,000 Glns.

Balance Capacity for GST.

=
95,595 Glns.
=
100,000 Glns.
Volum of GST.
=
16,000 Cft.
Proposed No. of tanks.
=
1 No:
Capacity of tank.
=
16,000 Cft.
Proposed working depth of tank.
=
16 Ft.
Area of tank
16000 /
16
=
1,000.00 Sft.
Dia of tank=
1000
x4x7/22)^.5
=
35.68 Ft.
Say:
=
36.00 Ft.
It is proposed to construct 1 No Ground storage tank 50 ft. dia. with 16 ft. working depth and 1.50 ft: dead storage
and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
Say

MACHINERY FOR GST.


Design period
Density per acre as per 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

20988
1049380

x
x

50
1.5

1574070

/
Or
Say
2

18

Average daily demand


Available pumping set(0.82 cusecs,130' Head,40 BHP)

=
=
=
=
=
=
=
=
=
=
=
=

No
Say

Proposed No of Sets.

1+1

Nos

HEAD LOSSES.
Suctional Head
Loss in specials
Head loss pipe line i/c height of OHR(as per Hyd.Statement)
Total
Say
BHP of Electric Motor for 1.00 Cusec
62.5
x
1.00
550

x
x

150
60

=
=
=
=
=
=
=
=

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

2.36 Cusec.
2.00 Cusec.
2 No.
20.00
20.00
110
150.00
150.00

Feet.
Feet.
Feet.
Feet.
Feet.

100

=
Say
=
So it is proposed to install 2 Sets of vertical turbine pumps capable to give a discharge of
1.00 cusec against a total head of 150 Ft directly coupled with vertical AC Electric Motor of 30
BHP with 15 Ft: column pipei/c assembly
DESIGN OF ZONE -8
Area of Zone-8
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

10
121
173
20988
50
1049380
1574070
18
87448
3.89
4.00
1.64

62630
3131490

x
x

50
1.5

4697235

/
Or

18

=
=
=
=
=
=
=
=
=
=
=

28.41 BHP.
30 BHP.

383
121
164
20
62630
50
3131490
4697235
18
260958
11.60

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.

Say

DESIGN OF OHR AND GST.


Area of Zone-8
Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Say

12.50 Cusec.

=
=
=
=
=
=
=
=

383
20
164
62630
50
3131500
3444650
344465

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

344,500 Glns.

Available Capacity of GST.

No.

100000

Glns.

100,000 Glns.

Available Capacity of GST.

No.

80000

Glns.

80,000 Glns.

Available Capacity of GST.

No.

40000

Glns.

80,000 Glns.

260,000 Glns.

=
=

84,500 Glns.
114,000 Glns.

=
=
=
=
=
=
=
=
=
=
=
=

10
121
383
46464
50
2323202
3484802
18
193600
8.60
9.50
3.60

Total
Balance Capacity for GST.
Say
It is proposed to construct 1 No Ground storage tank of 114000 Glns capacity in future.
MACHINERY FOR GST.
Design period
Density per acre asper 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
46464
x
50
Maximum daily demand
2323202
x
1.5
Proposed working hour
Discharge per hour
3484802
/
18
Or
Average daily demand
Say
Available pumping set(1.8 cusecs,200' Head,40 BHP)
2
No

=
Say
=
So it is proposed to install 3 Sets of vertical turbine pumps capable to give a discharge of
2.00 cusec in future.
DESIGN OF ZONE -9
Area of Zone-9
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

DESIGN OF OHR AND GST.


Area of Zone-9
Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita

39246
1962290

x
x

50
1.5

2943435

/
Or
Say

18

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

5.90 Cusec.
6.00 Cusec.

=
=
=
=
=
=
=
=
=
=
=
=

240
121
164
20
39246
50
1962290
2943435
18
163524
7.27
8.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=

240
20
164
39246
50

Acres.
Year.
pers/acre
Persons
GPCD.

Average day demand


Adding 10% for institutions
Take 1/10 of average day demand for OHR
Say
Available Capacity of GST.

No.

100000

Glns.
Total

Balance Capacity for GST.


Say
It is proposed to construct 1 No Ground storage tank of 150000 Glns capacity in future.
MACHINERY FOR GST.
Design period
Density per acre as per 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
29116
x
50
Maximum daily demand
1455792
x
1.5
Proposed working hour
Discharge per hour
2183688
/
18
Or
Average daily demand
Say
Available pumping set(0.75 cusecs,150' Head,30 BHP)
1
No

=
=
=

1962300 Glns.
2158530 Glns.
215853 Glns.

215,900 Glns.

100,000 Glns.

100,000 Glns.

=
=

115,900 Glns.
150,000 Glns.

=
=
=
=
=
=
=
=
=
=
=
=

10
121
240
29116
50
1455792
2183688
18
121316
5.39
6.00
0.75

=
Say
=
So it is proposed to install 3 Sets of vertical turbine pumps capable to give a discharge of
2.00 cusec in future.
DESIGN OF ZONE -10
Area of Zone-10
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

17170
858500

x
x

50
1.5

1287750

/
Or
Say

18

DESIGN OF OHR AND GST.


Area of Zone-10
Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Available Capacity of GST.

No.

20000

Glns.
Total

Balance Capacity for GST.


Propsed

50000 Glns

Say

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

5.25 Cusec.
6.00 Cusec.

=
=
=
=
=
=
=
=
=
=
=
=

105
121
164
20
17170
50
858500
1287750
18
71542
3.18
9.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=
=
=
=

105
20
164
17170
50
858500
944350
94435

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

=
=

40,000 Glns.
40,000 Glns.

=
=

54,435 Glns.
50,000 Glns.

Volum of GST.
Proposed No. of tanks.
Capacity of tank.
Proposed working depth of tank.
Area of tank
Dia of tank=

=
8,000 Cft.
=
1 No:
=
8,000 Cft.
=
16 Ft.
8000 /
16
=
500.00 Sft.
500
x4x7/22)^.5
=
25.23 Ft.
Say:
=
25.00 Ft.
It is proposed to construct 1 No Ground storage tank 50 ft. dia. with 16 ft. working depth and 1.50 ft: dead storage
and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
MACHINERY FOR GST.
Design period
Density per acre as per 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

19896
994790

x
x

50
1.5

1492185

/
Or
Say
2

18

Average daily demand


Available pumping set(0.82 cusecs,130' Head,40 BHP)

=
=
=
=
=
=
=
=
=
=
=
=

No
Say

Proposed No of Sets.

1+1

Nos

HEAD LOSSES.
Suctional Head
Loss in specials
Head loss pipe line i/c height of OHR(as per Hyd.Statement)
Total
Say
BHP of Electric Motor for 1.00 Cusec
62.5
x
1.00
550

x
x

150
60

=
=
=
=
=
=
=
=

DESIGN OF OHR AND GST.


Area of Zone-11
Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

2.36 Cusec.
2.00 Cusec.
2 No.
20.00
20.00
110
150.00
150.00

Feet.
Feet.
Feet.
Feet.
Feet.

100

=
Say
=
So it is proposed to install 2 Sets of vertical turbine pumps capable to give a discharge of
1.00 cusec against a total head of 150 Ft directly coupled with vertical AC Electric Motor of 30
BHP with 15 Ft: column pipei/c assembly
DESIGN OF ZONE -11
Area of Zone-1
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

10
121
164
19896
50
994790
1492185
18
82899
3.68
4.00
1.64

29520
1476000

x
x

50
1.5

2214000

/
Or
Say

18

28.41 BHP.
30 BHP.

=
=
=
=
=
=
=
=
=
=
=
=

180
121
164
20
29520
50
1476000
2214000
18
123000
5.47
9.00

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.

=
=
=
=
=

180
20
164
29520
50

Acres.
Year.
pers/acre
Persons
GPCD.

Average day demand


Adding 10% for institutions
Take 1/6 of average day demand for OHR
Proposed Capacity of GST.

No.

100000

Glns.
Total

=
=
=

1476000 Glns.
1623600 Glns.
162360 Glns.

=
=

200,000 Glns.
200,000 Glns.

Say

=
100,000 Glns.
=
16,000 Cft.
=
1 No:
=
16,000 Cft.
=
16 Ft.
16000 /
16
=
1,000.00 Sft.
1000
x4x7/22)^.5
=
35.68 Ft.
Say:
=
36.00 Ft.
It is proposed to construct 1 No Ground storage tank 50 ft. dia. with 16 ft. working depth and 1.50 ft: dead storage
and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
Volum of GST.
Proposed No. of tanks.
Capacity of tank.
Proposed working depth of tank.
Area of tank
Dia of tank=

MACHINERY FOR GST.


Design period
Density per acre as per 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

21780
1089000

x
x

50
1.5

1633500

/
Or
Say
2

18

Average daily demand


Available pumping set(0.82 cusecs,130' Head,40 BHP)

=
=
=
=
=
=
=
=
=
=
=
=

No
Say

Proposed No of Sets.

1+1

Nos

HEAD LOSSES.
Suctional Head
Loss in specials
Head loss pipe line i/c height of OHR(as per Hyd.Statement)
Total
Say
BHP of Electric Motor for 1.00 Cusec
62.5
x
1.00
550

x
x

160
60

=
=
=
=
=
=
=
=

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

2.36 Cusec.
2.00 Cusec.
2 No.
20.00
5.00
130
155.00
160.00

Feet.
Feet.
Feet.
Feet.
Feet.

100

=
Say
=
So it is proposed to install 2 Sets of vertical turbine pumps capable to give a discharge of
1.00 cusec against a total head of 160 Ft directly coupled with vertical AC Electric Motor of 30
BHP with 15 Ft: column pipei/c assembly
DESIGN OF ZONE -12
Area of Zone-12
Density per acre as per 2023
Density per acre as per 2033
Design period
Projected Population upto 2033
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

10
121
180
21780
50
1089000
1633500
18
90750
4.03
4.00
1.64

15088
754400

x
x

50
1.5

1131600

18

=
=
=
=
=
=
=
=
=
=

30.30 BHP.
30 BHP.

92
121
164
20
15088
50
754400
1131600
18
62867

Acres.
pers/acre
pers/acre
Year.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.

Or
Say

=
=

DESIGN OF OHR AND GST.


Area of Zone-12
Design period
Density per acre as per 2033
Projected population upto 2033
Consumption per capita
Average day demand
Adding 10% for institutions
Take 1/10 of average day demand for OHR
Available Capacity of GST

No.

10000

Glns.
Total

2.79 Cusec.
9.00 Cusec.

=
=
=
=
=
=
=
=

92
20
164
15088
50
754400
829840
82984

Acres.
Year.
pers/acre
Persons
GPCD.
Glns.
Glns.
Glns.

=
=

20,000 Glns.
20,000 Glns.

Balance Capacity for GST.

=
62,984 Glns.
=
60,000 Glns.
Volum of GST.
=
9,600 Cft.
Proposed No. of tanks.
=
1 No:
Capacity of tank.
=
9,600 Cft.
Proposed working depth of tank.
=
16 Ft.
Area of tank
9600 /
16
=
600.00 Sft.
Dia of tank=
600
x4x7/22)^.5
=
27.64 Ft.
Say:
=
28.00 Ft.
It is proposed to construct 1 No Ground storage tank 50 ft. dia. with 16 ft. working depth and 1.50 ft: dead storage
and 1.0 ft: Free Board. Total Depth of GST, is 20 Feet.
Say

MACHINERY FOR GST.


Design period
Density per acre as per 2023
Area served
Projected Population upto 2023
Consumption
Average daily demand
Maximum daily demand
Proposed working hour
Discharge per hour

11132
556600

x
x

50
1.5

834900

/
Or
Say
1

18

Average daily demand


Available pumping set(1 cusecs,160' Head,30 BHP)

=
=
=
=
=
=
=
=
=
=
=
=

No
Say

Proposed No of Sets.

1+1

Nos

HEAD LOSSES.
Suctional Head
Loss in specials
Head loss pipe line i/c height of OHR(as per Hyd.Statement)
Total
Say
BHP of Electric Motor for 1.00 Cusec
62.5
x
1.00
550

x
x

160
60

=
=
=
=
=
=
=
=

10
121
92
11132
50
556600
834900
18
46383
2.06
2.00
1.64

Year.
pers/acre
Acres.
Persons
GPCD.
Glns.
Glns.
Hours.
Glns.
Cusec.
Cusec.
Cusec.

0.36 Cusec.
2.00 Cusec.
2 No.
20.00
20.00
110
150.00
160.00

Feet.
Feet.
Feet.
Feet.
Feet.

100

=
Say
=
So it is proposed to install 2 Sets of vertical turbine pumps capable to give a discharge of
1.00 cusec against a total head of 150 Ft directly coupled with vertical AC Electric Motor of 30
BHP with 15 Ft: column pipei/c assembly

30.30 BHP.
30 BHP.

SCOPE OF WORK
The estimate consists of following scope.
Sub Work No.1
Sub Work No.2
Sub Work No.3
Sub Work No.4
Sub Work No.5

Sub Work No.6


Sub Work No.7
(a)
(b)

Sub Work No.8


Sub Work No.9
Sub Work No.10
a)
a)
Sub Work No.11

Survay & Investigation


Tubewell 1 Cusec discharge
Pump House 12'x12'
Pumping Machinery
Rising Main/Inter Connection
28'' i/d
24'' i/d
20" i/d
18" i/d
16" i/d
14" i/d
12" i/d
10" i/d
8" i/d
6" i/d
4" i/d
3" i/d
G.S.T
Pumping Machinery.for GST

=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=

20
20
20
20

Job
Nos
Nos
Sets

#REF!
#REF!
#REF!
34000
#REF!
29386
5420
500
100
100
#REF!
#REF!
3

Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Rft
Nos

1 cusecs,30 BHP,150' Head


1 cusecs,40 BHP,200' Head
3 cusecs,100 BHP,200' Head
Staff Quarter

=
=
=
=
=

2
2
2
6
10

Sets
Sets
Sets
Nos
Nos

=
=
=
=
=

1
1
20
20
12

Nos
Nos
Jobs
Nos
Set

Hyphochlorinator
OHR
50000 Glns
100000 Glns
Transmission Line

Sub Work No 12 Hyphochlornator


Sub Work No 13 Generator
RATES

Rates provided in the estimate as per market for non schedule items and as per
market schedule rates(1st FEBRUARY, 2013 TO 31st JULY, 2013)
SPECIFICATION
The Work will be completed according to PHE specification inforced at
the time of execution of work and upto entire satisfication of Engineer in Charge.
FUNDS
Total funds will be provided by the Govt: of Punjab .
TIME LIMIT
The work will take 2 years for completion if full funds will be provided by the Govt:
LAND
The land will be purchased for intermediate pumping station by PHE department/TMA
O & M COST
After completion of the scheme TMA Sadiqabad will be responsible for O & M

COST
Total cost of the estimate is work out to

696.617 Millions

Sub Engineer

Sub Divisional Officer


Public Healt Engg: Sub Division
Sadiqabad

Executive Engineer
Public Health Engg: Division
Rahimyarkhan

SUB WORK NO. 1

SURVEY AND INVESTIGATION.

1 Provision for trial bore.


(Detail attached)

Rs.

424000

/-

Rs.

150000

/-

Rs.

574000

/-

2 Electric Resistivety Survey complete in all respect.


10

Nos.

Probes

@ Rs.

15000
Total

Each

DETAIL OF TRIAL BORE


1 Chapter 23 item No.1
Boring for tubewell in all types of soil except shingle and
rock, from ground level to 100 ft: (30m) depth, including
sinking and withdrawing of casing pipe, complete.
6" i/d
Rft
@ Rs.
147.45 P.Rft
100

Rs.

14745

/-

2 Chapter 23 item No.2


Boring for tubewell in all types of soil except shingle and
rock, from ground level to 100.1 ft:to 200 ft: (30 to 60 m) depth,
sinking and withdrawing of casing pipe, complete.
6" i/d
Rft
@ Rs.
229.95 P.Rft
100

Rs.

22995

/-

4 Chapter 23 item No.8


Furnishing samples of water from bore holes.
4 Nos.
@ Rs.

169.20

Per Rft.

Rs.

677

/-

5 Testing charges of water samples.


4 No.
@ Rs.

1000.00

Each

Rs.

4000

/-

Total

Rs.

42417

/-

Say.

Rs.

42400

/-

For 10 Nos

42400 x

10

424000

Sub Work No.2


TUBE WELL 1 Cusec
Chapter 23 item No.5
1

Direct Rotary / Reverse Rotary drilling of bore for tube wells in all type of soil except shingle,
gravel and rock.
From ground level to 250 below ground level. 15 to 18dia
0
to 250
Chapter 23 item No.7

200 Rft. @ Rs.

398.35

Per Rft.

Rs.

79670

/-

Rs.

10788

/-

Rs.

222000

/-

Rs.

287833

/-

Rs.

1500

/-

Rs.

13236

/-

1096.55 Per Hour

Rs.

78952

/-

169.20

Rs.

677

/-

1000.00 Each

Rs.

1000

/-

1000.00 Each
TOTAL

Rs.
Rs.

4000
699656

//-

Rs.

699700

/-

Providing strong substantially built box of deodar wood 4'x2-1/2'x9"(1200x750x225 mm),


with compartments, lock and locking arranagement, for preserving samples of strata from
bore hole.

P/Installing fiber glass strainer in tube-well bore holes including sockets, specials
sockets,special socket studs, intergral, Nylon locking straps, blind pipes with intergral
sockets joints to join the strainer with M.S blind pipe complete 12" i/d.i/c bail plug 2 ft: long.

1 Set @ Rs.

74 Rft

@ Rs.

10788.25

3000.00

Each

P.Rft

Chapter 23 item No.14


4

Providing and installing M.S. blind pipe socketed


/ welded joints, M.S. reducer (where
necessary) in tube well bore hole,i/c joining / welding with strainer etc. complete.
12 dia 1/4 thick

130 Rft

@ Rs.

2214.10 Per Rft.

P/F in position M.S. suspension clamp M.S flat iron 4' long embedded i/c (C.C 1:2:4)
complete in all respect 12 i/d.
1 No.

@ Rs.

1500

Each

Chapter 23 item No.18


6

Shrouding with graded pea gravel 3/8 to 1/8 (10 to 3 mm)around tube well in bore
hole.
3.142 x
1.50
x
1.5
x
0.25
x
200
=
353
Total
=
353
1.08
x
1.08
x
0.25
x
200
=
183
d/d for 12" 3.142 x
Total
183
353
183
=
=
170
Net Total
170
Cft. @ Rs.
77.75 Per Cft.
Chapter 23 item No.17

Cft
Cft
Cft
Cft

Testing and developing for tubewell of size 6" and above continuously. Upto 1.5 cusecs
discharge.
72 Hours @ Rs.
Chapter 23 item No.8

Furnishing samples of water from bore holes.


4 Nos.

@ Rs.

Per Rft.

P/F M.S. cap on tube well 12dia with locking arrangmewnt


1 No.
@ Rs.
10 Testing charges of water samples.
4 No.
@ Rs.

Say

(Rs.

For
10
6997000 C/o to G.Abstract of Cost.)

Nos

6997000

SUB WORK No: 3

PUMP HOUSE 12'x 12' SIZE.

Chapter 3 item No.21


1

Excavation in foundation of building bridges and other structures, including


degbelling, dressing refilling around structure with excavated earth,
watering and ramming lead upto one chain(30m)and lift upto 5 ft (1.5m) in
ordinary soil.
L.Wall

2 x

16.13

2.25

218

Cft.

Short Wall

2 x
4 x

10.13
19.5

x
x

3
2

x
x

2.25
1.25

=
=

137
195

Total
3833.30

355
Per %o

Cft.
Cft.
Cft.
Cft.

Plinth protection wall

355

Cft. @ Rs.

Rs.

1361 /-

Rs.

25537 /-

Rs.

94866 /-

Rs.

2616 /-

Chapter 6 item No.3


Cement concerete brick ballas 1/12" to 2" guage complete in all respect
(1:6:12).
2
L.Wall

2 x

16.13

0.75

73

Cft.

Short Wall
Under floor

2 x
2 x
4 x

10.13
12

x
x

3
12

x
x

0.75
0.5

=
=

46
144

19.5

0.25
Total
8479.35

=
=

39
301
Per %

Cft.
Cft.
Cft.

Plinth protection wall

301

Cft. @ Rs.

Cft.
Cft.

Chapter 7 item No.4


3

Pacca brick work in 1:5 cement sand morter in foundation and plinth.
Long wall
1st step:
2nd step:

2 x
2 x

15.38
15

x
x

2.25
1.875

x
x

0.5
0.5

=
=

35
28

Cft.
Cft.

3rd step:
Short wall
1st step:

2 x

14.63

1.5

3.5

154

Cft.

2 x

10.88

2 x
2 x

11.25
11.63

2.25
1.875
1.5

x
x
x

0.5
0.5
3.5

=
=
=

24
21
122

Cft.

2nd step:
3rd step:

x
x
x

1st step:

4 x

19.5

1.5

0.5

59

Cft.

2nd step:
3rd step:

4 x
4 x

19.5
19.5

x
x

1.13
0.75

x
x

0.5
2

=
=

44
117

Cft.
Cft.

604
Per %

Cft.
Cft.

32
27

Cft.
Cft.

59
Per %

Sft.
Sft.

Cft.
Cft.

Plinth protection wall

604 Cft. @ Rs.

Total
=
15716.65

Chapter 6 item No.33


4

Providing and laying DPC of cement cncrete1:2:4 ( using cement sand and
shingle ) i/c bitumen coating with 2 coats of bitumen 1-1/2 " thick
Long wall
short wall

2 x
2 x

14.25
12
59

x
x

1.125
1.125

Sft. @ Rs.

Chapter 7 item No.5


5

Pacca brick work in ground floor in 1:6 cement sand morter.

=
=
Total
=
4429.40

super structure
L.Wall

2 x

14.25

1.125

12

385

Cft.

Short Wall

2 x

12

1.125

12

324

Cft.

Parapet
L.Wall

2 x
2 x

x
x

0.75
0.75

x
x

=
=
=

29
27
765

Cft.

Short Wall

14.25
13

DEDUCTION.
Door.

1 x

1.125 x

32

Cft.

Almira
window.

1 x
1 x

3
3

x
x

9
14

Cft.
Cft.

c.window

2 x

0.75 x
1.125 x
1.125 x

7 =
4 =
4 =
1.5 =
Total
=

10
64

Cft.
Cft.

Per %

Cft.

Net

= 765-64
=
701
701 Cft. @ Rs.

1.375
1.375
Total

16143.35

Cft.
Cft.

Rs.

113165 /-

Per . Cft Cft.

Rs.

32339 /-

Chapter 6 item No.6


6

Providing and laying reinforced cement concrete (including pre- stressed


concrete) using coarse sand and screened graded and washed aggregate
in required shape and design, including forms, moulds, shuttering, lifting,
compacting, curing, rendering, and finishing exposed surface, complete
(but excluding the cost of steel reinforcement, its fabrication and placing in
position etc).
(a) (1) Reinforced cement concrete: in roof slab, columns lintels, girders
and other structural members laid in situ or pre cast laid in position, or pre
stressed members cast in situ, complete in all respect. Type X ( norminal
mix) 1:2:4
Roof slab

1 x

W. sun shade
D. sun shade

1 x
1 x

13.5
4
5

x
x
x

C.W. sun shade


Lintal Door

2 x
1 x

4.25
6

x
x

Lintal window
Lintal Almirah

1 x
1 x

5
5

x
x

Linta C.W

2 x

13.5 x
1.5 x
1.5 x
1.5 x
1.125 x

0.5
0.25
0.25

=
=
=

91
2
2

Cft.

0.25
0.5

=
=

3
3

Cft.
Cft.

1.125 x
1.125 x
1.125 x

0.5
0.5

=
=

3
3

Cft.
Cft.

0.5
Total

=
=

5
111

Cft.
Cft.

111 Cft. @ Rs.

290.85

Cft.
Cft.

Chapter 6 item No.9


7

Fabricatin of mild steel reinforcement for cement concrete including cutting


,bending,laying in position making joints and fastening I/c cost of steel
reinforcement (also including removal of rust from bars ) deformed bar.
111 x
6.75 x
341 Kg. @ Rs.

0.454 =
11460.85

341
Per %

Kg.
kg

Rs.

39051 /-

12
12
1.38
Total
1299.50

576
144
70
790
Per %

Sft
Sft
Sft
Sft
Sft.

Rs.

10271 /-

Chapter 11 item No.9


Cementer plaster 1:4 upto 20' height 1/2" thick
4
1
4

x
x
x

12 x
12 x
12.75 x

790 Sft. @ Rs.


Chapter 11 item No.18+31

=
=
=
=

Cement pointing struck joints on walls upto 20'(6 m) height ratio 1:2.
i/c extra cost of labour and material for red oxide pigment in cement
pointing to match with the colour of bricks.
plinth protection wall

14.25 x
20.25 x

15.13
1
Total

Sft
Sft

862

=
=

81
943

=
=

28
9

Sft
Sft

=
=

12
49

Sft
Sft

Sft

Deduction
Door
C.Window

1
2

x
x

4
3

x
x

Window

7
1.5
4
Total

= 943-49 =
894 Sft. @ Rs.

Net

894
Sft
1600.15
1387.15 +

Per % Sft.
213.00

Rs.

1145 /-

Per % Kg
456.15

Rs.

39574 /-

Rs.

1512 /-

Rs.

1558 /-

Chapter 25 item No.10+11


10 Fabrication of heavy steel work,with angle tees,flate iron ,round iron
and sheet iron for making trusses ,girders,tanks etc. i/c cutting ,drilling
revitting,handling assembling and fixing but excluding erection in position
i/c erection and fitting in position iron trusses ,staging of water tanks etc.
Door
Window

1 No.
1 No.

=
=

120
60

Kg.
Kg.

Almirah C.Window

1 No.
2 No.

=
=

54
80

Kg.
Kg.

Total =
314
Kg.
12603.15
314 Kg.. @ Rs.
12147.00 +
Chapter 13 item No.5
11 Preparing surface and painting of doors and window and C.Windows
any type ( i/c edges) three coas.
Door
1 x
2
x
4 x
7
Window
Almirah

1 x
1 x

2
2

x
x

3
3

x
x

C.Window

2 x

122 Sft. @ Rs.


567.95 +

4
4
1.5
Total

56

Sft

=
=

24
24

Sft
Sft

=
=

18
122

Sft
Sft

Per %

Sft.

68

Cft

38
106
Per %

Cft
Cft
Cft

120
96
216

Rft
Rft
Rft

1239.55
2 x

335.8

Chapter 7 item No.30


12 S/filling sand under floor or plugging in well.
Floor
1 x 11.63
x
plinth protection wall
4 x
17
x

11.63 x
2.25 x

106 Sft. @ Rs.

0.5

0.25
=
Total
=
1471.80

Chapter 10 item No.42


13 Providing and fixing marble strips of any shade for dividing the
mosaic flooring into panels.
size
1-1/2"x 3/8"
2 x
5
x
12
4 x
8
x
3
Total

=
=
=

216 Rft. @ Rs.

6.60

P.Rft

Rs.

1426 /-

Chapter 10 item No.15


14 Providing and laying topping of cement concrete 1:2:4 i/c surface
finishing and dividing in pannels.1-1/2" thick
1 x
12
x
12
4 x

17.25

3
Total

216 Sft. @ Rs.

=
=
=

2986.85

Chapter 3 item No.15


15 Filling, watering and ramming earth under floor.with surplus earth
from foundation , etc.
2 x 16.13
x
3
x
2.25
=
Plinth protection wall
2 x 10.13
x
3
x
2.25
=
4 x
19.5
x
2
x
1.25
=
Total
=
355 Cft. @ Rs.
1829.50
Chapter 9 item No.5
16 Single layer of tiles 9''x4.5''x1.5"(225x113x40 mm) laid 4"(100 mm)earth
and 1"(25 mm)mud plaster with out Bhoosa, qrouted with cement sand in
1:3 on top of RCC roof slab provided with 34 Lbs:% Sft or 1.72 Kg/Sq.m
bitumen coating sand blinded.
1 x

13.5
x
13.5
182 Sft. @ Rs.

=
5799.05

Chapter 9 item No.14


17 Khasi parnalas in cement sand morter 1:2:12" out side with finished
smooth with a floating coat of neat cement.
1 x
15
=
15 Rft. @ Rs.
70.55
Chapter 9 item No.15
18 Khurras on roof 2'x2'x6" (600x600x150 mm)
1 No. @ Rs.
Chapter 9 item No.16

376.90

19 Bottom khuras of brick masonary in cement mortor 1:6,


4'x2'x4.5"(1200x600x113 mm) over 3" cement concrete (1:4:8).
1 No. @ Rs.
697.30
Chapter 11 item No.25
20 White washing three coats. On new surface.
790 Sft.
As per item No. 8
790 Sft. @ Rs.

353.90

Chapter 10 item No.9


21 Brick on edge flooring laid in 1:6 cement sand mortor
over a bed of 3/4"(20 mm) cement sand mortor. 1:6
2 x 20.25
x
3
2 x 14.25
x
3
207 Sft. @ Rs.
22 Providing and fixing ceiling Fan ( GFC, ROYAL)

Total
6699.40

=
=
=

=
1.00 No. @ Rs.
23 Providing and hoisting R.S joist size 4x8" of 18 Lbs.
14.25 x
1
14.25 Rft. @ Rs.

3000.00
=
882.75

144
207
351

Sft

P.%

Sft

Rs.

6452 /-

218
137
195
355
P.%0

Cft.
Cft.
Cft.
Cft.
Cft

Rs.

649 /-

182
P.%

Sft
Sft

Rs.

10569 /-

15
P.

Rft
Rft

Rs.

1058 /-

Each

Rs.

377 /-

Each

Rs.

697 /-

Sft
Sft

P. %

Sft

Rs.

2797 /-

122
86
207
P. %

Sft
Sft
Sft
Sft

Rs.

13868 /-

0.00
Per No.

Rft
Rs.

3000 /-

14.25
Per Rft

Rft
Rs.

12579 /-

For

10

Nos
4,165,000 C/O to General Abstract of cost

Total:Say:-

Rs.
Rs.

416468 /416,500 /4,165,000

PUMPING MACHINERY (For Tube Well)

Sub work No. 4


1

Supplying, installtion and testing of vertical turbine pumping unit ( Manufactured by approved manufactures
of HUD & PHED) capable to give a discharge of 1 cusec of clear water against a total dynamic head of 190
ft. with 90 ft. colunmn pipe directly coupled with verticle 3 phase 40 BHP electric motor (Siemens ) 380/440
Volts holllow shaft with following technicall data and accessories complete in all respect. (1450 RPM)

ACCESSORIES
a) Supplying of tool kit comprising of one china spanner set, one china screw
wrench of 12" Size, 1 china insulated pliers 8" size and 1 china screw driver
set, 1 grase gun for lubricating.
b) Supplying of MCU (motor controll unit) of same rating as per electric motor
meter
ampareboard
meter4'x3'
.relays,transformer,circuit
breaker
c) consisting
Installationofofvolt
MCU
on matellic
made of 1/16" thick MS
sheet with
,on/off
switch
,fuse
etc.
complete
in
all
respect.
1-1/2x1-1/2x3/16" angle iron frame dully painted in smoke colour.
e) S/F phase indicator i/c cost of brass holder bulb 0 volts and its wiring
complete in all respect.
f) S/F of electric wiring of suitable size in flexible PVC pipe (safe & protected )
from energy
meterand
to MCU
electric motor.
g) Earthing
of motor
othertoequipment
using copper strip charcoal etc. as
per
specification
using
GI
wire
No.8
SWG
in GIon
pipe
1/2" dia
ressesed
or on
h) S/F CI flanged special of BSS quality required
delivery
complete
in all
surface
of
wall
complete
,with
1.5
meters
long
GI
pipe
,2"
dia
4-5
meters
respect.
deep or upto spring level and 2 meters away from wall.
i) S/F kit kat fuses 0 to 500 volts 4" dia on bord china made
j) S/F base plate of channal 2.50"x2.50" of suitable size properly grouted in
foundation i/c nuts and bolts complete in al respect.
k) PCC (1:2:4) foundation of pump and motor as per manufacturer's
specification with stainless steel Nuts and Bolts complete in all respect
l) S/F 4" i/d CI non return valve BSS on delivery.
m) S/F CI sluice valve of 4" i/d as per BSS on delivery end complete in all
respect.
n) Internal electification of pump house complete for lighting inside and out side
i/c pluges,
and
tube
complete
all respect.
o) S/F
delivery
pipe
4" light
i/d MS
pipe in in
pump
house 25 ft: out side pump house
to connect with rising main complete in all respect.
p) Supplying of test report from MEPCO (WAPDA) by the approved
contractors.
q) Providing and fixing chain pully block 3 tons capacity with 5- meter chain
complete in all respect.
Complete .1 Set
### @ Rs.
###

1250000 Each

For
12500000

10

Nos

Set

No.

No.

1
1
1

Job.
Job.
Job.

Job.

Nos.

Job.

1
1
2

Job.
No.
No.

1
1

Job.
Job.

1
1

No.
Set

Rs.
Rs.

1250000
1250000
12500000

C/O to general Abstract of cost.

Conditions.
i
ii
iii
iv
v

Minimum efficiency of pumping machinery must be at least 75%


Two years un conditioned full warranty to be obtained from contractor/ manufacture.
Physical test for efficiency of pump at the test bed of manufacture before supply.
Contractor must mention the name of the approved manufacturer at the time of submitting tender.
The contractor will install the machinery under supervision of the manufacturer representative.

vi

The MCU will be certified for capability by the manufacturer of pumping machinery.

