Академический Документы
Профессиональный Документы
Культура Документы
June 2014
CONTENTS
Chapter
No.
Description
Page
No.
Executive Summary
Introduction
II
Acknowledgement
III
IV
66
VI
Annexure
70
VII
Back-up Calculations
90
EXECUTIVE SUMMARY
Asian Paints is one of the India's largest paint companies which manufacture
paints for decorative and industrial use. Since its foundation in 1942, Asian
Paints has come up a long way to become Indias largest and Asias third
largest paint company, with a turnover of Rs. 127.15 billion. Asian Paints
operates in 17 countries and has 23 paint manufacturing facilities in the world
servicing consumers in over 65 countries.
The plant team has done exceedingly well in incorporating certain energy
efficiency aspects in design stage. Further, plant team has taken many steps
towards the improvement in energy efficiency.
CII has conducted the Detailed Energy Audit at Asian Paints Limited.,
Patancheru Plant from 15 to 21 January, 2014. A detailed presentation was
made to the plant team covering various energy conservation opportunities on
25th January, 2014. The combined efforts of Asian Paints Limited., Patancheru
and CII-Godrej GBC team have together identified, annual energy saving
potential of Rs. 98.81 Lakhs, based on present energy cost.
The summary of the annual energy savings identified is as below:
Total Annual Savings (14 proposals)
: 9 months
CHAPTER I
INTRODUCTION
Asian Paints Limited, Patancheru evinced keen interest in availing the services
of CII - Godrej Green Business Centre (CII Godrej GBC) of the Confederation
of Indian Industry (CII) for conducting a detailed energy audit at their unit.
The CII-Godrej GBC proposal for conducting a detailed energy audit at Asian
Paints Limited, Patancheru was accepted by management; vide their Reference
P.O. No. 15191843, dated 26th November, 2013.
The field activities of the detailed energy audit were conducted in one visit and
the final presentation to the plant team was made on 25th January, 2013.
The methodology adopted for conducting the detailed energy audit at
Asian Paints Limited, Patancheru is as follows:
Basic data collection on list of power consuming equipments, design
specifications of the major equipments and actual operating parameters
Power measurements of major electrical energy consumers
Measurement of operating parameters of various equipments to estimate
their operating efficiency
Analysis of data collected and measurements, to develop specific energy
saving proposals
Discussion with the plant personnel on the identified proposals
Presentation on the findings of the detailed energy audit to the plant
personnel, with the cost economic analysis
We are pleased to mention that all the identified energy saving proposals have
been discussed with the plant executives before finalizing the ideas.
The contents of the report are based on the data provided by the plant
personnel and actual measurements conducted jointly by the CII-Godrej GBC
and plant team during the detailed energy audit.
The plant personnel should implement the suggestions made in this report,
after verifying the necessary regulatory safety aspects. It is solely the
responsibility of the plant personnel to observe statutory regulations, if any, as
applicable to their plant.
CHAPTER II
ACKNOWLEDGEMENT
CII acknowledges with thanks the co-operation and the support extended to
the CII energy audit team during the detailed energy audit at Asian Paints
Limited, Patancheru.
The interactions and deliberations with Asian Paints Limited, Patancheru
team were exemplary and the whole exercise was thoroughly a rewarding
experience for CII.
The arrangements and support during the energy audit were excellent. We
deeply appreciate the interest, enthusiasm and commitment of Asian Paints
Limited, Patancheru team towards the energy conservation.
We would also like to place on record our sincere thanks and appreciation for
all the senior plant executives.
CHAPTER III
Annual
Savings
(Rs. Lakhs)
Investment
Required
(Rs. Lakhs)
Payback
Period
(Months)
28
0.9
31
1.8
13
24
2.8
13
56
22.3
0.31
13.45
14.5
13
1.97
19
0.44
0.6
17
12
4.2
1.6
3.5
42
9.9
11.54
98.81
75.0
Chapter IV
Energy Saving Proposals
The scotopic curve and photopic curve mention the day-time lighting and
night-time lighting respectively. The eye colour is more sensitive towards the
green colour for photopic curve and is correspondingly for blue colour in the
case of scotopic vision. This data of relative sensitivity of eye helps us in
designing the correct colour of the lamp required for different lighting
conditions. The scotopic vision is well suited for night environment such as
street lights, basements, closed rooms where sunlight is not available. The
photopic on the other hand will be closer to day-time environment.
The earlier system of lighting wherein the quantity of light delivered was
mentioned in lumen and not in pupil lumen considered only the photopic
curve.
Comparison of Lamps
The table below shows a brief comparison of all the lamps. LED is the latest
energy efficient technology in lighting. Compared to the conventional lamps, it
offers significant advantages in terms of energy consumption along with other
benefits. The latest trend is to go for LED lamps. These LED lamps have very
high scotopic to photopic ratio of 2.4. This is very well suited for lighting in
dark surroundings. Eg: street lighting, Closed rooms with low sunlight.
S.No Parameter
LED
HPSV
CFL
Metal
Halide
FTL T8
15,00020,000
Hours
60008000
Hours
10,00012,000
Hours
8000 Hours
Life
50000
Hours +
Lamp
Efficacy
90-100
90-140
60-65
65 to 90
60-68
30% @
Lumen
50,000
Depreciation
Hours
Upto
40% @
15000
Hours
1520%
till end
of life
Upto 40% @
12000
Hours
15-20% till
end of life
CRI
70-90
22- 25
65-85
65-90
60-72
Color
Variety
Yellow
White
White
White
Color
temperature
210010000K
2100K3000K
30006000K
4000-5000K
3000-6500K
S/P Ratio
Upto
2.4
0.62
1.3-2.2
1.6
1.3
Warm up
time 90%
Lumen
Instant
4
minutes
1
minute
5 minutes
10-50
Seconds
Flicker free
yes
No
No
No
No
Advantages of LEDs
As identified from the above table, LED lamps offer the following advantages
Lower energy consumption
High S/P ratio
Longer life time
Faster switching
Greater durability and reliability
Good Colour Rendering Index (CRI)
More focused light and reduced glare
Does not contain pollutants like mercury
Highly compatible for solar lighting as low-voltage power supply is sufficient
for LED illumination
Higher Light Output Ratio (LOR): The Light Output Ratio indicates the actual
amount of light that can be obtained after considering the losses in
luminaire. As can be seen from the figure below, the light output also
depends on the light fixture. In the first fixture, certain amount of light is
lost. The second fixture has a mirror finish reflecting the light lost to the
ceiling in the first case is directed downwards and the loss of light is low in
comparison to the fixture on left. The light fixtures that house LED lamps
are latest and hence the loss of light is low. LED fixtures have an LOR close
to 100%.
