Академический Документы
Профессиональный Документы
Культура Документы
Pakistan
Quarterly Portfolio Performance Review
Third Fourth Quarter 20143
CURRENCY EQUIVALENTS
(301September December 20143)
Currency Unit Pakistan rupee
PR 1.00 = $0.009898540.009417
$1.00 = PRs 101.025106.19
ABBREVIATIONS
ADB
ADF
AGP
CPRM
DISCOs
EAD
ED
FY
GoB
GoKP
GoPb
GoS
IA
ICB
LAR
LARP
MoC
MFF
NCB
NHA
NTDC
OCR
PEPCO
PFR
PIU
PMU
PPP
PRM
PRs
PSU
QPPR
TA
ToR
W/A
W&SD
(i)
(ii)
CONTENTS
I.
INTRODUCTION
II.
PORTFOLIO OVERVIEW
III.
PORTFOLIO PERFORMANCE
IV.
SECTOR OVERVIEW
V.
APPENDICES
1.
2.
3.
4.
5.
ANNEXURE
I-
Pakistan
Quarterly Portfolio Performance Review
Third Fourth Quarter 20134
I.
INTRODUCTION
1. The Pakistan Quarterly Portfolio Performance Review Third Fourth Quarter 20134 (QPPRIIIV) will be conducted during 21xx-29xxNovember February 20134 by Asian Development
Bank (ADB) and the Government of Pakistan (the Government).It will be a joint review after
lapse of 4 months since after the annual country portfolio review (CPR) that was concluded
in October 2014. was carried out in July 2013. The QPPR-III will review the status of the
ADB-financed portfolio of loans and grants projects during the quarter up to the cut-off date
of 3031 SDecember eptember 20143.
2. The Mission will (i) review the status of agreed actions of CPR; (ii) examine the country
portfolio performance as measured by key indicators; (iii) assess the latest project outputs
achieved under the active portfolio; (iv) review progress in achieving disbursement and
contract awards target; and (iv) review the status of project specific agreed actions. This
background paper will be presented to the Government by the Mission and forms the basis
for discussion with the Government,and executing and implementing agencies.The Mission
will present the findings in the wrap-up meeting with Secretary EAD, followed by an Aide
Memoire.
II.
PORTFOLIO OVERVIEW
3. The Pakistan active public sector portfolio amounts to $35.5107 billion as of 310September
December 2014 3including 2435 active loans for 1725projects. There are214 technical
assistance (TA) projects amounting to $20.13.58 million. The accounts of all grants still
active in the second quarter were closed in the third quarter with the result that tThe portfolio
does not have
longer have any grant financed projects. Of the 17 projects, 3
projects($2During the year 2014, loan accounts of two projects (201.783 million) were
closed. that were competed in 2012 and 2013 still required closure of loan accounts 1.
Moreover, 141 projects ($1,990.24479 million) are scheduled to be completed in by 31
December 20135. with loan accounts scheduled to close in 2014. The remaining 10 24
ongoing projects ($32.3152 billion) will continue to be implemented beyond 2013in 2015
and onward as per the project implementation schedules.2Moreover 4 projects ($1.6 billion)
are expected to be approved in the last quarter of 2013, so that the total ongoing portfolio
value will increase to about $3.9 billion by end 2013.
4. During the year, overdue 3 grants and 3 two loans accounts were closed amounting to about
$550201.7 million. and further closure of accounts of $278 million is expected by end 2013.
All ongoing projects (except for Flood Emergency Reconstruction Projects) are now
subsequent tranches of multi tranche financing facility (MFF). The portfolio is now sharply
focused with energy, transport, and agriculture and irrigation, and transportaccounting for
more than 950% of the portfolio. In terms of lending modality, the multi tranche financing
facility (MFF) accounts for more than 751% of the active portfolio while the remainder (49%)
are project/program loans. The Asian Development Fund (ADF) provides $1,460.7558
million (1826%) for the active portfolio while remaining $4.2.15 billion (8274%) is financed
1Federally Administered Tribal Areas Rural Development Project was closed in October
2013
2 Unless projects are not extended that are scheduled to close on 31 December 2013
4
7. Changes till Quarter III: During the year, the active portfolio value was reduced from $3.46
billion to $3.07 billion as large amount of overdue projects accounts were closed and surplus
amount cancelled. The value of ongoing projects however remainedunchanged and stayed
at about $2.5 billion as new projects, which were approved in 2012, reached effectiveness in
2013. The CAD achievements were higher in the second quarter, slowed in third quarter.
While no substantial contract awards are expected in last quarter, additional disbursements
of about $135 millionmay be achieved, mostly depending upon performance in energy and
transport sectors.