Sub work No. 5


1

SOLAR PUMP

Supplying, installtion and testing of solar pumping unit ( Manufactured by approved


manufactures of HUD & PHED/ WAPDA) capable to give a discharge of 1 cusec of clear
water against a total dynamic head of 170 ft. with 70 ft. colunmn pipe directly coupled
complete solar energy system.

Complete .1 Set
### @ Rs.
###

4780000 Each

For
9560000

Nos

C/O to general Abstract of cost.

Rs.
Rs.

4780000
4780000
9560000

SUB WORK NO. 5

RISING MAIN/DISTRIBUTION SYSTEM

Chapter No. 3 item No.44


1 Earth work excavation of trenches in all kinds of soil except cutting rock for water supply pipe
line up to 5' depth G . L. I. /c trimming dressig sides leveling the beds of trenches to correct
grade cutting its for jiontnig etc :comlete in all respect .

500 mm dia HDPE pipe


450 mm dia HDPE pipe
400 mm dia HDPE pipe
355 mm dia HDPE pipe
12'' dia PVC pipe
10'' dia PVC pipe
8'' dia PVC pipe
6'' dia PVC pipe
4'' dia PVC pipe
3'' dia PVC pipe

(20'')
(18'')
(16'')
(14'')

34000
22800
29386
1000
5420
500
7500
500
100
100

x
x
x
x
x
x
x
x
x
x

4.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
2.50
2.00

x
x
x
x
x
x
x
x
x
x

4.50
4.00
4.00
4.00
4.00
4.00
4.00
4.00
3.75
3.50

=
=
=
=
=
=
=
=
=
=

612000
273600
352632
12000
65040
6000
90000
6000
938
700

Total
cft
1418910
2735.05 Per %o Cft.

1418910 Cft. @ Rs.

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

Rs.

3880790 /-

Chapter No. 23 item No.26


2 P/L Cutting jointing testing and disinfecting PVC pipe line of BSS with '' B''class working
pressure pipe in tranches complete in all respect:

500 mm dia HDPE pipe


450 mm dia HDPE pipe
400 mm dia HDPE pipe
355 mm dia HDPE pipe
12'' dia PVC pipe
10'' dia PVC pipe
8'' dia PVC pipe
6'' dia PVC pipe
4'' dia PVC pipe
3'' dia PVC pipe

(20'')
(18'')
(16'')
(14'')

34000
22800
29386
1000
5420
500
7500
500
100
100

Rft. @
Rft. @
Rft. @
Rft. @
Rft. @
Rft. @
Rft. @
Rft. @
Rft. @
Rft. @

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

6600.50
3362.73
2632.80
2152.40
1084.95
779.95
502.50
326.10
168.90
112.15

Per Rft.
Per Rft.
Per Rft.
Per Rft.
Per Rft.
Per Rft.
Per Rft.
Per Rft.
Per Rft.
Per Rft.

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

224417000
76670244
77367461
2152400
5880429
389975
3768750
163050
16890
11215

//////////-

Chapter No. 23 item No.22


3 P/L Cutting jointing testing and disinfecting G.I pipe in tranches with socket joints using G.I
pipes of BSS 1387-1967 complete in all respect with specials and valves: for canal crossing
20"dia G.I Medium Quality pipe
Chapter No. 23 item No.
4 P/F C. I. Special of BSS Class "B"
5 % of total cost of item No. 2+3 =
Chapter No. 23 item No.13

950

Rft. @

Rs.

11000.00 Per Rft.

311736835

Rs.

10450000 /-

Rs.

15586842 /-

Rs.

25687 /-

Rs.

215205 /-

Rs.
Rs.
Rs.

1690000 /1036835 /1049270 /-

5 Providing and installing P.V.C Bail/End plug, in tubewell bore hole.


3" i/d

435 No.

Rs.

59.05 Each

Chapter No. 23 item No.33


6 P/F Air Valve 3" dia. of BSS quality and weight with flenged joint complete (I/c cost of
jointing materials.) double.
29 No. @ Rs.
7420.85 Each
Chapter No. 23 item No.30
7 P/F S/Valve of BSS quality and weight for class B' for cost iron pipe line ,and Asbostos
cement pipe line(i/c cost of jointing materials.)
20" i/d
18" i/d
16" i/d

13 No. @ Rs.
9 No. @ Rs.
16 No. @ Rs.

###
Each
115203.85 Each
65579.40 Each

12" i/d
20 No. @ Rs.
35809.80 Each
8" i/d
25 No. @ Rs.
21538.95 Each
6" i/d
30 No. @ Rs.
12161.10 Each
4" i/d
45 No. @ Rs.
7363.20 Each
3" i/d
60 No. @ Rs.
6247.50 Each
8 Const: of Sluice Valave / Air valve Chamber size 3' x 3'
247 Nos. @ Rs.
18,300 Each
9 P/F Non Return Valve for 6" dia PVC/AC. pipe line (I/c cost of jointing materials.)
28"dia
12 No. @ Rs.
80000.00 Each

Rs.
Rs.
Rs.
Rs.
Rs.

716196
538474
364833
331344
374850

/////-

Rs.

4520100 /-

Rs.

960000 /-

Rs.

1033875 /-

138684 Cft.
138684 Cft.
Per %o Cft.
Rs.

1010521 /-

Chapter No.3 item No.13


10

Back filling of earth by rehandling of earth work laid upto single throw of Kassi
&/compaction.
Take 80% of Item NO:1 above
1418910 x
80/100
1135128 Cft. @ Rs.

1135128 Cft
910.80 %o Cft

Chapter No. 4 item No.45


11 Dismentlig and removing road mentling.
19050

8.00

138684 Cft. @ Rs.

0.91
Total
728.65

Chapter No. 21 item No.12c


12 Restoration of metalled road, on laid service line, including 13.1
compaction:-Black Topped Road with two coats of surfacing & 10"(250 mm) depth of stone
metal, for sub base & base.
19050

8.00

138684 Cft. @ Rs.

0.91
=
138684 Cft.
Total
138684 Cft.
4225.70 Per % Cft.
Rs.

Chapter No. 4 item No.29


13 Dismentiling brick or flaged flooring without concrete foundatin.
12000
x
4.00
48000 Cft. @ Rs.

=
Total
309.65

48000 Cft.
48000 Cft.
Per % Cft.
Rs.

5860370 /-

148632 /-

Chapter No.21 item No.10


14 Restoration of brick pavement sand grouted over 2" (50mm ) thick dry sand cushion, under
soiling on laid service line.
12000
x
4.00
x
=
48000 Cft.
Total
48000 Sft.
48000 Cft
2573.45 Per % Cft.
Rs.
1235256
15 Demand Notice for Canal crossing
Rs.
600000
16 Demand Notice for Highway & Railway crossing i/c box culvert by NHA
Rs.
5000000
17 Provision for under ground services for Sui-Gass, Telephone, water supply etc.
Rs.
2500000
Total:Rs. 449,966,493
Say
Rs. 449966500
(Rs.
449966500
C/o to G.Abstract of Cost.)
Note
Provision for repair of under ground services is only for estimation purpose.Payment will be made
against certified demand notice.Saving will not be utilised in other sub heads.

//////-

IPS 900000 Glns

Sub work No.6

1 Design & Construction of RCC ground storage tank having a capcity 900000
Gallons i/c of sami circular pumping chamber for pumping machinery, i/c of soil
investigation complete.

900000 Glns

### @ Rs.
###

25

For

P Glns

Rs.
Rs.

Nos

22500000
22500000
67500000

2 Boundary wall for IPS

Rs.

2474900

3 Gate and Pillar

Rs.

52500

4 Land acquision for IPS near Ahmadpur Lamma(4 Acre)

Rs.

8000000

G. Total
Rs.
C/O to general Abstract of cost.

78027400

78027400

GST 200000 Glns

Sub work No. 7

1 Design & Construction of RCC ground storage tank having a capcity 200000
Gallons i/c of sami circular pumping chamber for pumping machinery, i/c of soil
investigation complete (Zone-3)

200000 Glns

### @ Rs.

45.16 P Glns

For
1
GST 100000 Glns

Rs.

Nos

9032700
9032700

1 Design & Construction of RCC ground storage tank having a capcity 100000
Gallons i/c of sami circular pumping chamber for pumping machinery, i/c of soil
investigation complete(Zone-1&4)

100000 Glns

### @ Rs.

55.75 P Glns

For
2
GST 50000 Glns

Rs.

Nos

5574800
11149600

1 Design & Construction of RCC ground storage tank having a capcity 60000
Gallons i/c of sami circular pumping chamber for pumping machinery, i/c of soil
investigation complete (Zone-7)

60000 Glns

### @ Rs.

91.41

For

P Glns

Rs.

Nos

Rs.
Total
C/O to general Abstract of cost.

5484800
5484800

25667100

Sub work No. 8 (a)


1

PUMPING MACHINERY (For IPS)

Supplying, installtion and testing of vertical turbine pumping unit ( Manufactured by approved manufactures
of HUD & PHED) capable to give a discharge of 4 cusec of clear water against a total dynamic head of 170
ft. with 25 ft. colunmn pipe directly coupled with verticle 3 phase 120 BHP electric motor (Siemens ) 380/440
Volts holllow shaft with following technicall data and accessories complete in all respect.(960 RPM)

ACCESSORIES
a) Supplying of tool kit comprising of one china spanner set, one china screw
wrench of 12" Size, 1 china insulated pliers 8" size and 1 china screw driver
set, 1 grase gun for lubricating.

Set

No.

c) Installation of MCU on matellic board 4'x3' made of 1/16" thick MS sheet with
1-1/2x1-1/2x3/16" angle iron frame dully painted in smoke colour.

No.

e) S/F phase indicator i/c cost of brass holder bulb 0 volts and its wiring
complete in all respect.

Job.

f)
g)
h)

1
1
1

Job.
Job.
Job.

1
3

Job.
Nos.

Job.

1
1
2

Job.
No.
No.

1
1

Job.
Job.

1
1

No.
Set

Rs.
Rs.

2000000
2000000

b) Supplying of MCU (motor controll unit) of same rating as per electric motor
consisting of volt meter ampare meter .relays,transformer,circuit breaker
,on/off switch ,fuse etc. complete in all respect.

S/F of electric wiring of suitable size in flexible PVC pipe (safe & protected )
from
energy
meterand
to MCU
electric motor.
Earthing
of motor
othertoequipment
using copper strip charcoal etc. as
per
specification
using
GI
wire
No.8
SWG
in GIon
pipe
1/2" dia
ressesed
or on
S/F CI flanged special of BSS quality required
delivery
complete
in all
surface
of
wall
complete
,with
1.5
meters
long
GI
pipe
,2"
dia
4-5
meters
respect.
deep or upto spring level and 2
i) S/F kit kat fuses 0 to 500 volts 4" dia on bord china made
j) S/F base plate of channal 2.50"x2.50" of suitable size properly grouted in
foundation i/c nuts and bolts complete in al respect.

k) PCC (1:2:4) foundation of pump and motor as per manufacturer's


specification with stainless steel Nuts and Bolts complete in all respect
l) S/F 4" i/d CI non return valve BSS on delivery.
m) S/F CI sluice valve of 4" i/d as per BSS on delivery end complete in all
respect.
n) Internal electification of pump house complete for lighting inside and out side
and
tube
complete
all respect.
o) i/c
S/Fpluges,
delivery
pipe
4" light
i/d MS
pipe in in
pump
house 25 ft: out side pump house
to connect with rising main complete in all respect.
p) Supplying of test report from MEPCO (WAPDA) by the approved
contractors.
q) Providing and fixing chain pully block 3 tons capacity with 5- meter chain
complete in all respect.
Complete .1 Set
### @ Rs.
###

2000000 Each

For
10000000

Nos

10000000

C/O to general Abstract of cost.

Conditions.
i
ii
iii
iv
v

Minimum efficiency of pumping machinery must be at least 75%


Two years un conditioned full warranty to be obtained from contractor/ manufacture.
Physical test for efficiency of pump at the test bed of manufacture before supply.
Contractor must mention the name of the approved manufacturer at the time of submitting tender.
The contractor will install the machinery under supervision of the manufacturer representative.

vi

The MCU will be certified for capability by the manufacturer of pumping machinery.

Sub work No. 8 (b)


1

PUMPING MACHINERY (For GST)

Supplying, installtion and testing of vertical turbine pumping unit ( Manufactured by approved manufactures
of HUD & PHED) capable to give a discharge of 1 cusec of clear water against a total dynamic head of 150
ft. with 25 ft. colunmn pipe directly coupled with verticle 3 phase 30 BHP electric motor (Siemens ) 380/440
Volts holllow shaft with following technicall data and accessories complete in all respect. (1450 RPM)

ACCESSORIES
a) Supplying of tool kit comprising of one china spanner set, one china screw
wrench of 12" Size, 1 china insulated pliers 8" size and 1 china screw driver
set, 1 grase gun for lubricating.
b) Supplying of MCU (motor controll unit) of same rating as per electric motor
consisting of volt meter ampare meter .relays,transformer,circuit breaker
,on/off switch ,fuse etc. complete in all respect.
c) Installation of MCU on matellic board 4'x3' made of 1/16" thick MS sheet with
1-1/2x1-1/2x3/16" angle iron frame dully painted in smoke colour.
e) S/F phase indicator i/c cost of brass holder bulb 0 volts and its wiring
complete in all respect.
f) S/F of electric wiring of suitable size in flexible PVC pipe (safe & protected )
energy
meterand
to MCU
electric motor.
g) from
Earthing
of motor
othertoequipment
using copper strip charcoal etc. as
per
specification
using
GI
wire
No.8 SWG
in GIon
pipe
1/2" dia
ressesed
or on
h) S/F CI flanged special of BSS quality
required
delivery
complete
in all
surface
of
wall
complete
,with
1.5
meters
long
GI
pipe
,2"
dia
4-5
meters
respect.
deep or upto spring level and 2 meters away from wall.
i) S/F kit kat fuses 0 to 500 volts 4" dia on bord china made
j) S/F base plate of channal 2.50"x2.50" of suitable size properly grouted in
foundation i/c nuts and bolts complete in al respect.
k) PCC (1:2:4) foundation of pump and motor as per manufacturer's
specification with stainless steel Nuts and Bolts complete in all respect
l) S/F 4" i/d CI non return valve BSS on delivery.
m) S/F CI sluice valve of 4" i/d as per BSS on delivery end complete in all
respect.
n) Internal electification of pump house complete for lighting inside and out side
and
tube
complete
all respect.
o) i/c
S/Fpluges,
delivery
pipe
4" light
i/d MS
pipe in in
pump
house 25 ft: out side pump house
to connect with rising main complete in all respect.
p) Supplying of test report from MEPCO (WAPDA) by the approved
contractors.
q) Providing and fixing chain pully block 3 tons capacity with 5- meter chain
complete in all respect.
Complete .1 Set
### @ Rs.
###
For
2200000

1100000 Each

Nos

Set

No.

No.

1
1

Job.
Job.

1
1

Job.
Job.

1
3

Job.
Nos.

Job.

1
1
2

Job.
No.
No.

1
1

Job.
Job.

1
1

No.
Set

Rs.
Rs.

1100000
1100000
2200000

C/O to general Abstract of cost.

Conditions.
i
ii
iii
iv
v
vi

Minimum efficiency of pumping machinery must be at least 75%


Two years un conditioned full warranty to be obtained from contractor/ manufacture.
Physical test for efficiency of pump at the test bed of manufacture before supply.
Contractor must mention the name of the approved manufacturer at the time of submitting tender.
The contractor will install the machinery under supervision of the manufacturer representative.
The MCU will be certified for capability by the manufacturer of pumping machinery.

Sub work No. 8 (c)


1

PUMPING MACHINERY (For GST)

Supplying, installtion and testing of vertical turbine pumping unit ( Manufactured by approved manufactures
of HUD & PHED) capable to give a discharge of 1 cusec of clear water against a total dynamic head of 200
ft. with 25 ft. colunmn pipe directly coupled with verticle 3 phase 40 BHP electric motor (Siemens ) 380/440
Volts holllow shaft with following technicall data and accessories complete in all respect.(1450 RPM)

ACCESSORIES
a) Supplying of tool kit comprising of one china spanner set, one china screw
wrench of 12" Size, 1 china insulated pliers 8" size and 1 china screw driver
set, 1 grase gun for lubricating.

Set

No.

c) Installation of MCU on matellic board 4'x3' made of 1/16" thick MS sheet with
1-1/2x1-1/2x3/16" angle iron frame dully painted in smoke colour.

No.

e) S/F phase indicator i/c cost of brass holder bulb 0 volts and its wiring
complete in all respect.

Job.

f)
g)
h)

1
1
1

Job.
Job.
Job.

1
3

Job.
Nos.

Job.

1
1
2

Job.
No.
No.

1
1

Job.
Job.

1
1

No.
Set

Rs.
Rs.

1250000
1250000

b) Supplying of MCU (motor controll unit) of same rating as per electric motor
consisting of volt meter ampare meter .relays,transformer,circuit breaker
,on/off switch ,fuse etc. complete in all respect.

S/F of electric wiring of suitable size in flexible PVC pipe (safe & protected )
from
energy
meterand
to MCU
electric motor.
Earthing
of motor
othertoequipment
using copper strip charcoal etc. as
per
specification
using
GI
wire
No.8
SWG
in GIon
pipe
1/2" dia
ressesed
or on
S/F CI flanged special of BSS quality required
delivery
complete
in all
surface
of
wall
complete
,with
1.5
meters
long
GI
pipe
,2"
dia
4-5
meters
respect.
deep or upto spring level and 2 meters away from wall.
i) S/F kit kat fuses 0 to 500 volts 4" dia on bord china made
j) S/F base plate of channal 2.50"x2.50" of suitable size properly grouted in
foundation i/c nuts and bolts complete in al respect.

k) PCC (1:2:4) foundation of pump and motor as per manufacturer's


specification with stainless steel Nuts and Bolts complete in all respect
l) S/F 4" i/d CI non return valve BSS on delivery.
m) S/F CI sluice valve of 4" i/d as per BSS on delivery end complete in all
respect.
n) Internal electification of pump house complete for lighting inside and out side
and
tube
complete
all respect.
o) i/c
S/Fpluges,
delivery
pipe
4" light
i/d MS
pipe in in
pump
house 25 ft: out side pump house
to connect with rising main complete in all respect.
p) Supplying of test report from MEPCO (WAPDA) by the approved
contractors.
q) Providing and fixing chain pully block 3 tons capacity with 5- meter chain
complete in all respect.
Complete .1 Set
### @ Rs.
###

1250000 Each

For
1250000

Nos

1250000

C/O to general Abstract of cost.

Conditions.
i
ii
iii
iv
v

Minimum efficiency of pumping machinery must be at least 75%


Two years un conditioned full warranty to be obtained from contractor/ manufacture.
Physical test for efficiency of pump at the test bed of manufacture before supply.
Contractor must mention the name of the approved manufacturer at the time of submitting tender.
The contractor will install the machinery under supervision of the manufacturer representative.

vi

The MCU will be certified for capability by the manufacturer of pumping machinery.

Sub work No. 8 (d)


1

PUMPING MACHINERY (For GST)

Supplying, installtion and testing of vertical turbine pumping unit ( Manufactured by approved manufactures
of HUD & PHED) capable to give a discharge of 3 cusec of clear water against a total dynamic head of 200
ft. with 25 ft. colunmn pipe directly coupled with verticle 3 phase 100 BHP electric motor (Siemens ) 380/440
Volts holllow shaft with following technicall data and accessories complete in all respect.(960 RPM)

ACCESSORIES
a) Supplying of tool kit comprising of one china spanner set, one china screw
wrench of 12" Size, 1 china insulated pliers 8" size and 1 china screw driver
set, 1 grase gun for lubricating.

Set

No.

c) Installation of MCU on matellic board 4'x3' made of 1/16" thick MS sheet with
1-1/2x1-1/2x3/16" angle iron frame dully painted in smoke colour.

No.

e) S/F phase indicator i/c cost of brass holder bulb 0 volts and its wiring
complete in all respect.

Job.

f)
g)
h)

1
1
1

Job.
Job.
Job.

1
3

Job.
Nos.

Job.

1
1
2

Job.
No.
No.

1
1

Job.
Job.

1
1

No.
Set

Rs.
Rs.

1700000
1700000

b) Supplying of MCU (motor controll unit) of same rating as per electric motor
consisting of volt meter ampare meter .relays,transformer,circuit breaker
,on/off switch ,fuse etc. complete in all respect.

S/F of electric wiring of suitable size in flexible PVC pipe (safe & protected )
from
energy
meterand
to MCU
electric motor.
Earthing
of motor
othertoequipment
using copper strip charcoal etc. as
per
specification
using
GI
wire
No.8
SWG
in GIon
pipe
1/2" dia
ressesed
or on
S/F CI flanged special of BSS quality required
delivery
complete
in all
surface
of
wall
complete
,with
1.5
meters
long
GI
pipe
,2"
dia
4-5
meters
respect.
deep or upto spring level and 2 meters away from wall.
i) S/F kit kat fuses 0 to 500 volts 4" dia on bord china made
j) S/F base plate of channal 2.50"x2.50" of suitable size properly grouted in
foundation i/c nuts and bolts complete in al respect.

k) PCC (1:2:4) foundation of pump and motor as per manufacturer's


specification with stainless steel Nuts and Bolts complete in all respect
l) S/F 4" i/d CI non return valve BSS on delivery.
m) S/F CI sluice valve of 4" i/d as per BSS on delivery end complete in all
respect.
n) Internal electification of pump house complete for lighting inside and out side
and
tube
complete
all respect.
o) i/c
S/Fpluges,
delivery
pipe
4" light
i/d MS
pipe in in
pump
house 25 ft: out side pump house
to connect with rising main complete in all respect.
p) Supplying of test report from MEPCO (WAPDA) by the approved
contractors.
q) Providing and fixing chain pully block 3 tons capacity with 5- meter chain
complete in all respect.
Complete .1 Set
### @ Rs.
###

1700000 Each

For
3400000

Nos

3400000

C/O to general Abstract of cost.

Conditions.
i
ii
iii
iv
v

Minimum efficiency of pumping machinery must be at least 75%


Two years un conditioned full warranty to be obtained from contractor/ manufacture.
Physical test for efficiency of pump at the test bed of manufacture before supply.
Contractor must mention the name of the approved manufacturer at the time of submitting tender.
The contractor will install the machinery under supervision of the manufacturer representative.

vi

The MCU will be certified for capability by the manufacturer of pumping machinery.

SUB WORK No: 9

SINGLE ROOM STAFF QUARTER

Chapter 3 item No.21


1 Excavation in foundation of building bridges and other structures, including
degbelling, dressing refilling around structure with excavated earth,
watering and ramming lead upto one chain(30m)and lift upto 5 ft (1.5m) in
ordinary soil.
L.Wall Room
Short Wall
Small Wall Ver.
Kitchen Long Wall
Kitchen Short Wall
Bath
Short Wall

2
2
1
1
2
2
3

x
x
x
x
x
x
x

19.00
12.75
12.75
10.75
4.75
11.00
3.25

x
x
x
x
x
x
x

2.00
2.00
1.50
2.00
2.00
1.50
1.50

x
x
x
x
x
x
x

2.00
2.00
1.50
2.00
2.00
1.50
1.50
Total
3833.50

=
=
=
=
=
=
=
=

Cft. @ Rs.
436
Chapter 6 item No.3
2 Cement concrete brick or stone ballast 11/2'' to 2'' guage in foundation and
plinth.
Ratio (1:6:12)
L.Wall Room
2 x
=
19.00
x
2.00
x
0.75
Short Wall
2 x
=
12.75
x
2.00
x
0.75
Small Wall Ver.
1 x
=
12.75
x
1.50
x
0.75
Kitchen Long Wall
1 x
=
10.75
x
2.00
x
0.75
Kitchen Short Wall
2 x
=
4.75
x
2.00
x
0.75
Bath
2 x
=
11.00
x
1.50
x
0.75
Short Wall
3 x
=
3.25
x
1.50
x
0.75
Total =
Cft.
@
Rs.
213
8479.35
Chapter 7 item No.4
3 Pacca brick work in 1:5 cement sand morter in foundation and plinth.
L.Wall Room
Short Wall
Short Wall Ver.
Kitchen
Short Wall

Short Wall

2
2
2
2
1
1
1
2
2
2
3

x
x
x
x
x
x
x
x
x
x
x

17.75
17.375
13.25
13.625
14.00
10.25
9.875
5.25
5.625
8.75
4.00

x
x
x
x
x
x
x
x
x
x
x

1.50
1.125
1.50
1.125
0.75
1.50
1.125
1.50
1.125
0.75
0.75

x
x
x
x
x
x
x
x
x
x
x

0.75
2.125
0.75
2.125
2.125
0.75
2.125
0.75
2.125
2.125
2.125
Total
###

=
=
=
=
=
=
=
=
=
=
=
=

361 Cft. @ Rs.


Chapter 6 item No.33-b
4 Providing and laying DPC of cement cncrete1:2:4 ( using cement sand and
shingle ) i/c bitumen coating with 2 coats of bitumen 1-1/2 " thick
Long wall

Bath

2
1
2
2
1
2
3

x
x
x
x
x
x
x

14.00
14.00
17.75
6.00
9.50
10.25
4.00
131

x
x
x
x
x
x
x

1.125
0.75
1.125
1.125
1.125
0.75
0.75

Sft. @ Rs.

Total
4429.40

=
=
=
=
=
=
=
=

152
102
29
43
38
50
22
436
Per %o

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft. Rs.

1671 /-

57
76
14
16
14
25
11
213
Per %

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft. Rs.

18098 /-

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft. Rs.

56760 /-

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Sft.
Sft. Rs.

5780 /-

40
83
30
65
22
12
24
12
27
28
19
361
Per %

32
11
40
14
11
15
9
131
Per %

Chapter 7 item No.5


5 Pacca brick work in ground floor in 1:5 cement sand morter.
L.Wall Room
Short Wall Room
L.Wall ver.
Short Wall ver.
Kitchen
Kitchen

2
2
2
2
1
1
2
2

x
x
x
x
x
x
x
x

15.50
9.00
15.50
6.50
6.00
10.50
10.25
4.00

2
1
1
1
1
1
1
1
2
1
2
15.5

x
x
x
x
x
x
x
x
x
x
x
x

5.875
4.50
3.50
3.00
2.00
3.00
4.50
4.50
2.50
3.00
3.50
7.50

Bath & Lat:


Bath & Lat:

DEDUCTION.
Ver. Dening
Ver. Dening
Door
window
Window
C/Wall
Lintle door
Window of c/w
Bath & Lat:door
Window of c/w
Lintle

Lintle over open

Net

x
x
x
x
x
x
x
x

x
x
x
x
x
x
x
x
x
x
x
x

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

x
x
x
x
x
x
x
x

x
x
x
x
x
x
x
x
x
x
x
x

= 1005-194 =
811
811 Cft. @ Rs.

10.875
10.875
9.375
9.375
9.375
9.375
8.375
8.375
Total

=
=
=
=
=
=
=
=
=

253
148
218
91
42
74
129
50
1005

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

7.00
7.00
6.50
4.00
4.00
1.50
0.50
0.50
6.00
0.50
0.50
0.50
Total

=
=
=
=
=
=
=
=
=
=
=
=
=

62
24
17
9
6
3
2
2
23
1
3
44
194

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

###

Per %

Cft. Rs.

133799 /-

Chapter 6 item No.6


6 Providing and laying reinforced cement concrete (including pre- stressed
concrete) using coarse sand and screened graded and washed
aggregate in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering, and finishing exposed
surface, complete (but excluding the cost of steel reinforcement, its
fabrication and placing in position etc).
(a) (1) Reinforced cement concrete: in roof slab, columns lintels, girders
and other structural members laid in situ or pre cast laid in position, or pre
stressed members cast in situ, complete in all respect. Type C ( norminal
mix) 1:2:4
Slab of Room
Slabo of Ver.
Bath & Lat:

Lat. & Bath


Lintle over m/d
Lintle of window &
C-Window.
Lintle of window &
C-Window.
Lintle of over Lat: &
Bath.
Opening door

1
1
1
1
1
1

x
x
x
x
x
x

14.75
14.75
9.75
9.75
6.85
4.50
2.00

x
x
x
x
x
x
x

9.75
8.00
6.75
4.75
0.75
0.75
0.75

3.00

0.75

3.50

0.75

1 x (15.50+7.50)x

0.75

4 x
1 x
2 x

x
x
x
x
x
x
x
x
x
x

0.375
0.375
0.375
0.375
0.75
0.50
0.50
0.50
0.50

=
=
=
=
=
=
=
=
=

54
44
25
17
4
2
3
1
3

=
0.50
9
Total
=
162
290.85
Per . Cft

162 Cft. @ Rs.


Chapter 6 item No.9
7 Fabricatin of mild steel reinforcement for cement concrete including cutting
,bending,laying in position making joints and fastening I/c cost of steel
reinforcement (also including removal of rust from
bars ) deformed
bar.qty. as per item No. 6

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft. Rs.

46977 /-

Fabricatin of mild steel reinforcement for cement concrete including cutting


,bending,laying in position making joints and fastening I/c cost of steel
reinforcement (also including removal of rust from
bars ) deformed
bar.qty. as per item No. 6
1094 x

162 @
6.75
0.4536
496 Kg. @ Rs.

lbs./ Cft

=
=

1094 Kg.
496
Per %
kg Rs.

56873 /-

Sft
Sft
Sft
Sft
Sft
Sft Rs.

36577 /-

Per

Sft
Sft
Sft
Sft
Sft Rs.

10772 /-

206
122
115
43
263
594
1342
P.%0

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft Rs.

2455 /-

Cft
Cft
Cft
Cft.
Cft Rs.

1192 /-

Cft Rs.

6868 /-

11460.85
Chapter 12 item No.51
Providing and fixing panelled door of M.S sheet, with forged door leaves of
MS sheet 22 SWG fitted in hollow frame chowkat 3"x4-1/2"(75x113 mm)
made of MS sheet 18 SWG fitted with plain cement concrete 1:6:3 etc.
complete with all fittings and hammer painting ,i/c carriage to site and
fixing in position.
Door of C/yard
=
1
x
4.00
x
7.00
28
Room Door
=
1
x
3.50
x
6.50
23
Door Kitchen
=
1
x
3.00
x
6.50
20
Lat:& Bath.
=
2
x
2.50
x
6.00
30
Total
=
101
101 Sft.
@ Rs.
Per
362.15
Chapter 25 item No.41
Providing and fixing steel windows with open able glazed penals'
using beams sectionfor frame 1-1/2"x1"x5/8"x1 (40x25x16x3mm), Z
section for leaves 3/4"x1"x3/4"x1/8"(20x25x20x3 mm),T-section
sashes 1"x1"x1/8"(25x25x3 mm) glass panes, wooden screed for glazing
embeded over a thin layer of putty dully screed with leaves brasss fitting
holdfast , dully painted ,complete in all respect, i/c all cost of materials
and labour ,etc. as per approved design and as directed by the
Engineer -in-Charge.
with wire guage glass pane 2.50 mm thick 22 SWG
Window
1
x
4.00
C-Window
2
x
2.00
C-Window
1
x
3.00

x
x
x

29 Sft.
@ Rs.
Chapter 3 item No.15
Filling, watering and ramming earth under floor.with new earth
excavated earth from out side.
Room
1 x 13.625 x
8.63
x
Ver.
1 x 13.625 x
5
x
Kitchen
1 x
8.625
x
7.63
x
Bath & Lat:
2 x
3.375
x
3.63
x
C/Yard
1 x
20.00
x
7.50
x
1 x
14.75
x
23.00
x
1342 Cft. @ Rs.
Chapter 7 item No.30
S/filling sand under floor.
Room
1.00 x
Ver.
1.00 x
Bath & Lat:
2.00 x

14.00
14.00
4.00

x
x
x

9.00
6.00
4.00

x
x
x

3.00
3.00
1.50
Total
377.95

=
=
=
=

1.75
1.75
1.75
1.75
1.75
1.75
Total
1829.50

=
=
=
=
=
=
=

0.33
0.33
0.33
Total
1471.80

=
=
=
=

12
12
5
29

81 Cft. @ Rs.
P.%
Chapter 6 item No.3
Cement concrete brick or stone ballast 11/2'' to 2'' guage in foundation and
plinth. Ratio (1:6:12)
Qty. as per item No. 11 above
81 Cft. @ Rs.
8479.35
P.%
Chapter 11 item No.9
8 Cementer plaster 1:4 upto 20' height 1/2" thick

42
28
11
81

In side room
Ver L/Side
Short Side
Pillars
Kitchen
Para pit of room
Para pit of room
Para pit of lat: & bath
Compound

2.00
1.00
1.00
5.00
2.00
2.00
2.00
1.00
2.00
1.00

x
x
x
x
x
x
x
x
x
x

(14+9) x
x
14.00
x
6.00
x
1.25
x
3.38
x
(8+6)
(14.75+9.75) x
(6.75+6.75) x
(9.50+4.75) x
(16+18+20) x

10.00
8.00
8.00
7.00
7.00
9.375
2.25
2.25
1.88
1.88
Total

=
=
=
=
=
=
=
=
=
=
=

Deduction.
Door
Window
Kitchen

1.00
1.00
1.00

x
x
x

3.50
2.00
8.00

x
x
x

6.50
4.00
6.50
Total

=
=
=
=
=

Net

1268.00 82.75
1185 Sft. @ Rs.

