Вы находитесь на странице: 1из 43

Contract

Number: 1007

File Reference

Page

1007-DISQ-0-P-SS-48080-Rev.3

1 of 43

RWE Dea

Disouq Field Development


FEED

Specification
Sales Gas Metering Package
A-5401

Document number
1007-DISQ-0-P-SS-48080

10.05.12 Issued for Design

A Saleh

A Fawzi

A Hamdan

RWE

08.02.12 Re-Issued for Approval

A Saleh

A Fawzi

A Hamdan

RWE

26.01.12 Issued for Approval

A Saleh /
A Khamisy

A Fawzi

A Hamdan

RWE

11.12.11 Issued for Client comment

A Saleh /
A Khamisy

A Fawzi

A Hamdan

RWE

Approved
By

Client
Approval

Rev

Date

Description

Issued By Checked By

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

Changes List
Rev.

Date
prepared

Prepared by

Description

(DD.MM.YYYY)

26.01.12

A Saleh /
A Khamisy

Client Comments incorporated

08.02.12

A Saleh

Client Comments incorporated

10.05.12

A Saleh

GASCO requirements and client comments


incorporated

Page: 2 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

Table of Contents
1

Introduction ....................................................................................................................6

1.1

Background ................................................................................................................6

1.2

Purpose of Document .................................................................................................7

Referenced Documents .................................................................................................7

2.1

Project Documentation ...............................................................................................7

2.2

International Codes and Standards ............................................................................9

2.3

Order of Precedence ................................................................................................13

Package Components ..................................................................................................14

3.1

Inlet / Outlet Pipe Spools and Interconnecting Piping ...............................................15

3.2

Sales Gas Filter ........................................................................................................15

3.3

Metering Module .......................................................................................................16

3.3.1
3.4

Ultrasonic Meter ....................................................................................................16


Metering System ......................................................................................................18

3.4.1

Multi-stream Flow Computer .................................................................................19

3.4.2

Supervisory Computer ..........................................................................................19

3.4.3

Operator Work Station ..........................................................................................19

3.4.4

Instrumentation Panel ...........................................................................................20

3.4.5

Secondary Devices ...............................................................................................20

Extent of Supply ...........................................................................................................21

4.1

Inclusions .................................................................................................................21

4.2

Exclusions ................................................................................................................22

4.3

Battery Limits............................................................................................................22

Design Requirements...................................................................................................24

5.1

Basic Design Data ....................................................................................................24

5.2

Piping, Flanges, Gaskets and Bolts ..........................................................................26

5.3

Painting ....................................................................................................................26

5.4

Skid Assembly ..........................................................................................................27

5.5

Metering System Design Requirements....................................................................27

5.5.1

Transient, Static and RFI Protection......................................................................27

5.5.2

Cabinet Design .....................................................................................................28

5.6

System Software Design Requirement .....................................................................28

5.7

Noise Limitations ......................................................................................................29

Page: 3 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

5.8

Utilities......................................................................................................................29

5.9

Material Certificate to Conformance (C&C)& Traceability .........................................29

5.10

Name plates .............................................................................................................29

5.11

Climate Condition .....................................................................................................30

Electrical Requirements ...............................................................................................30

6.1

General ....................................................................................................................30

6.2

Power Supply Voltages ............................................................................................30

6.3

Hazardous Area Requirements.................................................................................30

6.4

Certifying Authorities ................................................................................................30

6.5

Ingress Protection for Electrical Equipment ..............................................................30

6.6

Cabling .....................................................................................................................31

6.7

Equipment Earthing & Bonding .................................................................................31

Installation, Operation and Maintenance ......................................................................32

7.1

Installation, Pre-commissioning and Commissioning ................................................32

7.1.1

Start-Up, Pre-commissioning and Commissioning Services ..................................32

7.2

Maintainability...........................................................................................................32

7.3

Calibration ................................................................................................................33

7.3.1

Ultrasonic Meters Calibration ................................................................................33

7.3.2

Secondary Devices ...............................................................................................33

7.4

Special Tools ............................................................................................................33

7.5

Spare Parts ..............................................................................................................33

7.6

Training ....................................................................................................................34

7.6.1

Training Philosophy ..............................................................................................34

7.6.2

Training Course Documentation ............................................................................34

7.6.3

Operator Training Course .....................................................................................34

7.6.4

Maintenance Training Course ...............................................................................34

7.6.5

System Configuration Course ...............................................................................34

7.6.6

Training Aids .........................................................................................................34

Preparation for Shipment .............................................................................................35

Quality Assurance & Health, Safety and Environment ..................................................35

9.1

QC Factory Acceptance Test (FAT) ..........................................................................35

9.2

QC System Integration Test (SIT) .............................................................................37

9.3

QC Site Acceptance Test (SAT) ...............................................................................37

Page: 4 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

9.4

Ultrasonic Meter Inspection ......................................................................................38

10

Vendor Data Requirements ......................................................................................39

10.1

Functional and Detail Design Specification (FDS and DDS) .....................................39

List of Abbreviations ............................................................................................................41

Page: 5 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

Introduction

1.1

Background

RWE Dea Egypt has discovered seven natural gas reserves in the Disouq Concession within
the onshore Nile Delta, starting in 2008, as shown on the concession map below. Further
exploration in the concession is on-going. RWE Dea Egypt is the operator of the Concession
with EGAS as a partner.

The selected development comprises a central gas treatment plant near NSG-1x, where the
gas is collected, treated by means of Low Temperature Separation utilizing the Joule Thomson
effect to achieve sales gas quality, and compressed for export. Sales gas is transferred via a
16 pipeline directly into the GASCO NTS pipeline.
The well fluids are gathered and fed to a common inlet separator at the central plant. All gases
and liquids will be separated and processed on the central treatment plant into sales gas,
stabilized condensate, and free production water.
Treatment of gas is carried out in two trains, while treatment of condensate is in a single train.
Three trains of gas compression and three metering streams shall be installed. Fuel gas for
the gas engine driven main power generators will be taken from the suction of the gas
compressors upstream of the sales gas metering package.

Page: 6 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

1.2

Purpose of Document

This Specification defines the minimum technical requirements for the design, material
specification, fabrication, assembly, QC inspection, QC testing and preparation for shipment of
a fiscal / custody transfer Sales Gas Metering Package to be installed on the Central
Treatment Plant as part of the Disouq Field Development Project.
The Sales Gas Metering Package shall be designed and supplied as a single skid mounted
package if technically feasible with three Ultrasonic Meter Streams and metering room
equipment to be located in the Equipment room of the central room building. The arrangement
of the package and skids to be determined by Vendor. The package shall comprise all
necessary equipment including a minimum of 2 Multi-stream flow computers (with nonresettable flow totalizers), one supervisory computer, one online gas chromatograph to be
located on the skid, sales gas filters, shutdown valve, blow down valve, pressure control
valves, manual valves, field instrumentation and pipe work and fittings as per P&ID Metering
Skid no 1007-DISQ-O-P-DW-48059 and Sales Gas Metering Package Process Data Sheet
document number 1007-DISQ-0-P-DP-48131.
Compliance with this specification shall not relieve the Vendor of his responsibility to provide a
fully completed and safe equipment design including all auxiliary elements necessary to
ensure reliable and efficient operation under the specified operating conditions.

Referenced Documents

The design, construction, fabrication, QC inspection, QC testing, calibration and supply of the
Sales Gas Metering Package shall be in accordance with the latest revisions of the following
specifications, data sheets, codes and standards.
2.1

Project Documentation

NUMBER
1007-DISQ-0-M-RT-42015
1007-DISQ-0-P-DW-48059
1007-DISQ-0-L-DW-39000
1007-DISQ-0-P-SS-48079
1007-DISQ-0-P-DP-48131
1007-DISQ-0-G-MA-30092
1007-DISQ-0-G-DW-30036
1007-DISQ-0-J-SS-33010
1007-DISQ-0-J-SS-33030
1007-DISQ-0-J-SS-33033
1007-DISQ-0-J-SS-33055
1007-DISQ-0-L-SS-39010
1007-DISQ-0-F-DW-10012
1007-DISQ-0-O-CF-48065
1007-DISQ-0-E-SS-27023
1007-DISQ-0-G-MA-30088
1007-DISQ-0-L-SS-39004
1007-DISQ-0-F-G-SP-10014
1007-DISQ-0-F-SS-10018

DESCRIPTION
Environmental Data and Units of Measurement
P&ID Metering Skid
Plot Plan - CTP
Specification for Integrated Control and Safety System
(ICSS)
Sales Gas Metering Package Process Data Sheet
Control System Philosophy
Control System Architecture Central Treatment Plant
Field Instrumentation General Specifications and Testing
Requirements
Control Valve Specification
Shutdown Valve Specification
Safety Relief Valves Specification
Specification for Piping Material
Hazardous Area Classification Layout
Cause & Effect Diagram
Electrical Specifications for Packaged Equipment
Electrical System Design Philosophy
Specification for Painting and Protective Coatings
F&G Requirement Specification
Specification for Equipment Noise Control

Page: 7 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

1007-DISQ-0-M-SS-42003
1007-DISQ-00-QP-1008
1007-DISQ-00-F-QA-1007
Article 5 (2 pages of GSA)
GASCO Vendor list

Package Equipment Specification


Project Quality Plan
QA Plan
Measurements and Tests, Para 5.1 to 5.6
PNM /2011 Reducing and Metering Gas Stations

Page: 8 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

2.2 International Codes and Standards


NUMBER

DESCRIPTION

AGA Eng. Tech.