Table-1: Quarterly Portfolio Changes in 2014
(Amounts in $ million)
3
Description
Active Loans
Ongoing
Awaiting Signing
Awaiting Effectiveness
Awaiting Closure of Accounts
Closed Accounts
No.
No.
No.
No.
No.
No.
Active Grants
CAD
Contract Awards (quarter)
Disbursements (quarter)
III.
Unit
Projects
Projects
Projects
Projects
Projects
Projects
$b
$b
$m
$m
$m
$m
25
18
4
3
2
QTR-I
18 3.46
12 2.55
3
416
3
2
494
157
24
19
1
2
2
1
QTR-II
17 3.11
13 2.52
1
245
1
98
2
246
1
222
No | $m
3 | 143.5
3 | 143.5
$m
$m
45.8
78.1
292.7
143.5
24
20
1
3
QTR-III
17
3.07
13
2.54
1
3
245
278
19.9
93.4
PORTFOLIO PERFORMANCE
8. Performance Indicators: ADB monitors the implementation performance using the baseline
projections of contract awards and disbursements agreed with EAs/IAs at loan approval.
These projection targets are only revised during a midterm review (MTR), or after a major
change of scope, or approval of an extension of project duration of more than 12 months. By
the end of thirdquarter 2013, performance of 13ongoing loan financed projectswasrated. The
rating of the following 5projects have has been changing facing implementation challenges
and the ratingsover the past 4 quarters are given as detailed below.
Table-2: Project Performance Ratings of Ongoing Projects
Q1
On
Track
Ratings
Q2
Q3
On
On
Track
Track
On
Track
On
Track
On
Track
On
Track
On
Track
On
Track
NameName
MFF: Sindh Cities
Improvement
Investment
Program-Project 2
MFF: Punjab
Irrigated Agriculture
Investment
Program - Project 1
MFF-Power
Distribution
Enhancement
Investment
Program -Tranche
Remarks
Q4
Potential Rating dropped due to
Problem
delayed
start-up
delays
caused by delays in key
decision
making
and
approvals leading to lower
disbursements against the
projections for 2014.
Potential Rating dropped due to lower
Problem
disbursements against the
target for 2014.
Potential Rating dropped due to lower
Problem
disbursements against the
target for 2014.
NameName
Ratings
Q3
Remarks
Q1
Q2
On
Track
On
Track
On
Track
n.a.
n.a.
On
Track
Actual
Problem
On
Track
On
Track
On Track
MFF: National
Trade Corridor
Highway
Investment
Program-Tranche 2
n.a.
n.a.
n.a.
Actual
Problem
MFF: Energy
Efficiency
Investment
Program - Tranche
1
Social Protection
Development
Project
On
Track
On
Track
On
Track
Potential
Problem
Potentia
l
Problem
On Track
2
MFF: Power
Distribution
Enhancement
Investment
Program-Project 3
MFF: Power
Distribution
Enhancement
Investment
Program-Tranche 4
MFF-National
Trade Corridor
Highway
Investment
Program-Proj 1
Q4
Rating improved to On
Track in second quarter
and sustained till year end,
due to higher contract
award and disbursements
compared to the projections
for 2014, and compliance to
financial covenants.
The loan became effective in
Nov 2014. As of 31 Dec 2014,
20% project period has elapsed
but no contract could be
awarded. Similarly
disbursements are also only 3%
of the targets for 2014.
Rating deteriorated due to
lower CAD achievements
against the targets for
2014..
n.a = not applicable (since the loan not effective yet), Q = quarter
Flood Emergency
Reconstruction
Project
Actual
Problem
Actual
problem
Actual
Problem
On track
Power Transmission
Enhancement
Investment
Program - Tranche
III4
Potential
Problem
Potential
Problem
Actual
problem
Actual
problem
Punjab Irrigated
Potential
Actual
On track
Agriculture
Investment
Program (PIAIP)
Tranche-II
Problem
Potential
Problem
problem
Sindh Cities
Improvement
Investment
Program (SCIIP) Tranche II
Potential
Problem
No
.
21
1
22
2
%
95%
No
.
22
5%
100%
22
%
100%
No
.
