Вы находитесь на странице: 1из 164

Presentation on

Detailed Energy Audit


at
Ultratech Cement Limited, APCW
02nd December 2014
Visit 1
Confederation of Indian Industry

At the outset

Thank You
 Opportunity
 Support
 Hospitality

Confederation of Indian Industry

Objective
 Ultratech Cement Limited, APCW
 Should achieve maximum Energy
savings
 Ultimately achieve the status of
Excellent Energy Efficient Unit

Confederation of Indian Industry

Past EnCon Activities at Ultratech, APCW


 Installation of WHRS from cooler gases
 Installation of VFDs for several process fans
 Installation of VFDs for compressors
 Installation of Light pipe
 Utilization of AFR - Rice Husk

Committed Technical Team


Confederation of Indian Industry

Open Mind and Commitment


 In
spite
of
in-house efforts

successful

 CII invited

Confederation of Indian Industry

Methodology
 Data Collection
 Measurements
 Identification of projects
 Discussion
 Now the Final Presentation..

Confederation of Indian Industry

ROLE OF CII
 Catalyst / Facilitator role
 Supplement in-house activities
 Identify energy saving proposals
 All possible assistance
Monitoring
Vendor identification

Not fault finders !!


Confederation of Indian Industry

Calculation Basis
 Energy Cost

4.23 Rs /kWhr

 Coal Cost
 Kiln

 Kiln Production -

Rs 1000 / MCal
7440 TPD

Confederation of Indian Industry

PROCESS

Confederation of Indian Industry

Raw Mill

Confederation of Indian Industry

Optimize the air volume in Line-1 Raw


mills
 Observations:
 Air flow through mill depends on
 Louvre velocity
 Drying requirement
 Separator requirement
 Air requirement:
 High efficiency separator = 0.6-0.8 kg
matl./kg air
 Conventional separator = 0.4 0.5 kg matl.
/ kg of air
Confederation of Indian Industry

Optimize the air volume in Line-1 Raw


mills
 Observations:
 Present separator loading
 RM 1: 0.389 Kg material/kg air
 RM 2: 0.383 Kg material/kg air
 Fan SEC is observed high i.e.
 RM 1: 7.45 KW/MT Material
 RM 2: 7.60 KW/MT Material

Confederation of Indian Industry

Optimize the air volume in Line-1 Raw


mills
Parameters

Operating detail
Raw Mill 1 Fan

Operating detail
Raw Mill 2 Fan

Volume

761407

772893

Head

707

713

Power

2165

2124

Speed

88 %

87 %

Efficiency

75.66

74.71

Speed control type

SPRS

SPRS

Confederation of Indian Industry

Optimize the air volume in Line-1 Raw


mills
Sl.
No
.
1
2
3

Description

Unit

Plant 1

Plant 2

UTCL,
Tadipatri
RM 1

UTCL,
Tadipatri
RM2

Atox Mill

Atox Mill

Atox Mill

Atox Mill

TPH

325

410

285

285

m3/hr

8, 02, 245

9, 96, 213

7, 61, 407

7, 72, 893

Model
Production
Air volume

Concentratio
n at mill
outlet

g/m3

405

411

374

369

Nozzle
Velocity

m/s

51

51

40

41.8

Confederation of Indian Industry

Optimize the air volume in Line-1 Raw


mills
 Increase material concentration at the
outlet of the mill
 Optimize the raw mill fan volume by taking trial
by reducing the fan speed
 Maintain the present nozzle ring velocity of 42
m/s by blocking some of the nozzle area
 Monitor mill performance, Reject BE load, RABH
fan power & Mill fan power

Confederation of Indian Industry

Optimize the air volume in Line-1 Raw


mills
 Recommendation:
 Increase material concentration at the outlet of
the mill
 Reduce the flow and maintain same nozzle
velocity by reducing the louvre area
 Reduce the flow by 5 % and observe the
operation
 Conduct trail in 1 mill and replicate in other mills
 Savings possible:
 RM 1: 108 KW
 RM 2: 106 KW
Confederation of Indian Industry

Optimize the air volume in Line-1 Raw


mills

Annual Saving

Rs 62.39 Lakhs

Investment

Nil

Confederation of Indian Industry

Replace Raw Mills Fan with High


Efficiency Impeller
Raw Mill 1

-725 mm WC

Raw Mill 2
-15 mm WC

-15 mm WC

-715 mm WC

-728 mm WC

-722 mm WC

Parameters

Operating detail
Raw Mill 1 Fan

Operating detail
Raw Mill 2 Fan

Volume

761407

772893

Head

707

713

Power

2165

2124

Speed

88 %

87 %

Efficiency

75.66

74.71

Speed control type

SPRS

SPRS

Confederation of Indian Industry

Replace Raw Mills Fan with High


Efficiency Impeller
 Observation
Present Raw Mill fan efficiency
 Raw Mill 1- 75.66 %
 Raw Mill 2- 74.71 %

Raw Mills fans generally designed for


over 85 % efficiency

Confederation of Indian Industry

Replace Raw Mills Fan with High


Efficiency Impeller
 Recommendation:
 Replace the existing fan impeller with new
correct size fan head of 85% efficiency

 Saving Potential:
 Raw Mill 1: 164 KW
 Raw Mill 2: 188 KW
 Considering operating efficiency of at least 82 %

Confederation of Indian Industry

Replace Raw Mills Fan with High


Efficiency Impeller
Annual Saving
Investment
Payback

Raw mill 1
Rs 47.3 Lakhs
Rs 35.0 Lakhs
9 Months

Annual Saving
Investment
Payback

Raw mill 2
Rs 55.6 Lakhs
Rs 35.0 Lakhs
8 Months

Confederation of Indian Industry

Reduce Pressure drop across baghouse


outlet to fan inlet in RABH Fan

- 161 mmWC

Pressure drop across


bag house outlet
venturi: 34 mmWC

- 195
mmWC

RABH fan

Confederation of Indian Industry

Reduce Pressure drop across baghouse


outlet to fan inlet in RABH Fan
 Observation
 Pressure drop across bag house outlet to fan
inlet 34 mmWC
 Possible reasons
 Pressure drop across venturi

