Академический Документы
Профессиональный Документы
Культура Документы
Advances in Process
Control 9
20 September 2011, York, United Kingdom
APC
9
Jasjeet Singh
Objectives
APC
9
Introduce briefly to Blowout Preventer (BOP), and Fire and Gas Systems (FGS) in
offshore oil & gas installation context;
Simplistically evaluate the Safety Integrity Level (SIL) these systems would be
expected to achieve; and,
Discuss if these systems should be designated as Safety Instrumented Systems
(SIS);
Discuss challenges in upgrading BOP and FGS to SIS status.
Jasjeet Singh
Jasjeet Singh
Detec
t
Decid
e
Sensor
Elements
Pressure
Temperature
Flowrate
Composition
Logic
Control
Safety PLC
Relay Logic
Execut
e
Final Elements
Valve
Assemblies
Circuit Breakers
Power Drives
Secondary
Systems
Jasjeet Singh
Jasjeet Singh
Jasjeet Singh
Jasjeet Singh
APC
9
Scenario
Consequences
Target Frequency
Factor
Initiating Event
Initiating Event
Frequency Factor
Conditional
Modifiers
Jasjeet Singh
APC
9
Jasjeet Singh
Elements:
Pressure measurement devices (an array of pressure transmitters /
switches at different strategic locations)
Logic Control (Sub sea modules and on Topsides)
Final Elements (The BOP assembly - Actuators & Valves)
Support Elements (Hydraulic Power Unit)
Jasjeet Singh
Jasjeet Singh
APC
9
Technical Challenges:
Complex System An array of devices including multiple sensors
Manufacturing high integrity equipment for subsea environment
Operation and Maintenance Challenges:
Proof Testing as per requirements of the Standard
End to End tests in operation are not feasible - Destructive nature of
final elements
Maintenance of equipment under harsh & corrosive environment
Compliance / Standards related Challenges:
Human in the loop limited reliability issues
Same Equipment Different Requirements
LOOP, LOOP AND THE WHOLE LOOP, NOTHING BUT THE LOOP
Jasjeet Singh
APC
9
PHASE 1
PHASE 11 Safety Life Cycle Structure and
Planning (IEC 61511-1 Clause 6.2)
PHASE 2
Allocation of Safety Functions to
Protection Layers
PHASE 3
SIS Safety Requirements
Specifications
PHASE 4
SIS Design & Engineering
PHASE 5
IEC 61511-1
Clause 9
IEC 61511-1 Clause
10, 12
IEC 61511-1
Clause 16
IEC 61511-1
Clause 17
SIS Decommissioning
STAGE 1: Analysis
Stage
STAGE 2: Realization
Stage
IEC 61511-1
Clause 8
IEC 61511-1
Clause 18
Jasjeet Singh
Regulators Position
APC
9
United Kingdom
?
HSE Offshore Divisions Guide GASCET (April 2006) includes BOP as one of the
devices for which a functional safety assessment is recommended using:
UKOOA Guidelines for Instrument Based Protective Systems
IEC 61508
IEC 61511
Norway
Australia
United States
Middle East South Asia -
?
?
Jasjeet Singh
HVAC System
Emergency Shut Down Sequence Initiation
Shut Off / Isolation Valves
Blowdown and Depressurisation System
Jasjeet Singh
Consequences
Target Frequency
Factor
Initiating Event
Initiating Event
Frequency Factor
Conditional
Modifiers
Jasjeet Singh
Jasjeet Singh
APC
9
Technical Challenges:
FSG is also a complex system and is linked with the Emergency Shutdown
System
FSG is a combination of a number of loops multiple SIFs with different SIL
requirements
Operation and Maintenance Challenges:
A large amount of kit to be maintained
Compliance / Standards related Challenges:
Usual suspects
LOOP, LOOP AND THE WHOLE LOOP, NOTHING BUT THE LOOP
Jasjeet Singh
APC
9
For
Too costly
Difficult to materialise
Continuous improvement
Jasjeet Singh
Recommendations
APC
9
Jasjeet Singh
Closing Remarks
APC
9
Jasjeet Singh
APC
9
Jasjeet Singh