Note M-96-2-3

Ultrasonic Flow Measurement for Natural Gas Applications

AGA Rep. No.3

Orifice Metering of Natural Gas and Other related Hydrocarbons Fluids

AGA Rep. No.7

Measurement of Gas by Turbine Meters

AGA Rep. No.8

Compressibility Factors of Natural Gas and Other Related


Hydrocarbon Gases

AGA Rep. No.9

Measurement of Gas by Multipath Ultrasonic Meters, second edition


2007

AGA Rep. No. 10

Speed of Sound in Natural Gas and Other Related Hydrocarbons

ANSI B2.1

Pipe Threads (Except Dry seal) Specifications, Dimensions, and


Gauging for Taper and Straight Pipe Threads Including Certain Special
Applications

ANSI B16.20

Ring-Joint Gaskets and Grooves for Steel Pipe Flanges

ANSI B 16.47

Large Diameter Steel Flanges NPS 26 Thru NPS 60

ANSI B16.5

Pipe Flanges and Flanged Fittings

ANSI B 16.9

Factory Made Wrought Steel Butt welding Fittings

ANSI B 16.11

Forged Steel Fittings, Socket Welding and Threaded

ANSI B 31.1

Power Piping Code

ANSI B 31.3

Chemical Plant and Petroleum Refinery Piping

ANSI B 31.4

Liquid Transportation Systems for Hydrocarbons, Liquid Petroleum


Gas, Anhydrous Ammonia, and Alcohols

ANSI B 31.8

Gas Transmission and Distribution Piping Systems

ANSI B16.34

Valves - Flanged and Butt welding End Steel, Nickel Alloy and Other
Special Alloys

ANSI B16.104

Valve Leakage Classifications

ANSI B 36.10M

Welded and Seamless Wrought Steel Pipe

ANSI C 37.96

IEEE Guide for AC Motor Protection

API 1104

Standard for Welding of Pipelines and Related Facilities

API 2B

Specification for Fabricated Structural Steel Pipes

API 500

Recommended practice for classification of locations for electrical


installations at petroleum facilities classified as Class 1, Division 1 and
Division 2

Page: 9 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

API RP 520

Sizing, Selection and Installation Of Pressure-Relieving Devices in


Refineries

API RP 550

Manual on Installation of Refinery Instruments and Control Systems,


Part 1 - Process Instrumentation and Control, Section 6 - Control
Valves and Accessories

API 551

Process Measurement Instrumentation

API 552

Transmission Systems

API RP 553

Refinery Control Valves

API SPEC 6FA

Specification for fire test for valves

API RP 14C

Recommended Practice for Analysis, Design, Installation and Testing of


Basic Surface Safety Systems for Offshore Production Platforms

API 554

Process Control and Instrumentation

API SPEC 6D

Specifications for Pipeline Valves, End Closures, Connectors and


Swivels

ASME B31.3

Chemical Plant & Petroleum Refinery Piping

ASME B16.5

Pipe Flanges and Flanged Fittings

ASME PTC

Temperature Measurement

ASME Section II

Material Specifications

ASME Section IX

Welding and Brazing Qualifications

ASTM A193/A193M

Standard Specification for Alloy Steel and Stainless Steel Bolting


Materials for High Temperature Service

ASTM A194

Standard Specification for Carbon and Alloy Steel Nuts for Bolts for
High pressure / High-Temperature Service

ASTM A234

Specification for Piping fittings of Wrought Carbon Steel and Alloy Steel
for Moderate and Elevated Temperatures

ASTM A269

Standard Specification for Seamless and Welded Austenitic


Stainless Steel Tubing for General Service

ASTM A269

Specification for Seamless and Welded Austenitic Stainless Steel


Tubing for General Service

ASTM A320

Specification for Alloy Steel Bolting Materials for Low Temperature


Service

ASTM A325

High Strength Bolts for Structural Joints, including Suitable Nuts and
Plain Hardened Washers

ASTM A370

Methods and Definitions for Mechanical Testing of Steel Products.

ASTM A403

Standard Specification for Wrought Austenitic Stainless Steel Piping


Fittings

Page: 10 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

ASTM A450/450M

Specification for General Requirements for Carbon Steel, Ferritic Alloy,


and Austenitic Alloy Steel Tubes

ATEX 95 (Directive
94/9/EC)

Directive on Equipment and Protective Systems Intended for use in


Potentially Explosive Atmospheres

BS EN ISO 10204
2004

Metallic Products - Types of Inspection Documents

DIN EN 10204

Metallic Products - Types of Inspection Documents

DIN 50049

Metallic Products - Types of Inspection Documents

EI15

Energy Institute Model Code of Safe Practice Part 15 Area


Classification Code for Installation Handling Flammable Fluids (3rd
Edition).

IEC 664

Insulation co-ordination within low-voltage systems including


clearances and creep age distances for equipment

IEC 60059

IEC Standards Current Ratings

IEC 60079

Electrical Apparatus for Explosive Gas Atmospheres


Part 0: General requirements
Part 1: Flameproof enclosures d
Part 2: Pressurized enclosures p"
Part 4: Method of test for ignition temperature
Part 7: Increased safety "e"
Part 10: Classification of hazardous areas
Part 11: Intrinsic safety I
Part 12: Classification of mixtures of gases or vapours with air
Part 13: Construction and use of rooms or buildings protected by
pressurization
Part 14: Electrical installations in hazardous areas (other than mines)
Part 16: Artificial ventilation for the protection of analyser house
Part 18: Encapsulation m( why this gap here?)according to their
maximum experimental safe gaps and minimum
igniting currents

IEC 60085

Thermal Evaluation and Classification of Electrical Insulation

IEC 60228

Test for electric cables under fire conditions Circuit integrity

IEC 60331

Degrees of protection provided by enclosures (IP Code)

IEC 60529

Industrial Process Control Valves Inspection & Routine Testing

IEC 60751

Industrial Platinum Resistance Thermometer Sensors

Page: 11 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

IEC 61000

Electro-magnetic compatibility Generic emissions standard

ISA 5.1

Instrument Symbols and Identification

ISA 5.4

Instrument loop diagrams

ISA 18.1

Annunciator Sequences and Specifications

ISA 20

Specifications forms for process measurement and control instruments


primary elements and control valves

ISA 50.1

Compatibility of analogue signals for electronic industrial process


Instruments

ISA 51.1

Process Instrumentation Terminology

ISA S75.01

Control Valve Sizing Equations

ISA S75.02

Control Valve Capacity Test Procedures

ISA S75.03

Uniform Face-to-face Dimensions for Flanged Globe Style Control


Valve Bodies

ISA S75.04

Face-to-face Dimensions of Flangeless Control Valves

ISO 1000

SI units and recommendations for use of their multiples and of


certain other units

ISO 4406

Hydraulic fluid power Fluids Method for coding the level of


contamination by solid particles

ISO 6551

Petroleum Liquids and Gases Fidelity and Security of Dynamic


Measurement Cabled Transmission of Electric and/or Electric
Pulsed Data

ISO 14617-1:2005

Graphical symbols for diagrams

ISO 9001:2008

Quality Management System Requirements

ISO 15408

Common Criteria for Information Technology Security Evaluation

ISO14001:2004/2009 Environment Management System- requirements


OHSAS18001:2007

Occupational health and safety system- requirements

ISO 17089

Measurement of Gas by Ultrasonic Meters

ISO 5167-1.

Measurement of fluid flow by means of pressure differential devices


inserted in circular cross-section conduits running full -- Part 1: General
principles and requirements

ISO 6976

Calculation of calorific value, density and relative density

ISO 5167

Measurement of fluid flow by means of pressure differential devices


inserted in circular cross-section conduits running full.

ISO 5168

Methods of measurement of fluid flow, estimation of Uncertainty of a


flow rate measurement.

