Академический Документы
Профессиональный Документы
Культура Документы
Page | 1
force majeure and other causes beyond the control of the respondent
Airline.
Civil Case No. 1797
Page | 2
the event must be such as to render it impossible for the debtor to fulfill
his obligation in a normal manner; and (d) the debtor must be free from
any participation in, or aggravation of the injury to the creditor (Lasam v.
Smith, 45 Phil. 657 [1924]; Austria v. Court of Appeals, 39 SCRA 527
[1971]; Estrada v. Consolacion, supra; Vasquez v. Court of Appeals, 138
SCRA 553 [1985]; Juan F. Nakpil & Sons v. Court of Appeals, 144 SCRA 596
[1986]). Caso fortuito or force majeure, by definition, are extraordinary
events not foreseeable or avoidable, events that could not be foreseen, or
which, though foreseen, are inevitable. It is, therefore, not enough that the
event should not have been foreseen or anticipated, as is commonly
believed, but it must be one impossible to foresee or to avoid. The mere
difficulty to foresee the happening is not impossibility to foresee the same
(Republic v. Luzon Stevedoring Corporation, 21 SCRA 279 [1967]).
Applying the above guidelines to the case at bar, the failure to transport
petitioners safely from Davao to Manila was due to the skyjacking incident
staged by six (6) passengers of the same plane, all members of the Moro
National Liberation Front (MNLF), without any connection with private
respondent, hence, independent of the will of either the PAL or of its
passengers.
Under normal circumstances, PAL might have foreseen the skyjacking
incident which could have been avoided had there been a more thorough
frisking of passengers and inspection of baggages as authorized by R.A.
No. 6235. But the incident in question occurred during Martial Law where
there was a military take-over of airport security including the frisking of
passengers and the inspection of their luggage preparatory to boarding
domestic and international flights. In fact military take-over was
specifically announced on October 20, 1973 by General Jose L. Rancudo,
Commanding General of the Philippine Air Force in a letter to Brig. Gen.
Jesus Singson, then Director of the Civil Aeronautics Administration (Rollo,
pp. 71-72) later confirmed shortly before the hijacking incident of May 21,
1976 by Letter of Instruction No. 399 issued on April 28, 1976 (Rollo, p.
72).
Otherwise stated, these events rendered it impossible for PAL to perform
its obligations in a nominal manner and obviously it cannot be faulted with
negligence in the performance of duty taken over by the Armed Forces of
the Philippines to the exclusion of the former.
Finally, there is no dispute that the fourth element has also been satisfied.
Consequently the existence of force majeure has been established
exempting respondent PAL from the payment of damages to its passengers
who suffered death or injuries in their persons and for loss of their
BELLOSILLO, J.:
This petition for review in certiorari seeks to annul and set aside the
decision of the then Intermediate Appellant Court, 1 now Court of Appeals,
dated 28 February 1985, in AC-G.R. CV No. 69327 ("Pedro Zapatos v.
Philippine Airlines, Inc.") affirming the decision of the then Court of first
Instance, now Regional Trial Court, declaring Philippine Airlines, Inc., liable
in damages for breach of contract.
On 25 November 1976, private respondent filed a complaint for damages
for breach of contract of carriage 2 against Philippine Airlines, Inc. (PAL),
before the then Court of First Instance, now Regional Trial Court, of Misamis
Occidental, at Ozamiz City. According to him, on 2 August 1976, he was
among the twenty-one (21) passengers of PAL Flight 477 that took off from
Cebu bound for Ozamiz City. The routing of this flight was Cebu-OzamizCotabato. While on flight and just about fifteen (15) minutes before landing
at Ozamiz City, the pilot received a radio message that the airport was
closed due to heavy rains and inclement weather and that he should
proceed to Cotabato City instead.
Upon arrival at Cotabato City, the PAL Station Agent informed the
passengers of their options to return to Cebu on flight 560 of the same day
and thence to Ozamiz City on 4 August 1975, or take the next flight to
Cebu the following day, or remain at Cotabato and take the next available
flight to Ozamiz City on 5 August 1975. 3 The Station Agent likewise
informed them that Flight 560 bound for Manila would make a stop-over at
Cebu to bring some of the diverted passengers; that there were only six (6)
seats available as there were already confirmed passengers for Manila;
and, that the basis for priority would be the check-in sequence at Cebu.
