Академический Документы
Профессиональный Документы
Культура Документы
I. INTRODUCTION
The Electricity & Energy Directorate of the Nelson
Mandela Bay Municipality (NMBM) requires a concise code of
practice that sets out the connections, earthing, ratings and
standards for voltage transformers (VTs) used in tariff
metering. Due to unknown consumer earthing practices,
metering errors could occur during unbalanced loading. When
a loads primary is unknowingly earthed and supplied from an
earthed source, a three-phase/four-wire system will exist where
the two-element tariff metering method will be inaccurate [1].
VT burden ratings may be inappropriate due to improper
loading of the VT secondary. When the VT is not loaded to at
least 25% of its burden rating, it will not operate in its ideal
accuracy range [2]. In the past couple of years with the
introduction of numerical tariff meters and relays, the actual
burdens presented by these secondary devices have become
very small. It became necessary to add dummy resistor loads
to the secondary circuit of VTs. Not only does this add
additional requirements to the installation of VTs but a VT is
C. Ferroresonance
The inductance of the VT is in parallel with the system
capacitance and a sudden transient overvoltage will result in
one or several phases of the VT going into saturation. The
saturation of the iron core of the VT results in a change in the
inductance parallel with the system capacitance. If the
inductance of the VT exactly matches the system capacitance,
Z load load =
Vload 1
I load 1
(1)
(3)
(4)
(5)
(6)
(7)
The load currents for both balanced and unbalanced loads can
therefore be calculated from the phase voltages and the
consumer load impedances.
(2)
Vsec( ph n ) =
V prim ( ph n ) (1 %regulation)
n
(8)
Pa = V a I a cos( a a )
(9)
Pb = Vb I b cos( b b )
(10)
Pc = Vc I c cos( c c )
(11)
Pt = Pa + Pb + Pc
V an an
V cn cn
V ab ab = V an an Vbn bn
(13)
V cb cb = Vcn cn Vbn bn
(14)
Wt = W1 + W 2
(15)
Where:
W1 = V ab I a cos( ab a )
And:
W 2 = V cb I c cos( cb c )
(12)
Vbn bn
V an an
Vbn bn
V cn cn
Wt = W1 + W2 + W3
(16)
Where:
W1 = V an I a cos( an a )
W 2 = Vbn I b cos( bn b )
W3 = Vcn I c cos( cn c )
5) Percentage Error:
The difference between the Real Power and Measured
Power was expressed as a percentage error and indicates the
VT error due to two factors, namely the VT losses and
connection methods. The VT losses observed in the
calculations were due to the voltage drops from primary to
secondary. As the same parameters were used for the
equivalent circuit calculations for the different VT
connections, the VT losses are relatively constant. Any
variation in the error results, should be due to the type of VT
connection used. The percentage error between Real Power
and Measured Power is given by:
%error =
Pt Wt
100
Pt
(17)
VII. RECOMMENDATIONS
It is recommended after considering the results from the
research that the NMBM accept the Code of Practice
Inductive Type VTs as used for tariff metering and all
standards and guidelines therein. The primary finding of which
is that the earthed primary star-star connected VT (YNyn),
should be used in future tariff meter installations of MV and
HV consumers.
The three-phase VT used for tariff metering of 6.6kV and
11kV consumer should be of the 5-limb construction. The VTs
used for the tariff metering of 22kV consumers should be three
single phase transformers arranged star-star in one three-phase
unit and the those used for tariff metering of HV consumers
should be separate single phase VTs connected star-star.
It is also recommended that VTs be selected with a burden
rating corresponding to 75% of its actual secondary load and
therefore would be in the range of 10-15VA, instead of the
current 50-100VA range. When the VT cannot be loaded to
within the 25%-100% accuracy range, it becomes necessary to
employ a dummy load in the form of a resistor added to the
secondary installation circuit. The calculation of the dummy
burden resistor should be applied to each case individually if a
burden resistor becomes necessary.
It is recommended that future research be done to compare
the monetary advantage of using the earthed primary VT of
five limb constructions and the 3phase/4wire metering method,
with the unearthed VT of three limb construction and the
REFERENCES
[1] S.J. van Zyl, Electrical Technology, 3rd ed., Vanderbijlpark,
2007.
[2] SABS IEC 60044-2, Instrument Transformers part 2: Inductive
Voltage Transformers, ANSI, 2007.
[3] V. Valverde, A.J. Mazon, I. Zamora and G. Buigues,
Ferroresonance in voltage transformers: analysis and
simulations, International conference on renewable energies
and power quality, p. 7, 2007.
[4] W.T. McLyman, Transformer and Inductor Design Handbook,
3rd ed., Dekker, 2009.
[5] IEEE SA-C57.12.51-2008, "IEEE Standard for requirements for
instrument transformers, IEEE Standards Association, 2008.
[6] NRS030, "Inductive voltage transformers for rated a.c. voltages
from 3.6kV up to and including 145kV for indoor and outdoor
applications," Pretoria, 2001.
[7] D.I. Taylor, J.D. Law, B.K. Johnson and N. Fischer, Singlephase transformer inrush current reduction using prefluxing,
IEEE Trans. On Power Delivery, vol. 27, no. 1, pp. 245-252,
January 2012.
[8] Cadick Corporation technical bulletin no. 004a, 2002.
[9] R. Tajali, Line to ground voltage monitoring on underground
and impedance ground power systems, Square D Company,
2007.