Page: 12 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

MSS SP 61

Pressures Testing of Steel Valves

NFPA 72E-4

National Fire Alarm and Signalling Code - Automatic Fire


Detectors

NFPA 90A

Standard for the Installation of Air Conditioning and


Ventilation Systems

SI 1994 3260

The Electrical Equipment (Safety) Regulations

SI 1992 2372

The Electromagnetic Compatibility Regulations

2.3 Order of Precedence


In case of discrepancies among the various documents, the following order of precedence shall
be applied:
1. Purchase Order and amendments thereto
2. Data Sheets
3. This Package Specification
4. Other Referenced Project Specifications
5. Egyptian National/Local Codes and Standards
6. International Codes and Standards
7. Egyptian environment law 4 /2011

Page: 13 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

Package Components

The Sales Gas Metering Package shall be used as a fiscal sales gas metering system for the
sales gas of the Disouq Field Development Project to be transferred from the Central
Treatment Plant into the sales gas pipeline. The Sales Gas Metering Package shall
compensate the flow readings for the online pressure and temperature readings as well as gas
composition through one online gas chromatograph and calculate instantaneous flow rate
based on the sales gas composition. The system shall use an ultrasonic meter as the primary
method of flow metering method. Other flow terms such as volumetric or energy flow rate and
flow tantalization shall be calculated in multi stream flow computers. Non resettable flow
totalization shall be recorded in the flow computer, supervisory computer and the ICSS.
The sales gas metering package shall consist of all mechanical, electrical and instrumentation
equipment such as rigid base frame, piping, gas filters, three ultrasonic flow meters,
instrumentation, one online gas chromatograph, cabling and the metering system. The
metering system shall be located in the equipment room of the control room building and shall
include the metering cabinet with marshalling cabinet ex interfaces/barriers, 2 multi stream
flow computer for handling of four ultrasonic meter streams in minimum, supervisory computer,
printer and operator workstation c/w keyboard, mouse and LCD display or touch screen, two
communication interfaces with the ICSS, two communication interfaces for the communication
with the SCADA system of the Gas Grid Operations Company shall be provided and a junction
box or terminal strip with four hardwired signals (IS type) for the hardwired transfer of these
signals to the Gas Grid Operation Company.
The Gas Grid Operations Company will be responsible for the pick-up and transfer of all
signals and communications from the metering cabinet inside the equipment room of the
control room building on the CTP to the location of the SCADA system of the Gas Grid
Operations Company.
Each multi-stream flow computer function shall calculate, record, report the corrected sales
gas volumetric flow rate (in MMSCF/d and in MMSCM/d), energy flow rates (in BTU and
kWh/MWh) and associated total quantities of ultrasonic flow meters as required. The
Supervisory computer shall manage, compare and report the flow computer results and
validity of measurements where the operator workstation shall provide the GUI for the operator
to interface with the system and provide access for printing and reporting.
The Sales Gas Metering Package inlet gas composition, pressure, temperature, flow rate and
sales gas outlet pressure is detailed within the Sales Gas Metering Process Data Sheet
number 1007-DISQ-0-P-DP-48131.
The Vendor is required to confirm the necessary technology and equipment required to meet
the specification. As a minimum, the package will consist of inlet/outlet headers,
interconnecting piping, gas filters, ultrasonic meter runs (US Meter Streams), pressure control
valves, shutdown valve, blow down valve, relief valves, ultrasonic flow meter, field
instrumentation, two multi stream Flow Computer in minimum, supervisory computer,
instrumentation panels and metering cabinets, skids and supports, electrical and instrument
wiring and junction boxes as shown in figure 1 below.

Page: 14 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

Figure 1
The following is a description of the minimum Sales Gas Package Process Components as
per P&ID No:
- 1007-DISQ-0-P-DW-48059
P&ID Metering Skid
3.1

Inlet / Outlet Pipe Spools and Interconnecting Piping

The main inlet / outlet piping, metering runs and header shall be designed for 100% of the
maximum flow rate and shall be equipped with the required instrumentation as shown in the
P&ID- Metering Skid 1007-DISQ-0-P-DW-48059.
The complete pipe inlet and outlet spools layout, arrangement of thermowell tap and
dimensions shall follow the recommended default installation requirements of AGA Report No.
9, Edition 2007, Section 7, for unidirectional design in minimum unless otherwise
recommended or required by the Ultrasonic meter manufacturer.
The requirements and dimensions of the piping shall be according to the Specification for
Piping Material document number 1007-DISQ-0-L-SS-39010.
The inside surface finish of the piping used with Ultrasonic meters shall be 250inch Ra or
better and machined honed. The welds shall be 100% radiographic tested.
The inlet pipe spool shall be equipped with a threadolet for bypass connection of inlet ball
valve. The outlet pipe shall be equipped with threadolets for connections of instruments and
other required equipment as specified by the relevant code.
3.2

Sales Gas Filter

Dependent on the gas analysis and quality, the gas metering skid shall be equipped with gas
filters. Gas filters shall have 100% standby capacity. The gas filter shall be able to separate
liquids from natural gas. Each gas filter shall consist of one/multi cycle separation stage,
cartridge filters and shall have required valves and instrumentation including a vent and
depressurizing connections.
For a quick and easy replacement of the filter cartridges the filter shall be equipped with full
size opening with a quick closing door. The filter shall be equipped with:

Page: 15 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

o
o
o
o
o
o
o

Inlet and outlet plug valves


Pressure Differential transmitter
Pressure Differential and Pressure Indicator
Level Indicator
Drain and vent valves
Safety relief valve
Maintenance manhole (if applicable)

The pressure drop across the clean filter shall not exceed 0.5 barg at the maximum flow.
3.3

Metering Module

The metering module shall consist of three metering runs (metering streams), and the
associated instrumentation necessary to calculate, correct, record flow rate and gas quantities
at standard conditions in MMSCF/d and MMSCM/d. The number of metering streams in
operation shall be decided based on plant production and consumer requirement although
there shall be at least one stream as a hot stand-by meter.
The change-over of the metering streams from operating stream to stand-by and vice-versa,
shall be achieved by manually operated valves. Each Metering stream (Metering Run) shall be
supplied with calibration certificate.
Metering runs or metering streams sizing shall take in consideration the maximum and
minimum flow rate as specified in the process data sheet to insure maximum accuracy within
the full flow operation range.
The minimum equipment of each metering run shall comprise:
o
o
o
o
o
o
o
o

Inlet and Outlet ball valves.


Ultrasonic flow meter.
Pressure transmitter.
Temperature transmitter.
The meter module instrumentations shall be designed and connected to the flow
computer for totalizing, correction and recording.
Each meter shall have a maximum permissible error of 0.5% over the flow range.
Repeatability of the meters must be within +/- 0.2% for the higher velocity range
The total uncertainty of the metering package shall not exceed 1% independent of the
number of streams in operation and shall be tested and verified during flow calibrations
in accordance with AGA Report No.9, Edition 2007, section 6 and the recommended
flow rates. Flow Calibrations are mandatory for fiscal metering applications.

Pressure, Temperature transmitters and instrumentation shall be supplied with high accuracy
and valid calibration test certificates.
3.3.1

Ultrasonic Meter

An ultrasonic meter shall be installed as the primary measuring device in the metering system
in compliance with AGA Report NO. 9. The ultrasonic meter shall be based on the latest
technology and shall be multi-path type (4-path in minimum) with the chords arranged such
that the flow profile can be analysed. Failure of a path shall not result in a measurement failure

Page: 16 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

but shall trigger an alarm that accuracy or measurement is affected. The meter reading shall
be corrected or compensated for the temperature and pressure effect on the measuring path.
Accuracy of Ultrasonic Meter shall be equal to or more than 99.5%. The ultrasonic meter shall
be installed in a way to minimize the accumulation of contaminants.
The ultrasonic meters shall have a large dynamic range and within this range, the following
requirements must be fulfilled:

Negligible offset error.


High repeatability.
High absolute accuracy.

Moreover, the ultrasonic meters shall be unaffected by installation effects such as:

Swirl.
Asymmetry.
Pulsations

The signal transmission of the Ultrasonic Meter shall use digital signals to avoid fluctuations in
sound velocity and to be able to check signal quality in addition to having built in diagnostics.
The Ultrasonic Meter shall have dedicated software to examine the performance of the
metering system. The performance of the metering system shall examine but not limited to the
following:

Swirl and asymmetry.


Ultrasonic meter footprint and ratio (verify the meter by checking the measured Velocity
of Sound versus the Calculated Velocity of Sound).
Performance monitoring of the meter.

The measuring device and associated transducers shall be capable of operating without
detriment of performance throughout the expected pressure and temperature range and
should not be affected by changes in ambient conditions.
The Vendor shall provide a study on how to minimize the effect of unsteady flow conditions
due to the presence of compressors upstream the Metering Package on the Ultrasonic meter
performance.
The Ultrasonic meter shall provide two types of signals:

Frequency/Pulse signal.
Serial port for a minimum distance of 300m between each meter and the flow
computer.

