Академический Документы
Профессиональный Документы
Культура Документы
Suo-Motu
In the matter of determination of generic tariff for sale of electricity from wind
power plants in the state to Distribution Licensee for FY 2012-13.
Coram:
1. Shri D.C. Samant, Chairman
2. Shri S.K.Mittal, Member
3. Shri S.Dhawan, Member
Date of hearing
12.07.2012
Date of order
07.09.2012
Order
1.
2.
The RERC Tariff Regulations, 2009 provide for terms and conditions for
determination of generic tariff for wind power projects to be
commissioned during the Control Period of FY 2009-10 to FY 2013-14,
based on the parameters outlined in Part VII of these Regulations.
Commission had recently issued Fourth Amendment in RERC Tariff
Regulations, 2009 vide Notification dated.18.05.2012.
3.
4.
09.06.2012
Rashtradoot
09.06.2012
09.06.2012
Page 1
Public notices along with the draft order were also placed on
Commissions website.
5.
6.
7.
8.
9.
(1)
(2)
(3)
(4)
(5)
(6)
Page 2
(2)
(3)
(4)
11.
(5)
(6)
The GERC model for solar tariff may be adopted and for initial
period, a low tariff may be given, which may be gradually
increased.
The Generation Based Incentive (GBI) was available for the wind
turbines commissioned after the issue of the scheme for
implementation of GBI for Grid interactive wind power projects
issued by Ministry of New & Renewable Energy (MNRE), GoI, vide
letter dated 17.12.2009 and before 31.03.2012.The duration of
scheme has not been extended so far. As per clause 4.6 of the
Page 6
scheme, this incentive is over and above the tariff that may be
approved by the State Electricity Regulatory Commission. In other
words, this incentive is sanctioned by the Union Government to
enhance the availability of power to the Grid and is not be taken
into account while fixing tariff by the State Regulators.
(3)
Reducing GBI from the tariff would render the GBI scheme itself
meaningless. Further, if GBI is reduced from the tariff, none of the
investors would want to get into the effort and expenses towards
availing this incentive.
(4)
(5)
(6)
(7)
GBI sharing. Yet another suggestion for GBI was that it should be
adjusted in tariff only in project specific tariff.
(8)
13.
Page 8
(2)
(3)
(4)
(5)
(6)
JVVNL and AVVNL stated that clarification for providing basis for
applying preference is required specifically through an example, if
there are two generators providing wind power, one based on
higher depreciation and another one without higher depreciation,
and if the RPO has not been met then in that case how should
Page 9
(2)
(3)
(4)
(5)
(6)
(7)
(8)
While entering PPA with wind generator for RPO, Discoms may
consider normative generation by considering CUF 20% or 21% as
the case may be. It should also be clarified that distribution
Page 11
Page 13
19.
(2)
(3)
(4)
Page 15
Other Suggestions:
(1) RVVS suggested that it may be advisable to prescribe a standard
Format which should be annually furnished by the Developers to
the Distribution licensee ensuring the disclosure of any policy/
capital finance assistance or higher depreciation benefit etc. The
Page 16
The levelised generic tariff for wind power projects for FY 2012-13.
22.
The levelised generic tariff for wind power plants, getting commissioned
during FY 2012-13, has been worked out based on operational and
performance parameters as specified under Regulation 83(6) of RERC
Tariff Regulations, 2009 and the Financial Principles as stipulated under
Part III of RERC Tariff Regulations, 2009, read with Fourth Amendment
finalised vide Notification dated 18.05.2012. The parameters adopted
in this order have been discussed in the following sub-paras.
Debt-Equity Ratio
(1) The Debt-Equity ratio of 70:30 as envisaged at regulation 17 of RERC
Tariff Regulations 2009 has been taken for working out the debt and
equity components of normative capital cost for determination of
levelised generic tariff.
Capital Cost
(2) Capital cost of Rs 530 Lacs/MW, including connectivity charges (of Rs.
