Вы находитесь на странице: 1из 78

NOTICE INVITING TENDERS

1.0

Sealed item rate tenders are invited by M/s. Mindspace, No. 3, Kalpana Chawla Road,
nd
R.M.V. 2 Stage, Sanjay Nagar, Bangalore - 560 094, on behalf of M/s. Onella Infra Pvt
Ltd, Hyderabad for Civil, Electrical & Plumbing works for the Proposed Farm House at
Jodupal Village, Madikeri. The Tender should be in the prescribed form attached to the tender
notice and should be submitted to the office of M/s. Mindspace, on or before 21-01-2015.@
3.00pm.

2.0

No tender will be received on or after 3.00pm on 21-01-2015 under any circumstances


whatsoever.

3.0

Tender document in one Volume along with tender drawings can be collected from the office of
M/s. Mindspace, Bangalore, at any time from 14-01-2015. during working hours.
Tender schedule is as follows:
a.
Issue of Tender Documents to Vendors
b.
Pre bid meeting
c.
Release of Addendum to Tender (if any)
d.
Submission of Tender to M/s. Mindspace

:
:
:
:

4.0

This will be a closed tender, which will be opened with the representatives of the Employer and
Architects.

5.0

The tender submitted on behalf of a firm shall be signed in ink by a person who has the
necessary authority on behalf of the firm to enter into the proposed contract; otherwise, the
tender is liable to be rejected. Each page of the tender document and each drawing
accompanying is required to be signed by the authorized person submitting the tender with the
company seal in token of their having acquainted themselves with the General Conditions of
Contract, Specifications, Instructions to Tenderers as laid down. The form of tender is to be filled
in completely without fail. Any tender with any of documents not so signed will be rejected.

6.0

The tenderer must quote rates both in figures and words. All erasures and alterations made
while filling the tender must be attested by dated initials of the tenderer. Over writing of figures is
not permitted. Failure to comply with either of these conditions will render tender liable for
rejection. No advice of any change in rate or conditions after the opening of the tender will be
entertained.

7.0

Errors in the bill of quantities shall be dealt within the following manner :
i)
In the event of a discrepancy between the rates quoted in words and the rates in figures
the former shall be deemed to be correct.
ii)

In the event of an error occurring in the amount column of the bill of quantities as a result
of the wrong extension of the unit rate and the quantity, the unit rate shall be regarded as
firm and extension shall be amended on the basis of rates.

iii)

All errors in totaling in amount column and in carrying forward totals shall be corrected.

iv)

The tender total shall be accordingly amended except that there shall be no rectification
of any errors, omissions or wrong estimate, in the prices inserted by the tenderer in the
bill of quantities.

8.0

Where alternative items are given only the rates in figures and words are to be entered and not
the amounts thereof. A tender which does not show the rates in figures and words for alternative
items are liable to be rejected. The Employer /Architect reserves the right to take into account
any of the alternative items for the purpose of accepting a tender or to operate upon any or all of
the said alternative items during the execution of the work, partly or fully as required.

9.0

The tenderers must obtain for themselves on their own responsibility and at their own expense
all the information which may be necessary, including risks, contingencies and other

circumstances to enable them in making a proper tender and for entering into a contract, and
must examine the drawings, specifications and conditions and inspect the site of the work and
acquaint themselves with all local conditions, means and access to the work, nature of the work
and all the matters pertaining thereto before submitting the tender. They can also get any
clarifications required from the Architects, before tendering, by contacting them at their office
during working hours.
No claim for extra payment on the pretext of not having full specifications, or not understanding
the drawings or misunderstanding any of the conditions of contract and instructions to tenderers
will be entertained. The decision of the architect in all these will be final and binding on the
contractors once the contract is awarded.
10.0

The tenderers shall submit along with their tender, a list mentioning the names of manufacturers
of specialized items like steel windows, patented water proofing, flush doors, floor tiles, false
ceiling, etc. which they propose to use.
All service contractors and sub-contractors for specialized jobs should be approved by Clients /
Architects.
The tenderers shall submit along with their tender the Rate Analysis for all the items
quoted in the tender in the electronic (CD) form, basic rates of the materials for items
other than mentioned in the tender, Project Schedule, Cash flow Chart (based on the
quantities and time mentioned in the tender) and Organization Chart.

11.0

Earnest Money Deposit:


Nil
Mobilisation Advance:
Mobilization advance of 10% the contract value shall be provided against Bank Guarantee for
successful contractor. The contractor shall furnish Bank Guarantee (from any Nationalized Bank
/ Bank acceptable to the Employer) in the format approved by the Employer within 10 days from
the date of "Letter of Intent". Upon furnishing the Bank Guarantee, Mobilization advance shall be
paid. This mobilization advance shall be recovered in 4 equal installments starting from second
running bill.

12.0

Tenders will remain valid for a period of 90 days from last date notified for the receipt of tenders.

13.0

The quantities furnished in the schedule of quantities are only probable quantities and is liable to
alterations by omission, deductions or additions to any extent at the discretion of Architects /
Employer. Payments will be regulated on the actual quantities of work done at accepted rates.
Each tender should contain not only the rates but also the value of each items of work entered in
a separate column and all the items should be totaled in order to show the aggregate value of
the entire tender. Corrections that are not attested may entail the rejection of the tender. Rates
should be quoted both in figures and words in columns specified.

14.0

The rates quoted in tender shall include cost of all materials, labor and all charges for double
scaffolding, staging, shuttering & centering materials, water and meter rent charges, electric
charges, temporary plumbing, cost of cisterns, hire for any tool and plants, shed for materials,
marking out and clearing of site, watering, curing all cement work, concrete as mentioned in the
specifications, complete in all respects.

15.0

The rates quoted shall be deemed to be for the finished work to be measured at site. Tenderers
must include in their rates transportation of materials to site, The rates to be quoted by the
contractor shall be inclusive of all taxes like VAT, Service Tax, Excise Duty, Octroi and any
other tax and duty or other levy levied by the Central Government or any State Government or
Local Authorities etc., as applicable. No extra payment on this account will be made to the
contractor. No claim in respect of any of the above levies will be entertained by the Employer.
The tenderer to comply with the labour rules and regulations as prescribed in the labour act, shall
take coverage to the workers including CAR policy and shall pay all ESI, PF to the government
as applicable and as stipulated by the Govt. The employer / Architects / Consultants shall not be

held responsible for any reason for non fulfillment of rules and regulations.
16.0

The calculations made by the tenderers should be based upon probable quantities of several
items of work which are furnished for the tenderer's convenience in the schedule of probable
quantities, but it must be clearly understood that the contract is not a lumpsum contract. The
Employers do not in any way assure or guarantee that the said probable quantities are correct or
that the work would correspond thereto. The items of work irrespective of the quantities which
may vary shall be carried out at the same accepted tender rates and no escalation in the rates
will be entertained whatsoever.

17.

PROJECT COMPLETION SCHEDULE: The entire work should be completed within 12 Months
from the date of commencement.

17.1

INSTRUCTIONS TO TENDERER
The tenderer must understand clearly that the rates quoted are for complete items of works
including charges due to materials, labour, plant, scaffolding, supervision, service works,
power, royalties, sales tax etc., and includes all extra to cover the cost of night work if and
when required and no claim for additional payment beyond the prices or rates quoted will be
entertained for payment subsequently towards any claims on the grounds of
misrepresentation or on point that he was supplied with information given by promise or
guarantee by the trust, or by any person whether member of or employee in trust will not be
entertained. Failure on the contractors part to obtain all necessary information for the
purpose of submitting his tender and quoting rates therein shall not absolve him of any
risk or liability consequent upon the submission for tender.

17.2

The contractor should note that classifications of various floors of the main building will be
strictly according to the approved plans and as shown on plan, one set of plans, are enclosed
with tender form. The plan shall be signed and enclosed along with the tenders as token of
acceptance. The rates should be quoted considering the lifts and leads involved. No claims
towards extra lead and lift charges will be entertained.

17.3

The tenderer may read carefully the specifications for the items Tor-Steel / TMT / HySD and
Mild Steel as the rates to be quoted for these items should be inclusive of all laps and
wastages. Laps, pins, chairs and wastages will not be measured and paid.

17.4

The successful tenderer shall submit for approval a P.E.R.T. chart (Programme Evaluation
and Review Technique) from the date of commencement of the work to the date of completion
as per agreement. The contractor is bound to adhere to the schedule. The PERT chart should
be submitted within one week from the date of issue of work order or from the date of handing
over site whichever is earlier.

17.5

Tenderer should submit their tenders in separate sealed covers duly super scribing the name
of the respective work on the face of the cover.

17.6

Onella Infra Pvt Ltd / MS reserve the right to accept or reject any or all tenders without
assigning any reasons thereof.

18.0

The liquidated damages as per clause 39.0 of General Conditions of Contract and Appendix to it
will be applicable for work covered in this contract.

19.0

Cement and Steel:


Cement and all steel supplied shall be in accordance with the relevant IS specifications. As and
when directed by the Architect / Engineer, the Contractor at his cost shall get the materials tested
in an approved testing laboratory and submit the test results/reports for approval before using
them in the Work.
The contractor has to make his own arrangements for the procurement of Cement &
Steel of approved brand and make required for the Project. The cement to be used should be
Ordinary Portland Cement (OPC) - 43/53 Grade of ACC/ Ultra/ Coromandal /Birla / Zuari /
Dalmia.
3

Note: No blended cement will be permitted for use.


19.1.0 (Deleted)
19.2.0 (Deleted)
19.3.0 Conditions when Cement & Steel is procured by the Contractor :
19.3.1 Materials :
The materials to be used shall be of the grades as mentioned above only. The make, brand &
grade shall be got approved by the Architects / Engineers before procurement.
a.
b.
c.
d.

Ordinary Portland Cement


Reinforcement steel
Structural steel
Tubular steel (ERW)

- Grade as specified above conforming to IS 8112.


- Fe 500 confirming to IS 1786.
- Confirming to IS as specified above.
- Confirming to IS specified above.

19.3.2 Unless otherwise specified, all cement, structural steel, and reinforcement steel, should be
procured by the contractor at his cost. The materials so procured should conform to I.S.
Specifications mentioned in the tender and from such manufacturers approved by the Architects.
Test Certificates for the batch of materials purchased should accompany each consignment of
material brought to site.
19.3.3 The following basic rates (inclusive of all taxes, duties, Octroi, etc. at the stockyard plus charges
for loading, transport to site, unloading at site and storing) i.e. Landed cost to site to be assumed
by the tenderer for quoting the rates.
a.

Ordinary Portland Cement


Without fly ash.
43 grade confirming to IS 8112
Rs. 380/- (Rs Three Hundred & Eighty Only) per Bag

b.

Reinforcement Steel Fe500 (TMT) Confirming to IS 1786


Per Metric Tonne
- Rs. 52,500/- (Rs Fifty Two Five Hundred Only)

c.

Structural

steel

d. Tubular steel (ERW)

Standard Quality confirming to IS 226. Rs.


57,000/- (Rs. Fifty Seven Thousand Only) per Metric Tone
- Confirming to IS 1161. Rs. 60,000/- (Rs. Sixty
Thousand Only) per Metric Tone

19.3.4 No claim for extra payment on account of wastages, excess consumption of cement on
any account will be entertained.
19.3.5 No claim for extra payment on account of increase in weight of steel due to rolling margins, extra
laps on account of short lengths of reinforcement steel will be entertained.
19.3.6 No claim for extra payment on account of increase in weight of structural steel due to rolling
margins and additional splicing due to short length of steel sections received will be entertained.
19.3.7 All materials left over at the end of the work whatsoever should be taken away from the site by
the contractor at his cost.
Apart from the items mentioned above, the employer reserves the right to supply any
material as required for the project. Contractor to arrange for unloading, stacking at site,
transporting the same from stock yard to work spot, cutting to required sizes, shape and
other works required for execution etc. In that case the basic cost of the material supplied
by the employer be deemed to include:
Cost of the material

Taxes as applicable
Transportation and loading at stock yard
Wastages up to 5% only
but shall exclude overheads and profit margin as considered by the contractor in the rate
analysis submitted along with tender
Upon supply of the material it is the responsibility of the contractor to receive and store till the
work get executed.
19.4.0 Electricity for Construction:
Electricity required for construction shall be arranged by the contractor himself.All necessary
deposits shall be borne by the Clients. Necessary Laisaioning works required shall be got
done by the Contractor.
20.0
20.1

Water for Construction:


Employer shall not make any arrangement for supply of water, the contractor shall make his
own arrangements for supply of water at his own cost for which no extra amount shall be paid.
In the event, contractor prefers to dig the bore well and get the water from bore, it is responsibility
of the contractor to get the permission of the authority, organize to dig the bore well, install a
required capacity pump and maintain bore including pump at his cost and hand over same free
of cost to the employer in good condition after work is completed.

21.0
21.1

Performance Bond:
The successful tenderer shall furnish a Performance Bond in the format as acceptable by the
Employer, for a sum of 2.5% of the Contract Value from any scheduled bank valid for the period
of the Contract within ten days from the date of issue of letter of intent towards the security for
the execution and fulfillment of the contract. This shall be released after the virtual completion of
the work. If the work is not completed within the stipulated duration, the bank guarantee should
be extended for the corresponding extension period.

21.2

The performance bond of the successful tenderer will be forfeited, if he fails to comply with any of
the conditions of the contract.

21.3

Security Deposit :
The successful tenderer shall furnish a Bank Guarantee, in the format as acceptable by the
Employer, for a sum of 2.5% of the Contract Value from any scheduled bank valid for the period
of the Contract within ten days from the date of issue of letter of intent towards the security for
the execution and fulfillment of the contract. This shall be released after the virtual completion of
the work. If the work is not completed within the stipulated duration, the bank guarantee should
be extended for the corresponding extension period.
The Security deposit of the successful tenderer will be forfeited, if he fails to comply with any of
the conditions of the contract.

22.0

Retention Money:
5% (Five percent) of the total gross bill value shall be retained in cash from each running bill
towards retention money up to a maximum limit of 5% of the Executed value including Tendered
Deviated items / Non Tendered / Additional Items.
50% of the amount so retained shall be released after the virtual completion of the work and the
balance 50% of the retention amount shall be released after the defects liability period.

23.0

24.0

Within 15 days of the receipt of intimation from the Employers / Architects of the acceptance of
their tender, the successful tenderer shall be bound to implement the contract by signing the
agreement in accordance with the draft agreement and the schedule of conditions, along with
other conditions that may be mutually agreed to, subsequent to the receipt of the tender, but the
written acceptance by the Employer / Architects of the tender will constitute a binding whether
such a formal contract is or is not subsequently entered into.
All compensations or other sums of money payable by the Contractor to the Employer under the
5

terms of this contract will be deducted from the bill amounts or from the Retention money, if the
amount so permits and the contractor shall, unless such retention money has become otherwise
payable, within ten days after such deductions make good in cash amount so deducted
25.0

The contractor shall carry out all the works strictly in accordance with the drawing, details and
instructions of the Architects / Employer. If in the opinion of the Architects, changes have to be
made in the design, and they desire contractor to carry out same, the contractor shall be bound
to comply. Architects decisions in such cases shall be final and shall not be open to arbitration.

26.0

The Contractor is bound to carryout any item of work necessary for the completion of the job
even through such items are not included in the schedule of quantities and rates. Schedule of
instructions in respect of such additional items and their quantities will be issued in writing by the
Architects with the prior consent in writing of the Employer.

27.0

The contractor shall not be entitled to any compensation for any loss suffered by him on account
of delays in commencing or executing the work whatever the cause of delay may be, including
delays arising out of modifications to the work entrusted to him or in any subcontracts connected
therewith or delays in awarding contracts for other trades of the project or in commencement or
completion of such other works or in procuring. Government controlled or other building
materials or in obtaining water and power connection for construction purposes or for any other
reason whatsoever and the Employer shall not be liable for any claim, in respect thereof. The
Employer does not accept liabilities for any sum besides the tender amount, subject to such
variations as are provided for herein.

28.0

The successful tenderer must cooperate and coordinate the work with the work of all the other
contractors appointed by the Employer, so that the work shall proceed with the least possible
delay and to satisfaction of the Architects. The Contractor's co-ordination with other Contractors
appointed by the Employer is essential to maintain smooth progress of work and any delays,
which in the opinion of the Architects / Employer is due to non-coordination and inefficient
management of the contractor, will not be entertained for any extension of time.

29.0

The tenders received will be jointly acknowledged by Architects/Employers/ Project Management


Consultants.

30.0

The prices quoted, time required for the completion, and the standard of workmanship will be the
main criteria for considering the tenders.

31.0

The Employers do not bind themselves to accept the lowest or any tender and reserve
themselves that right to accept or reject any or all the tenders, whether in whole or in part without
assigning any reason for doing so.

32.0

Every tenderer shall furnish along with the tender the latest income tax clearance certificate
without which his tender is likely to be rejected.

33.0

Non-tendered Items:

33.1

The rates furnished in the Schedule of Quantities will apply for the entire project. Any item of
work which is not covered in the Schedule of Quantities which may be required to be carried out
on site shall be executed by the Contractor and payment for such items of work shall be based
on the rates that may be derived from the rates quoted for similar comparable items.

33.2

And for such items which cannot be derived from the contract rates, the payment shall be based
on the actual cost of materials, labor, plus 5% towards overheads and 10% towards profit plus
the prevailing tax on works contract.

33.3

In case the work is executed by a subcontractor under the supervision of the main civil
contractor, then the payment shall be based on the actual agreed rate given for the sub
contractor (to enclose proof of work order or receipt of payment by the sub contractor), plus 5%
towards overheads and 5% towards profit plus the prevailing tax on works contract.

34.0

Escalation:

34.1

The rates and prices of the Schedule of Quantities shall remain firm for the entire period of
completion/ contract. However, for any extended period of the Contract due to reasons
beyond the control of the Contractor in accordance with Clause 38.1 of the General Conditions
of Contract, the Contract Price shall be adjusted for increase or decrease in rates and prices
of labor, materials, fuel and lubricants in accordance with following principles and procedures.

34.2

The cost of materials, electrical energy, water and/or services (if any) supplied by the
Employer at agreed fixed prices shall be excluded from the gross value for the purpose of
deriving the amount of escalation. The price variation given or paid for materials in the case
of materials procured by the contractor shall also be deducted from the gross value.

34.3

Price adjustment shall apply only for work, which could not be carried out within the stipulated
time for reasons attributable to the Employer and/or the Architect provided, extension of time
has been granted by the Employer on specific request of the Contractor due to such reasons.
It shall not apply to work carried out beyond the stipulated time with extension granted by the
Employer for reasons attributable to the Contractor. Further, in the later case, the excess cost
(if any incurred by the Employer) of materials supplied to the Contractor by the Employer over
and above the fixed prices specified in the Contract will be recovered from the Contractor.

34.4

The amounts payable to the contractors for the work done involving use of cement and steel
shall be adjusted for increase or decrease in the rate of these materials as under:

34.4.1 The basic rates of cement and steel to be brought by the contractor shall be considered as
under:___________________________________________________________________________
Material
Star Rates
Cement
Rs. 380/- per bag
Steel
Rs. 52,500/- per M. Ton
_______________________________________________________________________
34.4.2 The Fluctuation in rates of cement and steel shall be adjusted in bills payable to contractors as
under:A
A
B
C1

=
=
=
=

C2

B x (C1 / C2 1) x D
Difference of amount payable or recoverable
Basic rates of steel / cement
The quarterly average corresponding index for steel and cement, for the
quarter under consideration (as mentioned in monthly bulletin of Reserve
Bank of India)
Price index of Cement / Steel for the Aug 2009 I.e., 282 for steel and for
cement.
Quantity of Cement / Steel actually brought by the contractor on the site of the
work and consumed in the work during the quarter duly supported with
recorded measurements. Only recorded quantity is payable.

34.4.3 Conditions for variation in prices of Cement and Steel only:


a)
Variation of price shall not apply for fluctuation between + or 5% from the Basic
rates.
b)
The clause shall be operative from the date of issue of work order and upto the expiry
of the original time limit.
c)
The formula shall be used individually for cement / steel for calculating adjustment.
35.0

Material Advances / Unfixed Materials:


The client at his discretion may pay advance on Reinforcement Steel and Cement
procured and delivered at site by the contractor for use in works to a maximum extent
of 70% of the assessed value of the materials. Such materials on which payment has been
made to the contractor become the property of the Client. (For any loss or damage to which

the contractor is responsible). And they shall not be removed from the site except for use
upon the work. The material advance paid for the above mentioned items shall be recovered
in full in the subsequent running bill.
36.0

Guarantees:
The Contractor shall give a guarantee for ten years for the following works as well as where
called for in the item specification specifically executed by him and the approved patented
agencies/Specialist agencies (Sub-contractor).
a. Anti-termite Treatment (On Stamp paper)
b. Water proofing treatment (In the form of Bank guarantee for 10 years for an amount of 3% of
the amount as certified for the respective item)

37.0

Program for completion of work in the form of 'PERT' Charts and CPM Charts integrating all
services prepared by an experienced Project Management Consultant preferably on MS - Win
Project giving all details should be given by the contractors within 10 days of starting the work.
The Bar Bending Schedule for reinforcement steel and Cutting Schedule for the Structural steel
shall also be given by the contractor progressively as and when the drawings are issued to him.

38.0

Monthly cash-flow statement covering the period of contract including services should be given.

39.0

This notice inviting tenders will form part of the tender document.

I/We hereby declare that I/we have read and understood the above instructions for the guidance of the
tenderers.

(SIGNATURE OF THE TENDERER)

Name of Project

Name of Employer:

Civil, Electrical & Plumbing works for Proposed Farm House at Jodupal
Village, Madikeri
M/s. Onella Infra Pvt Ltd, Hyderabad.
INSTRUCTIONS TO TENDERERS

1.0

All the rates shall be filled up in figures as well as words without fail in ink only.

2.0

The rates and amount against each item of work shall be filled up only in the tender papers
issued to tenderers.

3.0

The tenders shall be accompanied by the Earnest Money Deposit for the specified amount.

4.0

The tenders shall be duly signed by the Legal Competent Officer of the company.

5.0

No paper or sheet shall be detached from or attached to the tender document issued to the
tenderers. The original binding of the tender document shall be retained in tact.

6.0

All the drawings shall be returned along with the tender duly signed with their Company's seal
affixed.

7.0

All the pages of the tender document should be signed by the tenderer.

8.0

The seal of the Company must be affixed below the signature of the tenderer on every sheet of
the tender document.

9.0

No corrections or alterations shall be made in the tender document. Tender with extra conditions
other than indicated in the tender is liable to be rejected.

10.0

Do not fill in the 'Articles of Agreement'.

11.0

This instruction to tenderers will form part of the tender document.

12.0

The rates for all items given in the schedule of rates should be quoted in figures and words and
valuation of the tender cost will be based on these rates only.

13.0

The rate quoted by the tenderer for any item of work for a particular building shall be applicable
for other buildings also. If different rates are quoted, lowest of the rates quoted will be applicable
for all buildings.

14.0

Failure to comply with these requirements or any other mentioned in the tender documents shall
render the tender liable for rejection.

15.0

Specifications for several items are given in three parts.


(a)
General Specifications
(b)
Common Specifications
(c)
Detail specifications for each item given in schedule of quantities.
Detailed Specification (c), Common Specifications (b) and the General Specification (a) along
with relevant ISI Codes referred to with it, should be considered for working out the rates.
The Specifications sets for the obligation of the contractor apart from these and those mentioned
in the Conditions of Contract.

16.0
16.1

SITE ESTABLISHMENT / INFRASTRUCTURE:


Laboratory:
The contractor has to setup a laboratory at site at his cost with all necessary equipments
required for the day to day monitoring of the Design Mix.

16.2

Site office for the Employers/Architects Engineers:


The contractor shall construct and provide free of charge an office with a carpet area of
approximately 150 Sqft, a waterproof office with tables, chairs, fans and light with toilet facility for
use by the Project Engineer, Project Engineer's Representative, Architects and their supervision
team. The office shall be constructed within the time stipulated by. On completion of the project
works, the site office will be formally handed over to the owner free of charge by the contractor
and will thereupon become the absolute property of the owner.

16.2.1 Telephone with E-mail facility


The contractor shall make his own arrangements for telephone with e-mail facility connection at
the site which should be accessible for the use of the Client / Project Adviser / Project manager /
Project Engineer PMC / Architects / Consultants and their representatives.
16.2.2 Temporary Roads
The contractor shall construct and maintain at his own cost all suitable temporary roads at the
work site for the use of his transport equipment and also the vehicles of the Owner / Project
Adviser / Project manager / Project Engineer PMC / Architects / Consultants and their
representatives.
16.3

Cement Go-down:
The contractor shall provide at his cost a waterproof shed for storing cement up to 50 Metric
Tones minimum.

16.4

Clearing Infrastructure:
After the completion of the work the contractor shall at his cost remove all temporary structure
and clear the premises of debris, etc. and hand over to the Employer.

16.5

The Contractor will not be permitted to make use of any space other than the working space
allotted to him without the specific written permission of the Employer.