The body of the ultrasonic meter shall be designed, manufactured and tested in accordance
with the relevant sections of API 6 D and ASTM A-216 GR WCB or other material standards
equivalent to these.
The pipe material for the ultrasonic meter, bolts, nuts and flanges shall designed,
manufactured and tested in accordance with the Specification for Piping Material, document
number 1007-DISQ-0-L-SS-39010 and the inside surface finish shall be designed as

Page: 17 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

250inch Ra or better and machined honed. The hydrostatic test pressure of the meter body
shall be 1.5 times the design pressure.
The inside diameter of the ultrasonic meter shall have the same inside diameter as the
upstream tubes diameter and must be within 1% or better in accordance with AGA Report
No.9.
All material exposed to the gas shall be gas-resistant. The surface of the transducers shall not
be degraded in performance due to contact with natural gas. The transducers shall be
removable under pressure. Removal and reinstallation of transducers shall not affect the
calibration of the meter nor the accuracy. The vendor shall supply the retraction equipment to
remove the transducers under pressure.
Each ultrasonic meter shall be sandblast and shall be painted in accordance with the
Specification for Painting and Protective Coatings, document number 1007-DISQ-0-L-SS39004.
3.4

Metering System

The metering system shall comprise of two multi stream flow computer in minimum,
Instrumentation Panel, supervisory computer, operator work station and secondary devices.
The metering system cabinets shall be located in the equipment room of the control room
building.
The Metering System shall interface with the plant DCS System via redundant single mode
fibre links or redundant copper cable serial links (Ethernet TCP/IP) which will be confirmed
during detail design and shall be monitored from the plant HMI (OWS) that will be located in
the Central Control Room (CCR) of the control room building on the Central Treatment Plant.
Vendor to provide intrinsically safe junction box with 12 terminals (3 terminals each signal) for
3 analogue intrinsically safe signals and one digital intrinsically safe impulse signal (max. 50
Hz) as interface point for the Gas Grid Operator GASCO located outside the metering cabinet
in a junction box or inside the metering cabinet on a terminal strip as follows:
Flow rate; 4-20mA, 0-165 MMSCF/d.
Pressure; 4-20mA, 0-100 barg.
Temperature; 4-20mA, 0-80 degree Celsius.
Impulse signal (max. 50 Hz, dry contact) for totalizer inside GASCO.
Above mentioned hardwired signals shall be in parallel also transferred via RS 232 interface.
Vendor shall provide active standard Serial link RS 232 port (physical DB 9 socket) in slave
mode and standard Modbus RTU.
Vendor shall provide also Ethernet connection (physical RJ45 socket), standard Modbus (for
future connection).
Gas analysis data C1 to C9 shall be transferred via serial link RS 232 and Ethernet
connection.
The Gas Grid operator GASCO shall be responsible to pick up the signals from above
mentioned interface points and transfer the signals to his premises.

Page: 18 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

3.4.1

Multi-stream Flow Computer

Multi stream flow computer shall be fully wired, furnished and configured to serve 4 streams in
minimum.
The Multi-stream flow computer convert uncorrected flow figures into corrected flow following,
the equations detailed in AGA 7 and shall compensate if required the flow readings for the
online pressure and temperature readings as well as gas composition through the online gas
chromatograph, and calculate flow rates (in MMSCF/d and in MMSCM/d) and shall be capable
to summarize at least 4 working metering streams.
One multi-stream flow computer shall be in operation and the other shall be a hot standby.
The operating flow computer shall receive the reading from the Ultrasonic Meters. As only two
out of the three meter streams are operating and the third is on standby, the flow computer
shall sum up the flow from the two meters and send the results to the supervisory computer.
3.4.2

Supervisory Computer

The Supervisory computer shall be equipped with necessary check and validation software to
confirm reading accuracy, reliability and validity. The supervisory computer shall supervise,
manage the flow computers and check flow calculation accuracy and validity. The Supervisory
Computer shall be able to change between main and standby flow computers as and when
required. The supervisory computer shall report the plant flow rate and sold quantities for
energy in BTU and kWh and volume in SCF and SCM (per shift, day, week, month, year and
total).
The Supervisory Computer software shall have the capability to check the validity, reliability,
performance and accuracy of the Ultrasonic Meters. The purpose of these checks is to
guarantee that the ultrasonic meters are performing satisfactorily within the specifications and
the initial meter calibration is still valid.
3.4.3

Operator Work Station

The Operator Work Station (OWS) shall be PC-based industrial computer type and shall be
provided with a dedicated keyboard, screen, mouse and printer.
The Operator Work Station OWS shall be provided with a proprietary software package
designed for easy, ergonomic operator interface with the Metering Package facilities.
The software package shall include a suite of Graphical User Interfaces (GUIs). The GUIs
shall be based on the Metering Skid P&ID to provide an accurate and familiar representation
of the process Arrangement.
The Operator Work Station (OWS) display pages shall give the operator an overview of all the
connected metering streams.
For each of the meter streams, the following data shall be displayed:

The volume flow rates at line conditions and at standard conditions in MMSCF/d and
MMSCM/d.
The energy flow rate in BTU and kWh/ MWh.
The mass flow rate in kg/h and metric tons/h

Page: 19 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

3.4.4

Volume-, Energy- and Mass Flow- total per shift, day, week, month, year and overall
totalizer
The pressure and temperature in barg and degree Celsius.
Detailed Information about the Ultrasonic Meter includes flow direction and data
validity.
Ultrasonic meter performance monitoring.
Signal to Noise Ratio.
Speed of Sound (SOS) Comparison as described in the AGA10 standard.
Swirl Angle Monitor.
Asymmetry Monitor.
Instrumentation Panel

Instrumentation Signals of the three metering runs shall be terminated at skid edge intrinsically
safe junction box. The layout, design of the junction box shall follow the 1007-DISQ-0-J-SS33010 Field Instrumentation General Specification and Testing Requirements and 1007DISQ-0-E-SS-27023 Electrical Specification for packaged Equipment and shall be subject to
company approval.
3.4.5

Secondary Devices

The Instrumentation for each metering run classified as "secondary devices" includes, but not
be limited, to the following:

One Electronic static pressure transmitter, 4-20mA, 2 wire, HART protocol compatible,
intrinsically safe transmitter.
One Electronic Temperature transmitter, 4-20mA, 2-wire, HART protocol compatible,
4-wire PT 100 from thermowell to head transmitter, intrinsically safe transmitter

Instrument vendors for all instruments shall be in accordance with attached vendors list. They
shall have required linearity and repeatability with negligible mounting position. It is required
that these transmitters are selected to have an accuracy of 0.1% of calibrated span and a
stability of 0.1% of URL per 60 months in minimum.

Page: 20 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

Extent of Supply

4.1

Inclusions

The scope of supply shall include, but not be limited to the following:

Package Process Components:


Inlet / Outlet Pipe Spools and Interconnecting Piping.
Sales Gas Filters.
Metering Module including three Ultrasonic Meters.
Metering System
Multi-stream Flow Computer.
Instrumentation Panel.
Supervisory Computer including Software and Hardware
Operator Work Station c/w screen, keyboard, mouse and printer including
Software and Hardware
Secondary Devices as per section 3.4.5
All flow, pressure and temperature instrumentation, together with manifold valves
and enclosures.
Gas chromatograph C1 up to C9 in online operation installed on the skid with all
accessories required such as test gas and data link to the metering cabinet for
monitoring purposes and link into the flow computers etc.
System /marshalling/termination cabinet.
Cable trays / supports JBs and for Companys power and Instrument cabling.
Special system cables, including data communication connections to ICSS and Gas
Grid Operations Company interface inside or outside the metering cabinet, any
special cables and connectors required for system operation and gas chromatograph
online operation and monitoring.
Intrinsically safe and other Junction boxes as required.
Terminations and isolation facilities for maintenance.
Redundant Power supply modules.
System Input/ Output interface equipment.
System computers and processors with battery backup.
System network Interface units.
Redundant network communication system.
All operational software (including all licensed operating software and required
protocols for system interfaces), configured to meet the application requirements.
Supervisory Computer management and validation software.
System engineering and design including system architecture and all cabinet design.
Implementation of functions.
Computational algorithms, logic and sequence design.
System power supply design, internal power distribution boards and earthing design.
All necessary equipment and communication cables fully configured for plug and
play to interface with other systems.
Structural Steel Skid Base plate(s) c/w drip pan, diagonally arranged two earthing
points per skid in minimum and flanged drain connection.

Page: 21 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

4.2

On skid interconnecting piping, pipe supports, valves and fittings for process,
utilities, vents, shutdown and relief systems terminating at skid edge with flanged
connections.
Instrumentation, valves, fittings and tubing.
Skid Earthing and Bonding.
Safety devices (including alarms, shutdowns, interlocks, signs, access restrictions,
personnel protection, lightning protection, etc.).
Skid lighting if required.
Special Tools.
Fabrication and Assembly.
QC Inspection & QC Testing (including calibration of each meter run and the whole
metering package, factory, system integration and site acceptance tests including
test procedures and report).
Painting and Protective Coating.
3rd Party Certification.
Supervision of Installation.
Commissioning and start-up spare parts.
List of Two Years operational spare parts.
List of Capital Spares.
Packing, Marking and Preservation.
QC Test Equipment required for Calibration runs, FAT, SIT, and SAT.
Documentation as detailed within VDRF and Minimum Quality Surveillance
(including installation, operation and metering maintenance manuals, validation,
factory acceptance-, system integration-, site acceptance test and calibration
procedures).
Performance and Mechanical Guarantees.
QC Calibration certificates as required for fiscal sales gas metering application.

