Академический Документы
Профессиональный Документы
Культура Документы
At the outset
Thank You
Opportunity
Support
Hospitality
Objective
Ultratech Cement Limited, APCW
Should achieve maximum Energy
savings
Ultimately achieve the status of
Excellent Energy Efficient Unit
successful
CII invited
Methodology
Data Collection
Measurements
Identification of projects
Discussion
Now the Final Presentation..
ROLE OF CII
Catalyst / Facilitator role
Supplement in-house activities
Identify energy saving proposals
All possible assistance
Monitoring
Vendor identification
Calculation Basis
Energy Cost
4.23 Rs /kWhr
Coal Cost
Kiln
Kiln Production -
Rs 1000 / MCal
7440 TPD
PROCESS
Raw Mill
Operating detail
Raw Mill 1 Fan
Operating detail
Raw Mill 2 Fan
Volume
761407
772893
Head
707
713
Power
2165
2124
Speed
88 %
87 %
Efficiency
75.66
74.71
SPRS
SPRS
Description
Unit
Plant 1
Plant 2
UTCL,
Tadipatri
RM 1
UTCL,
Tadipatri
RM2
Atox Mill
Atox Mill
Atox Mill
Atox Mill
TPH
325
410
285
285
m3/hr
8, 02, 245
9, 96, 213
7, 61, 407
7, 72, 893
Model
Production
Air volume
Concentratio
n at mill
outlet
g/m3
405
411
374
369
Nozzle
Velocity
m/s
51
51
40
41.8
Annual Saving
Rs 62.39 Lakhs
Investment
Nil
-725 mm WC
Raw Mill 2
-15 mm WC
-15 mm WC
-715 mm WC
-728 mm WC
-722 mm WC
Parameters
Operating detail
Raw Mill 1 Fan
Operating detail
Raw Mill 2 Fan
Volume
761407
772893
Head
707
713
Power
2165
2124
Speed
88 %
87 %
Efficiency
75.66
74.71
SPRS
SPRS
Saving Potential:
Raw Mill 1: 164 KW
Raw Mill 2: 188 KW
Considering operating efficiency of at least 82 %
Raw mill 1
Rs 47.3 Lakhs
Rs 35.0 Lakhs
9 Months
Annual Saving
Investment
Payback
Raw mill 2
Rs 55.6 Lakhs
Rs 35.0 Lakhs
8 Months
- 161 mmWC
- 195
mmWC
RABH fan
Annual Saving
Rs 26.43 Lakhs
Investment
Rs 15.0 Lakhs
Payback
7 Months
Pyro Section
Saving possible
2 kcal/kg clinker
Annual Saving
48.8 Lakhs
Investment
10.0 Lakhs
Payback
5 Months
303 oC
Case Study
Plant
274 oC
465oC
414 oC
575 oC
3
677
4
740oC
522 oC
3
oC
753oC
632 oC
820oC
792oC
820oC
811oC
Kiln Inlet
- 1200
Kiln Inlet
- 1200
Confederation of Indian Industry
Annual Saving
Rs 73 Lakhs
Investment
Rs 25 Lakhs
Payback
4 Months
255 mm WC
-105 mm WC
Operating
Cooler Fan 10
Power: 157 kW
Flow: 119595 m3/hr
Head: 360 mm WC
Temp.: 26oC
pressure
mm WC
mm WC
kW
kW
1R
-70
4.76
841
88
4.18
2L
-61
3.94
787
86
3.39
3L
-65
4.22
830
68
2.87
3R
-64
5.47
622
61
3.33
-108
13.15
593
141
18.41
-105
16.67
450
101
23.5
-73
7.77
553
106
8.24
10
-105
20.83
360
157
32.7
Annual Saving
Rs 32.45 Lakhs
Investment
Rs 8.00 Lakhs
Payback
3 Months
K STRING
-600 mm WC
- 650 mm WC
-630 mmWc
- 700mm WC
1B
Gas velocity:
Gas velocity:
20.9 m/s