21
3
%
88%
13%
100%
24
100%
No
.
17
6
2
25
%
68%
24%
8%
100%
6 Quarterly Portfolio Performance Review for Fourth Quarter 2012 19 to 28 February 2013
12. RP) ($60 million), (iv) start up delays under Sind Cities Improvement Investment Program
Tranche II ($45 million) and, (v) ongoing procurement in other projects which is not finalized
yet ($35 million).As of 30 September 2013, $359 million has been awarded so far. With
exception to few small contracts and contract variations, no major contractsmay be awarded
within the remaining period of 2013.
13. Similarly, the project profile for the entire implementation period recorded annual target of
disbursement as $551 million, which was later revised to $422 million after review missions
were carried out.The EAs assessment at the start of year was $553 million. As of
30September 2013, $314 million was disbursed in projects. Between now and close of year,
major gap in EAs assessment and achievements is in energy sector ($120 million),
FERP($36 million), transport sector ($35 million), agriculture and natural resources sector
($28 million) and Sindh Cities Improvement Investment Program ($19 million). It is
anticipated that disbursements may increase to $450 million by close of year; energy and
transport sectorsmay likely to contribute in projects which are due for completion in 2013.
14. Sector and EAs Performance: The following table presents the sector-wise achievements
against the targets showing the contract awards and disbursements performance against the
targets during 2014. Contract awards stood at $781.7 million for 2014 against the target of
$295.3 million, and the disbursements reached to a record level of $854.7 million against a
target of $834.9 million. The Energy sector ($692.6 million) followed by ANR ($58.4 million)
and PSM ($18.2 million) sector Projects agriculture and natural resources and FERP (multisector) have been the key drivers of contract awards. Energy sector also achieved the
highest disbursement ($496.6 million) followed by the Transport ($186.7 million), ANR ($90.7
million), and PSM ($68.2 million) sector projects. and disbursements. The details are given
in Appendixces 1.
Table-43: Contract Award and Disbursements by Sector 30 31 September December
20143
Sectors
Achieved till
Quarter - III
Disbursements $m (2013)
Yearly Projections
Achieved till
Quarter III
e-ops
By EAs
e-ops
By EAs
A&NR
Energy
231
82
261
64
206
4
127
143
82
199
53
79
MS
155
209
146
146
143
106
6
422a
104
25
553
69
6
314
Transport
W&OMIS
Total
10
477a
46
580
4
359
($ million)
#
1
2
3
4
5
Sector
ANR
Energy
PSM
Transport
W&OUIS
Total
Disbursement 2014
Projected
Achieved
%
112.676
90.735
81%
552.285
496.591
90%
14.320
68.176
476%
140.730
186.689
133%
14.934
12.533
84%
834.945
854.725
102%
A&NR = Agriculture and Natural Resources, PSM = public sector management, MS = Multisector, W&OUMIS = Water & Other
Municipal Urban Infrastructure & Services
a Targets from e-ops as of 30 September 2013
15. The contract award and disbursement targets and achievements by leading EAs (by volume)
are presented below. These agencies are Irrigation departments (ID) of Punjab and Sindh,
NHA, all EAs in energy sector, PSU and NSUSC7, and W&S Sindh.As explained above,
major under achievement in contract awards is by Irrigation Department in Punjab (mostly
due to low bid for New Khanki Barrage), NHA, PSU&NSUSCand NTDC. Most of the EAs
met or exceeded the disbursements targets for third quarter except for EAs for Renewable
Energy Development Sector Investment Program and Energy Efficiency Investment Program
(MoW&P) due to delays in implementation resulting in low disbursements against the
targets.
Figure 3: Performance of EAs/IAs during 2013
(Against Targets till 3rdQuarter Agreed with EAs)
IV.
SECTOR OVERVIEW
16. Energy:There are 11active loans ($1,247 million), comprising 7projects and 4 MFF
investment support components (all financed under four MFFs). Of this, loan account closure
of one project8 is long overdue while two projects are scheduled to complete this year. The
details are given in Appendix 2. The investments in energy sector are for programs covering
energy efficiency, power distribution enhancement, power transmission enhancement and
renewable energy development. All projects are administered by federal government
organizations except for one MFF tranche for renewable energy development, for which
implementing agencies are from the provinces of Punjab and Khyber Pakhtunkhwa.
