Вы находитесь на странице: 1из 19

EASTERN MAINE MEDICAL CENTER

DESIGN BASIS DOCUMENT


(Abridged Version)
For the

Combined Heat and Power Cogeneration Plant


Eastern Maine Medical Center
489 State Street
Bangor, Maine 04402-0404

R.G. Vanderweil Engineers, Inc.


274 Summer Street
Boston, MA 02210-1128
Vanderweil Project NO. 22651

Rev. Description Written By: Approved By: Date


Vanderweil Engineers EMMC/Cianbro
A Issued For Bid B. A. Bennett 09/30/04
B Website Version B.A.Bennett 12/05/05
TABLE OF CONTENTS

SECTION I ..........................................................................................................................2
INTRODUCTION .................................................................................................................2
SECTION II ........................................................................................................................3
GENERAL PROJECT DESCRIPTION .................................................................................3
SECTION III.......................................................................................................................4
OBJECTIVES ...........................................................................................................................4
SECTION IV .......................................................................................................................5
FUNCTIONAL REQUIREMENTS........................................................................................5
SECTION V.........................................................................................................................8
OCCUPANCY REQUIREMENTS) .......................................................................................8
SECTION VI .......................................................................................................................9
PERFORMANCE REQUIREMENTS .............................................................................................9
SECTION VII....................................................................................................................13
ENVIRONMENTAL QUALITY ...........................................................................................13
EXHIBIT A........................................................................................................................14
EMMC DESIGN STANDARDS ...........................................................................................14
EXHIBIT B........................................................................................................................15
HEAT BALANCE DIAGRAMS FOR CHP OPERATION ................................................................15
EXHIBIT C........................................................................................................................16
CHP PLANT SEQUENCE OF OPERATIONS (LATER) ......................................................16
EXHIBIT D........................................................................................................................17
NATURAL GAS SPECIFICATION ..............................................................................................17
EXHIBIT E........................................................................................................................18
DRAWINGS .........................................................................................................................18

Eastern Maine medical Center TABLE OF CONTENTS


Design Basis Document
CHP Cogen Plant 1
DESIGN BASIS DOCUMENT
(Abridged Version)
For the
CHP Cogeneration Plant
Eastern Maine Medical Center

SECTION I

INTRODUCTION

This Design Basis Document (DBD) establishes the design criteria for the new Combined Heat
and Power Cogeneration Plant (the CHP) at the Eastern Maine Medical Center (EMMC) Campus
(the Campus) in Bangor, Maine, and outlines the system design, equipment and component
design features and performance characteristics consistent with that design criteria. The DBD is
intended to fix the plant design and create the framework for the detailed design, construction
documents and construction specifications. The DBD represents the objectives of Vanderweil
Engineers (VE) and its sub-consultants, CIANBRO Corporation (CIANBRO) and EMMC in
terms of design features, modularity, systems functionality and performance.

The DBD serves to ensure consistency in project intent throughout the detailed design and
development of construction documents through construction, commissioning and long-term
plant operations. The DBD ensures that EMMC’s requirements for CHP performance and quality
of construction are met. The DBD translates the project intent into specific technical and
contractual requirements for the Designer, Contractor and equipment Suppliers.

The DBD that follows provides an abridged description of the CHP, and provides design details
for systems and equipment that embody EMMC’s objectives in terms of the functional uses of the
CHP. The DBD establishes quality of materials and construction, occupancy requirements,
performance, environmental requirements and acceptance criteria for the CHP.

Eastern Maine Medical Center SECTION I


Design Basis Document Introduction
CHP Cogen Plant 2
SECTION II

GENERAL PROJECT DESCRIPTION

The CHP is intended to meet most of the near-term electrical demand and a portion of the high-
pressure steam demand on the Campus through cogeneration - the simultaneous production of
electric power and steam.

