Вы находитесь на странице: 1из 23

risk management and assessment for business

Advances in Process
Control 9
20 September 2011, York, United Kingdom

APC
9

Are Blowout Preventers and Fire & Gas Systems ready to


be classified as Safety Instrumented Systems on offshore
installations?
Presented By:
Jasjeet Singh MCMI, AMIChemE, MBA, BE (Chemical)
Senior Engineer, Risktec Solutions Limited

Advances in Process Control 9

Jasjeet Singh

Objectives
APC
9
Introduce briefly to Blowout Preventer (BOP), and Fire and Gas Systems (FGS) in
offshore oil & gas installation context;
Simplistically evaluate the Safety Integrity Level (SIL) these systems would be
expected to achieve; and,
Discuss if these systems should be designated as Safety Instrumented Systems
(SIS);
Discuss challenges in upgrading BOP and FGS to SIS status.

Advances in Process Control 9

Jasjeet Singh

Functional Safety Definition


APC
9

What is Functional Safety?

The industry standard IEC 61511 defines it as Functional safety is


part of the overall safety that depends on a system or equipment
operating correctly in response to its inputs.
Example:
An over-temperature protection device, using a thermal sensor in
the windings of an electric motor to de-energise the motor before
they can overheat, is an instance of functional safety.
Specialised insulation to withstand high temperatures is not an
instance of functional safety (although it is still an instance of safety
and could protect against exactly the same hazard).

Advances in Process Control 9

Jasjeet Singh

Basic SIS Configuration


APC
9

Detec
t

Decid
e

Sensor
Elements
Pressure

Temperature
Flowrate

Composition

Logic
Control
Safety PLC
Relay Logic

Advances in Process Control 9

Execut
e
Final Elements
Valve
Assemblies
Circuit Breakers
Power Drives
Secondary
Systems

Jasjeet Singh

Systems under the Scanner


APC
9

Blow Out Preventer


Fire and Gas System

Advances in Process Control 9

Jasjeet Singh

Blow Out Preventer


APC
9
What is a Blow Out Preventer?
A Blow Out Preventer (BOP) is a
combination of several valves
installed at the wellhead.
Function: Prevention of escape
of well fluids from primary
containment
BOP Typical Location:
Beneath the rig for land rigs;
At the waters surface on jackup rigs;
On the seafloor for floating
offshore rigs.
Advances in Process Control 9

Jasjeet Singh

What a BOP Looks Like


APC
9

Advances in Process Control 9

Jasjeet Singh

Simplistic LOPA on a BOP


System

APC
9

Scenario

Unexpected release of high pressure gas in the reservoir


into the well causing abnormal and sudden increase in riser
pressure. Potential for release of high pressure oil / gas jet
at the platform from the well (Blow-Out).

Consequences

Multiple fatalities from fire & explosion on the installation;


MATTE

Target Frequency
Factor

6 (equivalent to 10-6 per year)

Initiating Event

Unexpected well pressure due to accumulated gas

Initiating Event
Frequency Factor

3 (equivalent to 1 in 1000 well sites)

Conditional
Modifiers

Ignition Control 0 (No credit)


Exposure 0 (No credit)

Advances in Process Control 9

Jasjeet Singh

Simplistic LOPA on a BOP


System
Independent Protection Layers
BPCS
Alarms
Mitigated
Event
Factor

APC
9

Risk Reduction Factor

Indication of pressure in the


control room and process shut
down

Linked to the BPCS system Not


Independent

(6) (3) (1)

Required SIL for chosen SIF

Hence the BOP System may be required to meet SIL 2 requirements.

Advances in Process Control 9

Jasjeet Singh

BOP Control System


APC
9
Primary Functions:
To ensure that sufficient hydraulic pressure is conveyed to the BOP
assembly when a demand is placed;
Ensure that the sequence of valve activation is executed as per
design;

Elements:
Pressure measurement devices (an array of pressure transmitters /
switches at different strategic locations)
Logic Control (Sub sea modules and on Topsides)
Final Elements (The BOP assembly - Actuators & Valves)
Support Elements (Hydraulic Power Unit)

Advances in Process Control 9

Jasjeet Singh

Typical BOP System


APC
9

Advances in Process Control 9

Jasjeet Singh

Challenges in upgrading BOP


to SIS Status

APC
9

Technical Challenges:
Complex System An array of devices including multiple sensors
Manufacturing high integrity equipment for subsea environment
Operation and Maintenance Challenges:
Proof Testing as per requirements of the Standard
End to End tests in operation are not feasible - Destructive nature of
final elements
Maintenance of equipment under harsh & corrosive environment
Compliance / Standards related Challenges:
Human in the loop limited reliability issues
Same Equipment Different Requirements

LOOP, LOOP AND THE WHOLE LOOP, NOTHING BUT THE LOOP

Advances in Process Control 9

Jasjeet Singh

APC
9

PHASE 1
PHASE 11 Safety Life Cycle Structure and
Planning (IEC 61511-1 Clause 6.2)