16.6

The security of the Contractor's equipment and materials is his own responsibility. The Employer
accepts no liability for loss or damage to the Contractor's plant, tools or materials.

16.7

The Contractor shall ensure that the Security Regulations of the Employer is strictly enforced.

16.8

First Aid: The Contractor shall be responsible for all first aid and he shall keep the site fully
equipped.

16.9

Minimum requirement of Technical Staff:


a)
One Qualified, competent experienced Engineer - Minimum 10 years experience in
construction of similar buildings, acceptable to Clients / Architects.
b)
Two Qualified experienced Engineers - Min. 5 years experience
c)
One Quantity Surveyor
d)
Two Supervisors
e)
Foremen for various trades as required.
f)
One Safety Supervisor

17.0

Minimum Equipment required along with Staff to run them:

17.1

The cost of providing all the equipment given under and anything more if required shall be
included in the item rate quoted under Bill of Quantities.

10

Sl.
No.
1

List of Machinery and Equipments available for the Project


Name
No of Type
& Capacit
Owned /
Units Make
y
Leased
Excavator

Front End Loader

Vibratory Roller

4
5

Water
tanker/sprinkler
Dumper

Plate compactor

Tower Crane

Temporary
water
tanks for construction
work) Liters capacity.

Concrete Mixer

10

Weigh Batcher

11

Vibrator

12

Generator

13

Air compressor

14

Concrete breaker

15

Welding machine

16

Surveying
Equipment
Shuttering
Plates/
System (Sqm)
Double Pole Tubular
H-Frame Scaffolding
confirming to IS
2750 1984/Platform
scaffolding
Vertical Hoist

17
18

19

20

21

Remarks

Compressor of 250
Cfm
with
jack
hammer
Computer / printer
with
necessary
software

11

22

Other Machineries
a)
b)
c)

18.0

SITE WORKING CONDITIONS:

18.1

The contractor shall at his own cost provide suitable residential accommodation for his staff and
labor. Land will not be provided within the Institute premises for putting up labor sheds.

18.2

Contractor will arrange for ration cards and permits as necessary for labor.

18.3

Provision for temporary toilets, urinals and bathing areas should be made for staff and labor by
the contractor within the living area. These should be maintained in a clean and orderly condition
and comply with local and Central Government regulations.

18.4

None of the staff, laborers, sub-contractors etc.; of the main contractors are allowed within the
existing buildings, canteen, offices, etc; if any. They should be confined to the areas of work for
which the contract is called for.

18.5

The entire working area and any other existing building should be cordoned off with a 6
Mtrs high GI sheet barricade fencing and provision of temporary urinals and toilets
should be made for his staff and labor by the contractor within the fenced area. Providing
barricading for existing buildings between proposed construction site and adjoining
properties around existing building including road side using 20G GI sheet, ISMC/ISA,
etc. The contractor shall provide and maintain at his own cost with necessary
excavation, PCC for fixing vertical poles, J bolts and painting MS surfaces including all
accessories for cutting, welding, etc. complete as directed at site.

18.6

Contractor, staff and labor should strictly follow the regulations in existence or to be formed for
purpose of entry of labor and material, working conditions, hours of working etc;

19.0

EXECUTION OF WORK:

19.1

The rates furnished in the Schedule of Quantities will apply for the entire project. Any item of
work which is not covered in the Schedule of Quantities (read with the General Conditions of
Contract) which may be required to be carried out on site shall be executed by the Contractor
and payment for such items of work shall be made as per clause 33.0 of the Notice Inviting
Tenders.

19.2

No material of any kind will be supplied by the Employer except for those referred in clause 19.0
of the Notice Inviting Tenders wherein the Employer has the option to supply, if required and the
Contractor must make his own arrangements to procure all the required materials conforming to
the relevant Indian Standard Specifications. In the absence of an Indian Standard Specification
for any material, such material shall be the best of its kind and approved by the Architect. All
materials (including water) proposed to be used on the Works should be got tested by the
Contractor at his cost as may be required by the Architects from approved laboratory and test
results shall be submitted to the Architects for approval. Only those materials (including water)
approved by the Architects are to be used on the Works.

20.0

SUPERVISION OF WORK:
The Contractor is required to have on site during all working hours a competent full time
Engineer acceptable to the Architect/Employer who will be responsible to the Employer for the
conduct of the Work and who has authority to receive and act on such instructions as the
Architect/Employer may give.

21.0

INSPECTION:
The Work of the Contractor is subject to inspection by the Employer at all times, but such
inspections do not relieve the Contractor of any of his responsibilities.
12

22.0

EMPLOYMENT OF LABOUR:

22.1

Contractor will be expected to employ on Work skilled employees with experience of his
particular work.

22.2

All incidental expenses towards employment of all kinds of labor necessary for the execution of
the Works such as compliance with all legislations in respect of wages and welfare schemes as
applicable (such as payment of Minimum Wages, Regulation and Control of Contract Labor, ESI
Scheme, Provident Fund, etc.) shall be the responsibility of the Contractor

22.3

The normal hours of work on the Site are from 0800 Hours to 1800 Hours and all materials
should be brought to site during working hours. Specific permission of the Employer shall be
taken for working outside the normal working hours and on holidays.

22.4

All employees of the Contractor, while on duty within the premises, shall wear identification
badges provided by the Contractor consistent with the security rules of the Employer.

22.5

The Contractor shall ensure that all notices displayed on site and any instructions issued by
Employer are strictly adhered to by Contractor's employees.

22.6

None of the Contractor's staff or workmen will be allowed to remain at Site except when they are
on duty.

23.0

SALIENT FEATURES OF SOME MAJOR LABOUR LAWS APPLICABLE


ESTABLISHMENTS ENGAGED IN BUILDING AND OTHER CONSTRUCTION WORK.

TO

Workmen Compensation Act 1923 / Payment of Gratuity Act 1972 / Employees P.F. and
Miscellaneous Provision Act 1952 / Maternity Benefit Act 1951 / Contract Labour [Regulation &
Abolition] Act 1970 / Minimum Wages Act 1948 / Payment of Wages Act 1936 / Equal
Remuneration Act 1979 / Payment of Bonus Act 1965 / Industrial Disputes Act 1947 / Industrial
Employment [Standing Orders] Act 1946 / Trade Unions Act 1926:- Act / Child Labour
[Prohibition & Regulation] Act 1986 / Inter-State Migrant Workmens [Regulation of Employment
& Conditions of Service] Act 1979 / The Building and Other Construction Workers [Regulation of
Employment and Conditions of Service] Act 1996 and the Cess Act of 1996 / Factories Act 1948
24.0

REPORTING:
From the Date of Commencement of the Contract, the Contractor must report the following
information to the Employer in writing each Friday, until the Date of Completion:
a)
Man power employed: managerial, supervisory and workmen (by trades).
b)
Progress achieved.
c)
Expected dates for completion of various phases of the Work.
d)
Any actual or potential delay in program caused by the action or inaction of the
Employer/ Architect and other contractors working on Site.

25.0

COMPLETION OF WORK:
Before finally leaving the site upon completion of the Works, the Contractor shall remove at his
cost all his infrastructural facilities like huts, display and notice boards, plants, tools, equipments,
scaffolding and centering materials, rubbish etc. and the site left clean and tidy.

26.0

WORKING AND SAFETY REGULATIONS:

26.1

The contractor will observe all statutory and legal requirements by Central and State
Governments and local bodies applicable to the work as well as any local regulations applying to
the site made over by Employer /other authority.

26.2

Particulars attention is drawn to the following:


a)
In case of accident, the Employer will be informed in writing forthwith. The contractor will
strictly follow regulations laid down by Factory Inspector, Government and State
authorities in this regard.
b)
Fencing all contractors plant, platform, excavation, pits & providing proper access
ladder with handrail for worker to climb to different level
13

c)
d)

Compliance with all electricity regulations.


Compliance with statutory requirements for inspection and testing of all lifting appliances
and auxiliary lifting gear.

26.3

Staircase, doors or gangways must not be obstructed in any way that will interfere with means of
access or escape.

26.4

No excavation will be started without the permission of the Employer who will inform the
contractor of the position of any pipes or cables known to be buried in the area. All excavation
must be effectively railed off at all times, or completely boarded over and properly marked during
the hours of darkness by red warning lamps, and using flame proof warning lamps in
non-smoking areas. During the hours of darkness heaps of debris or material which cannot be
immediately removed must be heaped in such a way as to leave adequate passage way.

26.5

The contractor will notify the Employer of his intention to bring on to the site any equipment such
as space heating or welding apparatus, or any container holding liquid or gaseous fuel or other
substance which might create a hazard. The Employer will have right to prohibit the use of such
equipment or to prescribe the conditions under which such equipment may be used. The
Employer will have the right to inspect any construction plant, and to forbid its use if in his opinion
it is unsuitable or unsafe. No claim arising there from shall be made by the Contractor nor
entertained by the Employer. The contractor or anyone acting on his instructions will not bring on
to the site any radio-active substance or any apparatus using such substance or any X-ray
apparatus until written permission and direction regarding the use of such equipment has been
received from Employer.

26.6

The contractor will meet all requirements and act on the instructions of the Employer where it is
necessary to operate a 'Permit-to-work' system.

26.7

Where it is necessary to provide and/or store petroleum products or petroleum mixtures &
explosives, contractor shall be responsible for carrying out such provision and/or storage in
accordance with rules & regulations laid down in Petroleum Act, 1934, Explosive Act 1948 &
Petroleum & Carbide of Calcium Manual published by Chief Inspector of Explosive of India. All
such storage shall have prior approval of owner. Incase any approvals are necessary from Chief
Inspector of Explosives or any statutory authorities, contractor shall be responsible for obtaining
same.

26.8

The contractor shall have his own Fire fighting extinguishers and equipments as per statutory
requirements and normal safety regulations.

26.9

The contractor shall be responsible for the provision of all safety notices and safety equipment
required by both the relevant legislation and such as the owner may deem necessary.

27.0

ELECTRICAL SAFETY REGULATIONS:

27.1

In no circumstances will the contractor interfere with fuses and electrical equipment belonging to
Employer.

27.2

Before contractor connects any electrical appliances to any plug or socket belonging to Employer
he will.
a)
satisfy the Employer that the appliance is in good condition.
b)
inform the Employer of the maximum current required and the voltage phase of the
appliance.
c)
obtain permission of the Employer detailing the sockets to which the appliances may be
connected.

27.3

The Employer will not grant permission to plug in until he is satisfied that:
a)
the appliance is in good condition and is fitted with a suitable plug;
b)
the appliance is fitted with a suitable cable having two earth conductors, one of which
shall be an earthed metal sheath surrounding the cores.

27.4

No electric cable in use by the Employer will be disturbed without prior permission of the
14

Employer. No weight of any description will be imposed on any such cable and no staging or
similar equipment will rest against or to be attached to it.
27.5

No work must be carried out on any live equipment. The equipment must be made safe, certified
and 'Permit-to-work' issued before any work is carried out.

27.6

No cable should be laid on ground surface. They should be taken above ground in such a way
that they do not obstruct the movement of vehicles, cranes, etc. and the work of other
contractors in the area.

27.7

The Employer has the right to discontinue supply if any equipment or installation is considered
unsafe. The contractor must replace or rectify the equipment installation at his own cost and
satisfy the Employer.

28.0

CONSTRUCTION SAFETY

28.1

Introduction

28.1.1 This part emphasizes the importance of carrying out all constructional operations in a safe and
efficient manner. Workers, in large number, both skilled and unskilled, are engaged in the
innumerable construction works. Due to increased tempo of such a building activity and large
scale mechanization, hazards of accidents have increased considerably. It has, therefore,
become imperative that adequate safety rules are laid down for every phase of construction
work.
28.1.2 Planning the various constructional operations before hand and making adequate
arrangements for procurement and storage of materials, and the machinery to get work done
is as important as carrying out these constructional operations in accordance with good
practice. Lack of planning or defective planning may result in avoidable delay in the
completion of work and consequently increased hazards from the point of view of fire, health
and structural soundness.
28.1.3 Information regarding handling operations that is unloading stacking, lifting, loading and
conveying of building materials, has also been given now along with the storage practices.
28.1.4 Additional information regarding the use of ladders; safety requirements for floor and wall
openings, railings and toe boards; piling and other deep foundations; constructions involving
use of hot bituminous materials; and erection of structural steel work and concrete framed
structures, etc, has been given.
28.1.5 The information contained in this part is largely based on the following Indian Standards:
IS: 3696 (Part I) - 1966 Safety code for scaffolds and ladders: Part I Scaffolds
IS: 3696 (Part ll) - 1966 Safety code for scaffolds and ladders: Part II Ladders
IS: 3764 - 1966-safety code for excavation work
IS: 4082 - 1977 Recommendations on stacking and storage of construction materials at site
st
(1 revision)
IS: 4130 - 1976 Safety code for demolition of buildings (first revision)
IS: 4912 - 1978 Safety requirements for floor and wall openings, railings and toe boards (First
revision)
IS: 5121 - 1969 Safety code for piling and other deep foundations
IS: 5916 - 1970 Safety cede for constructions involving use of hot bituminous materials
IS: 7205 - 1974 Safety code for erection of structural steel work
IS: 7969 - 1975 Safety code for handling and storage of building materials
IS: 8989 - 1978 Safety code for erection of concrete framed structures
28.1.6 A thorough inspection of tubular steel centering is necessary before its erection and members
showing evidence of excessive resting, kinks, dents or damaged welds shall be discarded.
Buckled or broken members shall be replaced. Care shall also be taken that locking devices
are in good working order and that coupling pins are effectively aligned to frames.
28.1.7 After assembling the basic unit, adjustment screws shall be set to their approximate final
15

adjustment and the unit shall be level and plumb so that when additional frames are installed
the tower shall be in level and plumb. The centering frames shall be tied together with
sufficient braces to make a rigid struts and diagonals braces are in proper position and are
secured so that frames develop full load carrying capacity. As erection progresses, all
connecting devices shall be in place and shall be fastened for full stability of joints and units.
28.1.8 No casurina poles / ballies shall be used for staging, props, centering, scaffolding, bracings,
platforms, ladders etc shall be used. Only MS poles, Jacks, acrospans shall be used.
28.1.9 Centering layout shall be made by a qualified engineer and shall be strictly followed. The
bearing capacity of the soil shall be kept in view for every centering job. The effect of weather
conditions shall also be taken into consideration as dry clay may become very plastic after a
rainfall and show marked decrease in its bearing capacity.
28.1.10 Sills under the supports shall be set on firm soil or other suitable material in a pattern which
assures adequate stability for all props. Care shall be taken not to disturb the soil under the
supports. Adequate drainage shall be provided to drain away water coming due to rains,
washing of forms or during the curing of the concrete to avoid softening of the supporting soil
strata.
28.1.11 All centering shall be finally, inspected to ensure that:
a) Footings or sills under every post of the centering are sound.
b) All lower adjustment screws or wedges are snug against the legs of the panels.
c) All upper adjustment screws or heads of jacks are in full contact with the formwork.
d) Panels are plumb in both directions.
e) All cross braces are in place and locking devices are in closed and secure position.
f) In case of CHAJJAS and balconies, the props shall be adequate to transfer the load to the
supporting point
28.1.12 During pouring of the concrete, the centering shall be constantly inspected and strengthened,
if required, wedges below the vertical supports tightened and adjustment screws properly
adjusted as necessary. Adequate protection of centering shall be secured from moving
vehicles or swinging loads.
28.1.13 Forms shall not be removed earlier than as laid down in the specifications and until it is certain
that the concrete has developed sufficient strength to support itself and all loads that will be
imposed on it. Only workmen actually engaged in removing the formwork shall be allowed in
the area during these operations. Those engaged in removing the formwork shall wear
helmets, gloves and heavy soled shoes and approved safety belts if adequate footing is not
provided above 2 m level. While cutting any tying wires in tension, care shall be taken to
prevent backlash which might hit a workman.
28.1.14 Particular order in which the supports are to be dismantled should be followed according to
the instructions of the site engineer.
28.2.0 Ramps and Gangways:
Ramps and gangways shall be adequate strength and evenly supported. They shall either
have a sufficiently flat stop or shall have cleats fixed to the surface to prevent slipping of
workmen. Ramps and gangways shall be kept free from grease, mud, snow or other slipping
hazards or other obstructions leading to tripping and accidental fall of workman.
Ramps and gangways meant for transporting materials shall have even surface and be of
sufficient width and provided with skirt boards on open sides.
28.3.0 Pre-stressed Concrete:
In pre-stressing operations, operating maintenance and replacement instructions of the
supplier of the equipment shall be strictly adhered to.
Extreme caution shall be exercised in all operations invoking the use of stressing equipment
as wires/strands under high tensile stresses become a lethal weapon.
During the jacking operation of any tensioning element(s) the anchor shall be kept turned up
16

close to anchor plate, wherever possible to avoid serious damage if a hydraulic line fails.
Pulling-headers, bolts and hydraulic jacks/rams shall be inspected for signs of deformation
and failure. Threads on bolts and nuts should be frequently inspected for diminishing cross
section. Choked units shall be carefully cleaned.
Care shall be taken that no one stands in line with the tensioning elements and jacking
equipment during the tensioning operations and that no one is directly over the jacking
equipment when deflection is being done. Signs and barriers shall be provided to prevent
workmen from working behind the jacks when the stressing operation is in progress.
Necessary shields should be put up immediately behind the pre-stressing jacks during
stressing operations.
Wedges and other temporary devices shall be inspected before use.
The pre-stressing jacks shall be periodically examined for wear and tear.
28.4.0 Erection of Prefabricated Members:
A spreader beam shall be used wherever possible so that the cable can be as perpendicular
to the members being lifted as practical. The angle between the cable and the members to be
lifted shall not be less than 60.
The lifting wires shall be tested for double the load to be handled at least once in six months.
The guy line shall be of adequate strength to perform is function of controlling the movement
of members being lifted.
Temporary scaffolding of adequate strength shall be used to support pre-cast members at
predetermined supporting points while lifting and placing them in position and connecting them
to other members.
After erection of the member, it shall be guyed and braced to prevent it from being tipped or
dislodged by accidental impact when setting the next member.
Pre-cast concrete units shall be handled at specific picking points and with specific devices.
Girders and beams shall be braced during transportation and handled. In such a way as to
keep the members upright
Methods of assembly and erection specified by the designer shall be strictly adhered to at site.
Immediately on erecting any unit in position, temporary connections or supports as specified
shall be provided before releasing the lifting equipment. The permanent structural connections
shall be established at the earliest opportunity.
Heated Concrete - When heaters are being used to heat aggregates and other materials and
to maintain proper curing temperatures, the heaters shall be frequently checked for
functioning and precautions shall be taken to avoid hazards in using coal, liquid, gas or any
other fuel.
28.5.0 Structural Connections
When reliance is placed on bond between pre-cast and in situ concrete the contact surface of
the pre-cast units shall be suitably prepared in accordance with the specifications
The packing of pints shall be carried out in accordance with the assembly instructions.
Leveling devices, such as wedges and nuts which have no load bearing function in the
completed structure shall be released or removed as necessary prior to integrating the joints.
If it becomes necessary to use electric power for in situ work, the same should be stepped
down to a safe level as far as possible.
28.6.0 General
Workmen working in any position where there is a falling hazard shall wear safety belts or
17

other adequate protection shall be provided.


29.0.0 ADDITIONAL SAFETY REQUIREMENTS FOR ERECTION OF STRUCTURAL STEEL
WORK
29.1.0 SAFETY ORGANIZATION:
The agency responsible for erecting the steel work should analyze the proposed erection
scheme for safety; the erection scheme should cover safety aspects right from the planning
stage up to the actual execution of the work.
29.2.0 SAFETY OF MEN:
29.2.1 GENERAL -While engaging men for the job, the supervisor should check up and make sure
that they are skilled in the particular job they have to perform.
29.2.2 The helmets shall be worn properly and at all times during the work and shall conform to the
accepted standards.
29.2.3 The safety goggles shall be used while performing duties which are hazardous to eye like
drilling, cutting and welding. The goggles used shall conform to the accepted standards and
should suit individual workers.
29.2.4 The welders and gas cutters shall be equipped with proper protective equipment like gloves,
safety boots, aprons and hand shields. The filter glass of the hand shield shall conform to the
accepted standards and should be suitable to the eyes of the particular worker.
29.2.5 When the work is in progress, the area shall be cordoned off by barricades to prevent persons
from hitting against structural components, or falling into excavated trenches or getting injured
by falling objects.
29.2.6 Warning signs shall be displayed where necessary to indicate hazards, for example
(a) '440 VOLTS',
(b) 'DO NOT SMOKE',
(c) 'MEN WORKING AHEAD', etc.
Hand lamps shall be of low voltage preferably 24 V prevent electrical hazards.
29.2.7 All electrically operated hand tools shall be provided with double earthing.
29.2.8 Anchors for guys or ties shall be checked for proper placement. The weight of concrete in
which the anchors are embedded shall be decked for uplift and sliding.
29.2.9 Split-end eye anchors shall only be used in good, solid rock.
29.2.10 The first load lifted by a guy derrick shall be kept at a small height for about 10 minutes and
the anchors immediately inspected for any signs or indications of fall
29.2.11 When a number of trusses or deep girders is loaded in one car or on me truck, all but one
being lifted shall be tied back unless they have been tied or braced to prevent their falling over
and endangering men unloading.
29.2.12 The erection gang shall have adequate supply of bolts. washers, rivets, pins, etc, of the
correct size. Enough number of bolts shall be used in connecting each piece using a minimum
of two bolts in a pattern to ensure that the joint will not fail due to dead load and erection
loads. All splice connections in columns, me girders, etc, shall be completely bolted or riveted
or welded as specified in the drawing before erection.
29.2.13 Girders and other heavy complicated structural members may require special erection devices
like cleats end hooks, which can be shop assembled and bolted or riveted or welded to the
piece and may be left permanently in the place after the work.
29.2.14 If a piece is Laterally unstable when picked at its centre, use of a balance beam is advisable,

18

and unless a pair of bridles slings can be placed far enough apart for them to be safe lifting
points. The top flange of a truss, girder or long beam may be temporarily reinforced with a
structural member laid flat on top of the member and secured temporarily.
29.2.15 On deep girders, and even on some trusses, a safety 'bar' running their full length ill aid the
riggers, fitters and others employed on the bottom Range or bottom chord to work with greater
safely. This can be a single 18 mm diameter wire rope through vertical stiffeners of such
members about one meter above the bottom flange and clamped at the ends with wire rope
clamps. If the holes cannot be provided, short eye bolts can be welded to the webs of the
girder at intervals to be removed and the surface chipped or ground to leave it smooth after all
work on the piece has been completed.
29.2.16 Safety belts shall always be available at work sport to be used whenever necessary. The rope
shall be chemically treated to resist dew and rotting. These shall not be tied on sharp edges of
steel structures. They shall be tied generally not more than 2 to 3 m away from the belt.
29.2.17 On a guy derrick or climbing crane job, the tool boxes used by the reaction staff shall be
moved to the new working floor each time the rig is changed. On a mobile crane job, the
boxes shall be moved as soon as the crane starts operating in a new area too far away for the
men to reach the boxes conveniently. While working a tall and heavy guy derrick, it is
advisable to control tension in guys by hand winches to avoid jerks, which may cause an
accident.
29.2.18 The proper size, number and spacing of wire rope clamps shall be used, depending on the
diameter of the wire rope. They shall be properly fixed in accordance with codes of good
practice. They shall be checked as soon as the rope has been stretched, as the rope
especially if new, tends to stretch under the applied load, which in turn may cause it to shrink
slightly in diameter. The damps shall them be promptly tightened to take care of this new
condition. In addition, the clamps shall be inspected frequently to be sure-that they have not
slipped and are tight enough.
29.2.19 When the men can work safely from the steel structure itself, this is preferable to hanging
platforms or scaffolds, as it eliminates additional operations, which in turn, reduces the hazard
of an accident.
29.2.20 To aid men working on floats or scaffolds, as well as men in erection gangs, or other gangs
using small material, such as bolts and drift pins, adequate bolt baskets or similar containers
with handles of sufficient strength and attachment to carry the loaded containers, shall be
provided.
29.2.21 The men should be trained to use such containers, and to keep small tolls gathered up and
put away in tool boxes when not in use. Material shall not be dumped overboard when a
scaffold is to be moved. Rivet heaters shall have sage containers or buckets for hot rivets over
at the end of day.
29.2.22 During the erection of tall buildings, it is desirable to use nylon nets at a height of 3 to 4 m to
provide safety to men.
29.3.0 SAFETY AGAINST FIRE:
29.3.1 A fire protection procedure is to be set up if there is to be any flame cutting, burning, heating,
riveting or any operation that could start a fire. For precautions to be observed during welding
and cutting operations, reference may be made to good practice.
29.3.2 The workers should be instructed not to throw objects like hot rivets, cigarette stubs, etc,
around.
29.3.3 Sufficient fire extinguishers, preferably, of soda acid type shall be placed at strategic points.
Extinguishers shall always be placed in cranes, hoists, compressors and similar places.