10
Type
of
Lamp
Luminous
Wattage
efficacy
of lamp
(lumen/Watt)
Correction
Photopic
factor
efficacy
(S/P
(pupil
ratio)
lumen/Watt)
Pupil
lumen
Can be
replaced
with
LED
Watt
T8
72 W
60
1.3
78
5616
20 W
CFL
72 W
65
1.3
84.5
6084
18 W
HPSV
70 W
90
0.62
55.8
3906
18 W
HPSV
150 W
90
0.62
55.8
8370
30 W
HPM
V
70 W
54
0.8
43.2
3024
18 W
MH
150 W
65
1.6
104
15600
70 W
MH
250 W
65
1.6
104
26000
100 W
Not all fixtures can be retrofitted with LED lamps directly and the fixtures may
need modification. The above methodology can be followed when considering
any future replacement of existing lamp fixtures.
Strategy for lighting fixture replacement
The following strategy can be adopted when replacing the existing lamps with
LEDs. During the audit, it was noted that the plant team has installed LEDs at
some locations on a trial basis. CII congratulates the plant team for the
excellent initiative taken. CII along with the plant team identified further
potential to replace the existing lamps with LEDs.
The lamps can be replaced in a phase-wise manner, prioritizing the ones with
higher energy savings and minimum pay back. These energy saving proposals
and the benefits were explained below.
1. Replacement of HPSV and HPMV lamps for street lighting
2. Replacement of T8 lamps with LEDs
3. Replacement of CFL lamps with LEDs
4. Opting renewable energy for street lighting
11
T8
FLUORESCENT
Location
Watt
Quantity
Power in
kW
Operating
Hours
Other Offices
36w x 2
746
53.71
2432
Engg Store
36w x 2
40
2.88
2432
Production Blocks
36w x 2
849
61.13
4984
BSR
36w x 2
90
6.48
4984
DC
36w x 2
10
0.72
4272
RMG
36w x 2
219
15.77
4984
PMG
72 w
80
5.76
4984
Based on the description earlier, considering factors like S/P ratio and LOR,
there is a good potential to replace these 2X36 W T8 lamps with 1X20 W LED
lamps.
Recommendation
It is recommended to replace the existing 2X36W T8 lamps with 1X20 W LEDs.
The energy saving that can be obtained by shifting to LEDs is around 106 kW.
It is recommended to replace the T8 lamps in a phased manner. The lamps
with higher operating hours can be replaced first for higher savings. Based on
the results, the lamps at the other locations can also be subsequently
replaced. The lamps in the DC, BSR, and PMG can be replaced first followed by
other areas. LEDs can be considered as priority when replacing a failed lamp.
Confederation of Indian Industry
12
Benefits
The estimated annual savings that can be obtained by replacing T8 lamps with
LEDs is Rs. 28 lakhs. The investment required is Rs. 31 lakhs. The payback
period is 14 months.
13
14
15
16
O2: 9.0 %
Temp:
175oC
Thermop
ac
20 Lakh
kcal/hr
APH
O2: 7.5 %
Flue gas:
6556 m3/hr
Temp: 283oC
Flame Modulation: High Flame
Scenario
Ambient air:
28oC
17
Temperature
Thermopack TP 405
% O2
CO (ppm)
Thermopac immediate
outlet before APH
7.5
5.0
283
9%
3.0
175
(Deg C)
19
Temp: 96oC
O2: 6.5 %
Removax
LPG/HSD
Fired
RXA 06
Flue gas:
Temp: 196 C
1669 m3/hr
With in
built feed
water
economis
er
Ambient air:
28oC
Boiler RXA 06
% O2
CO (ppm)
Boiler outlet
6.5
43
Temperature
(Deg C)
196
20
Benefits
Optimizing the combustion air supply to the boiler by reducing the combustion
air by modulating the inlet damper and maintaining 3 % O 2 at exit flue gases
would result in an annual savings of Rs. 1.00 lakhs. The investment required
for procuring a gas analyzer is already considered in the similar excess air
optimization project for thermopac operation and would have no additional
investment requirement.
22
23
R1
R3
R6
R8
R9
Bypass Valve
Thermopac
20 Lakh kcal
Recommendation
We recommend the following:
The thermic fluid pump is already installed with VFD
Interlock the thermic fluid pump discharge pressure header pressure to
the pump speed.
As per the optimization plan, thermic fluid pump speed can be varied
between 90 to 100 % of the rated speed.
As the pump seal air fan is build in pump main shaft, we recommend to
conduct trails during the night hours when the ambient air temperature
are lower compared to day time. (Caution should be taken in setting the
pump speed control limits to up to maximum reduction to 47.5 Hz)
Benefits
The annual energy saving potential by optimizing the thermic fluid circulation
pump operation based on the heat requirement in the resin house reactors
would be Rs. 0.31 lakhs which doesnt calls for any investment as VFD is
already installed in the pump.
24
Flow
(m3/hr)
43000*
Flow
(CFM)
25298
Power
(KW)
19
Efficiency SEC
SEC Norm
(%)
(W/CFM) (W/CFM)
0.75
0.18
39347
23149
17.79
28
0.77
0.18
43801
25770
8.55
56
0.33
0.18
45512
26776
8.46
49
0.32
0.18
69386
40822
28.44
48
0.70
0.18
* Actual flow to system for VSP 301 was measured to be 22480 m3/hr. This
reduced flow was mainly due to leakage at immediate blower discharge
ducting. For calculation of specific energy consumption (SEC), the rated flow
was considered to obtain the energy savings conservatively.
The specific energy consumption of the blowers were measured and are
compared with the specific energy consumption of high efficiency blowers of
same capacity.
Blower VSP 303 AND VSP 304 SEC is in the range of 0.32 to 0.33 W/CFM
whereas for the other three blower is over 0.70 W/CFM. This clearly indicates
lower operating efficiency of the blowers.
Confederation of Indian Industry
25
Recommendation
We recommend the following:
Phase I
Replace the discharge blower VSP 301 & 302 with two new high efficient
blower of 40000 m3/hr capacity.
Considering the new operating SEC of 0.25 W/CFM, the saving potential
for phase I blower would be 18.7 KW.
Phase II
Replace the discharge blower VSP 305 with a new high efficient blower of
70000 m3/hr capacity.
Considering the new operating SEC of 0.35 W/CFM, the saving potential
for phase I blower would be 9.9 KW.
Benefits
Replacing the low efficiency blower with new high efficiency lower SEC blower
would result in an annual saving of Rs. 13.45 Lakhs. This calls for an
investment of Rs. 14.50 Lakhs for installation of new blower and would have
an simple payback of 13 Months.
26
S.No
User
3 kL Reactor
50
5 kL Reactor
46
LDV
15
90
Total
200
(TR)
The operation of the users of the WBU cooling tower usually do not overlap
and one or two users of the cooling tower are in operation. But sometimes the
users of the cooling tower overlap and is as indicated by the usage of chilled
water for cooling tower water.
The installed capacity of the cooling tower in this section is only 120TR, which
is not sufficient to meet the maximum heat load. Since there is some risk that
all or many of the users may operate at the same time, it may be considered
to install an additional cooling tower of 120 TR capacity. Installing an
Confederation of Indian Industry
27
additional cooling tower of 120 TR will solve the issues related to cooling when
the operation of the users of the cooling tower overlap.
It has been understood from the plant team that there is issue of obtaining
lesser cooling from the cooling towers and increasing the duration of cooling
for reactors and LDV. This is an indication that the cooling tower heat rejection
is not sufficient when more users are in operation. If the cooling tower return
water temperature increases there is a possibility that the chiller may trip due
to high pressure.