Confederation of Indian Industry

Reduce Pressure drop across baghouse


outlet to fan inlet in RABH Fan
 Recommendation
 Conduct CFD study for bag house outlet to fan
inlet duct
 Remove the Venturi and implement the
recommended modifications
 Atleast 15 mm WC pressure drop can be
reduced
 Saving potential: 78 kW

Confederation of Indian Industry

Reduce Pressure drop across baghouse


outlet to fan inlet in RABH Fan

Annual Saving

Rs 26.43 Lakhs

Investment

Rs 15.0 Lakhs

Payback

7 Months

Confederation of Indian Industry

Pyro Section

Confederation of Indian Industry

Lower Dispersion Box in riser ducts and


increase heat transfer in Line-1
 PH system heat transfer
 Overall Counter current
 Each Stage Co-current
 Maximum heat transfer in riser ducts
 80% in Ducts
 20% in Cyclones
 Separation of material & air in cyclones
 Very little heat transfer in cyclones

Confederation of Indian Industry

Lower Dispersion Box in riser ducts and


increase heat transfer in Line-1
 Latest approach




Locate feed pipe as low as possible


Increases heat transfer in riser ducts
Lowers PH gas exit temperature

 Discussions with Suppliers & other


Cement Plants



Favour this step (Upto 1 m, easy)


Implemented in several plants

Confederation of Indian Industry

Lower Dispersion Box in riser ducts and


increase heat transfer in Line-1
 Observations:
 Material feed dispersion box heights
 Kiln String cyclone 4 riser = 3 m
 Kiln String cyclone 6riser = 3.2 m

 Good potential to lower the feed point in


above identified cyclones

Confederation of Indian Industry

Lower Dispersion Box in riser ducts and


increase heat transfer in Line-1

Confederation of Indian Industry

Lower Dispersion Box in riser ducts and


increase heat transfer in Line-1
 Recommendations:
 Reduce the dispersion box height by 2
meters
 Results in reduction in preheater exit
temperature by at least 10 Deg C

 Saving possible
 2 kcal/kg clinker

 Monitor temperature and pressure profile


closely
Confederation of Indian Industry

Lower Dispersion Box in riser ducts and


increase heat transfer in Line-1

Annual Saving

48.8 Lakhs

Investment

10.0 Lakhs

Payback

5 Months

Confederation of Indian Industry

Improve heat transfer in Kiln String


Line 1
UTCL, APCW

303 oC

Case Study
Plant

274 oC

465oC

414 oC

575 oC
3

677
4

740oC

522 oC
3

oC

753oC

632 oC

820oC

792oC

820oC

811oC

Kiln Inlet
- 1200

Kiln Inlet
- 1200
Confederation of Indian Industry

Improve heat transfer in Kiln String


Line 1
 Observations:
 Heat transfer rate is low from 6th outlet to
5th cyclone outlet & 5th outlet to 4th outlet
 Possible reasons
 Improper material distribution
 Worn out immersion tube

Confederation of Indian Industry

Improve heat transfer in Kiln String


Line 1
 Recommendations:
 Check the dip tube,
dispersion box and riser duct
in cyclone 5
 Conduct CFD study for 6th
stage outlet to 5th stage &
5th stage outlet to 4th stage
stage to analyse the reasons
for lower heat transfer
 Exit temperatures can be
reduced by at least 15 Deg C
 Saving potential: 3 Kcal/kg
Clinker
Confederation of Indian Industry

Improve heat transfer in Kiln String


Line 1

Annual Saving

Rs 73 Lakhs

Investment

Rs 25 Lakhs

Payback

4 Months

Confederation of Indian Industry

Reduce suction side pressure drop in


cooler fans Line 1

255 mm WC

-105 mm WC

Operating

Cooler Fan 10

Power: 157 kW
Flow: 119595 m3/hr
Head: 360 mm WC
Temp.: 26oC

Confederation of Indian Industry

Reduce Suction Loss in Cooler fans


Suction
Cooler
fan No.

pressure

Suction Fan head Operating


Saving
Loss
power
potential

mm WC

mm WC

kW

kW

1R

-70

4.76

841

88

4.18

2L

-61

3.94

787

86

3.39

3L

-65

4.22

830

68

2.87

3R

-64

5.47

622

61

3.33

-108

13.15

593

141

18.41

-105

16.67

450

101

23.5

-73

7.77

553

106

8.24

10

-105

20.83

360

157

32.7

Confederation of Indian Industry

Reduce suction side pressure drop in


cooler fans Line 1

Radius of bell mouth


- 0.25 x effective diameter
Flow measurements using aerofoil
Confederation of Indian Industry

Reduce suction side pressure drop in


cooler fans Line 1
 Recommendation:
 Widen the bell mouth opening
 Ensure suction pressure should not be more
than 30 mm WC
 Total saving potential: 96 KW
 Recalibrate the flow after modifying the fan
inlet

Confederation of Indian Industry

Reduce suction side pressure drop in


cooler fans Line 1

Annual Saving

Rs 32.45 Lakhs

Investment

Rs 8.00 Lakhs

Payback

3 Months

Confederation of Indian Industry

Reduce pressure drop in preheater


downcomer duct Line 1
C STRING

K STRING

-600 mm WC

- 650 mm WC
-630 mmWc

- 700mm WC

1B

Gas velocity:

Gas velocity:

20.9 m/s

20.3 m/s
-650 mmWc

-730 mmWc

-690 mmWc

- 730 mmWc

-690 mmWc

- 735 mmWc
- 25 mmWc

Total Pressure drop


80 mmWC

1A

- 25 mmWc

Total Pressure drop


90 mmWC
Confederation of Indian Industry

Reduce pressure drop in preheater


downcomer duct Line 1
 Observations:
 High pressure drop in Preheater downcomer
duct
 Calciner string: 90 mm WC
 Kiln string: 85 mm WC

 Pressure drop from cyclone outlet to first bend


before horizontal duct
 Kiln string: 50 mm WC
 Calciner string: 30 mm WC

Confederation of Indian Industry

Reduce pressure drop in preheater


downcomer duct Line 1
 Observations:
 Possible reasons for high pressure drop across
Kiln down comer
 Improper flow distribution
 High gas velocity in low diameter duct before
straight vertical down comer duct