17. In 6 ongoing projects amounting to $1 billion (excluding project support components), the
cumulative contract awards and disbursements are $420 million and $217 million - about
7 Program Support Unit and North Sindh Urban Services Corporation
8Power Distribution Enhancement Investment Program (PDEIP) Tranche I
10
42% and 22% of the net loan effective amount respectively.The status of ongoing projects is
presented below:
i.
ii.
A recent project review mission has identified priority actions 9 for Ministry of
Water and Power and PEPCO particularly in completing the deliveries by the loan
closing date and resultant disbursements of $21 million under Loan 2552 10. ADB
had received EADs request to extend the loan closing date to 31 December
2014. The decision in this respect is being deferred and ADB has requested biweekly reporting from PMU on delivery and distribution. For the investment
support component, the long overdue commitment in fully establishing Program
Management Office has not been met which has delayed commencement of
activities under the component especially commencement of procurement.
iii.
iv.
v.
ranges from 23% to 93% and it is expected that 5 subprojects are expected to be
completed by loan closing while 2 two subprojects in June 2014 (beyond the loan
completion date). The undisbursed contract balance is $48 million and it is
assessed that $25 to $30 million12will be disbursed during the remaining period of
the year.
vi.
The Tranche-III is the only project in the portfolio (as of 30 September 2013)
which is rated as Actual Problem project due to no contract awards and
disbursements13. The recent project review mission14listed key priority actions,
particularly pending procurement (500 KV transmission line and associated grid
stations estimated to cost $160 million carries the major project risks). The
mission had noted that unless NTDC meets its aggressive contract award
targets, it would be difficult for the project to be completed within the loan closing
date of 30 June 201.
18. Transport: The ongoing transport portfolio comprises three two projects (under two under
MFFs and one stand alone Project) for a total amount of $887.8400 million. These include
are National Trade Corridor Highway Investment Program (NTCHIP) Tranche I and Tranche
II, and National Highway Development Sector Investment Program (NHDSIPand the
t)ransport component of Flood Emergency Reconstruction Project. All three contracts under
the two projects have been awarded for $261 million. Total disbursements in under the two
projectstrenches of NTCHIP, as of 30September 31 December 20143, amounted to $12110
million. There is an uncommitted loan amount of $205.139 million and about $226.150
million is undisbursed loan amount in the awarded contracts. The bulk of this undisbursed
amount ($200.0 million) is related to Tranch II of NTCHIP which became effective in
November 2014.
19. Against the transport component of FERP, cumulative contract awards and disbursements
stood at $486.8 million and $413.6 million respectively as of 31 December 2014. The
contract awards on FERP for 2014 were $1.8 million against the target of $60.1 million,
whereas the disbursements were $107.8 million against the target of $71.6 million for the
year 2014. . Under the two MFFs, NHA has met the overall disbursements targets as
agreed in February 2013 due to overachievement in NHDSIP, offsetting slow progress (less
disbursement) on Motorway M-4 (NTCHIP).
20.
i.
ii.
iv.
21. In addition, there is a transport component of $418 million under Flood Emergency
Reconstruction Project. Of this, $287 million is to be implemented by NHA and $131 million
through the Sindh Works and Services Department (further explained under multi-sector).
22. Agriculture and Natural Resources: In the agriculture and natural resources, loan account
of one two project; Sindh Coastal Community Development Project Sustainable Livelihoods
in Barani Areas Project ($289.1834 million), and Power Distribution Enhancement
Investment Program Tranche 1 ($171.9 million) was were closed in February January 20134
while for MFF: Sindh Cities Improvement Investment Program Tranche 1 ($39.1 million) and
MFF: Energy Efficiency Investment Program - Tranche 1 ($30.0 million) Federally
Administered Tribal Areas Rural Development Project ($45.2 million)15, the accounts could
not be closed by 30 31 September December 20134. Similarly, the ,implementation activities
of MFF: Power Transmission Enhancement Investment Program-Tranche II ($165.0 million),
and MFF: National Highway Development Sector Investment Program Tranche II ($230
million) Sindh Coastal Community Development Project completed on 310 June December
20143 and now passing though winding-up period before closure of loan accounts. The
remaining projects are multiple tranches of the PIAIP. with status, as of 30 September 2013,
given below. With exception to low bid for New Khanki Barrage and remaining one contract
under Tranche I of PIAIP, tThe sector performance on contract award and disbursement
15
2234-PAK(SF) Federally Administered Tribal Areas Rural Development Project Both loans was closed in October June
20143
13
remained satisfactory. As of 31 December 2014, for ANR Projects contract awards were $
58.4 million against a target of $3.5 million, whereas the disbursements stood at $90.7
million against the target of $112.7 million during 2014. met the CAD targets till third quarter
2013 as agreed during February 2013.