1299.50
Chapter 10 item No.15
Providing and laying topping of cement concrete 1:2:4 i/c surface
finishing and dividing in pannels.3" (75mm) thick
Room
x
1.00
x
14.00
9.00
Ver:
x
1.00
x
14.00
6.00
Lat: & Bath.
x
2.00
x
4.00
4.00
Kitchen.
x
1.00
x
9.00
6.00
Total
Sft. @ Rs.
5193.50
296
Chapter 11 item No.18+31
9 Cement pointing struck joints on walls upto 20'(6 m) height ratio 1:2.
i/c extra cost of labour and material for red oxide pigment in cement
pointing to match with the colour of bricks.
Wall of Room
x
1.00
x
15.50
12.50
Room S/room
x
2.00
x
10.50
12.50
Ver: Long wall
x
2.00
x
15.50
2.50
Side wall of ver:
x
1.00
x
7.50
10.50
Lat: & Bath.
x
2.00
x
10.50
8.38
x
2.00
x
5.50
8.38
Total
Deduction
Lat: & Bath door
x
2.00
x
2.50
6.00
Total
30
=
Net 882 Sft.
@ Rs.
1600.15
852
Chapter 10 item No.6
1387.15
Dry brick on edge paving, sand grouted i/c preparation of bed by
watering ,ramming and bringing the same to the proper camber by
1/2" (13 mm) thick mud plaster.
Kitchen
x
1.00
x
8.00
3.00
x
1.00
x
9.00
3.00
x
1.00
x
20.00
7.50
x
1.00
x
14.75
23.00
Total
Sft.
@
Rs.
5313.00
540
Chapter 9 item No.15
Khurras on roof 2'x2'x6" (600x600x150 mm)
2 No. @ Rs.
376.90
Chapter 9 item No.16

=
=
=
=
=

=
=
=
=
=
=
=

460.00
112.00
48.00
44
47
263.00
110.00
30.00
53.00
101.00
1268.00

Sft
Sft
Sft
Sft
Sft
Sft
Sft
Sft
Sft
Sft
Sft

23
8
52
83
1185
Per %

Sft
Sft
Sft
Sft
Sft
Sft. Rs.

15402 /-

126
84
32
54
296
Per %

Sft
Sft
Sft
Sft
Sft
Sft. Rs.

15373 /-

194
263
78
79
176
92
882

Sft
Sft
Sft
Sft
Sft
Sft
Sft

=
=
=

Sft
30
30.00 Sft
852
Per %
Sft. Rs.
+
213.00

=
=
=
=
=

24
27
150
339
540
Per %

Each

13633 /-

Sft
Sft
Sft
Sft
Sft
Sft. Rs.

28703 /-

Rs.

754 /-

Bottom khuras of brick masonary in cement mortor 1:6,


4'x2'x4.5"(1200x600x113 mm) over 3" cement concrete (1:4:8).
2 No. @ Rs.
697.30
Each

Chapter 9 item No.14


Khasi parnalas in cement sand morter 1:2:12" out side with finished
smooth with a floating coat of neat cement.
1 x
=
Room
13
13
1 x
=
Ver.
11.00
11
Total
=
24
24 Rft.
@ Rs
70.55
P.Rft
Chapter 9 item No.5
Single layer of tiles 9''x4.5''x1.5"(225x113x40 mm) laid 4"(100 mm)earth
and 1"(25 mm)mud plaster with out Bhoosa, qrouted with cement sand in
1:3 on top of RCC roof slab provided with 34 Lbs:% Sft or 1.72 Kg/Sq.m
bitumen coating sand blinded.
1.00 x
=
14.00
x
9.00
126
1.00 x
=
14.00
x
6.00
84
1.00 x
=
9.00
x
6.00
54
Total
=
264
264.00 Sft. @ Rs.
5799.05
P.%
Chapter 11 item No.25 ( a )
White washing on new surface three coats.
Room
2.00 x (14+9) x
=
10.00
460
Ver:
2.00 x (14+6) x
=
8.00
320
Lat: & Bath
2.00 x (14+3) x
=
7.50
210
Room
1.00 x
=
14.00
x
9.00
126
Ceiling of ver:
1.00 x
=
14.00
x
6.50
91
Ceiling of lat: & bath
2.00 x
=
4.00
x
4.00
32
Kitchen
2.00 x
=
9+6
x
10.00
150
Total
=
1389
1389.00 Sft. @ Rs.
173.20
P.%

Rs.

1395 /-

Rs.

1693 /-

Sft
Sft
Sft
Sft
Sft Rs.

15309 /-

Sft
Sft
Sft
Sft
Sft
Sft
Sft
Sft
Sft Rs.

2406 /-

Cft.
Cft.
Cft.
Cft
Sft Rs.

627 /-

Cft.
Cft.
Cft.
Cft
Sft Rs.

1500 /-

Sft
Sft
Sft
Sft
Sft Rs.

2716 /-

Rft
Rft
Rft

Chapter 3 item No.21


Excavation in foundation of building bridges and other structures, including
degbelling, dressing refilling around structure with excavated earth,
watering and ramming lead upto one chain(30m)and lift upto 5 ft (1.5m) in
ordinary soil.
1 x
1 x
1 x

18.750
18.000
17.750

x
x
x

2.00
2.00
2.00

x
x
x

1.50
1.50
1.50
Total
3833.30

=
=
=
=

56
54
53
164
P.%o

164 Cft. @ Rs.


Chapter 6 item No.2
Dry rammed brick or stone ballast, 1-1/2" to 2" (40 to 50 mm) guage.
1 x 18.750 x
=
2.00
x
0.50
19
1 x 18.000 x
=
2.00
x
0.50
18
1 x 17.750 x
=
2.00
x
0.50
18
Total
=
55
55 Cft. @ Rs.
2752.20
P.%
Chapter 6 item No.33-b
Providing and laying DPC of cement cncrete1:2:4 ( using cement sand and
shingle ) i/c bitumen coating with 2 coats of bitumen 1-1/2 " thick
1 x 18.750 x
=
1.13
21
1 x 18.000 x
=
1.13
20
1 x 17.750 x
=
1.13
20
Total
=
61
61 Sft. @ Rs.
4429.40
P.%
Chapter 7 item No.4

Pacca brick work in 1:6 cement sand morter in foundation and plinth.
1 x 18.750 x
1.50
x
0.25
1 x 18.750 x
1.13
x
1.50
1 x 18.000 x
1.50
x
0.25
1 x 18.000 x
1.13
x
1.50
1 x 17.750 x
1.50
x
0.25
1 x 17.750 x
1.13
x
1.50
Total
112 Cft. @ Rs.
###

=
=
=
=
=
=
=

7
32
7
30
7
30
112
P.%

Chapter 7 item No.7


Pacca brick work other than building upto 10' height cement sand mortor.
Ratio 1:6
Piller for main door
2 x
=
1.125
x
0.75
x
7.00
12
pennels
2 x
4.875
x
0.38
x
5.125 =
19
pennels
2 x
4.875
x
0.38
x
5.125 =
19
pennels
2 x
=
5.375
x
0.38
x
5.125
21
2 x
5.375
x
0.38
x
5.125 =
21
compound
2 x
4.875
x
0.68
x
0.750 =
5
2 x
7.625
x
0.75
x
0.375 =
4
2 x
5.375
x
0.75
x
0.375 =
3
Total
=
103
103 Cft. @ Rs.
###
P.%
Provision of water supply saniyary and electric connection.
and satisfication of the Engineer in Charge.
Provision of Electricfication of staff quarter complete in all respect. And
satisfication of the Engineer in Charge.
Total:Say:4

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft
Sft Rs.

17268 /-

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft
Sft Rs.

16199 /-

Rs.

20000

Rs.
Rs.

5000
535801 /-

Rs.

535800 /2143200

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

//-

Sub work No. 10(a)

OVER HEAD RESERVOIR


1
Design and construction Over Head reservoir of 50,000, Glns. (Fifty
thousand Glen). Capacity with 10%extra capacity for free board. The
height of the base slab of tank shall be 50ft. (Fifty) feet above
finished ground level i/c cost of all kind of specials such as Tee,Bend,tail
piece,bell mouth,sluice valve etc.The rate also includes P/F of pipe of
rising main,delivery main and over flow scour pipe ctc complete in all
respect.
(i)

Testing of bearing capacity of soil at the proposed site of over head


reservoir from government organization like Unversity of Engineering and
technology Lahore/Taxila, Building/Road Research Stations Lahore of
C&W Deptt: Irrigation Research Institute Government of Punjab Lahore.

(i)

Physical and structural design of the over head reservoir according to the
given parameters of the department by a structural engineer having
qualifications not less than M.Sc. Structural Engineering (Civil), registered
with Pakistan Engineering Council, the design shall be approved by the
Superintending Engineering PHE Circle Multan, his decision shall be final.
The design shall be based on the following concrete mixture ratio and
allow able design stressed for concrete and steel.

(a) Compression stress for concrete for all water retaining in member 600PSI
(Mix not weaker than 1:1-1/2:3).
(b) Compression stress for concrete for all other than water retaining in
member 750PSI (Mix not weaker than 1:2:4).
Tensile stress for steel for 16,000, PSI water rating members
(d) Tensile stress for steel for 18,000, PSI other than water rating members.
(e) Min: cover on steel for RCC 3/4" members facing water rating side.
(ii) Providing laying hosting, testing and disinfection of medium class MS
pipes with flanged joints of size and thickness as given under for rising
delivery, overflow mains and scour pipe including nuts, bolts, rubber,
insertion sheet with two coats of bituminous painting.
(a) 6" i/d M.S 6-mm thick upto 10 ft from the outer edge of

over head

reservoir foundation for rising main


(b) 6" i/d M.S 6-mm thick upto 10 ft from the outer edge of

over head

reservoir foundation for delivery.


(c) 6" i/d M.S 6-mm thick upto 10 ft (Min) from the outer edge of

over
head reservoir foundation for over flow including cost of disposal
chamber of approved design .

(d) 6" i/d M.S 6-mm thick for scour pipe upto its connection with the

over flow pipe with control valve open able from stair case landing
at least brace level
(iii) P/F testing and disinfecting of flanged C.I/M.S specials and fittings of fixes
corresponding to respective sizes for rising, delivery and over flow mains
and scour pipe such as bell-mouths with puddles collar, tees, bends,
duck foot bends, complete in all respect.

(iv) P/F 18'' wide M.S. ladder from ground level to top of tank i/c 3-ft high

railing of 1-1/4'' i/d G.l pipe medium quality on both sides with vertical
posts on alternate steps i/c two coats of grey enamel painting on single
coat of red lead primer competed in all respect.

(v) P/F M.S ladder comprising of sides angle iron size 2-1/2''x 2-1/2"x1/4"

with 1-1/2" x3/16" steps at 1-ft c/c necessary stays, braces etc: and
foundation dowels and bolts from base of tank to top of tank.

(vi) P/F in top slab 2 No. Medium weight C.l manhole covers with frames of
22" i/d size complete i/c 2 coats of enamel painting

(vii) P/F in top tank to lightening conductor of appropriate design i/c 1" x1/8"

size copper strip fixed along tank wall, columns and under ground from
lightening conductor to earthling point at 30 ft (min) away from, outer edge
of tank foundation i/c cost of earthling of approved specification.

(viii) P/F along periphery on top of tank slab, 2-1/2 ft high railing of 1-1/4" i.d

size G.l pipe medium quality having two horizontal rows and vertical posts
spaced not more than 3-ft centre to centre i/c cost of G.l specials with
painting in grey enamel paint complete in all respect.

(ix) P/L of cement sand grouted brick on edge paving on 1" thick sand bed

laid on properly dressed, compacted and radically out wards sloping bed
upto outer edge of the over head reservoir foundation or upto 8-ft from the
out edge of columns of the over head reservoir with finished level of the
brick paving in the centre at 6" height above the plinth level around the
over head reservoir, duly provided with brick masonry on 4" thick 1:6:12
PCC foundation Toe-wall on the periphery for protection.

(x) Clearing of site for work before construction and its cleaning development

and restoration after completion of all works of over head reservoir upto
their required finished plinth level, respectable complete to the entire
satisfaction of Engineer In-charge.
Construction of 1No. OHR 50000 Gallon

(2) Testing of Soil bearing capacity through


approved agency

50000 P/G
2

Mode of Payment
i.
20% on completion of reservoir foundation footing and raising of
columns upto 2 ft above the ground level.
ii.
25% on completion of columns and braces upto base slab level of
reservoir.
iii.
30% on completion of water tank base slab and side walls.
iv.
15% on the construction of roof slab, construction fixing of stairs,
railing, rising, delivery, over flow rains and scour pipe etc, with fittings and
specials and all other allied works from Sub item (i) to )xi) of item 1
complete.
v.
10% on the hydraulic test and disinfection after final completion
and developments site.
Special Conditions
i.
The design calculations and working design will be submitted for
approval to competent authority with in 20 days after receive the bearing
capacity report.
ii/
The contractor will be bound to accept any correction/changes in
the design while checking and will have no claim what so ever for
additional cost of design and construction due to such
corrections/amendments in the design.
iii.
After approval of design calculations and detailed drawings the
contractor will have to submit 6 fair copies of the same for final approval
for fair copies for record with the department and for use at site.
iv.
All members in contact with water such as base slab and wall of the
reservoir will be of RCC (1:1-1/2:3)nominal mix and members remote
from water will be of RCC (1:2:4) nominal mix.
v.
The contractor shall cast and keep 6"x6"x6" size cubes for testing
from each days batch of concrete used in the reservoir. The contractor
shall get the crushing strength of cubes tested at his own cost, from
approved laboratory.For any cube found below the required strength the
contractor will have to dismantle the relative portion and reconstruct the
same without any extra cost.
vi.
The work shall be carried out strictly in accordance with the
sanctioned estimate and approved drawing/ design/ specifications and to
the entire satisfaction of Engineer In charge.

Job

135 Rs.

6750000

### Rs.

70000

Total = Rs.
For

2 No

6820000
13640000

Sub work No. 10(b)

OVER HEAD RESERVOIR


1
Design and construction Over Head reservoir of 100000, Glns. (Fifty
thousand Glen). Capacity with 10%extra capacity for free board. The
height of the base slab of tank shall be 50ft. (Fifty) feet above
finished ground level i/c cost of all kind of specials such as Tee,Bend,tail
piece,bell mouth,sluice valve etc.The rate also includes P/F of pipe of
rising main,delivery main and over flow scour pipe ctc complete in all
respect.
(i)

Testing of bearing capacity of soil at the proposed site of over head


reservoir from government organization like Unversity of Engineering and
technology Lahore/Taxila, Building/Road Research Stations Lahore of
C&W Deptt: Irrigation Research Institute Government of Punjab Lahore.

(i)

Physical and structural design of the over head reservoir according to the
given parameters of the department by a structural engineer having
qualifications not less than M.Sc. Structural Engineering (Civil), registered
with Pakistan Engineering Council, the design shall be approved by the
Superintending Engineering PHE Circle Multan, his decision shall be final.
The design shall be based on the following concrete mixture ratio and
allow able design stressed for concrete and steel.

(a) Compression stress for concrete for all water retaining in member 600PSI
(Mix not weaker than 1:1-1/2:3).
(b) Compression stress for concrete for all other than water retaining in
member 750PSI (Mix not weaker than 1:2:4).
Tensile stress for steel for 16,000, PSI water rating members
(d) Tensile stress for steel for 18,000, PSI other than water rating members.
(e) Min: cover on steel for RCC 3/4" members facing water rating side.
(ii) Providing laying hosting, testing and disinfection of medium class MS
pipes with flanged joints of size and thickness as given under for rising
delivery, overflow mains and scour pipe including nuts, bolts, rubber,
insertion sheet with two coats of bituminous painting.
(a) 6" i/d M.S 6-mm thick upto 10 ft from the outer edge of

over head

reservoir foundation for rising main


(b) 6" i/d M.S 6-mm thick upto 10 ft from the outer edge of

over head

reservoir foundation for delivery.


(c) 6" i/d M.S 6-mm thick upto 10 ft (Min) from the outer edge of

over
head reservoir foundation for over flow including cost of disposal
chamber of approved design .

(d) 6" i/d M.S 6-mm thick for scour pipe upto its connection with the

over flow pipe with control valve open able from stair case landing
at least brace level
(iii) P/F testing and disinfecting of flanged C.I/M.S specials and fittings of fixes
corresponding to respective sizes for rising, delivery and over flow mains
and scour pipe such as bell-mouths with puddles collar, tees, bends,
duck foot bends, complete in all respect.

(iv) P/F 18'' wide M.S. ladder from ground level to top of tank i/c 3-ft high

railing of 1-1/4'' i/d G.l pipe medium quality on both sides with vertical
posts on alternate steps i/c two coats of grey enamel painting on single
coat of red lead primer competed in all respect.

(v) P/F M.S ladder comprising of sides angle iron size 2-1/2''x 2-1/2"x1/4"

with 1-1/2" x3/16" steps at 1-ft c/c necessary stays, braces etc: and
foundation dowels and bolts from base of tank to top of tank.

(vi) P/F in top slab 2 No. Medium weight C.l manhole covers with frames of
22" i/d size complete i/c 2 coats of enamel painting

(vii) P/F in top tank to lightening conductor of appropriate design i/c 1" x1/8"

size copper strip fixed along tank wall, columns and under ground from
lightening conductor to earthling point at 30 ft (min) away from, outer edge
of tank foundation i/c cost of earthling of approved specification.

(viii) P/F along periphery on top of tank slab, 2-1/2 ft high railing of 1-1/4" i.d

size G.l pipe medium quality having two horizontal rows and vertical posts
spaced not more than 3-ft centre to centre i/c cost of G.l specials with
painting in grey enamel paint complete in all respect.

(ix) P/L of cement sand grouted brick on edge paving on 1" thick sand bed

laid on properly dressed, compacted and radically out wards sloping bed
upto outer edge of the over head reservoir foundation or upto 8-ft from the
out edge of columns of the over head reservoir with finished level of the
brick paving in the centre at 6" height above the plinth level around the
over head reservoir, duly provided with brick masonry on 4" thick 1:6:12
PCC foundation Toe-wall on the periphery for protection.

(x) Clearing of site for work before construction and its cleaning development

and restoration after completion of all works of over head reservoir upto
their required finished plinth level, respectable complete to the entire
satisfaction of Engineer In-charge.
Construction of 1No. OHR100000 Gallon

(2) Testing of Soil bearing capacity through


approved agency

100000 P/G
1

Mode of Payment
i.
20% on completion of reservoir foundation footing and raising of
columns upto 2 ft above the ground level.
ii.
25% on completion of columns and braces upto base slab level of
reservoir.
iii.
30% on completion of water tank base slab and side walls.
iv.
15% on the construction of roof slab, construction fixing of stairs,
railing, rising, delivery, over flow rains and scour pipe etc, with fittings and
specials and all other allied works from Sub item (i) to )xi) of item 1
complete.
v.
10% on the hydraulic test and disinfection after final completion
and developments site.
Special Conditions
i.
The design calculations and working design will be submitted for
approval to competent authority with in 20 days after receive the bearing
capacity report.
ii/
The contractor will be bound to accept any correction/changes in
the design while checking and will have no claim what so ever for
additional cost of design and construction due to such
corrections/amendments in the design.
iii.
After approval of design calculations and detailed drawings the
contractor will have to submit 6 fair copies of the same for final approval
for fair copies for record with the department and for use at site.
iv.
All members in contact with water such as base slab and wall of the
reservoir will be of RCC (1:1-1/2:3)nominal mix and members remote
from water will be of RCC (1:2:4) nominal mix.
v.
The contractor shall cast and keep 6"x6"x6" size cubes for testing
from each days batch of concrete used in the reservoir. The contractor
shall get the crushing strength of cubes tested at his own cost, from
approved laboratory.For any cube found below the required strength the
contractor will have to dismantle the relative portion and reconstruct the
same without any extra cost.

Job

113 Rs.
### Rs.
Total = Rs.

For

1 No

11300000
35000
11335000
11335000

vi.
The work shall be carried out strictly in accordance with the
sanctioned estimate and approved drawing/ design/ specifications and to
the entire satisfaction of Engineer In charge.

Sub work No.11

EXTERNAL ELECTRIFICATION

For Tube well


1 Transmission line.

500 Rft

@ Rs.

750000 P.Km Rs.

114329

2 Transformor 100 KVA

1 Nos.

@ Rs.

Each

Rs.

750000

3 Electric Meter

1 Nos.

@ Rs.

Each

Rs.

35000

4 Security

1 job

@ Rs.

P.Job

Rs.

45000

Total:-

Rs.

944329

Say

Rs.

950000

Tubewell

Rs.

9500000

For

10

Nos

For IPS
1 Transmission line.

2800 Rft

@ Rs.

750000 P.Km Rs.

640244

2 Transformor 500 KVA

1 Nos.

@ Rs.

Each

Rs.

2100000

3 Electric Meter

1 Nos.

@ Rs.

Each

Rs.

35000

4 Security

1 job

@ Rs.

P.Job

Rs.

110000

Total:-

Rs.

2885244

Say

Rs.

2885200

For GST- 3
1 Transmission line.

600 Rft

@ Rs.

750000 P.Km Rs.

137195

2 Transformor 200 KVA

1 Nos.

@ Rs.

Each

Rs.

1050000

3 Electric Meter

1 Nos.

@ Rs.

Each

Rs.

30000

4 Security

1 job

@ Rs.

P.Job

Rs.

70000

Total:-

Rs.

1287195

Say

Rs.

1287200

For GST- 11
1 Transmission line.

3350 Rft

@ Rs.

750000 P.Km Rs.

766006

2 Transformor 100 KVA

1 Nos.

@ Rs.

Each

Rs.

750000

3 Electric Meter

1 Nos.

@ Rs.

Each

Rs.

30000

4 Security

1 job

@ Rs.

P.Job

Rs.

35000

Total:-

Rs.

1581006

Say

Rs.

1581000

Rs.

2200000

Total

Rs.

2200000

G.Total

Rs.

17453400

Replacement of 1 No 50 KVA transformer on existing tube wells


2 Transformor 50 KVA

4 Nos.

@ Rs.

550000

NOTE. The payment will be made to WAPDA only.

17453400

SUB WORK NO. 12


1

Hyphochlorinator

Providing and fixing and testing of Hypo Chlorinator digital automatic (Chemical metering
pump), Capacity 0-30 gallons/day at 100 Psi max injection pressure fitted with 1/60 HP air
cooled heavy duty electric motor 220 V , 50 Hz , single phase AC complete with all
accessories like bleed valve and strainer assembly suction tubing, discharge tubing , foot
valve and strainer assembly with weight, back check valve assembly solution tanks,
injection fitting , wall brackets etc. complete in all respect.

Sets

Rs.

45000

Each
Total

For GST
450000

10 Nos
C/O to general Abstract of cost.

Rs.

45000

Rs.

45000
450000

Sub work No. 13

Generators

Supplying, installtion and testing of generators 300 KVA unit ( Manufactured by


approved manufactures of HUD & PHED) with automatic change over including
cost of 4 core PVC.

Complete .1 Set
### @ Rs.
###
For
1

5350000 Each
2

Rs.
Rs.

Nos

5350000
5350000
10700000

Supplying, installtion and testing of generators 120 KVA unit ( Manufactured by


approved manufactures of HUD & PHED) with automatic change over including
cost of 4 core PVC.From Generator to Pump house 600 Meter

Complete .1 Set
### @ Rs.
###
For

2850000 Each
4

Rs.
Rs.

Nos

G.Total

2850000
2850000
11400000

Rs.

22100000

ANNUAL O & M COST

Annual Operating Cost

A Establishment
1 Operator/Chowkidar

33 No. for 12 Month @ Rs.

9000
P.Month

Rs.

3564000

3 /

3 % of total cost of civil works


100 x
10828300

Rs.

324849

3 /

3 % of total cost of pipe lines.


100 x
307856045

Rs. 9235681.35

3 /

3 % of total cost of pipe lines.


100 x
29350000

B Repair
i

Repair of Civil Work

ii Repair of Pipe Line

iii Repair of Machinery


Rs.
Total

880500
14005030

Contingency
280101
G. Total

14285131

Rs.

46158601

Rs.

64007732

Say

64007700

C Electric charges.
Electric motorvertical turbine

1 Set

T/Well

10x35x8x0.746x365

1524824 unit

IPS

5x120x8x0.746x365
3x30x8x0.746x365
2x100x8x0.746x365
1x40x8x0.746x365
3550662 unit

1306992
196049
435664
87133
13

GST

Total A+B+C

unit
unit
unit
unit
P.Unit

1
i

ii

iii

iv

SUB WORK NO 7.
IPS
SUB HEAD NO 1.
GROUNG STORAGE TANK
Chapter 22 item No.1 (a)
Excavation of well in dry in ordinary soil upto 20 below ground
level, and disposal of soil with in one chain.
0 Ft. to 5 Ft. depth
1
x 3.143 x 110 x
110
x
0.25
x
5.00
=
47536
47536 Cft @ Rs
2706.90
%0 Cft
5 Ft. to 10 Ft. depth
1
x 3.143 x 110 x
110
x
0.25
x
5.00
=
47536
47536 Cft @ Rs
2827.10
%0 Cft
10 Ft. to 15 Ft. depth
1
x 3.143 x 110 x
110
x
0.25
x
5.00
=
47536
47536 Cft @ Rs
3180.50
%0 Cft
15 Ft. to 20 Ft. depth
1
x 3.143 x 110 x
110
x
0.25
x
2.00
=
19014
19014 Cft @ Rs
3650.50
%0 Cft
Chapter 6 item No.3 (b)
Cement concrete brick or stone ballast 1- 1/2" to 2" gauge in foundation and
plinth.(1:4:8)
Under Bed
1
x 3.143 x 110 x
110
x
0.25
x
0.75
=
7130
Under Apren
1 x 3.143 x
106
x
3
x
3.000
=
2998
Total
=
10129
10129 Cft @ Rs
10321.40
% Cft
Chapter 6 item No. 5 (F) , Item No.17
Cement concrete plain 1:2:4 i/c placing, compacting , finishing and curing
complete (i/c screening and washing of stone aggregate). i/c extra labour for
skipping concrete in wells.

Under Bed
i
1
x 3.143 x
ii Ratio. 1:1-1/2:3
1
x 3.143 x

103

103

103
x
0.25
8336 Cft @ Rs
19289.15
103
x
0.25
8337 Cft @ Rs
22033.5

1.00
21502.35
+
2213.20
x
1.00
24246.7
+
2213.2

96 FEET DIA
900000 GLNS

Cft.
Rs.

128,675 /-

Rs.

134,389 /-

Rs.

151,188 /-

Rs.

69,411 /-

Rs.

1,045,455 /-

Rs.

1,792,436 /-

Rs.

2,021,447 /-

Rs.

1,302,412 /-

Rs.

534,525 /-

Cft.

Cft.

Cft.

Cft.
Cft.
Cft.

8336 Cft.
% Cft

8337 Cft.
% Cft

Chapter 7 item No. 7 (i), 10, 8


4 Pacca brick work 1:3 cement sand mortar other then building up to 10 Ft height
i 1st step int
i 1st step out

ii 10 to 20'height
1st step int
2nd step out

1
1

1
1

x 3.143
x 3.143

x 3.143
x 3.143

Chapter 6 item No. 34 (b), (iii)

x
x

x
x

96.75
102.25

1.125
1.125
Total
7036 Cft @ Rs
###

96.75
102.25

x
x

x
x

x
x

10.00
10.00

18510.50
+
1227.00

0.750 x
6.00
0.750 x
6.00
Total
2814 Cft @ Rs
18992.30
17283.50 + 481.80 +
1227.00

=
=
=
% Cft

=
=
=
% Cft

3421 Cft.
3615 Cft.
7036 Cft.

1368 Cft.
1446 Cft.
2814 Cft.

5 Providing and laying thick vertical damp proof course with 1:2 cement sand
plaster and 2 coats of bitumen .
ist step
1
x 3.143
x
102
x
16.00
=
2nd step
1
x 3.143
x
102
x
4.00
=
Total
=
6411 Cft @ Rs
3080.80
% Sft
Chapter 6 item No. 6
6 Providing and laying reinforced cement concrete (including prestressed
concrete) using course sand and screened graded and washed agreegate in
required shape and designed icluding forms, moulds, shuttering, lifting,
compacting, curing, rendering and finis

5129 Sft
1282 Sft
6411 Sft
Rs.

197,510 /-

Rs.

2,908,500 /-

Rs.

2,983,158 /-

Rs.

6,116,312 /-

Rs.

24,243 /-

Rs.

66,927 /-

(a) (I).Reinforced cement concrete in roof slab, beams, columns, lintels, girders
and other structural members laid in situ or pre cast laid in position, or pre
stressed members cast in situ, complete in all respect. Type C (nominal mix
1:2:4)
Base
1 x 3.143 x
Cro
2 x
0 x
Tank
1 x 3.143 x
Beam Motar
Pillar
Center Pillar

105
102
48
1
16
1

x
x
x
x
x
x

D/d
2 x 3.143 x 2.00
Hole for fixing of Machin 3.00

x
x

105
1.5
1.5
15.00
1.25
2.00

x
x
x
x
x
x

0.25
0
0
2.00
1.25
2.00
Total
2.00
x
0.25
1.50
x
1.50
Net
10000 Cft @ Rs

x
x
x
x
x
x
x
x

1
2
2
0.75

=
=
=
=
20
=
20
=
=
2
=
1.25
=
=
290.85
P. Cft

8663
612
144
23
500
80
10021
13
8
10000

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

Chapter 6 item No. 6 (a) (3) (c), (2)


ii ( a ) ( ii )Reinforcement cement concrete in slab of rafts / strip foundation ; base
slab of column and retaining walls ; etc, and other structural member , complete
in all respect. (Type C nominal mix 1: 1-1/2 : 3 )
C.wall

x 3.143

99.500 x 1.500
9381 Cft @ Rs

20.00
318.00

=
P. Cft

9381 Cft.

30664 Kgs
22703 Kgs
53367 Kgs

Chapter 6 item No. 9


7 Fabrication of mild steel reinforcement for cement concrete, i/c cutting,
bending, laying in position, making joints and fastenings, i/c cost of binding
wire and labour charges for bending of steel reinforcement ( also includes
removal
of rust from bars )10021.0 @
Slab
3.06 Kgs/Cft
C.wall

9381.4 @

2.42 Kgs/Cft
Total
53367 Kgs @ Rs

=
11460.85

=
P%.Kgs

Chapter 11 item No. 7 (b)


8 Cement plaster thick 1: 2, upto 20 height.
i 0 to 20'Height
in side

0.25

3.143

96
Total
1509 Cft @ Rs

20.00

=
=
% Sft

1607.00
Chapter 10 item No. 9
9 Brick on edge flooring, laid in 1: 6 cement mortar, over a bed of 3/4" thick
cement mortar 1: 6,
1
x 3.143
x 106.00 x
3.00
=
999 Sft @ Rs
6699.40
P.% Sft

1509 Sft
1509 Sft

999 Sft

Chapter 21 item No. 17


10 Providing and fixing C.I.Manhole Cover 24"Dia as per standard drawing,
1.00 x
2.00
=
2 No @ Rs
4216.00
Each
Chapter 21 item No. 13
11 Providing and fixing 1 x1 x3/16 angle iron step in manhole chamber i/c
carriage and setting the same in work, to correct lines and level.
1
x
2
x
18
=
36 No @ Rs
236.30
Each
12 Providing and fixing over flow pipe.with C.I. flanged joints ( Medium quality)

2 No.
8,432 /-

Rs.

8,507 /-

Rs.

400,000 /-

Rs.

14,000 /-

Rs.

7,439 /-

Rs.

237,436 /-

Rs.

6,399 /-

36 No.

32" dia G.I.Pipe


20 Rft @ Rs
20000.00
P.Rft.
13 Providing and fixing ventshaft 4" dia G.I. pipe 4' long i/c cost of cowel dome
and fixing in top slab of GST, complete in all respect.
2 No @ Rs
7000.00
Each

PUMP HOUSE

Rs.