20.3 m/s
-650 mmWc
-730 mmWc
-690 mmWc
- 730 mmWc
-690 mmWc
- 735 mmWc
- 25 mmWc
1A
- 25 mmWc
12.7 Lakhs
Investment
10.0 Lakhs
Payback
10 Months
Calciner String:
Annual Saving
18.1 Lakhs
Investment
10.0 Lakhs
Payback
7 Months
-670 mmWC
-710 mmWC
-670 mmWC
K String Fan
-25 mmWC
-25 mmWC
C String Fan
Parameters
Operating detail
K String
Operating detail
C String
Volume
463154
664821
Pressure
685
645
Power
1301
1771
70.65
70.15
Speed
Efficiency
Speed control type
Confederation
of Indian Industry
SPRS
SPRS
Saving Potential:
K String: 180 KW
C String: 256 KW
Considering operating efficiency of at least 82 %
Annual Saving
Investment
Payback
K String
-
Rs 60.8 Lakhs
Rs 50.0 Lakhs
10 Months
Annual Saving
Investment
Payback
C String
-
Rs 54.85 Lakhs
Rs 70.0 Lakhs
16 Months
Coal Mill
25 mm WC
100 % Open
-870 mm WC
-914 mm WC
Operating
Power: 725.5 kW
Flow: 231238 m3/hr
Head: 939 mm WC
Speed: 97 %
Annual Saving
Rs 4.57 Lakhs
Investment
NIL
Cement Mill
3 mm WC
35 % Open
-340 mm WC
- 525 mm WC
Operating
Power: 61.26 kW
Flow: 23155 m3/hr
Head: 528 mm WC
Temp.: 90oC
Annual Saving
Rs 6.1 Lakhs
Investment
Rs 6.6 Lakhs
Payback
13 Months
+ 27 mm WC
-39 mm WC
-80 mm WC
Operating
Power: 160 kW
Flow: 327300 m3/hr
Head: 107 mm WC
Temp.: 195oC
Confederation of Indian Industry
Annual Saving
Rs 19.5 Lakhs
Investment
NIL
- 140 mm WC
- 159 mm WC
- -161 mm WC
Raw
Mill
Silo
Confederation of Indian Industry
Present
Suction
pressure
Norm for
silo
suction
pressure
Fan
Head
Fan
Power
Saving
potential
Mm WC
Mm WC
mm WC
KW
KW
-140
-50
157
23
13
Annual Saving
Investment
Payback
Rs 4.64 Lakhs
Rs 1.50 Lakhs
4 Months
Observation 1
VRM fan
cyc
P=- 58 mmWC
P=- 70 mmWC
P=- 60
mmWC
P=-60 mmWC
P=- 25
mmWC
PH fan
Observation 2
4
5
5.7 % O2
6
Kiln Riser
4.8 % O2
Confederation of Indian Industry
Electrical
Power
factor
Rated
Power
(kW)
%
Loading
P2U01
2.82
0.24
11
22.8
P2U09
3.92
0.43
15
23.3
P2U02
2.2
0.24
11
17.8
P2U19
0.71
0.38
15
4.2
P2U07
2.49
0.22
22
10.1
P2U13
2.61
0.24
22
10.6
3.3
0.35
22
13.4
2.57
0.26
11
20.8
P2U14
P2U03
Power
factor
Rated
Power
(kW)
%
Loading
P2U12
2.34
0.32
15
13.9
P2U04
1.32
0.65
11
10.7
P2U17
2.73
0.22
22
11.0
P2U18
3.72
0.41
22
15.0
P2U10
3.29
0.47
22
13.3
P2U06
2.47
0.41
11
20.0
P2U11
2.85
0.46
15
16.9
Tag No
VL
VP =
3
L1
Delta connection
VL
VL =
VP
L2
L2
L3
L3
Star connection
losses
Annual Saving
Rs 0.49 Lakhs
Investment
Nil
MRSS
Cement
mill
Cooler &
gypsum
yard
Rawmill &
Coal mill
Operating
Voltage
(V)
Operating
Power
(kW)
Recommended
Voltage
(V)
225
9.57
210
222
90.37
210
212
32.13
210
207
111.15
210
Rs 1.02 Lakhs
Investment
Nil
Harmonics Measurements
Harmonics are produced due to non
linear equipment