19

30.0.0 HEALTH AND SAFETY


30.1.0 Labour And Employment Laws
30.1.1 No labour below the age of Fourteen (14) years shall be employed on the Project.
30.1.2 The Contractor shall not pay the labourers engaged by it on the Project less that what is
provided for under the applicable laws. Whether for time or piece work, based on the
applicable rates of wages as fixed under law at the time. The Contractor shall ensure that the
provisions in the minimum Wages Act and the Provident Fund Act, as amended from time to
time, are fully complied with. The Contractor shall maintain the necessary registers and
records for payment of wages, overtime, Provident Fund etc made to its workmen / Regional
Provident Fund Commissioner as required by the Conciliation Officer (Central) Ministry of
Labour, Government of India, Provident Fund Department or such authorised person
appointed by the Central and / or State Government. The Contractor shall ensure this is
complied with on the Project, including any labour contractor employed by him.
30.1.3 The Contractor, at his own expense, shall comply with all the current applicable labour laws
and keep the Owner indemnified thereof.
30.1.4 The Contractor shall pay equal wages to both men & women in accordance with applicable
Labour Laws
30.1.5 The Contractor is covered under the Contractor Labour (Regulation and Abolition) Act, it shall
obtain a license from the licensing authority (i.e. Office of the Labour Commissioner) by
payment of the necessary prescribed fee and deposit. Such fees and deposits shall be borne
by Contractors and included in Bid.
30.1.6 The Contractor shall employ labour in sufficient numbers, either directly or through Subcontractors to maintain the required rate of progress and of quality to ensure workmanship is
to the degree specified in the Contract documents and to the satisfaction of the Consultant.
30.1.7 The Contractor shall furnish to the Consultant the labour returns of the number and
description, by trades, of the people employed on the Project every Saturday. This shall be for
the preceding week.
30.1.8 The Contractor shall submit in the last working day of each month to the Consultant an
Accident Status Report. This shall show the accidents that occurred during that time period;
the circumstances under which they occurred; and the extent of damage caused by them.
30.1.9 The Contractor shall submit on the last working day of each month to the Consultant a
Maternity Benefits Statement. This shall identify the number of female workers who have been
allowed Maternity Benefit as provided under Maternity Benefit Act 1961, or Rules made there
under, and the amounts paid to them.
30.1.10 The Contractor shall comply with all the provisions of the following statutory acts or any
modifications thereto and the rules made there under from time to time:
- Indian Factories Act 1948
- Payment of Wages Act 1936
- Minimum Wages Act 1948
- Owners Liability Act 1938
- Apprentices Act 1961
- Workmens Compensation Act 1923
- Industrial Disputes Act 1947
- The Maternity Benefits Act 1961
- Contract Labour (Regulation and Abolition) Act 1970
- Employment of Children Act 1933
- Provident Funds and Miscellaneous Provisions Act 1952
- The Employees Pension Scheme 1995
30.1.11 Should a report be made by an Inspecting Officer, as defined in the Contract Labour
20

(Regulation and Abolition) Act 1970, the Owner shall have the right to deduct from any money
due to the Contractor any sum required, or estimated to be required, for making good the
loss/losses suffered by a worker or workers by the reason of non-fulfillment of the Conditions
of the Contract relating to the benefits of workers, non-payment of wages or of deduction
made from their wages which are not justified by the terms of the Contract or non-observance.
30.1.12 The Contractor shall indemnify the Owner against any payments to be made under and for the
observance of the Provisions of the aforesaid Acts.
30.1.13 In the event of the Contractor committing a default or breach of any of the provisions of the
aforesaid Acts, as amended from time to time, of furnishing any information or submitting or
filling in any Form/Register/Slip under the provision of these Acts which is materially incorrect,
then on the report of the Inspecting officers, the Contractor shall, without prejudice to any
other liability, pay to the Owner a sum not exceeding Rs. 5000.00 as Liquidated Damages.
This shall be applied to each incident for every default, breach or furnishing of, submitting,
making and / or filling - in materially incorrect statements, the exact amount shall be fixed by
the Consultant.
30.1.14 In the event of the Contractors default continuing in this respect, the Liquidated Damages
may be increased to Rs. 1000.00 per day for each day that default occurs upto a maximum of
one percent (1%) of the Contract Amount.
30.1.15 The Consultant shall deduct such amounts from the Interim Application for payment or the
Security Deposit of the Contractor and credit the same to the Welfare Fund constituted under
these Acts. The decision of the Consultant in this respect shall be final and binding.
30.2.0 Health and Sanitary Arrangements for Workers Employed By The Contractor
30.2.1 These rules shall apply to all the building and construction contracts.
30.2.2 In respect of all the labour directly or indirectly employed on the Project for the execution of
the Works which is for the performance of the Contractors part of the Agreement, the
Contractor shall comply with, or cause to be complied with, all the rules and regulations of the
local sanitary and other Authorities or as required by the Consultant from time to time for the
provision of the adequate Health and Sanitary arrangements for all workers.
30.2.3 The Contractor shall provide shall provide off site, if required, its own separate labour camp
complete with all amenities such as electricity, water and other health and sanitary
arrangements. The Contractor shall also provide all the necessary surface transportation to
the project site and back to the labour camp for all their labour personnel accommodated in
the labour camp.
30.3.0 First Aid
The Contractor shall provide and maintain at the Project site, in an easily accessible place,
first aid supplies including an adequate supply of sterilized dressings and sterilized cottonwool.
These supplies shall be kept in good order and a member of the Contractors staff trained to
carry out this shall be nominated to be in charge of the same and shall be readily available
during working hours.
The Contractor shall maintain on site at all time a car. It shall be available to take any injured
person or persons to the nearest hospital.
30.4.0 Drinking Water
The Contractor shall provide and maintain at one central location, easily accessible to labour,
a sufficient supply of safe drinking water.
The water supply storage container shall be no closer than 20 meters from any latrine, drain or
other source of pollutions. Where water is obtained from an existing well, which is within the
proximity of latrines, drains or other sources of pollutions, the well shall be properly chlorinated
before water is drawn from it for drinking. All such wells shall be closed securely and be

21

provided with a trap door that shall be dust proof and the opening shall be sealed.
A reliable pump shall be fitted to each covered well. The trap door shall be kept locked and
shall be opened only for cleaning and inspection, which shall be done at least once a calendar
month.
30.5.0 Washing and Bathing Place
The Contractor shall provide adequate washing and bathing places separately for men and
women. Such places shall be maintained in a clean and dry state.
30.6.0 Latrines and Urinals
30.6.1 The Contractor shall provide on the Project site, within accessible location, latrines and urinals
such places shall be maintained in a clean and hygienic state.
30.6.2 The calculation of the number of units which shall be provided, separately for men and
women, is based on the following criteria :
1)
Where the number of persons does not exceed 50 - 2 units
2)
3)

Where the number of persons exceeds 50, but does not exceed 100 3 units
Extra for every additional 100 persons
- 3 units

30.6.3 If women are employed on the Project site, separate latrines, screened from those provided
for men, shall be provided. They shall be clearly marked For Women Only in local language.
A poster / symbol showing the figure of women shall be exhibited at the entrance of the
latrines. There shall be an adequate water supply close to the latrines.
30.6.4 The latrines and urinals for men shall be separate and screened from the womens. They shall
be clearly marked For Men Only in local language. A poster / symbol showing the figure of a
man shall be exhibited at the entrance of the latrines. There shall be an adequate water supply
close to the latrines.
30.6.5 The latrines shall be :
i) If a water borne sewage system is available, be water-flushed latrines; or
ii) Receptacles on a dry earth system which shall be cleared four times daily and at least
twice during the working hours. The latrines shall be kept in a strictly sanitary condition.
30.6.6 The latrine structure shall be constructed of masonry or some suitable heat resistant nonabsorbent material. It shall be cement plastered inside and outside and painted at least once a
calendar year. The latrine shall have insulated water proof roofs.
30.7.0 Disposal of Excreta
The Contractor shall make arrangements for proper disposal of excreta approved by the
Municipal Medical Office of Health in whose jurisdiction the project site is located.
30.8.0 Provision of Shelter
At the project site, the Contractor shall provide, free of cost, two suitable sheds for meals, one
each for men and women, to be used by the labour force. The sheds shall be roofed with
insulated water proof material and flooring will be provided with a dwarf wall of 750 mm. The
sheds shall be kept clean.
31.0.0 MANDATORY SAFETY GUIDELINES ON ELECTRIC ARC WELDING
Metal arc welding is hazardous and may pose substantial risk of electrical shock to the welder
and other persons working around him, if the hardware is not properly installed, or is not
maintained properly. The following guidelines are, therefore, mandatory and should be
followed without fail.
31.1.0 Welding Equipment:
a)
Welding equipment used should only be DC welding equipment i.e., a rectifier set or a
motor generator set. AC welding transformer sets should not be allowed inside the
22

b)
c)

Site/Factory to prevent any inadvertent use.


Welding equipment should conform to BS 638. Maximum open circuit voltage should
not exceed 100 V for the DC welding system.
Welding cable and return leads should be heavily insulated and there should be no
exposed live conductors. The electrode holder should be of fully insulated type with
no visible damage. There should be a welding cable connector within 3 feet of the
electrode holder with a male / female type plug socket connector which can be
disconnected by the welder.

31.2.0 Welding Circuit:


a)
The power supply to the each welding set should be through switch fuse unit (SFU)
for the main supply along with a 30mA ELCB in the circuit.
b)
Make sure that the metal part of the SFU is earthed properly with double earth.
c)
Make sure that the welding machine is suitably earthed with two earthing systems.
d)
Make sure that the welding cable and the return to the welding machine are
connected properly using suitable lugs, nut-bolts and washers etc.
e)
Make sure that there is a return cable from the workplace to the welding machine.
Make sure that the workplace is properly earthed to a sound earthing system using
proper connectors.
31.3.0 Working Procedures:
a)
Make sure that a competent person has checked that the welding equipment has
been correctly specified and installed accordingly.
b)
Make sure that welder and his helper has minimum personal protective equipment
(PPE) i.e. :
i) Proper welding screen.
ii) Proper welding gloves for both hands (fire resistant gauntlets
iii) Insulated safety shoes.
iv) Insulated mat or board for sitting / standing.
v) Flame proof skull cap
c)
Welder and his helper sit on an electrically insulated material while welding is in
progress.
d)
Make sure that a trained helper is available to the welder for the full tenure of his
welding job.
e)
SFU should be switched off during shot break of at the end of the days work.
f)
Make sure that no object is likely to fall from top while welding is in progress.
g)
Make sure before start of work that there is a valid `Safety work permit issued for the
job.
h)
Contractor shall get his welding sets certified by Elec. Section and these certificates
should be renewed every six months.
31.4.0 Maintenance:
a)
ELCBs should be tested every fortnight with an ELCB tester by a competent person
and recorded. Also, before every use of the equipment, the ELCB should be tested by
pushing the test button on the ELCB.
b)
Welding set and the associated electrical hardware should be checked by a
competent person once every month and record it.
c)
The welding supervisor / project engineer must check the PPE and welding hardware
every fortnight and defective ones must be removed from the site.
Quick Reference to Key Standards for Contractors at site
32.0.0 THIS IS NOT AN EXHAUSTIVE LIST FOR FULL DETAILS, REFER TO RELEVANT
STANDARDS
32.1.0 ENTRY:
1.
Entry only after Medical, Induction and with Photo ID card
2.
Re-induction and medical if there is 3 month break
3.
Entry only with Safety shoes, Helmet and proper dress (dhoti, loose clothing not
allowed)

23

4.

All electrical tools, welding m/c, lifting tools & tackles allowed entry & usage only after
certificat-ion by Electrical Inspectorate. Revalidation required every month for
electrical equipment & tools

32.2.0 WORK:
1.
Use of Personal Protective Equipment (PPE) compulsory
2.
All jobs to start only after valid work permit, authorised by designated Area In-charge
3.
Daily Tool-box talk to every worker before start of job
4.
Work above 1.8 Mtr with safety belt, duly anchored
5.
All jobs with adequate Supervision.
6.
High risk/ high hazard jobs should have 100% supervision from both contractor &
Client / Project management Team
7.
No High risk/ high hazard jobs after sunset
8.
Start High risk/ high hazard jobs only after risk assessment and approval by safety
officer
9.
Only crawling on beams. No walking.
10.
Use Lifeline and double hook safety belt, Fall arrestor etc. as per Risk assessment
11.
Only metal railing (not rope) around openings on floor /ground, trenches, building
edges.

We agree to the above conditions.


(TENDERER)

24

FORM

OF

TENDER

M/s. Onilla Infra Pvt Ltd


Hyderabad
Dear Sir,
1.0

Having examined the tender documents (contained hereto) relating to the works specified in the
Memorandum hereinafter set out and having visited and examined the site of the works specified
in the said Memorandum and having acquired the requisite information relating thereto as
affecting the tender, I/we hereby offer to execute the works specified in the said Memorandum at
the rates mentioned in the Schedule of Quantities hereto and in accordance with all respects of
the specifications, designs, drawings and instructions in writing referred to in the Tender Notice,
Articles of Agreement, General Conditions of Contract (including the Special Conditions),
Schedule of Quantities and with such materials as are provided for by and in all other respects in
accordance with such conditions so far as they may be applicable.
MEMORANDUM

1.1

1.2

Description of Work

Civil, Electrical, Plumbing works for proposed Farm House


at Jodupal Village, Madikeri.

Earnest Money Deposit

Nil

1.3

Performance Bond

2.5% (Two and Half Percent) of the Contract Value in the form
of a Bank guarantee valid for the duration of Contract &
Defects Liability Period.

1.4

Mobilisation Advance

10% of the contract value against submission of Bank


Guarantee.

1.5

Retention Money to
Account be deducted

:
:

1.6

Release of Retention
:
Liability Period Money

5% (Five Percent) of Certified Gross Value from the Running


bills.
50% on virtual completion and balance 50% after Defects
:
th

1.7

Date of Commencement :

7 Day from the date of Issue of Letter of Intent

1.8

Period of Completion

12 Months

1.9

Defects Liability period :

12 (Twelve) Months from the Date of Certification of the Final


Bill

1.10

Amount of Liquidated
:
Damages (penalty for delay)

1% of the Contract value per week of delay limited to 5% after


which the Employer may terminate the Contract if the
contractor makes up the Short-fall in the stipulated time of
completion, penalty may be refunded receiving written
application by the contractor.

1.11

Period of Final
Measurements

2 (Two) Months from the date of Virtual Completion.

1.12

Value of Running Bill

Minimum value Rs.40 Lakhs & above.

1.13

Period of checking

15 (Fifteen) Days from date of receipt of Contractors Bills with


all clear Interim bills and issuing measurements along with
measurement sheets, Bar Bending Schedule. Certificate
Rate Analysis for Non Tendered Items of Work if any and other

25

supporting purchase bills / documents / Vouchers


1.14

Period of Honoring
Architects Certificates

:
:

1.15

Water for Construction


:
Architects Certificates :

10 (Ten) Days from the date of receipt by the Employer.

10 (Ten) Days from the date of receipt by the Employer.

2.0

Should this tender be accepted, I/we hereby agree to abide by and fulfill the terms and provisions
of the said Conditions of Contract so far as they may be applicable or in default thereof to forfeit
and pay to ______________________, amount mentioned as "Liquidated Damages" in said
Memorandum.

3.0

In accordance with Clause 11.0 of Notice Inviting Tender, I/we have enclosed herewith (in a
separate envelope):

3.1

A Demand Draft / Banker's Cheque No._____________ Dated ____________ drawn on


_____________________ (Bank) for Rs.________/- (Rupees ___________________________
Only) payable at Bangalore, favoring ____________________ towards the requisite Earnest
Money. Should I/we fail to execute the Contract when called upon to do so, I/we do hereby agree
that this sum shall be forfeited by me/us to ____________________.

3.2

Xerox copy of the latest Income Tax Clearance Certificate dated ________ issued to me/us by
____________________ as required under Clause 32.0 of Notice Inviting Tender.

3.3

Certified true copy of the Power of Attorney (as applicable) in terms of Clause 7.0 below.

4.0

My / Our address is

5.0

My / Our Bankers are:

________________________________________,
________________________________________
________________________________________

5.1

________________________________________
________________________________________
________________________________________

5.2

________________________________________
________________________________________
________________________________________

6.0

The names of the Partners of our Firm are:


6.1
_______________________________________
6.2
_______________________________________
6.3
_______________________________________

7.0

The name of the Director of


our firm authorized to sign is

:
: ______________________________________
OR
Name of person having power of :
attorney to sign the contract is :______________________________________
(certified true copy of the power of attorney is enclosed).
Yours faithfully,

Place : _______________
Date : _______________

Signature of the Tenderer

26

FORM

OF

ARTICLES OF AGREEMENT

(To be executed by the Successful Tenderer on Rs.100/- non-judicial Stamp Paper in terms of Clause
2.1.1 of the General Conditions of Contract)
ARTICLES OF AGREEMENT made at _____________ the
____________ day of
__________________ between M/s. ________________ ____________, _________ _______ _______
________, __________________ (hereinafter called "the EMPLOYER") of the one part, and M/s.
___________________________, whose registered office is situated
at _________
_____________________________________________ hereinafter called "the CONTRACTOR") of the
other part.
WHEREAS the EMPLOYER is desirous of getting the for Construction of
___________________________ at ________ ________ _ _ __________ ___ ______ (hereinafter
called "the WORK") and has caused Drawings, Specifications and Schedule of Quantities showing and
describing the WORK to be done to be prepared by or under the direction of M/s. MINDSPACE, No. 3,
nd
Kalpana Chawla Road, R.M.V. 2 Stage, Sanjay Nagar, Bangalore - 560 094 (hereinafter called "the
ARCHITECTS").
AND WHEREAS the CONTRACTOR has supplied the EMPLOYER with a fully priced copy of
the said Schedule of Quantities (which copy is hereinafter referred to as "the CONTRACT BILLS")
amounting to Rs._____________________ (Rupees ________________________________________
_________________________________ Only) (hereinafter referred to as "the CONTRACT SUM").
AND WHEREAS the said Drawings (hereinafter referred to as "the CONTRACT DRAWINGS")
and the CONTRACT BILLS have been signed by or on behalf of the parties hereto.
AND WHEREAS the CONTRACTOR has deposited a Bank Guarantee bond bearing No.
__________________________ dated ____________ for a sum of Rs. ____________ (Rupees
___________________________________________________________ Only) issued by ___________
__________________________________ (Bank) with the EMPLOYER, for the due performance of this
Agreement.
NOW IT IS HEREBY AGREED BY AND BETWEEN THE PARTIES HERETO AS FOLLOWS:
1.

For the consideration hereinafter mentioned, the CONTRACTOR will upon and subject to the
Conditions Annexed carry out and complete the WORK shown upon the CONTRACT
DRAWING and described by or referred to in the CONTRACT BILLS and in the said Conditions
and said Specifications.

2.

The EMPLOYER will pay the CONTRACTOR the CONTRACT SUM or such other sum as shall
become payable hereunder at the times and in the manner specified in the said Conditions.

3.

The term "the ARCHITECT" in the said Conditions shall mean the said M/s. MINDSPACE, No. 3,
nd
Kalpana Chawla Road, R.M.V. 2 Stage, Sanjay Nagar, Bangalore - 560 094, or in the event of
their ceasing to be the ARCHITECT for the purpose of this Contract, such other person as the
EMPLOYER shall nominate for that purpose, not being a person to whom the CONTRACTOR
shall object for reasons considered to be sufficient by an Arbitrator appointed in accordance with
the said Conditions. Provided always that no person subsequently appointed to be the Architect
under this Contract shall be entitled to disregard or over-rule any certificate or opinion or decision
or approval or instruction given or expressed by the Architect for the time being.

4.

The said Conditions, Specifications, Contract Bills, Contract Drawings, all other documents
attached hereto and signed or initialed by both parties shall be read and construed as forming
part of this Agreement and the parties hereto will abide by and submit themselves to the
Conditions and stipulations and perform the agreements on their respective parts.
All disputes arising out of or in anyway connected with this Agreement shall be deemed to have
arisen in Bangalore and only the Courts in Bangalore shall have jurisdiction to determine the
same.
27

AS WITNESS our hands this ______________ day of ____________ 2014


Signed by the EMPLOYER

In the presence of
Witnesses:
1.
2.
Signed by the CONTRACTOR

In the presence of
Witnesses:
1.
2.

28

PROFORMA OF BANK GUARANTEE (PERFORMANCE)


To,

WHEREAS the ________ __________ ____________ __________ ________ (hereinafter called


"Client" which expression shall include its successors and assigns) having awarded a work order /
contract supply order No. ____________, Dated _________________ (hereinafter called "the Contract")
for Works for their Proposed Construction of _________ ___________ ________ on ________
________Road,
______
________
_______
to
M/s.
___
__________________
_________________________________ ______________________ (hereinafter called the contractor /
supplier) at a total price of ______________ subject to the terms and conditions contained in contract.
WHEREAS the terms and conditions of the contract required, the Contractor to furnish a bank guarantee
for Rs. _________________ (Rupees ____________________________________) being _____% of
the total value of the Contractor for proper execution and due fulfillment of the terms and conditions
contained in the contract.
We, the _______________________ Bank, (hereinafter called the "Bank" do hereby unconditionally and
irrevocably undertake to pay to Client immediately on demand in writing and without protest / or demur all
moneys payable by the contractor / supplier to Client in connection with the execution / supply of and
performance of the works / equipment, inclusion of any loss, damages, charges, expenses and costs
caused to or suffered by on which would be caused to or suffered by Client by reason of any breach by
the contractor / supplier of any of the terms and conditions contained in the contract as specified in the
notice of demand made by Client to the bank. Any such demand made by Client on the bank shall be
conclusive evidence of the amount due and payable by the bank under this guarantee. However, the
bank's liability under this guarantee shall be limited to Rs. ______________ in the aggregate and the
bank hereby agrees to the following terms and conditions:1.

This guarantee shall be a continuing guarantee and irrevocable for all claims of Client as
specified above and shall be valid during the period specified for the performance of the contract
including the period of maintenance / warranty i.e., up to ________________

2.

We, the said bank further agree with Client that Client shall have the fullest liberty without
consent and without effecting in any manner our obligations and liabilities hereunder to vary
any or the terms and conditions of the said contract or extend time for performance of contract
by the contractor from time to time any of the powers exercisable by Client against the contractor
/ supplier under the contract and forbear or enforce any of the terms and conditions relating to
the said contract and we shall not be relieved from any liability by reason of any such variations
or extension being granted to the contractor or for any forbearance, act or omission on the part of
Client of any indulgence by Client to the contractor or by any such matter a thing whatsoever,
which under, the law relating to the sureties would, but for this provision, have effect of so
relieving us.

3.

This guarantee / undertaking shall be in addition to any other guarantee or security whatsoever
Client may now or at any time have in relation to the performance to the works / equipment and
the company shall have full resource to or enforce this security in performance to any other
security or guarantee which Client may have or obtain and there shall be no forbearance on the
part of the company in enforcing or requiring enforcement of any other security which shall have
the effect on releasing Bank from its full liability. It shall not be necessary for Client to proceed
against the said contractor / supplier before proceeding against the bank.

4.

This guarantee / undertaking shall not be determined or affected by the liquidation or winding up,
dissolution or change of constitution or insolvency of the supplier / contractor, but shall in all
respects and for all purpose be binding and operative until payment of all moneys payable to
Client in terms thereof are paid by the Bank.

29

5.

The bank hereby waives all rights at any time inconsistent with the terms of this Guarantee and
the obligations of the Bank in terms hereof shall not be otherwise effected or suspended by
reasons of any dispute or disputes having been raised by the supplier / contractor (whether or
not pending before any arbitrator, Tribunal of Court) or any denial of liability by the supplier /
contractor stopping or preventing or purporting to stop or prevent any payment by the bank to
Client in terms hereof.

6.

We the said banks lastly undertake not to revoke this Guarantee during its currency except with
the previous consent of Client in writing. Unless a claim is made in writing within six months from
the date of expiry of this guarantee i.e. ________________________, we shall be relieved from
all liabilities under this guarantee thereafter.

Signed this ______________________ day of _______________ at

Bank

For and on behalf of:

Witnesses:
1.

2.

30

GENERAL CONDITIONS OF CONTRACT


(Referred to in Condition 1 of "Articles of Agreement")
1.0

DEFINITIONS:

1.1

The contract document shall consist of the various documents listed under Clause 2.0 herein
below.

1.2

The "Employer/Owner"

M/s. Onella Infra Pvt Ltd, Hyderabad

1.3

The "Contractor"

Name of the successful contractor.

1.4

The "Architect"

M/s. MINDSPACE, No. 3, Kalpana Chawla Road,


nd
R.M.V. 2 Stage, Sanjay Nagar, Bangalore - 560
094

1.5

The "Project Management


Consultant"

:
:

1.6

The Employer, the Contractor and the Architect are those mentioned as such in the Agreement
and shall include their legal representatives, assigns or successors. They are treated throughout
the Contract Document as if each were of the singular number and masculine gender.