Page | 3
the dispositive
10
Page | 4
the needs of the diverted passengers; and, that the question of negligence
was not and never put in issue by the pleadings or proved at the trial.
Contrary to the above arguments, private respondent's amended
complaint touched on PAL's indifference and inattention to his
predicament. The pertinent portion of the amended complaint 14 reads:
10. That by virtue of the refusal of the defendant
through its agent in Cotabato to accommodate (sic)
and allow the plaintiff to take and board the plane
back to Cebu, and by accomodating (sic) and
allowing passengers from Cotabato for Cebu in his
stead and place, thus forcing the plaintiff against
his will, to be left and stranded in Cotabato,
exposed to the peril and danger of muslim rebels
plundering at the time, the plaintiff, as a
consequence, (have) suffered mental anguish,
mental torture, social humiliation, bismirched
reputation and wounded feeling, all amounting to a
conservative
amount
of
thirty
thousand
(P30,000.00) Pesos.
To substantiate this aspect of apathy, private respondent testified
15
Page | 5
Atty. Rubin
counsel:
O.
Rivera
PAL's
The contract of air carriage is a peculiar one. Being imbued with public
interest, the law requires common carriers to carry the passengers safely
as far as human care and foresight can provide, using the utmost diligence
of very cautious persons, with due regard for all the circumstances. 20 In
Air France v. Carrascoso, 21 we held that
Private respondent:
A Yes.
Q Did you ask them to help you
regarding
any
offer
of
transportation or of any other
matter asked of them?
A Yes, he (PAL PERSONNEL) said
what is? It is not our fault.
Q Are you not aware that one
fellow passenger even claimed that
he was given Hotel accommodation
because they have no money?
xxx xxx xxx
A No, sir, that was never offered to
me. I said, I tried to stop them but
they were already riding that PAL
pick-up jeep, and I was not
accommodated.
Having joined in the issue over the alleged lack of care it exhibited towards
its passengers, PAL cannot now turn around and feign surprise at the
outcome of the case. When issues not raised by the pleadings are tried by
express or implied consent of the parties, they shall be treated in all
respects as if they had been raised in the pleadings. 19
With regard to the award of damages affirmed by the appellate court, PAL
argues that the same is unfounded. It asserts that it should not be charged
with the task of looking after the passengers' comfort and convenience
because the diversion of the flight was due to a fortuitous event, and that
if made liable, an added burden is given to PAL which is over and beyond
its duties under the contract of carriage. It submits that granting arguendo
that negligence exists, PAL cannot be liable in damages in the absence of
fraud or bad faith; that private respondent failed to apprise PAL of the
nature of his trip and possible business losses; and, that private
Page | 6
While we find PAL remiss in its duty of extending utmost care to private
respondent while being stranded in Cotabato City, there is no sufficient
basis to conclude that PAL failed to inform him about his nonaccommodation on Flight 560, or that it was inattentive to his queries
relative thereto.
COURT:
Q What do you mean by "yes"? You
meant you were not informed?
Page | 7
25
Atty. Rivera:
Q And, you were saying that
despite the fact that according to
your testimony there were at least
16 passengers who were stranded
there in Cotabato airport according
to your testimony, and later you
said that there were no other
people left there at that time, is
that correct?
A Yes, I did not see anyone there
around. I think I was the only
civilian who was left there.
Page | 8
The trial court, giving credence to the ocular inspection report to the
effect that subject school building had a defective roofing structure,
found that, while typhoon Saling was accompanied by strong winds, the
damage to private respondents house could have been avoided if the
construction of the roof of [petitioners] building was not faulty. The
dispositive portion of the lower courts decisionvii reads thus:
WHEREFORE, in view of the foregoing, the Court renders
judgment (sic) in favor of the plaintiff (sic) and against the
defendants, (sic) ordering the latter to pay jointly and severally
the former as follows:
Page | 9
Page | 10
regarding any defect on the same structure has ever been lodged before
his office prior to the institution of the case at bench. It is a matter of
judicial notice that typhoons are common occurrences in this country. If
subject school buildings roofing was not firmly anchored to its trusses,
obviously, it could not have withstood long years and several typhoons
even stronger than Saling.