23. On Tranche I, the performance of contractors on ICB contracts especially on Balloki Barrage
has not improved despite various efforts by the EA and ADB. It is recommended that EA
takes related contractual actions and establishes good contract administration for better
performance. As mentioned above, the contract of New Khanki Barrage under Tranche II
was awarded in May 2013 after rebidding which has improved the overall portfolio contract
commitments. The contract for the supervision consulting services was awarded in February
2013. The construction works is in progress. The Tranche III became effective on 6 June
2013 and procurement is in progress.
24.Multi-sector(Emergency): Theoverdue accounts related to Earthquake Emergency
Reconstruction Projects and two flood emergency grants of 2010 and 2011 were closed in
September 2013. The only ongoing project is Flood Emergency Reconstruction Project. In
national highways component, NHA could not engage FWO through force account
procedure, despite approval from NHAs Board and ADB. As a result about $60 million worth
of loan amount remained uncommitted and the scope is curtailed to 343 km. The overall
progress is slow (13% against the planned progress of 19%) and generally all ongoing
contracts are behind schedule. NHA could not achieve the CAD targets agreed in February
2013. All ICB contracts and one force account project has completion schedule beyond the
loan closing date of 30 September 2014. These projects require critical monitoring and
oversight by NHA, EAD and ADB to minimize the left over financing burden on Governments
budget.The mid-term review Mission and CPR made it clear that all awarded contracts shall
be completed within the current loan period, or otherwise any cost thereafter shall be
financed by the Government.
25.
26.On the contrary, FERP has seen impressive performance from the irrigation and drainage
and flood protection infrastructure component which has been completed more than a year
ahead of the loan closing period. This component has established good project
administration and best managed project practices. Likewise, provincial road component is
also progressing well. The overall progress is 86% against 92% and all projects will be
completednext year, well before the loan closing date.
27.Water and other municipal infrastructure and services sector: There are three two
ongoing loans ($137 95.4 million) for two projects under MFF Sindh Cities Improvement
Investment Program. The Tranche I will completed by in 31 December June 20134 and the
account closure is overdue by four months now. The outstanding issues under the program
are related to finalizing the Operational Support Fund (OSF) 2012-13 and approval of OSF
for 2013-14, elections for new Board and variations in ICB contracts (Tranche I). The
Tranche II was signed on 8 May 2013 and became effective on 30 July 2013. The current
project rating is Potential Problem due to start-up delays and not achieving the yearly
targets, both in project records finalized at inception as well as agreed at the start of the
year. Other than CAD targets, actions are required in opening of imprest account, expediting
procurement, releasing counterpart funds for both operations and capital works, restructuring
of NSUSC according to summary approved by CM, addressing legal impediments to
outsourcing operation to NSUSC in the local government ordinance and clarifying issue of
staff salaries.
V.
28.The following table presents the summary of proposed agenda of the Mission. The projects
details are presented in respective project summary sheets attached as Annexure I which
14
present the status of agreements of last portfolio review and proposed actions (for
discussion and confirmation).
Table-4: Summary of Missions Agenda
Sr.
No.
1
Actions
15
Appendix-1
Contract Awards and Disbursements Achievements from 1 January 2014 to 31 December 2014
($ million)
Contract Awards 2014
#
Targets
Achieved
3.474
58.383
Disbursement 2014
Targets
1
12.676
1
2
3
4
5
Energy
6
7
8
9
10
11
12
13
14
15
16
17
18
19
Achieved
90.735
0.144
3.330
0.023
0.282
58.078
104.103
0.915
7.325
0.333
(0.265)
37.664
1.419
40.486
11.431
163.034
692.607
552.28
5
496.59
1
0.062
0.975
7.803
30.000
26.025
73.800
10.069
14.300
-
0.063
0.975
167.810
9.234
114.514
0.853
399.158
26.195
0.156
37.137
0.484
0.600
51.186
15.000
20.254
0.005
2.108
399.160
25.190
0.103
0.391
16.241
13.435
(0.053)
1.640
24.507
11.122
0.106
4.570
0.182
399.158
0.135
18.170
14.32
0
68.17
6
0.135
18.170
14.320
68.176
117.944
4.404
140.73
186.68
Appendix-1
21
22
23
24
24
25
Targets
Achieved
Disbursement 2014
Targets
Achieved
45.504
6.800
60.052
5.588
2.600
1.804
-
41.819
26.377
0.500
71.579
0.455
48.066
30.238
0.013
107.233
0.482
0.657
10.757
8.127
14.93
4
12.53
3
1.449
2.363
6.945
0.638
1.859
5.630
8.202
1.682
5.050
6.849
1.448
4.236
295.344
781.691
834.945
854.725
Appendix-1
Appendix-2
Status of Ongoing Projects as of 31 December 2014
($ million)
#
Loan
Agriculture, natural resources and rural development
1
Remain
-ing
Imp.