 Possible reasons for high pressure drop across


Calciner down comer
 Pressure drop in bend from cyclone outlet to vertical
down comer

Confederation of Indian Industry

Reduce pressure drop in preheater


downcomer duct Line 1
 Recommendation:
 Conduct CFD study for kiln and calciner string
down comer ducts
 Best observed down comer pressure drop: 35
mmWC with 15 m/s down comer velocity
 At least 20 mm WC pressure drop can be
reduced in both strings
 Saving potential:
 Kiln string: 38 KW
 Calciner string: 54 KW

Confederation of Indian Industry

Reduce pressure drop in PH


down comer duct

Confederation of Indian Industry

Reduce pressure drop in preheater


downcomer duct Line 1
Kiln String:
Annual Saving

12.7 Lakhs

Investment

10.0 Lakhs

Payback

10 Months

Calciner String:
Annual Saving

18.1 Lakhs

Investment

10.0 Lakhs

Payback

7 Months

Confederation of Indian Industry

Replace Line 1 Kiln String & Calciner String


fans with high efficiency impeller
-705 mmWC

-670 mmWC

-710 mmWC
-670 mmWC

K String Fan

-25 mmWC

-25 mmWC

C String Fan

Parameters

Operating detail
K String

Operating detail
C String

Volume

463154

664821

Pressure

685

645

Power

1301

1771

70.65

70.15

Speed
Efficiency
Speed control type

Confederation
of Indian Industry
SPRS

SPRS

Replace Line 1 Kiln String & Calciner String


fans with high efficiency impeller
 Observations:
 Present preheater fan efficiency
 Kiln String- 70.6 %
 Calciner String- 70.1 %
 Preheater fans generally designed for over 85
% efficiency

Confederation of Indian Industry

Replace Line 1 Kiln String & Calciner String


fans with high efficiency impeller
 Recommendation:
 Replace the existing fan impeller with new
correct size fan head of 85% efficiency

 Saving Potential:
 K String: 180 KW
 C String: 256 KW
 Considering operating efficiency of at least 82 %

Confederation of Indian Industry

Replace Line 1 Kiln String & Calciner String


fans with high efficiency impeller

Annual Saving
Investment
Payback

K String
-

Rs 60.8 Lakhs
Rs 50.0 Lakhs
10 Months

Annual Saving
Investment
Payback

C String
-

Rs 54.85 Lakhs
Rs 70.0 Lakhs
16 Months

Confederation of Indian Industry

Coal Mill

Confederation of Indian Industry

Avoid damper loss across coal mill vent


fan

25 mm WC
100 % Open

-870 mm WC

-914 mm WC

Operating
Power: 725.5 kW
Flow: 231238 m3/hr
Head: 939 mm WC
Speed: 97 %

Confederation of Indian Industry

Avoid damper loss across coal mill vent


fan
Observation:
Fan operating with SPRS for speed control
Pressure drop across damper is found to
be 44 mmwc
This pressure drop is equal to 4.69% of
the head developed by the fan

Confederation of Indian Industry

Avoid damper loss across coal mill vent


fan
Recommendation
Inspect the louvers in next immediate
opportunity
Open the Damper fully
At least 20 mm WC pressure drop can be
reduced
Reduce the fan speed
Saving potential : 15 KW

Confederation of Indian Industry

Avoid damper loss across coal mill vent


fan

Annual Saving

Rs 4.57 Lakhs

Investment

NIL

Confederation of Indian Industry

Cement Mill

Confederation of Indian Industry

Avoid damper loss across mill vent fan


Cement Mill 1

3 mm WC
35 % Open

-340 mm WC

- 525 mm WC

Operating
Power: 61.26 kW
Flow: 23155 m3/hr
Head: 528 mm WC
Temp.: 90oC

Confederation of Indian Industry

Avoid damper loss across mill vent fan


Cement Mill 1
 Observation
 Fan is presently operating with damper control
 Damper opening is 35 % during normal
operation
 Pressure loss across damper is found to be 185
mmwg
 This pressure drop is equal to 35 % of the total
head developed by the fan

Confederation of Indian Industry

Avoid damper loss across mill vent fan


Cement Mill 1
 Recommendation
 Install VFD for mill vent fan
 Remove the Damper
 Convert existing pulley driven to direct couple
 Maintain same ventilation by reducing fan
speed
 Saving potential : 21 KW
 Similar opportunity available in CM 2

Confederation of Indian Industry

Avoid damper loss across mill vent fan


Cement Mill 1

Annual Saving

Rs 6.1 Lakhs

Investment

Rs 6.6 Lakhs

Payback

13 Months

Confederation of Indian Industry

Avoid Damper Loss Across Line 2 Cooler


Hot Gas Booster Fan

+ 27 mm WC

-39 mm WC

-80 mm WC

Operating
Power: 160 kW
Flow: 327300 m3/hr
Head: 107 mm WC
Temp.: 195oC
Confederation of Indian Industry

Avoid Damper Loss Across Line 2 Cooler


Hot Gas Booster Fan
Observation:
 Fan utilized for moving hot cooler exit gases to
Line 2 cement mills
 VFD installed for varying operating conditions
 Presently operating with fan inlet damper 100 %
open
 Pressure drop across damper is found to be 41
mmwc
 This pressure drop corresponds to 36 % of the
head developed by the fan

Confederation of Indian Industry

Avoid Damper Loss Across Line 2 Cooler


Hot Gas Booster Fan
Recommendation
 Remove the Damper
 Control the hot gases flow by VFD only
 Saving potential : 58 KW
 Much higher savings possible during
transferring hot gases from Line 2 to Line 1
WHRS systems

Confederation of Indian Industry

Avoid Damper Loss Across Line 2


Cooler Hot Gas Booster Fan

Annual Saving

Rs 19.5 Lakhs

Investment

NIL

Confederation of Indian Industry

Optimise suction in Raw Mill silo top bag


filter fans
Raw Mill Silo top bag filter fan
-4 mm WC

- 140 mm WC

- 159 mm WC
- -161 mm WC

Raw
Mill
Silo
Confederation of Indian Industry

Optimise suction in Raw Mill silo top bag


filter fans
 Observation
 Raw Mill silo ventilation
 To exhaust feeding & Extraction air qty
 To avoid condensation inside silo
 Observed high suction pressure of -140 mm WC
indicating higher capacity of bag filter fan