52.00 x 52.00

Chapter 6 item No. 33 (b) (ii)


14 Providing and laying 2 damp proof course of cement concrete 1:2:4 (using
cement, sand and shingle) with 2 coats of bitumen.
1.00
x 133.000 x
1.125
150 Sft @ Rs
4959.25
Chapter 7 item No. 7 (i) , 8
15 Pacca brick work for ground floor upto 10 height in 1:4 cement sand mortor
above P.L.
Wall
2
x 52.000 x 0.750 x
10.00
Wall
1
x 82.000 x 0.750 x
10.00
Out side stair
1 x
1
x 4.000
x 0.625 x
0.625
2nd step
1 x
1
x 4.000
x 0.625 x
0.625
3rd step
1 x
1
x 4.000
x 4.000 x
0.625
4th step
1 x
1
x 4.000
x 5.331 x
0.625
5th step
1 x
1
x 4.000
x 4.498 x
0.625
6th step
1 x
1
x 4.000
x 3.665 x
0.625
7th step
1 x
1
x 4.000
x 0.333 x
0.625
Total
D/Dection
Door
1
x 4.000
x 7.000
0.750
2
x 3.000
x 4.000
0.750
2
x 1.500
x 2.000
0.750
Lintel over door
1
x 5.000
x 0.500
0.750
2
x 4.000
x 0.500
0.750
2
x 2.500
x 0.500
0.750
Total
Net
= 1442.69 50
1392 Cft @ Rs
17057.15
ii 10 to 20'height
### +
481.80
1st step
1.000 x 80.000 x 0.750 x
1
Para pit Wall
2.000 x( 52.000 + 52.00
)x 0.750 x
1
Total
35 Cft @ Rs
18284.15
16575.35 + 1227.00 +
481.80
Chapter 6 item No. 6 (a), (3),

=
P.% Sft

=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
% Cft
=
=
=
% Cft

150 Sft

780
615
2
2
10
13
11
9
1
1443

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

21
18
5
2
3
2
50
1392

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

60 Cft.
156 Cft.
216 Cft.

16 Providing and laying reinforced cement concrete (including prestressed


concrete) using course sand and screened graded and washed agreegate in
required shape and designed icluding forms, moulds, shuttering, lifting,
compacting, curing, rendering and finis
i (a) (I).Reinforced cement concrete in roof slab , beams , columns , lintels ,
girders and other structural members laid in situ or pre cast laid in position , or
pre stressed members cast in situ , complete in all respect. Type C (nominal mix
1: 2 : 4 .
Roof
Roof beem
LainDoor
Window
C.window
Sun Door
Window
C.window

1
1
1
2
2
1
2
2

x
x
x
x
x
x
x
x

D/d of Hole

53.500
53.50
5.00
4.00
2.50
5.00
4.00
2.50

x
x
x
x
x
x
x
x

53.500
0.75
0.5
0.5
0.5
0.25
0.25
0.25
Total
1.50
x
1.50
Net
1484 Cft @ Rs

x
x
x
x
x
x
x
x

0.5
1.00
0.75
0.750
0.750
1.50
1.50
1.50

0.5

290.85
Chapter 6 item No. 9 (b)
17 Fabrication of mild steel reinforcement for cement concrete, i/c cutting,
bending, laying in position, making joints and fastenings, i/c cost of binding
wire and labour charges for bending of steel reinforcement ( also includes
removal of rust from bars )
Slab

1483.6 @

3.06 Kgs/Cft
Total
4540 Kgs @ Rs

11460.85
Chapter 12 item No. 51
18 Providing, fixing, paneled door of M.S. sheet with forged door leaves of M.S.
sheet 22 SWG fitted in hallow frame chowket 3x 4 made of M.S. sheet
18 SWG filled with plain cement concrete 1:3:6 etc; complete with all fittings
and harmer painting i/c
1

x
4.0
28 Sft @ Rs

7.0
362.15

=
=
=
=
=
=
=
=
=
=
=
P. Cft

1431
40
2
3
2
2
3
2
1485
1
1484

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

=
=
P%.Kgs

4540 Kgs
4540 Kgs

=
P. Sft

28 Sft

=
=
=
P. Sft

24 Sft
6 Sft
30 Sft

=
=
=
P. Sft

24 Sft
6 Sft
30 Sft

Rs.

431,621 /-

Rs.

520,323 /-

Rs.

10,140 /-

Rs.

11,447 /-

Rs.

5,408 /-

Chapter 25 item No. 41 (b-iii)


19 P/Fixing steel window with openable glazed panels making beams section for
frame 1 x1x5/8 section for leaves x1x3/8 T-section 1x1
x1/8embedded over a thin layer of putty duly screed with leaves brass fittings
holds fast, duly painted complete
Window
C.Window

1
1

x
x

2.00
2.00

x
x

3.00
1.50
Total
30 Cft @ Rs

x
x

4.00
2.00

381.55
Chapter 12 item No. 54
20 Providing and fixing M. S. flat 1/2x 1/8 grill, i/c 3 /4x 1/8 M.S. flat frame,
in windows of approved design, i/c painting 3 coats, complete in all respect.
Window
C.Window

Chapter 9 item No. 5

1
1

x
x

2.00
2.00

x
x

3.00
1.50
Total
30 Cft @ Rs

x
x

4.00
2.00
180.25

21 Single layer of tiles 9x1 x1 laid over 4 earth and 1 mud plaster with
out bhoosa grouted with cement sand 1:3 on top of RCC roof cement RCC
provided work 34 LBS bitumen coating sand grouted.
1.000 x
51.250 x
51.250
2627 Sft @ Rs
5799.05
Chapter 9 item No. 14
22 Kassi Parnalas in cement sand mortor 1:2 12 out side width finished smooth
with and floating coat of neat cement.
1.00
x
15.50
16 Rft @ Rs
70.55
Chapter 9 item No. 15
23 Khurras on roof 22x6
1.00
x
1.00
1 No @ Rs
376.90
Chapter 9 item No. 16
24 Bottom khurras or brick masonry in cement mortor 1:6,4 x2x4 over 3
cement concrete 1:4:8
1.00
x
1.00
1 No @ Rs
697.30
Chapter 10 item No. 15
25 Providing and laying topping of cement concrete '1 : 2 : 4, including surface
finishing and dividing in panels ' 3 inch thick
1.000 x
52.000 x
52.000
2704 Sft @ Rs
5193.10
Chapter 11 item No. 8
26 Cement plaster thick 1: 3, upto 20 height.
i 0 to 20'Height
in side
2.000 x( 52.000
+ 52.00 )x
10.00
2080 Cft @ Rs
1387.85
Chapter 11 item No. 18 (a)
27 Cement pointing struck joints on wall upto 20' height ratio 1:2 i/c extra cost of
labour and material for red oxide pigment in cement pointing to match with the
colour of bricks.
Out side. P.House
Out side. P.House
D/d
Door
Window
C.Window

2
1

x(
x

53.500
82.000

1
1
1

x
x
x

1
2.00
2.00

2627 Sft

=
P.Rft

16 Rft

=
Each

1 No

=
Each

1 No

=
P.% Sft

2704 Sft

=
% Sft

2080 Sft

+ 53.500 )x
+
x

10.00
10.00

=
=

2140 Sft
820 Sft

x
x
x

7.0
4.00
2.00

=
=
=
=
=
% Sft

28
24
6
58
2082

=
=
=
=
% Sft

2080
820
2704
5604

4.0
3.00
1.50
Total

x
x
x

Net
2082 Cft @ Rs
Chapter 11 item No. 25 (a)
28 White washing new surface three costs.
in side
2.000 x( 52.00
in side
1.000 x 82.00
Roof
1.00

=
P.% Sft

+
+
x

52.00

52.00
Total
5604 Cft @ Rs
173.2 + 213.00

1387.15

)x
x
x

10.00
10.00
52.00
386.20

Chapter 13 item No. 5


29 Painting of new surface, preparing surface and painting of doors and windows

Rs.

152,341 /-

Rs.

1,129 /-

Rs.

377 /-

Rs.

697 /-

Rs.

140,421 /-

Rs.

28,867 /-

Rs.

28,880 /-

Rs.

21,643 /-

Sft
Sft
Sft
Sft
Sft

Sft
Sft
Sft
Sft

Painting of new surface, preparing surface and painting of doors and windows
any type, three coat.
Door
1
x
2.00
x
4.00
x
7.00
Window
2
x
2.00
x
3.00
x
4.00
C.Window
2
x
2.00
x
1.50
x
2.00
Total
60 Cft @ Rs
1239.55
567.95 +
335.8
30 Providing and fixing R.S. joist quality china made, i/c 3 coats of paint and cost
of masonary work, complete in all respect.(8"x 6")
1.00
x
26.00
26 Rft @ Rs
882.50
31 Providing and fixing ceilling fan i/c of connections etc, complete in all respect
(Pak, Asia, Royal)
1 Job @ Rs
3000.00

=
=
=
=
% Sft
+

56
48
12
60

Sft
Sft
Sft
Sft

=
P.Rft

ii

iii

iv

P.Job.

SUB WORK NO 7.
ZONE-D
SUB HEAD NO 2.
SLUICE VALVE CHAMBER
Chapter 22 item No. 1 (a)
Excavation of well in dry in ordinary soil upto 20 below ground level, and
disposal of soil with in one chain.
0 to 5' depth
1
x 3.143 x 16.000 x 16.000 x
0.25
x
5.00
=
1006
1006 Cft @ Rs
2706.90
%0 Cft
5 to 10'depth
1
x 3.143 x 16.000 x 16.000 x
0.25
x
5.00
=
1006
1006 Cft @ Rs
2827.10
%0 Cft
10 to 15'depth
1
x 3.143 x 16.000 x 16.000 x
0.25
x
5.00
=
1006
1006 Cft @ Rs
3180.50
%0 Cft
15 to 20'depth
1
x 3.143 x 16.000 x 16.000 x
0.25
x
1.00
=
201
201 Cft @ Rs
3650.50
%0 Cft
Chapter 6 item No. 3 (b)
Cement concrete brick or stone ballast 1- 1/2" to 2" gauge in foundation and
plinth.(1:6:12)
Under Bed
1
x 3.143 x 6.000 x 6.000
x
0.25
x
0.50
=
14
Under Apren
1 x 3.143 x 11.250 x
3
x
0.375
=
40
Total
=
54
54 Cft @ Rs
10321.40
% Cft
Chapter 6 item No. 5 (f)
Cement concrete plain 1 : 2 : 4, i/c placing, compacting , finishing and curing
complete ( i/c screening and washing of stone aggregate). i/c extra labour for
skipping concrete in wells.
Under Bed
1
x 3.143 x 6.000

6.000

x
0.25
14 Cft @ Rs

Chapter 7 item No. 7 (i), 10, 8


4 Pacca brick work 1:3 cement sand mortar other then building

0.50
19289.15

744 /-

Rs.

22,945 /-

Rs.

3,000 /-

Rs.

20,572,730 /-

26 Rft

TOTAL.

Rs.
335.80

6 FEET DIA

Cft.
Rs.

2,723 /-

Rs.

2,844 /-

Rs.

3,200 /-

Rs.

734 /-

Rs.

5,574 /-

Rs.

2,700 /-

Cft.

Cft.

Cft.

Cft.
Cft.
Cft.

14 Cft.
% Cft

i 1st step
2nd step
3rd step
D/Dection

ii 10 to 20'height
1st step
2nd step
3rd step

6
i

1
1
1

x 3.143
x 3.143
x 3.143

x
x
x

x 3.143

1
1
1

x 3.143
x 3.143
x 3.143

10
11

1.500
1.13
1.125
Total
7.500
x 0.375
Net
769 Cft @ Rs
###

7.500
7.125
7.13

x
x
x

x
x
x

10.00
10.00
10.00

10.00

=
=
=
=
=
=

18510.50
1227.00

1.500 x
10
1.125 x
10.00
1.125 x
10.00
Total
D/Dection
1 x 3.143 x
7.500 x
0.375 x
10
Net
769 Cft @ Rs
18992.30
17283.50 + 1227.00 + 481.8
Chapter 6 item No. 34 (b), (iii)
Providing and laying thick vertical damp proof course with 1:2 cement sand
plaster and 2 coats of bitumen .
ist step
1
x 3.143
x 9.000 x
10.00
2nd step
1
x 3.143
x 8.250 x
6.00
Total
438 Cft @ Rs
3080.80
Chapter 11 item No. 7 (b)
Cement plaster thick 1: 2, upto 20 height.
0 to 20'Height
in side
1
x 3.143
x
6
x
18.00
Top
1
x 3.143
x 7.125 x
1.125
Total
365 Cft @ Rs
1607.00
Chapter 11 item No. 18 (a)
Cement pointing struck joints on wall upto 20' height ratio 1:2 i/c extra cost of
labour and material for red oxide pigment in cement pointing to match with the
colour of bricks.
1

x
x
x

7.500
7.13
7.125

x
x
x

3.143
x
8.25
x
10.00
259 Cft @ Rs
1600.15
1387.15 +
213.00

Chapter 21 item No. 13


Providing and fixing 1 x1 x3/16 angle iron step in manhole chamber i/c
carriage and setting the same in work, to correct lines and level.
1
x
2
x
18
36 No @ Rs
236.30
Chapter 10 item No. 9
Brick on edge flooring, laid in 1: 6 cement mortar, over a bed of 3/4" thick
cement mortar 1: 6,
1
x 3.143
x 11.250 x
3.00
106 Sft @ Rs
6699.40
Providing and Laying A.C. Pipe of BSS.B. Class working presure
32" Dia
40 Rft @ Rs
13298.85
Providing and Fixing Sluci Valve for A.C. Pipe of BSS.B. Class working
presure
1
x
2

354
252
252
857
88
769

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

% Cft

Rs.

142,346 /-

Rs.

146,051 /-

Rs.

13,494 /-

Rs.

5,866 /-

Rs.

4,144 /-

Rs.

8,507 /-

P.% Sft

Rs.

7,101 /-

P.Rft.

Rs.

531,954 /-

=
=
=
=
=
=

354
252
252
857
88
769

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

% Cft

=
=
=

283 Sft
156 Sft
438 Sft
% Sft

=
=
=

339 Sft
25 Sft
365 Sft
% Sft

259 Sft
% Sft

36 No.
Each

106 Sft

32"

1
i

ii

iii

iv

Dia

1 No @ Rs

165000.00

Each
TOTAL.
SAY,

Rs.
Rs.
Rs.

165,000 /1,042,238 /1,042,200 /-

SUB WORK NO 7.
ZONE-D
SUB HEAD NO 3
WASH OUT CHAMBER
6 FEET DIA
Chapter 22 item No. 1 (a)
Excavation of well in dry in ordinary soil upto 20 below ground level, and
disposal of soil with in one chain.
0 to 5' depth
1
x 3.143 x 16.000 x 16.000 x
0.25
x
5.00
=
1006 Cft.
1006 Cft @ Rs
2706.90
%0 Cft
Rs.
2,723
5 to 10'depth
1
x 3.143 x 16.000 x 16.000 x
0.25
x
5.00
=
1006 Cft.
1006 Cft @ Rs
2827.10
%0 Cft
Rs.
2,844
10 to 15'depth
1
x 3.143 x 16.000 x 16.000 x
0.25
x
5.00
=
1006 Cft.
1006 Cft @ Rs
3180.50
%0 Cft
Rs.
3,200
15 to 20'depth
1
x 3.143 x 16.000 x 16.000 x
0.25
x
4.00
=
805 Cft.
805 Cft @ Rs
3650.50
%0 Cft
Rs.
2,939
Chapter 6 item No. 3 (b)
Cement concrete brick or stone ballast 1- 1/2" to 2" gauge in foundation and
plinth.(1:4:8)
Under Bed
1
x 3.143 x 6.000 x 6.000
x
0.25
x
0.50
=
14 Cft.
Under Apren
1 x 3.143 x 11.250 x
3
x
0.375
=
40 Cft.
Total
=
54 Cft.
54 Cft @ Rs
10321.40
% Cft
Rs.
5,574
Chapter 6 item No. 5 (f)
Cement concrete plain 1 : 2 : 4, i/c placing, compacting , finishing and curing
complete ( i/c screening and washing of stone aggregate). i/c extra labour for
skipping concrete in wells.
Under Bed
1
x 3.143 x 6.000

6.000

x
0.25
14 Cft @ Rs

Chapter 7 item No. 7 (i), 10 , 8


4 Pacca brick work 1:3 cement sand mortar other then building
i 1st step
1 x 3.143 x 7.500
x 1.500
Total
D/Dection
1 x 3.143 x 7.500
x 0.375
Net
265 Cft @ Rs
###
ii 10 to 20'height
1st step
1 x 3.143 x 7.500
x 1.500
2nd step
1 x 3.143 x 7.125
x
1.13
3rd step
1 x 3.143 x
7.13
x 1.125

0.50
19289.15

10.00

10.00

=
=
=
=

+
x
x
x

18992.30
1227.00
3.00
5.50
1.50

=
=
=

/-

/-

/-

/-

14 Cft.
% Cft

/-

354
354
88
265

Rs.

2,700 /-

Rs.

50,330 /-

Cft.
Cft.
Cft.
Cft.

% Cft
481.80
106 Cft.
139 Cft.
38 Cft.

D/Dection

iii 20 to 30'height
3rd step

3.143 x

x 3.143

Total
0.375 x
3.00
Net
256 Cft @ Rs
18992.30
17283.5 + 1227.00 +
481.80
7.500

7.13

6
i

ii

3.143

% Cft

Rs.

48,620 /-

Rs.

7,400 /-

Rs.

15,712 /-

Rs.

6,460 /-

Rs.

333 /-

Rs.

1,248 /-

Rs.

9,925 /-

P.% Sft

Rs.

7,101 /-

P.Rft.

Rs.

326,447 /-

Rs.

280,000 /-

1.125 x
1.50
=
38 Cft.
Total
=
38 Cft.
Cft @ Rs
19474.10
% Cft
+ 1227.00 +
481.80 +
481.80

Chapter 6 item No. 34 (b), (iii)


Providing and laying thick vertical damp proof course with 1:2 cement sand
plaster and 2 coats of bitumen .
ist step
1
x 3.143
x 9.000 x
13.00
2nd step
1
x 3.143
x 8.250 x
5.50
Total
510 Cft @ Rs
3080.80
Chapter 11 item No. 7 (b)
Cement plaster thick 1: 2, upto 20 height.
0 to 20'Height
in side
1
x 3.143
x
6
x
20.00
Top
1
x 3.143
x 7.125 x
1.125
Total
402 Cft @ Rs
1607.00
20 to 30'Height
in side
1
x 3.143
x
6
x
1.00
19 Cft @ Rs
1754.45
1607.00 +
147.45
Chapter 11 item No. 18 (a)
Cement pointing struck joints on wall upto 20' height ratio 1:2 i/c extra cost of
labour and material for red oxide pigment in cement pointing to match with the
colour of bricks.
3rd step

282 Cft.
27 Cft.
256 Cft.

38
17283.5
5

=
=
=

x
8.25
x
3.00
78 Cft @ Rs
1600.15
1387.15 +
213.00

Chapter 21 item No. 13


8 Providing and fixing 1 x1 x3/16 angle iron step in manhole chamber i/c
carriage and setting the same in work, to correct lines and level.
1
x
2
x
21
42 No @ Rs
236.30
Chapter 10 item No. 9
9 Brick on edge flooring, laid in 1: 6 cement mortar, over a bed of 3/4" thick
cement mortar 1: 6,
1
x 3.143
x 11.250 x
3.00
106 Sft @ Rs
6699.40
10 Providing and Laying H.D. Pipe of PN 8
710 mm Dia
30 Rft @ Rs
10881.58
11 Providing and Fixing Sluice Valve for A.C. Pipe of BSS.B. Class working
presure
1
x
2
24''
Dia
2 No @ Rs
140000.00

=
=
=

368 Sft
143 Sft
510 Sft
% Sft

=
=
=

377 Sft
25 Sft
402 Sft
% Sft

19 Sft
% Sft

78 Sft
% Sft

42 No.
Each

106 Sft

2 No.
Each

TOTAL.
SAY,

(Carried Over to Summery of Cost)

24.88

Rs.
Rs.

773,556 /773,600 /22,388,530

SUB WORK NO 7.
SUB HEAD NO 1.
GROUNG STORAGE TANK
Chapter 22 item No.1 (a)
1 Excavation of well in dry in ordinary soil upto 20 below ground level,
and disposal of soil with in one chain.
i 0 Ft. to 5 Ft. depth
1 x 3.1429 x 45.00 x 45.00 x
0.25 x 5.00
=
7955
7955 Cft @ Rs
2706.90 %0 Cft
ii 5 Ft. to 10 Ft. depth
1 x 3.143 x 45.00 x 45.00 x
0.25 x 5.00
=
7955
7955 Cft @ Rs
2827.10 %0 Cft
iii 10 Ft. to 15 Ft. depth
1 x 3.1429 x 45.00 x 45.00 x
0.25 x 5.00
=
7955
7955 Cft @ Rs
3180.50 %0 Cft
iv 15 Ft. to 20 Ft. depth
1 x 3.1429 x 45.00 x 45.00 x
0.25 x 2.00
=
3182
3182 Cft @ Rs
3650.50 %0 Cft
Chapter 6 item No.3 (b)
2 Cement concrete brick or stone ballast 1- 1/2" to 2" gauge in foundation and
plinth.(1:4:8)
Under Bed
1 x 3.1429 x 43.340 x 43.340 x
0.25 x 0.75
=
1107
Under Apren
1
x 3.143 x 43.340 x
3
x 3.000 =
1226
Total
=
2333
2333 Cft @ Rs
10321.40
% Cft
Chapter 6 item No. 5 (F), (C) , Item No.17
3 Cement concrete plain 1:2:4 i/c placing, compacting , finishing and curing
complete (i/c screening and washing of stone aggregate). i/c extra labour for
skipping concrete in wells.

36 FEET DIA
100000 GLNS

Cft.
Rs.

21,533 /-

Rs.

22,490 /-

Rs.

25,301 /-

Rs.

11,616 /-

Rs.

240,798 /-

509 Cft.
% Cft
Rs.

109,447 /-

510 Cft.
% Cft
Rs.

123,659 /-

Cft.

Cft.

Cft.

Cft.
Cft.
Cft.

Under Bed
i

x 3.1429 x 36.000 x

ii Ratio. 1:1-1/2:3
1

x 3.1429 x 36.000 x

36.000 x
0.25
509 Cft @ Rs
19289.15
36.000 x
0.25
510 Cft @ Rs
22033.5

x 0.50
21502.45
+ 2213.3
x 0.50
24246.8
+ 2213.3

Chapter 7 item No. 7 (i), 10, 8


4 Pacca brick work 1:3 cement sand mortar other then building up to 10 Ft height
i 1st step
1
x 3.143 x 38.170 x 2.170 x 10.00
Total
D/Dection
C.wall
1
x 3.143 x 38.170 x 0.670 x 10.00
Net
1799 Cft @ Rs
18510.50
###
+ ###
ii 10 to 20'height
1st step
1
x 3.143 x 38.170 x 2.170 x 6.00
2nd step
1
x 3.143 x 37.500 x 1.500 x 4.00
Total
D/Dection
1
x 3.143 x 38.170 x
0.670 x 10.00
Net
1465 Cft @ Rs
18992.30

=
=

2603 Cft.
2603 Cft.

=
804 Cft.
=
1799 Cft.
% Cft
Rs.

333,004 /-

=
1562 Cft.
=
707 Cft.
=
2269 Cft.
=
804 Cft.
=
1465 Cft.
% Cft
Rs.

278,237 /-

17283.50 + 481.80 + ###


Chapter 6 item No. 34 (b), (iii)
Providing and laying thick vertical damp proof course with 1:2 cement sand
plaster and 2 coats of bitumen .
ist step
1
x 3.143 x 40.340 x 16.00
2nd step
1
x 3.143 x 39.000 x 4.00
Total
2519 Cft @ Rs
3080.80
Chapter 6 item No. 6
Providing and laying reinforced cement concrete (including prestressed
concrete) using course sand and screened graded and washed agreegate in
required shape and designed icluding forms, moulds, shuttering, lifting,
compacting, curing, rendering and finis

=
2029 Sft
=
490 Sft
=
2519 Sft
% Sft
Rs.

77,605 /-

=
930 Cft.
=
726 Cft.
=
23 Cft.
=
281 Cft.
=
263 Cft.
=
2223 Cft.
=
3 Cft.
=
8 Cft.
=
2211 Cft.
P. Cft
Rs.

643,069 /-

x 20.00 =
1608 Cft.
318.00 P. Cft
Rs.

511,344 /-

(a) (I).Reinforced cement concrete in roof slab, beams, columns, lintels, girders
and other structural members laid in situ or pre cast laid in position, or pre
stressed members cast in situ, complete in all respect. Type C (nominal mix
1:2:4)
Base Slab
1 x 3.1429 x 42.34 x
Tank roof
1 x 3.1429 x
43
x
Beam Motar
1
x
Pillar
9
x
Tank roof beem
6
x
D/d
2 x 3.1429 x
Hole for fixing of Machinery

2.00
3.00

x
x

42.34
43
15.00
1.25
0.75

x
x
x
x
x

0.25
0.25
2.00
1.25
1.50
Total
2.00
x
0.25
1.50
x
1.50
Net
2211 Cft @ Rs

x
x
x
x
x

0.66
0.5
0.75
20
39

x
x

0.5
1.25

290.85
Chapter 6 item No. 6 (a) (3) (c), (2)
ii ( a ) ( ii )Reinforcement cement concrete in slab of rafts / strip foundation ; base
slab of column and retaining walls ; etc, and other structural member , complete
in all respect. (Type C nominal mix 1: 1-1/2 : 3 )
C.wall

8
i

x 3.143 x

38.170 x 0.670
1608 Cft @ Rs

Chapter 6 item No. 9


Fabrication of mild steel reinforcement for cement concrete, i/c cutting,
bending, laying in position, making joints and fastenings, i/c cost of binding
wire and labour charges for bending of steel reinforcement ( also includes
removal
of rust from bars )
Slab
2223.0 @
3.06 Kgs/Cft
C.wall
1607.5 @
2.42 Kgs/Cft
Total
10693 Kgs @ Rs
11460.85
Chapter 11 item No. 7 (b)
Cement plaster thick 1: 2, upto 20 height.
0 to 20'Height
in side

0.25

3.143

=
6802 Kgs
=
3890 Kgs
= 10693 Kgs
P%.Kgs
Rs.

36.000 x 20.00 =
Total
=
566 Cft @ Rs
1607.00 % Sft

1,225,509 /-

566 Sft
566 Sft

Rs.
Chapter 10 item No. 9
Brick on edge flooring, laid in 1: 6 cement mortar, over a bed of 3/4" thick
cement mortar 1: 6,
1
x 3.143 x 43.34 x 3.00
=
409 Sft
409 Sft @ Rs
6699.40 P.% Sft
Rs.

9,091 /-

27,401 /-

Chapter 21 item No. 17


10 Providing and fixing C.I.Manhole Cover 24"Dia as per standard drawing,
1.00 x 2.00
=
2 No.
2 No @ Rs
4216.00 Each
Rs.
Chapter 21 item No. 13
11 Providing and fixing 1 x1 x3/16 angle iron step in manhole chamber i/c
carriage and setting the same in work, to correct lines and level.
1
x
2
x
18
=
36 No.
36 No @ Rs
236.30
Each
Rs.
12 Providing and fixing over flow pipe.with C.I. flanged joints ( Medium quality)
28''
dia G.I.Pipe
20 Rft @ Rs
3000.00 P.Rft.
13 Providing and fixing ventshaft 4" dia G.I. pipe 4' long i/c cost of cowel dome
and fixing in top slab of GST, complete in all respect.
2 No @ Rs
7000.00 Each

14

15

ii

16

PUMP HOUSE
9.00 x 9.00
Chapter 6 item No. 33 (b) (ii)
Providing and laying 2 damp proof course of cement concrete 1:2:4 (using
cement, sand and shingle) with 2 coats of bitumen.
1.00
x 47.000 x 1.125
53 Sft @ Rs
4959.25
Chapter 7 item No. 7 (i) , 8,10
Pacca brick work for ground floor upto 10 height in 1:4 cement sand mortor
above P.L.
Wall
1
x 60.000 x 0.750 x 10.00
Out side stair
1
x
1
x 4.000 x 0.625 x 0.625
2nd step
1
x
1
x 4.000 x 0.625 x 0.625
3rd step
1
x
1
x 4.000 x 4.000 x 0.625
4th step
1
x
1
x 4.000 x 5.331 x 0.625
5th step
1
x
1
x 4.000 x 4.498 x 0.625
6th step
1
x
1
x 4.000 x 3.665 x 0.625
7th step
1
x
1
x 4.000 x 0.333 x 0.625
Total
D/Dection
Door
1
x 4.000 x 7.000
0.750
2
x 3.000 x 4.000
0.750
2
x 1.500 x 2.000
0.750
Lintel over door
1
x 5.000 x 0.500
0.750
2
x 4.000 x 0.500
0.750
2
x 2.500 x 0.500
0.750
Total
Net
= 497.69 50
447 Cft @ Rs
17802.25
10 to 20'height
### + ###
1st step
1.000 x 60.000 x 0.750 x 0.00
Para pit Wall
2.000 x( 9.000 + 9.00 )x 0.750 x 0.875
Total
35 Cft @ Rs
18284.05
### + 481.80
Chapter 6 item No. 6 (a), (3),
Providing and laying reinforced cement concrete (including prestressed
concrete) using course sand and screened graded and washed agreegate in
required shape and designed icluding forms, moulds, shuttering, lifting,
compacting, curing, rendering and finis

8,432 /-

8,507 /-

Rs.

60,000 /-

Rs.

14,000 /-

=
53 Sft
P.% Sft
Rs.

2,628 /-

=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
% Cft
=
=
=
% Cft
+

450
2
2
10
13
11
9
1
498

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

21
18
5
2
3
2
50
447

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Rs.

79,576 /-

Rs.

6,399 /-

0 Cft.
24 Cft.
24 Cft.
###

Providing and laying reinforced cement concrete (including prestressed


concrete) using course sand and screened graded and washed agreegate in
required shape and designed icluding forms, moulds, shuttering, lifting,
compacting, curing, rendering and finis
i

(a) (I).Reinforced cement concrete in roof slab , beams , columns , lintels ,


girders and other structural members laid in situ or pre cast laid in position , or
pre stressed members cast in situ , complete in all respect. Type C (nominal mix
1: 2 : 4 .
Roof
Roof beem
Laintal

Sun shed

D/d of Hole

Door
Window
C.windo
Door
Window
C.windo

1
1
1
2
2
1
2
2

x
x
x
x
x
x
x
x

10.500
10.50
5.00
4.00
2.50
5.00
4.00
2.50

x
x
x
x
x
x
x
x

10.500
0.75
0.5
0.5
0.5
0.25
0.25
0.25
Total
1.50
x
1.50
Net
75 Cft @ Rs

x 0.5
x 1.00
x 0.750
x 0.750
x 0.750
x 1.50
x 1.50
x 1.50
x

0.5

290.80
Chapter 6 item No. 9 (b)
17 Fabrication of mild steel reinforcement for cement concrete, i/c cutting,
bending, laying in position, making joints and fastenings, i/c cost of binding
wire and labour charges for bending of steel reinforcement ( also includes
removal of rust from bars )
Slab

75.4 @

3.06 Kgs/Cft
Total
231 Kgs @ Rs

=
=
=
=
=
=
=
=
=
=
=
P. Cft

55
8
2
3
2
2
3
2
77
1
75

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Rs.

21,810 /-

=
231 Kgs
=
231 Kgs
11460.85 P%.Kgs
Rs.

26,475 /-

Chapter 12 item No. 51


18 Providing, fixing, paneled door of M.S. sheet with forged door leaves of M.S.
sheet 22 SWG fitted in hallow frame chowket 3x 4 made of M.S. sheet 18
SWG filled with plain cement concrete 1:3:6 etc; complete with all fittings and
harmer painting i/c
1

x
4.0
28 Sft @ Rs

7.0
362.15

=
P. Sft

28 Sft

=
=
=
P. Sft

24 Sft
6 Sft
30 Sft

=
=
=
P. Sft

24 Sft
6 Sft
30 Sft

Rs.

10,140 /-

Rs.

11,447 /-

Rs.

5,408 /-

Chapter 25 item No. 41 (b-iii)


19 P/Fixing steel window with openable glazed panels making beams section for
frame 1 x1x5/8 section for leaves x1x3/8 T-section 1x1
x1/8embedded over a thin layer of putty duly screed with leaves brass fittings
holds fast, duly painted complete
Window
C.Window

1
1

x
x

2.00
2.00

x
x

3.00
1.50
Total
30 Cft @ Rs

x
x

4.00
2.00

381.55
Chapter 12 item No. 54
20 Providing and fixing M. S. flat 1/2x 1/8 grill, i/c 3 /4x 1/8 M.S. flat frame,
in windows of approved design, i/c painting 3 coats, complete in all respect.
Window
C.Window

1
1

x
x

2.00
2.00

x
x

3.00
1.50
Total
30 Cft @ Rs

x
x

4.00
2.00

180.25
Chapter 9 item No. 5
21 Single layer of tiles 9x1 x1 laid over 4 earth and 1 mud plaster with
out bhoosa grouted with cement sand 1:3 on top of RCC roof cement RCC
provided work 34 LBS bitumen coating sand grouted.

Single layer of tiles 9x1 x1 laid over 4 earth and 1 mud plaster with
out bhoosa grouted with cement sand 1:3 on top of RCC roof cement RCC
provided work 34 LBS bitumen coating sand grouted.
1.000 x
8.250 x 8.250 =
68 Sft
68 Sft @ Rs
5799.65 P.% Sft
Rs.
Chapter 9 item No. 14
22 Kassi Parnalas in cement sand mortor 1:2 12 out side width finished smooth
with and floating coat of neat cement.
1.00 x 14.38
14 Rft @ Rs
70.55
Chapter 9 item No. 15
23 Khurras on roof 22x6
1.00 x 1.00
1 No @ Rs
376.90
Chapter 9 item No. 16
24 Bottom khurras or brick masonry in cement mortor 1:6,4 x2x4 over 3
cement concrete 1:4:8
1.00 x 1.00
1 No @ Rs
697.30
Chapter 10 item No. 10
25 Providing and laying topping of cement concrete '1 : 2 : 4, including surface
finishing and dividing in panels ' 3 inch thick
1.000 x
9.000 x 9.000
81 Sft @ Rs
5193.10
Chapter 11 item No. 9
26 Cement plaster thick 1: 3, upto 20 height.
i 0 to 20'Height
in side
2.000 x( 9.000 + 9.00 )x 10.00
360 Cft @ Rs
1387.85
Chapter 11 item No. 18 (a)
27 Cement pointing struck joints on wall upto 20' height ratio 1:2 i/c extra cost of
labour and material for red oxide pigment in cement pointing to match with the
colour of bricks.
Out side. P.House
D/d
Door
Window
C.Window

2.000 x( 10.500
1
1
1

x
x
x

1
2.00
2.00

Chapter 13 item No. 5


29 Painting of new surface, preparing
any type, three coat.
Door
Window
C.Window

9.00
1.00

14 Rft

=
Each

1 No

=
Each

1 No

Rs.

988 /-

Rs.

377 /-

Rs.

697 /-

=
81 Sft
P.% Sft
Rs.

4,206 /-

=
% Sft

Rs.

4,996 /-

Rs.

5,604 /-

Rs.