Exclusions

The following Items are excluded:

4.3

Civil Works including foundations


E+I cabling work from Metering Skid to Metering Cabinet and ICSS inside equipment
of Central Control Room building.
Earthing connection of metering skid to plant earthing system

Battery Limits

The battery limits shall be as indicated on the relevant P&IDs (1007-DISQ-0-P-DW-48059)


For skid mounted packaged equipment the battery limits (i.e. pipe work flanges and instrument
junction boxes) shall be located at the skid base plate edge, skid base frame supports or in the
metering room as applicable. This is as further defined below:

Gas Inlet (R1).


Gas Outlet (R2).
Flare (PSV Outlet) (N-5401 A) (R3).
Flare (PSV Outlet) (N-5401 B) (R4).
Flare (BDV Outlet) (R5).

Page: 22 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

Flare (PCV Outlet) (R6).


Manual Vent; Metering Run A (R7).
Manual Vent; Metering Run B (R8).
Manual Vent; Metering Run C (R9).
Instrument Air Supply connection.
Electrical supply connections.
Earthing connections.
Hardwired instrumentation interfaces (Junction Boxes on skid edge).
Interface connections for Gas Grid Operator Company.

Page: 23 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

Design Requirements

5.1

Basic Design Data

The Gas Metering package shall be designed for continuous operation outdoors on the Central
Treatment Plant (CTP) of the Disouq Field Development Project located in the North Nile Delta
of Egypt environment and in accordance with the relevant data sheets, specifications, codes
and standards and other applicable documents listed in section 2. All supplied equipment and
components thereof shall be designed for a minimum design life of twenty five (25) years. In
addition, the equipment shall be designed, engineered and constructed to ensure safety,
environmental compliance, reliability, quality, efficient operation and ease of maintenance. An
overall package availability of 99.8% is required.
Measuring equipment shall be designed and operated to ensure to meet also the requirements
of Article 5 Measurements and Tests Para 5.1 till 5.6 and an overall uncertainty of the
measurements not exceeding one percent (1%) as stated explicitly in Para 5.5 ( see attached
two pages of Article 5 ).
The total uncertainty of the each stream and the different combinations of stream and the
whole metering package shall be verified with individual meter and metering package testing
and calibration in accordance with AGA Report 9, Edition 2007, Section 6.
IEC 60079 or equal International standards shall be used to classify hazardous areas. FEED
Hazardous Area Classification Layout; see document number 1007-DISQ-0-F-DW-10012.
All electrical and instrumentation equipment on the skid shall be designed, mounted, classified
and certified for zone 1 in accordance with EN 60079-10 or 2G in accordance with ATEX 95
and Gas Group II CT4 or equal.
Associated ex interfaces/barriers in the metering cabinet shall be suitable classified and
certified to match the requirements of the electrical and instrumentation equipment installed in
zone 1 in accordance with EN 60079-10 or 2G in accordance with ATEX 95 and Gas Group II
CT4.
The Vendor shall confirm quantity of hydrocarbon releases and durations for all and any flaring
cases including start up, process shut down and ESD of the package. The Vendor shall pay
particular attention in the design to minimise emissions, air pollutants or releases of toxic
waste products or any other contaminants into the environment. Details of all hazardous and
non-hazardous emissions shall be identified (See emissions limits in appendix -6, Egyptian
environment law 4 /2011).
The Gas Metering Package shall be designed to avoid any hydrocarbon emissions.
Continuous flaring during normal operation is not allowed.
Particular attention shall be paid to prevent vibration of skid mounted pipe work. Adequate
pipe supports shall be provided at suitable intervals to prevent excessive vibration during
operation.
The Vendor shall supply and install insulation and/or protective equipment where required on
all pipe work supplied as part of the package.
The Metering Runs/Streams shall be installed between inlet and outlet headers. Each
metering run shall collectively cover the 50% of the maximum plant flow rate with 10% oversize. Each metering run/stream shall be designed to give a turndown ratio in accordance with

Page: 24 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

document number 1007-DISQ-0-P-DP-48131, Sales Gas Metering Process Data Sheet. Each
metering run/stream shall comprise of one Ultrasonic flow meter (USM), static pressure
transmitter upstream the USM and temperature transmitter with 4-wire PT 100 and head
transmitter downstream the USM, all field instrumentation shall meet the Field
Instrumentations General Specifications and Testing Requirements 1007-DISQ-0-J-SS33010.
The Gas Grid Operations Company requested 73 Diameter straight lengths upstream and
downstream pipe diameter of the USM.
Vendor to submit a comprehensive study on the advantages/disadvantages of installing flow
conditioner/ straightening vanes upstream the ultrasonic meter stating his recommendations
on whether such flow conditioner/vanes should or should not be installed for this application.
Company has the full right in view of this study or based on other technical opinions to decide
whether or not these flow conditioner/straightening vanes shall be installed.
The measuring process should take place in a pipeline of circular cross-section. The duct
cross section uncertainty is a factor in the total uncertainty calculation of the system.
Vendor shall submit detailed data regarding the ultrasonic meters. This data must cover in
detail the following items:

Theory of operation
Calculation of speed of sound, noise level and flow speed covering the flow range
Determination of upstream and downstream straight lengths of flow meter based on
process connections upstream and downstream of metering package, USM
manufacturer recommendation, process connection with other equipment, piping
arrangement and uncertainty requirements
Flow simulation for the package covering the max. flow range
Uncertainty calculation per stream, for different combinations of streams and with all
streams in operation
Detailed procedure of flow calculation for the different operation scenarios.
Data sheet to clarify the material of construction and important data for each part of
the Ultrasonic meter
Detailed study showing the increase of accuracy and advantages gained when
increasing the number of USM transducers and vendor recommendation for the
number of USM transducers (minimum 4-path )
All QC Tests and QC calibration procedures for which the USM will be subject

The Ultrasonic meters shall be approved for use in hazardous area Zone 1 independent of
the Hazardous Area Classification Layout document no. 1007-DISQ-0-F-DW-10012, and
shall have the certification for operation in Sales Gas Metering Stations (SGMSs) for gas flow
measurement equipment as per custody transfer measurement requirements in accordance
with AGA Report 9, Edition 2007.
The centre line of the ultrasonic flow meter shall be within 1% of the pipe centre. The
upstream pipe section adjacent to the ultrasonic meter shall be in accordance with AGA
Report 9, Edition 2007, section 7and the requirements of the USM manufacturer.
The inside surface finish of piping upstream and downstream of the USM shall be 250inch Ra
or better and machined honed.

Page: 25 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

Scope of ultrasonic Vendor shall include supply of upstream calibrated meter tubes and
downstream calibrated meter tubes, as required to guarantee fiscal metering system
uncertainty and requirements of ultrasonic vendor.
It shall be expected for the system to receive entrained liquids deposits.
The ultrasonic flow meters shall operate within the specified operating conditions to meet the
sales gas metering package uncertainty of less than 1% under all operating conditions and
over the whole flow range as permitted under the Gas Sales Agreement between the Seller
and Buyer of the Gas. Swirl and non-uniform velocity profile effects shall be reduced to an
insignificant level by proper installation of the meter.
Calculations necessary to calculate corrected volume, mass flow and energy flow rates shall
be performed by the flow computers and shall be in compliance with the flow equations of
AGA-7.
AGA-8 for the comparison of the meters reported SOS and AGA-10 for speed of sound
computing.
Field devices for flow metering service shall be 4-20mA, HART compatible type transmitters,
intrinsically safe. Field devices shall be wired to the flow computations via dedicated twisted
paired and individually screened and shielded cables.
The gas composition shall be determined by manual sampling and laboratory analysis at
regular intervals. The data will be manually input into the flow computer calculations and
additional online monitored with gas chromatograph from C1 up to C9.
5.2

Piping, Flanges, Gaskets and Bolts

All piping shall be contained within skid edge and shall be fabricated, assembled and secured
in position onto the skid prior to shipment. Process piping systems forming interconnections
between skid mounted equipment shall be designed in accordance with ASME B31.3.
External pipe work connections and pipe connections to all skid mounted equipment such as
gas filter, control valve and shutdown valve shall be flanged in accordance with ASME B16.5
and sized as appropriate to the service design conditions.
All Piping, Flanges, Gaskets and Bolts shall be designed in accordance to document number
1007-DISQ-0-L-SS-39010 Specifications for Piping Material.
The pipe work arrangement and connections to all equipment shall follow recommendations
stated in AGA Report 9, Edition 2007, Section 7 and the manufacturers requirements of the
USM.
Isolation and drain valves shall be provided in piping systems and around equipment in
accordance with the requirements of the applicable design code(s) where required to ensure
safe operation and/or adequate protection of equipment.
5.3

Painting

All equipment shall be painted and coated in accordance with Specification for Painting and
Protective Coatings 1007-DISQ-0-L-SS-39004.
A sufficient quantity of touch-up paint (10%) shall be supplied with the equipment to repair
minor damage to the paint finish after site installation.