Period
(Years)
Uncommitted
Loan
Amount
Undisbursed
Loan
Amount
Undisbursed
Contract
Amount
Cumulative
Contract
Awards
Cumulative
Disbursement
208.995
208.278
141.009
0.7
0.716
67.986
67.269
10.185
9.214
7.534
0.7
0.971
2.651
1.680
253.547
193.973
77.171
2.0
59.574
176.377
116.802
73.000
58.078
11.478
2.2
14.922
61.522
46.601
116.178
115.944
62.189
1.5
0.234
53.989
53.755
5.318
3.111
2.872
1.5
2.207
2.446
0.239
10.052
5.036
3.600
2.0
5.016
6.452
1.436
243.240
167.810
13.981
1.5
75.430
229.259
153.829
9.027
8.362
3.510
4.0
0.665
5.517
4.852
172.300
131.767
99.999
0.7
40.533
72.301
31.767
245.000
114.514
11.122
2.0
130.486
233.878
103.392
167.200
0.853
0.106
2.5
166.347
167.094
0.748
18.558
399.158
1.300
399.158
0.672
399.158
2.2
0.4
17.258
-
17.887
-
0.628
-
413.355
18.170
68.176
4.5
395.185
345.179
-50.007
Net Loan
Amount
Transport
Appendix-2
#
16
Loan
2400-PAK: MFF-National Trade Corridor Highway Investment
Program-Proj 1
17
3121-PAK: MFF: National Trade Corridor Highway Investment
Program-Tranche 2
18
2742-PAK-01: Component A and B: National Highways And
Provincial Roads
18
2742-PAK-02: Component C: Irrigation and Drainage And
Flood Protection
Water and other urban infrastructure and services
19
20
Remain
-ing
Imp.
Period
(Years)
0.2
Uncommitted
Loan
Amount
4.554
Undisbursed
Loan
Amount
26.147
Undisbursed
Contract
Amount
21.593
3.0
200.000
199.988
-0.013
248.045
0.4
54.448
125.894
71.446
167.280
165.555
0.4
0.595
2.320
1.725
25.100
1.859
1.463
2.6
23.241
23.637
0.396
70.288
5.630
4.236
2.6
64.658
66.052
1.394
3,328.31
6
2,071.27
5
1,441.74
2
1,257.042
1,886.57
5
629.53
3
Net Loan
Amount
146.000
Cumulative
Contract
Awards
141.446
Cumulative
Disbursement
119.853
200.000
0.013
373.939
319.491
167.875
Appendix-2
Appendix-3
List of Loans in 2014 as of 31 December 2014
Approval
No.
Name
Approval
Effectivity
15.Jan.07
18.Dec.06
27.Feb.08
24.Aug.07
Original
Closing
Rev/
Actual
Closing
Status
Fund
Net Loan
Amount
($ million)
30.Jan.14
30.Sep.15
Closed
Ongoing
ADF
OCR
29.834
208.995
1
2
2310-PAK(SF)
2299-PAK
30.Jun.13
30.Sep.1
3
Appendix-3
#
3
Approval
No.