In light of the foregoing, we find no clear and convincing evidence to
sustain the judgment of the appellate court. We thus hold that petitioner
has not been shown negligent or at fault regarding the construction and
maintenance of its school building in question and that typhoon Saling
was the proximate cause of the damage suffered by private respondents
house.
With this disposition on the pivotal issue, private respondents claim
for actual and moral damages as well as attorneys fees must fail. xxiv
Petitioner cannot be made to answer for a purely fortuitous event. xxv More
so because no bad faith or willful act to cause damage was alleged and
proven to warrant moral damages.
Private respondents failed to adduce adequate and competent proof
of the pecuniary loss they actually incurred. xxvi It is not enough that the
damage be capable of proof but must be actually proved with a reasonable
degree of certainty, pointing out specific facts that afford a basis for
measuring whatever compensatory damages are borne. xxvii Private
respondents merely submitted an estimated amount needed for the repair
of the roof of their subject building. What is more, whether the necessary
repairs were caused ONLY by petitioners alleged negligence in the
maintenance of its school building, or included the ordinary wear and tear
of the house itself, is an essential question that remains indeterminable.
The Court deems unnecessary to resolve the other issues posed by
petitioner.
As regards the sixth issue, however, the writ of execution issued on
April 1, 1993 by the trial court is hereby nullified and set aside. Private
respondents are ordered to reimburse any amount or return to petitioner
any property which they may have received by virtue of the enforcement
of said writ.
WHEREFORE, the petition is GRANTED and the challenged Decision is
REVERSED. The complaint of private respondents in Civil Case No. 7314
before the trial court a quo is ordered DISMISSED and the writ of execution
issued on April 1, 1993 in said case is SET ASIDE. Accordingly, private
respondents are ORDERED to return to petitioner any amount or property
received by them by virtue of said writ. Costs against the private
respondents.
SO ORDERED.
G.R. No. 147324
Moreover, the city building official, who has been in the city
government service since 1974, admitted in open court that no complaint
Page | 11
TINGA, J.:
Before the Court are two Petitions for Review assailing the Decision of the
Court of Appeals, dated 27 February 2001, in CA-G.R. CV No. 63619. 1
The facts of the case are undisputed.
For several years prior to 1991, Globe Mckay Cable and Radio Corporation,
now Globe Telecom, Inc. (Globe), had been engaged in the coordination of
the provision of various communication facilities for the military bases of
the United States of America (US) in Clark Air Base, Angeles, Pampanga
and Subic Naval Base in Cubi Point, Zambales. The said communication
facilities were installed and configured for the exclusive use of the US
Defense Communications Agency (USDCA), and for security reasons, were
operated only by its personnel or those of American companies contracted
by it to operate said facilities. The USDCA contracted with said American
companies, and the latter, in turn, contracted with Globe for the use of the
communication facilities. Globe, on the other hand, contracted with local
service providers such as the Philippine Communications Satellite
Corporation (Philcomsat) for the provision of the communication facilities.
On 07 May 1991, Philcomsat and Globe entered into an Agreement
whereby Philcomsat obligated itself to establish, operate and provide an
IBS Standard B earth station (earth station) within Cubi Point for the
exclusive use of the USDCA.2 The term of the contract was for 60 months,
or five (5) years.3 In turn, Globe promised to pay Philcomsat monthly
rentals for each leased circuit involved.4
At the time of the execution of the Agreement, both parties knew that the
Military Bases Agreement between the Republic of the Philippines and the
US (RP-US Military Bases Agreement), which was the basis for the
occupancy of the Clark Air Base and Subic Naval Base in Cubi Point, was to
expire in 1991. Under Section 25, Article XVIII of the 1987 Constitution,
foreign military bases, troops or facilities, which include those located at
the US Naval Facility in Cubi Point, shall not be allowed in the Philippines
unless a new treaty is duly concurred in by the Senate and ratified by a
majority of the votes cast by the people in a national referendum when the
Congress so requires, and such new treaty is recognized as such by the US
Government.
Page | 12
Philcomsat sent a reply letter dated 10 August 1992 to Globe, stating that
"we expect [Globe] to know its commitment to pay the stipulated rentals
for the remaining terms of the Agreement even after [Globe] shall have
discontinue[d] the use of the earth station after November 08, 1992." 7
Philcomsat referred to Section 7 of the Agreement, stating as follows:
7. DISCONTINUANCE OF SERVICE
Should [Globe] decide to discontinue with the use of the
earth station after it has been put into operation, a written
notice shall be served to PHILCOMSAT at least sixty (60)
days prior to the expected date of termination.