The new CHP is located east of the Maintenance Garage, about 100 feet from the existing steam
plant. The CHP comprises a nominal 4.6 MW gas turbine module with heat recovery steam
generator (HRSG), together with auxiliary systems and ancillary equipment necessary to provide
steam and electricity for the campus. The modular HRSG, matched to the gas turbine, delivers
approximately 23,000 lb/hr of steam at 110 psig/344 oF outlet steam conditions. The CHP will
supplement the existing firetube boilers, designed to deliver up to 42,000 lb/hr of steam at header
pressure conditions of approximately 100 psig/338 oF. The gas turbine is designed to fire either
natural gas or transportation grade fuel oil. The HRSG is unfired.

The CHP connects to the existing campus steam distribution system, at the existing steam plant.
Steam is distributed throughout the hospital Campus at approximately 100 psig (high pressure
steam, HPS). Condensate is returned to the existing steam plant and collected in a condensate
receiver. From the receiver, hot condensate is pumped to an existing deaerator to complete the
steam cycle. The deaerator drains into a piping header to supply the existing boiler feed pumps. A
branch connection in each of these steam and feedwater headers will accommodate new steam
and feedwater piping to and from the CHP. This will maximize the use of existing infrastructure.

Cogen plant equipment is arranged in a modular fashion within a new building to provide
operators with a single point of control for monitoring Campus steam production (see General
Arrangement Drawings).

The design philosophy described above allows construction of this facility and interconnecting
piping independent of the existing steam plant up to the tie-in points.

The combustion turbine, heat recovery boiler, control room and other spaces and auxiliary
equipment are housed in a new steel framed building. The building is designed to be compatible
with the campus environment and adjacent buildings. The building retains a low profile.
Outdoor equipment and utilities are oriented to face away from adjacent neighborhoods, the
campus community, and adjacent roadways. Existing trees and earthen banks provide screening
elements. Building drainage and storm water run-off will be directed to new drain manholes.

Natural gas is the primary fuel for the gas turbine. Transportation grade No. 2 fuel oil is the back-
up fuel for the gas turbine and the primary fuel for the packaged boilers. EMMC will separately
contract with Bangor Gas for permitting and development of the high pressure gas pipeline to the
CHP.

Eastern Maine Medical Center SECTION II


Design Basis Document General Project Description
CHP Cogen Plant 3
SECTION III

OBJECTIVES

1 Project Objectives

EMMC has several key objectives for this project which include:

1.1 That all contractual obligations of the Designer and Contractor are met.
1.2 That the project is completed and operated in compliance with the conditions of
state and local permits.
1.3 That design and operation of the CHP minimizes any potential impact to the
hospital campus (the Campus) and adjacent neighborhoods.
1.4 That the CHP and related ancillaries generally comply with the EMMC Board-
approved Total Project Cost Estimate for the CHP. Deviations from this plan will
be documented, justified and subject to EMMC-Board approval.
1.5 That the “power island” comprising gas turbine and heat recovery steam generator
are designed as modules for integration at similar CHP Energy Projects.
1.6 That quality processes are enabled by all project team members to eliminate
problems and to ensure that errors are corrected prior to becoming problems.
1.7 The project is constructed safely with a goal of zero OSHA recordable events
throughout construction and start-up.
1.8 That systems operation and levels of quality are verified and documented during
construction, start-up, and commissioning.
1.9 That the gas turbine and heat recovery steam generator are operational within 16
months after CON and EMH Board approval.
1.10 That a 100% acceptance rate is achieved on start-up and commissioning,
performance and emissions tests.

Eastern Maine Medical Center SECTION III


Design Basis Document Objectives
CHP Cogen Plant 4
SECTION IV

FUNCTIONAL REQUIREMENTS

1 Architecture

2 Civil/Structural Building Systems

3 Operator Safety Systems

4 Combustion Turbine-Generator System

Table 1
CTG Performance and Emissions Guarantees
Natural Gas

Ambient Full Load Heat Rate, Exhaust Exhaust Emissions, ppmvd Emissions,
Temp., Output, Btu/kWhr Gas Flow, Gas Corrected to 15% O2 lb/hr
o
F kWe (LHV) lb/hr Temp.,
o
F