In the subsequent proposals of optimizing the cooling water for reactors and
LDV, the cost of installing a 120TR cooling tower is considered for the reactors.
The cooling water to the reactors and LDV can then be optimized to obtain
sufficient cooling with lower flow and optimized T. The details of these are
also explained in the proposals.
28
As indicated in the figure, when only 5kL reactor pump was running,
recirculation of 27 m3/hr (22%) was observed through 3 kL pump due to the
Confederation of Indian Industry
29
CIISohrabji Godrej Green Business Centre
30
Recommendation
We recommend to
Step 1:
Avoiding recirculation
Step 2:
Step 3:
Install VFD for one pump and operate only that pump even for 2
reactors
Before installing VFD, plant can take a trial by reducing the flow by
throttling the pump in steps of 10% till temperature difference of
40C is achieved across the reactor
Benefits
Implementing the above recommendation will save Rs 1.90 Lakhs annually.
This requires an investment of Rs 3.0 Lakhs for VFD, control valves & new
cooling tower, which will be paid back with a simple pay back period of 19
months.
31
The temperature difference across LDV is only 20C. For a heat exchanger, the
minimum temperature difference that can be maintained is 4 0C. This indicates
excess flow through LDV which can be reduced.
32
Flow can be reduced by throttling the pump or installing VFD and operating it
with pump discharge pressure as feedback. Controlling the flow by throttling
leads to partial energy savings. Some of the power will be lost in overcoming
the pressure drop across the throttle valve. Controlling the flow by reducing
the speed of the pump by installing VFD will save more power.
Before installing VFD, trail can be taken by throttling the pump in steps till the
temperature difference of 40C is achieved & simultaneously monitoring the
material temperature.
Recommendation
We recommend to
Before installing VFD, trail can be taken by throttling the pump in steps
till temperature difference across LDV reaches 40C.
Install VFD for the pump
Operate VFD in closed loop with the header pressure
Benefits
Installing VFD and operating VFD in closed loop with header pressure will save
Rs 0.44 Lakhs annually. This requires an investment of Rs 0.60 Lakhs,
which will be paid back with a simple pay back period of 17 months
33
490
64
2.92
49
0.4
7.1
8.3
3500
491
64
2.92
25
0.2
5.0
2400
492
64
2.92
71
1.2
4.41
58.5
5500
470
91
5.0
74
2.6
21.3
27
160
481
125
3.2
28
8.7
39
100
482
125
3.2
64
3.7
12.3
58
1300
483
125
3.2
3500
34
Since the running hours of pump were low, replacement with energy efficient
pump was not viable.
Recommendation
We recommend the following
Replace the existing impeller with a new one for the pump 491
Avoid running the pump 490, 491 till the impeller gets replaced
Run only pump 492 as it can deliver required flow
Run higher efficient pump for maximum number of hours
Benefits
Implementing the above proposal will save Rs 1.0 Lakh annually. This
requires an investment of Rs 1.0 Lakh for new impeller, which will be paid
back with a simple payback period of 12 months.
35
Cooling tower fans were operating based on the cold well temperature. Fans
switch on when cold well temperature reaches 270C and switches off when it
reaches 250C. Currently, the temperature feedback to the fan to switch on and
off has failed and the cooling tower sump temperature of 32 oC has been
observed, instead of desired temperature of 25oC.
The energy saving by switching on and off the cooling tower fan is partial. The
cooling tower requires good air water contact to achieve a good approach.
There is a good potential to install VFD for the Cooling tower fans and operate
with a feedback based on cooling water leaving temperature. The desired
temperature of the cooling tower sump can be given as feedback to the VFDs
of cooling tower fans. Currently, the process parameters are not affected by
the cooling water temperature of 32oC. Thus 32oC of cooling water
Confederation of Indian Industry
36
temperature can be maintained and the calculations have been considered for
32oC. If the temperature of 25 -27 oC is considered, the energy savings will be
lower.
When measurements were taken, CT fans were in OFF condition. The range of
20C was being achieved by the cooling tower. Generally, cooling towers are
designed to give a range of 6-80C. By switching on the fans and running them
continuously with a VFD, cooling tower can give minimum range of 4 0C i.e.,
range will get doubled and the cooling water flow can be halved.
Currently, 2 pumps are running continuously and delivering 93m 3/hr (P458)
and 62m3/hr(P457) continuously. Total cooling water flow is around 150m 3/hr.
One pump P457 can be switched off. Then the second pump (P458) will deliver
more flow than before as the system resistance reduces as the cooling water
flow reduces.
The power consumption of the second pump can be optimized by installing
VFD and operating it with pump discharge pressure of 2 kg/cm 2 as feedback.
Cooling tower fans can be installed with VFD and operated in closed loop with
cold well temperature interlock of 320C.
Recommendation
We recommend the following
Install VFD for CT fans and operate the VFDs in closed loop with the cold
well temperature of 320C
Operate the VFD in closed loop with the discharge header pressure of 2
kg/cm2
Benefits
Optimizing the operation of industrial cooling water pumps will save Rs 1.60
Lakhs annually. This requires an investment of Rs 4.20 Lakhs, which will be
paid back with 5 months.
37
REPLACE INEFFICIENT
EFFICIENT PUMPS
PUMPS
WITH
NEW
ENERGY
During the detailed energy audit at Asian Paints Limited., Patancheru Unit
the performance of the water pumps in the plant were studied in detail for
identifying energy saving opportunity.
Background
The water flow and head measurement was carried out for all pumps in the
plant. The design parameters and measured values are as follows.
Pumps
Tag #
70 TR chiller
monomer pump
70 TR chiller hot well
pump
Pump house P504
Design
Parameters
Operating Parameters
Motor
Flow Head Loading Efficiency
m3/hr (m)
kW
%
Flow
m3/hr
Head
(m)
60
21.00
24
6.15
24
18
33.00
10*
2.4
41
23.5-9.5
11-39
21.00
32
5.79
34
The operating efficiency of above pumps is low due to mismatch between the
design and operating head / ageing of the pumps / low efficiency by design.
The below diagram shows how efficiency of the pump reduces with mismatch
between design and operating parameters
38
Characteristic curve
Operating point
*
Design point
*
Iso efficiency curves
Head
60%
50%
40%
Power
25 m3/hr
Head
Efficiency
:
:
25 m
> 70%
35 m3/hr
Head
pressure guage
Efficiency
> 70%
25 m3/hr
Head
Efficiency
:
:
35 m
> 70%
Benefits
39
Installing new high efficiency pumps in identified areas will save Rs 1.0 Lakh
annually. This requires an investment of Rs 3.50 Lakhs for three new pumps,
which will be paid back with a simple pay back period of 42 months.
40
OF
THE
AIR
Present status
During the detailed energy audit of Asian Paints Limited, Patancheru Unit,
a detailed study of all the compressed air units was carried out for possible
energy saving opportunities.