764 /-

360 Sft

+ 10.500 )x 11.00 =

462 Sft

x
x
x

28
24
6
58
404

4.0
3.00
1.50
Total

Net
404 Cft @ Rs
Chapter 11 item No. 25 (a)
28 White washing new surface three costs.
in side
2.000 x(
Roof

=
P.Rft

+
x

9.00
9.00
Total
441 Cft @ Rs

x
x
x

7.0
4.00
2.00

=
=
=
=
=
1387.15 % Sft

)x 10.00
x 9.00
173.20

=
=
=
% Sft

Sft
Sft
Sft
Sft
Sft

360 Sft
81 Sft
441 Sft

surface and painting of doors and windows


1
2
2

x
x
x

2.00
2.00
2.00

x
x
x

4.00
3.00
1.50

x
x
x

7.00
4.00
2.00

3,944 /-

=
=
=

56 Sft
48 Sft
12 Sft

Total
=
60 Sft
60 Cft @ Rs
1239.55 % Sft
Rs.
567.95 + 335.8 + 335.80
30 Providing and fixing R.S. joist quality china made, i/c 3 coats of paint and cost
of masonary work, complete in all respect.(8"x 6")
1.00 x 16.00 =
16 Rft
16 Rft @ Rs
882.50 P.Rft
Rs.
31 Providing and fixing ceilling fan i/c of connections etc, complete in all respect
(Pak, Asia, Royal)
1 Job @ Rs
3000.00 P.Job.
Rs.
TOTAL.
SAY,
For

1 No.P.House Rs 3,954,366

SUB WORK NO 7.
SUB HEAD NO 2.
SLUICE VALVE CHAMBER
Chapter 22 item No. 1 (a)
1 Excavation of well in dry in ordinary soil upto 20 below ground level, and
disposal of soil with in one chain.
i 0 to 5' depth
1 x 3.1429 x 16.000 x 16.000 x
0.25 x 5.00
=
1006
1006 Cft @ Rs
2706.90
%0 Cft
ii 5 to 10'depth
1 x 3.143 x 16.000 x 16.000 x
0.25 x 5.00
=
1006
1006 Cft @ Rs
2827.10 %0 Cft
iii 10 to 15'depth
1 x 3.1429 x 16.000 x 16.000 x
0.25 x 5.00
=
1006
1006 Cft @ Rs
3180.50
%0 Cft
iv 15 to 20'depth
1 x 3.1429 x 16.000 x 16.000 x
0.25 x 1.00
=
201
201 Cft @ Rs
3650.50
%0 Cft
Chapter 6 item No. 3 (d)
2 Cement concrete brick or stone ballast 1- 1/2" to 2" gauge in foundation and
plinth.(1:4:8)
Under Bed
1 x 3.1429 x 6.000 x 6.000 x
0.25 x 0.50
=
14
Under Apren
1
x 3.143 x 11.250 x
3
x 0.375 =
40
Total
=
54
54 Cft @ Rs
10321.40
% Cft
Chapter 6 item No. 5 (f)
3 Cement concrete plain 1 : 2 : 4, i/c placing, compacting , finishing and curing
complete ( i/c screening and washing of stone aggregate). i/c extra labour for
skipping concrete in wells.

744 /-

14,120 /-

3,000 /-

Rs.
3,954,366 /Rs.
3,954,400 /Say
Rs 3,954,400
/-

6 FEET DIA

Cft.
Rs.

2,723 /-

Rs.

2,844 /-

Rs.

3,200 /-

Rs.

734 /-

Rs.

5,574 /-

Rs.

2,700 /-

Cft.

Cft.

Cft.

Cft.
Cft.
Cft.

Under Bed
i

4
i

x 3.1429 x 6.000 x

6.000 x
0.25
14 Cft @ Rs

x 0.50
19289.15

Chapter 7 item No. 7 (i), 10, 8


Pacca brick work 1:3 cement sand mortar other then building
1st step
1
x 3.143 x 7.500 x 1.500

x 10.00

14 Cft.
% Cft

354 Cft.

2nd step
3rd step

1
1

x 3.143 x
x 3.143 x

D/Dection

x 3.143 x

ii 10 to 20'height
1st step
2nd step
3rd step

1
1
1

x 3.143 x
x 3.143 x
x 3.143 x

D/Dection

6
i

3.143 x

7.13
7.125

x
x

1.13
1.125
Total
7.500 x 0.375
Net
265 Cft @ Rs
###

x
x

7.500
7.125
7.13

x
x
x

x
x
x

1.500
1.125
1.125
Total
7.500 x
0.375
Net
214 Cft @ Rs
###

0.00
0.00

0
0
354
88
265
% Cft

Cft.
Cft.
Cft.
Cft.
Cft.

0
139
76
214
x 0.00
0
214
18992.30
% Cft
+ 481.80 +
###

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

x 10.00
18510.50
+ ###
0.00
5.50
3.00

Chapter 6 item No. 34 (b), (iii)


Providing and laying thick vertical damp proof course with 1:2 cement sand
plaster and 2 coats of bitumen .
ist step
1
x 3.143 x 9.000 x 10.00
2nd step
1
x 3.143 x 8.250 x 5.50
Total
425 Cft @ Rs
3080.80
Chapter 11 item No. 7 (b)
Cement plaster thick 1: 2, upto 20 height.
0 to 20'Height
in side
1
x 3.143 x
6
x 18.00
Top
1
x 3.143 x 7.125 x 1.125
Total
365 Cft @ Rs
1607.00
Chapter 11 item No. 18 (a)
Cement pointing struck joints on wall upto 20' height ratio 1:2 i/c extra cost of
labour and material for red oxide pigment in cement pointing to match with the
colour of bricks.
1

3.143 x
8.25
78 Cft @ Rs

=
=
=
=
=

x 3.00
1387.15

Rs.

49,053 /-

Rs.

40,644 /-

283 Sft
143 Sft
425 Sft
% Sft
Rs.

13,093 /-

339 Sft
25 Sft
365 Sft
% Sft
Rs.

5,866 /-

=
=
=
=
=
=

=
=
=

=
=
=

78 Sft
% Sft

Rs.

Chapter 21 item No. 13


8 Providing and fixing 1 x1 x3/16 angle iron step in manhole chamber i/c
carriage and setting the same in work, to correct lines and level.
1
x
2
x
18
=
36 No.
36 No @ Rs
236.30
Each
Rs.
Chapter 10 item No. 9
9 Brick on edge flooring, laid in 1: 6 cement mortar, over a bed of 3/4" thick
cement mortar 1: 6,
1
x 3.143 x 11.250 x 3.00
=
106 Sft
106 Sft @ Rs
6699.40
P.% Sft
Rs.
10 Providing and Laying H.D. Pipe of PN 8
800 mm Dia
40 Rft @ Rs
13791.69
P.Rft.
Rs.
11 Providing and Fixing Sluci Valve for A.C. Pipe of BSS.B. Class working
presure
1
x
2
=
800 mmDia
1 No @ Rs
###
Each
Rs.

1,082 /-

8,507 /-

7,101 /551,668 /-

165,000 /-

TOTAL.
SAY,
SUB WORK NO 7.
SUB HEAD NO 3
WASH OUT CHAMBER
Chapter 22 item No. 1 (a)
1 Excavation of well in dry in ordinary soil upto 20 below ground level, and
disposal of soil with in one chain.
i 0 to 5' depth
1 x 3.1429 x 16.000 x 16.000 x
0.25 x 5.00
=
1006
1006 Cft @ Rs
2706.90
%0 Cft
ii 5 to 10'depth
1 x 3.143 x 16.000 x 16.000 x
0.25 x 5.00
=
1006
1006 Cft @ Rs
2827.10 %0 Cft
iii 10 to 15'depth
1 x 3.1429 x 16.000 x 16.000 x
0.25 x 5.00
=
1006
1006 Cft @ Rs
3180.50
%0 Cft
iv 15 to 20'depth
1 x 3.1429 x 16.000 x 16.000 x
0.25 x 4.00
=
805
805 Cft @ Rs
3650.50
%0 Cft
Chapter 6 item No. 3 (b)
2 Cement concrete brick or stone ballast 1- 1/2" to 2" gauge in foundation and
plinth.(1:4:8)
Under Bed
1 x 3.1429 x 6.000 x 6.000 x
0.25 x 0.50
=
14
Under Apren
1
x 3.143 x 11.250 x
3
x 0.375 =
40
Total
=
54
54 Cft @ Rs
10321.4
% Cft
Chapter 6 item No. 5 (f)
3 Cement concrete plain 1 : 2 : 4, i/c placing, compacting , finishing and curing
complete ( i/c screening and washing of stone aggregate). i/c extra labour for
skipping concrete in wells.

Rs.
Rs.

859,789 /859,800 /-

6 FEET DIA

Cft.
Rs.

2,723 /-

Rs.

2,844 /-

Rs.

3,200 /-

Rs.

2,939 /-

Rs.

5,574 /-

Rs.

2,700 /-

Rs.

49,053 /-

Rs.

48,620 /-

Cft.

Cft.

Cft.

Cft.
Cft.
Cft.

Under Bed
i

x 3.1429 x 6.000 x

6.000 x
0.25
14 Cft @ Rs

Chapter 7 item No. 7 (i), 10 , 8


4 Pacca brick work 1:3 cement sand mortar other then building
i 1st step
1
x 3.143 x 7.500 x 1.500
Total
D/Dection
1
x 3.143 x 7.500 x 0.375
Net
265 Cft @ Rs
###
ii 10 to 20'height
1st step
1
x 3.143 x 7.500 x 1.500
2nd step
1
x 3.143 x 7.125 x
1.13
3rd step
1
x 3.143 x
7.13
x 1.125
Total
D/Dection
1
x 3.143 x 7.500 x
0.375
Net
256 Cft @ Rs
### + 1227.00

x 0.50
19289.15

x 10.00

=
=
=
=

x 10.00
18510.50
+ ###
x
x
x

3.00
5.50
1.50

3.00

18992.30
+ 481.80

14 Cft.
% Cft

=
=
=
=
=
=

354
354
88
265
% Cft

Cft.
Cft.
Cft.
Cft.

106
139
38
282
27
256
% Cft

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

iii 20 to 30'height
3rd step

x 3.143 x

7.13

1.125 x 1.50
=
38 Cft.
Total
=
38 Cft.
38
Cft @ Rs 19474.10
% Cft
Rs.
### + 1227.00 + 481.80 + 481.80

Chapter 6 item No. 34 (b), (iii)


5 Providing and laying thick vertical damp proof course with 1:2 cement sand
plaster and 2 coats of bitumen .
ist step
1
x 3.143 x 9.000 x 13.00
2nd step
1
x 3.143 x 8.250 x 5.50
Total
510 Cft @ Rs
3080.80
Chapter 11 item No. 7 (b)
6 Cement plaster thick 1: 2, upto 20 height.
i 0 to 20'Height
in side
1
x 3.143 x
6
x 20.00
Top
1
x 3.143 x 7.125 x 1.125
Total
402 Cft @ Rs
1607.00
ii 20 to 30'Height
in side
1
x 3.143 x
6
x 1.00
19 Cft @ Rs
1754.45
1607.00 + 147.45
Chapter 9 item No. 18 (a)
7 Cement pointing struck joints on wall upto 20' height ratio 1:2 i/c extra cost of
labour and material for red oxide pigment in cement pointing to match with the
colour of bricks.
3rd step

3.143 x
8.25 x 3.00
78 Cft @ Rs
1600.15
1387.15 + 213.00

=
=
=

=
=
=

7,400 /-

368 Sft
143 Sft
510 Sft
% Sft
Rs.

15,712 /-

377 Sft
25 Sft
402 Sft
% Sft
Rs.

6,460 /-

19 Sft
% Sft

Rs.

333 /-

Rs.

1,248 /-

78 Sft
% Sft

Chapter 21 item No. 13


Providing and fixing 1 x1 x3/16 angle iron step in manhole chamber i/c
carriage and setting the same in work, to correct lines and level.
1
x
2
x
21
=
42 No.
42 No @ Rs
236.30
Each
Rs.
Chapter 10 item No. 9
9 Brick on edge flooring, laid in 1: 6 cement mortar, over a bed of 3/4" thick
cement mortar 1: 6,
1
x 3.143 x 11.250 x 3.00
=
106 Sft
106 Sft @ Rs
6699.40
P.% Sft
Rs.
10 Providing and Laying H D . Pipe PN 8
710 mm Dia
30 Rft @ Rs
10492.95
P.Rft.
Rs.
11 Providing and Fixing Sluice Valve
8

1
710 mmDia

=
2 No @ Rs

###

(Carried Over to Summery of Cost)

2 No.
Each
Rs.
TOTAL.
Rs.
SAY,
Rs.

9,925 /-

7,101 /314,789 /-

280,000 /760,621 /760,600 /5,574,800

55.75

1
i

ii

iii

iv

SUB WORK NO 7.
SUB HEAD NO 1.
GROUNG STORAGE TANK
Chapter 22 item No.1 (a)
Excavation of well in dry in ordinary soil upto 20 below ground
level, and disposal of soil with in one chain.
0 Ft. to 5 Ft. depth
1 x 3.143 x 39.00 x
45.00
x
0.25
x
5.00
=
6895
6895 Cft @ Rs
2706.90 %0 Cft
5 Ft. to 10 Ft. depth
1 x 3.143 x 39.00 x
39.00
x
0.25
x
5.00
=
5975
5975 Cft @ Rs
2827.10 %0 Cft
10 Ft. to 15 Ft. depth
1 x 3.143 x 39.00 x
39.00
x
0.25
x
5.00
=
5975
5975 Cft @ Rs
3180.50 %0 Cft
15 Ft. to 20 Ft. depth
1 x 3.143 x 39.00 x
39.00
x
0.25
x
2.00
=
2390
2390 Cft @ Rs
3650.50 %0 Cft
Chapter 6 item No.3 (b)
Cement concrete brick or stone ballast 1- 1/2" to 2" gauge in foundation
and plinth.(1:4:8)
Under Bed
1 x 3.143 x 32.340 x 32.340
x
0.25
x
0.75
=
616
Under Apren
1
x 3.143 x 32.340
x
3
x 3.000 =
915
Total
=
1531
1531 Cft @ Rs
10321.40
% Cft
Chapter 6 item No. 5 (F), (C) , Item No.17
Cement concrete plain 1:2:4 i/c placing, compacting , finishing and curing
complete (i/c screening and washing of stone aggregate). i/c extra labour
for skipping concrete in wells.
Under Bed
1 x 3.143 x 32.340 x

ii Ratio. 1:1-1/2:3
1 x 3.143 x 32.340 x

32.340
x
0.25
411 Cft @ Rs
19289.2
32.340
x
0.25
412 Cft @ Rs
22033.5

25 FEET DIA
60000 GLNS

Cft.

=
=

Rs.

16,892 /-

Rs.

19,003 /-

Rs.

8,725 /-

Rs.

158,021 /-

Rs.

88,375 /-

Rs.

99,897 /-

Rs.

237,120 /-

Cft.

Cft.

Cft.
Cft.
Cft.

1853 Cft.
1853 Cft.

=
572 Cft.
=
1281 Cft.
% Cft

=
=
=
=
=

18,664 /-

Cft.

x
0.50
=
411 Cft.
21502.45
% Cft
+
2213.3
x
0.50
=
412 Cft.
24246.8
% Cft
+ 2213.3

Chapter 7 item No. 7 (i), 10, 8


4 Pacca brick work 1:3 cement sand mortar other then building up to 10 Ft
i 1st step
1
x 3.143 x 27.170
x
2.170
x 10.00
Total
D/Dection
C.wall
1 x
3.143 x 27.170
x
0.670 x
10.00
Net
1281 Cft @ Rs
18510.50
17283.5 +
###
ii 10 to 20'height
1st step
1
x 3.143 x 27.170
x
2.170
x
6.00
2nd step
1
x 3.143 x 26.500
x
1.500
x
4.00
Total
D/Dection
1 x
3.143 x
27.170 x
0.670 x
10.00
Net

Rs.

1112
500
1612
572
1039

Cft.
Cft.
Cft.
Cft.
Cft.

1039 Cft @ Rs
###

18992.30 % Cft
+
### +
481.80

Chapter 6 item No. 34 (b), (iii)


5 Providing and laying thick vertical damp proof course with 1:2 cement
sand plaster and 2 coats of bitumen .
ist step
1
x
3.143
x 29.340 x 16.00
2nd step
1
x
3.143
x 28.000 x
4.00
Total
1827 Cft @ Rs
3080.80
Chapter 6 item No. 6
6 Providing and laying reinforced cement concrete (including prestressed
concrete) using course sand and screened graded and washed agreegate in
required shape and designed icluding forms, moulds, shuttering, lifting,
compacting, curing, rendering and finis

=
=
=
% Sft

1475 Sft
352 Sft
1827 Sft

=
=
=
=
=
=
=
=
=
P. Cft

772
805
23
313
189
2100
6
8
2086

Rs.

197,330 /-

Rs.

56,286 /-

Rs.

606,713 /-

Rs.

407,358 /-

Rs.

1,091,875 /-

Rs.

6,313 /-

(a) (I).Reinforced cement concrete in roof slab, beams, columns, lintels,


girders and other structural members laid in situ or pre cast laid in position,
or pre stressed members cast in situ, complete in all respect. Type C
(nominal mix 1:2:4)
Base 1 x 3.143 x
Tank 1 x 3.143 x
Beam Motar
Pillar
Tank roof beem

31.34
32
1
10
6

x
x
x
x
x

D/d 2 x 3.143 x 2.00


Hole for fixing of Machi 3.00

x
x

31.34
32
15.00
1.25
0.75

x
x
x
x
x

0.25
0.25
2.00
1.25
1.50
Total
2.00
x
0.25
1.50
x
1.50
Net
2086 Cft @ Rs

x
x
x
x
x

1
1
0.75
20
28

x
x

1
1.25

27.170
x
0.750
1281 Cft @ Rs

290.85
Chapter 6 item No. 6 (a) (3) (c), (2)
ii ( a ) ( ii )Reinforcement cement concrete in slab of rafts / strip foundation ;
base slab of column and retaining walls ; etc, and other structural member ,
complete in all respect. (Type C nominal mix 1: 1-1/2 : 3 )
C.wall

3.143 x

20.00 =
318.00 P. Cft

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

1281 Cft.

Chapter 6 item No. 9


7 Fabrication of mild steel reinforcement for cement concrete, i/c cutting,
bending, laying in position, making joints and fastenings, i/c cost of
binding wire and labour charges for bending of steel reinforcement ( also
includes
removal of rust from
bars@)
Slab
2100.3
3.06 Kgs/Cft
=
6427 Kgs
C.wall
1280.9 @
2.42 Kgs/Cft
=
3100 Kgs
Total
=
9527 Kgs
9527 Kgs @ Rs
11460.85 P%.Kgs
Chapter 11 item No. 7 (b)
8 Cement plaster thick 1: 2, upto 20 height.
i

0 to 20'Height
in side

0.25

3.143

25.000
Total
393 Cft @ Rs

20.00

1607.00
Chapter 10 item No. 9
9 Brick on edge flooring, laid in 1: 6 cement mortar, over a bed of 3/4" thick
cement mortar 1: 6,

=
=
% Sft

393 Sft
393 Sft

10

11

12

13

3.143
x
33.00
311 Sft @ Rs

x
3.00
6699.40

Chapter 21 item No. 17


Providing and fixing C.I.Manhole Cover 24"Dia as per standard drawing,
1.00 x
2.00
2 No @ Rs
4216.00
Chapter 21 item No. 13
Providing and fixing 1 x1 x3/16 angle iron step in manhole
chamber i/c carriage and setting the same in work, to correct lines and
level.
1
x
2
x
18
36 No @ Rs
236.30
Providing and fixing over flow pipe.with C.I. flanged joints ( Medium
quality)
28'' dia G.I.Pipe
20 Rft @ Rs
20000.00
Providing and fixing ventshaft 4" dia G.I. pipe 4' long i/c cost of cowel
dome and fixing in top slab of GST, complete in all respect.
2 No @ Rs
7000.00

PUMP HOUSE
6.25 x 6.25
Chapter 6 item No. 33 (b) (ii)
14 Providing and laying 2 damp proof course of cement concrete 1:2:4
(using cement, sand and shingle) with 2 coats of bitumen.
1.00
x 41.500 x 1.125
47 Sft @ Rs
4959.25
Chapter 7 item No. 7 (i) , 8
15 Pacca brick work for ground floor upto 10 height in 1:4 cement sand
mortor above P.L.
Wall
2
x 35.000
x
0.750
x 10.00
Wall
1
x 55.000
x
0.750
x 10.00
2nd step
1
x
1
x
4.000
x
0.625
x 10.000
3rd step
1
x
1
x
4.000
x
4.000
x 10.000
4th step
1
x
1
x
4.000
x
5.331
x 10.000
5th step
1
x
1
x
4.000
x
4.498
x 10.000
6th step
1
x
1
x
4.000
x
3.665
x 10.000
7th step
1
x
1
x
4.000
x
0.333
x 10.000
Total
D/Dection
Door
1
x
4.000
x
7.000
0.750
2
x
3.000
x
4.000
0.750
2
x
1.500
x
2.000
0.750
Lintel over door
1
x
5.000
x
0.500
0.750
2
x
4.000
x
0.500
0.750
2
x
2.500
x
0.500
0.750
Total
Net
= 1675.60 50
1625 Cft @ Rs
17802.35
ii 10 to 20'height
### + ###
1st step
1.000 x 35.000
x
0.750
x
0.00
Para pit Wall 2.000 x( 6.250 +
6.25
)x 0.750
x 0.875
Total
35 Cft @ Rs
18284.15
### + 481.80
Chapter 6 item No. 6 (a), (3),

=
311 Sft
P.% Sft

Rs.

20,835 /-

=
Each

2 No.
Rs.

8,432 /-

36 No.
Rs.

8,507 /-

P.Rft.

Rs.

400,000 /-

Each

Rs.

14,000 /-

Rs.

2,331 /-

Rs.

289,288 /-

Rs.

6,399 /-

Each

=
P.% Sft

=
=
=
=
=
=
=
=
=

47 Sft

525
413
25
160
213
180
147
13
1676

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

=
21
=
18
=
5
=
2
=
3
=
2
=
50
=
1625
% Cft

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

=
0 Cft.
=
16 Cft.
=
16 Cft.
% Cft
+ 1227.00

16 Providing and laying reinforced cement concrete (including prestressed


concrete) using course sand and screened graded and washed agreegate in
required shape and designed icluding forms, moulds, shuttering, lifting,
compacting, curing, rendering and finis
i

(a) (I).Reinforced cement concrete in roof slab , beams , columns , lintels ,


girders and other structural members laid in situ or pre cast laid in
position , or pre stressed members cast in situ , complete in all respect.
Type C (nominal mix 1: 2 : 4 .
Roof
Roof beem
LainDoor
Window
C.windo
Sun Door
Window
C.windo

1
1
1
2
2
1
2
2

x
x
x
x
x
x
x
x

D/d of Hole

7.750
7.75
5.00
4.00
2.50
5.00
4.00
2.50

x
x
x
x
x
x
x
x

7.750
0.75
0.5
0.5
0.5
0.25
0.25
0.25
Total
1.50
x
1.50
Net
48 Cft @ Rs

x
x
x
x
x
x
x
x

0.5
1.00
0.750
0.750
0.750
1.50
1.50
1.50

0.5

290.85
Chapter 6 item No. 9 (c)
17 Fabrication of mild steel reinforcement for cement concrete, i/c cutting,
bending, laying in position, making joints and fastenings, i/c cost of
binding wire and labour charges for bending of steel reinforcement ( also
includes removal of rust from bars )
Slab

48.2 @

3.06 Kgs/Cft
Total
148 Kgs @ Rs

=
=
=
=
=
=
=
=
=
=
=
P. Cft

30
6
2
3
2
2
3
2
49
1
48

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

=
148 Kgs
=
148 Kgs
11460.85 P%.Kgs

Rs.

13,961 /-

Rs.

16,962 /-

Rs.

10,140 /-

Rs.

11,447 /-

Rs.

5,408 /-

Chapter 12 item No. 51


18 Providing, fixing, paneled door of M.S. sheet with forged door leaves of
M.S. sheet 22 SWG fitted in hallow frame chowket 3x 4 made of
M.S. sheet 18 SWG filled with plain cement concrete 1:3:6 etc; complete
with all fittings and harmer painting i/c
1

x
4.0
28 Sft @ Rs

7.0
362.15

=
P. Sft

28 Sft

=
=
=
P. Sft

24 Sft
6 Sft
30 Sft

=
=
=
P. Sft

24 Sft
6 Sft
30 Sft

Chapter 25 item No. 41 (b-iii)


19 P/Fixing steel window with openable glazed panels making beams section
for frame 1 x1x5/8 section for leaves x1x3/8 T-section 1x1
x1/8embedded over a thin layer of putty duly screed with leaves brass
fittings holds fast, duly painted complete
Window
C.Window

1
1

x
x

2.00
2.00

x
x

3.00
1.50
Total
30 Cft @ Rs

x
x

4.00
2.00

381.55
Chapter 12 item No. 54
20 Providing and fixing M. S. flat 1/2x 1/8 grill, i/c 3 /4x 1/8 M.S. flat
frame, in windows of approved design, i/c painting 3 coats, complete in all
respect.
Window
C.Window

Chapter 9 item No. 5

1
1

x
x

2.00
2.00

x
x

3.00
1.50
Total
30 Cft @ Rs

x
x

4.00
2.00
180.25

21 Single layer of tiles 9x1 x1 laid over 4 earth and 1 mud plaster
with out bhoosa grouted with cement sand 1:3 on top of RCC roof cement
RCC provided work 34 LBS bitumen coating sand grouted.
1.000 x
5.500 x 5.500 =
30 Sft @ Rs
5799.05 P.% Sft
Chapter 9 item No. 14
22 Kassi Parnalas in cement sand mortor 1:2 12 out side width finished
smooth with and floating coat of neat cement.
1.00
x 14.38
14 Rft @ Rs
70.55
Chapter 9 item No. 15
23 Khurras on roof 22x6
1.00
x
1.00
1 No @ Rs
376.90
Chapter 9 item No. 16
24 Bottom khurras or brick masonry in cement mortor 1:6,4 x2x4 over 3
cement concrete 1:4:8
1.00
x
1.00
1 No @ Rs
697.30
Chapter 10 item No. 10
25 Providing and laying topping of cement concrete '1 : 2 : 4, including
surface finishing and dividing in panels ' 3 inch thick
1.000 x
6.250 x 6.250
39 Sft @ Rs
5193.10
Chapter 11 item No. 8
26 Cement plaster thick 1: 3, upto 20 height.
i 0 to 20'Height
in side
2.000 x( 6.250
+
6.25
)x 10.00
250 Cft @ Rs
1387.85
Chapter 11 item No. 18 (a)
27 Cement pointing struck joints on wall upto 20' height ratio 1:2 i/c extra
cost of labour and material for red oxide pigment in cement pointing to
match with the colour of bricks.
Out side. P.House
D/d
Door
Window
C.Window

2.000 x(
1
1
1

x
x
x

30 Sft

=
P.Rft

14 Rft

=
Each

1 No

=
Each

1 No

=
P.% Sft

=
% Sft

7.750

)x

11.00 =

341 Sft

1
2.00
2.00

x
x
x

4.0
3.00
1.50
Total

x
x
x

7.0
4.00
2.00

=
=
=
=
=
% Sft

28
24
6
58
283

=
=
=
% Sft

250 Sft
39 Sft
289 Sft

Chapter 11 item No. 25 (a)


28 White washing new surface three costs.
in side
2.000 x(
6.25
Roof
1.00

+
x

6.25
6.25
Total
289 Cft @ Rs

)x
x

10.00
6.25

173.20

Chapter 13 item No. 5


29 Painting of new surface, preparing surface and painting of doors and
windows any type, three coat.
Door
1
x
2.00
x
4.00
x
7.00
=

Rs.

988 /-

Rs.

377 /-

Rs.

697 /-

Rs.

2,025 /-

Rs.

3,470 /-

Rs.

4,528 /-

Rs.

501 /-

250 Sft

1600.15
+ 213.00

1,740 /-

39 Sft

7.750

Net
283 Cft @ Rs
1387.15

Rs.

Sft
Sft
Sft
Sft
Sft

56 Sft

Window
C.Window

2
2

x
x

2.00
2.00

x
x

3.00
x
4.00
1.50
x
2.00
Total
60 Cft @ Rs
1239.55
567.95 +
335.8
30 Providing and fixing R.S. joist quality china made, i/c 3 coats of paint and
cost of masonary work, complete in all respect.(8"x 6")
1.00
x 16.00
16 Rft @ Rs
882.50
31 Providing and fixing ceilling fan i/c of connections etc, complete in all
respect (Pak, Asia, Royal)
1 Job @ Rs
3000.00

=
48 Sft
=
12 Sft
=
60 Sft
% Sft
+
335.80

=
P.Rft

1
i

ii

iii

iv

1 No.P.House

P.Job.

Rs 3,852,472

Say

SUB WORK NO 7.
SUB HEAD NO 2.
SLUICE VALVE CHAMBER
Chapter 22 item No. 1 (a)
Excavation of well in dry in ordinary soil upto 20 below ground level, and
disposal of soil with in one chain.
0 to 5' depth
1 x 3.143 x 16.000 x 16.000
x
0.25
x
5.00
=
1006
1006 Cft @ Rs
2706.90
%0 Cft
5 to 10'depth
1 x 3.143 x 16.000 x 16.000
x
0.25
x
5.00
=
1006
1006 Cft @ Rs
2827.10 %0 Cft
10 to 15'depth
1 x 3.143 x 16.000 x 16.000
x
0.25
x
5.00
=
1006
1006 Cft @ Rs
3180.50
%0 Cft
15 to 20'depth
1 x 3.143 x 16.000 x 16.000
x
0.25
x
1.00
=
201
201 Cft @ Rs
3650.50
%0 Cft
Chapter 6 item No. 3 (b)
Cement concrete brick or stone ballast 1- 1/2" to 2" gauge in foundation
and plinth.(1:4:8)
Under Bed
1 x 3.143 x 6.000 x
6.000
x
0.25
x
0.50
=
14
Under Apren
1
x 3.143 x 11.250
x
3
x 0.375 =
40
Total
=
54
54 Cft @ Rs
10321.4
% Cft
Chapter 6 item No. 5 (f)
Cement concrete plain 1 : 2 : 4, i/c placing, compacting , finishing and
curing complete ( i/c screening and washing of stone aggregate). i/c extra
labour for skipping concrete in wells.
Under Bed
1 x 3.143 x

6.000 x

6.000
x
0.25
14 Cft @ Rs

Chapter 7 item No. 7 (i), 10, 8


4 Pacca brick work 1:3 cement sand mortar other then building

x
0.50
19289.15

744 /-

Rs.

14,120 /-

Rs.

3,000 /-

16 Rft

TOTAL.
SAY,
For

Rs.

Rs. 3,852,472 /Rs. 3,852,500 /Rs 3,852,500 /-

6 FEET DIA

Cft.
Rs.

2,723 /-

Rs.

2,844 /-

Rs.

3,200 /-

Rs.

734 /-

Rs.

5,574 /-

Rs.

2,700 /-

Cft.

Cft.

Cft.

Cft.
Cft.
Cft.

14 Cft.
% Cft

1st step
2nd step
3rd step

1
1
1

x
x
x

3.143 x
3.143 x
3.143 x

D/Dection

3.143 x

ii 10 to 20'height
1st step
1
2nd step
1
3rd step
1
D/Dection

x
x
x
x

3.143 x
3.143 x
3.143 x
3.143 x

7.500
7.13
7.125

x
x
x

1.500
1.13
1.125
Total
7.500
x
0.375
Net
265 Cft @ Rs
###

18510.50
+
###

7.500
7.125
7.13

x
x
x

x
x
x

1.500
1.125
1.125
Total
7.500 x
0.375
Net
214 Cft @ Rs
###

x
x
x

10.00
0.00
0.00

10.00

0.00
5.50
3.00
0.00

18992.30
+
###

Chapter 6 item No. 34 (b), (iii)


5 Providing and laying thick vertical damp proof course with 1:2 cement
sand plaster and 2 coats of bitumen .
ist step
1
x
3.143
x
9.000
x 10.00
2nd step
1
x
3.143
x
8.250
x
5.50
Total
425 Cft @ Rs
3080.80
Chapter 11 item No. 7 (b)
6 Cement plaster thick 1: 2, upto 20 height.
i 0 to 20'Height
in side
1
x
3.143
x
6
x 18.00
Top
1
x
3.143
x
7.125
x 1.125
Total
365 Cft @ Rs
1607.00
Chapter 11 item No. 18 (a)
7 Cement pointing struck joints on wall upto 20' height ratio 1:2 i/c extra
cost of labour and material for red oxide pigment in cement pointing to
match with the colour of bricks.
1

3.143
x
8.25
78 Cft @ Rs
1387.15

x
3.00
1600.15
+ 213.00

=
=
=
=
=
=

354
0
0
354
88
265
% Cft

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

0
139
76
214
0
214
% Cft
+
481.8

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

=
=
=
=
=
=

=
=
=

Rs.

49,053 /-

Rs.

40,644 /-

Rs.

13,093 /-

Rs.

5,866 /-

Rs.

1,248 /-

Rs.

8,507 /-

Rs.

7,101 /-

Rs.