1.7

The "Site" shall mean the site of the Contract Works including any building and erections
thereon and any other land allotted by Employer for Contractor's use.

1.8

The term "Sub-Contractor", as employed herein, includes those having a direct contract with the
Contractor and it includes one who furnishes materials worked to a special design according to
the plans or specifications of the Work but does not include one who merely furnishes materials,
not so worked. Any one doing work on a piece rate basis shall be deemed a Sub-Contractor.

1.9

"Written Notice" shall be deemed to have been duly served if delivered in person to the
individual or to a member of the firm or to an office of the Corporation for whom it is intended, or
if delivered at or sent by registered mail to the last business address known to him who gives the
notice.

1.10

The term "Work" of the Contractor or Sub-Contractor includes Labour or material or both.

1.11

"Clerk of Works" shall mean the person appointed by the Employer to inspect and certify
measurements of the Works at Site.

1.12

All time limits stated in Contract Document are of the essence of Contract

1.13

The law of the place of work shall govern the construction under this contract.

1.14

The "Date of Virtual Completion" of the Work or specified portion of the Work is the date when
construction is sufficiently completed, in accordance with the Contract Documents as modified by
any change or variation order agreed to by the parties, so that the Employer can take over such
completed work and occupy for the use it was intended.

2.0

CONTRACT DOCUMENT:

2.1

The following documents shall constitute the Contract Document:

2.1.1

Articles of Agreement (executed by the Employer and the Contractor).

2.1.2
2.1.3

Notice Inviting Tender.


Instructions to Tenderers.

31

2.1.4

Form of Tender (submitted by the Contractor).

2.1.5

General Conditions of Contract

2.1.6

General specifications.

2.1.7

Common specifications.

2.1.8

Detailed item specifications.

2.1.9

Drawings submitted with the tender in terms of Clause 3.0 of the Tender Notice.

2.1.10 Contract Bills (including all modifications thereof incorporated before execution of the
Agreement).
2.1.11 Letters (if any) accompanying the tender.
2.1.12 Correspondences (if any) between the parties hereto after submission of tender and the
Employer's Letter of Acceptance of the Tender
2.1.13 Letter of acceptance of the tender (or Work Order) issued to the Contractor by the Employer
2.1.14 Further, drawings and/or instructions issued by the Architect/Employer from time to time relating
to the Works.
2.1.15 Samples, Shop Drawings and Progress Charts referred to in Clauses 12.0 and 13.0 herein
below.
2.2

The Contract Document is complementary. What is called for in any one shall be as binding as if
called for by all.

2.3

The original Contract Document shall remain in the custody of the Employer so as to be available
at all reasonable times for the inspection of the Architect or of Contractor. Immediately after
execution of the Contract Agreement, one copy of Contract Document shall (without charge) be
supplied to Contractor

2.4

So soon as is possible after the execution of this Contract, two copies of the Specifications,
Drawings, Descriptive Schedules or other like documents necessary for use in carrying out the
Work shall (without charge) be supplied to the Contractor. Provided that nothing contained in the
said specifications, descriptive schedules or other documents shall impose any obligation
beyond those imposed by the Contract Document namely, the Contract Drawing, the Contract
Bills, the Articles of Agreement and this General Conditions of Contract.

2.5

After the award of the Contract, the Contractor (without charge) shall be supplied two copies of
all such further drawings and details as may be prepared by the Architect/Employer from time to
time as the Work proceeds as are reasonably necessary either to explain or amplify the Contract
Drawings or to enable the Contractor to carry out and complete the Work in accordance with this
General Conditions of Contract. Provided all such drawings and details shall be a reasonable
development of the Work described in the Contract Document.

2.6

The Contractor shall keep upon the Site one copy of the Specifications, Drawings, Descriptive
Schedules or other like document referred to in Clauses 2.4 and 2.5 above, and written
instructions referred to in clauses 8.0, 15.2 and 29.0 herein below so as to be available to the
Architect/Employer or his representative/s at all reasonable times.

2.7

None of the documents hereinbefore mentioned shall be used by the Contractor for any purpose
other than this Contract and neither the Employer nor the Architect shall divulge or use any of the
prices in the Contract Bills except for the purpose of this Contract.

2.7

Towards the issue of Final Certificate under Clause 30.8 herein below, the Contractor shall if so
requested by the Architect forthwith return to the Architect all Drawings, Details, Specifications,
32

Descriptive Schedules and other documents of like nature which bears his name.
3.0

TYPE OF CONTRACT:
The Contract shall be an item-rate contract. The Contractor shall be paid for the actual quantity
of work done, as measured at site, at the accepted contract rates as provided in the Contract
Bills.

4.0

SCHEDULE OF QUANTITIES / CONTRACT BILLS:


The quantities given in the Schedule of Quantities are provisional and are meant to indicate the
intent of the work and to provide a uniform basis for tendering. The Architect and/or Employer,
reserves the right to increase or decrease any of the quantities or to totally omit any item
of work and the Contractor shall not claim any extra or damages on these grounds.

4.2.

The quality and quantity of work included in the Contract Sum shall be deemed to be that which
is set out in the Contract Bills which bills, unless otherwise expressly stated in respect of any
specified item, shall be deemed to have been prepared in accordance with the principles of the
Standard Method of Measurement of Building Works last before issued by the Indian Standard
Institution but save as aforesaid nothing contained in the Contract Bills shall override, modify or
affect in anyway whatsoever the application or interpretation of that which is contained in any of
the clauses of this General Conditions of Contract.

4.3

Any error in description or in quantity or omission of items from the Contract Bills shall not vitiate
this contract but shall be treated as a variation under Clause 29.0 herein below.

5.0

CONTRACT DRAWINGS:

5.1

In general, the Drawings shall indicate dimensions, positions and type of construction; the
Specifications shall indicate the qualities and the methods; and the Bill of Quantities shall indicate
the quantum and the rate for each item of work. Any work indicated on the Drawings but not
mentioned in the Specification or vice-versa shall be furnished as though fully set forth in both.
Work not specifically detailed, called for, marked or specified shall be the same as similar parts
that are detailed, marked or specified.

5.2

The Contractor's work shall not deviate from the Drawings and the Specifications.
Architect's interpretation of these documents shall be final and without appeal.

5.3

Errors or inconsistencies discovered by the Contractor in the Drawings and Specifications shall
be promptly brought to the attention of the Architect, through the Clerk of Works, for
interpretation or correction. Local conditions which may affect the Work shall likewise be brought
to the Architect's attention. If at any time, it is discovered that Work is being done which is not in
accordance with the Contract Drawings and Specifications, the Contractor shall correct the work
immediately. Corrections of defective work shall not be a basis for any claim for extension of
time. The Contractor shall not carry on work except with the knowledge of the Clerk-of-Works.

5.4

Figured dimensions on the Scale Drawings and large size details shall take precedence over
small scale drawings. Any work done before receipt of such details, if not in accordance with the
same, shall be removed and replaced or adjusted by the Contractor at his own expense to the
satisfaction of the Architect/Employer. This General Condition shall apply with equal force to all
the Work including authorized extra works.

5.5

All drawings, Bill of Quantities and Specifications including copies thereof furnished to the
Contractor are the property of the Architects and Employer. They shall not be used on any other
work and shall be returned to the Architect or Employer on request upon completion or
termination of Contract.

5.6

Steel requirement and/or bar bending schedules shall given by the contractor to the Employer/
Architects based on the drawings issued to them well in advance so as to procure steel.

6.0

CONTRACT SUM: The contract sum shall not be adjusted or altered in any way whatsoever
otherwise than in accordance with the express provisions of this General Conditions of Contract,

The

33

and subject to Clause 5.2 above, any error (whether of arithmetic or otherwise) in the
computation of the Contract Sum shall be deemed to have been accepted by the parties hereto.
7.0

SCOPE AND INTENT:

7.1

SCOPE: The general character and the scope of the Work is illustrated and defined by the
signed Drawings, the Specifications and the Bill of Quantities hereto annexed. If the Contractor
shall find any discrepancy in or divergence between the Contract Drawings, Specifications and/or
the Contract Bills, he shall immediately give to the Architect/Employer a written notice specifying
the discrepancy or divergence and the Architect/Employer shall issue instructions in regard
thereto.

7.2

EXTENT: The Contractor shall carry out and complete the Work in every respect in accordance
with this Contract and with the directions of and to the reasonable satisfaction of the Employer
/Architect. The Architect may, in his absolute discretion and from time to time, issue further
drawings, details and/or written instructions, written directions and written explanations all of
which are collectively referred to as Architect's Instructions. All such Drawings and Instructions
shall be consistent with Contract Document, true developments thereof and reasonably inferable
there from.

7.3

INTENT: The intention of the Document is to include all labour and materials, equipment and
transportation necessary for the proper execution of Work. Materials of work described in words,
which so applied have a well known technical / trade meaning, shall be held to refer to such
recognized standard.

8.0

ARCHITECT'S INSTRUCTIONS:

8.1

The Contractor shall forthwith comply with and duly execute any such works comprised in such
instructions issued to him by Architect in regard to any matter in respect of which Architect is
expressly empowered by these Conditions to issue instructions. Provided always that verbal
instructions, directions and explanations given to the Contractor (or his work representative) by
Architect shall if involving a variation be confirmed in writing. If within seven days after receipt of
a written notice from Architect, requiring compliance with an instruction the Contractor does not
comply herewith, then the Employer may employ and pay other persons to execute any work
whatsoever which may be necessary to give effect to such instructions and all cost incurred with
such employment shall be recoverable from the Contractor by the Employer as a debt or may be
deducted by him from any moneys due or to become due to the Contractor under this Contract

8.2

Upon receipt of what purports to be instruction issued to him by the Architect, the Contractor may
request the Architect to specify in writing the provision of these conditions which empowers the
issue of the said instruction. The Architect shall forthwith comply with any such request, and if the
Contractor shall thereafter comply with the said instruction, then the issue of the same shall be
deemed for all purposes of this Contract to have been empowered by the provision of these
Conditions specified by the Architect in answer to the Contractor's request

8.3

All instructions issued by the Architect shall be in writing with copy to the Employer. Any
instruction issued orally shall be of immediate effect, but shall be confirmed in writing by the
Contractor to the Architect within seven days, and if not dissented from in writing by the Architect
to the Contractor within seven days from receipt of the Contractor's confirmation shall take effect
as from the expiration of the latter said seven days

8.3.1

8.3.2

Provided always :
That if the Architect within seven days of giving such an oral instruction shall himself confirm the
same in writing, then the Contractor shall not be obliged to confirm as aforesaid, and the said
instruction shall take effect as from the date of the Architect's confirmation and;
That if neither the Contractor nor the Architect shall confirm such an oral instruction in the
manner and at the time aforesaid but the Contractor shall nevertheless comply with the same,
then the Architect may confirm the same in writing at any time prior to the issue of the Final
Certificate, and said instruction shall thereupon be deemed to have taken effect on the date on

34

which it was issued.


8.4

Clerk of Works shall maintain a log of all verbal instructions and changes issued at site

9.0

FACILITIES AND CO-OPERATION:

9.1

In the case of works indicated on the Drawings but not included in the contract the, Contractor
shall provide necessary facilities and co-operation for any Sub-contractor or supplier who may be
approved by the Employer. The Contractor shall do all cutting, filling or patching of his work that
may be required to make its several parts come together properly and fit it to receive or be
received by work of other contractors shown upon or reasonably implied by the Drawings and
Specifications for the completed structure, and he shall make good all such cutting, filling or
patching after completion of works of other contractors as the Architect may direct Any cost
caused by the defective or ill-timed work shall be borne by party responsible therefore.

9.2

The Contractor shall not endanger any work by cutting, excavating or otherwise altering the work
and shall not cut or alter the work of any other contractor save with the consent of the
Architect/Employer.

10.0

SETTING OUT:

10.1

The Architect shall determine any lines, levels, etc. which may be required for the execution of
the Work and shall furnish to the Contractor by way of accurately dimensioned drawings such
information as shall enable the Contractor to set out the Work at ground level.

10.2

The Contractor shall set out and level the Work and shall be responsible for the accuracy of the
same. He shall provide all the instruments and attendance required by the Architect/Employer
for checking the Work. He shall entirely at his own cost amend to satisfaction of Architect
/Employer any error found at any stage which may arise through inaccurate setting.

10.3

Dimensioned drawings, levels and other information necessary to enable the contractor to set
out the works shall be prepared by the Architects and released to the contractor through the
Project Engineer.

10.4

The contractor shall set out the works and shall be responsible for the true and proper setting out
of the works and for the correctness of the position, levels, dimensions and alignment of all parts
of the works and far the provision of all necessary instruments, appliances and labour in
connection therewith. If at any during the progress of the works any error shall ,appear or arise in
the position, levels, dimensions or alignment of any part of the works, the contractor, on being
required to do so by the Architects / Project Engineer, shall at his own expenses rectify such
error to the satisfaction of the Architects / Project Engineer. The checking of any setting out or of
any line or level by the Architects or their supervision team shall not in any way relieve the
Contractor of his responsibility for the correctness thereof and the Contractor shall carefully
protect and preserve all bench marks, sight rails, pegs and other things used in setting out the
works.

11.0

SITE:

11.1

VISIT: Before tendering, the Contractor shall have visited and examined the site and satisfied
himself as to the nature of the existing roads or other means of communication and the
character of the soil and of the excavations, the correct dimensions of the Work and the facilities
for obtaining any special articles called for in the Contract Document and shall have obtained
generally his own information on all matters affecting the commencement, continuation and
progress of the Works. No extra charge made in consequence of any misunderstanding or
incorrect information of any of these points, or on the grounds of insufficient description, will be
allowed. Should the Contractor after visiting the Site, find any discrepancies, omissions,
ambiguities or conflicts in or among the Contract Document, or to be in doubt as to their
meaning, he shall bring the questions to the Architect's attention, not later than seven days
before last date for submission of tender and obtain all necessary clarifications thereto
POSSESSION: The Contractor shall be allowed admittance to the Site on the "Date of

11.2

35

Commencement" stated in the Appendix hereto and he shall thereupon and forthwith begin the
Work and shall regularly proceed with and complete the same on or before the "Date of
Completion" stated in the Appendix hereto subject nevertheless to the provision for extension of
time hereinafter contained.
11.3

TREASURES: Any Treasures, coins or objects of Antiquity, which may be found at site shall be
handed over to the Employer.

12.0

SAMPLES AND SHOP DRAWINGS:

12.1

After the award of the Contract, the Contractor shall furnish to the Clerk of Works for the
approval of the Architect, with such promptness as to cause no delay in his work or in that of any
other Sub-contractor, samples and shop drawings required by the specifications or by the
Architect / Employer. Samples shall be delivered free of cost.

12.2

A schedule giving dates for the submission of samples shall be included in the schedule
described under Clause 13.0 herein below. Unless specifically authorized, all samples must be
submitted for approval within thirty days before the date the particular work involved is scheduled
to begin.

12.3

The Architect shall check and approve such samples, with reasonable promptness only for
conformity with the design concept of the Works and for compliance with the information in the
Contract Documents. The Work shall be in accordance with the approved samples.

13.0

PROGRESS CHART:
The Contractor shall prepare progress charts and submit the same for approval of Architect and
for his record within ten days of award of Contract.
The charts shall indicate the "expected dates" of commencement and completion of each of the
items of the Work and shall be in a form approved by the Architect. The charts shall also
indicate the scheduling of samples, shop drawings and the approvals. The charts as approved
by the Architect will form part of the Agreement.

14.0

ACCESS FOR ARCHITECT/EMPLOYER TO THE WORKS:


The Architect/Employer and his representatives shall at all reasonable times have access to the
Works and to workshops or other places of the Contractor where work is being prepared for the
Contract and when Work is to be so prepared in workshops or other places of a Sub-contractor
(whether or not a nominated Sub-contractor as defined in Clause 25.0 herein below), the
Contractor shall have a term in the Subcontract so as to secure a similar right of access to those
workshops or places for the Architect/Employer and his representatives and shall do all things
reasonably necessary to make such right effective

15.0

ARCHITECT'S STATUS AND DECISIONS:

15.1

The Architect shall be the Employer's representative during the construction period. The
Architect shall periodically visit the site to familiarize himself generally with the progress and the
quality of the work and to determine in general if the Work is proceeding in accordance with the
Contract Document. He shall not be required to make exhaustive or continuous on site
inspection to check the quality or quantity of the work and he shall not be responsible for the
Contractor's failure to carry out the construction work in accordance with the Contract Document.
During such visits and on the basis of his observations while at the Site he shall keep the
Employer informed of the progress of the Work, shall endeavor to guard the Employer against
defects and deficiencies in the Work of the Contractor and he shall condemn work which fails to
conform to the Contract Document. He shall have authority to act on behalf of the Employer only
to the extent expressly provided in the Contract Document or otherwise in writing which shall be
shown to the Contractor. He shall have authority to stop the Work, whenever such stoppage
may be necessary in his reasonable opinion to ensure proper execution of the Contract. The
Architect shall be in the first instance the interpreter of the Conditions of this Contract
and the judge of its performance. He shall side neither with the Employer nor with the

36

Contractor but shall use his powers under the Contract to enforce its faithful performance by
both. In case of the termination of the appointment of Architect, the Employer shall appoint a
capable and reputable Architect against whom the Contractor shall make no reasonable
objection and whose status under the Contract shall be that of the former Architect. Any dispute
in connection with such appointment shall be subject to Arbitration.
15.2

DECISION: The Architect shall within a reasonable time make decisions on all claims of the
Employer or the Contractor and all other matters relating to the execution and progress of the
Work or the interpretation of the Contract Document. The Architect may in his absolute
discretion and from time to time issue further drawings, details and/or written instructions, written
directions and written explanations in regard to:
15.2.1

Variation or modifications of the design.

15.2.2

The quality / quantity of works / the additions / omission / substitution of any work.

15.2.3

Any discrepancy in or divergence between the Drawings and/or specifications.

15.2.4

Removal and/or re-examination of any works executed by the Contractor

15.2.5

The dismissal from the Works of any persons employed thereon.

15.2.6

Opening up for inspection of any work covered up.

15.2.7

Amending & making good of any defects under Defects Liability Period.

15.2.8

Removal from the Site of any materials brought thereon by the Contractor and the
substitution of any other material therefore.

15.2.9

Assignment and subletting.

15.2.10

Delay and extension time.

15.2.11

Postponement of any work to be executed under the provision of this Contract.

15.3

DISMISSAL: The Contractor shall on the request of the Employer/Architect immediately


dismiss from the Works any person employed thereon by him who may in the opinion of the
Employer/Architect be incompetent or misconducts himself and such person shall not be again
employed on the Work without the permission of the Employer/Architect.

16.0

PERFORMANCE BOND (SECURITY DEPOSIT):

16.1

Within ten days of the award of the Contract, the Contractor shall deposit with the Employer a
sum which shall be equal to that referred to in the Appendix hereto as SECURITY DEPOSIT for
due performance of the Contract.

16.2

The SECURITY DEPOSIT shall be in the form approved by the Employer and shall remain so
deposited with the Employer till the end of the Date of Completion referred to in the Appendix
hereto. If the work is not completed within the stipulated time of completion, the Bank Guarantee
should be extended for the corresponding extension period.

16.3

The said SECURITY DEPOSIT shall indemnify the Employer against loss from defects arising
from any clause under this Contract or due to the failure of Contractor to promptly carry out any
matters arising under this Contract.

17.0

CLERK OF WORKS:

17.1

The Contractor shall afford the Clerk of Works every facility and assistance for inspecting the
Works and materials and for checking and measuring time and materials. Neither the Clerk of
Works nor any representative of the Architect shall have power to set out Works or to revoke,

37

alter, enlarge or relax any requirements of the Contractor to sanction any day work, additions,
alterations, deviations or omissions, or any extra work whatever except in so far as such
authority may be specially conferred by a written order of Architect / Employer
17.2

The Clerk of Works or any representative of the Architect shall have power to give notice to the
Contractor or to his representative of non-approval of any work or materials and such work shall
be suspended or the use of such materials shall be discontinued until the decision of the
Architect is obtained. The Works will from time to time be examined by the Architect, the Clerk of
Works or the Architect's representative but such examination shall not in any way exonerate the
Contractor from the obligation to remedy any defects which may be found to exist at any stage of
the Works or after the same is completed. Subject to the limitation of this clause, the Contractor
shall take instructions only from the Architect/Employer.

17.3

SITE ORDER BOOK


Throughout the construction period, the Contractor shall at his' own cost maintain a "Site Order
Book at site with the Project Engineer to enable the Architects/Directors/Project Adviser/Project
Engineer to issue written instructions to the Contractor from time to time. On no account shall the
Contractor accept instructions from any persons except those authorised by the
Architects/Director/Project Adviser/Project Engineer.
The Site Order Book shall be supplied by the Contractor within seven days of the receipt of order
to take up the works.
The Site Order Book shall be kept at the site of work under the custody of the Project Engineer
or the Project Engineer's Representative.
The Site Order Book shall have machine numbered pages in triplicate. Observations and
remarks pertaining to the construction, directions or instructions from the Director/Architects and
other authorised persons to be issued to the Contractor will all be entered ( in triplicate) in the
Site Order Book (except when such observations, directions or instructions are given by separate
letters). The Contractor or his authorised representative shall regularly note the entries in the Site
Order Book and also record therein the action taken or being taken by him complying with the
said directions or instructions or any relevant point relating to the work. The Contractor or his
representative may take away the duplicate page of the Site Order Book for his own record. In
case of supplementary items, claim may not be entertained unless supported by entries in the
Site Order Book. or any written order.
The first page of the Site Order Book shall contain the following particulars:Name of the work
Reference to Contract No
Date of opening the Site Order Book.
Name and address of the Contractor
Signature of the Contractor
Name and address of the authorised representative (if any) of the contractor
Specific purpose for which the Contractor's representative is authorised to act on behalf of the
contractor.
Signature of authorised representative duly attested by the contractor
Signature of Project Engineer / Architect
Date of actual completion of work.
Date of recording final measurements.
Note : Entries for completion and recording measurements above shall be filled in on completion
of work.

18.0

CONTRACTOR'S FIELD ORGANISATION AND EQUIPMENT:

18.1

WORKS MANAGER: The Contractor shall constantly keep on his Work during its progress one
qualified and competent Works Manager acceptable to the Employer/Architects (assisted by a
team of Engineers, Supervisors and Technicians) who will be responsible for the carrying out of
the Works to the true meaning of Drawings, Specifications, Schedule of Quantities and
Architect's instructions and directions, to the satisfaction of the Architect / Employer. Any
directions or instructions given to him (or to his assistants) by the Architect / Employer shall be
38

deemed to have been issued to the Contractor. Attention of the Contractor is called to the
importance of requesting instructions from the Architect before undertaking any work where
Architect's directions or instructions are required. Any such work done in advance of such
instructions will be liable to be removed.
18.2

EQUIPMENT: The Contractor shall provide and install all necessary barricades, hoists, ladders,
staging, scaffoldings, tools, tackles, plants, instruments, equipments etc. and all transport for
labor, materials and plant necessary for the proper carrying on execution, completion and
maintenance of the Work to the satisfaction of the Architect/Employer.

18.3

SECURITY: The Contractor shall make his own security arrangements to guard the Site and
Works at all times, at his own expense. The security arrangements shall be adequate to
maintain strict control on the movement of material and labor. The Contractor shall extend the
security arrangements to guard the materials stored and/or fixed on the premises by the Subcontractors.

18.4

STORAGE OF MATERIALS: The Contractor shall provide, erect, maintain and remove after
completion of the Works, proper temporary sheds for the storage and protection of the materials
etc. and also for the execution of Work which may be prepared on the Site.

18.5

SANITARY CONVENIENCES: The Contractor shall provide and erect all necessary temporary
sanitary conveniences for the site staff and the workmen maintain in a clean orderly condition,
clear away and deodorize the ground after removal.

18.6

SCAFFOLDING, STAGING, GUARDRAILS, ETC.: Contractor shall provide all necessary


temporary scaffoldings, staging, platforms, guardrails, stairs, etc. (with sufficiently strong and
adequate supports suitable for particular situations) which shall be required during construction.
The temporary access to various parts of work shall be rigid and strong enough to avoid any
chance of mishaps. The arrangement proposed shall be subject to the approval of Employer/
Architect.

19.0

TAXES:
Unless otherwise specified under clause 15.0 of Notice Inviting Tender, the Contractor shall
include in his tender for all incidentals towards Service Tax, Sales Tax, Works Contract Tax,
Excise Duty, Octroi and similar taxes, cesses, duties, levies, etc. legally payable and it shall be
assumed that his rates cover for all taxes, duties and levies and no claim on this account will be
entertained.