The plant has installed a centralised compressed air system consisting of two
screw compressors which maintain the pressure of the receiver at 5.7 bar. This
centralized compressed air system supplies air to all the sections of the plant
viz. Water Based Unit, Solvent Based Unit, Industrial Paint Unit, Resin Block
and the Monomer block.
Monomer
Tank
P405
587 CFM
5.7 bar
5.6 bar
5.5 bar
Refrigerant
Drier
10m3
Receiver
P406
587 CFM
5.5 bar
Industrial Based Unit
Phase I & II
5.5
bar
Resin
Block
5.4
bar
Compressor
P405
P406
Location
Compressor
House
Compressor
House
Loading
Pressure
bar
Unloading
Pressure
bar
Average
Pressure
bar
Power
kW
5.7
6.2
5.95
88.30
5.5
6.0
5.75
86.03
It was observed that when the plant is in full load operation, one compressor is
continuously running and the second compressor is running for 10 % of the
time. This compressor has been set in such a way that if it is in unload for
more than 10 minutes it automatically switches off. The limit of switching on
and off for a 110 kW motor is not more than four times in an hour.
41
During the detailed energy audit of the plant, a comprehensive compressed air
distribution study was carried out to understand the compressed air
requirement at the end users and the pressure drop at the farthest point in the
plant. During the compressed air user study of the plant, it was observed that
the compressed air pressure drop at the farthest point from the generation
was not more than 0.2 bar.
The compressed air pressure being maintained at different applications in the
plant is as follows:
Purpose of Compressed Air
Pressure Maintained
Open/Close valves
4.0 bar
Hopper Aeration
3.0bar
Bag Filters
4.0bar
3.0bar
4.0bar
5.0bar
Cleaning Purpose
3.0bar
It was observed that in most of the end users the pressure setting being
maintained was between 3.0 bar to 4.0 bar. The only operation which requires
a pressure of 5.0 bar is the Lid pressing operation in packer area. The
manufacturer has advised a pressure setting of 6.0 bar considering a safety
margin but the plant is running the packer machine successfully maintaining a
pressure setting of 5.0 bar. It was also observed that these packing machines
were already installed with additional booster compressors, which cater to the
higher pressure compressed air requirements of these machines. CII
congratulates the plant team for this excellent initiative towards
energy conservation activity.
Here is a good opportunity to utilise this booster compressor so that it supplies
high pressure compressed air to the packer machine and reduce the
compressor air pressure at the generation end itself.
Proposed System
The compressed air pressure maintained for most of the applications in the
plant is not more than 4.0 bar. Only the lid pressing operation in the packing
Confederation of Indian Industry
42
CIISohrabji Godrej Green Business Centre
- 4.2 bar
Unload point
- 4.7 bar
The above set points have been suggested on a conservative basis and there is
still further scope for the plant team to reduce the generation air pressure.
By reducing the generating pressure of compressed air, energy savings of
around 29 kW is possible.
Benefits
The annual energy savings achieved by implementing this project is Rs. 9.9
Lakhs. This does not require any major investment.
Confederation of Indian Industry
43
44
Sl. No.
Area
Leakage (%)
Total Leakage
47
24
12
11
10
11
12
13
At AML area near mixer 253, lid pressing unit FRL leakage
Solvent Based Paint Unit - First Floor (Processing)
14
15
16
17
18
19
45
20
21
22
Dust collector TSD 211 air inlet line leakage QRC fitting
Industrial Paint Unit
23
24
25
26
27
28
29
30
31
32
CA inlet to BL P413
Resin House (1st Floor)
33
34
35
CV BLP 402
36
37
38
39
40
FRV bottom
41
42
46
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
47
66
67
68
69
Pug mill hopper 183 I/L to purge line 3rd from top
70
71
Diverter valves
Terrace
72
73
Hopper no 5
Usually the norm is of maintaining compressed air leakage to less than 15% in
a plant. In some of the energy efficient plants, compressed air leakage was
observed to be as less as 6%. Therefore, here is a good opportunity to
conserve energy and minimize the leakages in the plant.
Recommendations
It is recommended to
Avoid unwanted purging of compressed air
Arrest the leakages at identified locations
Avoid the use of High Pressure compressed air for cleaning
Increase the awareness among the operators and the workers on the value
of compressed air
Promote Red-tag system among the workers in the plant, wherein
whenever any worker identifies a leakage point, he will attach a red tag at
the leakage point
The maintenance staff then addresses the leakage with the help of the tag
and minimum leakages are maintained in the plant
Conduct leakage test during shut down time
Identify & arrest the leakages
Considering reduction in the leakage to 30% from the current values,
Benefits
Confederation of Indian Industry
48
The annual energy saving potential by arresting the compressed air leakage
points is Rs. 11.54 Lakhs. This does not require any major investment.
49
Observation
50
OBSERVATION No. 1
L is used when speed and accuracy is not important and task is executed
occasionally.
51
The lux measurements were carried out at various locations in the plant,
during the detailed energy audit.
The lux levels measured and the recommended values are mentioned below.
The lux levels were sufficient at the following areas:
Location
SBU Ground
floor
Time
Avg lux
Recommende
d Lux
Corridor
130
50
BOPT changing
area
270
100
Area
Day time
SBU Ground
floor
Day time
IPU- FF
Day time
189
100
IPU- FF
Day time
Lab area ph -1
103
100
IPU SF
Day time
545
100
RH- MF
Day time
stair case
1500
50
RH- SF
Day time
55
50
Avg lux
Recommende
d Lux
23
100
Corridor- 1
28
100
Filling area
58
100
23
100
Corridor- 1
20
100
Time
Area
WBU - Ground
floor
Day time
Night time
52
Day time
Night time
Day time
WBU Second floor
Night time
Filling area
27
100
Filling vessels
18
100
33
100
22
100
Process area
34
100
Pugmill area- 1
49
100
Pugmill area- 2
26
100
Liquid storage
25
100
Filling vessels
20
100
22
100
18
100
Process area
34
100
Pugmill area- 1
40
100
Pugmill area- 2
30
100
Liquid storage
25
100
Reactors
28
100
27
50
Hoppers
65
100
TSD
24
100
Storage area
34
75
Reactors
20
100
53
18
50
Hoppers
30
100
TSD
38
100
Storage area
20
75
53
100
61
100
70
100
77
100
56
100
56
100
80
100
89
100
Corridor
37
50
BOPT changing
area
27
100
Process stations
62
100
circle 2
Below tanks &
filling stationscircle 3
Below tanks &
filling stationscircle 4
Below tanks &
filling
stations -circle 1
Below tanks &
filling
stations -circle 2
SBU Ground
floor
Night time
SBU
Day time
54
1
Process stations
2
43
100
Process stations
1
47
100
Process stations
2
22
100
Corridor
19
50
Day time
Below tanks
36
100
Night time
Below tanks
18
100
Process stations -1
68
100
Process stations -2
34
100
Corridor
32
50
Process stations -1
50
100
Process stations -2
20
100
Corridor
16
50
Mixer/packing
floor ph- 1
63
100
Batching area
18
100
Mixer/ packing
floor ph -2
30
100
Mixer/packing
floor
34
100
Batching area
15
100
Mixer/ packing
floor ph -2
19
100
48
100
56
100
First floor
Night time
SBU MF
Day time
SBU - second
floor
Night time
Day time
IPU GF
Night time
IPU FF
Day time
55
Night time
Day time
IPU SF
Night time
RH GF
Day time
51
100
Passage area Ph
2
29
50
14
100
Lab area ph -1
86
100
19
100
22
100
Passage area Ph
2
22
50
43
100
SM/TR area
77
100
TSD/ATT area
53
100
FG storage area
25
100
Solvent storage
tank area
42
100
25
100
SM/TR area
34
100
TSD/ATT area
17
100
FG storage area
15
100
Solvent storage
tank area
41
100
47
100
21
100
Corridor
37
50
MCC room
20
200
56
Night time
12
100
10
100
50
MCC room
17
200
Tank area
20
100
entrance corridor
33
50
filter areas
63
100
Tank area
20
100
entrance corridor
33
50
filter areas
63
100
50
32
100
36
100
Charging area
36
100
31
200
15
200
28
100
30
100
50
Charging area
15
100
22
200
20
200
Corridor
Day time
RH- MF
Night time
stair case
Day time
RH- SF
Night time
57
58
OBSERVATION No. 2
HARMONIC MEASUREMENTS
During the course of detailed energy audit at Asian Paints,
Patancheru Unit, harmonic measurements were carried out in detail.