Page: 26 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

5.4

Skid Assembly

As far as practical within the limits of manufacture, transportation and installation, all
equipment supplied as part of the Sales Gas Metering package shall be supplied fully
assembled and mounted on a common rigid welded steel skid base-frame calibrated and fully
pre-commissioned ex works in order to minimise site installation and hook-up.
The skid shall be completed with all equipment, interconnecting piping, pipe supports, fittings,
wiring, cabling, junction boxes, panels, metering cabinets as separated items but fully
pretested, instrumentation, control valves, blow down valves and shutdown valves as shown
on the P&ID- Metering Skid 1007-DISQ-0-P-DW-48059. All skid wiring and terminals shall be
labelled and wiring for connections shall terminate in appropriate junction boxes at the edge of
the skid.
In determining the equipment/package skid sizing, the Vendor shall take into account the
maximum permitted limits for road and rail transportation as defined within the material
requisition. The skid shall be suitable for mounting directly onto concrete foundations and the
metering cabinets on cabinet foundations in the equipment room of the control room building
(foundation details layout and dimensions and weight of metering cabinets to be handed over
to civil engineering of building designer).
Provision shall be made for venting of equipment where necessary.
The skid design and layout shall comply with project document number 1007-DISQ-0-M-SS42003, Package Equipment Specification.
5.5

Metering System Design Requirements

The Metering system shall be designed for continuous operation. Central Treatment Plant
(CTP) production will be continuous, 24 hours per day, 365 days per year.
The system shall be designed upon the philosophy of long term, trouble free operation with
minimum downtimes for maintenance only. Functionality for performance monitoring and
validation comparison of all instrumentation including flow meters, temperature and pressure
transmitters shall be included in the Metering system.
The Metering system shall contain diagnostic routines to alert the operator of component
failure, over range operation, invalid metering data and shall raise an individual alarms on the
DCS System.
5.5.1

Transient, Static and RFI Protection

Each element of the metering system shall operate normally and within the same
specifications, when subjected to an RFI test according to IEC 61000-4-3 test level/test field
strength (10 V/m) with a frequency range 26 MHz to 2000 MHz The total effects of the radio
frequency interference shall be equal or less than 0.1% of the output spans, with the
transmitter enclosure cover in place.
The vendor shall describe in his proposal the system transient immunity testing and
certifications that have been obtained.

Page: 27 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

5.5.2

Cabinet Design

The cabinet shall be Rittal type or similar. The cabinet shall include any cable marshalling and
shall be free standing, designed and constructed with sufficient strength and ruggedness to
support the equipment without flexing.
Cable entry to the cabinet shall be from the bottom, with a suitable cable clamping
arrangement and certified method for sealing the cabinet against dust and dirt entry. The
cabinet shall have front lockable doors and a suitable plinth. The cabinet shall be identified
with a nameplate on the front door.
The cabinet shall be supplied with cooling fans if necessary to maintain the cabinet interior
temperature a maximum of 10C above the maximum building environment temperature with
all internal equipment and external loads energised. Fan failures in the cabinets shall be
alarmed.
The cabinet shall be equipped with an internal light and continental 230 Volt, 50Hz, 1Ph, N, PE
outlet socket derived internally inside the metering cabinet from the main power supply input.
For the cabinet Earthing & Bonding Refer to Doc. No. 1007-DISQ-0-E-SS-27023 Electrical
specifications for packaged equipment.
The cabinet wiring shall be sized to suit the individual load requirements. All wiring shall run in
cable trays and cable ducts and transmission cables sized to provide at least 20% spare
capacity.
Adequate segregation shall be provided between the instrument analogue signals, the
instrument digital signals, NON-IS- and IS-Signals and the AC power wiring.
All terminating wiring shall be fitted with crimp tags. Terminals shall be Weidmueller SAKR or
similar knife-edge isolating terminals for incoming/outgoing low voltage/low current signals.
SAK type or similar shall be used for other signals. Fused indicating type terminals (e.g.
Weidmueller AFT or similar) shall be used for power.
The layout and identification of terminals for the field cable terminations shall be on a multicore cable basis, with all spare cores terminated.
5.6

System Software Design Requirement

The Gas Metering system software shall monitor the flow, pressure and temperature s of each
Metering Run/Stream. The software shall be able to calculate e.g. all other parameters,
convert uncorrected into corrected gas figures and shall be able to monitor and diagnose the
each meter stream and the whole system in accordance with AGA Report 9, Edition 2007
relevant sections.
The software shall be able to carry out the Performance QC test, Verification and Validation
process on a routine basis and if and when required by metering focal point of operations
company. Any changes in composition data shall be manually input into the system when
identified.
All measured, calculated and diagnostic data for each Metering Run shall be monitored by
DCS System via redundant Fibre optic cores links (FOC). The interface shall be redundant
and fully compatible with the selected DCS System.

Page: 28 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

5.7

Noise Limitations

The overall Sound Pressure Level from the package shall not exceed 80 dBA at 1 metre
distance from the skid edge. If necessary noise control measures shall be applied to the
equipment by the Vendor to ensure that these limits are adhered to. Where noise control
measures such as acoustic insulation or acoustic enclosures are required, these shall be
provided by the Vendor. These enclosures shall be easily removable without the need to
dismantle any part of the equipment or otherwise shall not obstruct operational or routine
maintenance activities.
The VDRF will require the vendor to confirm the predicted sound power level and maximum
overall sound pressure level in accordance with Noise Control Specification document number
1007-DISQ-0-F-SS-10018 and Egyptian environment law 04/2011, appendix 7.
5.8

Utilities

The design shall conform to the available site utilities and respective Utility Conditions
detailed in the process data sheets 1007-DISQ-0-P-DP-48131.
5.9

Material Certificate to Conformance (C&C)& Traceability

All field instrumentation shall be supplied with valid calibration certificates. The Vendor shall
provide (C&C) to ensure appropriate manufacturing systems and procedures are used to
ensure full traceability of materials (see Quality Assurance Plan, requirement No. 22). During
manufacture each assembled component shall be clearly and permanently marked in order
that it can be traced back to the originally supplied material certificate and its origin
determined.
5.10 Name plates
The Ultrasonic meter and all field instruments shall be equipped with a manufacturers
nameplate of 316 stainless steel permanently attached with stainless steel screws or rivets
indicating the specified data. In addition to specified data the following data shall be provided
which is a minimum:

Tag number
Serial number
Model number
Direction of flow
Flow Range
Number of Paths
Purchase Order Number
Manufacturers Name
Year of Manufacture
Other important design parameters ( e.g. medium and ambient operating temperatures )
Ingress Protection
Hazardous Area classification and certificate number

Page: 29 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

5.11 Climate Condition


The Sales Gas Metering Package shall be suitable to operate in the north delta climate
conditions as per Environmental Data and Units of Measurement, document number 1007DISQ-0-M-RT-42015.
The metering system shall be installed in the equipment room of the control room building with
the following conditions:
Normal HVAC conditions:

Temperature 22 C +/- 2 C.
Relative Humidity 40% to 60%

Design conditions:

Temperature 45 C.
Relative Humidity 80%

Electrical Requirements

6.1

General

Electrical equipment shall be provided in compliance with the codes & standards and in
accordance with Doc. No. 1007-DISQ-0-E-SS-27023 Electrical Specifications for Packaged
Equipment.
The insulating and dielectric materials used in all electrical equipment shall be non-toxic and
shall not contain components that are persistent and/or hazardous environmental
contaminants.
The design of the electrical installation and equipment shall ensure that easy and adequate
access is provided for all operational and maintenance purposes.
6.2

Power Supply Voltages

Refer to Doc. No. 1007-DISQ-0-E-SS-27023 Electrical Specifications for Packaged


Equipment.
6.3

Hazardous Area Requirements

Refer to Doc No. Document No. 1007-DISQ-0-F-DW-10012 Hazardous Area Classification


Layout.
6.4

Certifying Authorities

Refer to Doc. No. 1007-DISQ-0-E-SS-27023 Electrical Specifications for Packaged


Equipment.
6.5

Ingress Protection for Electrical Equipment

Refer to Doc. No. 1007-DISQ-0-E-SS-27023 Electrical Specifications for Packaged


Equipment.

Page: 30 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

6.6

Cabling

Refer to Doc. No. 1007-DISQ-0-E-SS-27023 Electrical Specifications for Packaged


Equipment.
6.7

Equipment Earthing & Bonding

Refer to Doc. No. 1007-DISQ-0-E-SS-27023 Electrical Specifications for Packaged


Equipment.

Page: 31 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

Installation, Operation and Maintenance

7.1

Installation, Pre-commissioning and Commissioning

All installation, Pre-commissioning, commissioning and operating instructions for electrical,


instrument and mechanical equipment shall be included and indexed in the Installation, Precommissioning, Commissioning and Operating Manuals for the sales gas package in
accordance with Contract requirements as described in the Requisition.
The Vendor shall ensure that sufficient qualified personnel are at all times allocated to the
project. The Installation of the sales gas package shall be carried out with the assistance and
under supervision of the Vendor representative, any special tools required for installation, start
up, Pre-commissioning and commissioning and acceptance QC tests shall be provided by
Vendor.
7.1.1

Start-Up, Pre-commissioning and Commissioning Services

The Vendor shall provide services related to the Pre-commissioning, Commissioning and
Start-up of the Package equipment which shall include, but not be limited to, the following:

Verify proper package system components and installation


System power up
Perform diagnostics on all package components
Verify metering and control system
Verify overall integrity of the package system and the integrity with the ICSS as well
Verify proper package system operation
Submit detailed installation, start-up, Pre-commissioning, commissioning and
acceptance QC test reports for the sales gas package system and individual items as
required

All QC test and QC verification equipment shall be provided by Vendor.