NOx CO UHC PM/P SOx


M10
Total
59 4,294 12,306 144,000 960 25 50 25 0.0419 None

Table 2
CTG Performance and Emissions Guarantees
Low Sulfur Diesel Oil

Ambient Full Load Heat Rate, Exhaust Exhaust Emissions, ppmvd Emissions,
Temp., Output, Btu/kWhr Gas Flow, Gas Corrected to 15% O2 lb/hr
o
F kWe (LHV) lb/hr Temp.,
o
F
NOx CO VOC PM/P SOx
M10
Total
59 4,024 12,471 150,000 930 65 50 25 0.061 None

5 Heat Recovery Steam Generator

Eastern Maine Medical Center SECTION IV


Design Basis Document Functional Requirements
CHP Cogen Plant 5
6 Steam System -CHP

7 Existing Boilers and Steam System – Campus Distribution

8 Boiler Feedwater System

9 Condensate System

10 Boiler Blowdown and Wastewater Sump

11 Piping Systems

12 Insulation System

13 Potable Water System

14 Water Treatment System

15 Wastewater Handling System

16 Fire Protection Systems

17 Fuel Oil System

18 Natural Gas Fuel System

19 Compressed Air Systems

20 Absorption Chiller & Cooling Tower

21 Electrical System

22 Medium Voltage Switchgear

23 480 Volt Unit Substation

24 Lighting System

25 Grounding System

26 Lightning Protection

27 Power and Control Cable

28 Fire Alarm System

29 Communication System

Eastern Maine Medical Center SECTION IV


Design Basis Document Functional Requirements
CHP Cogen Plant 6
30 Electrical Acceptance Testing

31 Instrumentation & Controls

32 Chemical Feed System

33 Sampling System

Eastern Maine Medical Center SECTION IV


Design Basis Document Functional Requirements
CHP Cogen Plant 7
SECTION V

OCCUPANCY REQUIREMENTS

The CHP will be designed to accommodate the current level of staffing required
by the state office of Chief Boiler Inspector.

Eastern Maine Medical Center SECTION V


Design Basis Document Occupancy Requirements
CHP Cogen Plant 8
SECTION VI

PERFORMANCE REQUIREMENTS

1 General

1.1 American Society of Mechanical Engineers (ASME) Performance Test Codes will
guide development of testing procedures for individual plant systems. Examples
include PTC 22 for the gas turbine and PTC 36 for industrial sound measurement.
1.2 A Commissioning Manual will be used to organize testing of power generation and
auxiliary systems.
1.3 Start-up, commissioning and performance testing of electrical systems shall comply
with the International Electrical Testing Association (NETA) and the Institute of
Electrical and Electronics Engineers, Inc. (IEEE) codes and standards.
1.4 Minimum standards will be used in conjunction with manufacturer checklists and
system testing documentation as well as state and local codes and ordinances.
1.5 CIANBRO Corporation, its Subcontractors and Sub-Subcontractors shall make-up
any pre-functional checklists or forms required for equipment and/or systems to be
commissioned.
1.6 EMMC’s acceptance of CHP design and construction will be based on the
successful operation of the Facility in the mode described at the conditions stated in
Exhibit B. These conditions are presented on Energy Balance Diagrams included in
Exhibit B.
1.7 Vanderweil will develop the detailed criteria against which Facility performance
will be measured during start-up and commissioning, and on which equipment
warranties are based. Such criteria will measure Facility performance at both
maximum continuous rating and warrantee conditions. Equipment vendors will
submit Predicted Performance Sheets for their equipment based on these
performance criteria. The Predicted Performance Sheets for the CTG will state
assumptions such as inlet air temperature, unit load and exhaust gas flow when the
unit is operated on gas and oil.

2 Operating Conditions

2.1 Facility Performance Requirements are based on the following operating criteria
and description of CHP plant operation in Exhibit C:

a) Design Outdoor Dry Bulb Temperatures:

 CTG performance guarantees at 59 F and 60% RH

b) Design for Summer:

 Indoor areas for a Dry Bulb of 95 Fo and Control Room for Dry Bulb of
82 Fo.