Notwithstanding the non-use of the earth station, [Globe]
shall continue to pay PHILCOMSAT for the rental of the
actual number of T1 circuits in use, but in no case shall be
less than the first two (2) T1 circuits, for the remaining life
of the agreement. However, should PHILCOMSAT make use
or sell the earth station subject to this agreement, the
obligation of [Globe] to pay the rental for the remaining life
of the agreement shall be at such monthly rate as may be
agreed upon by the parties.8
After the US military forces left Subic Naval Base, Philcomsat sent Globe a
letter dated 24 November 1993 demanding payment of its outstanding
obligations under the Agreement amounting to US$4,910,136.00 plus
interest and attorneys fees. However, Globe refused to heed Philcomsats
demand.
On 27 January 1995, Philcomsat filed with the Regional Trial Court of Makati
a Complaint against Globe, praying that the latter be ordered to pay
liquidated damages under the Agreement, with legal interest, exemplary
damages, attorneys fees and costs of suit. The case was raffled to Branch
59 of said court.
Globe filed an Answer to the Complaint, insisting that it was constrained to
end the Agreement due to the termination of the RP-US Military Bases
Agreement and the non-ratification by the Senate of the Treaty of
Friendship and Cooperation, which events constituted force majeure under
the Agreement. Globe explained that the occurrence of said events
exempted it from paying rentals for the remaining period of the
Agreement.
On 05 January 1999, the trial court rendered its Decision, the dispositive
portion of which reads:
WHEREFORE, premises considered, judgment is hereby
rendered as follows:
defendants
Page | 13
party involved including, but not limited to, any law, order, regulation,
direction or request of the Government of the Philippines, strikes or other
labor difficulties, insurrection riots, national emergencies, war, acts of
public enemies, fire, floods, typhoons or other catastrophies or acts of
God," should be deemed subject to Article 1174 which defines fortuitous
events as events which could not be foreseen, or which, though foreseen,
were inevitable.13
Philcomsat further claims that the Court of Appeals erred in holding that
Globe is not liable to pay for the rental of the earth station for the entire
term of the Agreement because it runs counter to what was plainly
stipulated by the parties in Section 7 thereof. Moreover, said ruling is
inconsistent with the appellate courts pronouncement that Globe is liable
to pay rentals for December 1992 even though it terminated Philcomsats
services effective 08 November 1992, because the US military and
personnel completely withdrew from Cubi Point only in December 1992.
Philcomsat points out that it was Globe which proposed the five-year term
of the Agreement, and that the other provisions of the Agreement, such as
Section 4.114 thereof, evince the intent of Globe to be bound to pay rentals
for the entire five-year term.15
Both parties filed their respective Petitions for Review assailing the
Decision of the Court of Appeals.
In G.R. No. 147324,11
assignments of error:
petitioner
Philcomsat
raises
the
following
Page | 14
The Court is tasked to resolve the following issues: (1) whether the
termination of the RP-US Military Bases Agreement, the non-ratification of
the Treaty of Friendship, Cooperation and Security, and the consequent
withdrawal of US military forces and personnel from Cubi Point constitute
force majeure which would exempt Globe from complying with its
obligation to pay rentals under its Agreement with Philcomsat; (2) whether
Globe is liable to pay rentals under the Agreement for the month of
December 1992; and (3) whether Philcomsat is entitled to attorneys fees
and exemplary damages.
6. War;
7. Acts of public enemies;
8. Fire, floods, typhoons or other catastrophies or acts of
God;
9. Other circumstances beyond the control of the parties.
Clearly, the foregoing are either unforeseeable, or foreseeable but beyond
the control of the parties. There is nothing in the enumeration that runs
contrary to, or expands, the concept of a fortuitous event under Article
1174.