20.0

STATUTORY OBLIGATIONS, NOTICES, FEES AND CHARGES:

20.1

The Contractor shall comply with and give all notices required by any Government authority, and
instrument, rule or order made under any Act of Parliament or any regulation or bye-law of any
local authority relating to the Work or with whose system the same is or will be connected. The
Contractor, before making any variation from the Contract Drawings or Contract Bills
necessitated by such compliance, shall give to the Employer /Architect a written notice specifying
and giving reasons for such variations and the Employer/Architect may issue instructions in
regard thereto. If within 10 days of having given the said written notice, the Contractor does not
receive any instruction in regard to the matters therein specified, he shall proceed with the Work
conforming to the Act of Parliament, instrument, rule, order, regulations or bye-law in question
and any variation thereby necessitated shall be deemed to be a variation required by the
Employer /Architect

20.2

The Contractor shall pay and indemnify the Employer against liability in respect of any fees or
charges (including any rates and taxes) legally demandable under any Act of Parliament,
instrument, rule or order or any regulation or bye-law or any local authority in respect of the
Work.

21.0

ROYALTIES AND PATENT RIGHTS:


All royalties or other sums payable in respect of the supply and use in carrying out the Work as
desired by or referred to in the Contract Bills of any patented articles, process or inventions shall

39

be deemed to have been included in the Contract Sum, and the Contractor shall indemnify the
Employer from and against all claims, proceedings, damages, costs and expenses which may be
brought or made against the Employer or to which he may be put by reason of the Contractor
infringing or being held to have infringed any patent rights in relation to any such articles,
processes and inventions.
22.0

LICENSES & PERMITS FOR MATERIALS UNDER GOVT CONTROL:


Licenses and Permits for all materials under Government control shall be obtained by the
Contractor through the collaboration and help of the Employer. The Contractor shall include in
his tender all transport charges, procurement charges and other expenses likely to be incurred to
bring the materials to the Site.

23.0

WATER AND ELECTRICITY FOR CONSTRUCTION:


Unless otherwise specified under clause 20.0 of notice inviting tender, the Contractor will make
his own arrangements for the supply of Water and Electricity required for the works.

24.0

ASSIGNMENT OR SUB-LETTING:
The Contractor shall not without the written consent of the Employer assign this Contract, and
shall not without the written consent of the Employer /Architect (which consent shall not be
unreasonably withheld to the prejudice of the Contractor) sublet any portion of the Work.

25.0

SUB-CONTRACTOR:
As soon as practicable and before awarding any Subcontract, the Contractor shall notify the
Employer/Architect in writing the names of the Subcontractors proposed for the principal parts of
the Work and for such other parts as the Employer /Architects may direct, and shall not employ
any to whom the Employer /Architect may have reasonable objection. The Employer/Architect,
however, shall have power to obtain estimate and select other agencies to carry out any of the
Work as described below:

25.1

All specialists, merchants, tradesmen and others executing any works or supplying and fixing
any goods, who may be nominated or selected by the Employer /Architect shall be deemed to be
Sub-contractors employed by the Contractor and are to be referred as nominated
Sub-Contractors. No nominated Sub-contractor shall be employed on or in connection with the
Work against whom the Contractor shall make reasonable objection or (save where the
Employer /Architect and Contractor shall otherwise agree) who will not enter into a contract
providing:

25.1.1 That the nominated Sub-Contractor shall carry out and complete the sub-contract works in every
respect to the reasonable satisfaction of the Contractor and of the Employer /Architect and in
conformity with all the reasonable directions and requirements of the Contractor.
25.1.2 That the nominated Sub-Contractor shall observe, perform and comply with all the provisions of
this Contract on the part of the Contractor to be observed performed and complied with (other
than Clause 45.0 herein below) so far as they relate and apply to the sub-contract works or to
any portion of the same.
25.1.3 That the nominated Sub-Contractor shall indemnify the Contractor against the same liabilities in
respect of the sub-contract work as those for which Contractor is liable to indemnify the
Employer under this Contract.
25.1.4 That the nominated Sub-Contractor shall indemnify the Contractor against claims in respect of
any negligence, omission or default of such Sub-contractor, his servants or agents or any misuse
by him or them of any scaffolding or other plant, and shall insure himself against any such claims
and produce the policy or policies and premium receipts as and when required by the Contractor
or Architect.
25.1.5 That payment in respect of any work, materials or goods comprised in the sub-contract shall be
made within fourteen days after receipt by the Contractor of the Architect's certificate under Clause
30.0 herein below which states as due an amount calculated by including the total value of such
work, materials or goods, and shall when due be subject to retention by Contractor of the sums
mentioned in Clause 25.1.9 herein below.
40

25.1.6 That Employer/Architect and his representative shall have right of access to workshops and
other places of nominated Sub-contractor as mentioned in Clause 14.0 above.
25.1.7 That the sub-contract work shall be completed within the period or (where they are to be
completed in sections) periods therein specified, that the Contractor shall not without the written
consent of the Employer/Architect grant any extension of time for the completion of the
sub-contract work or any section thereof, and that the Contractor shall inform the
Employer/Architect of any representations made by the nominated Sub-Contractor as to the
cause of any delay in the progress of completion of the sub-contract work or of any section
thereof.
25.1.8 That if the nominated Sub-Contractor shall fail to complete the sub-contract work or (where the
sub- contract works are to be completed in sections) any section thereof within the period therein
specified or within any extended time granted by the Contractor with the written consent of the
Employer/Architect, and the Architect certifies in writing to the Contractor that the same ought
reasonably so to have been completed the nominated Sub-Contractor shall pay or allow to the
Contractor either a sum calculated at the rate therein agreed as Liquidated and Ascertained
Damages for the period during which the said work or any section thereof, as the case may be,
shall so remain or have remained incomplete or (where no such rate is therein agreed) a sum
equivalent to any loss or damage suffered or incurred by the Contractor and caused by the
failure of the nominated Sub-Contractor as aforesaid.
25.1.9 That the Contractor shall retain from the sum directed by the Architect having been included in
the calculation of the amount stated as due in any certificate issued under Clause 30.0 herein
below in respect of the total value of work, materials or goods executed or supplied by the
nominated Sub-contractor the percentage of such value named in the Appendix hereto as
"Retention Percentage" up to a total amount not exceeding a sum which bears the same ratio to
the sub-contract price as the unreduced sum named in Appendix hereto as "Limit of Retention
Fund" bears to the Contract sum; and that Contractor's interest in any sums so retained (by
whomsoever held) shall be fiduciary as trustee for nominated Sub-contractor (but without
obligation to invest); that the nominated Sub-contractor's beneficial interest in such sums shall
be subject only to the right of the Contractor to have recourse thereto from time to time for
payment of any amount which he is entitled under the Sub-contract to deduct from any sum due
or to become due to the nominated Sub-contractor; and that if and when such sums or any part
thereof are released to the nominated Sub-contractor they shall be paid in full if paid within
fourteen days of the date fixed for their release in the sub-contract.
25.2

Before issuing any certificate under Clause 30.0 herein below, the Architect may request the
Contractor to furnish to him reasonable proof that all amounts included in the calculation of the
amount stated as due on previous certificates in respect of the total value of work materials or
goods executed or supplied by any nominated Sub-Contractor have been duly discharged and if
the Contractor fails to comply with such request, the Architect shall issue a certificate to that
effect and thereupon the Employer may himself pay such amounts to any nominated
Sub-Contractor concerned and deduct the same from any sums due or to become due to the
Contractor.

25.3

The Contractor shall not grant to any nominated Sub-contractor any extension for the period
within which the sub-contract work or (where the sub-contract works are to be completed in
sections) any section thereof is to be completed without the written consent of the
Employer/Architect. Provided always that the Contractor shall inform the Employer/Architect of
any representation made by the nominated Sub-contractor as to the cause of any delay in the
progress or completion of the sub-contract work or any section thereof and that consent of
Employer/Architect shall not be unreasonably withheld.

25.4

If any nominated Sub-contractor fails to complete the sub-contract work or (where the
sub-contract works are to be completed in sections) any section thereof within the period
specified in the sub-contract or within the extended time granted by the Contractor with the
written consent of the Employer /Architect then if the same ought reasonably so to have been
completed the Architect shall certify in writing accordingly. Any such certificates shall be issued
to the Contractor and immediately upon issue the Architect shall send a duplicate copy thereof to
41

the nominated Sub-Contractor.


25.5

If the Employer/Architect desires to secure final payment to any nominated Sub-contractor before
final payment is due to the Contractor, and if such Sub- contractor has satisfactorily indemnified
the Contractor against any latent defects then the Architect may in an Interim Certificate include
an amount to cover the said final payment and thereupon the Contractor shall pay such
nominated Sub-contractor the amount so certified. Upon such final payment the amount named
in Appendix hereto, as "Limit of Retention Fund" shall be reduced by the sum which bears the
same ratio to the said amount as does such Sub-Contractor's sub-contract price to the Contract
Sum, and save for latent defects the Contractor shall be discharged from all liability for the work
materials or goods executed or supplied by such Sub-contractor under the sub-contract to which
the payment relates

25.6

Neither the existence nor exercise of foregoing powers nor anything else contained in this
General Conditions of Contract shall render Employer in any way liable to any nominated
Sub-contractor.
Where Contractor in the ordinary course of his business directly carried out works for which
Prime Cost or Provisional Sums are included in Contract Bills and the Employer/Architect is
prepared to receive tenders from other contractors for such items, then the Contractor shall be
permitted to tender for the same or any of them but without prejudice to the Employer's right to
reject the lowest or any tender If the Contractor's tender is accepted he shall not sublet the work
without the consent in writing of the Employer/ Architect.

25.7

25.8

25.9

It shall be a condition of any tender accepted under Clause 25.7 above that Clause 29.0 herein
below shall apply in respect of the Item Work included in the tender as if for the reference therein
to the Contract Drawings and the Contract Bills there were references to the equivalent
documents included in or referred to in the Tender.
Contractor shall allow for general attendance upon Sub-Contractors including free use of plant,
scaffolding etc. and is to allow them the use of sanitary convenience, facilities for storing
materials, other amenities & affording them all reasonable facilities for carrying out their
contracts.

26.0

Deleted

27.0

ARTISTS AND TRADESMEN:


The Contractor shall permit the execution of work not forming part of this Contract by artists,
tradesmen or others engaged by the Employer. Every such person shall for the purposes of
Clause 43.0 herein below be deemed to be a person for whom Employer is responsible and not
be a Sub-Contractor.

28.0

SEPARATE CONTRACTS:
The Employer reserves the right to let other contracts in connection with his work under similar
general conditions. The Contractor shall afford other contractors reasonable opportunity for
introduction and storage of their materials and the execution of their work, and shall properly
connect and coordinate his work with theirs. If any part of the Contractor's or Sub-contractor's
work depends for proper execution or results upon the work of any other contractor or
Sub-contractor, the Contractor shall inspect and promptly report to the Architect any defects in
such work that render it unsuitable for such proper execution and results. Failure of the
Contractor to so inspect and report shall constitute an acceptance of the other contractor's work
as fit and proper for the reception of his Work, except as to defects which may develop in the
other contractor's or Sub-contractor's work after execution of work. To ensure proper execution
of his subsequent work, Contractor shall measure work already in place & shall at once report to
Architect / Employer any discrepancy between executed work & Drawings.

29.0

VARIATIONS, PROVISIONAL AND PRIME COST SUMS:

29.1

Architect/Employer may issue instructions requiring a Variation and he may sanction in writing
any Variation made by Contractor otherwise than pursuant to an instruction of Employer/
Architect. No Variation required by Employer /Architect or subsequently sanctioned by him shall
vitiate this Contract.
The term "Variation" as used in these Conditions means the alteration or modifications of the

29.2

42

design, quality or quantity of the work as shown upon the Contract Drawings and desired by or
referred to in the Contract Bills, and includes the addition, omission or substitution of any work,
the alteration of the kind of standard of any of the materials or goods to be used in the Work,
and the removal from the Site of any works, materials or goods to be used in the Work and the
removal from the Site of any works materials or goods executed or brought thereon by the
Contractor for the purposes of Work other than work, materials or goods which are not in
accordance with this Contract.
29.3

The Employer/Architect shall issue instructions in regard to the expenditure of Prime Cost and
Provisional Sums included in the Contract Bills and of Prime Cost Sums which arise as a result
of instructions issued in regard to expenditure of Provisional sum.

29.4

All Variations required by the Employer/Architect or subsequently sanctioned by him in writing


and all work executed by the Contractor for which Provisional Sums are included in the Contract
Bills (other than work for which a tender may under Clause 25.7 herein above has been
accepted) shall be measured and recorded by the Contractor in the presence of the Clerk- ofWorks and submitted to the Architect who will value it after checking. The valuation of Variations
and of work executed by the Contractor for which a Provisional Sum is included in the Contract
Bills (other than work for which a tender has been accepted as aforesaid), unless otherwise
agreed, shall be made in accordance with the following rules:

29.4.1 The price in the Contract Bills shall determine the valuation of work of similar character executed
under similar conditions as work priced therein.
29.4.2 The said prices, where work is not of a similar character or executed under similar conditions as
aforesaid, shall be the basis of prices for the same so far as may be reasonable, failing which a
fair valuation thereof shall be made.
29.4.3 Where work cannot properly be measured and valued, the Contractor shall be allowed day-work
rates on the prices prevailing when such work is carried out (unless otherwise provided in the
Contract Bills):
a)
At the rates if any, inserted by the Contractor in the Contract Bills or
b)
When no such rates have been inserted, at the prevailing market rates for material and
labor and at the control rates for the controlled materials including in all cases rate for
delivery of material at Work.
Provided that in any case voucher specifying the time daily spent upon the work (and if required
by the Clerk of Works the workmen's names) and the materials employed shall be delivered for
verification to the Architect or his authorized representative not later than the end of the week
following that in which the work has been executed.
29.4.4 The prices in the Contract Bills shall determine the valuation of items omitted, provided that if
omissions substantially vary the conditions under which remaining items of work are carried out,
the prices for such remaining items shall be valued under rule 29.4.2 herein above.
29.5

Effect shall be given to the measurement and valuation of Variations under Clause 29.4 herein
above in Interim Certificates and by adjustment of the Contract sum; and effect shall be given to
the measurement and valuation of work for which a Provisional Sum is included in the Contract
Bills under the said Clause in Interim Certificate and by adjustment of the Contract Sum in
accordance with Clause 30.7 herein below.

29.6

If upon written application being made to him by the Contractor, the Architect is of the opinion
that a Variation or the execution by the Contractor of work for which a Provisional Sum is
included in the Contract Bills (other than work for which a tender made under Clause 25.7 above
has been accepted) has involved the Contractor in direct loss and/or expense for which he would
not be reimbursed by payment in respect of a valuation made in accordance with the rules
contained in Clause 29.4 above and if the said application is made within a reasonable time of
the loss or expense having been incurred then the Architect shall ascertain the amount of such
loss or expense. Any amount from time to time as ascertained shall be added to the Contract
Sum, and if an Interim Certificate is issued after the date of ascertainment any such amount shall
be added to the amount which would otherwise be stated as due in such certificate.
43

30.0

CERTIFICATES AND PAYMENTS:

30.1

At the "Period of Interim Certificate" named in the Appendix hereto, the Architect shall issue a
certificate stating amount due to Contractor from Employer, and Contractor be entitled to
payment therefore within the "Period of Honoring Certificates" named in the Appendix hereto.
Interim Certificates shall be made by the Architect not more than once a month based on
"quantities" certified by the Clerk of Works against Running Bills presented (in quadruplicate) by
Contractor.

30.2

The amount stated as due in an Interim Certificate shall, subject to any agreement between the
parties as to stage payments, be the total value of the Work properly executed and of the
materials and goods (for materials as per clause 35.0 of Notice Inviting Tenders) delivered to or
adjacent to the work for use thereon up to and including a date not more than seven days before
the date of the said Certificate less any amount the Employer is bound to make statutory
deduction towards Income tax (T.D.S.) etc. less any amount which shall be retained by the
Employer (as provided in Clause 30.3 herein below) and less any installments previously paid
under these Conditions. Provided that the value of the unfixed materials and goods as agreed
upon included in such certificate shall only be up to (75%) seventy five percent of the value of the
said materials and goods as and from such time as they are reasonably, properly and not
prematurely brought to or placed adjacent to the Work and then only if adequately protected
against weather or other casualties.

30.3

The Employer shall retain the percentage of the total value of the work referred to in Clause 30.2
herein above, which is named in the Appendix hereto as "Retention Percentage". Provided
always that when the sum of the amounts so retained equals the amount named in said
Appendix as "Limit of Retention Fund" or that amount as reduced in pursuance of Clause 25.1.9
above, as the case may be, no further amounts shall be retained by virtue of this Clause.

30.4
The amounts retained by virtue of Clause 30.3 above shall be subject to the following rules:
30.4.1 The Employer's interest in any amounts so retained shall be fiduciary as trustee for the
Contractor (but without obligation to invest), and the Contractor's beneficial interest therein shall
be subject only to the right of the Employer to have recourse thereto from time to time for
payment of any amount which he is entitled under the provisions of this Contract to deduct from
any sum due or to become due to the Contractor.
30.4.2 On the issue of the Certificate of Virtual Completion, the Architect shall issue an Interim
Certificate for one moiety of the total amounts then so retained and the Contractor shall be
entitled to payment of the said moiety within the "Period of Honoring Certificate" named in the
Appendix hereto.
30.5

The measurement and valuation of the Work shall be completed within the "Period of Final
Measurement and Valuation" stated in the Appendix hereto and the Contractor shall be supplied
with a copy of the priced Bills of Variation not later than the end of the said period and before the
issue of the Final Certificate under Clause 30.8 herein below.

30.6

Either before or within a reasonable time after Virtual Completion of the Work, the Contractor
shall send to the Architect all documents necessary for purposes of computations required by
conditions including all documents relating to accounts of Nominated Sub-Contractors &
Nominated Suppliers.

30.7

In the settlement of accounts, the amounts paid or payable under the appropriate contracts by
the Contractor to nominated Sub-Contractors or nominated Suppliers, the amounts paid or
payable by virtue of Clause 20.2 above in respect of fees or charges for which a Provisional Sum
is included in the Contract Bills, the amounts paid or payable in respect of any insurance
maintained in compliance with clauses 44.0 and 45.0 herein below, the tender sum (or such
other sum as is appropriate in accordance with the terms of the tender) for any work for which a
tender made under Clause 25.7 above is accepted and the value of any work executed by the
Contractor for which a Provisional Sum mentioned in the Contract Bills or arising under
Architects Instructions issued under Clause 29.3 above as the case may be, and the balance
after allowing in all cases pro-rata for the Contractor's profit at the rates shown in the Contract
44

Bills, shall be added to or deducted from the Contract Sum. Provided that no deduction shall be
made in respect of any damages paid or allowed to Contractor by any Sub-Contractor or
Supplier.
30.8

So soon as is practicable but before the expiration of the "Period for issue of Final Certificate"
stated in the Appendix hereto or from completion of making good defects under clause 40.0
herein below or from receipt by the Architect of the documents referred to in Clause 30.6 above
whichever is latest, the Architect shall issue the Final Certificate. The Final Certificate shall state:

30.8.1 The sum of the amount paid to the Contractor under Interim Certificates and the amount named
in the said Appendix as limit of Retention Fund, and
30.8.2 The Contract Sum adjusted as necessary in accordance with the terms of this General Conditions
of Contract and the difference (if any) between the two sums shall be expressed in the said
Certificate as a balance due to the Contractor from the Employer or to the Employer from the
Contractor as the case may be, and subject to any deductions authorized by this General
Conditions of Contract, the said balance shall as from the fourteenth day after the issue of the
said Certificate be a debt payable as the case may be by the Employer to the Contractor or by
the Contractor to the Employer.
30.9

Unless a written request to concur in the appointment of an Arbitrator shall have been given
under Clause 54.0 herein below by either party before the Final Certificate has been issued or by
the Contractor within twenty eight days after such issue, the said Certificate shall be conclusive
evidence in any proceedings arising out of this Contract (whether by Arbitration under Clause
54.0 herein below or otherwise) that the Works have been properly carried out and completed in
accordance with the terms of this Contract and that any necessary effect has been given to all
the terms of this Contract which require an adjustment to be made to the Contract Sum, except
and in so far as any sum mentioned in the said Certificate is erroneous by reason of :

30.9.1 Fraud dishonesty or fraudulent concealment relating to the Works, or any part thereof, or to any
matter dealt with in the said Certificate; or
30.9.2 Any defect (including any omission) in the Works, or any part thereof which reasonable
inspection or examination at any reasonable time while carrying out of the Works or before the
issue of the said Certificate would not have disclosed; or
30.9.3 Any accidental inclusion or exclusion of any work, materials, goods or figure in any computation
or any arithmetical error in any computation.
30.10

Save as aforesaid no certificate of the Architect shall of itself be conclusive evidence that any
works materials or goods to which it relates are in accordance with this Contract.

30.11

The Contractor, before settlement of payment against Final Bill, shall sign and deliver to the
Employer, either in the measurement books or otherwise, as may be required, a valid release
and discharge from any and all claims and demands whatsoever from the Employer for all
matters arising out of this Contract, except in respect of Defects Liability under Clause 40.0.

31.0

CLAIMS FOR EXTRA:

31.1

When any instruction or decision given at Site involves an extra or whereby the Contractor may
plan to claim an extra, it shall be the responsibility of the Contractor to inform the Employer/
Architect of the extra amount and get written authorization from the Employer/Architect before
proceeding with the work involved.

31.2

Any modification carried out for expediting or simplifying work at the request of the Contractor or
his representatives shall not be taken as the basis for claiming an extra. However, if such
modification shall also involve an extra, the rate for such modification shall be settled in advance
and written authorization obtained by the Contractor from the Employer/Architect before
proceeding with the work involved. If no such information is given by the Contractor in writing to
the Employer/Architect, such modification shall not be accepted as the basis for extra charge.

45

32.0

DEDUCTION FOR UNCORRECTED WORK:


If the Architect deems it inexpedient to correct work damaged or not done in accordance with the
Contract, an equitable deduction from the Contract Sum as may be decided by the Architect shall
be made therefore.
Regarding action and penalty in case of Bad Work if the work done by the contractor is found to
be executed with unsound, imperfect or unskillful workmanship or with materials of inferior quality
and not in accordance with tender specifications, the same should be brought to the notice of the
contractor to rectify the same. If he fails to rectify the same within ten days he shall be liable to
pay penalty not exceeding 1% on the amount of estimate per day from 11th day till such time the
bad work is rectified by him. If the contractor does not rectify the damages within the stipulated
time, such bad work will be got done by the Executive Engineer at the risk and cost of the
contractor.

33.0

FLUCTUATIONS:
The Contractor shall not claim any extra for fluctuation for price and the Contract Sum shall not
be subject to any rise or fall of prices, unless specifically provided otherwise.

34.0

UNFIXED GOODS AND MATERIALS:


Unfixed materials and goods intended for, delivered to and placed on or adjacent to the Work
shall not be removed except for use upon the Work unless the Architect/Employer has
consented in writing to such removal which consent shall not be unreasonably withheld. Where
value of any such materials or goods has in accordance with clause 30.2 above been considered
for payment of an advance to Contractor, such materials and goods shall become property of
Employer, but subject to Clause 45.2 herein below, Contractor shall remain responsible for loss
or damage to the same.

35.0

MATERIALS AND WORKMANSHIP:

35.1

All materials and workmanship unless otherwise specified shall be as per the relevant code of
ISI Specification and of approved type and the Contractor shall immediately remove from the
Works any material and/or workmanship which in the opinion of the Architect are defective or
unsuitable and shall substitute proper materials and/or workmanship at his own cost. The term
approval used in connection with this Contract shall mean approval of the Employer/Architect.

35.2

The Contractor shall, if required, submit satisfactory evidence as to kind and quality of material.

35.3

Where special makes or brands are called for they are mentioned as standard. Others of equal
quality may be used provided approval is first obtained in writing from the Employer/Architect.
Unless substitutions are requested no deviation from the Specification will be permitted. Failure
to propose the substitution of any article within thirty days after of award of the Contract will be
deemed sufficient cause for denial of request for substitution.

35.4

The Contractor shall indicate and submit evidence in writing of those materials or articles called
for in the Specifications that are not obtainable for installation in the Work within the time limits of
the Contract. Failure to indicate the above, within thirty days after the award of the Contract, will
be deemed sufficient cause for denial of request for extension of Contract time.

35.5

All materials shall be delivered so as to ensure speedy and uninterrupted progress of the Work.
Such material shall be stored so as to cause no obstruction and so as to prevent overloading of
any portion of the structure, and the Contractor shall be entirely responsible for damage or loss
by weather or other cause.

35.6

Within thirty days after the award of the Contract, the Contractor shall submit for approval of the
Employer/Architect a complete list of all materials he and his Sub-Contractors propose to use in
the Work of definite brand or make which differ in any respect from those specified; also the
particular brand of any article where more than one is specified as a standard. He shall also list
items not specifically mentioned in the Specifications but which are reasonably inferred and
necessary for the completion of the Work.