Confederation of Indian Industry

Optimise suction in Raw Mill silo top bag


filter fans
Bag Filer

Raw Mill Silo

Present
Suction
pressure

Norm for
silo
suction
pressure

Fan
Head

Fan
Power

Saving
potential

Mm WC

Mm WC

mm WC

KW

KW

-140

-50

157

23

13

Confederation of Indian Industry

Optimise suction in Raw Mill silo top bag


filter fans
 Recommendation:
 Install VFD
 Interlock the fan speed with silo suction
pressure
 Target silo suction pressure at 50 mm WC
 Saving potential: 13 KW

Confederation of Indian Industry

Optimise suction in Cement silo top bag


filter fans

Annual Saving
Investment
Payback

Rs 4.64 Lakhs
Rs 1.50 Lakhs
4 Months

Confederation of Indian Industry

Observation 1

Reduce suction pressure at Raw


Mill Inlet
P=- 715 mmWC
To bag house
inlet

P=- 610 mmWC

VRM fan

cyc
P=- 58 mmWC

P=- 70 mmWC

P=- 60
mmWC

P=-60 mmWC

P=- 25
mmWC

PH fan

Reduce suction pressure at Raw


Mill Inlet
 Observations:
 Higher suction pressure was observed at mill
inlet
 RM 1: -74 mm WC
 RM 2: - 77 mm WC

 Suction pressure after junction box to mill inlet


duct: - 60 mm WC
 Higher suction pressure leads to increase head
developed by mill fan
 Possible reasons:
 Higher resistance in recirculation duct leading to
higher mill inlet pressure

Observation 2

Reduce Excess air in Kiln Line 1


6.8 % O2
1

4
5

5.7 % O2
6

Kiln Riser
4.8 % O2
Confederation of Indian Industry

Reduce Excess air in Kiln Line 1


 Observations:
 Measured Kiln inlet O2: 4.8 %
 CCR Kiln inlet O2: 3 3.5 %
 Excess air is also indicated by high NOx at kiln
inlet
 Total excess air to Kiln: 16 - 20 %
 Present Kiln String flow: 0.62 Nm3/kg Clinker
 Excess air to Kiln: 0.10 Nm3/kg Clinker

Confederation of Indian Industry

Electrical

Confederation of Indian Industry

Activities Carried Out - Electrical


 Electrical measurements of all motors
above 11 kW of phase-1, Packing Plant and
CPP ( 1 unit) have been carried out
 Analysis conducted during Audit are
 Motor loading analysis for all motors
 Harmonics measurements in transformers and
other major feeders
 Lighting Measurements :in Phase-1

 More than 150 measurements carried out


Confederation of Indian Industry

Improve Loading of Packing Plant Belt


Conveyors
 Detailed power measurements carried
out for motors above 11 kW
 15 motors are under loaded in packing
plant
 Under loaded motors
 Higher voltage related losses
 Lower power factor
 Lower operating efficiency

Confederation of Indian Industry

Optimize Capacity of Motors in Packing


plant
Running
Power
(kW)

Power
factor

Rated
Power
(kW)

%
Loading

P2U01

2.82

0.24

11

22.8

P2U09

3.92

0.43

15

23.3

P2U02

2.2

0.24

11

17.8

P2U19

0.71

0.38

15

4.2

P2U07

2.49

0.22

22

10.1

P2U13

2.61

0.24

22

10.6

3.3

0.35

22

13.4

2.57

0.26

11

20.8

P2U14
P2U03

Confederation of Indian Industry

Optimize Capacity of Motors


Actual
Power
(kW)

Power
factor

Rated
Power
(kW)

%
Loading

P2U12

2.34

0.32

15

13.9

P2U04

1.32

0.65

11

10.7

P2U17

2.73

0.22

22

11.0

P2U18

3.72

0.41

22

15.0

P2U10

3.29

0.47

22

13.3

P2U06

2.47

0.41

11

20.0

P2U11

2.85

0.46

15

16.9

Tag No

Confederation of Indian Industry

Optimize Capacity of Motors


 OPTION 1: Recommended to convert
delta connection to star connection
L1
IL = 3 Ip

VL
VP =
3

L1

Delta connection

VL

VL =
VP
L2

L2

L3

L3
Star connection

Confederation of Indian Industry

Optimize Capacity of Motors


 Effect on motor performance operating
in star mode
 Reduction in voltage related Iron

losses

 Reduction in copper losses


 Operates with improved P.F
 Motor operating efficiency improves

Option 2:- Recommended to replace the


identified motors with next size spare
motors
Confederation of Indian Industry

Optimize Capacity of Motors


 Saving potential : 6%

Annual Saving

Rs 0.49 Lakhs

Investment

Nil

Confederation of Indian Industry

Optimize Lighting Voltage


 Detailed lighting measurements carried out
during detailed energy audit
 Plant team has installed energy savers in
majority of areas
 Excellent Initiative by Plant Team
 Voltage is high in few areas

Confederation of Indian Industry

Optimize Lighting Voltage


Sl.N
o
LOCATION
1

MRSS
Cement
mill
Cooler &
gypsum
yard
Rawmill &
Coal mill

Operating
Voltage
(V)

Operating
Power
(kW)

Recommended
Voltage
(V)

225

9.57

210

222

90.37

210

212

32.13

210

207

111.15

210

Confederation of Indian Industry

Optimize Lighting Voltage


 Optimum Voltage for lamps is 210
 Higher Voltage results
 Higher Power consumption
 Increased failure rate of lamps

 10% reduction in Voltage


 10% reduction in Power consumption

Confederation of Indian Industry

Optimize Lighting Voltage


 Recommendation
 Reduce the tap setting of energy
saver in MRSS and Cement mill to
210V
Annual Saving

Rs 1.02 Lakhs

Investment

Nil

Confederation of Indian Industry

Harmonics Measurements
 Harmonics are produced due to non
linear equipment
 Variable frequency drives
 DC drives
 UPS, Computers, etc

 Harmonics are measured at


 All transformers and major vfd feeders and
cooler fans

Confederation of Indian Industry

Harmonic Distortion - IEEE Norm


Harmonic Voltage Distortion limits at any point on the system

Total
Supply System
Voltage (kV) at
Harmonic
Voltage
point of common
coupling
Distortion VT
(%)
0.415
6.6 and 11
33 and 66
132

Individual
Harmonic
Voltage
Distortion (%)

5
4
3
1.5

Odd
4
3
2
1

IEEE G.5/3 Sept. 1976 : Limits for Harmonics.