551,668 /-

283 Sft
143 Sft
425 Sft
% Sft

=
=
=

339 Sft
25 Sft
365 Sft
% Sft

78 Sft
% Sft

Chapter 21 item No. 13


8 Providing and fixing 1 x1 x3/16 angle iron step in manhole
chamber i/c carriage and setting the same in work, to correct lines and
level.
1
x
2
x
18
=
36 No.
36 No @ Rs
236.30
Each
Chapter 10 item No. 9
9 Brick on edge flooring, laid in 1: 6 cement mortar, over a bed of 3/4" thick
cement mortar 1: 6,
1
x
3.143
x 11.250 x
3.00
=
106 Sft
106 Sft @ Rs
6699.40
P.% Sft
10 Providing and Laying H,D Pipe of PN 8
800 mm Dia
40 Rft @ Rs
13791.70
P.Rft.
11 Providing and Fixing Sluci Valve for A.C. Pipe of BSS.B. Class working
presure
1
x
2
=

800 m Dia

1
i

ii

iii

iv

1 No @ Rs

165000.00

Each
TOTAL.
SAY,

SUB WORK NO 7.
SUB HEAD NO 3
WASH OUT CHAMBER
Chapter 22 item No. 1 (a)
Excavation of well in dry in ordinary soil upto 20 below ground level, and
disposal of soil with in one chain.
0 to 5' depth
1 x 3.143 x 16.000 x 16.000
x
0.25
x
5.00
=
1006
1006 Cft @ Rs
2706.90
%0 Cft
5 to 10'depth
1 x 3.143 x 16.000 x 16.000
x
0.25
x
5.00
=
1006
1006 Cft @ Rs
2827.10 %0 Cft
10 to 15'depth
1 x 3.143 x 16.000 x 16.000
x
0.25
x
5.00
=
1006
1006 Cft @ Rs
3180.50
%0 Cft
15 to 20'depth
1 x 3.143 x 16.000 x 16.000
x
0.25
x
4.00
=
805
805 Cft @ Rs
3650.50
%0 Cft
Chapter 6 item No. 3 (d)
Cement concrete brick or stone ballast 1- 1/2" to 2" gauge in foundation
and plinth.(1:4:8)
Under Bed
1 x 3.143 x 6.000 x
6.000
x
0.25
x
0.50
=
14
Under Apren
1
x 3.143 x 11.250
x
3
x 0.375 =
40
Total
=
54
54 Cft @ Rs
10321.40
% Cft
Chapter 6 item No. 5 (f)
Cement concrete plain 1 : 2 : 4, i/c placing, compacting , finishing and
curing complete ( i/c screening and washing of stone aggregate). i/c extra
labour for skipping concrete in wells.
Under Bed
1 x 3.143 x

6.000 x

6.000
x
0.25
14 Cft @ Rs

Chapter 7 item No. 7 (i), 10 , 8


4 Pacca brick work 1:3 cement sand mortar other then building
i 1st step
1
x 3.143 x
7.500
x
1.500
Total
D/Dection
1
x 3.143 x
7.500
x
0.375
Net
265 Cft @ Rs
###
ii 10 to 20'height
1st step
1
x 3.143 x
7.500
x
1.500
2nd step
1
x 3.143 x
7.125
x
1.13
3rd step
1
x 3.143 x
7.13
x
1.125
Total
D/Dection
1 x
3.143 x
7.500 x
0.375
Net
256 Cft @ Rs

x
0.50
19289.15

10.00

10.00

=
=
=
=

3.00
5.50
1.50
3.00

18992.30

=
=
=
=
=
=

165,000 /859,955 /860,000 /-

6 FEET DIA

Cft.
Rs.

2,723 /-

Rs.

2,844 /-

Rs.

3,200 /-

Rs.

2,939 /-

Rs.

5,574 /-

Rs.

2,700 /-

Rs.

49,053 /-

Rs.

48,620 /-

Cft.

Cft.

Cft.

Cft.
Cft.
Cft.

14 Cft.
% Cft

18510.50
+
###
x
x
x

Rs.
Rs.
Rs.

354
354
88
265
% Cft

Cft.
Cft.
Cft.
Cft.

106
139
38
282
27
256
% Cft

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

17283.50 +
iii 20 to 30'height
3rd step
1

3.143 x

1227.00

481.80

1.125
Total
38
Cft @ Rs
17283.50 + 1227.00

1.50

7.13

3.143
x
8.25
78 Cft @ Rs
1387.15

38 Cft.
38 Cft.

19474.10
% Cft
+ 481.80 + 481.80

Chapter 6 item No. 34 (b), (iii)


5 Providing and laying thick vertical damp proof course with 1:2 cement
sand plaster and 2 coats of bitumen .
ist step
1
x
3.143
x
9.000
x 13.00
2nd step
1
x
3.143
x
8.250
x
5.50
Total
510 Cft @ Rs
3080.80
Chapter 11 item No. 7 (b)
6 Cement plaster thick 1: 2, upto 20 height.
i 0 to 20'Height
in side
1
x
3.143
x
6
x 20.00
Top
1
x
3.143
x
7.125
x 1.125
Total
402 Cft @ Rs
1607.00
ii 20 to 30'Height
in side
1
x
3.143
x
6
x
1.00
19 Cft @ Rs
1754.45
1607.00 + 147.45
Chapter 9 item No. 18 (a)
7 Cement pointing struck joints on wall upto 20' height ratio 1:2 i/c extra
cost of labour and material for red oxide pigment in cement pointing to
match with the colour of bricks.
3rd step

=
=

x
3.00
1600.15
+ 213.00

=
=
=

Rs.

7,400 /-

Rs.

15,712 /-

Rs.

6,460 /-

Rs.

333 /-

Rs.

1,248 /-

Rs.

9,925 /-

Rs.

7,101 /-

Rs.

326,447 /-

Rs.
Rs.
Rs.

280,000 /772,279 /772,300 /5,484,800

368 Sft
143 Sft
510 Sft
% Sft

=
=
=

377 Sft
25 Sft
402 Sft
% Sft

19 Sft
% Sft

78 Sft
% Sft

Chapter 21 item No. 13


8 Providing and fixing 1 x1 x3/16 angle iron step in manhole
chamber i/c carriage and setting the same in work, to correct lines and
level.
1
x
2
x
21
=
42 No.
42 No @ Rs
236.30
Each
Chapter 10 item No. 9
9 Brick on edge flooring, laid in 1: 6 cement mortar, over a bed of 3/4" thick
cement mortar 1: 6,
1
x
3.143
x 11.250 x
3.00
=
106 Sft
106 Sft @ Rs
6699.40
P.% Sft
10 Providing and Laying H DPipe of PN 8
710 mm Dia
30 Rft @ Rs
10881.58
P.Rft.
11 Providing and Fixing Sluci Valve
1
710 m Dia

=
2 No @ Rs

140000.00

2 No.
Each
TOTAL.
SAY,

(Carried Over to Summery of Cost)


91.41

1
i

ii

iii

iv

SUB WORK NO 7.
SUB HEAD NO 1.
GROUNG STORAGE TANK
Chapter 22 item No.1 (a)
Excavation of well in dry in ordinary soil upto 20 below ground
level, and disposal of soil with in one chain.
0 Ft. to 5 Ft. depth
1
x 3.143 x 62.00 x 45.00 x
0.25
x
5.00
= 10961
10961 Cft @ Rs
2706.90 %0 Cft
5 Ft. to 10 Ft. depth
1
x 3.143 x 62.00 x 62.00 x
0.25
x
5.00
= 15101
15101 Cft @ Rs
2827.10 %0 Cft
10 Ft. to 15 Ft. depth
1
x 3.143 x 62.00 x 62.00 x
0.25
x
5.00
= 15101
15101 Cft @ Rs
3180.50 %0 Cft
15 Ft. to 20 Ft. depth
1
x 3.143 x 62.00 x 62.00 x
0.25
x
2.00
=
6041
6041 Cft @ Rs
3650.50 %0 Cft
Chapter 6 item No.3 (b)
Cement concrete brick or stone ballast 1- 1/2" to 2" gauge in foundation and
plinth.(1:4:8)
Under Bed
1
x 3.143 x 57.340 x 57.340 x
0.25
x
0.75
=
1937
Under Apren
1
x 3.143 x 57.340 x
3
x 3.000 =
1622
Total
=
3559
3559 Cft @ Rs
10321.40
% Cft
Chapter 6 item No. 5 (F), (C) , Item No.17
Cement concrete plain 1:2:4 i/c placing, compacting , finishing and curing
complete (i/c screening and washing of stone aggregate). i/c extra labour for
skipping concrete in wells.
Under Bed
1

3.143 x 50.000 x 50.000 x


0.25
x
0.50
982 Cft @ Rs
21502.45
ii Ratio. 1:1-1/2:3
19289.15 + 2213.3
1
x 3.143 x 50.000 x 50.000 x
0.25
x
1.00
1965 Cft @ Rs
22869.7
22033.5 + 2213.3
Chapter 7 item No. 7 (i), 10, 8
4 Pacca brick work 1:3 cement sand mortar other then building up to 10 Ft
i 1st step
1
x 3.143 x 52.170 x
2.170
x 10.00
Total
D/Dection
C.wall
1 x
3.143 x 52.170 x
0.670 x
10.00
Net
2459 Cft @ Rs
18510.50
17283.50 + 1227.00
ii 10 to 20'height
1st step
1
x 3.143 x 52.170 x
2.170
x
6.00
2nd step
1
x 3.143 x 51.500 x
1.500
x
4.00
Total
D/Dection
1 x
3.143 x 52.170 x
0.670 x
10.00
Net

=
=

50 FEET DIA
200000 GLNS

Cft.
Rs.

29,670 /-

Rs.

42,692 /-

Rs.

48,029 /-

Rs.

22,053 /-

Rs.

367,339 /-

982 Cft.
% Cft

Rs.

211,154 /-

1965 Cft.
% Cft

Rs.

449,390 /-

Rs.

455,173 /-

Cft.

Cft.

Cft.

Cft.
Cft.
Cft.

3558 Cft.
3558 Cft.

=
1099 Cft.
=
2459 Cft.
% Cft

=
=
=
=
=

2135
971
3106
1099
2007

Cft.
Cft.
Cft.
Cft.
Cft.

2007 Cft @ Rs
### + 1227.00

18992.30 % Cft
+ 481.80

Chapter 6 item No. 34 (b), (iii)


5 Providing and laying thick vertical damp proof course with 1:2 cement
sand plaster and 2 coats of bitumen .
ist step
1
x 3.143 x 54.340 x 16.00
2nd step
1
x 3.143 x 53.000 x
4.00
Total
3399 Cft @ Rs
3080.80
Chapter 6 item No. 6
6 Providing and laying reinforced cement concrete (including prestressed
concrete) using course sand and screened graded and washed agreegate in
required shape and designed icluding forms, moulds, shuttering, lifting,
compacting, curing, rendering and finis

Rs.

381,175 /-

=
2733 Sft
=
666 Sft
=
3399 Sft
% Sft

Rs.

104,716 /-

=
=
=
=
=
=
=
=
=
P. Cft

Rs. 1,552,557 /-

(a) (I).Reinforced cement concrete in roof slab, beams, columns, lintels,


girders and other structural members laid in situ or pre cast laid in position, or
pre stressed members cast in situ, complete in all respect. Type C (nominal
mix 1:2:4)
Base S
1 x
Tank r
1 x
Beam Motar
Pillar
Tank roof beem

3.143 x 56.34 x
3.143 x
57
x
1
x
18
x
6
x

0.25
0.25
2.00
1.25
1.50
Total
2.00 x
0.25
1.50 x
1.50
Net
5338 Cft @ Rs

x
x
x
x
x

1
0.75
0.75
20
53

x
x

0.75
1.25

x 3.143 x 52.170 x
1.000
3279 Cft @ Rs

D/d
2 x 3.143 x
Hole for fixing of Machinery

2.00
3.00

x
x

56.34
57
15.00
1.25
0.75

x
x
x
x
x

290.85
Chapter 6 item No. 6 (a) (3) (c), (2)
ii ( a ) ( ii )Reinforcement cement concrete in slab of rafts / strip foundation ;
base slab of column and retaining walls ; etc, and other structural member ,
complete in all respect. (Type C nominal mix 1: 1-1/2 : 3 )
C.wall

2494
1915
23
563
358
5351
5
8
5338

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

20.00 =
3279 Cft.
318.00 P. Cft

Rs. 1,042,722 /-

Chapter 6 item No. 9


7 Fabrication of mild steel reinforcement for cement concrete, i/c cutting,
bending, laying in position, making joints and fastenings, i/c cost of binding
wire and labour charges for bending of steel reinforcement ( also includes
removal of rust from bars )
Slab
C.wall

5351.4 @
3279.3 @

3.06 Kgs/Cft
2.42 Kgs/Cft
Total
24311 Kgs @ Rs

= 16375 Kgs
=
7936 Kgs
= 24311 Kgs
11460.85 P%.Kgs

Rs. 2,786,247 /-

Chapter 11 item No. 7 (b)


8 Cement plaster thick 1: 2, upto 20 height.
i

0 to 20'Height
in side

0.25

3.143

50.000
Total
786 Cft @ Rs

20.00

1607.00
Chapter 10 item No. 9
9 Brick on edge flooring, laid in 1: 6 cement mortar, over a bed of 3/4" thick

=
786 Sft
=
786 Sft
% Sft

Rs.

12,626 /-

10

11

12

13

Brick on edge flooring, laid in 1: 6 cement mortar, over a bed of 3/4" thick
cement mortar 1: 6,
1
x 3.143 x
57.34
x
3.00
541 Sft @ Rs
6699.40
Chapter 21 item No. 17
Providing and fixing C.I.Manhole Cover 24"Dia as per standard drawing,
1.00 x
2.00
2 No @ Rs
4216.00
Chapter 21 item No. 13
Providing and fixing 1 x1 x3/16 angle iron step in manhole chamber
i/c carriage and setting the same in work, to correct lines and level.
1
x
2
x
18
36 No @ Rs
236.30
Providing and fixing over flow pipe.with C.I. flanged joints ( Medium
quality)
28'' dia G.I.Pipe
20 Rft @ Rs
20000.00
Providing and fixing ventshaft 4" dia G.I. pipe 4' long i/c cost of cowel dome
and fixing in top slab of GST, complete in all respect.
2 No @ Rs
4000.00

PUMP HOUSE
12.50 x 12.50
Chapter 6 item No. 33 (b) (ii)
14 Providing and laying 2 damp proof course of cement concrete 1:2:4 (using
cement, sand and shingle) with 2 coats of bitumen.
1.00 x 54.000 x 1.125
61 Sft @ Rs
4959.25
Chapter 7 item No. 7 (i) , 8
15 Pacca brick work for ground floor upto 10 height in 1:4 cement sand mortor
above P.L.
Wall
1
x 60.000 x
0.750
x 10.00
Out side stair
1
x
1
x 4.000 x
0.625
x 0.625
2nd step
1
x
1
x 4.000 x
0.625
x 0.625
3rd step
1
x
1
x 4.000 x
4.000
x 0.625
4th step
1
x
1
x 4.000 x
5.331
x 0.625
5th step
1
x
1
x 4.000 x
4.498
x 0.625
6th step
1
x
1
x 4.000 x
3.665
x 0.625
7th step
1
x
1
x 4.000 x
0.333
x 0.625
Total
D/Dection
Door
1
x 4.000 x
7.000
0.750
2
x 3.000 x
4.000
0.750
2
x 1.500 x
2.000
0.750
Lintel over door
1
x 5.000 x
0.500
0.750
2
x 4.000 x
0.500
0.750
2
x 2.500 x
0.500
0.750
Total
Net
= 497.69 50
447 Cft @ Rs
17802.35
ii 10 to 20'height
16575.35 + 1227.00
1st step
1.000 x 60.000 x
0.750
x
0.00
Para pit Wall
2.000 x( 12.500 + 12.50 )x 0.750
x 0.875
Total
35 Cft @ Rs
18284.15
16575.35 + 481.80

=
541 Sft
P.% Sft

Rs.

36,244 /-

=
Each

Rs.

8,432 /-

Rs.

8,507 /-

P.Rft.

Rs.

400,000 /-

Each

Rs.

8,000 /-

=
61 Sft
P.% Sft

Rs.

3,025 /-

Rs.

79,577 /-

Rs.

6,399 /-

2 No.

36 No.
Each

=
=
=
=
=
=
=
=
=

450
2
2
10
13
11
9
1
498

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

=
21
=
18
=
5
=
2
=
3
=
2
=
50
=
447
% Cft

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

=
0 Cft.
=
33 Cft.
=
33 Cft.
% Cft
+
###

Chapter 6 item No. 6 (a), (3),


16 Providing and laying reinforced cement concrete (including prestressed
concrete) using course sand and screened graded and washed agreegate in
required shape and designed icluding forms, moulds, shuttering, lifting,
compacting, curing, rendering and finis
i

(a) (I).Reinforced cement concrete in roof slab , beams , columns , lintels ,


girders and other structural members laid in situ or pre cast laid in position ,
or pre stressed members cast in situ , complete in all respect. Type C (nominal
mix 1: 2 : 4 .
Roof
Roof beem
Lainta Door
Window
C.window
Sun shDoor
Window
C.window

1
1
1
2
2
1
2
2

x 14.000 x
x 14.00 x
x 5.00 x
x 4.00 x
x 2.50 x
x 5.00 x
x 4.00 x
x 2.50 x

14.000
0.75
0.5
0.5
0.5
0.25
0.25
0.25
Total
1.50 x
1.50
Net
121 Cft @ Rs

x
x
x
x
x
x
x
x

0.5
1.00
0.750
0.750
0.750
1.50
1.50
1.50

=
98 Cft.
=
11 Cft.
=
2 Cft.
=
3 Cft.
=
2 Cft.
=
2 Cft.
=
3 Cft.
=
2 Cft.
=
122 Cft.
=
1 Cft.
=
121 Cft.
P. Cft

D/d of Hole

0.5

Rs.

35,193 /-

=
370 Kgs
=
370 Kgs
11460.85 P%.Kgs

Rs.

42,405 /-

Rs.

10,140 /-

Rs.

11,447 /-

Rs.

5,408 /-

290.85
Chapter 6 item No. 9 (b)
17 Fabrication of mild steel reinforcement for cement concrete, i/c cutting,
bending, laying in position, making joints and fastenings, i/c cost of binding
wire and labour charges for bending of steel reinforcement ( also includes
removal of rust from bars )
Slab

120.9 @

3.06 Kgs/Cft
Total
370 Kgs @ Rs

Chapter 12 item No. 51


18 Providing, fixing, paneled door of M.S. sheet with forged door leaves of M.S.
sheet 22 SWG fitted in hallow frame chowket 3x 4 made of M.S. sheet
18 SWG filled with plain cement concrete 1:3:6 etc; complete with all
fittings and harmer painting i/c
1

x
4.0
28 Sft @ Rs

7.0
362.15

=
P. Sft

28 Sft

=
=
=
P. Sft

24 Sft
6 Sft
30 Sft

=
=
=
P. Sft

24 Sft
6 Sft
30 Sft

Chapter 25 item No. 41 (b-iii)


19 P/Fixing steel window with openable glazed panels making beams section for
frame 1 x1x5/8 section for leaves x1x3/8 T-section 1x1
x1/8embedded over a thin layer of putty duly screed with leaves brass
fittings holds fast, duly painted complete
Window
C.Window

1
1

x
x

2.00
2.00

x
x

3.00
1.50
Total
30 Cft @ Rs

x
x

4.00
2.00

381.55
Chapter 12 item No. 54
20 Providing and fixing M. S. flat 1/2x 1/8 grill, i/c 3 /4x 1/8 M.S. flat
frame, in windows of approved design, i/c painting 3 coats, complete in all
respect.
Window
C.Window

1
1

x
x

2.00
2.00

x
x

3.00
1.50
Total
30 Cft @ Rs

x
x

4.00
2.00
180.25

Chapter 9 item No. 5


21 Single layer of tiles 9x1 x1 laid over 4 earth and 1 mud plaster
with out bhoosa grouted with cement sand 1:3 on top of RCC roof cement
RCC provided work 34 LBS bitumen coating sand grouted.
1.000 x
11.750 x 11.750 =
138 Sft
138 Sft @ Rs
5799.05 P.% Sft
Chapter 9 item No. 14
22 Kassi Parnalas in cement sand mortor 1:2 12 out side width finished smooth
with and floating coat of neat cement.
1.00
x 14.38
14 Rft @ Rs
70.55
23 Khurras on roof 22x6
1.00
x
1.00
1 No @ Rs
376.90
Chapter 9 item No. 16
24 Bottom khurras or brick masonry in cement mortor 1:6,4 x2x4 over 3
cement concrete 1:4:8
1.00
x
1.00
1 No @ Rs
697.30
Chapter 10 item No. 15
25 Providing and laying topping of cement concrete '1 : 2 : 4, including surface
finishing and dividing in panels ' 3 inch thick
1.000 x
12.500 x 12.500
156 Sft @ Rs
5193.10
Chapter 11 item No. 9
26 Cement plaster thick 1: 3, upto 20 height.
i 0 to 20'Height
in side
2.000 x( 12.500 + 12.50 )x 10.00
500 Cft @ Rs
1387.85
Chapter 11 item No. 18 (a)
27 Cement pointing struck joints on wall upto 20' height ratio 1:2 i/c extra cost
of labour and material for red oxide pigment in cement pointing to match
with the colour of bricks.
Out side. P.House
D/d
Door
Window
C.Window

2.000 x( 14.000
1
1
1

x
x
x

1
2.00
2.00

8,003 /-

Rs.

988 /-

Rs.

377 /-

Rs.

697 /-

=
156 Sft
P.% Sft

Rs.

8,101 /-

=
500 Sft
% Sft

Rs.

6,939 /-

Rs.

7,740 /-

Rs.

2,322 /-

=
P.Rft

14 Rft

=
Each

1 No

=
Each

1 No

14.000

)x

11.00 =

x
x
x

4.0
3.00
1.50
Total

x
x
x

7.0
4.00
2.00

Net
558 Cft @ Rs
Chapter 11 item No. 25 (a)
28 White washing new surface three costs.
in side
2.000 x( 12.50
Roof
1.00

Rs.

+
x

12.50
12.50
Total
656 Cft @ Rs

1387.15

)x
x

10.00
12.50
353.90

616 Sft

=
28
=
24
=
6
=
58
=
558
% Sft

Sft
Sft
Sft
Sft
Sft

=
500 Sft
=
156 Sft
=
656 Sft
% Sft

Chapter 13 item No. 5


29 Painting of new surface, preparing surface and painting of doors and windows
any type, three coat.
Door
1
x 2.00 x
4.00
x
7.00
=

56 Sft

Window
C.Window

2
2

x
x

2.00
2.00

x
x

3.00
x
4.00
1.50
x
2.00
Total
60 Cft @ Rs
1239.55
567.95 +
335.8
30 Providing and fixing R.S. joist quality china made, i/c 3 coats of paint and
cost of masonary work, complete in all respect.(8"x 6")
1.00
x 16.00
16 Rft @ Rs
882.50
31 Providing and fixing ceilling fan i/c of connections etc, complete in all
respect (Pak, Asia, Royal)
1 Job @ Rs
3000.00

=
48 Sft
=
12 Sft
=
60 Sft
% Sft
+ 335.80

=
P.Rft

1
i

ii

iii

iv

1 No.P.House

P.Job.

Rs 8,213,351

Say

SUB WORK NO 7.
SUB HEAD NO 2.
SLUICE VALVE CHAMBER
Chapter 22 item No. 1 (a)
Excavation of well in dry in ordinary soil upto 20 below ground level, and
disposal of soil with in one chain.
0 to 5' depth
1
x 3.143 x 16.000 x 16.000 x
0.25
x
5.00
=
1006
1006 Cft @ Rs
2706.90
%0 Cft
5 to 10'depth
1
x 3.143 x 16.000 x 16.000 x
0.25
x
5.00
=
1006
1006 Cft @ Rs
2827.10 %0 Cft
10 to 15'depth
1
x 3.143 x 16.000 x 16.000 x
0.25
x
5.00
=
1006
1006 Cft @ Rs
3180.50
%0 Cft
15 to 20'depth
1
x 3.143 x 16.000 x 16.000 x
0.25
x
1.00
=
201
201 Cft @ Rs
3650.50
%0 Cft
Chapter 6 item No. 3 (b)
Cement concrete brick or stone ballast 1- 1/2" to 2" gauge in foundation and
plinth.(1:4:8)
Under Bed
1
x 3.143 x 6.000 x 6.000 x
0.25
x
0.50
=
14
Under Apren
1
x 3.143 x 11.250 x
3
x 0.375 =
40
Total
=
54
54 Cft @ Rs
10321.40
% Cft
Chapter 6 item No. 5 (f)
Cement concrete plain 1 : 2 : 4, i/c placing, compacting , finishing and curing
complete ( i/c screening and washing of stone aggregate). i/c extra labour for
skipping concrete in wells.
Under Bed
1

3.143 x 6.000 x

6.000 x
0.25
14 Cft @ Rs

Chapter 7 item No. 7 (i), 10, 8


4 Pacca brick work 1:3 cement sand mortar other then building

x
0.50
19289.15

744 /-

Rs.

14,120 /-

Rs.

3,000 /-

16 Rft

TOTAL.
SAY,
For

Rs.

Rs. 8,213,351 /Rs. 8,213,400 /Rs 8,213,400 /-

6 FEET DIA

Cft.
Rs.

2,723 /-

Rs.

2,844 /-

Rs.

3,200 /-

Rs.

734 /-

Rs.

5,574 /-

Rs.

2,700 /-

Cft.

Cft.

Cft.

Cft.
Cft.
Cft.

14 Cft.
% Cft

1st step
2nd step
3rd step

1
1
1

x 3.143 x
x 3.143 x
x 3.143 x

D/Dection

x 3.143 x

ii 10 to 20'height
1st step
2nd step
3rd step

1
1
1

x 3.143 x
x 3.143 x
x 3.143 x

D/Dection

3.143 x

7.500
7.13
7.125

x
x
x

1.500
1.13
1.125
Total
7.500 x
0.375
Net
265 Cft @ Rs
17283.50

x
x
x

10.00
0.00
0.00

10.00

7.500
7.125
7.13

x
x
x

x
x
x

1.500
1.125
1.125
Total
7.500 x
0.375
Net
214 Cft @ Rs
17283.50

354
0
0
354
88
265
% Cft

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

0
139
76
214
x
0.00
0
214
18992.30
% Cft
+ 1227.00 +
481.8

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

18510.50
+ 1227.00
0.00
5.50
3.00

Chapter 6 item No. 34 (b), (iii)


5 Providing and laying thick vertical damp proof course with 1:2 cement
sand plaster and 2 coats of bitumen .
ist step
1
x 3.143 x
9.000
x 10.00
2nd step
1
x 3.143 x
8.250
x
5.50
Total
425 Cft @ Rs
3080.80
Chapter 11 item No. 7 (b)
6 Cement plaster thick 1: 2, upto 20 height.
i 0 to 20'Height
in side
1
x 3.143 x
6
x 18.00
Top
1
x 3.143 x
7.125
x 1.125
Total
365 Cft @ Rs
1607.00
Chapter 11 item No. 18 (a)
7 Cement pointing struck joints on wall upto 20' height ratio 1:2 i/c extra cost
of labour and material for red oxide pigment in cement pointing to match
with the colour of bricks.
1

10
11

3.143 x
8.25
78 Cft @ Rs
1387.15

=
=
=
=
=
=

x
3.00
1600.15
+ 213.00

Rs.

49,053 /-

Rs.

40,644 /-

283 Sft
143 Sft
425 Sft
% Sft

Rs.

13,093 /-

339 Sft
25 Sft
365 Sft
% Sft

Rs.

5,866 /-

Rs.

1,248 /-

Rs.

8,507 /-

Rs.

7,101 /-

Rs.

102,400 /-

=
=
=
=
=
=

=
=
=

=
=
=

78 Sft
% Sft

Chapter 21 item No. 13


Providing and fixing 1 x1 x3/16 angle iron step in manhole chamber
i/c carriage and setting the same in work, to correct lines and level.
1
x
2
x
18
=
36 No.
36 No @ Rs
236.30
Each
Chapter 10 item No. 9
Brick on edge flooring, laid in 1: 6 cement mortar, over a bed of 3/4" thick
cement mortar 1: 6,
1
x 3.143 x 11.250 x
3.00
=
106 Sft
106 Sft @ Rs
6699.40
P.% Sft
Providing and Laying A.C. Pipe of BSS.B. Class working presure
20'' Dia
40 Rft @ Rs
2560.00
P.Rft.
Providing and Fixing Sluci Valve for A.C. Pipe of BSS.B. Class working
presure
1
x
2
=

20''

1
i

ii

iii

iv

Dia

1 No @ Rs

109893.85

Each
TOTAL.
SAY,

SUB WORK NO 7.
SUB HEAD NO 3
WASH OUT CHAMBER
Chapter 22 item No. 1 (a)
Excavation of well in dry in ordinary soil upto 20 below ground level, and
disposal of soil with in one chain.
0 to 5' depth
1
x 3.143 x 16.000 x 16.000 x
0.25
x
5.00
=
1006
1006 Cft @ Rs
2706.90
%0 Cft
5 to 10'depth
1
x 3.143 x 16.000 x 16.000 x
0.25
x
5.00
=
1006
1006 Cft @ Rs
2827.10 %0 Cft
10 to 15'depth
1
x 3.143 x 16.000 x 16.000 x
0.25
x
5.00
=
1006
1006 Cft @ Rs
3180.50
%0 Cft
15 to 20'depth
1
x 3.143 x 16.000 x 16.000 x
0.25
x
4.00
=
805
805 Cft @ Rs
3650.50
%0 Cft
Chapter 6 item No. 3 (b)
Cement concrete brick or stone ballast 1- 1/2" to 2" gauge in foundation and
plinth.(1:6:12)
Under Bed
1
x 3.143 x 6.000 x 6.000 x
0.25
x
0.50
=
14
Under Apren
1
x 3.143 x 11.250 x
3
x 0.375 =
40
Total
=
54
54 Cft @ Rs
10321.40
% Cft
Chapter 6 item No. 5 (f)
Cement concrete plain 1 : 2 : 4, i/c placing, compacting , finishing and curing
complete ( i/c screening and washing of stone aggregate). i/c extra labour for
skipping concrete in wells.
Under Bed
1

3.143 x 6.000 x

6.000 x
0.25
14 Cft @ Rs

Chapter 7 item No. 7 (i), 10 , 8


4 Pacca brick work 1:3 cement sand mortar other then building
i 1st step
1
x 3.143 x 7.500 x
1.500
Total
D/Dection
1
x 3.143 x 7.500 x
0.375
Net
265 Cft @ Rs
17283.50
ii 10 to 20'height
1st step
1
x 3.143 x 7.500 x
1.500
2nd step
1
x 3.143 x 7.125 x
1.13
3rd step
1
x 3.143 x 7.13 x
1.125
Total
D/Dection
1 x
3.143 x 7.500 x
0.375
Net
256 Cft @ Rs

x
0.50
19289.15

=
=
=
=

Cft.

2,844 /-

Rs.

3,200 /-

Rs.

2,939 /-

Rs.

5,574 /-

Rs.

2,700 /-

Rs.

50,330 /-

Rs.

48,620 /-

Cft.
Cft.
Cft.

14 Cft.

Cft.
Cft.
Cft.
Cft.
Cft.
Cft.

18992.30

Rs.

Cft.

x
x
x

3.00

2,723 /-

Cft.

% Cft

=
=
=
=
=
=

Rs.
Cft.

Cft.
Cft.
Cft.
Cft.

3.00
5.50
1.50

109,894 /355,581 /355,600 /-

6 FEET DIA

354
354
x 10.00
88
265
18992.30
% Cft
+ 1227.00 + 481.80

10.00

Rs.
Rs.
Rs.

106
139
38
282
27
256
% Cft

iii 20 to 30'height
3rd step

x 3.143 x

###

7.13

38
###

1227.00

481.80

1.125
Total
Cft @ Rs
+ 1227.00

1.50

3.143 x
8.25
78 Cft @ Rs
1387.15

38 Cft.
38 Cft.

19474.10
% Cft
+
481.8 + 481.80

Chapter 6 item No. 34 (b), (iii)


5 Providing and laying thick vertical damp proof course with 1:2 cement
sand plaster and 2 coats of bitumen .
ist step
1
x 3.143 x
9.000
x 13.00
2nd step
1
x 3.143 x
8.250
x
5.50
Total
510 Cft @ Rs
3080.80
Chapter 11 item No. 7 (b)
6 Cement plaster thick 1: 2, upto 20 height.
i 0 to 20'Height
in side
1
x 3.143 x
6
x 20.00
Top
1
x 3.143 x
7.125
x 1.125
Total
402 Cft @ Rs
1607.00
ii 20 to 30'Height
in side
1
x 3.143 x
6
x
1.00
19 Cft @ Rs
1754.45
1607.00 + 147.45
Chapter 9 item No. 18 (a)
7 Cement pointing struck joints on wall upto 20' height ratio 1:2 i/c extra cost
of labour and material for red oxide pigment in cement pointing to match
with the colour of bricks.
3rd step

=
=

x
3.00
1600.15
+ 213.00

=
=
=

=
=
=

Rs.

7,400 /-

368 Sft
143 Sft
510 Sft
% Sft

Rs.

15,712 /-

377 Sft
25 Sft
402 Sft
% Sft

Rs.

6,460 /-

Rs.

333 /-

Rs.

1,248 /-

Rs.

9,925 /-

Rs.

7,101 /-

Rs.

76,800 /-

Rs.
Rs.
Rs.

219,788 /463,697 /463,700 /9,032,700

19 Sft
% Sft

78 Sft
% Sft

Chapter 21 item No. 13


8 Providing and fixing 1 x1 x3/16 angle iron step in manhole chamber
i/c carriage and setting the same in work, to correct lines and level.
1
x
2
x
21
=
42 No.
42 No @ Rs
236.30
Each
Chapter 10 item No. 9
9 Brick on edge flooring, laid in 1: 6 cement mortar, over a bed of 3/4" thick
cement mortar 1: 6,
1
x 3.143 x 11.250 x
3.00
=
106 Sft
106 Sft @ Rs
6699.40
P.% Sft
10 Providing and Laying A.C. Pipe of BSS.B. Class working presure
20 Dia
30 Rft @ Rs
2560.00
P.Rft.
11 Providing and Fixing Sluci Valve
1
20 Dia

=
2 No @ Rs

109893.85

2 No.
Each
TOTAL.
SAY,

(Carried Over to Summery of Cost)


45.16

9E+006
9E+006
500

DETAIL OF GATE AND GATE PILLARS.