Harmonics are measured at the transformer and main incomers at the
following locations:
Location
THD-V%
THD-I%
Main incomer
0.9
4.3
Transformer
2.6
6.3
WBU 1
2.2
22.3
WBU 2
2.7
16.8
Resin House 1
2.7
8.5
Resin House 2
2.6
4.2
SBU 1
2.9
10.5
SBU 2
2.9
5.9
IPU 1
16
IPU 2
8.6
Recommendation
In most of the places, harmonic levels are with in the permissible limit of 5%
for voltage harmonics and 15% for current harmonics (as per IEEE standard).
It was observed that % Current THD is higher than the permitted range at
WBU and IPU.
The 5th order current harmonics were observed to be high at WBU and IPU.
Order of harmonics
WBU 1
I1= 187.2 A
WBU 2
I1= 193.5 A
IPU 1
I1= 95.6 A
59
THD
22.3 %
16.8 %
16 %
3rd
0.4 %
3%
0.6 %
5th
22.4 %
18 %
10.2 %
7th
4%
7.7 %
8%
9th
0%
1.8 %
1.1 %
11th
0.4 %
3.1 %
4.2 %
PF
Y-Phase
B-Phase
THD
V%
THD
I%
PF
THD
V%
THD
I%
PF
THD
V%
THD
I%
Main
Cap 0.93
bank
with
reactors
switched off
1.00
2.70
0.95
1.10
3.80
0.93
1.00
3.70
With
0.94
capacitor
panel MCCB
on
1.00
2.30
0.95
1.10
4.20
0.94
1.00
3.20
1.00
2.80
0.99
0.90
3.30
0.99
1.00
3.40
Auto Mode
1.00
2.80
0.99
0.90
3.20
0.99
0.90
3.10
0.99
60
It was observed that there isnt much difference in the harmonic levels with
the reactors switched on or off. These reactors can be shifted to the areas of
concern, to eliminate the 5th and 7th order harmonics.
61
OBSERVATION No. 3
Voltage at
PCC (V)
Voltage at
MCC (V)
Drop (V)
SBU 1
247.50
244.83
2.57
SBU 2
246.30
243.30
3.00
WBU 1
244.13
243.67
0.47
WBU 2
243.30
239.00
4.30
RH 1
244.83
241.00
3.83
RH 2
248.84
244.30
4.54
IPU 1
242.73
241.00
1.73
IPU 2
243.20
242.00
1.20
62
120 m length
20 m underground (open trench)
100 m in air cable tray
The current carrying capacity of the compressor cable is:
Current carrying capacity
381 A
270.51 A
339.09 A
63
OBSERVATION No. 4
RECOVER HEAT FROM RESIN HOUSE CONDENSATE FOR
PREHEATING THE BOILER FEED WATER
During the detailed energy audit at Asian Paints Limited, Patancheru, the
resin house boiler and condensate recovery system was studied in details to
identify any possible energy savings.
The revomax boiler are used to provide steam to the industrial resin reactors
and the condensate from the reactor discharge is been collected in condensate
tank. The Condensate was observed to be at a temperature of above 60 Deg C
at all the time. The condensate at present is not being utilized back to boiler
due to higher TDS levels and is been sent to softening plant.
As the TDS levels of the condensate is very higher cause of intermixing of
cooling water and steam being passed though the same reactor coils it is not
possible to recycle the same condensate though the boiler feed water pump
due to increased chances of scaling in boiler coils.
This condensate at over 60 Deg C can be used for pre heater the boiler feed
water to reduce the boiler fuel consumption. The heat available in condensate
at 60 Deg C can be used for heating up the boiler feed water which is at 30
Deg C.
By preheating the boiler feed water to boiler by 30 Deg C would result in fuel
savings of 0.67 kg of LPG per hour.
Preheating the boiler feed water would increase the feed water vapour
pressure which again can effect the NPSH of the boiler feed water pump. After
installation of heat exchanger for preheating boiler feed water from process
condensate would increase the water temperature to around 45 Deg C. The
vapour pressure of the water at 45 Deg C is 0.15 bar, so at all the time a
positive head of over 0.15 bar has to be maintained for smooth operation of
boiler feed water pump.
The water vapour pressure curve is as below:
64
30 Deg C
Condensate temperature
60 Deg C
0.65 m3/hr
0.65 m3/hr
At least 10 Deg C increase in boiler feed water can be achieved at all the time
Heat savings
6500 kcal/hr
LPG GCV
10700 kcal/kg
Saving in LPG
6500 Kcal/hr___________________
10700 kcal/kg x90% Boiler Efficiency
65
=
Running hours
Annual savings
0.67 kg of LPG
=
3000 Hours/Annum
=
0.67 kg x 3000 hrs/annum x Rs.
60/kg of LPG
=
Rs. 1, 20, 000
Say Rs. 1.20 Lakhs
Payback
66
Chapter V
Management Aspects and Conclusions
67
CHAPTER V
5.1
5.2
Specific Recommendations
Asian Paints Limited, Patancheru should form an energy conservation
committee. The committee should consist of senior operating, electrical
and maintenance personnel.
The committee should meet once in a month with a specific agenda to
review the progress of implementation of proposals and to guide the
implementation team.
Asian Paints Limited, Patancheru should also select a senior person as
energy manager and he should coordinate all the implementation
activities. The main responsibility of implementing the proposals and
achievement of savings should be with the concerned operating and
maintenance personnel and not with the energy manager.
The immediate task of Asian Paints Limited, Patancheru should be to
implement the identified proposals and get the savings.
We would recommend Asian Paints Limited, Patancheru to introduce a
suggestion scheme for energy conservation. The energy conservation
committee should review all suggestions and good proposals should be
implemented. The originator for the good suggestion, which has been
successfully implemented, has to be rewarded.