Furthermore, under Article 130626 of the Civil Code, parties to a contract
may establish such stipulations, clauses, terms and conditions as they may
deem fit, as long as the same do not run counter to the law, morals, good
customs, public order or public policy.27
Article 1159 of the Civil Code also provides that "[o]bligations arising from
contracts have the force of law between the contracting parties and should
be complied with in good faith."28 Courts cannot stipulate for the parties
nor amend their agreement where the same does not contravene law,
morals, good customs, public order or public policy, for to do so would be
to alter the real intent of the parties, and would run contrary to the
function of the courts to give force and effect thereto. 29
Page | 15
Not being contrary to law, morals, good customs, public order, or public
policy, Section 8 of the Agreement which Philcomsat and Globe freely
agreed upon has the force of law between them.30
In order that Globe may be exempt from non-compliance with its obligation
to pay rentals under Section 8, the concurrence of the following elements
must be established: (1) the event must be independent of the human will;
(2) the occurrence must render it impossible for the debtor to fulfill the
obligation in a normal manner; and (3) the obligor must be free of
participation in, or aggravation of, the injury to the creditor. 31
The Court agrees with the Court of Appeals and the trial court that the
abovementioned requisites are present in the instant case. Philcomsat and
Globe had no control over the non-renewal of the term of the RP-US
Military Bases Agreement when the same expired in 1991, because the
prerogative to ratify the treaty extending the life thereof belonged to the
Senate. Neither did the parties have control over the subsequent
withdrawal of the US military forces and personnel from Cubi Point in
December 1992:
Obviously the non-ratification by the Senate of the RP-US
Military Bases Agreement (and its Supplemental
Agreements) under its Resolution No. 141. (Exhibit "2") on
September 16, 1991 is beyond the control of the parties.
This resolution was followed by the sending on December
31, 1991 o[f] a "Note Verbale" (Exhibit "3") by the
Philippine Government to the US Government notifying the
latter of the formers termination of the RP-US Military
Bases Agreement (as amended) on 31 December 1992 and
that accordingly, the withdrawal of all U.S. military forces
from Subic Naval Base should be completed by said date.
Subsequently, defendant [Globe] received a formal order
from Cdr. Walter F. Corliss II Commander USN dated July 31,
1992 and a notification from ATT dated July 29, 1992 to
terminate the provision of T1s services (via an IBS
Standard B Earth Station) effective November 08, 1992.
Plaintiff [Philcomsat] was furnished with copies of the said
order and letter by the defendant on August 06, 1992.
Resolution No. 141 of the Philippine Senate and the Note
Verbale of the Philippine Government to the US
Government are acts, direction or request of the
Government of the Philippines and circumstances beyond
the control of the defendant. The formal order from Cdr.
Walter Corliss of the USN, the letter notification from ATT
and the complete withdrawal of all the military forces and
personnel from Cubi Point in the year-end 1992 are also
acts and circumstances beyond the control of the
defendant.
Page | 16
With respect to the issue of whether Globe is liable for payment of rentals
for the month of December 1992, the Court likewise affirms the appellate
courts ruling that Globe should pay the same.
GAISANO
CAGAYAN,
INC.
Petitioner,
vs.
INSURANCE COMPANY OF NORTH AMERICA, Respondent.
AUSTRIA-MARTINEZ, J.:
Neither did the appellate court commit any error in holding that Philcomsat
is not entitled to attorneys fees and exemplary damages.
The award of attorneys fees is the exception rather than the rule, and
must be supported by factual, legal and equitable justifications. 36 In
previously decided cases, the Court awarded attorneys fees where a party
acted in gross and evident bad faith in refusing to satisfy the other partys
claims and compelled the former to litigate to protect his rights; 37 when the
action filed is clearly unfounded, 38 or where moral or exemplary damages
are awarded.39 However, in cases where both parties have legitimate
claims against each other and no party actually prevailed, such as in the
present case where the claims of both parties were sustained in part, an
award of attorneys fees would not be warranted.40
Exemplary damages may be awarded in cases involving contracts or quasicontracts, if the erring party acted in a wanton, fraudulent, reckless,
oppressive or malevolent manner. 41 In the present case, it was not shown
that Globe acted wantonly or oppressively in not heeding Philcomsats
demands for payment of rentals. It was established during the trial of the
case before the trial court that Globe had valid grounds for refusing to
comply with its contractual obligations after 1992.
WHEREFORE, the Petitions are DENIED for lack of merit. The assailed
Decision of the Court of Appeals in CA-G.R. CV No. 63619 is AFFIRMED.
SO ORDERED.