2300-PAK(SF)
2841-PAK(SF)
2971-PAK
3239-PAK(SF)
7
8
3159-PAK
3160-PAK(SF)
Status
Ongoing
Fund
ADF
Net Loan
Amount
($ million)
10.185
Ongoing
ADF
253.547
Ongoing
OCR
73.000
ADF
42.466
OCR
ADF
50.000
94.265
30.Jun.16
Ongoing
OCR
116.178
30.Jun.16
Ongoing
ADF
5.318
Ongoing
ADF
10.052
Ongoing
OCR
165.000
Ongoing
OCR
243.240
Closed
OCR
171.894
Ongoing
ADF
9.027
Ongoing
OCR
172.300
Ongoing
OCR
245.000
Ongoing
OCR
167.200
OCR
30.000
31.Mar.17
Require account
closing
Ongoing
ADF
18.558
30.Jun.15
31.Mar.19
30.Jun.24
Ongoing
Not yet effective
Not yet effective
ADF
OCR
OCR
399.158
840.000
30.000
Original
Closing
30.Sep.1
3
31.Dec.1
6
31.Mar.17
Rev/
Actual
Closing
30.Sep.15
Name
MFF-Punjab Irrigated Agriculture Investment
Program - Project 1
Punjab Irrigated Agriculture Investment Program
(Tranche 2)
MFF: Punjab Irrigated Agriculture Investment
Program-Project 3
Federally Administered Tribal Areas Water
Resources Dev't Project
Trimmu And Panjnad Barrages Improvement Project
Trimmu And Panjnad Barrages Improvement Project
Approval
18.Dec.06
Effectivity
24.Aug.07
22.Dec.11
17.Feb.12
13.Dec.12
06.Jun.13
13.Dec.06
29.Nov.07
30.Jun.12
13.Dec.06
29.Nov.07
30.Jun.12
13.Dec.06
11.May.07
17.Dec.07
17.Apr.09
31.Dec.14
22.Dec.11
21.Feb.12
31.Dec.1
6
31.Dec.1
3
30.Jun.16
12.Sep.08
13.Jan.09
30.Jun.12
03.Jan.14
12.Sep.08
13.Jan.09
14.Dec.10
05.Oct.11
14.Dec.12
10.Dec.13
13.Dec.13
18.Jul.14
31.Dec.1
8
30.Sep.1
5
31.Dec.1
6
30.Jun.17
22.Sep.09
30.Aug.10
31.Jul.12
22.Sep.09
30.Aug.10
24.Apr.14
09.Dec.13
09.Dec.13
28.Apr.14
15.Dec.14
30.Sep.2
0
31.Mar.21
31.Mar.21
22.Sep.14
22.Sep.14
Energy
2286-PAK
10
2287-PAK(SF)
11
2290-PAK(SF)
12
2396-PAK
13
2846-PAK
14
2438-PAK
15
2439-PAK(SF)
16
2727-PAK
17
2972-PAK
18
3096-PAK
19
2552-PAK
20
2553-PAK(SF)
21
22
23
3126-PAK(SF)
3090-PAK
3091-PAK
30.Jun.14
Appendix-3
#
24
25
Approval
No.
3092-PAK(SF)
3203-PAK
Name
Jamshoro Power Generation Project
MFF: Power Transmission Enhancement Investment
Program-Project 4
Original
Closing
31.Mar.19
31.Dec.1
6
Approval
09.Dec.13
03.Dec.14
Effectivity
22.Oct.13
04.Dec.14
24.Jun.14
30.Jun.19
30.Jun.20
26.Aug.09
21.Sep.09
17.Dec.07
22.Dec.08
31.Dec.1
3
30.Jun.14
01.Apr.14
11.Nov.14
27.Jun.14
Rev/
Actual
Closing
Status
Not yet effective
Not yet effective
Fund
ADF
OCR
Net Loan
Amount
($ million)
28.113
248.000
Ongoing
Not yet effective
ADF
ADF
413.355
19.524
31.Dec.14
Ongoing
OCR
230.000
31.Mar.15
Ongoing
OCR
146.000
Ongoing
OCR
200.000
OCR
127.000
25.May.15
Ongoing
OCR
373.939
25.May.15
Ongoing
OCR
167.875
Require account
closing
Not yet effective
ADF
47.716
OCR
195.000
26
27
3049-PAK(SF)
3214-PAK(SF)
Transport
28
2540-PAK
29
2400-PAK
30
3121-PAK
31
3197-PAK
32
2742-PAK-01
32
2742-PAK-02
32
2743-PAK(SF)
33
3134-PAK
25.Nov.14
30.Mar.11
26.May.11
30.Mar.11
26.May.11
30.Mar.11
26.May.11
31.Dec.1
7
10.Dec.1
7
30.Sep.1
4
30.Sep.1
4
30.Sep.1
4
31.Dec.1
8
2499-PAK(SF)
35
2975-PAK
36
2976-PAK(SF)
Total
Water and other urban infrastructure and services
19.Dec.08
06.Mar.09
18.Dec.12
30.Jul.13
18.Dec.12
30.Jul.13
31.Dec.1
2
31.Aug.1
7
31.Aug.1
7
30.Jun.14
Require account
closing
Ongoing
ADF
39.078
OCR
25.100
Ongoing
ADF
70.288
5,716.206
Appendix-3
Approval
No.