Confederation of Indian Industry
68
5.3
5.4
Monitoring of Proposals
All the implemented proposals are to be monitored on a proposal-byproposal basis for actual achievement of savings on a monthly basis.
5.5
Motivational Aspects
The successful management of energy depends on motivation of
technical personnel and their commitment. For this reason, Asian Paints
Limited, Patancheru should carry out the following motivational aspects
to sustain energy conservation activities.
Send operating, electrical and maintenance personnel for training
programs in specific areas like:
Pumps
Fans & Blowers
Air Compressors
Refrigeration and Air conditioning
Motors
Organise visits for executives to similar units to know the energy
conservation / process development, etc.
5.6
Conclusions
The Asian Paints Limited, Patancheru and CII Godrej GBC
teams have jointly identified 14 energy saving proposals worth an
annual savings potential of Rs. 98.81 Lakhs. The investment
required for implementation of energy saving proposals is
Rs. 75.0 Lakhs. The total investment will have a simple payback
period of 9 months.
Implementation of identified proposals should be given top priority
and should be done step-by-step.
Confederation of Indian Industry
69
5.7
70
Annexure
71
AnnexureA
SUPPLIER ADDRESS
VFD and other drives
1. Rockwell Automation India Pvt.
Ltd. (Allen-Bradley India Ltd.)
C - 11, Industrial Area
Site - 4, Sahibabad
Ghaziabad - 201 010
Tel: +91 120 2895245, 2895252
Fax: +91 120 2895226
72
2.
3.
6.
5.
73
74
75
LED LAMPS
1. Binay Opto Electronics Pvt Ltd.
44, Armenian Street
Calcutta 700 001
Ph: 033 22103807, 22429082,
22102039
Fax : 033 22421493
Email: binay@vsnl.com
info@binayLED.com
76
2.
SUPERLITE LUMINAIRES
33, Guru Gobindsingh Estate,
Jay Coach, Goregaon (E),
Mumbai - 400 063. INDIA.
Tel : +91-22-26852822
Telefax : +91-22-26853027
Email: info@superliteindia.com
Contact person name
Mr Atul Lotia
Director
3.
4.
77
CAPACITORS
1. Momaya Capacitors
401, Madhav Apartments
Jawahar Road, Opp. Rly. Stn.
Ghatkopar (East)
Mumbai - 400 077
Tel: 022 - 25168281/82,
65754001/02
Fax: 022 - 2516 0758
2. Baron Power
No. 3, Karpagambal Nagar,
Mylapore, Tamil Nadu, India
Ph: +91-44-24356383/84/86,
42131849/50
Fax: +91-44-24356385
3. Meher Capacitors
11th Floor
28 Dr. Gopal Das Towers
Barakhamba Road
New Delhi- 110 001
Tel: + 91 11 23 70 41 43
+ 91 11 23 70 41 44
Fax: + 91 11 23 70 41 46
3. KLG Systel
Plot No. 70A,
Sector - 34, Gurgaon - 122 004
Haryana (India)
Telephone: +91 (0) 124-4129900
Fax: +91 (0) 124-4129999
e-mail : klg.ho@klgsystel.com
78
Flat belts
2. Habasit-Iakoka Pvt. Ltd.
Goldwins
Civil Aerodrome Post
IND-Coimbatore, 641 014
Tel.: +91-(0)422-262 78 79, 262
84 20/21
Fax: +91-(0)422-262 72 14
Email:habasit.iakoka@habasit.com
79
Agitators
1. Fluidyme Technologies
E-2/4, Popular Prestige,
Near Highway Bridge, Warje,
Pune-411058
Maharashtra, INDIA
TeleFax : +91-20-25293397
Mobile : 09422009479
E-mail :fluidyme@sanchaernet.in
fluidyme@yahoo.co.in
2. Pinnacle Equipments
Gat No - 103, Jyotiba Nagar
Talawade Road, Pune
Maharashtra - 412 114
Ph: 020-27690413/27690890 /
32661602
Fax: 020-27690413/32661602
3. Indofab Industries
Street Address: C/3, Hatkesh Udyog
Nagar
City: Thane
Maharashtra 400 606
Ph: + (91)-9820077092
4. Elof Hansson (India) Pvt. Ltd.
Old No 11, New No. 23
2nd Main Road
Raja Annamalai Puram
Chennai - 600 028
India
Ph: +91-44 461 7901/ 7905
Fax: +91-44 461 7907 / 790
80
UPS
APC
# 16, Row House, Goyal Inter City
Behind Drive in cinema, Thaltej Road,
Thaltej
Ahmedabad, Gujarat 380 054
India
Ph: (079) 2684 0124/ 324
APC
# 5, Lake Avenue,
Near Mudiali Bus Stop
Kolkata, West Bengal 700 026
India
Ph: (033)2465 5519, 2463 0064
Thermax Limited
Process Heat Division
Fathima Akhtar Court
3rd Floor, 453, Anna Salai
Thermal Systems (Hyd) Pvt. Ltd.
Plot No.1, Apuroopa Township
IDA, Jeedimetla
Hyderabad - 500 055
Tel: 91-040-23091801-06
Fax(s): 91-040-23097433
info@thermalindia.com
81
Furnace
Thermal Systems
Plot No.150, SIDCO Industrial Estate (NP)
Ambattur, Chennai - 600 098
Tamil Nadu, India
Ph: 044 - 42140877, 26257625, 26255790
Fax: 044 - 42140977
Email: thermalsystems@yahoo.com
thermalsystems@airtelbroadband.in
HOC Dryers
Fax: 91-44-2553-2205
Email: nadiair@vsnl.net
Website: www.nadiindia.com
Insultions
Megha Insulations Pvt Ltd.
A-11/6th Floor, Dada Saheb Flats
Kalanala, Bhavnagar 364001
Ph: 0278-3004523/26
Fax: 0278-3004728
Email: mipl@meghainsulation.com
Contact Person
Mr H V Shah -98252-07723 & 94262-12823
Mrs. Madhu: 98795-46523
2.
Investment
Required
(Rs. Lakhs)
Payback
Period
(Months)
28
31
13
0.9
1.8
24
2.8
13
56
22.3
Sl.
No
0.31
13.45
14.5
13
1.97
19
0.44
0.6
17
3
4
5
6
Person/Depa
rtment
Responsible
Target
Date
Remarks
10
12
11
4.2
1.6
12
3.5
42
13
9.9
14
11.54
98.81
75.0
Total
Backup Calculations
91
Watt
Quantity
Power in
kW
Other Offices
36w x 2
746
53.71
2432
Engg Store
36w x 2
40
2.88
2432
Production Blocks
(floor wise)
36w x 2
849
61.13
4984
BSR
36w x 2
90
6.48
4984
DC
36w x 2
10
0.72
4272
RMG
36w x 2
219
15.77
4984
PMG
72 w
80
5.76
4984
S.No
Location
Total
hours
146.45
Around 146 KW
Proposed
It is recommended to replace these T8 lamps with 1X20 W LEDs.