Confederation of Indian Industry

Even
2
1.75
1
0.5

Harmonics Measurements in Plant


TAG NAME

% V-THD

% I-THD

Cooler fan 1L

8.0

31.0

Cooler fan 1R

8.1

30.4

Cooler fan 2L

8.3

32.1

Cooler fan 2R

8.2

31.1

Cooler fan 3L

8.1

58.3

Cooler fan 3R

7.9

34.9

7.2

61.9

7.6

36.8

Cooler fan 5

8.1

32.6

Cooler fan 6

7.1

29.3

Cooler fan 4L
Cooler fan 4R

Confederation of Indian Industry

Harmonics Measurements

TAG NAME

% V-THD

% I-THD

Cooler fan 7

7.6

34.9

Cooler fan 8

7.5

40.5

Cooler fan 10

7.4

38.8

Incomer 1

2.3

9.6

Incomer 2

2.4

14.1

Incomer 3

7.8

24.8

Confederation of Indian Industry

Install Harmonic Filters for cooling fans


 Harmonics leads to
 Reduction in life of power equipment
 Degraded efficiency and performance

 Harmonic distorted current are prevented


from flowing back into power system by
diverting them through low impedance
shunt path called HARMONIC FILTER

Confederation of Indian Industry

Install Harmonic Filters in Cooler Fans


 Recommended to
 Recommended to install Filter in incomer-3
 Anticipated Savings-3 %

Annual Saving

Rs 12.32 Lakhs

Investment

Rs 25.00 Lakhs

Simple pay back -

25 Months

Confederation of Indian Industry

Improve Transformer Loading in Raw Mill


section
Raw Mill & stacker reclaimer Load is
supplied from 3 transformers
 T-5,T-6 & T-7

Transformers
are
independent mode

operating

in

During detailed energy audit the loading


of all transformers was studied.
The transformers in above area were
partially loaded
Confederation of Indian Industry

Improve Transformer Loading in


Raw Mill section

Rated
(KVA)

Load
(kW)

Actual
(KVA)

%
Loading

T5

2000

399.72

524.13

26.2

T7

2000

251.16

342.9

17.14

T6

2000

92.00

125.00

6.25

Transformer
No.

Confederation of Indian Industry

Improve Transformer Loading in Raw


Mill section
6.6kV
Rated 2 MVA
Actual 524 KVA
26% Load

T-5

Rated 2 MVA
Actual 125 KVA
7% Load

T-6

0.433kV
Confederation of Indian Industry

Existing system

Rated 2 MVA
Actual 343 KVA
17% Load

T-7

Improve Transformer Loading in Raw


Mill section
 Losses due to the operation of two
transformers T5 & T6
 7.44 kW

 Isolate one of the transformer from


operation
 Total losses= 5.05 kW

 Saving potential = 2.4 kW

Confederation of Indian Industry

Improve Transformer Loading in Raw


Mill section
6.6kV
Rated 2 MVA
Actual 649 KVA
32.5% Load

T-5

Rated 2 MVA
Actual 0 KVA
0Load

T-6

0.433kV
Confederation of Indian Industry

Proposed system

Rated 2 MVA
Actual 343 KVA
17% Load

T-7

Improve Transformer Loading in


Raw Mill section
Isolate transformer-6 and shift the load
on T-5
This will avoid the losses in transformer
T6 and improve loading of T-5
Keep transformer T-5 as stand by

Confederation of Indian Industry

Improve Transformer Loading in Raw


Mill section

 Annual Savings

Rs 0.81 Lakhs

 Investment

Nil

Confederation of Indian Industry

Replace 150W MV lamps with 70W


MH/HPSV lamps
150 W MV lamps are installed in packing
plant
50 Nos
Mercury vapor lamps are inefficient and
poor efficacy
 Luminous efficacy- 50 Lm/W

These lamps can be replaced with 70W


Metal Halide / HPSV lamps
 Luminous efficacy- 105 Lm/W - HPSV
 Luminous efficacy- 80 Lm/W- MH lamp
Confederation of Indian Industry

Replace 150W MV lamps with 70W


MH/HPSV lamps

Annual Savings

Rs. 0.75 Lakhs

Investment

Rs. 1.25 Lakhs

Simple Payback period -

20 months

Confederation of Indian Industry

Install Energy Efficient Fluorescent


Lamps in Packing Plant
 Majority of the lamps in the plant
 36W/40W conventional fluorescent lamps with
Electronic ballasts
 Few Lamps are operating with Copper Ballast

 Copper ballasts consumes 14-15W


 Power consumption of each lamp-50W

 There are about 50 lamps


 Latest trend is to use T5 lamps
 Consumes 28W
Confederation of Indian Industry

Install Energy Efficient Fluorescent


Lamps in Packing Plant
 Comparison

Conventional
FTL

T5 lamps

Power
consumption

50W (36+14W)

28W

Life

20000 hrs

25000hrs

Luminous
efficacy

68lm/W

104lm/w

Confederation of Indian Industry

Install Energy Efficient Fluorescent


Lamps in Packing Plant

Annual Saving

Rs 0.34 Lakhs

Investment

Rs 0.25 Lakhs

Simple Pay back -

9 months

Confederation of Indian Industry

Compressed Air System

Confederation of Indian Industry

Approach for Energy Saving in


Compressors

1. Generation

 Generating at optimum pressure


 Use of energy efficient compressors
 Lower specific power consumption
(kW/CFM)