7.2

Maintainability

The package shall be arranged to allow sufficient access for maintenance and operation. The
layout of the package shall reflect a compact ergonomic design with adequate spacing
between adjacent equipment and pipe work. The assembled skid shall be supplied with all
required access platforms, valves and instruments for safe operation and routine maintenance.
Adequate withdrawal space and/or removable pipe spools shall be provided, where necessary,
to permit removal and replacement of major components of the package.
Piping shall be arranged and supported so that the identified equipment maintenance items
can be removed without dismantling surrounding equipment other than removing spool pieces
adjacent to equipment connections.
All valves shall be located and arranged for operation from suitable access platforms or from
ground level.
The Vendor shall supply necessary special tools (i.e. withdrawal tools and associated cradles
as required) to enable periodic maintenance.

Page: 32 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

Instrumentation supplied with the equipment shall be located to permit easy access for
operation and maintenance.
7.3

Calibration

Ultrasonic Meters and Secondary Devices shall be QC calibrated as follows:


7.3.1

Ultrasonic Meters Calibration

Calibration of Ultrasonic Meter shall be calibrated at a certified High Pressure Calibration


Facility against a certified master meter with certified calibration and accuracy. The calibration
rig shall be approved by a recognized "Office for Weights and Measurements".
The Range ability of the Ultrasonic meter shall be > 100: 1.
QC Calibration shall be done in accordance with AGA Report 9, Edition 2007 and section 6 in
minimum.
The Vendor shall provide Ultrasonic meter calibration procedures and package calibration
procedures for company review and approval.
The individual meter and metering package performance and calibration curves, accuracy and
uncertainty shall be recorded. These records are an integral part of the documentation.
7.3.2

Secondary Devices

All secondary devices shall be delivered with valid calibration certificates. Adjustments to the
Pressure transmitter can be made on site but these should be limited to the zero and span
adjustments.
Temperature shall be measured by means of 4-wire PT100 which shall be connected to the
flow computer by temperature transmitter with head transmitter and two wire 4-20mA IS signal
which shall be HART compatible.
The output current of all instruments operating on a 4-20mA loop shall be checked by
measuring the output voltage across a precision resistor (+0.01%).
Analogue to digital converters are tested either by internal circuitry in the flow computer or by
measuring the voltage across a precision resistor with an applied current.
The calculation software of each flow computer must be checked and validated periodically.
The validation test software has to be supplied by the vendor.
7.4

Special Tools

All special tools, software and hardware required for the installation, adjustment, Precommissioning, commissioning, operation, validation, calibration and maintenance shall be
included in the Vendors scope of supply.
This shall also include any special lifting devices required for site installation of the equipment.
7.5

Spare Parts

All spare parts necessary for the construction, Pre-commissioning, commissioning and start up
on site shall be provided by the Vendor with the package, unless otherwise specified in the
purchase order. The spare parts for two years operation may be purchased separately from
the main equipment supplier unless otherwise specified in the purchase order. They shall be

Page: 33 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

listed (as per Vendor recommendation with the turn over methodology) and quoted separately
from the main equipment as optional item.
7.6
7.6.1

Training
Training Philosophy

Vendor shall provide formal training both on site and at the Vendor facility for Company
personnel.
7.6.2

Training Course Documentation

For each trainee who will attend a training course, a copy of the complete training course,
material, notes, and drawings shall be provided to Company one week prior to the
commencement of the training course. The copies shall be retained by the trainees on
completion of the training course and an original copy shall be the property of Company.
7.6.3

Operator Training Course

Operator manuals shall be made available to Company prior to this course.


7.6.4

Maintenance Training Course

The course purpose is to train technicians, operators and engineers for first line fault
diagnosis and repair.
7.6.5

System Configuration Course

The purpose of this training course is to enable Company personnel to be able to


understand and modify system configuration control and sequencing.
The Vendor shall recommend the location for this training in coordination with the company.
7.6.6

Training Aids

The Vendor shall list training aids required for above courses.

Page: 34 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

Preparation for Shipment

All equipment shall be supplied fully assembled wherever and whenever possible. In order to
minimise the installation and pre-commissioning time at site, the equipment shall be suitably
packed ready for shipment. The Vendor shall also include adequate protection and
preservation for a minimum of six months outdoor storage from delivery to site. All necessary
temporary supports and other facilities shall also be provided to enable the equipment to be
securely anchored during transport.
Each equipment item shall be clearly identified on the outside of the packing with a description
and tag number so that any packaging doesnt need to be removed until such time as the
equipment will be required to be installed.
Spare parts shall be individually packed for long term storage. All exposed or loose parts shall
be completely boxed with identification tag. Gaskets supplied by the fabricator shall be new;
gaskets used for shop hydrostatic test are not acceptable.

Quality Assurance & Health, Safety and Environment

The Vendor and his Sub-Suppliers shall maintain be certified and maintain active BS EN ISO
9001:2008 certificate Quality Management Systems Requirements and in accordance with
Disouq Project Quality Plan and its Quality Assurance Plan and the Minimum Quality Audit
Surveillance Requirements document.
Also, the Vendor and his Sub-Suppliers shall be certified and maintain active ISO14001:2004
and OHSAS18001:2007 certificates
These integrated management Systems shall be adopted by the Vendor throughout the
various phases of the project (Engineering, fabrication, assembly, QC testing and Inspection).
The Vendor shall manage and implement the work in accordance with good management
practice, covering engineering, purchasing, expediting, fabrication and QC testing in respect of
the applicable regulations, Codes and Standards.
9.1

QC Factory QC Acceptance Test (FAT)

The Vendor shall perform inspection and testing at his shop in the presence of Company
and/or its representative prior to shipment. Vendor shall be fully responsible for the complete
design, fabrication, integration, QC inspection and testing of all the Gas Metering system
components in accordance with AGA Report 9, Edition 2007 in minimum.
The Vendor shall perform a complete functional QC test of all the Gas Metering system
components before making the equipment available for the witnessed Factory QC Acceptance
Test (FAT). The FAT shall comprise testing of the performance of the Gas Metering system,
with simulated instrument inputs.
All QC testing will be conducted in accordance with test procedures. The vendor shall furnish
the QC test procedures to the Purchaser for review at least 2 months prior to the FAT.
The vendor shall supply, at his cost, all necessary test equipment, tools, cables and personnel
for the duration of the QC tests. The system workstation, communication links and all other
accessories shall be thoroughly QC tested to verify complete conformance with the scope of
work and the project requirements.

Page: 35 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

The vendor shall supply all QC test equipment conforming to the relevant standards and
traceable. Prior to testing the vendor shall provide valid certificates to confirm calibration of QC
test equipment.
The FAT shall be performed at the Vendors facilities with a comfortable work environment and
easy access to all equipment.
A QC test log shall be maintained by the vendor to keep record of all tests carried out, any
fault, rectification work done, etc..
As minimum the FAT shall include the following:

Verification that the system is physically complete, in accordance with the project
material requisition
Verification that the system has been assembled in accordance with the requirements of
this specification and the approved Vendor drawings
Functionality QC testing to verify that the hardware and software configuration can
perform all functions required by this project.
All system inputs and outputs shall be simulated to determine the correct functionality of
the system. This includes all FOC links, links to gas grid operator and hardwired signals
from/to ICSS and to gas grid operator.
Complete hardware QC testing (flow computers, supervisory computer, instruments,
power supplies, I/O signals, all communication modules to/from ICSS, ESD signals
to/from ICSS, all interfaces to the Gas Grid Operator Company etc.), observation of fault
reporting via hardware indicators and data transfers, and online component replacement.
Verification of diagnostic software.
Verification that all system interfaces function correctly and reliably including FOC
interfaces with the control and monitoring system.
Verification of the serial numbers of all major components.
Verification of total uncertainty of sales gas metering package in different operating
modes

The vendor shall at an agreed stage of the project prior to FAT, demonstrate the ability of the
Metering System to communicate with other systems such as ICSS and SCADA of Gas grid
operator via the dedicated interfaces. The Vendor shall include in the quotation, a detailed
proposal of how this will be achieved. The stage and integration requirements shall be
indicated on the fabrication, QC inspection and test plan to be submitted by the vendor for
review. It shall be the Vendors responsibility that all interfaces function correctly.
Any system components that fail during any phase of the QC testing shall be replaced not
repaired, without cost compensation.
Radio Frequency Interference QC Test shall be carried out with the cabinet doors open using
an RFI source and covering frequency levels to be specified during design. This shall not
interfere with the normal operation of the system and should not trigger any alarm when the
receiver is activated.
Deficiencies noted during QC FAT shall be corrected during the test and fully retested to
company satisfaction. Any outstanding items that cant be rectified and retested in the agreed