Power consumption of LEDs
=
2034 Nos X 20 W each
=
40.68 kW
Say 40 kW
Savings
=
146 - 40 kW
Say 106 kW
92
S.No
Location
Watt
W1
Quantity
Nos (Q)
Power
in kW
Annual
Operating
hours (h)
Savings kW
= Q*(W120)
Savings=
kWhXRs
6.7/kWh
Other Offices
36w x 2
746
53.71
2432
38.79
6,32,059.78
Engg Store
36w x 2
40
2.88
2432
2.08
33,892.35
Production
Blocks (floor
wise)
36w x 2
849
61.13
4984
44.15
14,74,292.10
BSR
36w x 2
90
6.48
4984
4.68
1,56,278.30
DC
36w x 2
10
0.72
4272
0.52
14,883.65
RMG
36w x 2
219
15.77
4984
11.39
3,80,343.99
PMG
72 w
80
5.76
4984
4.16
1,38,914.05
2034
146.45
105.77
28,30,664.24
Total
Annual Savings
=
=
2034 X 1500
Rs. 30.51 Lakhs
Payback period
(Investment) X 12 months
(Savings)
=
12.9 Months
Say 13 months
93
=
=
=
108 X 2 X 36 W
7.776 kW
Say 7.78 kW
Proposed
It is recommended to replace these CFL lamps with 1X18 W LEDs.
Power consumption of LED lamps
=
=
108 X 18 W
1.94 kW
Savings in KW
=
7.78 1.94 kW
=
5.84 kW
Say 5.8 kW
=
=
=
=
=
=
Payback period
Investment X 12 Months
Savings
28 months
94
=
=
150 X 70 W
10.5 kW
=
=
150 X 18 W
2.7 kW
A 3 KW solar wind hybrid system can be installed at the plant to tap solar and
wind energy. It is suitable for operation at 2 m/s to 17 m/s of wind speed.
=
=
Rs. 9 Lakhs
Total Investment
Say 13 Lakhs
Savings
95
=
=
Rs 13.0 Lakhs x 12
Rs 2.80 Lakhs
55 months
96
7.5 %
7.5 x 100 %
(20.9 7.5)
55.9 %
3 x 100 %
(20.9 3)
16.7 %
4284 m3/hr
3885.5 Nm3/hr
3885.5 Nm3/hrx(55.9%-16.7%)
1523.5 Nm3/hr
175 Deg C
Ambient temperature
28 Deg C
Heat savings
=
0.31
kcal/Nm3/DegC
Nm3/hr x (175- 28) Deg C
=
69426 Kcal/hr
LPG GCV
10700 kcal/kg
Saving in LPG
69426 Kcal/hr
10700 kcal/kg
6.48 kg of LPG
5500 Hours/Annum
Running hours
1523.5
97
Annual savings
=
6.48 kg x 5500 hrs/annum x Rs.
60/kg of LPG
=
Rs. 21, 38, 400
Say Rs. 21.38 Lakhs
4284 m3/hr
7.68 KW
Option 1:
Combustion
modulation:
air
supply
blower
capacity
controlled
by
damper
55.9 % - 16.7 %
39.2 %
39.2 % x 7.68 KW
3 KW
=
1 KW x 5500 hrs/annum x Rs.
6.7/KWh
=
Rs. 36,850
Thermal savings
Total savings
Payback
=
Option 2:
55.9 % - 16.7 %
39.2 %
39.2 % x 7.68 KW
3 KW
98
As VFD reduces the capacity of the blower by altering the operating speed this
arrangement doesnt calls for any need of damper control operation. Saving of
at least 2.5 KW can be achieved.
Annual savings
=
2.5 KW x 5500 hrs/annum x Rs.
6.7/KWh
=
Thermal savings
Total savings
Investment for online gas analyser with controller for blower frequency
(includes the VFD cost)
Payback
99
6.5 %
6.5 x 100 %
(20.9 6.5)
45.1 %
3 x 100 %
(20.9 3)
16.7 %
520 m3/hr
471 Nm3/hr
133 Nm3/hr
175 Deg C
Ambient temperature
28 Deg C
Heat savings
=
0.31 kcal/Nm3/DegC x 133 Nm3/hr x
(175- 28) Deg C
=
6060 Kcal/hr
LPG GCV
10700 kcal/kg
6060 Kcal/hr
10700 kcal/kg
0.56 kg of LPG
10200 kcal/kg
HSD GCV
100
6060.0 Kcal/hr
10200 kcal/kg
0.59 kg of LPG
Running hours
3000 Hours/Annum
Annual savings
=
0.56 kg x 3000 hrs/annum x Rs.
60/kg of LPG
=
Rs. 1, 00, 800
Say Rs. 1.0 Lakhs
Investment required
NIL
101
: 55 m
Discharge
Power
: 31.8 KW
31.8 KW
10 % x 31.8 KW
3.1 KW
Considering the operation can be only carried out during the night hours when
the ambient temperatures are lower, the above only 1500 hours of the above
4000 hours are taken for savings calculations.
Annual savings
=
3.1 KW x 1500 hrs/annum x
Rs. 6.7/KWh
=
Investment required
NIL
NOTE:
As the pump seal air fan is build in pump main shaft, we recommend to
conduct trails during the night hours when the ambient air temperature are
lower compared to day time. (Caution should be taken in setting the pump
speed control limits to upto maximum reduction to 47.5 Hz)
102
43000 m3/hr *
17.79 KW
0.75 W/CFM
0.25 W/CFM
Saving potential
(0.75 0.25) x 19 KW
9.5 KW
* Actual flow to system for VSP 301 was measured to be 22480 m3/hr. This
reduced flow was mainly due to leakage at immediate blower discharge
ducting. For calculation the specific energy consumption (SEC) the rated flow
was considered for comparing the savings possible. Saving potential can be
even higher then calculated due to non availability of exact discharge flow.
Present Flow of VSP 302
39347 m3/hr
17.79 KW
0.77 W/CFM
0.25 W/CFM
Saving potential
9.25 KW
(9.5 + 9.25) KW
18.75 KW
Annual savings
=
18.75 KW x 7000 hrs/annum x Rs.
6.7/KWh
=
103
Phase II:
Present Flow of VSP 302
69386 m3/hr
28.44 KW
0.70 W/CFM
0.35 W/CFM
9.95 KW
9.95 KW
Annual savings
=
9.95 KW x 7000 hrs/annum x Rs.
6.7/KWh
Saving potential
Investment requirements
Phase I
Two blower of 40000 m3/hr capacity would be Rs. 7.5 Lakhs
Phase II
Single blower of 70000 m3/hr capacity would be 7.0 Lakhs
Total investment
Payback
=
=
=
104
15m3/hr
120 m3/hr
Minimum % of recirculation
=
=
15 m3/hr x 100
120 m3/hr
12.5%
7.7 kW
Annual Saving
=
=
1.50C
40C
=
=
=
=
60%x 7.7kW
4.6 kW
=
=
60% x6.3kW
3.7 kW
=
=
=
4.6kW + 3.7kW
8.3 kW
Say 8 kW
Annual saving
=
=
=
=
=
=
=
=
Rs 1.50 Lakhs
Rs 1.50 Lakhs
Total investment
Rs 3.0 Lakhs
Rs 3.0 Lakhs x 12
Rs 1.97 Lakhs
19 months
106
5kW
20C
40C
=
50% of the flow can be reduced,
Annual saving
=
=
=
Rs 0.60 Lakhs
Rs 0.60 Lakhs x 12
Rs 0.44 Lakhs
17 months
107
5kW
3200 hrs
=
=
=
Investment
Rs 1.0 Lakh
Rs 1.0 Lakh x 12
Rs 1.0 Lakh
12 months
108
6kW
By installing VFD for CT fans, at least 25% of the flow can be reduced
i.e., VFDs will operate at 75% of the speed
As Power (Speed)2,
Annual saving in the fans
=
=
Investment
Rs 0.8 Lakhs
9kW
=
=
=
Rs 0.80 Lakhs
=
=
Rs 4.20 Lakhs
Rs 1.60 Lakhs
Rs 1.60 Lakhs x 12
Rs 4.20 Lakhs
5 months
109
6.15 6.15 x 24 %
70 %
=
4 kW
* 70% new pump efficiency is considered only for savings calculation.
Specifications of 70TR chiller monomer pump:
Flow
25 m3/hr
Head
25 m
Efficiency
> 70%
6.15 kW
Annual savings
4 kW x 3300 hrs/year
/kWh
Rs. 0.8 Lakhs
x Rs. 6.7
110
OF
THE
AIR
Present status
During the detailed energy audit of Asian Paints Limited Patancheru, a detailed
study of all the compressed air units was carried out for possible energy saving
opportunities.
The plant has installed a centralised compressed air system consisting of two
screw compressors which maintain the pressure of the receiver at 5.7 bar. This
centralized compressed air system supplies air to all the sections of the plant
viz. Water Based Unit, Solvent Based Unit, Industrial Paint Unit, Resin Block
and the Monomer block.
Monomer
Tank
P405
587 CFM
5.7 bar
5.6 bar
5.5 bar
Refrigerant
Drier
10m3
Receiver
P406
587 CFM
5.5 bar
Industrial Based Unit
Phase I & II
5.5
bar
Resin
Block
5.4
bar
Compressor
P405
P406
Location
Compressor
House
Compressor
House
Loading
Pressure
bar
Unloading
Pressure
bar
Average
Pressure
bar
Power
kW
5.7
6.2
5.95
88.30
5.5
6.0
5.75
86.03
It was observed that when the plant is in full load operation, one compressor is
continuously running and the second compressor is running for 10 % of the
time. This compressor has been set in such a way that if it is in unload for
more than 10 minutes it automatically switches off. The limit of switching on
and off for a 110 kW motor is times in an hour.
During the detailed energy audit of the plant, a comprehensive compressed air
distribution study was carried out for the compressed air requirement of the
Confederation of Indian Industry
111
end users and the pressure drop at the farthest point in the plant. During the
compressed air user study of the plant, it was observed that the compressed
air pressure drop at the farthest point from the generation was not more than
0.2 bar.
The compressed air pressure being maintained at different applications in the
plant is as follows:
Purpose of Compressed Air
Pressure Maintained
Open/Close valves
4.0 bar
Hopper Aeration
3.0bar
Bag Filters
4.0bar
3.0bar
4.0bar
5.0bar
Cleaning Purpose
3.0bar
It was observed that in most of the end users the pressure setting being
maintained was between 3.0 bar to 4.0 bar. The only operation which requires
a pressure of 5.0 bar is the Lid pressing operation in packer area. The
manufacturer has advised a pressure setting of 6.0 bar considering a safety
margin but the plant is running the packer machine successfully maintaining a
pressure setting of 5.0 bar. It was also observed that these packing machines
were already installed with additional booster compressors, which cater to the
higher pressure compressed air requirements of these machines. CII
congratulates the plant team for this excellent initiative towards
energy conservation activity.
Here is a good opportunity to utilise this booster compressor so that it supplies
high pressure compressed air to the packer machine and reduce the
compressor air pressure at the generation end itself.
Proposed System
The compressed air pressure maintained for most of the applications in the
plant is not more than 4.0 bar. Only the lid pressing operation in the packing
machine requires a higher compressed air pressure requirement of 5.0 bar.
These packer machines are already installed with booster compressors. We can
Confederation of Indian Industry
112
CIISohrabji Godrej Green Business Centre
use these booster compressors in such a way that when we give an input of
4.0 bar compressed air, it gives an output of air at a pressure of 5.0 bar.
Utilizing this booster compressor we will be able to cater to the pressure
requirement of 5.0 bar for the lid pressing machine and at the same time we
will be able to reduce the pressure of the compressed air at the generation end
to less than 4.5 bar average pressure which is sufficient for all the other
compressed air applications.
When we utilize this booster compressor, it increases the amount of
compressed air usage as it increases the pressure of the incoming air and
produces high pressure air. But this increase in compressed air consumption is
not as significant when compared to the savings we will achieve by reducing
the compressed air generation pressure.
Recommendation
Step 1:
Firstly, we recommend to reduce the compressor pressure by 0.2 bar at the
generating point and at the same time adjust the compressed air pressure
setting in the booster compressor of all the packing machines such that
these booster compressors gives an output of 5.0 bar compressed air to the
packer machines.
Run the plant in normal operation for a few days.
Step 2:
If there is no issue with the operation of the plant, keep on reducing the
generation pressure in steps of 0.2 bar until the generating pressure is set
to an average pressure of 4.5 bar and utilizing the booster compressor in
the packing machines so that the required pressure of 5.0 bar is
continuously maintained in the packing machines.
keep on reducing it until the generating set points are:
Load point
- 4.2 bar
Unload point
- 4.7 bar
Calculations
For Compressor P405:
Percentage Pressure reduction
Annual Savings
Annual Savings
Investment
= Nil
114
Area
Leakage (%)
Total Leakage
47
24
12
11
It is difficult to find out the leakages in a continuous process plant. The ideal
time to find out the leakages is during shut down time by conducting a leakage
test.
A simple procedure for conducting leakage test is:
Close all the user end points
Start the compressor and allow it to run
If there are no leakages, the compressor once unloaded should not load
again as there is no consumption at the user point
If there are leakages, it will operate in load and unload mode
Note down the loading and unloading time of the compressor. The
percentage loading indicates the percentage leakage.
Walk along the compressed air lines to identify the leakage points
Arrest the leakage at all the identified points
However, leakage test and arresting leakages is not one time activity. It is a
continuous activity. Leakage may not be avoided but can be brought down to a
very minimum level by continuous efforts.
Recommendations
Confederation of Indian Industry
115
It is recommended to
Avoid unwanted purging of compressed air
Arrest the leakages at identified locations
Avoid the use of High Pressure compressed air for cleaning
Increase the awareness among the operators and the workers on the value
of compressed air
Conduct leakage test during shut down time
Identify & arrest the leakages
Calculations
For Compressor P405:
Leakage Test:
Loading time (LT)
= 83 sec
= 92 sec
% Leakage
Total Savings
=
=
Investment
Nil
116
117