2. Consumption
 Optimum usage of compressed air
at optimum pressure
 Segregating HP & LP users
Confederation of Indian Industry

Approach for Energy Saving in


Compressors
3. Distribution
 Reducing the loss in the distribution
system
 Arresting leakages
 Avoiding unwanted use of
compressed air

Confederation of Indian Industry

Approach for Energy Saving in


Compressors
 Approach
 System studied
 Operating parameters - observed
 Measurements done
 Specific observations made

Confederation of Indian Industry

Installed Capacity
 Total Installed HP Compressors
capacity in Line-1:9 No's
 230 m3/min or 8144 CFM
 Users: Poking, Inter coal transport,
WHR and other plant operations

 Total Installed HP Compressor


capacity in Line-2: 4 No's
 106 m3/min or 3745 CFM

Confederation of Indian Industry

Best Practice's Implemented by


UTCL team
 Installation of SX Controller in
Line-1
 Installation of VFD in Line-2 and
Cement Mill compressors
 Isolation of dryers for Poking Line
 Installation of Timers and Level
Based systems for Auto draining
moisture
Confederation of Indian Industry

Capacity Test
 The
performance
of
the
compressors analyzed
 Free Air Delivered is evaluated by
conducting the capacity test
 FAD= P2- P1 x Vr
PO x T

Confederation of Indian Industry

FAD Test
Area

Rated
Actual
Actual
Avg
capacity capacity capacity pressure
(m3/min) (m3/min)
CFM
(bar)

Actual
Actual
Norm
power
SEC
(kW) (kW/CFM) (kW/CFM)

Line-1
Compressor-1

25.0

25.00

883.3

6.15

154

0.17

0.16

Compressor-2

23.5

23.50

830.3

6.15

142

0.17

0.16

Compressor-3

27.5

24.41

862.4

6.15

142

0.16

0.16

Compressor-4

27.5

23.40

826.7

6.15

142

0.17

0.16

Compressor-6

27.5

21.99

776.9

6.15

142

0.18

0.16

Compressor-7

25.0

22.80

805.5

5.75

144

0.18

0.15

Compressor-9

23.5

22.31

788.2

6.05

132

0.17

0.16

Line-2
Compressor-1

25

25.00

883.3

5.65

155.1

0.18

0.15

Compressor-2

25

24.84

877.6

6.25

150.2

0.17

0.16

Confederation of Indian Industry

Improve SEC of Identified


Compressors in Plant
 Higher SEC might be due to
 Wear out of the internals
 Increase in the tolerances
 Ageing of the compressor

 The volumetric efficiency of the


compressor can be improved by
 Complete overhauling of the
compressor

Confederation of Indian Industry

Improve SEC of Identified


Compressors in Plant
 Recommendation
 Carry out complete overhauling for
the compressors
 Repeat FAD test after the
overhauling
Annual Saving

Rs 11.43 Lakhs

Investment

Nil

Confederation of Indian Industry

Reduce Fly Ash Unloading System


Pressure
 Fly ash unloading is done through two
Screw compressors
 G2 CP1- 5.4 bar @ 133 kW
 G2 CP2- 5.8 bar @ 143 kW

 Higher pressure generation leads to higher


power consumption
 Power

Pressure

 Maximum system pressure required during


tanker unloading (from tanker to hopper) is
2.0bar
 Many plants are using 2 bar for dry fly ash
unloading application
Confederation of Indian Industry

Reduce Fly Ash Unloading System


Pressure
 It is suggested to
 Install
Low
Pressure
compressor
(2.5 bar)
 Maintain pressure at 2.0 bar
 Plant team has already planned for this
project and it may get completed by next
February

 Immediate step can be Reduction of


pressure setting at least possible
 Load Pressure
 Unload Pressure

- 4.5 bar
- 5.2 bar

Confederation of Indian Industry

Reduce Fly Ash Unloading


System Pressure

Annual Saving

Rs 21.13 Lakhs

Investment

Rs 30.00 Lakhs

Simple Pay back -

17 months

Confederation of Indian Industry

Avoid Compressed air leakage in the


plant
 Leakage test was carried out in
 Line-2
 Leakage is coming around 30%

 The leakages are observed in following


sections





Coal Mill
Cooler
Preheater
Raw Mill

Confederation of Indian Industry

Identified Leakage points: Line-2


1. In Raw Mill Cylinder Valve By passed near
363 MW2 reject Bucket Elevator
2. Preheater 8th Floor Oil filter for Lubrication
Cylinder near 431 PG7
3. Preheater 7th Floor Poking Header dummy
leakage
4. Preheater 6th Floor Poking Header dummy
leakage
5. Preheater 1st Floor Oil Filter leakage near
PH APDB2F6
Confederation of Indian Industry

Identified Leakage points: Line-2


6. Pyroclone -2 dryer hose leakage in Coal
mill First Floor
7. Compressed Air Pipe Line Leakage near
L61FN2 in coal mill
8. Coal Mill JPF Cylinder Air Line Gate valve
by passed near L9SC11
9. L91FN2 Bag Filter Solenoid Valve
Leakage
10. Cylinder valve by pass near L21BF1

Confederation of Indian Industry

Identified Leakage points: Line-2


11.Burner Platform Air Blaster Junction
Box Union Leakage
12.Valve Leakage near 461 FN7 fan
13.Cooler Hopper ground floor near
471FN4

Confederation of Indian Industry

Identified Leakage points: Line-1


14.Preheater 8th floor hose damaged
( large hole)
15.Preheater 3rd Floor near Air Blaster
valve leakage
16.Solenoid valve air leakage near 48 no
air blaster
17.Calciner Air blaster line leakage near
swivel gate
18.Blaster 34 air line
Confederation of Indian Industry

Identified Leakage points: Line-1


19.Blaster 28 air line
20.Cooler area tertiary duct hose
leakages
21.Blower line pipe leakage near kiln
22.Coal Mill bag house leakage on stack
side
23.Solenoid valves leakage in coal mill
bag house
Confederation of Indian Industry

Identified Leakage points: Line-1


24.Coal Mill Bag filter near K203 hose
leakage
25.Bag house top J1C06 hose leakage
26.J1C06RA
27.J1C15RA two ball valves leakage
28.J1C12Ra cylinder piston