2 Lacs/MW) and cost of evacuation network (Rs 15 Lacs/MW) as per
sub-regulation 6(b)(i) of RERC Tariff Regulations 2009, has been taken
for FY 2012-13.
Capacity Utilisation Factor (CUF) & de-ration in CUF
(3) Regulation 83(6)(b)(ii) of RERC Tariff Regulations 2009 provides for CUF
of 21% for Jaisalmer, Jodhpur and Barmer districts and 20% for other
districts. Further, regulation 83(6)(b)(iii) also stipulates a de-ration of
1.25% from 6th ,10th, 14th & 18th year in the above CUFs. Accordingly,
CUFs along with de-ration have been taken.
Operation & Maintenance Expenses
(4) O&M expenses have been taken as 1.25% of capital cost for power
plant and 3% of cost of transmission line in accordance with
Regulation 83 (6)(b)(iv) of RERC Tariff Regulations,2009.
Depreciation
(5) In accordance with regulation 83(6)(b)(vi) of RERC Tariff Regulations
2009, the rate of the depreciation has been considered as 5.28% of
the total project cost for the first 12 years and remaining depreciable
value has been spread over the balance useful life of the power
project and transmission system.
Page 18
Page 19
24.
In light of the above position, the levelised generic tariff applicable for
wind power plant for FY 2012-13 has been determined as under:
S.
No.
Particulars
Tariff (Rs/kWh)
if higher
depreciation
benefit is not
availed
3
Tariff (Rs/kWh) if
higher
depreciation
benefit is
availed
4
5.18
4.89
5.44
5.13
Page 20
27.
28.
A generator claiming the higher tariff worked out as above for projects
not availing higher depreciation benefit would have to furnish an
undertaking in advance to the buyer regarding higher depreciation
benefit not being availed and this would have to be followed for each
financial year.
Similarly, annual undertaking would need to be
furnished if CDM benefit is not availed. However, if CDM benefit is
availed, it would have to be shared with distribution licensee as
envisaged in applicable Regulations.
29.
30.
(S. Dhawan)
Member
(S.K. Mittal)
Member
(D.C. Samant)
Chairman
Page 21
Annexure-III
List of Stakeholders who submitted their comments
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
M/s CLP Wind Farms (India) Private Limited (CLP India), Mumbai
M/s Indian Wind Power Association(IWPA), Jaipur
M/s ReGen Powertech Pvt. Ltd.(REGEN), Chennai
Shri Bal Mukund Sandhya, Director, Samta Power, Jaipur
M/s Acciona Energy India Pvt. Ltd.(Acciona Energy), Bangalore
M/s Enercon (India) Limited(EIL), Jaipur
Shri P. N. Mandola, Committee for Protection of Public Properties,
Jaipur
M/s Indian Wind Energy Association(InWEA), New Delhi
M/s Eoxis Renewable Energy India Private Limited(EOXIS),
Mumbai
M/s South Asia Energy Policy, Bangalore
M/s Power & Energy Consultants(PEC), Delhi
M/s INOX Renewables Limited, Noida
M/s ReNew Power Ventures Pvt. Ltd.(ReNeW), Gurgaon
M/s Green Infra Limited(Green Infra), New Delhi
M/s Tanot Wind Power Ventures private Limited(TANOT POWER),
Hyderabad
M/s Greenergy Renewables Pvt. Ltd., Mumbai
M/s Torrent Power Limited(Torrent Power), Ahmedabad
Superintending Engineer (RDPPC), Ajmer Discom
M/s Rajasthan Vidhyut Vikas Sansthan(RVVS), Jaipur
M/s Indian Wind Turbine Manufacturers Association(IWTMA),
Chennai
M/s CVK Solar Enterprises(CVK Solar), Jaipur
Jaipur Vidyut Vitran Nigam Limited, Jaipur
Page 22
Annexure-IV
List of Stakeholders present during the hearing
Page 23