Академический Документы
Профессиональный Документы
Культура Документы
I. INTRODUCTION
Lightning surges may impinge on substations due to either
backflashover in the connected overhead transmission lines,
that is, flashover of line insulation caused by lightning flash
to shield wire, or shielding failure in the incoming overhead
lines, that is, lightning flash to phase conductors. The
impinging surges may cause substation outages, thus,
consequently, interruptions in power supply, which result in
economic losses and affect reliability of power systems. Thus,
insulation coordination of substations necessitates the
estimation of the arising backflashover and shielding failure
overvoltages. This can be accomplished analytically [1] or
through computer simulations [2].
For modeling of the basic components of overhead
transmission lines, that is, the towers and their grounding
system and flashover of insulator strings, several simulation
models have been proposed in literature. Specifically, tower
segments are modeled either as single-phase vertical lossless
lines with the same [3]-[10] or different surge impedance
(multiconductor models) [10]-[13] or as a combination of the
latter and lumped circuit elements (multistory models) [14][17]. The tower grounding system is represented by models of
either constant [6], [18] or current dependent grounding
Fig. 1. Tower models: (a) single vertical lossless line models [3]-[10], (b)
multiconductor models [11], [12] (c) Hara et al. multiconductor model [10],
(d) multistory models [14]-[16], (e) Baba & Ishii multistory model [17].
TABLE I
TOWER SURGE IMPEDANCE FOR SINGLE VERTICAL LOSSLESS LINE MODELS
TABLE II
SURGE IMPEDANCE ACCORDING TO MULTICONDUCTOR TOWER MODELS
Fig. 2. Typical towers of (a) 150 kV and (b) 400 kV double-circuit lines of
the Hellenic transmission system; the length of insulator strings is 1.86 m and
3.62 m for the 150 kV and 400 kV line, respectively.
Ri =
2 Z Ti ln
h1 + h2 + h3
hi , i = 1 3 and R4 = 2 Z T 4 ln (1)
Li = Ri
ki h
vT
, i = 1 4
(2)
where h is the tower height, h1, h2, h3 (m) are defined in Fig.
1, ki = 2, and vT is the surge propagation velocity equal to the
speed of light. Baba and Ishii model [17] incorporates fixed
TABLE III
SURGE IMPEDANCE AND ATTENUATION COEFFICIENT ACCORDING TO
TABLE VI
CURRENT DEPENDENT TOWER GROUNDING RESISTANCE MODELS
TABLE IV
DAMPING RESISTANCE AND ki ACCORDING TO BABA & ISHII [17]
TABLE V
DAMPING RESISTANCE AND INDUCTANCE FOR MULTISTORY TOWER MODELS
(3)
where D(m) is the insulator string length and t(s) the elapsed
time after lightning stroke.
According to leader progression models [28], [29] line
insulation flashover occurs when the insulator string length is
bridged by a leader. The leader progresses when the average
electric field strength in the unabridged gap becomes equal to
or higher than a critical value E0. Leader progression models
employ differential equations (Table VII) to compute the
leader length, L, at each time instant; flashover occurs when L
becomes equal to the gap length, D, that is, the insulator
string length. Thus, the 150 kV and 400 kV line insulator
strings were represented by voltage-dependent flashover
switches with the aid of MODELS by incorporating (3)
according to [26], [27] and the differential equations shown in
Table VII according to leader progression models [28], [29].
TABLE VII
LEADER PROGRESSION MODELS
Fig. 4. Computed peak overvoltages at the entrance of the (a), (c) 150 kV
and (b), (d) 400 kV GIS substations; models are numbered according to
Tables I-III, vertical bars indicate the variation of peak overvoltages among
tower models, red line corresponds to safety margin of BIL/1.15.
Fig. 5. Computed peak overvoltages at the entrance of the (a) 150 kV and
(b) 400 kV GIS substations; low current and low frequency grounding
resistance 10 , red line corresponds to safety margin of BIL/1.15.
Fig. 8. Computed peak overvoltages at the entrance of the (a) 150 kV and
(b) 400 kV GIS substations as a function of tower grounding resistance; red
line corresponds to safety margin of BIL/1.15.
Fig. 6. Computed peak overvoltages at the entrance of the (a) 150 kV and
(b) 400 kV GIS substations as a function of low current and low frequency
grounding resistance; red line corresponds to safety margin of BIL/1.15.