Confederation of Indian Industry

Identified Leakage points: Line-1


29.J1C01A near oil filter
30.J1C08A cylinder
31.Hopper area near additive feeder
valve joint leakage
32.Compressor House Air drier-4 pipe
line leakage
33.Air drier-3 hose leak

Confederation of Indian Industry

Avoid Compressed air leakage in the


plant
 Recommendation
 Implement red tag system
 Arrest all the identified leakage
areas
 Conduct leakage test regularly &
monitor the improvement
 Maintain compressed air leakage
less than 10% in the plant
 Saving potential : 15 kW
Considered only 10% of total power
consumption
Confederation of Indian Industry

Avoid Compressed air leakage in the


plant

Annual Saving

Rs 5.08 Lakhs

Investment

Nil

Confederation of Indian Industry

Improve Operation Of Poking


Compressor
 Presently Compressor-7 is used
for Poking operation
 Compressor is rated for 25m3/min
and rated for 160 kW
 Compressor loading details
 Loaded for 85% past history
 Loaded for 72% during Audit

 Present and past history shows


the capacity is in excess
Confederation of Indian Industry

Improve Operation Of Poking


Compressor
 Trial can be taken with stand by
compressor 23.5 m3/min
 It improves utilization factor and
reduces unloading time
Annual Saving

Rs 1.93 Lakhs

Investment

Nil

Confederation of Indian Industry

Reduce Generating Pressure of


Compressors
 Total
Plant
is
operating
6.1- 6.3 bar pressure in Phase-1

with

 Measured Pressure in various areas


 Poking Line

- 5.75 bar

 WHR

- 6.0-6.1 bar

 Cooler

- 6.0 bar

 Coal Mill

- 6.0 bar

 Higher operating Pressure results in


higher power consumption
Confederation of Indian Industry

Reduce Generating Pressure of


Compressors
 Compressor operating power is directly
proportional to operating pressure
 Compressed air applications & pressure
requirements
 Bag filter

- 5.0 bar

 Instrument Air

- 5.5- 5.8 bar

 Air Blaster

- 5.5 bar

 FK pump seal air - 4.5 bar


 Bag house

- 4.5-4.8 bar
Confederation of Indian Industry

Reduce Generating Pressure of


Compressors
 Many plants has optimized
generating pressure at 5.5 bar

the

 Pressure drop across the compressed


air lines is negligible
 Pressure at the user end is almost same as
generating

Confederation of Indian Industry

Reduce Generating Pressure of


Compressors
 Good potential to optimize the generating
pressure of the compressors
 Raw Mill Bag House
 Coal Mill & Waste Heat Recovery
 Jet Pulse Bag Filters

 Recommended to
 Reduce the pressure setting of the compressors
in steps of 0.1 bar
 After rectifying SX controller
 Option of Segregating Low Pressure users also
can be tried
Confederation of Indian Industry

Reduce Generating Pressure of


Compressors
 Option of Segregating Low Pressure users
also can be tried
 Investment considered for any modification in
line
Annual Saving

Rs 7.32 Lakhs

Investment

Rs 5.00 Lakhs

Simple Pay back -

8 months

Confederation of Indian Industry

Reduce Pressure drop in Raw Mill


Bag House circuit
 Detailed study of Compressed air
distribution system is studied during
audit
 Measured pressures
 Generation Pressure -

6.1 bar

 Bag house receiver -

5.4 bar

 Bag house top

5.0 bar

 We recommend to verify pressure


settings with new gauge in shut down
Confederation of Indian Industry

Reduce Pressure drop in Raw Mill Bag


House circuit
CP1

5.0 bar

Bag House

CP2
5.4 bar
6.1 bar

CP5
Receiver

CP9

Stand by/ Auto mode Confederation of Indian Industry

All users

Reduce Pressure drop in Raw Mill


Bag House circuit
 Minimize pressure drop in compressed
air line
 Operate compressed air line at
optimum pressure settings
Annual Saving

Rs 0.74 Lakhs

Investment

Nil

Confederation of Indian Industry

CAPTIVE POWER PLANT

Confederation of Indian Industry

Install New efficient pump for CEP in


Units 1 & 2
CEP 1 Running
100 % close

Deaerator

5 kg/cm2

CRT

LPH
105 m3/hr
CEP - 1

8.9
kg/cm2

Ejector
Operating
Parameters CEP 1
105 m3/hr
9.0 bar,

CEP 2

67 kW
Confederation of Indian Industry

Install New efficient pump for CEP in


Units 1 & 2
CEP 2 Running
100 % close

Deaerator

5 kg/cm2

CRT

LPH
104 m3/hr
CEP - 1

CEP 2

9.0
kg/cm2

Ejector
Design Parameters
CEP

Operating
Parameters CEP 1

104 m3/hr

104 m3/hr

14 bar

8.9 bar,
68 kW

Confederation of Indian Industry

Install New efficient pump for CEP in


Units 1 & 2
 Condensate extraction pump is pumping the water
to deaerator
 One pump is running continuously
 CEP-1 with VFD and CEP -2 without VFD
 CEP Speed interlocked with Discharge Pressure 9 kg/cm2
 CII congratulates plant team for excellent step
Unit
No.

Pump

Flow

Head
m

Power

Efficienc
y

CEP

105

91

67.7

41

CEP

104

93

60.2

46

Confederation of Indian Industry

Install New efficient pump for CEP in


Units 1 & 2
 Recommendation
 Install new Efficient pumps for CEP with
VFD
 125 m3/hr, 120m, 75 % efficiency
Annual Saving
Investment
Pay back period

Rs 10 Lakhs
Rs 10 Lakhs
12 months

Confederation of Indian Industry

Observation: Potential in BFP in Unit 1 & 2


Unit -1 & 2
4.5 kg/cm2

105 kg/cm2

Deaerator

DRUM
1&2

Economizers
Flow
control
valve

ARC valve

HPHs
Common
Header

126 kg/cm2
220
m3/hr
BFP -

Operating
Parameters
Flow > 220 m3/hr
BFP -3

Head - 120 kg/cm2


Power = 667, 691
kW

Confederation of Indian Industry

Feed water pump is catering for the boiler water


requirement
 2 feed water pumps is operation
 BFP discharge pressure
: 126 kg/cm2
 Drum pressure
: 105 kg/cm2
 Possibility of Inefficiency in pump should be studied
further
Valve control is an inefficient way of controlling the flow
 Part of energy lost across the valve as the pressure drop
 Pressure Drop across the valve can be reduced by varying
speed to maintain required discharge pressure


Confederation of Indian Industry

Estimated Pressure drop in Line across


various equipments in FW circuit
Sl. No.