PHASE 10 SIS Functional Safety Assessment (IEC


61511-1 Clause 5)

PHASE 9 SIS Verification (IEC 61511-1 Clause 7,


12.4 and 12.7)

SIS Safety Life Cycle


Where will a BOP cause issues

PHASE 2
Allocation of Safety Functions to
Protection Layers
PHASE 3
SIS Safety Requirements
Specifications
PHASE 4
SIS Design & Engineering
PHASE 5

SIS Operation & Maintenance


PHASE 7
SIS Modification
PHASE 8

Advances in Process Control 9

IEC 61511-1
Clause 9
IEC 61511-1 Clause
10, 12

IEC 61511-1 Clause


11, 12

IEC 61511-1 Clause


14, 15

IEC 61511-1
Clause 16

IEC 61511-1
Clause 17

SIS Installation, Commissioning &


Validation
PHASE 6

SIS Decommissioning
STAGE 1: Analysis
Stage
STAGE 2: Realization
Stage

IEC 61511-1
Clause 8

Hazard and Risk Assessment

IEC 61511-1
Clause 18

STAGE 3: Operations and Maintenance Stage


STAGE 4: Management and Planning Stage

Jasjeet Singh

Regulators Position
APC
9
United Kingdom
?
HSE Offshore Divisions Guide GASCET (April 2006) includes BOP as one of the
devices for which a functional safety assessment is recommended using:
UKOOA Guidelines for Instrument Based Protective Systems
IEC 61508
IEC 61511
Norway
Australia

United States
Middle East South Asia -

Advances in Process Control 9

?
?

Jasjeet Singh

Fire and Gas System


APC
9

Fire and Gas Detection Systems


Three principal types of detectors commonly in use on off-shore
installations:
Heat, Flame & Smoke
Flammable Gas
Toxic Gas

Fire and Gas System Final Elements

HVAC System
Emergency Shut Down Sequence Initiation
Shut Off / Isolation Valves
Blowdown and Depressurisation System

Advances in Process Control 9

Jasjeet Singh

Simplistic LOPA on a FGS


APC
9
Scenario

Release of flammable gas. Potential for jet fire / VCE.

Consequences

Multiple fatalities from fire & explosion on the installation

Target Frequency
Factor

6 (equivalent to 10-6 per year)

Initiating Event

10 gas pipeline failure due to vessel impact

Initiating Event
Frequency Factor

Conditional
Modifiers

Ignition Control 0 (No credit)


Exposure 0 (No credit)

Advances in Process Control 9

Jasjeet Singh

Simplistic LOPA on a FGS


APC
9
Independent Protection Layers
BPCS
Alarms
SRPS
Mitigated
Event
Factor

Risk Reduction Factor

Process shut down. Isolation of


pipeline from nearest isolation
valves.

Non - Independent Alarms

Temporary refuges & escape


crafts

(6) (3) (1)

Required SIL for chosen SIF

Hence the FGS may be required meet SIL 1 requirements.

Advances in Process Control 9

Jasjeet Singh

Challenges in upgrading FGS to


SIS Status

APC
9

Technical Challenges:
FSG is also a complex system and is linked with the Emergency Shutdown
System
FSG is a combination of a number of loops multiple SIFs with different SIL
requirements
Operation and Maintenance Challenges:
A large amount of kit to be maintained
Compliance / Standards related Challenges:
Usual suspects

LOOP, LOOP AND THE WHOLE LOOP, NOTHING BUT THE LOOP

Advances in Process Control 9

Jasjeet Singh

BOP and FGS as SIS The Two


Sides
Against

APC
9
For

Field devices and technologies are


fundamentally different

But the devices are available, and are


being developed

Not be considered performing a critical


safety function

They do. ESD is only part of the overall


safety & risk control

IEC 61508 is not applicable

Covers all E/E/PE systems...

Too costly

Not more than cost of an accident

Difficult to materialise

Effort should be made necessity is


mother of invention

Regulator does not want this

Post DwH, they domostly

Industry has been operating this way


Why now?

Continuous improvement

Advances in Process Control 9

Jasjeet Singh

Recommendations
APC
9

Oil and gas industry should explore the possibility of


upgrading the BOP and FGS to SIS.
IEC, Industry and Regulators should red-define / amend
the relevant requirements to clarify the issue.
Design engineers and safety consultants should be
aware of the issue and endeavour to improve the safety
system .

Advances in Process Control 9

Jasjeet Singh

Closing Remarks
APC
9

Not all safety systems are created equal and every


installation has different performance, risks and financial
goals to meet.
Small regional operators are much less likely to make
this step change in the way the BOP and the FGS are
managed due to limited resources. It is up to global
organisations to take this initiative, and raise standard of
best practice in managing these systems.

Advances in Process Control 9

Jasjeet Singh

APC
9

Thank You for Your Attention

Advances in Process Control 9

Jasjeet Singh

Вам также может понравиться