Eastern Maine Medical Center SECTION VI


Design Basis Document Performance Requirements
CHP Cogen Plant 9
c) Design for Winter:

 Indoor Plant areas for a Dry Bulb of 55 Fo and Control Room for a Dry
Bulb of 68 Fo.

d) Snow load and wind load design shall comply with IBC 2003.
e) Frost Depth: 60 inches minimum cover
f) Barometric pressure = 14.7 psia
g) Generator Power Factor = 0.90
h) Power output measured at the 12.5 kV voltage level at the metering location.
i) All electric loads required for normal operation of the CHP in full operation
during testing.
j) Natural gas meeting the requirements of the combustion turbine as given in
Exhibit D.
k) The CTG meets all conditions of its air permit. Emissions maintained within
air quality permit limits as measured by third party test.
l) Zero blowdown of Heat Recovery Steam Generator during HRSG
performance testing.
m) Design criteria for the CHP shall contain sufficient and suitable margins
within new components and systems such that the ability of the cycle to
operate continuously shall not be compromised due to normal wear and
deterioration of equipment

3 Noise Controls

The Facility will be designed to control internal and external noise based on the following
considerations:

3.1 Noise shall be used as a factor in selecting equipment and for design of air intake
and exhaust systems. The sound power levels of the CTG shall be based on Solar-
furnished data.
3.2 Where practical, internal plant noise shall be controlled such that Speech
Interference Levels (SIL)1 allow verbal communications to be intelligible by a
raised voice and for the emergency address system to be heard adjacent to
machinery. Around motors and fans, SIL levels shall permit communication by a
loud voice. SIL levels shall not exceed the following guidelines:

Distance in Feet
Between Talker and Raised Voice Loud Voice
Listener SIL (dB) SIL (dB)

1 73 85
3 64 70
5 59 65

1
The arithmetic average of the octave band sound pressure levels in the 500-, 1000-,
2000-, and 4000-Hz octave bands.

Eastern Maine Medical Center SECTION VI


Design Basis Document Performance Requirements
CHP Cogen Plant 10
3.3 The noise level inside the plant shall be controlled so that worker exposure
compiles with the noise regulations of the Occupational Safety and Health
Administration (OSHA). Specifically, noise in plant areas where workers spend
their time shall not exceed an A-weighted level of 85 dB(A). The noise level in
areas such as the control room, shall be limited to a design goal of 60 dB(A).
3.4 Outdoor noise associated with normal operation of the plant shall be controlled so
that the resulting increase in broad band noise level at the Campus property line
(locations to be determined) shall not exceed 70 dBA—daytime levels and 60 dBA
– night levels. Vents shall be provided with silencers to achieve these sound levels.

4 Combustion Turbine-Generator

4.1 The CTG shall be designed to operate continuously 24 hours a day at 96% annual
plant factor to supply the varying steam and electric demands.
4.2 To meet this operation, the CTG will require periodic engine maintenance at 30,000
to 40,000 hour operating intervals.

5 Steam and Electric Systems

5.1 Steam and electric systems shall be designed to meet steam and electric output over
a 20-year design life, adjusted for normal degradation of equipment.
5.2 HRSG and auxiliary equipment shall maintain steam temperatures and flow rates at
their set point levels, changing less than 2 F or ½ % in 30 minutes at steady state
conditions.

6 Piping Systems

Pipe sizes shall be determined primarily on the basis of allowable pressure drop for the
service. The following velocity limits shall generally apply:

6.1 General Service Water piping (other than boiler feed):

a) 6” nominal pipe size and above: 8 -- 9 ft/sec


b) 4” NPS and below: 5 – 8 ft/sec.