Parameters

Pressure
drop

FCV (Flow control valve) 4.0

H P Heater

1.0

ECO

2.0

Static head

4.0

Pipe losses

1.0

Total

12 kg/cm2

Confederation of Indian Industry

 Plant has removed one stage of pump and


is operating at 126 kg/cm2 discharge
pressure
 CII congratulates Plant personnel on their
step
 Further potential to tap into in terms of
efficiency and pressure drop required
across system

Confederation of Indian Industry

Optimize the operation of Auxiliary


cooling tower Circuit
 Before

32 0C

50 %
Open
2 KG/cm2

Cold well

ACW 1

Heat Exchangers

4.8
KG/cm2
28 0C

ACW 2

130 A

Confederation of Indian Industry

940 m3/hr

Optimize the operation of Auxiliary


cooling tower circuit
 After

50 %
Open

31.5 0C

1.5
KG/cm2

Cold well

ACW 1

4 KG/cm2

Heat Exchangers

26.5 0C
ACW 2

80 A

Confederation of Indian Industry

800 m3/hr

Optimize the operation of Auxiliary


cooling tower circuit





Earlier, one cooling fan were operating


Earlier Cold well temperature only 2829 0C
Current cold well temperature 26.5 0 C
Plant has reduced discharge pressure from 4.8 bar
to 4.2 bar and further to 4 bar
 Further scope to reduce the discharge pressure
 Inlet valve to Cooling tower is heavily throttled at
50 % open
 Creating artificial system resistance to increase
pump discharge pressure
 At least 0.5 bar can be reduced

Confederation of Indian Industry

Optimize the operation of Auxiliary


cooling tower circuit
 Recommedations
 Open valve in Cooling tower outlet
 Reduce speed of the pump to control
flow at the lesser discharge pressure
 Maintain required T across all the Heat
exchangers by throttling
Annual Saving
Investment

Rs 4 Lakhs
Maintenance

Confederation of Indian Industry

Optimize the excess air in Boiler 1 & 2


O2: 6.5 %
CO : 96 ppm

APH

ECO

ESP

Boiler 2
@110 TPH
Load

ID Fans A &
B
348 kW

Design Parameters
Load

- 25 MW

Steam flow

- 110 TPH

Steam Pressure

- 95 kg/cm2
Confederation of Indian Industry

Optimize the excess air in Boiler 1 & 2


 Observations
 Flue gas analysis was carried out across the flue gas
path to identify air ingress
 Oxygen at ECO inlet for Boiler 1
6.5 %
 Excess air: 44 %
CO at Furnace outlet was found to be 96 ppm
Loss in boiler efficiency

5.05 %
 Oxygen at ECO inlet for Boiler 2
6.4 %
 Excess air: 43 %
CO at Furnace outlet was found to be 124 ppm
Confederation of Indian Industry
Loss in boilerefficiency
4.9 %

Optimize the excess air in Boiler 1 & 2


 Recommendations


Reduce excess air to boiler in steps

Maintain eco inlet oxygen at 5%

Operate SA fan in closed loop with O2 level for better


control of excess air supply

Good potential to improve boiler efficiency

Confederation of Indian Industry

Optimize the excess air in Boiler 1 & 2


 Savings possible:


Maintaining oxygen at 5 % will result in 13 %


reduction in excess air supply

Minimum improvement in boiler efficiency 0.4 %

Reduction in coal consumption:


Boiler 1 & 2: 160 kg/hr

Annual Saving

Rs 30 Lakhs

Confederation of Indian Industry

Optimization of Service Air Compressors


 Present system
 Four screw compressors are present

 Two in each Phase


 According to the requirement no of
compressors are in operation

 Loading pressure : 4.8 kg/cm2


 Unloading pressure : 5.5 kg/cm2
 Operating 2 in operation
 VFD installed in one compressor
 Initially operating at 6 bar, optimized later
to 4.8 bar
Confederation of Indian Industry

Optimization of Service Air Compressors


 Maximum Vessel pressure 1.6 bar
 Recommendation
 Reduce Average pressure of compressors to 4.5
bar

 in steps of 0.1 bar


 Target Pressure setting of 4 bar pressure

Annual Saving

Rs 10 Lakhs

Confederation of Indian Industry

CPP Observation 1

Confederation of Indian Industry

Install High Energy Efficient ID fans


Unit -1
Operating Parameter

Design
Parameter

Name of fans

ID - 1

ID - 2

ID Fan

Flow (m3/sec)

29.6

26.4

34.9

Head developed by fan


(mm WC)

271

273

551

RPM

734

726

980

Efficiency (%)

46.6

43.6

73

SEC (kW/Mw)

13.96
Confederation of Indian Industry

Best No.
10.45

Install High Energy Efficient ID fans


 Possible reasons for low efficiency
 Mismatch between the operating & design
parameters
 Fan Designed for 550 mm WC
 Operating at 280 mm WC
 To be studied in detail along with Unit II ID
fan

Confederation of Indian Industry

SUMMARY OF FINDINGS
Parameter
Total Annual Saving
Annual saving without
investment
Annual saving with investment
Investment required
Simple payback period

No. of
Projects

Rs. in Lakhs

28

644

11

152

17

492

17

342
8 Months*

* For capital proposals only excluding nil investment


and long term proposals

To Sum-up
 UTCL, APCW - Already several efforts taken
towards energy efficiency
Several projects on anvil
 UTCL, APCW & CII- Energy Audit indicates
further Potential
 The Present Audit - A Beginning

Confederation of Indian Industry

Thank you

Confederation of Indian Industry

Вам также может понравиться