Name
Approval
Effectivity
Original
Closing
Rev/
Actual
Closing
Status
Fund
Net Loan
Amount
($ million)
Appendix-4
List of Active Technical Assistance Projects
(As of 31 December 2014)
#
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
TA
No.
7795
8309
8337
8371
8404
8405
8406
8410
8443
8488
8531
8648
8683
8735
8862
8772
8795
8796
8800
8832
8818
Title
CAPACITY BUILDING FOR THE FLOOD EMERGENCY RECONSTRUCTION PROJECT
CAPACITY BUILDING FOR ENHANCED SAFEGUARDS MANAGEMENT
SOCIAL PROTECTION DEVELOPMENT PROJECT
JAMSHORO POWER GENERATION PROJECT
JALALPUR IRRIGATION PROJECT
REGIONAL IMPROVING BORDER SERVICES PROJECT
PROVINCIAL ROAD IMPROVEMENT PROJECT
POWER DISTRIBUTION ENHANCEMENT INVESTMENT PROGRAM 2
SUPPORT FOR EFFICIENT STRUCTURING OF PPP IN PUNJAB & SINDH PROVINCES
PREPARING MFF KHYBER PAKHTUNKHWA WATER RESOURCES SECTOR
KARACHI BUS RAPID TRANSIT PROJECT
DETERMINING THE POTENTIAL FOR CARBON CAPTURE AND STORAGE
PUNJAB INTERMEDIATE CITIES IMPROVEMENT INVESTMENT PROGRAM
IMPROVED INVESTMENT CLIMATE FOR MINERAL SECTOR DEVELOPMENT IN PAKISTAN
IMPLEMENTATION SUPPORT FOR THE RURAL FINANCIAL INCLUSION FACILITY
STRENGTHENING THE CENTRAL POWER PURCHASING AGENCY
PESHAWAR SUSTAINABLE BUS RAPID TRANSIT CORRIDOR
PUBLIC SECTOR ENTERPRISES REFORM PROGRAM
BALOCHISTAN WATER RESOURCES DEVELOPMENT
PRIORITIZING INTERVENTIONS FOR FINANCIAL SECTOR DEVELOPMENT IN PAKISTAN
POWER TRANSMISSION ENHANCEMENT INVESTMENT PROGRAM II
Total
Type
CDTA
CDTA
PPTA
PPTA
PPTA
PPTA
PPTA
PPTA
PATA
PPTA
PPTA
CDTA
PPTA
PATA
CDTA
CDTA
PPTA
PPTA
PPTA
SPATA
PPTA
Approval
30-Mar-11
10-Dec-12
11-Mar-13
27-May-13
18-Jul-13
18-Jul-13
18-Jul-13
29-Jul-13
05-Sep-13
24-Oct-13
06-Dec-13
14-May-14
10-Jul-14
16-Sep-14
28-Nov-14
3-Dec-14
15-Dec-14
15-Dec-14
15-Dec-14
15-Dec-15
16-Dec-15
Closing
30-Sep-15
06-Dec-14
30-Sep-15
31-Mar-15
27-Mar-15
30-Apr-15
31-Mar-15
31-Dec-15
31-Mar-15
31-Aug-15
31-Aug-15
31-Aug-15
29-Feb-16
30-Sep-15
31-Dec-18
31-Jul-16
31-Jan-16
31-Dec-18
31-Dec-16
30-Nov-15
31-Dec-15
Amounts
In
US$ 000
4,000
550
650
525
800
800
700
1,500
225
1,000
825
1,000
800
225
225
1,500
1,500
500
1,100
225
1,500
20,150
Appendix-4
CDTA = capacity development technical assistance
, PATA =
policy advisory technical assistance, PPTA = project preparatory technical assistance, SPATA = small-scale policy advisory technical assistance, TA = technical assistance
Appendix-5
List of Loans requiring submission of Audited Project Financial Statements, Audit Reports and Management
Letter
Appendix-5