46

35.7

INSPECTION:

35.7.1 All materials and workmanship shall be subject to inspection, examination and test by the
Architect/Employer and/or any inspecting Authority of the Employer at any and all times during
and/or after manufacture and/or construction. The Architect/Employer and/or any Inspecting
Authority of the Employer shall have the right to reject defective material and workmanship or
require its correction. Rejected workmanship shall be satisfactorily replaced with proper material
without additional charge therefore and the Contractor shall promptly segregate and remove the
rejected material from the Works. If the Contractor fails to proceed at once with the replacement
of rejected materials and/or the correction of the defective workmanship, the Employer may by
contract or otherwise replace such materials and/or correct such workmanship and charge cost
thereof to Contractor, or may terminate the right of Contractor to proceed further with the Work.
35.7.2 The Contractor shall furnish promptly without additional charge all reasonable facilities, labor and
materials necessary for the safe and convenient inspection and test that may be required by the
Architect/Employer and/or the Inspecting Authority of the Employer.
36.0

DEFECTS:

36.1

The Contractor shall make good at his own cost and to the satisfaction of the Architect, all
defects, shrinkages, settlements or other faults, arising in the opinion of the Architect from work
or materials not being in accordance with the Drawings or Specifications or Schedule of
Quantities or the Instructions of the Architect/Employer, which may appear within "Defects
Liability Period" referred to in the Appendix hereto.

36.2

Such defects, shrinkages, settlements or other faults shall upon directions in writing of the
Architect/Employer, and within such reasonable time as shall be specified therein be amended
and made good by the Contractor, at his own cost unless the Architect shall decide that he ought
to be paid for such amending and making good and in case of default the Employer may employ
and pay other contractor/s to amend and make good such defects, shrinkage, settlements or
other faults and all damages loss and expense consequent thereon or incidental thereto shall be
made good and borne by the Contractor and such damage, loss or expense shall be recoverable
from him by the Employer or may be deducted by the Employer upon the Architect's certificate in
writing from any amount due or may become due to the Contractor or the Employer may, in lieu
of such amending and making good by the Contractor deduct from any moneys due to the
Contractor a sum to be determined by the Architect as equivalent to the cost of amending such
work and in the event of the Retention Amount being insufficient, recover the balance from the
Contractor together with any expenses the Employer may have incurred in connection therewith.

37.0

POSSESSION OF SITE, COMPLETION AND POSTPONEMENT:

37.1

On the "Date of Commencement" stated in the Appendix hereto possession of the Site shall be
given to the Contractor who shall thereupon begin the Works and regularly and diligently proceed
with the same and who shall complete the same on or before the "Date of Completion" stated in
the Appendix hereto subject nevertheless to the provisions for extension of time contained in
Clause 38.0 herein below.

37.2

The Employer/Architect may issue instructions in regard to the postponement of any work to be
executed under the provisions of this Contract.

37.3

If at any time or times before Virtual Completion of the Work the Employer with the consent of
the Contractor shall take possession of any part or parts of the same for his own use and/or for
handing over to any other contractor or agency for carrying out his work referred to in Clause
28.0 above, then notwithstanding anything expressed or implied elsewhere in the Contract:

37.3.1 Such part or parts shall not be deemed to be virtually complete.


37.3.2 Virtual completion of such part or parts would occur on the completion of the last element of
Work in such part or parts under this Contract.
37.3.3 The Contractor shall not claim that such part or parts are complete and request refund of
47

payments in lieu thereof.


38.0

EXTENSION:

38.1

Upon it becoming reasonably apparent that the progress of the Works is delayed, the Contractor
shall forthwith (within a maximum period of seven days) give written notice of the cause of the
delay to the Employer/Architect and if, in the opinion of the Architect, the completion of the Work
is likely to be or has been delayed beyond the "Date of Completion" stated in the Appendix
hereto or beyond any extended time previously fixed under this clause :

38.1.1

By force majeure, or

38.1.2

By reason of any exceptionally inclement weather, or

38.1.3

By reason of loss or damage occasioned by any one or more of the contingencies referred to
in Clause 45.0 herein below, or

38.1.4

By reason of civil commotion, local combination of workmen strike or lockout affecting any of
the trades employed upon the Works or any of the trades engaged in the preparation,
manufacture or transportation of any of the goods or materials required for the Work, or

38.1.5

By reason of Architect's and/or the Employer's instructions issued under Clauses 8.0, 29.1
and/or 37.2 above, or

38.1.6

By reason of Contractor not having received in due time necessary instructions, drawings,
details or levels from the Employer/Architect for which he specifically applied in writing on a
date which having regard to the "Date of Completion" stated in Appendix hereto or to any
extension of time then fixed under Clause 38.1 herein was neither unreasonably distant from
nor unreasonably close to date on which it was necessary for him to receive the same, or

38.1.7

By delay on the part of Nominated Sub-Contractors or Nominated Suppliers which the


Contractor has taken all practicable steps to avoid or reduce, or

38.1.8

By delay on the part of artists, tradesmen or others engaged by the Employer in executing
work not forming part of this Contract, or

38.1.9

By reason of the opening up for inspection of any work covered up or of the testing of any of
the works, materials or goods in accordance with Clause 35.7 above (including making good in
consequence of such opening up or testing) unless inspection of test showed that the work
materials or goods were not in accordance with this Contract, or

38.1.10

By reason of the Contractor's inability for reason beyond his control and which he could not
reasonably have foreseen at the date of this Contract to secure such labor, goods or materials
as are essential to the proper carrying out of the Works, then the Architect shall so soon as he
is able to estimate the length of the delay beyond the date or time aforesaid make in writing a
fair and reasonable extension of time for completion of Works, provided always that the
Contractor shall use constantly his best endeavors to prevent delay and shall do all that may
reasonably be required to the satisfaction of the Architect to proceed with the Work.

38.2

The Contractor will forfeit his claim for extension if he does not report the cause of delay in
completion date within seven days of date of occurrence.

39.0

DAMAGES FOR NON-COMPLETION

39.1

If the Contractor fails to complete the Works by the "Date of Completion" stated in the Appendix
hereto or within any extended time fixed under Clause 38.0 above and the Architect certifies in
writing that in his opinion the same ought reasonably so to have been completed, the Contractor
shall pay or allow to the Employer a sum calculated at the rate stated in the Appendix hereto as
"Liquidated Damages" for period during which said work shall so remain or have remained
incomplete & Employer may deduct such damages from any moneys otherwise payable to
Contractor under this Contract.
48

39.2

(Deleted)

40.0

VIRTUAL COMPLETION AND DEFECTS LIABILITY PERIOD:

40.1

As soon as the Works are virtually complete, the Contractor shall inform the fact to the Employer
and the Architect and if in the opinion of the Architect, the Works are practically completed, he
shall forthwith issue a certificate to that effect and Virtual Completion of the Work shall be
deemed for all the purpose of this Contract to have taken place on the day named in such
certificate.

40.2

Any defects shrinkages or other faults which shall appear within the "Defects Liability Period"
stated in the Appendix hereto, and which are due to materials and workmanship not in
accordance with this Contract shall be specified by the Architect in a "Schedule of Defects" which
he shall deliver to the Contractor not later than fourteen days after the expiration of the said
"Defects Liability Period" and within a reasonable time after receipt of such "Schedule of Defects"
the defects, shrinkages and other faults therein specified shall be made good by the Contractor
and (unless the Architect shall otherwise instruct in which case the Contract Sum shall be
adjusted accordingly) entirely at his own cost.

40.3

Notwithstanding Clause 40.2 above, the Architect/ Employer may whenever he considers it
necessary so to do, issue instructions requiring any defects, shrinkages or other fault which shall
appear within the "Defects Liability Period" named in the Appendix hereto and which is due to
materials and workmanship not in accordance with this Contract to be made good and the
Contractor shall within a reasonable time (which shall be specified in such instructions of the
Architects/Employer) after receipt of such instructions comply with the same (and unless the
Architect/Employer shall otherwise instruct in which case the Contract sum shall be adjusted
accordingly) entirely at his own cost. Provided that no such instruction shall be issued after 14
days from the expiration of the said "Defects Liability Period"

40.4

When in the opinion of the Architect any defects shrinkages or other faults which he may have
required to be made good under Clauses 40.2 and 40.3 above shall have been made good he
shall issue a certificate to that effect, and completion of making good such defects, shrinkages or
other faults shall be deemed for all the purposes of this Contract to have taken place on the day
named in such certificates.

40.5

In no case shall the Contractor be required to make good at his own cost any damage which
may appear after the Virtual Completion of the work, unless the Architect shall certify that such
damage is due to injury which took place before Virtual Completion of the Works.

41.0

LOSS & EXPENSE CAUSED BY DISTURBANCE OF REGULAR PROGRESS OF WORKS:

41.1

If upon written application being made to him by the Contractor the Architect is of the opinion that
the Contractor has been involved in direct loss and/or expense for which he would not be
reimbursed by a payment made under any other provision in this Contract by reason of the
regular progress of the Works or of any part thereof having been materially affected by:

41.1.1 The Contractor not having received in due time necessary Instructions, Drawings, Details of
Levels from the Architect for which he specifically applied in writing on a date which having
regard to the "Date of Completion" stated in the Appendix hereto was neither unreasonably
distant from nor unreasonably close to the date on which it was necessary for him to receive the
same; or
41.1.2 The opening up for inspection of any work covered up or the testing of any work material or
goods in accordance with Clause 35.7 above (including making good in consequence of such
opening up or testing) unless the inspection or test showed that the work materials or goods
were not in accordance with this Contract; or
41.1.3 Any discrepancy or divergence between the Contract Drawings and/or the Contract Bills; or
41.1.4 Delay on the part of the Artists, Tradesmen or others engaged by the Employer in executing
work not forming part of this Contract; or
49

41.1.5 Architect's instructions issued in regard to the postponement of any work to be executed under
the provisions of this Contract and if the written application is made within a reasonable time of it
becoming apparent that the progress of the work or of any part thereof has been affected as
aforesaid then the Architect shall ascertain the amount of such loss and/or expense. Any
amount from time to time so ascertained shall be added to the amount which would otherwise be
stated as due in such certificate.
41.2

The provisions of Clause 41.1 above are without prejudice to any other rights and remedies
which the Contractor may possess.

42.0

PAYMENTS WITHHELD:

42.1

The Architect may withhold or on account of subsequently discovered evidence nullify whole / a
part of any certificate to such extent as may be necessary in his reasonable opinion to protect
Employer from loss on account of:

42.1.1 Defective work not remedied.


42.1.2 Failure of the Contractor to make payments properly to Sub-Contractor or for materials or labor.
42.1.3 A reasonable doubt that Contract can be completed for balance then unpaid.
42.1.4 Damage to another contractor or Sub-Contractor.
42.1.5 Claims filed on reasonable evidence indicating probable filing of claims.
42.2

When above grounds are removed payment shall be made for amounts withheld because of
them.

43.0

INJURY TO PERSONS AND PROPERTY OF EMPLOYER:

43.1

The Contractor shall be liable for and shall indemnify the Employer against any liability, loss,
claim or proceedings whatsoever arising under any statute or at common law in respect of
personal injury to or the death of any person whomsoever arising out of or in the course of or
caused by the carrying out of the Works, unless due to any act or neglect of the Employer or of
any person for whom the Employer is responsible.
The Contractor shall be liable for and shall indemnify the Employer against any expense, liability,
loss, claim or proceedings in respect of any injury or damage whatsoever to any property real or
personal in so far as such injury or damage arises out of or in the course of or by reason of the
carrying out of the Works, and provided always that the same is due to any negligence, omission
or default of the Contractor, his servants or agents of any Sub-Contractor, his servant or agent.

43.2

44.0

INSURANCE AGAINST INJURY TO PERSONS AND PROPERTY:

44.1

Without prejudice to his liability to indemnify the Employer under Clause 43.0 above, the
Contractor shall take all the insurances (CAR Policy with third party liability and Workmen's
Compensation Policy) at his cost in the joint names of the Contractor and Employer and
maintain and shall cause any Sub-Contractor to maintain until Virtual Completion of the Works:

44.1.1 Such insurances as are necessary to cover the liability of the Contractor or as the case may be
of such Sub-Contractor, in respect of personal injuries or deaths arising out of or in course of or
caused by carrying out of Work; and
44.1.2 Such insurances as may be specifically required by the Contract Bills in respect of injury or
damage to any property real or personal at Site arising out of or in the course of or by reason of
carrying out of the Work, and caused by any negligence, omission or default of the Contractor,
his servants or agents or, as case be of such Sub-Contractor, his servants or agents. The cost of
all materials supplied by Employer shall be covered in insurance policy.
44.2

The Contractor shall produce or cause any Sub-Contractor to produce for inspection the relevant

50

policy or policies of insurance together with the receipts in respect of premiums paid under such
policy or policies as and when required so to do by the Architect/Employer provided always that
as and when may be reasonably required by the Architect/Employer the production by either the
Contractor or any Sub-Contractor of a current certificate of insurance from the company or firm
which shall have issued the policy or policies aforesaid shall be a good discharge of the
Contractor's obligation to produce or to cause the production of the policy or policies and the
receipts in respect of premium paid.
44.3

The Contractor at his cost shall maintain in the joint names of the Employer and Contractor such
insurances as may be required in respect of any expense, liability, loss, claim or proceedings
which the Employer may incur or sustain by reason of injury or damage to property real or
personal arising out of or in the course or by reason of the carrying out the Work, and caused
otherwise than by the negligence, omission or default of the Contractor, his servants or agents or
any Sub-Contractor, his servants or agents.

44.4

Any such insurance as is referred to in the Clause 44.3 above shall be placed with insurers to be
approved by the Architect/Employer and the Contractor shall have to deposit with the Architect/
Employer, the policy or policies and the receipts in respect of premiums paid.

44.5

Should the Contractor or any Sub-Contractor make default in insuring or in continuing to insure
as provided in Clauses 44.1 and 44.3 above or does not take the insurance policies, the
Employer shall himself insure against any risk with respect to which the default shall have
occurred and may deduct a sum equivalent to the amount paid in respect of the premiums from
any moneys due to or become due to the Contractor.

45.0

INSURANCE OF THE WORKS AGAINST FIRE ETC.:

45.1

The Contractor at his cost shall in the joint names of the Employer and Contractor insure against
loss or damage by fire, storm, tempest, lightning, flood, earth-quake, aircraft or anything
dropped there from, aerial objects, riot and civil commotion for the full value thereof all works
executed and all unfixed materials and goods intended for, delivered to and placed on or
adjacent to the Work, including the cost of all materials supplied by the Employer for the work
which is in the custody of the contractor, but excluding temporary building plant, tools and
equipment owned or hired by the Contractor or any Sub-Contractor and shall keep such work
materials and goods so insured until Virtual Completion of the Work. Such insurances shall be
with insurers approved by the Architect /Employer and the Contractor shall deposit with the
Architect /Employer the policy or policies and the receipts in respect of premium paid; Should the
Contractor make default in insuring or continuing to insure as aforesaid the Employer may
himself insure against any risk with respect of which the default shall have occurred and deduct a
sum equivalent to the amount paid by him in respect of premium from any moneys due to or to
become due to the Contractor. Provided always that if the Contractor shall independently of his
obligations under this Contract maintain a policy of insurance which covers (inter-alia) the said
Work, materials and goods against the aforesaid contingencies to the full value thereof then the
maintenance by the Contractor of such policy shall if the Employer's interest is endorsed thereon,
be a discharge of the Contractor's obligation to insure in the joint names of the Employer and the
Contractor and the production by the Contractor as and when may reasonably be required by the
Architect/Employer of a current certificate of insurance from the company or firm which shall
have issued the said policy shall be a discharge of the Contractor's obligation to deposit with the
Architect/Employer a policy or policies and the receipts in respect of premiums paid.

45.2

Upon settlement of any claim by the insurance companies under the insurances aforesaid, the
Contractor with due diligence shall restore work damaged, replace or repair unfixed materials or
goods which have been destroyed or injured, remove or dispose of any debris and proceed with
the carrying out and completion of the Work. All moneys received from such insurances shall be
paid to the Contractor by installments under certificates of the Architect issued at the "Period of
Interim Certificates" named in Appendix hereto. The Contractor shall not be entitled to payment
in respect of restoration of work damaged, replacement and repair of any unfixed materials or
goods and removal and disposal of debris other than moneys received under said insurance.

51

46.0

DETERMINATION BY THE EMPLOYER:

46.1

DEFAULT: If Contractor shall make default in anyone or more of following respects, that is to
say

46.1.1 If he without reasonable cause wholly suspends carrying out of Works before completion thereof,
or
46.1.2 If he fails to proceed regularly and diligently with the Works, or
46.1.3 If he refuses/neglects to comply with written notice from Architect/Employer requiring him to
remove defective work or improper materials or goods and by such refusal or neglect the work is
materially affected, or
46.1.4 If engages sub-contractor without complaining provision of Clause 24, then the Employer
/Architect may give him a notice by registered post or recorded delivery specifying the default.
46.2

BANKRUPTCY OF CONTRACTOR: In the event of Contractor becoming bankrupt or making a


composition or arrangement with his creditors or being a company having a winding up order
made or (except for purpose of reconstruction) a resolution for voluntary winding up passed or a
receiver or manager of his business or undertaking duly appointed or possession taken by or on
behalf of holders of any debentures secured by a floating charge, of any property comprised
in or subject to floating charge, employment of Contractor under this Contract shall be forthwith
automatically determined.

46.3

The Employer shall be entitled to determine the employment of Contractor under this Contract, if
Contractor shall have offered or given or agreed to give to any person any gift or consideration of
any kind as an inducement or reward for doing or forbearing to do or for having done or forborne
to do any action in relation to the obtaining or execution of this Contract with the Employer, or for
showing or forbearing to show favor or disfavor to any person relating to this Contract or any
other contract with the Employer, or if the like acts shall have been done by any person
employed by the Contractor or acting on his behalf (whether with or without the knowledge of the
Contractor), or if in relation to this Contract or any other contract with the Employer the
Contractor or any person employed by him or acting on his behalf shall have committed any
offense under the prevention of corruption act, or any other offence such as misappropriation,
cheating and involving moral turpitude and any other offence Employer deems fit to terminate the
contract, or shall have given any fee or reward, the receipt of which is an offense under the Local
Government Act.

46.4

In the event of the employment of the Contractor being determined as aforesaid and so long as it
has not been reinstated and continued, the following shall be respective rights and duties of
Employer and Contractor.

46.4.1 The Employer may employ and pay other persons to carry out and complete the Works and he
or they may enter upon the Works and use all temporary buildings, plant, machinery, appliances,
goods and materials intended for, delivered to and placed on or adjacent to the Works and may
purchase all materials and goods necessary for carrying out and completion of the Works.
46.4.2 The Contractor shall if so required by the Employer or Architect within fourteen days of the date
of determination assign to the Employer without payment the benefit of any Agreement for the
supply of materials or goods and/or for the execution of any works for the purposes of this
Contract but on the terms that a supplier or Sub-Contractor shall be entitled to make any
reasonable objection to any further assignment thereof by the Employer. In any case the
Employer may pay any supplier or Sub-Contractor for any materials or goods delivered or Works
executed for the purpose of the Contract (whether before or after the date of determination), in
so far as the price thereof has not already been paid by the Contractor. The Employer's rights
under this Clause are in addition to his rights to pay nominated Sub-Contractors as provided in
Clause 25.2 above and payments made under this Clause may be deducted from any sum due
or to become due to the Contractor.
46.4.3 The Contractor shall as and when required in writing by the Employer /Architect so to do (but not
before) remove from the Works any temporary buildings, plant, tool equipments, goods and
52

materials belonging to or hired by him. If within a reasonable time after any such requirements
has been made the Contractor has not complied therewith, then the Employer may (but without
being responsible for any loss or damage) remove and sell any such property of the Contractor,
holding the proceeds less all costs incurred to the credit of the Contractor.
46.4.4 The Contractor shall allow or pay to the Employer in the manner hereinafter appearing the
amount of any direct loss and/or damage caused to the Employer by the determination. Until
after completion of the Works under Clause 46.4.1 above, the Employer shall not be bound by
any provisions of this Contract to make any further payment to the Contractor, but upon such
completion and the verification within a reasonable time of the accounts therefore the Architect
shall certify the amount of expense properly incurred by the Employer and the amount of any
direct loss and/or damage caused to the Employer by the determination and if such amounts
when added to the moneys paid to the Contractor before the date of determination exceed the
total amount which would have been payable on due completion in accordance with this
Contract, the difference shall be a debt payable to the Employer by the Contractor; and if the said
amounts, when added to the said moneys be less than the said total amount, the difference shall
be a debt payable by the Employer to the Contractor.
47.0

DETERMINATION BY THE CONTRACTOR:

47.1

Without prejudice to any other rights and remedies which Contractor may possess, if:

47.1.1 The Employer does not pay to the Contractor the amount due on any certificate within the
"Period for Honoring Certificates" named in the Appendix hereto and continues such default for
seven days after receipt by registered post or recorded delivery of a notice from the Contractor
stating that notice of determination under this Condition will be served if payment is not made
within seven days from receipt thereof; or
47.1.2 The Employer interferes with or obstructs the issue of any certificate due under this Contract; or
47.1.3 The carrying out of the whole or substantially the whole of the uncompleted works (other than the
execution of work required under Clause 40.0 above) is suspended for a continuous period of
the length by reason of:
a) Force majeure, or
b) Loss or damage occasioned by any one or more of the contingencies referred to in Clause
45.0 above; or
c) Civil commotion; or
d) Architect's instructions issued under Clauses 5.3, 29.1 / 37.2 above; or
e) The Contractor not having received in due time necessary instructions, drawings, details or
levels from the Architect for which he specifically applied in writing on a date which having
regard to the "Date of Completion" stated in the Appendix hereto or to any extension of time
then fixed under Clause 38.0 above was neither unreasonably distant from nor unreasonably
close to the date on which it was necessary for him to receive the same, or
f) Delay on the part of Artists, Tradesmen or others engaged by the Employer in executing
work not forming part of this Contract, or
g) The opening up for inspection of any work covered up or of the testing of any of the work,
materials or goods in accordance with Clause 35.7 above (including making good in
consequence of such opening up or testing) unless the inspection or test showed that the
work, materials or goods were not in accordance with this Contract,
Then the Contractor may thereupon by notice by registered post or recorded delivery to the
Employer or Architect forthwith determine the employment of the Contractor under this Contract;
provided that such notice shall not be given unreasonably or exatiously.
47.2

Upon such determination, then without prejudice to the accrued rights or remedies of either party
or to any liability of the classes mentioned in Clause 41.0 above which may accrue either before
the Contractor or any Sub-Contractors shall have removed his or their temporary buildings, plant,
machinery, appliances, goods or materials or by reason of his or their so removing the same, the
respective rights and liabilities of Contractor and the Employer shall be as follows that is to say:

47.2.1 The Contractor shall with all reasonable dispatch and in such manner and with such precautions
as will prevent injury, death or damage of the classes in respect for which before the date of
53

determination he was liable to indemnify the Employer under Clause 43.0 above, remove from
site all his temporary buildings, plant, machinery, appliances, goods and materials and shall give
facilities for his Sub-Contractors to do the same but subject always to the provisions of
sub-paragraph (c) of Clause 47.2.2 herein below.
47.2.2 After taking into account amounts previously paid under this Contract, the Contractor shall be
paid by the Employer:
b)
The total value of the Works completed at the date of determination.
b)
The total value of work begun and executed but not completed at the date of
determination the value being ascertained mutates in accordance with Clause 29.4
above.
c)
The cost of materials or goods properly ordered for the Works for which the Contractor
shall have paid or of which the Contractor is legally bound to pay, and on such payment
by the Employer materials or goods so paid for shall become the property of the
Employer.
d)
The reasonable cost of the removal under Clause 47.2.1 above.
e)
Any direct loss and/or damage caused to the Contractor by the determination.
Provided that in addition to all other remedies the Contractor upon such determination may take
possession of and shall have a lien upon all unfixed materials which may have become the
property of the Employer under Clause 34.0 above until payment of all moneys due to Contractor
from the Employer.
48.0

COORDINATION OF WORK:

48.1

At the commencement of Work, and from time to time, the Contractor shall confer with the
Sub-Contractors, persons engaged on separate contracts in connection with the Work, and with
the Architect for the purpose of the coordination and execution of the various phases of the
Work.
The Contractor shall ascertain the Sub-Contractors, persons engaged on separate contracts in
connection with the Works, the extent of all chasing, cuttings and forming of all openings, holes,
grooves, etc. as may be required to accommodate the various services, the routes of all services
and the positions of all floor outlets, traps, etc. in connection with the installation of plant and
services and arrange for the construction of Work accordingly. The breaking and cutting of
completed work must be avoided.

48.2

49.0

LABOUR:
The Contractor shall employ no child labor under 14 years of age on Work. If female labor
is engaged, the Contractor shall make necessary provision for safeguarding children and
keeping them clear of site of operations. No laborer shall reside within compound except
authorized guards. Female workers will not be allowed to work between 1830 and 0630
hours.