Page: 36 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

FAT time scale shall be rectified at site and retested during SAT at the Vendors cost.
Certification of completion of QC FAT including a list of outstanding deficiencies shall require
signature by the Company.
QC Non Destructive Examination (NDE) shall be carried out in accordance with applicable
referenced codes and standards.
The vendor is to propose arrangements for QC testing, checking repeatability/accuracy and for
providing information detailing calibration and traceability to a recognised and agreed
Authority.
Company reserves the right to inspect all stages of manufacturing/assembling/ QC testing of
the equipment package at Vendor/Sub-Vendor shop.
Company shall have the right to reject any equipment non-conforming to the purchase order
and referenced specifications.
The Vendor shall carry out all specified QC testing and inspection required by contractual
documentation, specifications, applicable codes & standards and the manufacturers quality
management system. The Vendor shall retain all required records and documentation
pertinent to these activities.
Acceptance criteria of QC tests, when not defined by the applicable codes, shall be specified
by the Vendor in the Vendor Quality Control/Assurance Plans and/or QC test procedures and
shall be sent to Company for review.
9.2

QC System Integration Test (SIT)

The purpose of the QC System Integration Test (SIT) is to check for the correct operation and
function of FOC communications links and all hardwired signals between the Metering System
and the ICSS System. The SIT shall also include the test of the all signals transfer and
communications links with the Gas Grid Operator. SIT to be performed as part of the QC
FAT.
The SIT shall be carried out at the Metering System Vendors premises. The system shall be
connected in a manner identical to that which will exist on site and shall use the same system
configuration and software that will be used on site.
A detailed QC system integration test procedure for the SIT shall be provided as part of the
detailed design documentation of the sales gas metering package. The QC SIT procedure
shall be agreed between Metering Vendor and Control System Vendor to ensure all interfaces
will be QC tested and fully operational when the SIT has been completed and QC test reports
signed off by the metering vendor, the ICSS vendor and the company or its representative.
9.3 QC Site Acceptance Test (SAT)
As minimum the QC SAT shall include the following:
A complete audit of all equipment to verify that it has been received and does not have
any mechanical damage, loose parts, etc.
Verify that agreed minor outstanding items noted during QC FAT and QC SIT have been
corrected and tested.
Verification that the installation meets the Company specifications.
Verification that all equipment is fully functional tested.

Page: 37 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

Verification that all communication links and interfaces operate correctly and have
successfully passed the QC SAT and the QC SIT on site.
Complete system power-up and testing of all network equipment, including the test of all
interfaces with SCADA system of Gas Grid Operation Company.

Finally Metering Run test with product as part of the final SAT. The SAT shall be completed
only with full operational test when gas plant brought into production with all relevant parties
and authorities present to sign off the final QC Site Acceptance Test Procedure after
completion of the final performance test.
9.4

Ultrasonic Meter Inspection

As a minimum all ultrasonic shall be inspected by a 3rd party during FAT to ensure compliance
with all approved calculations, documentation and material certifications.
The Meter Tubes shall be subject to a full hydrostatic pressure test in accordance with
ASME B31.3.

Page: 38 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

10 Vendor Data Requirements


The Vendor data requirements shall be as specified on the Vendor Data Requirements Form
(VDRF) attached to the Material Requisition. The required number of reproducible and copies
shall be as specified.
An installation, operating and maintenance manual (IOM) and manufacturers record book
(MRB) shall be provided as detailed in the material requisition..
10.1 Functional and Detail Design Specification (FDS and DDS)
Vendor shall provide FDS and DDS for the Metering System. The FDS shall precisely define
the hardware and the software proposed and shall be in sufficient depth. The Detail Design
specification shall be fully detailed. The FDS and DDS shall include, but not be limited to the
following:

Component selection.
System details.
Proposed hardware and software configuration details.
Communication and hardwired interface details.
System capacity, constraints and options.
System diagnostics details.
Bill of Materials.
Sizing Calculations.
Uncertainty Calculations.
Ultrasonic Meter Data Sheets
System power consumption and heat load calculations.
Power distribution within the system with electrical single line diagrams.
Documentation schedule.
Production schedule.
Drawings (e.g. wiring drawings, etc.).
Technical Description with principle of operation and installation instructions.
Operating and Maintenance Manuals for each Equipment
Outline Dimensions
Assembly Drawing - Ultrasonic Meter Run with all installed Equipment.
Explosions Drawings with mechanical details and part numbers.
Total spare part list.
Maintenance Procedures.
Calibration and Settings Procedures.
Calibration and Material Certificates.
QC FAT proposals and test plans.
QC SIT proposal and test plans.
QC SAT proposals and test plans.
QC Test Reports.

Page: 39 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

All above mentioned documents shall be in English Language as specified. Before starting any
of the proceeding activities, the vendor shall acquire the approval of the submitted documents.

Page: 40 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

List of Abbreviations
Abbreviation
AC
AGA
AGC
AI
AISI
AO
ANSI
API
ASME
ASTM
ATEX
BS
CCR
C&E
CHV
CTP
dB(A)
DC
DCS
DDS
DIN
EEMUA
EGAS
EI
EIA
EN
ESD
FAT
FDS
FEED
F&G
FOC
GASCO
GUI
HART
HAZOP
HVAC
HH

Description
Alternating Current
American Gas Association
Automatic Gain Control
Analogue Input
American Iron and Steel Institute
Analogue Output
American National Standards Institute
American Petroleum Institute
American Society of Mechanical Engineers
American Society of Testing and Material
Atmospheres Explosibles
British Standard
Central Control Room
Cause and Effect
Choke Valve
Central Treatment Plant
Decibels (A weighted average value)
Direct Current
Distributed Control System
Detail Design Specification
Deutsches Institut fr Normung
Engineering Equipment and Materials Users Association
Egyptian Natural Gas Holding Company
Energy Institute
Electronic Industries Association
European Norm
Emergency Shut Down
Factory Acceptance Test
Functional Design Specification
Front End Engineering Design
Fire and Gas
Fibre Optic Cable
Egyptian Natural Gas Company
Graphical User Interface
Highway Addressable Remote Transmitter
Hazard and Operability
Heating, Ventilation and Air Conditioning
High High

Page: 41 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

HP
HPU
IEC
IEEE
ICSS
I/O
IP
IS
ISA
ISO
LER
LL
LP
LMV
MSS
MTBF
MTTF
MTTR
MV
MWP
NACE
NAS
NDE
NPS
NEMA
NFPA
NPT
OWS
PCN
PFD
P&ID
PSD
PT
PTFE
PVC
Ra
RF
RFI
RTU
SAT

High Pressure
Hydraulic Power Unit
International Electro-technical Commission
Institute of Electrical and Electronics Engineers
Integrated Control and Safety System
Input/Output
Ingress Protection
Intrinsic Safety
International Society of Automation
International Organisation for Standardization
Local Equipment Room
Low Low
Low Pressure
Lower Master Valve
Manufacturers Standardization Society of the Valve and Fittings Industry
Mean Time Between Failures
Mean Time To Failure
Mean Time To Repair
Master Valve
Maximum Working Pressure
National Association of Corrosion Engineers
National Aeronautical Society
Non Destructive Examination
Nominal Pipe Size
National Electrical Manufacturers Association
National Fire Protection Association
National Pipe Threads
Operator Work Station
Process Control Network
Process Flow Diagram
Piping and Instrument Diagram
Process Shut Down
Pressure Transmitter
PolyTetraFluoroEthylene
Polyvinyl Chloride
Radius Absolut
Raised Face
Radio Frequency Interference
Remote Termination Unit
Site Acceptance Test

Page: 42 of 43

Onspec Engineering Solutions


Disouq Field Development Project
Specification
Sales Gas Metering Package

SAW
SS
SSSV
SCSSSV
SDV
SGMS
SI
SIL
SIT
SOS
TIA
TT
TV
UCP
UPS
USM
UMV
VDRF
VOS
WHPHU
WHCP
WHOP
WV
QA
QC
MSDS

Submerged Arc Welded pipe


Stainless Steel
Sub-Surface Safety Valve
Surface Controlled Sub-Surface Safety Valve
Shutdown Valve
Sales Gas Metering Stations
international System of Units
Safety Integrity Level
System Integration Test
Speed Of Sound
Telecommunications Industry Association
Temperature Transmitter
Technischer berwachungs-Verein
Unit Control Panel
Uninterruptible Power Supply
Ultrasonic meter
Upper Master Valve
Vendor Data Requirements Form
Velocity of Sound
Well Head Pneumatic Hydraulic Unit
Well Head Control Panel
Well Head Operators Panel
Wing Valve
Quality Assurance
Quality Control
Material Safety Data Sheet

Page: 43 of 43

Вам также может понравиться