Sub Head No.6

Chapter 3 item No.21


1 Excavation in foundation of building bridges and other
structures, including degbelling, dressing refilling around
structure with excavated earth, watering and ramming lead upto
one chain(30m)and lift upto 5 ft (1.5m) in ordinary soil.
For pillers

2 X

2.625
17

X 2.625
Cft. @ Rs.

1.25

3833.30

Chapter 6 item No.3(d)


2 Cement concrete brick or stone ballast 11/2'' to 2'' guage
foundation and plinth 1:6:12
Pillars
2 X
2.625
x 2.625
x
0.50
Cft.
@
Rs.
7
8479.35
Chapter 7 item No.4(i)
3 Pacca brick work in ground floor
a) In 1:4 cement sand mortar .
Ist Step
2 X
2.25
x
2.25
x
0.75
2nd Step
2 x
1.875
x 1.875
x
1.25
Above plinth
2 X
1.875
x 1.875
x
6.50
Total
Cft. @ Rs.
63
16188.70
Chapter 6 item No.33(b)
4 P/L D.P.C 1:2:4 of cement cementsand shingle i/c
bitumen coating with 2 coats of bitumen 1-1/2" thick
Pillar
2 x
1.88 x
1.88
sft. @ Rs.
7
4429.40
Chapter 11 item No.18+31)
6 Cement pointing struck joints on wall 1:2 above plinth.
2 x
4 x
1.875 x
6.5
Sft.
@
Rs.
98
1600.31
1387.31 +
213.00
Chapter 25 item No.30
7 Making and fixing steel grated doors complete with
locking aganrement angle iron 2"x2"x3/8" and
1/4" square bars, 4" center to centre.
Gate
2 x
6
x
4.50

17
Per %

Cft
Cft. Rs.

66 /-

Cft
Cft. Rs.

584 /-

Cft
Cft
Cft
Cft
Cft. Rs.

10199 /-

in
=

7
Per %

=
=
=
=

8
9
46
63
Per %

Sft

Per %

Sft. Rs.

311 /-

98

Sft
Sft Rs.

1560 /-

Per %

54

Sft

Sft. @ Rs.
54
716.05
Chapter 13 item No.5
8 Painting guard bars, gate of iron bras, grating, sailing,
i/c slanders braces etc; and similar open works, 3 coats
45 x
2
x
=
Sft. @ Rs.
90
1239.55
567.95 +
335.80 +

Per

Sft Rs.

90
Sft
Per % Sft Rs.
335.80
Total
Rs.
Say
Rs.

38667 /-

1116 /52503 /52500 /-

Sub Head No.5


BOUNDARY WALL
Chapter 3 item No.21)
Excavation in foundation of building bridges and other structures,
including degbelling, dressing refilling around structure with excavated
earth, watering and ramming lead upto one chain(30m)and lift upto 5 ft
(1.5m) in ordinary soil.
1 X 1672 X
2.50 X
1
Total
Cft.
@
Rs.
4180
3833.30
Chapter 6 item No.3
P/L Cement concrete brick or stone ballast 1 1/2'' to 2'' guage in
foundation and plinth 1:6:12.
1
X 1672
x
2.50 x 0.50
Cft. @ Rs.
Chapter 7 item No.7
2090
8479.35
Pacca brick work O.T.B.building upto 10' cement sand
mortar Ratio 1;5
1st step
1
1672
X
1.50 X 0.75
2nd step
1 X 1672
X
1.125 X 2.50
Total
Cft. @ Rs.
Chapter 6 item No.33(b)
16103.30
6584
P/L 1-1/2" thick D.P.C of cement concrete 1;2:4
(using cement, sand and shingle) i/c two coat of bitumen
1
x 1672
x
1.125
Sft. @ Rs.
Chapter 7 item No.7
1881
4429.40
Pacca brick work O.T.B.building upto 10' cement sand
mortar Ratio 1;6
Wall
1
x 1463
x
0.75 x
5
Pillars
209 x 1.125
x
0.375 x
5
Total
Sft. @ Rs.
Chapter 11 item No.9
5927
15748.55
Cement plaster 1:4 upto 20' height 1/2" thick
Wall
1
x 1463
x
4.75 x
Pillars
2
x 209
x
0.375 x
4
Total
Sft. @ Rs.
Chapter 11 item No.18+31
7576
1299.50
Cement pointing struck joint on wall upto 20' height 1:2
Wall
1
x 1463
x
4
x
Pillar
2
x 209
x
0.375 x
4
Total
Sft. @ Rs.
6479
1600.31
1387.31 +
213.00
Chapter 3 item No.13
Rehandling of earth work lead upto a single throw of kassi
phorah or shovel
4180 x 0.675
Cft. @ Rs.
2822
910.80

4180 Cft
4180 Cft
Per %o Cft. Rs.

16023 /-

2090 Cft
Per % Cft. Rs. 177218 /-

=
=
=

1881 Cft.
4703 Cft.
6584 Cft.
Per % Cft. Rs. 1060161 /-

1881 Sft
Sft Rs.

Per %

83317 /-

=
=
=

5486 Cft
441 Cft
5927 Cft
Per % Sft Rs. 933434 /-

=
=
=

6949 Cft
627 Cft
7576 Cft
Per % Sft Rs.

98453 /-

=
=
=

5852 Cft
627 Cft
6479 Cft
Per % Sft Rs. 103684 /-

2822 Cft
Per % Sft Rs.
2570 /Total
=
2474860 /Say

Rs. 2474900 /-

1
i

ii

iii

iv

SUB WORK NO 7.
ZONE-D
SUB HEAD NO 1.
GROUNG STORAGE TANK 36 FEET DIA
Chapter 22 item No.1 (a)
Excavation of well in dry in ordinary soil upto 20 below ground
level, and disposal of soil with in one chain.
0 Ft. to 5 Ft. depth
1 x 3.143 x 45.00 x 45.00
x
0.25
x 5.00
=
7955 Cft.
7955 Cft @ Rs
2706.90 %0 Cft
Rs.
21,533
5 Ft. to 10 Ft. depth
1 x 3.143 x 45.00 x 45.00
x
0.25
x 5.00
=
7955 Cft.
7955 Cft @ Rs
2827.10 %0 Cft
Rs.
22,490
10 Ft. to 15 Ft. depth
1 x 3.143 x 45.00 x 45.00
x
0.25
x 5.00
=
7955 Cft.
7955 Cft @ Rs
3180.50 %0 Cft
Rs.
25,301
15 Ft. to 20 Ft. depth
1 x 3.143 x 45.00 x 45.00
x
0.25
x 2.00
=
3182 Cft.
3182 Cft @ Rs
3650.50 %0 Cft
Rs.
11,616
Chapter 6 item No.3 (b)
Cement concrete brick or stone ballast 1- 1/2" to 2" gauge in foundation
and plinth.(1:4:8)
Under Bed
1 x 3.143 x 43.340 x 43.340 x
0.25
x 0.75
=
1107 Cft.
Under Apren
1 x 3.143 x 43.340 x
3
x 3.000
=
1226 Cft.
Total
=
2333 Cft.
2333 Cft @ Rs
10315.65
% Cft
Rs.
240,664
Chapter 6 item No. 5 (F), (C) , Item No.17
Cement concrete plain 1:2:4 i/c placing, compacting , finishing and curing
complete (i/c screening and washing of stone aggregate). i/c extra labour
for skipping concrete in wells.
Under Bed

x 3.143 x 36.000 x

ii Ratio. 1:1-1/2:3
1 x 3.143 x 36.000 x

36.000 x
0.25
509 Cft @ Rs
19278.6
36.000 x
0.25
510 Cft @ Rs
22020

Chapter 7 item No. 7 (i), 10, 8


4 Pacca brick work 1:3 cement sand mortar other then building
i height
1st step
1 x 3.143 x 38.170 x 2.170
Total
D/Dection
C.wall
1 x 3.143 x 38.170 x 0.670
Net
1799 Cft @ Rs
16469.90
ii 10 to 20'height
1st step
1 x 3.143 x 38.170 x 2.170
2nd step
1 x 3.143 x 37.500 x 1.500
Total
D/Dection
1 x 3.143 x 38.170 x
0.670

x 0.50
21491.90
+ 2213.30
x 0.50
22869.7
+ 2213.3

509 Cft.
% Cft

=
=

804 Cft.
1799 Cft.

x
x

1562 Cft.
707 Cft.
2269 Cft.
804 Cft.

=
=
=
10.00 =

Rs.

116,635

Rs.

307,849

2603 Cft.
2603 Cft.

10.00 =
=
17112.25 % Cft
+ 1177.80
6.00
4.00

109,394

510 Cft.
% Cft

up to 10 Ft
x 10.00

Rs.

Net
=
1465 Cft @ Rs
18129.50 % Cft
16469.90 + 1177.80 + 481.80
Chapter 6 item No. 34 (b), (iii)
5 Providing and laying thick vertical damp proof course with 1:2 cement
sand plaster and 2 coats of bitumen .
ist step
1
x 3.143
x 40.340 x 16.00
=
2nd step
1
x 3.143
x 39.000 x 4.00
=
Total
=
2519 Cft @ Rs
3597.40 % Sft
Chapter 6 item No. 6
6 Providing and laying reinforced cement concrete (including prestressed
concrete) using course sand and screened graded and washed agreegate in
required shape and designed icluding forms, moulds, shuttering, lifting,
compacting, curing, rendering and finis

1465 Cft.
Rs.

265,597

Rs.

90,619

Rs.

642,848

Rs.

511,103

2029 Sft
490 Sft
2519 Sft

(a) (I).Reinforced cement concrete in roof slab, beams, columns, lintels,


girders and other structural members laid in situ or pre cast laid in position,
or pre stressed members cast in situ, complete in all respect. Type C
(nominal mix 1:2:4)
Base Sla
1 x 3.143 x 42.34 x
Tank roof
1 x 3.143 x 43 x
Beam Motar
1
x
Pillar
9
x
Tank roof beem
6
x
D/d
2 x 3.143 x 2.00
Hole for fixing of Machiner 3.00

x
x

42.34
43
15.00
1.25
0.75

x
x
x
x
x

0.25
0.25
2.00
1.25
1.50
Total
2.00
x
0.25
1.50
x
1.50
Net
2211 Cft @ Rs

x
x
x
x
x

0.66
0.5
0.75
20
39

=
=
=
=
=
=
=
=
=
P. Cft

930 Cft.
726 Cft.
23 Cft.
281 Cft.
263 Cft.
2223 Cft.
3 Cft.
8 Cft.
2211 Cft.

x
x

0.5
1.25

38.170 x 0.670
1608 Cft @ Rs

20.00
=
317.85 P. Cft

1608 Cft.

290.75
Chapter 6 item No. 6 (a) (3) (c), (2)
ii ( a ) ( ii )Reinforcement cement concrete in slab of rafts / strip foundation ;
base slab of column and retaining walls ; etc, and other structural member ,
complete in all respect. (Type C nominal mix 1: 1-1/2 : 3 )
C.wall

x 3.143 x

Chapter 6 item No. 9


7 Fabrication of mild steel reinforcement for cement concrete, i/c cutting,
bending, laying in position, making joints and fastenings, i/c cost of
binding wire and labour charges for bending of steel reinforcement ( also
includes
removal of rust from2223.0
bars ) @
Slab
3.06 Kgs/Cft
C.wall

1607.5 @

2.42 Kgs/Cft
Total
10693 Kgs @ Rs

Chapter 11 item No. 7 (b)


8 Cement plaster thick 1: 2, upto 20 height.
i 0 to 20'Height
in side
0.25 x 3.143

36.000
Total
566 Cft @ Rs

Chapter 10 item No. 9

=
=

=
11265.95 P%.Kgs

20.00
809.15

=
=
% Sft

6802 Kgs
3890 Kgs
10693 Kgs
Rs. 1,204,668

566 Sft
566 Sft
Rs.

4,577

9 Brick on edge flooring, laid in 1: 6 cement mortar, over a bed of 3/4" thick
cement mortar 1: 6,
1
x 3.143
x 43.34 x 3.00
=
409 Sft
409 Sft @ Rs
6215.50 P.% Sft
Rs.
Chapter 21 item No. 17
10 Providing and fixing C.I.Manhole Cover 24"Dia as per standard drawing,
1.00 x 2.00
=
2 No.
2 No @ Rs
3986.10 Each
Rs.
Chapter 21 item No. 13
11 Providing and fixing 1 x1 x3/16 angle iron step in manhole chamber
i/c carriage and setting the same in work, to correct lines and level.
1
x
2
x
18
=
36 No.
36 No @ Rs
227.45
Each
Rs.
12 Providing and fixing over flow pipe.with C.I. flanged joints ( Medium
quality)
8"
dia G.I.Pipe
20 Rft @ Rs
3000.00 P.Rft.
Rs.
13 Providing and fixing ventshaft 4" dia G.I. pipe 4' long i/c cost of cowel
dome and fixing in top slab of GST, complete in all respect.
2 No @ Rs
4000.00 Each
Rs.
PUMP HOUSE
9.00 x 9.00
Chapter 6 item No. 33 (b) (ii)
14 Providing and laying 2 damp proof course of cement concrete 1:2:4 (using
cement, sand and shingle) with 2 coats of bitumen.
1.00
x 47.000 x 1.125
=
53 Sft @ Rs
4817.35 P.% Sft
Chapter 7 item No. 7 (i) , 8
15 Pacca brick work for ground floor upto 10 height in 1:4 cement sand
mortor above P.L.
Wall
1
x 60.000 x 0.750 x 10.00
=
Out side stair
1 x
1
x 4.000
x 0.625 x 0.625
=
2nd step
1 x
1
x 4.000
x 0.625 x 0.625
=
3rd step
1 x
1
x 4.000
x 4.000 x 0.625
=
4th step
1 x
1
x 4.000
x 5.331 x 0.625
=
5th step
1 x
1
x 4.000
x 4.498 x 0.625
=
6th step
1 x
1
x 4.000
x 3.665 x 0.625
=
7th step
1 x
1
x 4.000
x 0.333 x 0.625
=
Total
=
D/Dection
Door
1
x 4.000
x 7.000
0.750 =
2
x 3.000
x 4.000
0.750 =
2
x 1.500
x 2.000
0.750 =
Lintel over door
1
x 5.000
x 0.500
0.750 =
2
x 4.000
x 0.500
0.750 =
2
x 2.500
x 0.500
0.750 =
Total
=
Net
= 497.69 50
=
447 Cft @ Rs
17112.25 % Cft
ii 10 to 20'height
15944.30 + 1167.95
1st step
1.000 x 60.000 x 0.750 x 0.00
=
Para pit Wall
2.000 x( 9.000 +
9.00
)x 0.750 x 0.875
=
Total
=

25,421

7,972

8,188

60,000

8,000

53 Sft
Rs.

2,553

Rs.

76,492

450 Cft.
2 Cft.
2 Cft.
10 Cft.
13 Cft.
11 Cft.
9 Cft.
1 Cft.
498 Cft.
21 Cft.
18 Cft.
5 Cft.
2 Cft.
3 Cft.
2 Cft.
50 Cft.
447 Cft.

0 Cft.
24 Cft.
24 Cft.

35 Cft @ Rs
16426.10 % Cft
15944.30 + 481.80

Rs.

5,749

Rs.

20,936

Rs.

24,824

Rs.

9,531

Rs.

10,877

Chapter 6 item No. 6 (a), (3),


16 Providing and laying reinforced cement concrete (including prestressed
concrete) using course sand and screened graded and washed agreegate in
required shape and designed icluding forms, moulds, shuttering, lifting,
compacting, curing, rendering and finis
i (a) (I).Reinforced cement concrete in roof slab , beams , columns , lintels ,
girders and other structural members laid in situ or pre cast laid in position ,
or pre stressed members cast in situ , complete in all respect. Type C
(nominal mix 1: 2 : 4 .
Roof
Roof beem
Laintal Door
Window
C.windo
Sun shedDoor
Window
C.windo

1
1
1
2
2
1
2
2

x
x
x
x
x
x
x
x

D/d of Hole

10.500
10.50
5.00
4.00
2.50
5.00
4.00
2.50

x
x
x
x
x
x
x
x

10.500
0.75
0.5
0.5
0.5
0.25
0.25
0.25
Total
1.50
x
1.50
Net
75 Cft @ Rs

x
x
x
x
x
x
x
x

0.5
1.00
0.750
0.750
0.750
1.50
1.50
1.50

0.5

279.15
Chapter 6 item No. 9 (b)
17 Fabrication of mild steel reinforcement for cement concrete, i/c cutting,
bending, laying in position, making joints and fastenings, i/c cost of
binding wire and labour charges for bending of steel reinforcement ( also
includes removal of rust from bars )
Slab

75.4 @

3.06 Kgs/Cft
Total
231 Kgs @ Rs

=
=
=
=
=
=
=
=
=
=
=
P. Cft

=
=
10746.25 P%.Kgs

55 Cft.
8 Cft.
2 Cft.
3 Cft.
2 Cft.
2 Cft.
3 Cft.
2 Cft.
77 Cft.
1 Cft.
75 Cft.

231 Kgs
231 Kgs

Chapter 12 item No. 51


18 Providing, fixing, paneled door of M.S. sheet with forged door leaves of
M.S. sheet 22 SWG fitted in hallow frame chowket 3x 4 made of
M.S. sheet 18 SWG filled with plain cement concrete 1:3:6 etc; complete
with all fittings and harmer painting i/c
1

x
4.0
28 Sft @ Rs

7.0
340.40

=
P. Sft

28 Sft

=
=
=
P. Sft

24 Sft
6 Sft
30 Sft

Chapter 25 item No. 41 (b-iii)


19 P/Fixing steel window with openable glazed panels making beams section
for frame 1 x1x5/8 section for leaves x1x3/8 T-section 1x1
x1/8embedded over a thin layer of putty duly screed with leaves brass
fittings holds fast, duly painted complete
Window
C.Window

1
1

x
x

2.00
2.00

x
x

3.00
1.50
Total
30 Cft @ Rs

x
x

4.00
2.00

362.55
Chapter 12 item No. 54
20 Providing and fixing M. S. flat 1/2x 1/8 grill, i/c 3 /4x 1/8 M.S. flat
frame, in windows of approved design, i/c painting 3 coats, complete in all
respect.
Window

2.00

3.00

4.00

24 Sft

C.Window

2.00

1.50
Total
30 Cft @ Rs

2.00

293.75
Chapter 9 item No. 5
21 Single layer of tiles 9x1 x1 laid over 4 earth and 1 mud plaster
with out bhoosa grouted with cement sand 1:3 on top of RCC roof cement
RCC provided work 34 LBS bitumen coating sand grouted.
1.000

=
=
P. Sft

x
8.250 x 8.250
=
68 Sft @ Rs
4977.80 P.% Sft

Chapter 9 item No. 14


22 Kassi Parnalas in cement sand mortor 1:2 12 out side width finished
smooth with and floating coat of neat cement.
1.00
x 14.38
=
14 Rft @ Rs
56.90 P.Rft
23 Khurras on roof 22x6
1.00
x 1.00
=
1 No @ Rs
620.50 Each
Chapter 9 item No. 16
24 Bottom khurras or brick masonry in cement mortor 1:6,4 x2x4 over 3
cement concrete 1:4:8
1.00
x 1.00
=
1 No @ Rs
274.80 Each
Chapter 10 item No. 10
25 Providing and laying topping of cement concrete '1 : 2 : 4, including
surface finishing and dividing in panels ' 3 inch thick
1.000 x
9.000 x 9.000
=
81 Sft @ Rs
2450.10 P.% Sft
Chapter 11 item No. 9
26 Cement plaster thick 1: 3, upto 20 height.
i 0 to 20'Height
in side
2.000 x( 9.000
+ 9.00 )x 10.00
=
360 Cft @ Rs
1530.50 % Sft
Chapter 11 item No. 18 (a)
27 Cement pointing struck joints on wall upto 20' height ratio 1:2 i/c extra cost
of labour and material for red oxide pigment in cement pointing to match
with the colour of bricks.
Out side. P.House
D/d
Door
Window
C.Window

2.000 x(
1
1
1

x
x
x

Chapter 11 item No. 25 (a)


28 White washing new surface three costs.
in side
2.000 x(
Roof

Chapter 13 item No. 5

10.500

6 Sft
30 Sft

9.00
1.00

)x 10.00
x 9.00

360 Sft
81 Sft
441 Sft

145.50

=
=
=
% Sft

Rs.

621

Rs.

275

Rs.

1,985

Rs.

5,510

Rs.

4,129

Rs.

642

360 Sft

Net
404 Cft @ Rs
809.15

9.00
9.00
Total
441 Cft @ Rs

797

81 Sft

28 Sft
24 Sft
6 Sft
58 Sft
404 Sft

+
x

Rs.

1 No

=
=
=
=
=
1022.15 % Sft
+ 213.00

7.0
4.00
2.00

3,385

1 No

x
x
x

x
x
x

Rs.

14 Rft

462 Sft

4.0
3.00
1.50
Total

8,813

68 Sft

+ 10.500 )x 11.00 =

1
2.00
2.00

Rs.

29 Painting of new surface, preparing surface and painting of doors and


windows any type, three coat.
Door
1
x
2.00
x
4.00
x 7.00
=
Window
2
x
2.00
x
3.00
x 4.00
=
C.Window
2
x
2.00
x
1.50
x 2.00
=
Total
=
60 Cft @ Rs
818.80 % Sft
337.5 +
228.4 +
30 Providing and fixing R.S. joist quality china made, i/c 3 coats of paint and
cost of masonary work, complete in all respect.(8"x 6")
1.00
x 16.00
=
16 Rft @ Rs
882.50 P.Rft
31 Providing and fixing ceilling fan i/c of connections etc, complete in all
respect (Pak, Asia, Royal)
1 Job @ Rs
3360.00 P.Job.

56 Sft
48 Sft
12 Sft
60 Sft

3 No.P.House Rs 11,638,695

491

Rs.

14,120

Rs.

3,360

16 Rft

TOTAL.
SAY,
For

Rs.
228.40

Rs. 3,879,565
Rs. 3,879,600
Say Rs 11,638,700

1
i

ii

iii

iv

SUB WORK NO 7.
ZONE-D
SUB HEAD NO 2.
SLUICE VALVE CHAMBER
6 FEET DIA
Chapter 22 item No. 1 (a)
Excavation of well in dry in ordinary soil upto 20 below ground level, and
disposal of soil with in one chain.
0 to 5' depth
1 x 3.143 x 16.000 x 16.000 x
0.25
x 5.00
=
1006 Cft.
1006 Cft @ Rs
2706.90
%0 Cft
Rs.
2,723
5 to 10'depth
1 x 3.143 x 16.000 x 16.000 x
0.25
x 5.00
=
1006 Cft.
1006 Cft @ Rs
2827.10 %0 Cft
Rs.
2,844
10 to 15'depth
1 x 3.143 x 16.000 x 16.000 x
0.25
x 5.00
=
1006 Cft.
1006 Cft @ Rs
3180.50
%0 Cft
Rs.
3,200
15 to 20'depth
1 x 3.143 x 16.000 x 16.000 x
0.25
x 1.00
=
201 Cft.
201 Cft @ Rs
3650.50
%0 Cft
Rs.
734
Chapter 6 item No. 3 (b)
Cement concrete brick or stone ballast 1- 1/2" to 2" gauge in foundation
and plinth.(1:6:12)
Under Bed
1 x 3.143 x 6.000 x 6.000
x
0.25
x 0.50
=
14 Cft.
Under Apren
1 x 3.143 x 11.250 x
3
x 0.375
=
40 Cft.
Total
=
54 Cft.
54 Cft @ Rs
9733.9
% Cft
Rs.
5,256
Chapter 5 item No. 5 (f)
Cement concrete plain 1 : 2 : 4, i/c placing, compacting , finishing and
curing complete ( i/c screening and washing of stone aggregate). i/c extra
labour for skipping concrete in wells.
Under Bed

x 3.143 x 6.000 x

6.000

x
0.25
14 Cft @ Rs

Chapter 7 item No. 7 (i), 10, 8


4 Pacca brick work 1:3 cement sand mortar other then building
i 1st step up to 10 Ft height
1 x 3.143 x 7.500
x 1.500
2nd step
1 x 3.143 x
7.13
x
1.13
3rd step
1 x 3.143 x 7.125
x 1.125
Total
D/Dection
1 x 3.143 x 7.500
x 0.375
Net
265 Cft @ Rs
15944.30
ii 10 to 20'height
1st step
1 x 3.143 x 7.500
x 1.500
2nd step
1 x 3.143 x 7.125
x 1.125
3rd step
1 x 3.143 x
7.13
x 1.125
Total
D/Dection
1 x 3.143 x
7.500 x
0.375
Net
214 Cft @ Rs

x 0.50
18212.05

x
x
x

10.00
0.00
0.00

10.00

=
=
=
=
=
=

17112.25
+ 1167.95
x
x
x

0.00
5.50
3.00

0.00

17112.25

14 Cft.
% Cft

Rs.

2,550

Rs.

45,347

Rs.

36,620

354 Cft.
0 Cft.
0 Cft.
354 Cft.
88 Cft.
265 Cft.
% Cft

=
=
=
=
=
=

0 Cft.
139 Cft.
76 Cft.
214 Cft.
0 Cft.
214 Cft.
% Cft

6
i

15944.30 + 1167.95
Chapter 6 item No. 34 (b), (iii)
Providing and laying thick vertical damp proof course with 1:2 cement
sand plaster and 2 coats of bitumen .
ist step
1
x 3.143
x 9.000 x 10.00
2nd step
1
x 3.143
x 8.250 x 5.50
Total
425 Cft @ Rs
3060.50
Chapter 11 item No. 7 (b)
Cement plaster thick 1: 2, upto 20 height.
0 to 20'Height
in side
1
x 3.143
x
6
x 18.00
Top
1
x 3.143
x 7.125 x 1.125
Total
365 Cft @ Rs
1530.50
Chapter 11 item No. 18 (a)
Cement pointing struck joints on wall upto 20' height ratio 1:2 i/c extra cost
of labour and material for red oxide pigment in cement pointing to match
with the colour of bricks.
1

3.143

x
8.25
x 3.00
78 Cft @ Rs
1556.10
1343.10 + 213.00

Chapter 21 item No. 13


8 Providing and fixing 1 x1 x3/16 angle iron step in manhole chamber
i/c carriage and setting the same in work, to correct lines and level.
1
x
2
x
18
36 No @ Rs
227.45
Chapter 10 item No. 9
9 Brick on edge flooring, laid in 1: 6 cement mortar, over a bed of 3/4" thick
cement mortar 1: 6,
1
x 3.143
x 11.250 x 3.00
106 Sft @ Rs
6215.50
10 Providing and Laying A.C. Pipe of BSS.B. Class working presure
18" Dia
40 Rft @ Rs
2560.00
11 Providing and Fixing Sluci Valve for A.C. Pipe of BSS.B. Class working
presure
1
x
2
18" Dia
1 No @ Rs
109893.85

=
=
=

283 Sft
143 Sft
425 Sft
% Sft

Rs.

13,007

Rs.

5,586

Rs.

1,214

Rs.

8,188

P.% Sft

Rs.

6,588

P.Rft.

Rs.

102,400

Each
TOTAL.
SAY,

Rs.
Rs.
Rs.

109,894
346,151
346,200

=
=
=

339 Sft
25 Sft
365 Sft
% Sft

78 Sft
% Sft

36 No.
Each

106 Sft

SUB WORK NO 7.
ZONE-D
SUB HEAD NO 3
WASH OUT CHAMBER
6 FEET DIA
Chapter 22 item No. 1 (a)
1 Excavation of well in dry in ordinary soil upto 20 below ground level, and
disposal of soil with in one chain.
i 0 to 5' depth
1 x 3.143 x 16.000 x 16.000 x
0.25
x 5.00
=
1006 Cft.
1006 Cft @ Rs
2706.90
%0 Cft
Rs.
2,723
ii 5 to 10'depth
1 x 3.143 x 16.000 x 16.000 x
0.25
x 5.00
=
1006 Cft.
1006 Cft @ Rs
2827.10 %0 Cft
Rs.
2,844

iii 10 to 15'depth
1
iv 15 to 20'depth
1

x 3.143 x 16.000 x

x 3.143 x 16.000 x

16.000 x
0.25
1006 Cft @ Rs

x 5.00
3180.50

16.000 x
0.25
805 Cft @ Rs

x 4.00
3650.50

Chapter 6 item No. 3 (b)


2 Cement concrete brick or stone ballast 1- 1/2" to 2" gauge in foundation
and plinth.(1:6:12)
Under Bed
1 x 3.143 x 6.000 x 6.000
x
0.25
x 0.50
Under Apren
1 x 3.143 x 11.250 x
3
x 0.375
Total
54 Cft @ Rs
9733.9
Chapter 6 item No. 5 (f)
3 Cement concrete plain 1 : 2 : 4, i/c placing, compacting , finishing and
curing complete ( i/c screening and washing of stone aggregate). i/c extra
labour for skipping concrete in wells.

1006 Cft.
%0 Cft
Rs.

3,200

805 Cft.
%0 Cft

14 Cft.

=
=

40 Cft.
54 Cft.
% Cft

Rs.

2,939

Rs.

5,256

Rs.

2,550

Rs.

46,622

Rs.

45,039

Rs.

6,868

Rs.

15,609

Under Bed
i

4
i

ii

iii

x 3.143 x 6.000 x

6.000

x
0.25
14 Cft @ Rs

x 0.50
18212.05

Chapter 7 item No. 7 (i), 10 , 8


Pacca brick work 1:3 cement sand mortar other then building
1st step up to 10 Ft height
1 x 3.143 x 7.500
x 1.500 x 10.00
Total
D/Dection
1 x 3.143 x 7.500
x 0.375 x 10.00
Net
265 Cft @ Rs
17593.25
15944.30 + 1167.95
10 to 20'height
1st step
1 x 3.143 x 7.500
x 1.500 x 3.00
2nd step
1 x 3.143 x 7.125
x
1.13
x 5.50
3rd step
1 x 3.143 x
7.13
x 1.125 x 1.50
Total
D/Dection
1 x 3.143 x
7.500 x
0.375 x
3.00
Net
256 Cft @ Rs
17593.25
15944.3 + 1167.95 +
481
20 to 30'height
3rd step
1 x 3.143 x
7.13
x 1.125 x 1.50
Total
38
Cft @ Rs 18074.25
15944.3 + 1167.95 +
481 +
Chapter 6 item No. 34 (b), (iii)
Providing and laying thick vertical damp proof course with 1:2 cement
sand plaster and 2 coats of bitumen .
ist step
1
x 3.143
x 9.000 x 13.00
2nd step
1
x 3.143
x 8.250 x 5.50
Total
510 Cft @ Rs
3060.50
Chapter 11 item No. 7 (b)

14 Cft.
% Cft

=
=
=
=

354 Cft.
354 Cft.
88 Cft.
265 Cft.

% Cft
+ 481
=
=
=
=
=
=

106 Cft.
139 Cft.
38 Cft.
282 Cft.
27 Cft.
256 Cft.
% Cft

=
=

38 Cft.
38 Cft.
% Cft
481

=
=
=

368 Sft
143 Sft
510 Sft
% Sft

6 Cement plaster thick 1: 2, upto 20 height.


i 0 to 20'Height
in side
1
x 3.143
Top
1
x 3.143

6
7.125
Total
402 Cft @ Rs

ii 20 to 30'Height
in side

3.143

x
x

x
x

20.00
1.125

=
=
=

1530.50

x
6
x 1.00
19 Cft @ Rs
1630.50
1530.50 + 100.00

377 Sft
25 Sft
402 Sft
% Sft

Rs.

6,153

Rs.

310

Rs.

1,214

19 Sft
% Sft

Chapter 9 item No. 18 (a)


7 Cement pointing struck joints on wall upto 20' height ratio 1:2 i/c extra cost
of labour and material for red oxide pigment in cement pointing to match
with the colour of bricks.
3rd step

3.143

x
8.25
x 3.00
78 Cft @ Rs
1556.10
1343.10 + 213.00

78 Sft
% Sft

Chapter 21 item No. 13


8 Providing and fixing 1 x1 x3/16 angle iron step in manhole chamber
i/c carriage and setting the same in work, to correct lines and level.
1
x
2
x
21
42 No @ Rs
227.45
Chapter 10 item No. 9
9 Brick on edge flooring, laid in 1: 6 cement mortar, over a bed of 3/4" thick
cement mortar 1: 6,
1
x 3.143
x 11.250 x 3.00
106 Sft @ Rs
6215.50
10 Providing and Laying A.C. Pipe of BSS.B. Class working presure
6 Dia
30 Rft @ Rs
2560.00
11 Providing and Fixing Sluci Valve for A.C. Pipe of BSS.B. Class working
presure
1
x
2
6 Dia
2 No @ Rs
109893.85

(Carried Over to Summery of Cost)

42 No.
Each

Rs.

9,553

P.% Sft

Rs.

6,588

P.Rft.

Rs.

76,800

Rs.
Rs.
Rs.