54

ANNEXURE - I
SHORT TILES:
These regulations may be called the Karnataka Public Works Department Contractors Labour
regulations.
DEFINITION:
In these regulations unless otherwise, expressed or indicated the following words and
expressions shall have the meaning hereby assigned respectively that is to say :
i)

ii)

iii)
iv)

Labour means workers employed by the Contractor or Karnataka Public Works Dept
directly or indirectly through sub-contractor or any other person, or any agent on his
behalf on a payment not exceeding Rs.400/- per month and will not include supervisory
staff like overseers, etc.
Fair wages means whether for item or place work notified at the time of inviting tenders
for the work and where such wages have not been so notified, the wages prescribed by
the Karnataka Public Works Department for the district in which the work is done.
Contractors shall include every person whether a Sub-contractor head or agent
employing Labour on the work taken contract.
Wages shall have the same meaning as defined in the payment of wages Act 1936 and
included item a piece rate wages.

WORKING HOURS:
a)
Normally working hours of an adult employed should not exceed 9 hours a day. The
working day shall be so arranged that inclusive of interval for rest if any, it shall not
spread over more than 12 hours on any day.
b)
When an adult worker is made to work for more than 9 hours on day or for more than 48
hours in any week he is entitled to double the ordinary rate of wages. Children shall not
be made to work extra hours.
c)
Every worker shall be given a paid weekly holiday normally on Sunday.
DISPLAY OF NOTICE REGARDING WAGES, ETC:
The contractor shall (a) before he commences his work on contract, display and correctly
maintain in a clean legible condition in conspicuous places on the work, notices in English and in
the local language spoken by the majority of the workers, giving the rate of wages which have
been certified by the Executive Engineer, the Superintending Engineer, or The Chief Engineer, or
Regional Labour Commissioner, as fair wages and the hours of work, which such wages are
earned and a copy of such notices shall be sent to the certifying officers.
PAYMENT OF WAGES:
a)
Wages due to every worker shall be paid to him direct.
b)
All wages shall be paid on current coin or currency or in both.
c)
Arrears claimed after 2 months after the completion of the work shall not be entertained.
FIXATION OF WAGES PERIODS:
a)
The contractor shall fix the wages period of which the wages shall be payable.
b)
No wages period shall exceed one month.
c)
Wages of every workers employed on the contract shall be paid.
i) In case of establishments in which the wage period is one week within three days from
the end of wage period and
th
th
ii) In the case of other establishment before the expiry of the 7 day or 10 day from the
end of the wage period according as the numbers of the workers employed in such
establishment does not exceed 100 or exceeds 1000.
d)
When the employment of any workers is terminated by or on behalf of the contractor the
wages earned by him shall be paid before the expiry of the days succeeding the one
which his employment is terminated.
e)
All payment of wages shall be made on a working day except when the work is
completed before the expiry of the wages period in which case final payment shall be
made with 48 hours of the last working day at work site and during the time.

55

NOTE: The term working day means a day on which the Labour is employed and the work is in
progress.
WAGE BOOK AND WAGE SLIPS, ETC.
The Contractor shall maintain a wage book of each worker as far as may be convenient at, the
place of work, but the same shall include the following particulars:
a)
Name of the workers.
b)
Rate of daily or monthly wages.
c)
Nature of work on which employed.
d)
Total number of days worked over time.
e)
Dates and period for which worked during each wage period.
f)
Gross wages payable for the work during each wage period.
g)
All deductions as made from the wage with an indication in each case of the ground of
which the deduction is made.
h)
Wages actually paid for each wage period.
i)
Signature of thumb impression of the worker.
j)
Percentage of loss of earning capacity and disability as assessed by Medical Officer.
k)
Claim required to be held under workmens compensation Act.
l)
Date of payment of compensation.
m)
Amount paid with details of the period to whom the same was paid.
n)
Authority by whom the compensation was assessed.
o)
Remarks.
FINES AND DEDUCTIONS WHICH MAY BE MADE FROM WAGES :
The Wages of workers shall be paid to him without any deductions of any kind except the
following:Deductions:
a)
Deductions for absence for duty i.e., from the places or the places where by the terms of
his employment he is required to work. The amount of deductions shall be in proportion
to the period for which he was absent.
b)
Deductions for damage or loss of goods expressly entrusted to the employed person for
custody or for loss of money or any other deduction which he is required to account,
where such damage or loss of directly attributable to neglect or default.
c)
Deduction for recovery of advance or for adjustment of over payment of wages, advance
granted shall be entered in a register.
d)
And other deductions which the Government may from time to time allow.
Fines:
a) No fine shall be imposed on any worker save in respect of such acts and omissions on his
part as have been approved of the Commissioner for Labour.
b) No fine shall be imposed on a worker and no deduction for damage or loss be made from
his wages until the worker has been given an opportunity of showing cause against such
fines or deductions.
c) The total amount of fines which may be imposed in any one wage period on a worker shall
not exceed an amount equal to the naya-paisa in rupee of the wages payable to him in
respect of that wage period.
d) No fine imposed on any worker shall be recovered from him by installments or after the
expiry of sixty days from the date which it was imposed.
e) Every fine shall be deemed to have imposed on a day of the act or omission in respect of
which it was imposed.
The contractor shall also issue a wage slip containing the aforesaid particulars to each worker
employed by him on the work at least a day prior to the disbursement of wages.
The contractor shall issue an employment card in form III each worker on the day of the workers
entry into the employment. If the worker has already any such card with him for the previous
employment of contractor, he shall merely endorse that employment card with relevant entries.
On termination of employment of employment card shall again be endorsed by the contractor
and returned to the worker.

56

REGISTER OF UNPAID WAGES:


The contractor should maintain a register of unpaid wages in such a form as may be convenient
at the place of work but same shall include the following particulars:
a)
Full particular of the Labourers whose wages have not been paid.
b)
Reference number of the muster roll and wage register
c)
Rate of wages
d)
The period
e)
Total amount not paid
f)
Reasons for not making payment
g)
How the amount of unpaid wages was utilized
h)
Acquaintance with dates
REGISTER OF ACCIDENTS:
The contractor should maintain a register of accidents in such form as may be convenient at the
work place but the same shall include the following particulars:
a)
Full particulars of the Labourers whom with accidents.
b)
Rates of wages
c)
Sex
d)
Age
e)
Nature of accidents and cause of accident
f)
Time and date of accidents
g)
Date and time when admitted in Hospital
h)
Date of discharge from the Hospital
IN REGISTER OF FINES, ETC.:
The contractor shall maintain a register of fines and a register of deductions for damages or loss
in form No.1 and II respectively which shall be kept at the place of work.
The contractor shall maintain both in English and local language a list approved by
Commissioner for Labour clearly stating the acts and commissions for which penalty or fine may
be imposed on a workmen and display it in a good condition in conspicuous place on the work.
PRESERVATION OF REGISTERS:
The wage book, the wage slips, the registers of fines, deductions required to be maintained
under these regulations shall be preserved for 12 months after the date of last entry made in
them and shall be made available for inspection by the Engineer-in-charge Labour welfare officer
or any other officer authorized by the Minister of W.H. & S. in this behalf.
POWERS OF LABOUR WELFARE OFFICERS TO MAKE INVESTIGATION FOR ENQUIRY:
The Labour welfare officer or any other person authorized by the Government on their behalf
shall have power to make enquiries with a view to ascertaining and enforcing due and proper
observance of the wage clauses and the provisions of these regulations. He shall investigate
into any complain regarding the default made by the contractor or sub-contractor in regard to
such provisions.
REPORT OF LABOUR WELFARE OFFICER:
i)

The Labour welfare officer or other person authorized as aforesaid shall submit a report
of the results of his investigations or enquiry to the Executive Engineer concerned
indicating the extent if any, to which the default has been committed, with an note that
necessary deductions from the contractors bill be made the wage and other dues be
paid to the Labourers concerned. In these cases regulation appeal shall be made by the
contractor under Clause 14 of these regulation Actual payment to Labour will be made
by the contractor under Clause 14 of these regulation Actual payment to Labour will be
made by the Executive Engineer after the Regional Labour Commissioner has given his
decision on such appeal.

ii)

The Executive Engineer shall arrange payments to the Labourers concerned within 45
days from the report from Labour welfare officer or the Regional Labour Commissioner
as the case may be.

57

APPEAL AGAINST THE DECISION OF LABOUR WELFARE OFFICER:


Any person aggrieved by the decision and recommendation of the Labour welfare officer or other
person so authorized may appeal against such decision to the Regional Labour Commissioner
concerned within 30 days from the date of decision simultaneously with a copy of his appeal to
Executive Engineer, concerned by subject to such appeal decision of the officer shall be final and
binding upon the contractor.
PROHIBITION REGARDING REPRESENTATION THROUGH LAWERS:
i)
A Workman shall be entitled to represent in any investigation:
a)
An officer of a registered Trade Union of which he is a member.
b)
An officer of a Federation of a Trade Union to which Trade referred to in Clause
(a) affiliated.
c)
When the worker is not member of any registered Trade Union, connected
within or by any other workmen employed in the industry in which the worker is
employed.
ii)

An employer shall be entitled to be represented in investigation or enquiry under these


regulations by:
a)
An officer of a Federation of Association of Employer of which he is a member.
b)
An officer of an Association of Employer which the Association referred to in
Clause (2) is affiliated.
c)
Where the employer is not a member of any association of employer by an
officer of an association of employer connected with or by any other employer
engaged in the industry in which the employer is engaged.

iii)

No party shall be entitled to be represented by legal practitioner in any investigation of


enquiry these regulations.

SUBMISSION OF BOOK & SLIPS:


The contractor shall allow submission of the wage books, wage slips, register of un-paid wages,
the register of accidents and the register of fines and deductions to any of his workers or to his
agent of convenient time and place after due notices is received or the Labour Welfare Officer or
any other person authorized by the Govt. on his behalf.
SUBMISSION OF RETURNS:
The contractor shall submit periodical returns as may be specified from time to time.
AMENDMENTS:
The Government may from time to time add, to or amend the regulations and on may question
as to the application interpretation on effect if these regulations the decision of the Commissioner
of Labour or Deputy Commission for Labour to Govt. in that behalf shall be final.

58

ANNEXURE - II
Labour Clause 19
Clause 19 A

Clause B

Female labour shall be employed within the limits of cantonment.


No labourers below the age of 14 years shall be employed on the
work
Payment of wages of labourers

The contractor shall pay not less than fair wage of labourers engaged by him on the work.
EXPLANATION:
Fair wage means wage whether for time or piece work, notified at the time of inviting tenders for
the work and where such wages have not been so notified, the wages prescribed by the
Karnataka Public Works Department in consultation with the officer of the Industrial Relationship.
Machinery located in the respective areas and will not be less than the maximum rates of wages
fixed by the Govt. for that class of employees engaged on the same type of work in the same
area.
The contractor shall not withstanding the provision of any contract, to the contrary cause to be
paid wages to labourers indirectly engaged for the work including engaged by his sub-contractors
in connection with the same work if the labourers has been immediately employed by him.
In respect of all labours directly or indirectly employed in the works for the performance of the
contractors part of this agreement. The contractor shall comply with or cause to be complied
with Karnataka Public Works Dept Contractors labour regulations made by Govt. from time to
time, in regard to payment of wages. Wage period, deductions from wages recovered of wages
not paid and deductions unauthorizedly made, maintenance of wage book, wage slips,
publication of scale of wage and other terms of employments, inspection, inspection and
submission of periodical returns and all other matters of a like nature.
The Executive Engineer of sub-divisional officer concerned shall have the right to deduct from
the money due to the contractors any sum required from making good, the loss suffered by a
worker or workers by reason of non-fulfillment of the conditions of the contract for the benefit of
the workers, non-payment of wages or of deductions made from his or her wages which are not
justified by their terms of the contract or non-observance of the regulations.
Under the provisions of the minimum wages Act 1948, and the minimum wages (control) rules
1949, the contractor is bound to allow or cause to allow to the labourers directly or indirectly
employed in the works one day rest of six days continuous work and pay wages at the same rate
as for duty. In the event of default the Executive Engineer or Sub-Divisional Officer concerned
shall have the right to deduct the sum of sums not paid on account of wages of weekly holiday
and labourers, and pay the same to the persons initiated to their from any money due to the
contractors.
Vis--vis the Government the contractor shall be primarily liable for all payments to be made
under and for the observance of the regulations aforesaid without prejudice to his right to claim
indemnity from his sub-contractors. The regulations aforesaid shall be deemed to be part of this
contract, and any breach thereof shall be deemed to be a breach of this.
Clause 19(c) :
In respect of all labour directly or indirectly employed in the work for the
performance of the contractors part of this agreements the contractor shall at his own expense
arrange for the safety provisions as per Karnataka P.W.D. Safety code framed from time to time
and shall at his own expense provide for all facilities in arrangements and provide necessary
facilities as aforesaid he shall be liable to pay penalty of Rs.50/- for each default and addition the
Executive Engineer-in-charge shall be at liberty to make arrangements and provide facilities as
aforesaid and recover the cost incurred in that behalf from the contractor.
th

th

Clause 19(d) : The contractor shall submit by the 4 and 19 of every month of the Engineer-incharge of true statement showing in respect of the second half of the preceding month and the
59

first half of the current month respectively (1) the name of the labourers employed by him on the
work (2) their working hours (3) the wages paid to them (4) the accidents that occurred during
the said fortnight showing the circumstances under which they happened and the extent of
damage and injury caused by them and (5) the number of female worker who have been allowed
maternity benefit according to clause 19F and the amount paid to them, failing which the
contractor shall be liable to pay of Govt. a sum of not exceeding Rs.50/- for each default or
materially incorrect statement by deduction from any bill due to the contractor and amount levied
as fine.
Clause 19(e) : In respect of all labour directly or indirectly employed in the works for the
performance of the contractors part of this agreement, the contractor shall comply with or cause
to be complied with all the rules framed by Govt. from time to time for the protection of health and
sanitary arrangements for worker employed by the Karnataka P.W.D. and its contractors.
Clause 19(f) : Maternity benefit rules for female workers employed by contractor, leave and pay
during leave shall be regulated as follows :
Leave (i) In case of delivery : Leave during maternity leave not exceeding 8 weeks up to and
including the day of delivery and 4 weeks following that day.
(ii) In case of miscarriage, up to 3 weeks from the date of miscarriage.
Pay 1) In case of delivery : Leave pay during Maternity Leave will be at the rate of womens
average daily earning calculated on the total wages earned on the days when full time work was
done during period of three months immediately proceeding the date on which she gives notice
that she expects to be confined or at the rate of twelve annas a day which ever is greater.
i)

In case of miscarriages : Leave pay at the rate of average daily earnings calculated on
the total wages earned on the days full time works was done during a period of 3 months
immediately preceding the date of miscarriage.

ii)

Conditions for the grant of maternity leave: No maternity leave benefit shall be
admissible to a woman unless she has been employed for a total period not less than 6
months immediately preceding the date of miscarriage.

Model rules for the protection of Health and Sanitary arrangements for workers employed by the
Karnataka Public Works Department or its contractors.
Applications: The rule shall apply to all building and construction work in charge of K.P.W.D.
Definition: Work place means a place at which on an average fifty or more workers are employed
in connection with construction work.
Aid:
At every place, there shall be maintained in readily accessible place first and appliance including
adequate supply sterilized dressing and sterilized cotton wool. The appliances shall be kept in
good order and in large work places. They shall be placed under the charge of responsible
person who shall be readily during working hours.
At large work place where hospital facilities are not available within easy distance of the works
first aid posts shall be established and be run by a trained compounder.
Where large place are remote regular hospitals an underward shall be provided with one bed for
every 250 employees.
Where large work places are situated in cities, town or in their suburbs and no beds are
considered necessary due to proximity of city or town hospitals, suitable transport shall be
provided to facilitate of urgent cases to these hospitals at the work places, some conveyance
facilities such as a car should be kept readily available to take injured persons suddenly taken
seriously ill to the nearest hospital.

60

DRINKING WATER:
In every work place there shall be provided and maintained at suitable places, easily accessible
to labour, a sufficient supply of cold water fit for drinking.
Where drinking water is obtained from an intermittent public water supply each work place shall
be provided with storage here such drinking water shall be stored.
Every drinking water supply of storage shall be at distance not less than 50 ft. from any latrine,
drain or other source of pollution. The well shall be properly chlorinated before water is drawn
from it for drinking. All such wells shall be entirely closed in be provided with a trap door which
shall be dust and waterproof.
A reliable pump shall be fitted to each covered well. The trap door shall be kept locked and
opening only for cleanings or inspection which shall be at least once a month.
WASHING AND BATHING PLACES:
i)
Adequate washing and bathing places shall be provided separately for men & women
ii)
Such places shall be kept in clean and drained conditions.
SCALE OF ACCOMODATION TO LATRINES AND URINALS:
There shall be provided within premises of every work place latrines and urinal in an accessible
place, and the accommodation separately for each of them shall not be less than following scale:
Where the No. of Persons does not exceed 50
2
Where the No. of Persons exceeds but does not exceed 100
3
For every additional 100
- 3 per 100
In particular cases the Executive Engineer, shall have the power to vary the scale wherever
necessary.
LATRINES AND URINALS FOR WOMEN:
If women also employed separate latrines and urinals screened from those form men, and
marked in the vernacular conscious letter. For women only shall be provided on the scale in rule
6. Those for men shall be similarly marked for men only. A poster showing figures of men and
women shall also be exhibited at the entrance of latrines of each sex. There shall be adequate
supply of water closet for the urinals and latrines.
LATRINES AND URINALS:
Except in work provided with water flushed latrines connected with water brone sewerage all
latrines shall be provided with receptacles on dry earth system which shall be cleaned at least
four times daily and at least twice during working hours and kept in a strictly sanitary condition.
The replaces shall be tarred inside and outside at least once a year.
CONSTRUCTION OF LATRINES:
The inside walls shall be constructed of masonry or some suitable heat-resisting non-absorbent
materials and shall be cement washing shall be noted in a register maintained for this purpose
and kept available for inspection. Latrines shall not be of a standard lower than borned other
system and should have thatched roofs.
DISPOSAL OF EXCRETA:
Unless otherwise arranged for the local sanitary authority arrangements for proper disposal of
excreta by incineration at the work place shall be made by means of a suitable incinerator
approved by the Asst. Director of Public Health or the Municipal Medical Officer of Health, as the
case may be in whose jurisdiction the work place is situated. Alternately excreta may be
disposed of by putting power of night soil at the bottom of pucca tank prepared for purpose of
covering it with 6 layer of waste or refuse and then covering it up with a layer of earth for a
fortnight (when it will turn into manure).
PROVISIONS OF SHELTERS DURING REST:
At every work place there shall be provided free of cost two suitable sheds one for meals and
other for rest separately for men and women for use of labour. The height of the shelter shall not
61

be less than 11 ft from the floor level to the lowest part of the roof. The sheds should be roofed
with at least thatch and mud flooring will be provided with dwarf wall around not less than 2.5
feet. Sheds shall be kept clean and space shall be on the basis of at least 5 square feet per
head.
Crche (A) : At every place, at which fifty or more women or ordinary employed there shall be
provided two huts for the use of children under the age 6 years belonging to such women. One
hut shall be used for infants games and place and the other as their bed room. The huts shall
not be constructed of a lower standard than the following :
i)
Thatched roofs
ii)
Mud floor and walls
iii)
Planks spread over the mud floor and covered with matting.
The huts shall be provided with suitable and sufficient openings for light and ventilation. There
shall be adequate provision of sweepers to keep the places clean, there shall be two boys in
attendance. Sanitary utensils shall be provided to the satisfaction of the Health Officer of the
area concerned. The use of the hut shall be restricted to children, their attendants and mother of
the children.
Where the number of Women workers is more than 35 but less than 50 of the contractor shall
provide at least one hut and one boy to look after the children of women workers.
The crche shall be properly maintained and necessary equipments like toys etc. shall be
provided.
The size of the cretches shall vary accordingly to the number of workers.
CANTEENS:
A cooked food canteen on a moderate scale shall be provided for the benefit of workers
wherever it considered expedient.
The above rules shall be incorporated in the contract and in notices inviting tenders, and shall
form an integral part of the contract.

62

FORM I
REGISTER OF FINES (REGULATION 10)

Sl.
No
.

Nam
e

Fathers
Name /
Husband
s
Name

Sex

De
pt.

Nature
&
Date of
Offenc
e
for
which
Fine
Impose
d

Whether
Workme
n
showed
cause
against
fine / not.
If
so, enter
Date
7

Date
of
Wage
s

Date
and
Amoun
t
of fine
Impose
d

Date
on
Which
Fine
Realize
d

10

Remark
s

11

FORM II
REGULATION 10 (1) EMPLOYER
Register of Deductions for damaged or loss caused to Employer by the
Neglect or default of the employed person

Sl.
N
o.

Name

Fathers
Name /
Sex Dep
Husbands
t.
Name

Damag
ed or
loss
Caused
With
date

5
6

Whether
Workers
should
Cause
against
deductio
n
If so,
enter
Date
7

Date &
amount
of
deductio
n
imposed

Date
and
Amount
Of fine
Impose
d

Date
on
Which
Fine
Realize
d

10

Remark
s

11

63

FORM III
EMPLOYMENT CARD (REGULATION 6 III)

Sl.
No
.

Name &
Address
of
Specially
Whether
a
Contract
or

Particular
s of
location
work site
&
descriptio
n of work
3

Total
period
for
which
the
worker
employe
d
From
To
4

Actual
No. of
days
worke
d

Leave
Taken
(No. of
days
should
be
specifie
d)
6

Give
Sl.
No. as
on
revers
e

Natur
e of
work
done
by the
worke
r

Wages
Rate
Particulars
unit in case
of piece
work

Total wages
earned by
Worker
during the
period
shown
under
Clause 5
10

Remarks
Signature of
Employer
_____________________________________________________________________________________
50.0

PROTECTION OF TREES AND SHRUBS:


Trees and shrubs designated by the Architect/Employer shall be protected from damage during
the course of the Work and the earth level shall not be changed within immediate surroundings
of such trees & shrubs. Where necessary, such trees and shrubs shall be protected by means
of temporary fencing.

51.0

GUARANTEE:

51.1

Besides guarantees required elsewhere, the Contractor shall guarantee the Work in general for
one year as noted under Clauses 36.0 and 40.0 above. All Bank Guarantees referred to in this
Agreement shall be renewed from time to time and kept alive during the entire period of contract.
All required guarantees shall be submitted to Architect by Contractor when requesting
certification of accounts for payment by Employer.

52.0
52.1

ANTIQUITIES:
All fossils and other objects of interest or value which may be found on the Site or in excavating
the same during the progress of the Work shall become the property of the Employer. The
Contractor shall carefully take out and preserve all such objects and shall immediately or as soon
as conveniently may be after the discovery of such articles deliver the same into the possession
of Architect / Clerk-of-Works un-cleaned and as excavated.

52.2

If in the opinion of the Architect compliance with the provisions of Clause 52.1 above has
involved the Contractor in direct loss and/or expense for which he would not be reimbursed by a
payment made under any other provision in this Contract then the Architect shall ascertain the
amount of such loss and/or expense. Any amount, from time to time, so ascertained shall be
added to the Contract Sum, and if an Interim Certificate is issued after the date of ascertainment
any such amount shall be added to the amount which would otherwise be stated as due in such
certificates.

52.3

EXCEPT MATTERS:
The decision, opinion, direction, certificate (except for payment) with respect to all or any of the
matters under Clauses 5.0, 8.0, 18.0, 24.0, 25,0, 35.0, 38.1.1, 38.1.2, 38.1.4, 38.1.7, 38.1.8 and
46.0 hereof (which matters are herein referred to as the Excepted Matters) shall be final and
64

conclusive and binding on the parties hereto and shall be without appeal. Any other decision,
opinion, direction, certificate or valuation of the Architect or any refusal of the Architect to give
any of the same shall be subject to any right of Arbitration and review in the same way in all
respects (including the provision as to opening the reference) as hereinafter provided.
54.0

ARBITRATOR:
All disputes and differences of any kind whatever arising out of or in connection with the Contract
or the carrying out of the works (whether during the progress of the works or after their
completion and whether before or after the determination, abandonment or breach of the
Contract) shall be referred to and settled by the Architect who shall state his decision in writing.
Such decision may be in the form of a Final Certificate or otherwise. The decision of the
Architect with respect of any of the Excepted Matters (referred to under Clause 53.0
hereinabove) shall be final and without appeal; but if either the Employer or the Contractor be
dissatisfied with the decision of the Architect on any matter, question or dispute of any kind
(except any of the Expected Matters) or as to the withholding by the Architect of any certificate to
which the Contractor may claim to be entitled then and in any such case the Employer will
appoint an Arbitrator from a panel of Architects suggested by the Indian Institute of Architects
and the Arbitrator will be a fellow of the Institute of Architects whose decision will be final and
binding on both the parties.

55.0

PROTECTION AND CLEANING:

55.1

The Contractor shall protect and preserve the Work from all damage or accident providing any
temporary roof, window and door coverings, boxing or other construction as required by the
Architect. This protection shall be provided for all property adjacent to Site as well as on the Site.

