Академический Документы
Профессиональный Документы
Культура Документы
Numerical/Formulae:
Section
Formula/Equation
RoI ARR
PV
Benefit-Cost
Analysis;
Project
Selection
criteria
Time
Management
FV
(1 r ) N
NPV
i 0
CFi
(1 r ) i
IRR
Total Float = LS ES
= LF EF
= (P O)/6
CV = EV AC
SV = EV PV
CPI = EV/AC
SPI = EV/PV
Earned Value
Management
VAC = BAC EAC
Channels of
communication
Legend
RoI = Return on Investment
ARR = Average Rate of Return
I = Initial Investment
PV = Present Value
FV = Future Value
R = Rate of discounting
N = Number of years
NPV = Net Present Value
CFi = Cash flow for year I
r = Rate of discounting
N = Number of years
IRR = Internal rate of return; Rate of discount at which
the Present Value of benefits = Present Value of costs;
i.e. In the NPV formula; treat r as a variable and
equate NPV to zero
BCR = Benefit/Cost Ratio
LS = Latest Start Time; LF = Latest Finish Time
ES = Earliest Start Time; EF = Earliest Finish Time
= Expected time
= Standard deviation
O = Optimistic Time estimate
P = Pessimistic Time estimate
M = Most likely Time estimate
CV = Cost Variance; SV = Schedule Variance
CPI = Cost Performance Index; SPI = Schedule
Performance Index
EV = Earned Value; PV = Planned Value; AC = Actual Cost
EAC = Estimate at Complete; BAC = Budget at Complete
ETC = Estimate to Complete
CPIest = Estimated CPI for the remaining period
VAC = Variance at Completion
TCPI = To-complete cost performance index ; to manage
overall spent to Target
C = Number of channels of communication
N = Number of team members
Risk
Management
Important definitions
Term
Project
Program
Portfolios
Stakeholder
Payback
period
Opportunity
cost
Configuration
management
systems
Product
scope
Project scope
Control
account
Work
package
Rolling wave
planning
Leads and
Lags
Critical path
Crashing
Fast tracking
Resource
optimization
Depreciation
Definition
Temporary endeavor undertaken to create a unique product, service or result
A group of projects managed in a coordinated way to obtain benefits or control not
available from managing them individually
A collection of projects, programs, sub-portfolios and operations managed as a group to
achieve strategic objectives
An individual, group or organization who may affect, be affected by or perceive itself to
be affected by a decision, activity or outcome of a project
Number of time periods it takes to recover the initial investment
The value of the opportunity that was available but had to be given up in order to
pursue another opportunity
A set of procedures used to apply technical and administrative direction and
surveillance to identify and document the functional and physical characteristics of a
product, service or a result component
Features and functions that characterize a product
The work that must be done to deliver a product, service or result with the specified
features and functions
The level of work at which the management wishes to exercise control
A unit of work or deliverable at the leaf node of a work package
An iterative planning technique in which the work to be accomplished in the near term
is planned in greater detail while the work to be done in the future is planned at a
higher level
A successor activity is said to have a lead when it can start in advance of the
predecessor; it is said to have a lag when it has to wait for a certain period after the
predecessor
Longest path from start to finish in a project network diagram; All activities on the
critical path have zero float
Achieving reduction in time taken by increasing the cost
Achieving reduction in time taken by increasing the work being done in parallel
Applying optimization techniques to achieve the desired level of utilization of resources
An accounting practice or entry that takes into consideration the reduction in the value
of an asset over time
www.simplilearn.com || Email: supportrequest@simplilearn.com ||
Quality
Grade
Cost of
quality
RACI
Risk
Contract
Cost
reimbursable
contract
Fixed price
contract
Important concepts/mind-maps
Knowledge areas of project management
Matrix
Functional Weak Matrix Balanced Matrix Strong Matrix Projectized
Little or
None
Limited
Low or Moderate
Moderate to
Hogh
High to
almost
total
Virtually
None
0-25%
15-60%
50-95%
85-100%
Part-time
Full-time
Full-time
Full-time
Project
Manager /
Program
Manager
Project
Manager /
Program
Manager
Full-time
Full-time
Percent of Performing
Organization's Personnel
Assigned Full Time to
Project Work
Project Manager's Role
Common Titles for Project
Manager's Role
Project Management
Administrative staff
Part-time
Project
Coordinat
or /
Project
Leader
Project
Coordinator Project Manager
/ Project
/ Project officer
Leader
Part-time Part-time
Part-time
Discuss internally
Discuss externally
Brainstorming
Idea/Mind mapping
Affinity diagram
Majority
Plurality
Dictatorship
Expert
Analogous
Parametric
o Bottom up or detailed
Critical chain method: Including logical and resource dependencies simultaneously to produce a
critical path
Properties of normal distributions
o 68% observations between 1 std deviation of the mean
o 95% observations between 2 std deviation of the mean
o 99.73% observations between 3 std deviation of the mean
o 99.999966% observations between 6 std deviation of the mean
Float or Slack: The amount of time that an activity can be delayed without delaying the project
Schedule compression techniques
o Crashing: Increasing cost to save time
o Fast tracking: Performing activities in parallel to save time
o
o
o
o
o
HR management concepts:
Stages of team formation: Forming, Storming, Norming, Performing and Adjourning
Sources of conflict: Resources, Scheduling, Personality
Conflict resolution techniques:
o Withdraw/Avoid
o Smooth/Accommodate
o Compromise/Reconcile
o Force/Direct
o Collaborate/Problem solve
Forms of authority for the manager: Formal, Expert, Reward, Penalty, Referent
Maslows hierarchy: Physiological, Safety, Social, Esteem, Self Actualization
Herzbergs theory: Hygiene factors, Motivating agents
Mcgregors theory: X theory (people want to avoid work) and Y theory (people are self
motivated)
Leadership styles: Autocratic/Authoritarian, Participative/Democratic, Delegative/Laissez Faire
McKinseys 7-S: Hard elements Strategy, Structure, Systems; Soft elements: Shared values,
Skills, Style, Staff
Risk management concepts:
Contingency reserves are for known unknowns, management reserves for unknown unknowns
Strategies for responding to pure risks or threats:
o Avoid
o Transfer
o Mitigate
o Accept
Strategies for responding to positive risks or opportunities:
o Exploit
o Share
o Enhance
o Accept
Procurement management concepts:
Contract types:
o Cost reimbursable: Buyer pays all costs plus a profit
Cost risk lies with the buyer
www.simplilearn.com || Email: supportrequest@simplilearn.com ||