Variable frequency drives
DC drives
UPS, Computers, etc
Total
Supply System
Voltage (kV) at
Harmonic
Voltage
point of common
coupling
Distortion VT
(%)
0.415
6.6 and 11
33 and 66
132
Individual
Harmonic
Voltage
Distortion (%)
5
4
3
1.5
Odd
4
3
2
1
Even
2
1.75
1
0.5
% V-THD
% I-THD
Cooler fan 1L
8.0
31.0
Cooler fan 1R
8.1
30.4
Cooler fan 2L
8.3
32.1
Cooler fan 2R
8.2
31.1
Cooler fan 3L
8.1
58.3
Cooler fan 3R
7.9
34.9
7.2
61.9
7.6
36.8
Cooler fan 5
8.1
32.6
Cooler fan 6
7.1
29.3
Cooler fan 4L
Cooler fan 4R
Harmonics Measurements
TAG NAME
% V-THD
% I-THD
Cooler fan 7
7.6
34.9
Cooler fan 8
7.5
40.5
Cooler fan 10
7.4
38.8
Incomer 1
2.3
9.6
Incomer 2
2.4
14.1
Incomer 3
7.8
24.8
Annual Saving
Rs 12.32 Lakhs
Investment
Rs 25.00 Lakhs
25 Months
Transformers
are
independent mode
operating
in
Rated
(KVA)
Load
(kW)
Actual
(KVA)
%
Loading
T5
2000
399.72
524.13
26.2
T7
2000
251.16
342.9
17.14
T6
2000
92.00
125.00
6.25
Transformer
No.
T-5
Rated 2 MVA
Actual 125 KVA
7% Load
T-6
0.433kV
Confederation of Indian Industry
Existing system
Rated 2 MVA
Actual 343 KVA
17% Load
T-7
T-5
Rated 2 MVA
Actual 0 KVA
0Load
T-6
0.433kV
Confederation of Indian Industry
Proposed system
Rated 2 MVA
Actual 343 KVA
17% Load
T-7
Annual Savings
Rs 0.81 Lakhs
Investment
Nil
Annual Savings
Investment
20 months
Conventional
FTL
T5 lamps
Power
consumption
50W (36+14W)
28W
Life
20000 hrs
25000hrs
Luminous
efficacy
68lm/W
104lm/w
Annual Saving
Rs 0.34 Lakhs
Investment
Rs 0.25 Lakhs
9 months
1. Generation
2. Consumption
Optimum usage of compressed air
at optimum pressure
Segregating HP & LP users
Confederation of Indian Industry
Installed Capacity
Total Installed HP Compressors
capacity in Line-1:9 No's
230 m3/min or 8144 CFM
Users: Poking, Inter coal transport,
WHR and other plant operations
Capacity Test
The
performance
of
the
compressors analyzed
Free Air Delivered is evaluated by
conducting the capacity test
FAD= P2- P1 x Vr
PO x T
FAD Test
Area
Rated
Actual
Actual
Avg
capacity capacity capacity pressure
(m3/min) (m3/min)
CFM
(bar)
Actual
Actual
Norm
power
SEC
(kW) (kW/CFM) (kW/CFM)
Line-1
Compressor-1
25.0
25.00
883.3
6.15
154
0.17
0.16
Compressor-2
23.5
23.50
830.3
6.15
142
0.17
0.16
Compressor-3
27.5
24.41
862.4
6.15
142
0.16
0.16
Compressor-4
27.5
23.40
826.7
6.15
142
0.17
0.16
Compressor-6
27.5
21.99
776.9
6.15
142
0.18
0.16
Compressor-7
25.0
22.80
805.5
5.75
144
0.18
0.15
Compressor-9
23.5
22.31
788.2
6.05
132
0.17
0.16
Line-2
Compressor-1
25
25.00
883.3
5.65
155.1
0.18
0.15
Compressor-2
25
24.84
877.6
6.25
150.2
0.17
0.16
Rs 11.43 Lakhs
Investment
Nil
Pressure
- 4.5 bar
- 5.2 bar
Annual Saving
Rs 21.13 Lakhs