219,788
454,056
454,100
12,439,000

106 Sft

2 No.
Each
TOTAL.
SAY,

ET DIA

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

////-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

//-

///-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

/-

//-

///-

Sr. No

Type of Road

Name of Line

TST

Pavement

Ahmadpur Lamma

1800

Taj Chowk

300

Charian Wala Chowk

150

Ghosia Chowk To Hospital

700

GST No.3 To Zikria Chowk

1100

E-F

3000

Tibba Zahir Peer, Tibba Balochan,


Tibba Qadirabad, Chak No 169/P

12000

Total

16950

Brick Pavement

12000

2100

12000

ROUGH COST ESTIMATE WATER SUPPLY SCHEME SADIQABAD


DISTT: RAHIMYARKHAN "Length statement"

Line

500 mm 450 mm 400 mm


(20") dia. (18") dia. (16") dia.
HDPE
HDPE
HDPE

355 mm
(14'')
12" dia. 10" dia. 8" dia.
dia.
PVC
PVC
PVC
HDPE

6" dia.
PVC

4" dia. 3" dia.


PVC
PVC

Yard Piping

1000

500

1000

1000

500

500

500

A-IPS
IPS-B
B-C
C-D
D- GST No.5

33000
-

22300
-

6800
600
4000

for connections

100

100

GST No.3 - E
E-F
F - p2
F - GST No.10
E - GST No.12
GST No.11 - OHR
GST No.10 - H
GST No.11 - G
I-J
J-K
J-L
M-N
O-P
P-Q
E1-E2
E1-E2
Total

34000

22800

8220
2266
6500
29386

1000

2624
2296
5420

500

7000
7500

500 for connection


500
100
100

HYDRAULIC STATEMENT FOR WATER SUPPLY SCHEME


SADIQABAD DISTRICT RAHIMYARKHAN.
AREA SERVED
S.
NO

Name of Line

Length
In Feet Own Oth Total
er

Projected Population
2033 175 Persons
/Acre

175

50

18

Discharge
Dia of Pipe
Head Loss
Terminal Head
Max:
Velocit
Discharge
Actual
Water
IGPH @
Value
y, Feet Loss Loss I/c
Conp: @. for rising
18
In
In
Upper Lower
of C.
per
in %0 10%
50 GPCD main1.5 & Working Cusec In mm. Inches
End
End
Second
distributio
Feet
for
Hours.
n system
specials
2.25
8
9
10
11
12
13
14
15
16
17
18
19

Class of
pipe

20

RISING MAIN
1 TW1-TW2

500

1.00

200

130

2.96

4.48

2.47 172.17 169.71 B Class

2 TW2-TW3

500

2.00

250

10

130

3.78

5.45

3.00 169.71 166.71 B Class

3 TW3-TW4

500

3.00

300

12

130

3.94

4.75

2.61 166.71 164.10 B Class

4 TW4-TW5

500

4.00

355

14

130

3.75

3.56

1.96 164.10 162.14 B Class

5 TW5-TW6

500

5.00

355

14

130

4.69

5.38

2.96 162.14 159.18 B Class

6 TW6-TW7

500

6.00

400

16

130

4.43

4.22

2.32 159.18 156.86 B Class

7 TW7-TW8

500

7.00

400

16

130

5.17

5.61

3.09 156.86 153.77 B Class

8 TW8-TW9

500

8.00

450

18

130

4.67

4.05

2.23 153.77 151.55 B Class

9 TW9-TW10

500

9.00

500

20

130

4.26

3.01

1.66 151.55 149.89 B Class

10 TW10-A

500

10.00

500

20

130

4.73

3.66

2.01 149.89 147.88 B Class

11 A-IPS

33000

600

600 104751 5237552

7856328 436463 10.00

500

20

130

4.73

3.66 132.9 147.88

15.00 B Class

12 IPS-B,New Line 22300

600

600 104751 5237552

7856328 436463 10.00

450

18

130

5.84

6.11 150.0 295.63 145.63 B Class

13 B-C

6800

600

600 104751 5237552

7856328 436463 10.00

400

16

130

7.39 10.85 81.17 145.63

64.46 B Class

14 C-D

600

0 600

600 104751 5237552

7856328 436463 10.00

400

16

130

7.39 10.85

7.16

64.46

57.30 B Class

15 D-GST6

3500 198

198

34568 1728392

2592588 144033

6.40

400

16

130

4.73

4.75 18.31

38.31

20.00 B Class

16 D-GST5

4000 202

202

35266 1763309

2644964 146942

6.53

400

16

130

4.83

4.93 21.71

41.71

20.00 B Class

Hydraulic statement Sadiqabad

HYDRAULIC STATEMENT FOR WATER SUPPLY SCHEME


SADIQABAD DISTRICT RAHIMYARKHAN.
AREA SERVED
S.
NO

Name of Line

17 D-GST4

Length
In Feet Own Oth Total
er

Projected Population
2033 175 Persons
/Acre

175

50

18

Discharge
Dia of Pipe
Head Loss
Terminal Head
Max:
Velocit
Discharge
Actual
Water
IGPH @
Value
y, Feet Loss Loss I/c
Conp: @. for rising
18
In
In
Upper Lower
of C.
per
in %0 10%
50 GPCD main1.5 & Working Cusec In mm. Inches
End
End
Second
distributio
Feet
for
Hours.
n system
specials
2.25
8
9
10
11
12
13
14
15
16
17
18
19

200

34917 1745851

2618776 145488

6.47

400

16

130

Distribution System
18 GST3-E
8200 377

377

65819 3290929

4936393 274244 12.19

400

16

130

9.0 15.65 141.2 245.15 103.99 B Class

19 E-F

2268 285

285

49757 2487837

3731756 207320

9.21

400

16

130

6.8

20 F-GST 11

2624 180

180

31425 1571266

2356898 130939

5.82

300

12

130

7.65 16.18 46.70

66.70

20.00 B Class

21 F-GST 10

2296 105

105

18331

916572

1374857

76381

3.39

300

12

130

4.46

5.97 15.08

35.08

20.00 B Class

92

92

16062

803091

1204637

66924

2.97

300

12

130

3.91

4.67 60.72

80.72

20.00 B Class

5000 232

232

3037780 168766

7.50

400

16

130

5.54

6.37 35.06 135.06 100.00 B Class

23 GST 11-OHR

11808

40504 2025187

Hydraulic statement Sadiqabad

4.84 37.30

57.30

20

7000 200

22 E-GST 12

4.78

Class of
pipe

9.33 23.27 103.99

20.00 B Class

80.72 B Class

HYDRAULIC STATEMENT FOR WATER SUPPLY SCHEME


SADIQABAD DISTRICT RAHIMYARKHAN.
AREA SERVED
S.
NO

Name of Line

Length
In Feet Own Oth Total
er

Projected Population
2033 175 Persons
/Acre

175

50

18

Discharge
Dia of Pipe
Head Loss
Terminal Head
Max:
Velocit
Discharge
Actual
Water
IGPH @
Value
y, Feet Loss Loss I/c
Conp: @. for rising
18
In
In
Upper Lower
of C.
per
in %0 10%
50 GPCD main1.5 & Working Cusec In mm. Inches
End
End
Second
distributio
Feet
for
Hours.
n system
specials
2.25
8
9
10
11
12
13
14
15
16
17
18
19

Class of
pipe

20

DISTRIBUTION SYSTEM
ZONE -A
1 A1-A

500 4.03

4.03 703.58

35179

79153

4397

0.20

75

130

4.11 25.96 14.28

44.28

30.00 B Class

2 A2-A1

750 5.64

4 9.67 1688.2

84412

189927

10551

0.47

150

130

2.46

3.70

47.98

44.28 B Class

3 A2-A3

1300 ###

16 2793.4

139668

314253

17459

0.78

150

130

4.08 11.38 16.27

46.27

30.00 B Class

4 A9-A2

700 9.96

26 35.63 6220.5

311023

699802

38878

1.73

250

10

130

3.27

4.16

3.20

51.18

47.98 B Class

5 A7-A1

1200 13.3

13.25 2313.3

115663

260241

14458

0.64

150

130

3.38

8.03 10.60

40.60

30.00 B Class

6 A8-A7

1450 25.2

13 38.44

6711

335552

754993

41944

1.86

250

10

130

3.53

4.79

7.63

48.23

40.60 B Class

7 A9-A8

1900 24.9

38 63.36

11062

553085

1244442

69136

3.07

300

12

130

4.04

4.96 10.38

58.61

48.23 B Class

8 A5-A9

650 11.8

99 110.8

19344

967201

2176203 120900

5.37

350

14

130

5.19

6.59

4.71

63.32

58.61 B Class

9 A4-A3

1200 8.13

8.13 1419.4

70969

159680

8871

0.39

100

130

4.66 23.43 30.93

60.93

30.00 B Class

10 A5-A4

1050 12.1 8.1 20.2 3526.6

176331

396745

22041

0.98

200

130

2.90

4.31

4.98

65.91

60.93 B Class

4.48

11 A6-A5

100

0 131

131

22871 1143532

2572947 142942

6.35

350

14

130

6.13

8.98

0.99

66.90

65.91 B Class

12 OHR-A6

600

0 131

131

22871 1143532

2572947 142942

6.35

350

14

130

6.13

8.98

5.93

72.83

66.90 B Class

13 GST-OHR

200

0 131

131

22871 1143532

2572947 142942

6.35

350

14

130

6.13

8.98

1.98

71.98

70.00 B Class

ZONE-B

Hydraulic statement Sadiqabad

HYDRAULIC STATEMENT FOR WATER SUPPLY SCHEME


SADIQABAD DISTRICT RAHIMYARKHAN.
AREA SERVED
S.
NO

Name of Line

Length
In Feet Own Oth Total
er

1 B1-B

1400 11.7

2 B2-B1

1700 25.6

3 B2-B10

1400 14.7

4 B3-B2

1200 11.3

5 B5-B

Projected Population
2033 175 Persons
/Acre

175

11.68 2039.2

50

18

Discharge
Dia of Pipe
Head Loss
Terminal Head
Max:
Velocit
Discharge
Actual
Water
IGPH @
Value
y, Feet Loss Loss I/c
Conp: @. for rising
18
In
In
Upper Lower
of C.
per
in %0 10%
50 GPCD main1.5 & Working Cusec In mm. Inches
End
End
Second
distributio
Feet
for
Hours.
n system
specials
2.25
8
9
10
11
12
13
14
15
16
17
18
19

Class of
pipe

20

101958

229405

12745

0.57

150

130

2.98

6.36

9.79

39.79

30.00 B Class

6505

325252

731817

40656

1.81

250

10

130

3.42

4.52

8.45

48.24

39.79 B Class

14.69 2564.7

128233

288524

16029

0.71

150

130

3.74

9.72 14.96

44.96

30.00 B Class

11039

551951

1241889

68994

3.07

250

10

130

5.80 12.02 15.86

64.10

48.24 B Class

300 1.31

1.31 228.71

11435

25729

1429

0.06

75

130

1.34

1.07

31.07

30.00 B Class

6 B5-B6

900 7.35

7.35 1283.2

64160

144360

8020

0.36

100

130

4.21 19.44 19.25

49.25

30.00 B Class

7 B4-B5

500 5.90 8.7 14.56

2542

127098

285970

15887

0.71

150

130

3.71

5.26

54.50

49.25 B Class

8 B4-B1

800 8.79

8.79 1534.6

76730

172643

9591

0.43

100

130

5.04 27.07 23.82

53.82

30.00 B Class

9 B7-B6

500 6.16

6.16 1075.4

53772

120987

6722

0.30

100

130

3.53 14.02

7.71

37.71

30.00 B Class

10 B4-B7

800 5.12 6.2 11.28 1969.3

98466

221548

12308

0.55

150

130

2.87

5.96

5.25

42.96

37.71 B Class

12 37.26
52 63.23

3.25
9.56

11 B3-B4

1000 7.87

35 42.5 7419.9

370993

834735

46374

2.06

250

10

130

3.90

5.76

6.34

60.84

54.50 B Class

12 B8-B7

1200 8.13 5.8 13.9 2426.7

121337

273007

15167

0.67

150

130

3.54

8.77 11.58

41.58

30.00 B Class

13 B9-B8

300 3.67

28 32.12 5607.7

280384

630863

35048

1.56

200

130

4.60 10.18

3.36

44.94

41.58 B Class

14 B18-B19

1300 11.3

11.29 1971.1

98553

221745

12319

0.55

150

130

2.88

5.97

8.54

38.54

30.00 B Class

15 B16-B18

1200 16.9

4925

246252

554068

30782

1.37

200

130

4.04

8.00 10.57

49.10

38.54 B Class

16 B17-B19

1200 5.25

5.25 916.57

45829

103114

5729

0.25

100

130

3.01 10.43 13.77

43.77

30.00 B Class

17 B16-B17

1200 17.3 5.3 22.57 3940.4

197019

443293

24627

1.09

200

130

3.24

5.30

6.99

50.76

43.77 B Class

18 B12-B16

1350 12.6

553173

1244639

69147

3.07

300

12

130

4.04

4.97

7.37

58.14

50.76 B Class

11 28.21

51 63.37

11063

Hydraulic statement Sadiqabad

HYDRAULIC STATEMENT FOR WATER SUPPLY SCHEME


SADIQABAD DISTRICT RAHIMYARKHAN.
AREA SERVED
S.
NO

Name of Line

Length
In Feet Own Oth Total
er

Projected Population
2033 175 Persons
/Acre

175

50

18

Discharge
Dia of Pipe
Head Loss
Terminal Head
Max:
Velocit
Discharge
Actual
Water
IGPH @
Value
y, Feet Loss Loss I/c
Conp: @. for rising
18
In
In
Upper Lower
of C.
per
in %0 10%
50 GPCD main1.5 & Working Cusec In mm. Inches
End
End
Second
distributio
Feet
for
Hours.
n system
specials
2.25
8
9
10
11
12
13
14
15
16
17
18
19

Class of
pipe

20

19 B15-B17

2100 27.5

27.5 4801.1

240054

540123

30007

1.33

200

130

3.94

7.64 17.64

47.64

30.00 B Class

20 B14-B15

700 9.58

28 37.08 6473.6

323681

728282

40460

1.80

200

130

5.32 13.27 10.22

57.86

47.64 B Class

21 B14-B13

1200 5.77

5.77 1007.4

50368

113328

6296

0.28

100

130

3.31 12.42 16.40

46.40

30.00 B Class

Hydraulic statement Sadiqabad

HYDRAULIC STATEMENT FOR WATER SUPPLY SCHEME


SADIQABAD DISTRICT RAHIMYARKHAN.
AREA SERVED
S.
NO

Name of Line

Length
In Feet Own Oth Total
er

Projected Population
2033 175 Persons
/Acre

175

50

18

Discharge
Dia of Pipe
Head Loss
Terminal Head
Max:
Velocit
Discharge
Actual
Water
IGPH @
Value
y, Feet Loss Loss I/c
Conp: @. for rising
18
In
In
Upper Lower
of C.
per
in %0 10%
50 GPCD main1.5 & Working Cusec In mm. Inches
End
End
Second
distributio
Feet
for
Hours.
n system
specials
2.25
8
9
10
11
12
13
14
15
16
17
18
19

20

22 B12-B14

825 10.4

43 53.21 9289.7

464484

1045088

58060

2.58

250

10

130

4.88

7.93

65.78

57.86 B Class

23 B12-B13

1100 7.08

7.08 1236.1

61803

139057

7725

0.34

100

130

4.06 18.14 21.95

51.95

30.00 B Class

2485349 138075

6.14

350

14

130

5.92

8.43

2.32

68.10

65.78 B Class

27912

1.24

200

130

3.67

6.68 16.16

46.16

30.00 B Class

24 B11-B12
25 B11-B10

250 2.88 124


2200 25.6

127

22092 1104600

25.58 4465.9

223294

502412

8.73

Class of
pipe

26 B9-B11

600 3.28 152 155.4

27131 1356526

3052183 169566

7.54

450

18

130

4.40

3.62

2.39

70.49

68.10 B Class

27 B3-B9

300 2.75 188

190

33218 1660915

3737059 207614

9.23

450

18

130

5.39

5.27

1.74

72.23

70.49 B Class

28 OHR-B3

250

0 296

296

51677 2583859

5813683 322982 14.35

600

24

130

4.71

2.94

0.81

73.04

72.23 B Class

29 GST-OHR

300

0 296

296

51677 2583859

5813683 322982 14.35

600

24

130

4.71

2.94

0.97

70.97

70.00 B Class

ZONE-C
1 C2-C3

750 21.9

21.86 3816.4

190821

429348

23853

1.06

150

130

5.57 20.27 16.72

46.72

30.00 B Class

2 C2-C1

1000 10.6

10.58 1847.1

92356

207800

11544

0.51

150

130

2.70

5.29

5.82

35.82

30.00 B Class

3 C6-C2

600 24.8

32 57.23 9991.5

499575

1124044

62447

2.78

250

10

130

5.25

9.99

6.60

53.32

46.72 B Class

4 C-C1

500 19.1

19.07 3329.3

166467

374550

20808

0.92

150

130

4.86 15.75

8.66

38.66

30.00 B Class

5 C6-C

1000 16.9

19 35.94 6274.6

313729

705891

39216

1.74

200

130

5.15 12.53 13.78

52.44

38.66 B Class

6 C7-C6

600 25.5

2331562 129531

5.76

350

14

130

5.56

58.26

53.32 B Class

93

119

20725 1036250

Hydraulic statement Sadiqabad

7.49

4.94

HYDRAULIC STATEMENT FOR WATER SUPPLY SCHEME


SADIQABAD DISTRICT RAHIMYARKHAN.
AREA SERVED
S.
NO

Name of Line

Length
In Feet Own Oth Total
er

Projected Population
2033 175 Persons
/Acre

175

50

18

Discharge
Dia of Pipe
Head Loss
Terminal Head
Max:
Velocit
Discharge
Actual
Water
IGPH @
Value
y, Feet Loss Loss I/c
Conp: @. for rising
18
In
In
Upper Lower
of C.
per
in %0 10%
50 GPCD main1.5 & Working Cusec In mm. Inches
End
End
Second
distributio
Feet
for
Hours.
n system
specials
2.25
8
9
10
11
12
13
14
15
16
17
18
19

Class of
pipe

20

7 C11-C7

800 ### 119

132

22989 1149468

2586303 143684

6.39

350

14

130

6.16

9.07

7.98

66.24

58.26 B Class

8 C10-C11

200

132

23112 1155579

2600052 144447

6.42

400

16

130

4.74

4.78

1.05

67.29

66.24 B Class

13247

0.59

150

130

3.09

6.83

9.01

39.01

30.00 B Class

3087733 171541

7.62

450

18

130

4.45

3.70

5.80

73.10

67.29 B Class

0.7 132

9 C10-C20

1200 12.1

10 C12-C10

1425 12.7 145

11 C9-C20

1550 ###

14 2444.2

122210

274971

15276

0.68

150

130

3.57

8.89 15.16

45.16

30.00 B Class

12 C12-C9

1300 11.2

14 25.2 4399.5

219977

494949

27497

1.22

150

130

6.42 26.37 37.71

82.87

45.16 B Class

3582682 199038

8.85

450

18

130

5.17

4.87

2.41

85.28

82.87 B Class

13 C21-C12

450

12.14 2119.5

0 182

157

182

105973

27447 1372326

31846 1592303

238440

14 C4-C3

1800

24

23.98 4186.5

209327

470987

26166

1.16

200

130

3.44

5.93 11.73

41.73

30.00 B Class

15 C8-C4

1150 11.2

24 35.13 6133.2

306659

689982

38332

1.70

200

130

5.04 12.01 15.19

56.93

41.73 B Class

16 C8-C7

1150

12.99 2267.9

113393

255134

14174

0.63

150

130

3.31

7.74

9.79

39.79

30.00 B Class

10346

517296

1163915

64662

2.87

250

10

130

5.44 10.66

8.79

65.72

56.93 B Class

3.94 687.87

34393

77385

4299

0.19

75

130

4.02 24.90 24.65

54.65

30.00 B Class

13

17 C14-C8

750 11.1

18 C14-C11

900 3.94

48 59.26

19 C13-C14

1200

19

63 82.24

14358

717894

1615261

89737

3.99

300

12

130

5.24

8.04 10.62

76.34

65.72 B Class

20 C17-C18

1050

26 7.1 33.07 5773.5

288676

649522

36085

1.60

200

130

4.74 10.74 12.41

42.41

30.00 B Class

21 C16-C17

1200 16.9

33 49.99 8727.5

436375

981845

54547

2.42

250

10

130

4.59

7.78 10.27

52.68

42.41 B Class

22 C15-C16

1750 34.6

50 84.54

14759

737971

1660435

92246

4.10

300

12

130

5.39

8.46 16.29

68.97

52.68 B Class

23 C15-C18

2500 13.8

13.77

2404

120202

270454

15025

0.67

150

130

3.51

8.62 23.71

53.71

30.00 B Class

24 C13-C15

1250 20.5

2332544 129586

5.76

350

14

130

5.56

7.49 10.30

86.64

76.34 B Class

98

119

20734 1036686

Hydraulic statement Sadiqabad

HYDRAULIC STATEMENT FOR WATER SUPPLY SCHEME


SADIQABAD DISTRICT RAHIMYARKHAN.
AREA SERVED
S.
NO

Name of Line

25 C21-C13
26 GST-C21

Length
In Feet Own Oth Total
er

300 4.59 201


2400

0 388

Projected Population
2033 175 Persons
/Acre

175

50

18

Discharge
Dia of Pipe
Head Loss
Terminal Head
Max:
Velocit
Discharge
Actual
Water
IGPH @
Value
y, Feet Loss Loss I/c
Conp: @. for rising
18
In
In
Upper Lower
of C.
per
in %0 10%
50 GPCD main1.5 & Working Cusec In mm. Inches
End
End
Second
distributio
Feet
for
Hours.
n system
specials
2.25
8
9
10
11
12
13
14
15
16
17
18
19

6.08

2.01

20

206

35893 1794647

4037956 224331

9.97

450

18

130

88.65

86.64 B Class

388

67739 3386950

7620638 423369 18.82

450

18

130 10.99 19.69 51.99 140.63

88.65 B Class

Hydraulic statement Sadiqabad

5.82

Class of
pipe

HYDRAULIC STATEMENT FOR WATER SUPPLY SCHEME


SADIQABAD DISTRICT RAHIMYARKHAN.
AREA SERVED
S.
NO

Name of Line

Length
In Feet Own Oth Total
er

Projected Population
2033 175 Persons
/Acre

175

50

18

Discharge
Dia of Pipe
Head Loss
Terminal Head
Max:
Velocit
Discharge
Actual
Water
IGPH @
Value
y, Feet Loss Loss I/c
Conp: @. for rising
18
In
In
Upper Lower
of C.
per
in %0 10%
50 GPCD main1.5 & Working Cusec In mm. Inches
End
End
Second
distributio
Feet
for
Hours.
n system
specials
2.25
8
9
10
11
12
13
14
15
16
17
18
19

Class of
pipe

20

ZONE-D
1 D10-D

1150 8.92

8.92 1557.3

77865

175196

9733

0.43

150

130

2.27

3.86

4.88

34.88

30.00 B Class

2 D10-D22

700 9.31

9.31 1625.4

81269

182856

10159

0.45

150

130

2.37

4.18

3.22

33.22

30.00 B Class

3 D8-D10

500 2.36

18 20.59 3594.7

179735

404404

22467

1.00

200

130

2.95

4.47

2.46

37.34

34.88 B Class

4 D8-D9

800 8.87

8.87 1548.6

77428

174214

9679

0.43

150

130

2.26

3.82

3.36

33.36

30.00 B Class

5 D7-D8

900 8.13

29 37.59 6562.7

328133

738298

41017

1.82

250

10

130

3.45

4.59

4.55

41.89

37.34 B Class

6 D7-D22

1700 17.7

17.71 3091.9

154595

347839

19324

0.86

200

130

2.54

3.38

6.33

36.33

30.00 B Class

7 D6-D7

800 7.21

10913

545666

1227748

68208

3.03

300

12

130

3.98

4.84

4.26

46.15

41.89 B Class

8 D21-D

1350 10.3

10.3 1798.2

89911

202300

11239

0.50

150

130

2.62

5.04

7.48

37.48

30.00 B Class

9 D1-D21

1200 8.32

10 18.62 3250.8

162539

365712

20317

0.90

200

130

2.67

3.71

4.90

42.38

37.48 B Class

19 26.62 4647.5

232373

522839

29047

1.29

200

130

3.82

7.19

6.25

48.63

42.38 B Class

11 D5-D9

1250 ###

15 2618.8

130939

294612

16367

0.73

150

130

3.82 10.10 13.89

43.89

30.00 B Class

12 D6-D5

250 3.75

42 45.37 7920.9

396046

891104

49506

2.20

200

130

6.50 19.28

5.30

53.93

48.63 B Class

2595338 144185

6.41

350

14

130

6.19

9.13 18.58

72.51

53.93 B Class

10 D5-D1

13 D4-D6

790

55 62.51

1850 24.3 108

132

23070 1153484

14 D12-D11

900 8.26

8.26 1442.1

72104

162233

9013

0.40

100

130

4.74 24.13 23.89

53.89

30.00 B Class

15 D12-D17

400 8.14

8.14 1421.1

71056

159876

8882

0.39

100

130

4.67 23.48 10.33

40.33

30.00 B Class

16 D15-D12

1200 7.61

16 24.01 4191.8

209589

471576

26199

1.16

200

130

3.44

61.73

53.89 B Class

Hydraulic statement Sadiqabad

5.94

7.84

HYDRAULIC STATEMENT FOR WATER SUPPLY SCHEME


SADIQABAD DISTRICT RAHIMYARKHAN.
AREA SERVED
S.
NO

Name of Line

Length
In Feet Own Oth Total
er

Projected Population
2033 175 Persons
/Acre

175

50

18

Discharge
Dia of Pipe
Head Loss
Terminal Head
Max:
Velocit
Discharge
Actual
Water
IGPH @
Value
y, Feet Loss Loss I/c
Conp: @. for rising
18
In
In
Upper Lower
of C.
per
in %0 10%
50 GPCD main1.5 & Working Cusec In mm. Inches
End
End
Second
distributio
Feet
for
Hours.
n system
specials
2.25
8
9
10
11
12
13
14
15
16
17
18
19

Class of
pipe

20

17 D16-D17

1200 6.03

6.03 1052.7

52637

118434

6580

0.29

100

130

3.46 13.48 17.79

47.79

30.00 B Class

18 D15-D16

450 4.72

6 10.75 1876.8

93839

211139

11730

0.52

150

130

2.74

5.45

2.70

50.49

47.79 B Class

19 D14-D15

700 8.79

35 43.55 7603.2

380159

855358

47520

2.11

250

10

130

4.00

6.03

4.64

66.37

61.73 B Class

20 D13-D12

700 8.13

8.13 1419.4

70969

159680

8871

0.39

100

130

4.66 23.43 18.04

48.04

30.00 B Class

3778

188901

425027

23613

1.05

200

130

3.10

4.90

6.20

54.24

48.04 B Class

21 D14-D13

1150 13.5 8.1 21.64

22 D20-D14

200 0.39

65 65.58

11449

572464

1288045

71558

3.18

250

10

130

6.02 12.86

2.83

69.20

66.37 B Class

23 D20-D19

550 9.05

9.05

1580

79000

177749

9875

0.44

100

130

5.19 28.57 17.28

47.28

30.00 B Class

75 99.63

17394

869696

1956815 108712

4.83

350

14

130

4.66

6.55

75.75

69.20 B Class

24 D3-D20

1100

25

5.41

25 D18-D19

1600 16.1

16.13 2816.1

140803

316806

17600

0.78

150

130

4.11 11.55 20.33

50.33

30.00 B Class

26 D3-D18

830 6.03

16 22.16 3868.8

193440

435241

24180

1.07

150

130

5.65 20.79 18.98

69.31

50.33 B Class

27 D2-D1

1200 8.26

8.26 1442.1

72104

162233

9013

0.40

100

130

4.74 24.13 31.85

61.85

30.00 B Class

28 D3-D2

1000 19.8 8.3 28.07 4900.6

245030

551318

30629

1.36

200

130

4.02

7.93

8.72

70.57

61.85 B Class

29 D4-D3

100

0 150

150

26163 1308166

2943373 163521

7.27

400

16

130

5.37

6.01

0.66

76.41

75.75 B Class

30 OHR-D4

150

0 282

282

49233 2461649

5538711 307706 13.68

600

24

130

4.49

2.69

0.44

76.85

76.41 B Class

31 GST-OHR

150

0 282

282

49233 2461649

5538711 307706 13.68

600

24

130

4.49

2.69

0.44

70.44

70.00 B Class

Hydraulic statement Sadiqabad

ENT FOR WATER SUPPLY SCHEME


ISTRICT RAHIMYARKHAN.

REMARKS

21

Yard Piping
Yard Piping
Yard Piping
Yard Piping
Yard Piping
Yard Piping
Yard Piping
Yard Piping
Yard Piping
Yard Piping
Proposed
Proposed
Proposed
Proposed
Existing
Proposed

Hydraulic statement Sadiqabad

ENT FOR WATER SUPPLY SCHEME


ISTRICT RAHIMYARKHAN.

REMARKS

21
Existing

Proposed
Proposed
Proposed
Proposed
Proposed
Proposed

Hydraulic statement Sadiqabad

ENT FOR WATER SUPPLY SCHEME


ISTRICT RAHIMYARKHAN.

REMARKS

21

OHR=60'Base slab
Head Loss=75 Feet

Hydraulic statement Sadiqabad

ENT FOR WATER SUPPLY SCHEME


ISTRICT RAHIMYARKHAN.

REMARKS

21

Hydraulic statement Sadiqabad

ENT FOR WATER SUPPLY SCHEME


ISTRICT RAHIMYARKHAN.

REMARKS

21

Hydraulic statement Sadiqabad

ENT FOR WATER SUPPLY SCHEME


ISTRICT RAHIMYARKHAN.

REMARKS

21

OHR=60'Base slab
Head Loss=75 Feet

Hydraulic statement Sadiqabad

ENT FOR WATER SUPPLY SCHEME


ISTRICT RAHIMYARKHAN.

REMARKS

21

Hydraulic statement Sadiqabad

ENT FOR WATER SUPPLY SCHEME


ISTRICT RAHIMYARKHAN.

REMARKS

21

Head Loss=100 Feet

Hydraulic statement Sadiqabad

ENT FOR WATER SUPPLY SCHEME


ISTRICT RAHIMYARKHAN.

REMARKS

21

Hydraulic statement Sadiqabad

ENT FOR WATER SUPPLY SCHEME


ISTRICT RAHIMYARKHAN.

REMARKS

21

OHR=60'Base slab
Head Loss=75 Feet

Hydraulic statement Sadiqabad

1 x

5.00 x
100

5.00 x
12.50

3.00 x
4.5 x
50.63

5.00 x
Cft @ Rs.

0.50 =
8479.35

0.75 x
0.75 x
Cft @ Rs.

4.50 =
4.50 =
Total
=
16103.3

Chapter No.11 item No.8


Cement plaster 1:3 upto 20 ft: height 1/2" thick
Inside:4 x
4.5
3 x
4 x
4.5
4.5 x
4 x
x
0.75
4.5
148.50

4.00 =
3833.30

100 Cft.
o% Cft.

Rs.

383

/-

12.50 Cft.
% Cft.
Rs.

1060

/-

20.25 Cft.
30.38 Cft.
50.63 Cft.
% Cft.
Rs.

8152

/-

54.00
81.00
13.50
148.50
% Sft.

Rs.

1930

/-

Rs.

278

/-

10.125
Per . Cft

Cft.
Cft. Rs.

2945

/-

30.98
Per %
G.Total

Kg
kg Rs.
Rs.

3551
18299

//-

Chapter No. 7 item No. 4


Pacca brick work in other then building upto 10' hight in cement sand mortor. Ratio
1:5
2 x
2 x

5.00 x
Cft @ Rs.

Chapter No. 6 item No. 3


Cement concrete brick or stone ballast 1-1/2" to 2" guage in foundation and plinth.
Ratio 1:6:12
1 x

size 3'x3'

DETAIL OF SLUICE VALVE & AIR VALVE CHAMBER (Rate Analysis)


Chapter No. 3 item No. 21
Excavation in foundation of building, bridges and other structures I/c dag-belling
dressing, refilling around structure with excavated earth watering and ramming
lead upto one chain(30m) and lift upto 5 ft: (1.5 m) etc:

Sft @ Rs.

Total
1299.5

=
=
=
=

Sft.
Sft.
Sft.
Sft.

Chapter No.6 item No.5


Cement concrete plain i/c placing complacting ,finishing and curing complete.
(i/c screening and washing of stone of aggregates) Ratio 1:2:4
1 x

3 x
1.44

3 x
Cft @ Rs.

0.16 =
19289.15

1.44 Cft.
% Cft.

Chapter 6 item No.6


6

Providing and laying reinforced cement concrete (including prestressed concrete) using coarse sand and screened graded and
washed aggregate in required shape and design, including
forms,moulds, shuttering, lifting, compacting, curing, rendering,
and finishing exposed surface, complete (but excluding the cost of
steel reinforcement, its fabrication and placing in position etc).

(a) (1) Reinforced cement concrete: in roof slab, columns lintels,


girders and other structural members laid in situ or pre cast laid in
position, or pre stressed members cast in situ, complete in all
respect. Type X ( norminal mix) 1:2:4
4.5 x

4.5 x
0.5
10.125 Cft. @ Rs.

=
290.85

Chapter 6 item No.9


7

Fabricatin of mild steel reinforcement for cement concrete


including cutting ,bending,laying in position making joints and
fastening I/c cost of steel reinforcement (also including removal of
rust from bars ) deformed bar.
10.125 Cft @

Kg.
3.06 Kg.
=
30.98 Kg. @ Rs.
11460.85

Say

Rs.

18,300

/-

Вам также может понравиться