6.2 Boiler Feedwater piping:

a) Suction: 4 -- 7 ft/sec
b) Discharge: 8 – 15 ft/sec

6.3 Steam piping:

a) Superheated steam: 120 – 300 ft/sec


b) Saturated steam: 100 – 150 ft/sec

6.4 Natural Gas (high pressure):


a) 40 –100 ft/sec

Eastern Maine Medical Center SECTION VI


Design Basis Document Performance Requirements
CHP Cogen Plant 11
7 Lighting Systems

Lighting and illumination levels shall meet the following footcandle (fc) values:

7.1 Outdoor Facilities:

a) General areas 2 fc
b) Stairs and platforms 10 fc
c) Ground level areas 10 fc
d) Truck unloading areas 10 fc

7.2 Interior Facilities:

a) Gas Turbine operating floor 30 fc


b) Control room 50 fc
c) Instrument areas and Boiler Front 30 fc

Eastern Maine Medical Center SECTION VI


Design Basis Document Performance Requirements
CHP Cogen Plant 12
SECTION VII

ENVIRONMENTAL QUALITY

1 Environmental Quality Acceptance Criteria

Acceptance will be based on the following criteria:

1.1 CHP systems meet applicable local, state and federal environmental regulations and
permit conditions.
1.2 The potential for nuisance noise generated by the CHP is mitigated using silencers
on gas turbine air ducts and sound attenuated enclosure.
1.3 CTG and HRSG stack emissions comply with conditions of the air permit, not
exceeding the limits for gas and oil firing presented below and in Section 4.

Table 1
CTG Performance and Emissions Guarantees
Natural Gas

Ambient Full Load Heat Rate, Exhaust Exhaust Emissions, ppmvd Emissions,
Temp., Output, Btu/kWhr Gas Flow, Gas Corrected to 15% O2 lb/hr
o
F kWe (LHV) lb/hr Temp.,
o
F
NOx CO UHC PM/P SOx
M10
Total
59 4,294 12,306 144,000 960 25 50 25 0.0419 None

Table 2
CTG Performance and Emissions Guarantees
Low Sulfur Diesel Oil

Ambient Full Load Heat Rate, Exhaust Exhaust Emissions, ppmvd Emissions,
Temp., Output, Btu/kWhr Gas Flow, Gas Corrected to 15% O2 lb/hr
o
F kWe (LHV) lb/hr Temp.,
o
F
NOx CO VOC PM/P SOx
M10
Total
59 4,024 12,471 150,000 930 65 50 25 0.0619 None

Eastern Maine Medical Center SECTION VII


Design Basis Document Environmental Quality
CHP Cogen Plant 13
EXHIBIT A

EMMC DESIGN STANDARDS

The EMMC Design Standards describe campus preferences for civil, structural,
architectural, mechanical, and electrical site and building systems.

Eastern Maine Medical Center Exhibit A


Design Basis Document EMMC Design Standards
CHP Cogen Plant 14
EXHIBIT B

HEAT BALANCE DIAGRAMS FOR CHP OPERATION

Eastern Maine Medical Center Exhibit B


Design Basis Document Heat Balance Diagrams for CHP Operation
CHP Cogen Plant 15
EXHIBIT C

CHP PLANT SEQUENCE OF OPERATIONS

Eastern Maine Medical Center Exhibit C


Design Basis Document CHP Plant Sequence of Operations
CHP Cogen Plant 16
EXHIBIT D

NATURAL GAS SPECIFICATION

Parameter Specification Limit2

Pressure (psig) 300

Maximum Flow Rate (scfm) 1,100

Wobbe Index 1,220

Maximum water (mg/m3) 112.0

Maximum water dew point at maximum


pipeline operating pressure (oC) 0.0

Maximum hydrocarbon dew point at 3,500 kPa


gauge pressure (oC) 2.0

Maximum oxygen (mole %) 0.2

Maximum total inert gas (mole %) 7.0

Maximum hydrogen sulfide (mg/m3) 5.7

Minimum gas temperature (oC) 2.0

Maximum gas temperature (oC) 50

2
Source: Gas Safety (Gas Quality) Regulations of 1999.

Eastern Maine Medical Center Exhibit D


Design Basis Document Natural Gas Specification
CHP Cogen Plant 17
EXHIBIT E

DRAWINGS

Eastern Maine Medical Center Exhibit E


Design Basis Document Drawings
CHP Cogen Plant 18

Вам также может понравиться