55.2

The Contractor shall properly clean the Work as it progresses and shall remove all rubbish and
debris from the Site from time to time as is necessary and as directed. On completion, the
Contractor shall ensure that the premises and/or Site are cleaned, surplus materials debris,
sheds etc. removed, areas under floors cleared of rubbish, gutters and drains cleared, doors and
sashes eased, locks and fastenings oiled, keys clearly labeled and handed over to the
Clerk-of-Works so that the whole is left fit for immediate occupation or use and to the satisfaction
of Architect /Employer.

56.0

TOLERANCE:

56.1

The Contractor shall exercise every care to ensure that all structural members are sufficiently
plumb and true to dimensions called for on the Drawings to receive prefabricated finishing
elements such as doors, windows, cabinet work, ceramic work, concrete, tiles etc. Any
variations may require rectification in the structural members or may involve remaking or
replacing the finishing elements, fabricated to fit into the openings or spaces, as called for on the
Drawings.

56.2

In case of separate contract, the contractor whose work does not conform to dimensions called
for, shall be liable for all the expenses which may have to be incurred for rectification or
replacement as may be required by the Architect for the proper installation of the finishing
elements. The Architect's decision in this respect shall be final and binding on the parties
concerned.

65

APPENDIX TO FORM OF TENDER


1)

2)
site.
3)

Performance Bond

2.5% (Two & Half Percent) of the sum for which Tender is
accepted rounded to nearest Rs.1,000/- in form of Bank
Guarantee from any Nationalized Bank valid for 24 months
from the date of award of contract.

Date of commencement :

7 Day from the date of receipt of Letter of Intent of work at

Time of Completion

th

12 Months

4)

Amount of Liquidated Damages

In respect of short fall in progress due to delay (penalty for


delay) only on the part of the contractor, the contractor shall be
liable to pay as penalty an amount equal to 1% per week of
delay upto 5% of Tendered Value (Refer Clause 2 of General
Conditions of Contract for CPWD works) after which the
contract gets terminated. If the contractor makes up the
shortfall in the stipulated time or extended time of completion,
penalty may be refunded on receiving written application by the
contractor

5)

Period of Maintenance

12
Months from the Date of Certification of Final Bill by
Architects (as detailed in General Conditions of Contract).

6)

Percentage of Retention Money : 5% (Five percent) to be deducted from each running bill and
Money shall be released as under:

7)

Value of Interim Bill

8)

Period of Certification

9)

Release of EMD

10)

Release of Performance Bond :

(i)

50% on completion of work and along with certification


of final bill by Project Management Consultant against
submission of Bank Guarantee.

(ii)

Balance 50% less recover, if any, towards cost of


defects rectified by the Employer due to lack of
response of the Contractor, on completion of defects
liability period and certification by Architects

Rs.40 Lakhs and above limited to One bill per month.


15 20 days from the date of submission of Bill to Accounts
Department along with measurement sheets, Bar Bending
Schedule, Rate Analysis for Non Tendered Items of Work if
any and other supporting purchase bills / documents /
Vouchers.
The Earnest Money Deposit (EMD) shall be refunded to the
unsuccessful bidders on issue of LOI to successful bidder. The
Earnest Money Deposit (EMD) of the successful bidder shall
be refunded after receipt of performance bond.
The performance bond shall be released at the end of the
defects liability period, after making such adjustments as may
be found necessary.

66

GENERAL

SPECIFICATIONS

MATERIAL & WORKMANSHIP - GENERAL


GENERAL SPECIFICATIONS:
These GENERAL SPECIFICATIONS should be read along with the relevant specifications, referred to in
the Common and Detailed specifications, applicable to the work in addition to the specifications given
below and the drawings mentioned in these documents shall be deemed to apply to the works unless
mentioned otherwise in the tender documents, in which case the provision in the tender document shall
take precedence.
Unless otherwise mentioned in the detailed specifications the rates quoted for all items should include
cost of materials, labor, machinery, plant and transportation.
NAME BOARD:
A name board about 2400mm x 2000mm as per drawings shall be made and displayed at site at an
approved place. The contents of board shall be as follows:
1.

Name of the Project

Civil, Electrical & Plumbing works for Proposed Farm House


At Jodupal Village, Madikeri.

2.

Name of the Employer.

M/s. Onella Infra Pvt Ltd, Hyderabad

3.

Name of the Architect &


Technical Consultants

M/s. MINDSPACE, No.3, Kalpana Chawla Road, R.M.V 2


Stage, Sanjay Nagar, Bangalore - 560 094

nd

Care should be taken to see that the height of letters especially for the Architect /Technical Consultants
should not be more than 2" to abide by the code of Professional Conduct prescribed by the Indian
Institute of Architects. The color, texture, etc. of the board shall be as per the Architect's instructions.
DRAWINGS, INSTRUCTIONS AND MEASUREMENTS: The contractor shall strictly adhere to working
drawings or detail drawings and written instructions of the Architects. No working drawing or detail
drawing shall be scaled. Figured dimensions alone shall be followed. Measurements shall be recorded of
the actual work done. However, the quantum of work over and above that indicated in the working or
detail drawings shall not be recorded unless the same is brought to the notice of the Architects. Mode of
measurement shall be generally in accordance with IS- 1200 for measurement of building works unless
otherwise specified. An approved Steel tape should be used at site and utmost care shall be taken to see
that the same is preserved in good condition throughout the period of execution. The contractor is
directed to deposit an identical tape with the Architects so that in case tape at site is lost or damaged,
another identical tape could be purchased after comparing it with the one deposited with Architects.
BENCH MARKS: The contractor shall erect sufficient bench marks in suitable locations for all the
buildings before starting the work, from which all important levels should be fixed. Exact levels of all floors
shall be set. A qualified surveyor shall be engaged by the contractor to locate all buildings, paths, roads,
utility lines etc. The contractor shall provide all pegs, flaps, pillars and labor required for setting out levels.
MEASURING MATERIALS: Materials requiring measuring shall be measured separately in boxes or in
appropriate stacked sizes before being mixed.
TESTING OF WORKS AND MATERIALS: If required by the Architects the Contractor shall arrange at
his own cost to test materials and portions of the work in order to prove their soundness and sufficiency
If, after any such test and in the opinion of the Architects, the materials or workmanship is found defective
or unsound, the Contractor shall pull down and re-execute the same at his own cost. All materials
deemed defective in the opinion of the Architects shall be removed from the site immediately.
CLEARING THE SITE: The "SITE" as indicated in the plan shall be cleared of all obstacles, loose
boulders or stones and materials, ash and rubbish of all kinds as well as brushwood. All holes and
hollows, whether originally existing or produced by removal of loose stones or brushwood shall carefully
be filled up with earth, well rammed and leveled. The site all round the building upto a distance of 3.0 M
shall be well dressed. The maximum cutting or filling being 300 mm, no extra for this shall be paid.
67

SITE CLEANLINESS: The Contractor shall see that the site always remains in a presentable condition
during the execution work. The construction work should display a marked degree of discipline. On
completion of the work, the Contractor shall at his own expenses, remove all surplus materials, debris
and rubbish of every description from the buildings, and site and shall find a place for depositing the
same. He shall remove all paint and whitewash stains, rub all floors, paving, etc. and shall leave
everything clean, watertight and perfect to deliver the buildings fit for occupation.
TREES: As far as possible trees shall be preserved unless otherwise instructed by the Architects If any
trees have to be cut, it shall form an extra item for which the Contractor shall be paid separately at the
rates detailed by the Architects. A tree shall be defined as a growth whose diameter of the trunk at the
base is more than 12" and the height is more than 12'.
TEMPORARY PROTECTION: All trenches, old and new walls, newly laid concrete or any other work
requiring protection from inclement weather or accidental injury shall be protected by means of tarpaulins
barricades, shoring strutting or in any other suitable manner to keep the work safe from damage.
MATERIALS AND WORKMANSHIP: The whole of the materials used on the work shall be new and of
the best quality of their respective kind. Other articles, tools, plants shall be the best of the several kinds
available in the market and shall be used in the best, most workmanlike, and most substantial manner to
complete satisfaction of the Architects and Employer.
SAMPLES OF MATERIAL: The Contractor shall deposit at the office of the Architects for their approval
samples of the materials proposed to be used in the works, and the bulk shall be equal in every respect
to the approved samples deposited. Such samples, including alternate samples should be furnished to
the Architects at least 15 days in advance of ordering for them.
SAMPLES OF WORKMANSHIP: The Contractor at his own expense shall prepare samples of all
joinery, cornice, parapets, mouldings, enrichments, etc. and shall obtain the approval of the Architects to
the same before putting the work in hand. If so required, by the Architect, the Contractor at his own
expense shall prepare the same and submit a second sample of each individual item of work. If the
Architects require more than two samples to be made of any individual item of work, the Contractor shall
prepare the same and shall be paid the actual cost of preparing the third and any subsequent samples of
such individual item. The Contractor shall carry out the work strictly in accordance with the approved
samples.
SKILLFUL WORK - PEOPLE TO BE EMPLOYED: The Contractor shall employ only experienced
competent, skillful work- people to do the work and whenever the Architects inform him in writing that
any man on the work, is untruthful or disorderly or otherwise unsuitable, such men shall be discharged
from the work and shall not be employed again on the job.
WATER: Unless otherwise specified the Contractor shall provide to the satisfaction of the Architects a
proper and sufficient supply of clean water for all purposes connected with the works, construct all
necessary service, with pipes, taps, stopcocks, tanks, etc. and he shall remove the same on completion
of the work. The water used in the work shall be perfectly clean, free from salt, vegetable matter and dirt
of any kind.
No water shall be taken from any place which in the opinion of the Architects is likely to be contaminated
with sewage or other impurity.
If so required by the Architects, the Contractor at his own expense shall have sample of water examined
by the chemical examiner to the Government and shall submit that official's report to the Architects. If the
chemical examiner's report on the water is favorable, the water shall be used on the work.
The Contractor shall bear all charges in connection with supply of the water required for the works.
SAND, ETC., AT THE SITE: Sand, gravel or other materials obtained on the site shall be used only by
the special permission of the Architects. Such permission shall be obtained by the Contractor in writing
before such material is used in the works and its agreed value shall be deducted from the amounts due
to the Contractor.

68

DEPOSITING DEBRIS ON SITE: Wherever it is stated in the schedule of quantities that debris shall be
deposited on the site, the rate quoted by the Contractor shall include for making all required excavations
for receiving or covering the debris within the limits of the site and neatly spreading the debris, and
covering the same with earth to the depth of at least 100 mm. If so ordered by the Architects, the
Contractor shall deposit and spread debris to form the foundations of roads, drives, paths, floors etc. in
such cases, the Contractor shall be entitled to payment only for consolidating the debris used for such
foundation.
CASING UP: The Contractor at his own expense shall board up all wood, stone, brick and other work
liable to injury and shall remove such casing when required or on completion of the work. He shall
thoroughly clean down the whole of the stone work etc., and make good any damage or defects.
PROTECTING FLOORS: The Contractor at his own expense, shall keep all floors covered with a good
layer of sand or shall otherwise protect them to the satisfaction of the Architects and shall clean the same
when necessary and shall make good all damage and leave it clean and perfect.
EXISTING DRIVES ETC: From the commencement of the contract until the work is handed over finally,
the Contractor at his own expense shall maintain to the satisfaction of the Architects all private roads,
drives, paths, car tracks, etc. over which traffic passes in connection with the works.
Upon completion of the work, the Contractor at his own expense shall provide all necessary materials
and shall make good all damage, consequent upon execution of work and shall leave such private roads,
etc. in good order to satisfaction of Architects.
REINSTATING COMPOUND: The Contractor at his own expense, shall reinstate to the satisfaction of
the Architects all parts of any compound disturbed by the building operations.
STORAGE: Safe, dry and proper storage shall be provided for all materials, particularly for materials like
cement. Adequate storage should be made at least sufficient for 3 months during active construction.
SPECIAL MATERIALS: If the materials of a particular brand are specified in the schedule these shall be
procured accordingly from approved manufacturers. These shall include materials such as: Bitumen and
Bituminous Compounds, Waterproofing, Hardening Compound, Special Paints, Acoustic and Insulation
Boards and other finishing materials. The Contractor shall procure necessary guarantee from the
manufacturers and furnish the same to the Architects.
DRAINAGE: The Contractors should ensure that during execution, efficient drainage of working area is
maintained and at no time accumulation of rain water occurs anywhere in working area.
SITE SURVEY: The contractor soon after the taking possession of the project site shall carryout at his
own cost accurate survey of the site and establish sufficient number of Grids, Level marks and
Permanent Bench marks to the satisfaction of the Architects, who on the basis of these grids and levels
shall decide the orientation of the proposed buildings/structures, the general finished ground levels
surrounding the proposed building/ structure and the finished floor level of the buildings/structures.

* * * * * * * * * * * * *

69

NOTES FOR EARTH WORK EXCAVATION AND FILLING


PS: THESE NOTES SHALL BE READ ALONG WITH THE COMMON SPECIFICATIONS AND THE
DETAILED ITEM SPECIFICATIONS:
Unless otherwise specified rates quoted for all excavation shall include the cost of the following:a. Site clearance such as clearing shrubs and growth, roots and small trees, brush wood, etc.
b. Cost of all materials and labour.
c. Setting out the works, profiles, etc.
d. Bailing out or pumping out all water which may accumulate in the excavation from all causes.
e. Getting out and throwing spoil clear off area being excavated or depositing clear of edge of
foundation to avoid fall in.
f. Trimming of all sides plumb or otherwise and square as instructed at site, leveling all bottoms &
ramming, clearing out all loose earth, etc;
g. Filling back with selected good earth and/or earth supplied, the sides of foundations and in plinth in
layers not exceeding 150 mm, watering, consolidation with mechanical rammers, wooden rammers or
roller, dressing, etc. including handling, loading, transporting, unloading, spreading complete.
h. Stacking excavated soft rock and/or hard rock for measurement as directed and disposing after
measurement within the site as directed.
i. Conveying manually or mechanically and disposing surplus soil/rock from the excavation site,
including loading and unloading ,as directed upto a lead of 150 mtrs ,spreading in layers of 200 mm,
leveling, dressing and forming to proper level and grade as directed.
j. Dismantling, removing and stacking as directed existing water pipes and/or soil pipes within the
excavation portion.
k. Providing shoring and strutting for protecting the sides of foundations where required.
l. Slinging or supporting pipes, electrical cables, telephone cables, etc; met during excavation.
m. Forming or leaving steps in the sides of deep excavation and their removal after measurement.
n. Providing guard lights and warning lights for trenches where required.
o. Making up pockets and undulation in the rock due to blasting or other means with PCC 1:5:10. (Not
measured for payment)
p. The compaction to be attained is 95% of maximum dry density at optimum moisture content as per
Standard Proctor Density Test.

70

NOTES FOR PLAIN AND REINFORCED CEMENT CONCRETE AND FORMWORK.


PS: THIS NOTES SHALL BE READ ALONG WITH THE COMMON SPECIFICATIONS AND THE
DETAILED ITEM SPECIFICATIONS:
Unless otherwise specified the following will apply for all items of plain and reinforced cement concrete
and formwork. Rates quoted shall be inclusive of the cost of the following but will exclude the cost of
reinforcement and inserts like bolts, plates, sleeves, pipes, etc.
a. All materials, labour and all form work, moulds, centering and shuttering.
b. Adequate protection to edges and corners from damage during construction.
c. Work either straight, curved, sloping, plain or tapered.
d. Keeping the work well watered for at least 10 days after casting.
e. Roughening/hacking concrete surface where required after removal of centering or shuttering to
receive plaster.
f. Work on all floors at all levels, locations, conditions and situations.
g. Building in and placing in position any inserts supplied.
h. Machine mixing and consolidation using vibrators of approved type.
i. Coarse graded sand shall be used for all concrete works.
j. Machine crushed coarse aggregate shall be of hard broken granite or Basalt or trap of sizes
specified.
k. Deshuttering, clearing and cleaning.
m. Test cubes and testing charges as specified.
n. Use of weigh batching equipment for design mix concrete, including the charges for getting the Mix
design done for grades as required.
o. Cost of all formwork including vertical supports of timber , MS props, MS spans, MS shuttering
sheets, wooden planks, runners, plywood, battens, bolts, etc;
p. Cost of all supports, struts, braces, ties, wedges, poles or other suitable arrangements to support
the formwork.
q. Cost of making and erecting formwork, scaffolding, staging, deshuttering, transporting, etc;
r. Cost of approved shuttering oil and labour, and consumables like wires, nails, ropes, clamps, bolts
or other items to hold the sheathing together.
s. Providing cutouts wherever necessary as indicated in the drawings.
t. Working scaffolds gangways, ladders and similar items.
u. Filleting to form stop - chamfered edge or splayed external angle, not exceeding 20 mm wide to
beams, columns and the like.
v. Splayed edges, notching allowance for overlaps, passings at angles, sheathing battens, strutting,
bolting, nailing, wedging, casing, striking and removing.
w. Bracing the scaffolding and staging at every 1.5 mtrs in both the directions.

71

x. Providing adequate no of props at suitable spacing so as to support the weight of wet concrete,
workmen during pouring, vibration due to equipments till formwork is removed.
y. Unless otherwise specified the material for formwork for different parts shall be as follows.
PART

TYPE OF FORMWORK.

1. Foundations

MS Sheet and/or wooden planks


and runners.

2. Pedestals, columns, beams,


lintels, pergolas, walls,
facias, drops and fins

Formwork with plywood lining.

3. Slabs and flat slabs of


all types

Formwork with MS sheets.

4. Staircases, lofts, cover


slabs, coping, chajja and
platforms

Formwork with MS Sheet and/or


wooden planks.

5. Pre cast concrete panels

Formwork with plywood lining.

REINFORCEMENT STEEL:
Unless otherwise specified the rate quoted for reinforcement steel shall include the cost of the
following.
a. The Cost of Steel including loading and delivery to site, unloading and storing at site or cost at issue
prices as specified and Receiving steel supplied by the Owner, unloading and storing.
b. Straightening, cutting, bending, conveying, hoisting and laying in position.
c. Providing 18 G black annealed binding wire in two folds.
d. Providing pre-cast concrete cover blocks or ACS plastic spacer blocks as specified.
e. Removing and cleaning oil, grease, oil stains, bitumen, paints, etc, from the steel rods, sheets, etc;
as directed.
f. Work at all heights and situations.

72

NOTES FOR STONE, BRICK AND CONCRETE BLOCK MASONRY WORK


PS: THESE NOTES SHALL BE READ ALONG WITH THE COMMON SPECIFICATIONS AND THE
DETAILED ITEM SPECIFICATIONS:
Unless otherwise specified, the rates quoted for all items shall include the cost of the following:
a. All scaffolding, ladders, platforms, staging & plant required in the execution of work to any height
and depth.
b. Hacking and roughening of concrete or other surface in contact with masonry for bondage.
c. Racking out joints to 12mm depth either for plastering or pointing.
d. Leveling up and preparing top of masonry for Damp Proof Course.
e. Building in holdfasts, bolts and such other inserts.
f. Keeping the work well wetted for two weeks.
g. Work at all heights, levels, depths, unless otherwise specified.
h. Providing through bond stones at every 2.0 M spacing in each coarse in stone masonry.
i. All works curved or straight.
j. Soaking of bricks and concrete blocks in water for minimum 12 hours.
k. Cost of all materials, transport to site and labour.
l. Leaving holes for pipes or similar items.
m. Building in ends of beams, joists, slabs, lintels, sills, trusses etc;
n. Stones used shall be granite, trap and/or basalt unless otherwise specified.

73

NOTES FOR FLOORING, PAVING, SKIRTING AND DADO:


PS: THESE NOTES SHALL BE READ ALONG WITH THE COMMON SPECIFICATIONS AND THE
DETAILED ITEM SPECIFICATIONS:
Unless otherwise specified rates quoted shall include the cost of the following:
a. Cost of all materials, transport, labour, etc;
b. Final preparation of base sub-grade or sub-floor by cleaning all dust/dirt, loose particles, and caked
mortar dropping by scrubbing with coir or steel wire brushes. Roughening surface if so directed,
cleaning with water & keeping surface wet for 12 hours and removing surplus water by mopping before
topping is laid and minor trimming of the base to remove undulations.
c. Cleaning and watering immediately before laying the floor as directed.
d. Providing bedding layer of mortar as specified in the case of slabs, tiles, etc. to correct levels or
steps as called for.
e. Cutting, rubbing and polishing where applicable.
f. Working at all heights, levels and situations.
g. Hire of all equipments and running costs of all ecumenists required.
h. Keeping the surface wet for a minimum period of one week.
i. Receiving all materials supplied by the Employers, unloading, storing, and conveying to work site
and fixing in position.
j. Cleaning tiles, waxing and/or acid washing where required.
k. Pointing with matching coloured cement and/or pigmented white cement to match the colour of the
tiles/stones.

74

NOTES FOR PLASTERING, POINTING AND PAINTING:


PS: THESE NOTES SHALL BE READ ALONG WITH THE COMMON SPECIFICATIONS AND THE
DETAILED ITEM SPECIFICATIONS:
Unless otherwise specified rate quoted for all items shall include the cost of the following:a. Cost of all materials and labour.
b. Hacking or scarifying concrete surfaces to be plastered or rendered.
c. Preparation of surfaces by raking out joints, wetting the surface etc;
d. Providing grooves at the junction of masonry and concrete members wherever different
materials are connected and in the pattern as shown in the drawing or as directed by the
Architects.
e. Work at all heights, levels and situations.
f. Providing drip moulds wherever necessary as directed.
g. Washing floors, cleaning glass and leaving premises clean and tidy.
h. Curing for at least 10 days.
i. Providing necessary scaffolding, ladder, platform for any height and depth and removing.
j. Providing Galvanised Expanded Metal Mesh (Plaster Mesh) of 0.35 mm thickness and 125 mm
width at the junctions of concrete and masonry including fixing in position.
k. Neat finishing of junctions of plaster and skirting.
l. Screening and washing approved fine aggregates.
m. Preparing surfaces for painting by cleaning and removing all dusts, dead mortar, etc;
n. Providing all materials like paints, brushes & other materials and application of paint as per
specifications and manufacturers instructions.
o. Making surfaces even by filling in putty, rubbing with sand paper and making good all depressions.
p. Providing polythene sheets and protecting adjacent equipments, furniture, floors, etc.
q. Curing, protecting the painted surface and thoroughly cleaning the premises (Floor, doors, windows,
glass panes and other surfaces after painting).

75

NOTES FOR STRUCTURAL STEEL WORK:


PS: THESE NOTES SHALL BE READ ALONG WITH THE COMMON SPECIFICATIONS AND THE
DETAILED SPECIFICATIONS:
Unless otherwise specified the rates quoted for all items shall include the cost of the following
a. Receiving all materials supplied by the Employer, unloading and storing.
b. Straightening, cutting, fabricating, conveying to work site, hoisting and fixing in position.
c. The cost of all materials and labor.
d. Work at all heights, levels and situations.
e. Providing necessary scaffolding, staging, platforms, ladders, etc; and removing.
f. Hire charges for necessary hoisting equipments like crane, chain pulley locks, derricks, winches,
screw jacks, hooks, wire ropes, etc;
g. All necessary fixtures like bolts, washers and nuts.
h. Approved quality welding electrodes like "Philips", "Advani Orlekon" make or approved equivalent.
i. Welding at all heights, levels, conditions and situations.
j. Cost of safety belts, goggles, helmets and other necessary safety equipments.
k. Preparing the surfaces for painting and also for welding.
l. Painting with two coats of primer and top coats wherever specified.

76

NOTES FOR MISCELLANEOUS WORKS:


PS: THESE NOTES SHALL BE READ ALONG WITH THE COMMON SPECIFICATIONS AND THE
DETAILED ITEM SPECIFICATIONS:
Unless otherwise specified the rates quoted for all items shall include the cost of the following
a. Cost of all materials and labour.
b. Work at all heights, levels, conditions and situations.
c. Providing necessary scaffolding, staging, platform, ladders, and removing.
d. Receiving all materials supplied by the Employer, unloading, storing, and conveying to work site and
fixing in position.
e. Cost of hiring necessary equipments where called for.
f. For specialized items the work should be carried out complete as per the manufacturer's
specification and recommendations if the item specifications are incomplete.

77

NOTES FOR WEATHERPROOFING WORKS


PS: THESE NOTES SHALL BE READ ALONG WITH THE COMMON SPECIFICATIONS AND THE
DETAILED ITEM SPECIFICATIONS:
Unless otherwise specified, the rates quoted for all items shall include the cost of the following:
a. All scaffolding, ladders, platforms, staging & plant required in the execution of work to any height
and depth.
b. Cleaning & preparing of concrete or other surface.
c. Laying it to proper slope as directed.
d. Building in holdfasts, bolts and such other inserts.
e. Keeping the work well wetted/flooded for two weeks.
f. Work at all heights, levels, depths, unless otherwise specified.
g. Providing good quality well burnt bricks/brick bats.
h. Cost of all materials, transport to site and labour.
i. Leaving holes for pipes or similar items and finishing around them properly after fixing the pipes.
j. Clearing the debris after completion of the work.

78

Вам также может понравиться