Investment
Rs 30.00 Lakhs
17 months
Coal Mill
Cooler
Preheater
Raw Mill
Annual Saving
Rs 5.08 Lakhs
Investment
Nil
Rs 1.93 Lakhs
Investment
Nil
with
- 5.75 bar
WHR
- 6.0-6.1 bar
Cooler
- 6.0 bar
Coal Mill
- 6.0 bar
- 5.0 bar
Instrument Air
Air Blaster
- 5.5 bar
- 4.5-4.8 bar
Confederation of Indian Industry
the
Recommended to
Reduce the pressure setting of the compressors
in steps of 0.1 bar
After rectifying SX controller
Option of Segregating Low Pressure users also
can be tried
Confederation of Indian Industry
Rs 7.32 Lakhs
Investment
Rs 5.00 Lakhs
8 months
6.1 bar
5.4 bar
5.0 bar
5.0 bar
Bag House
CP2
5.4 bar
6.1 bar
CP5
Receiver
CP9
All users
Rs 0.74 Lakhs
Investment
Nil
Deaerator
5 kg/cm2
CRT
LPH
105 m3/hr
CEP - 1
8.9
kg/cm2
Ejector
Operating
Parameters CEP 1
105 m3/hr
9.0 bar,
CEP 2
67 kW
Confederation of Indian Industry
Deaerator
5 kg/cm2
CRT
LPH
104 m3/hr
CEP - 1
CEP 2
9.0
kg/cm2
Ejector
Design Parameters
CEP
Operating
Parameters CEP 1
104 m3/hr
104 m3/hr
14 bar
8.9 bar,
68 kW
Pump
Flow
Head
m
Power
Efficienc
y
CEP
105
91
67.7
41
CEP
104
93
60.2
46
Rs 10 Lakhs
Rs 10 Lakhs
12 months
105 kg/cm2
Deaerator
DRUM
1&2
Economizers
Flow
control
valve
ARC valve
HPHs
Common
Header
126 kg/cm2
220
m3/hr
BFP -
Operating
Parameters
Flow > 220 m3/hr
BFP -3
Parameters
Pressure
drop
H P Heater
1.0
ECO
2.0
Static head
4.0
Pipe losses
1.0
Total
12 kg/cm2
32 0C
50 %
Open
2 KG/cm2
Cold well
ACW 1
Heat Exchangers
4.8
KG/cm2
28 0C
ACW 2
130 A
940 m3/hr
50 %
Open
31.5 0C
1.5
KG/cm2
Cold well
ACW 1
4 KG/cm2
Heat Exchangers
26.5 0C
ACW 2
80 A
800 m3/hr
Rs 4 Lakhs
Maintenance
APH
ECO
ESP
Boiler 2
@110 TPH
Load
ID Fans A &
B
348 kW
Design Parameters
Load
- 25 MW
Steam flow
- 110 TPH
Steam Pressure
- 95 kg/cm2
Confederation of Indian Industry
5.05 %
Oxygen at ECO inlet for Boiler 2
6.4 %
Excess air: 43 %
CO at Furnace outlet was found to be 124 ppm
Confederation of Indian Industry
Loss in boilerefficiency
4.9 %
Annual Saving
Rs 30 Lakhs
Annual Saving
Rs 10 Lakhs
CPP Observation 1
Design
Parameter
Name of fans
ID - 1
ID - 2
ID Fan
Flow (m3/sec)
29.6
26.4
34.9
271
273
551
RPM
734
726
980
Efficiency (%)
46.6
43.6
73
SEC (kW/Mw)
13.96
Confederation of Indian Industry
Best No.
10.45
SUMMARY OF FINDINGS
Parameter
Total Annual Saving
Annual saving without
investment
Annual saving with investment
Investment required
Simple payback period
No. of
Projects
Rs. in Lakhs
28
644
11
152
17
492
17
342
8 Months*
To Sum-up
UTCL, APCW - Already several efforts taken
towards energy efficiency
Several projects on anvil
UTCL, APCW & CII- Energy Audit indicates
further Potential
The Present Audit - A Beginning
Thank you