G.R. No. 147839
Before the Court is a petition for review on certiorari of the Decision 1 dated
October 11, 2000 of the Court of Appeals (CA) in CA-G.R. CV No. 61848
which set aside the Decision dated August 31, 1998 of the Regional Trial
Court, Branch 138, Makati (RTC) in Civil Case No. 92-322 and upheld the
causes of action for damages of Insurance Company of North America
(respondent) against Gaisano Cagayan, Inc. (petitioner); and the CA
Resolution dated April 11, 2001 which denied petitioner's motion for
reconsideration.
June 8, 2006
Page | 17
In its Answer with Counter Claim dated July 4, 1995, petitioner contends
that it could not be held liable because the property covered by the
insurance policies were destroyed due to fortuities event or force majeure;
that respondent's right of subrogation has no basis inasmuch as there was
no breach of contract committed by it since the loss was due to fire which
it could not prevent or foresee; that IMC and LSPI never communicated to it
that they insured their properties; that it never consented to paying the
claim of the insured.6
The CA held that the sales invoices are proofs of sale, being detailed
statements of the nature, quantity and cost of the thing sold; that loss of
the goods in the fire must be borne by petitioner since the proviso
contained in the sales invoices is an exception under Article 1504 (1) of the
Civil Code, to the general rule that if the thing is lost by a fortuitous event,
the risk is borne by the owner of the thing at the time the loss under the
principle of res perit domino; that petitioner's obligation to IMC and LSPI is
not the delivery of the lost goods but the payment of its unpaid account
and as such the obligation to pay is not extinguished, even if the fire is
considered a fortuitous event; that by subrogation, the insurer has the
right to go against petitioner; that, being a fire insurance with book debt
endorsements, what was insured was the vendor's interest as a creditor. 11
On August 31, 1998, the RTC rendered its decision dismissing respondent's
complaint.8 It held that the fire was purely accidental; that the cause of the
fire was not attributable to the negligence of the petitioner; that it has not
been established that petitioner is the debtor of IMC and LSPI; that since
the sales invoices state that "it is further agreed that merely for purpose of
securing the payment of purchase price, the above-described merchandise
remains the property of the vendor until the purchase price is fully paid",
IMC and LSPI retained ownership of the delivered goods and must bear the
loss.
Page | 18
for payment of the debt and such demands came from respondent only
after it had already paid IMC and LSPI under the fire insurance policies. 15
As to the second error, petitioner avers that despite delivery of the goods,
petitioner-buyer IMC and LSPI assumed the risk of loss when they secured
fire insurance policies over the goods.
Concerning the third ground, petitioner submits that there is no
subrogation in favor of respondent as no valid insurance could be
maintained thereon by IMC and LSPI since all risk had transferred to
petitioner upon delivery of the goods; that petitioner was not privy to the
insurance contract or the payment between respondent and its insured nor
was its consent or approval ever secured; that this lack of privity forecloses
any real interest on the part of respondent in the obligation to pay, limiting
its interest to keeping the insured goods safe from fire.
For its part, respondent counters that while ownership over the readymade clothing materials was transferred upon delivery to petitioner, IMC
and LSPI have insurable interest over said goods as creditors who stand to
suffer direct pecuniary loss from its destruction by fire; that petitioner is
liable for loss of the ready-made clothing materials since it failed to
overcome the presumption of liability under Article 1265 16 of the Civil
Code; that the fire was caused through petitioner's negligence in failing to
provide stringent measures of caution, care and maintenance on its
property because electric wires do not usually short circuit unless there are
defects in their installation or when there is lack of proper maintenance
and supervision of the property; that petitioner is guilty of gross and
evident bad faith in refusing to pay respondent's valid claim and should be
liable to respondent for contracted lawyer's fees, litigation expenses and
cost of suit.17
As a general rule, in petitions for review, the jurisdiction of this Court in
cases brought before it from the CA is limited to reviewing questions of law
which involves no examination of the probative value of the evidence
presented by the litigants or any of them. 18 The Supreme Court is not a
trier of facts; it is not its function to analyze or weigh evidence all over
again.19 Accordingly, findings of fact of the appellate court are generally
conclusive on the Supreme Court.20
Nevertheless, jurisprudence has recognized several exceptions in which
factual issues may be resolved by this Court, such as: (1) when the findings
are grounded entirely on speculation, surmises or conjectures; (2) when
the inference made is manifestly mistaken, absurd or impossible; (3) when
there is grave abuse of discretion; (4) when the judgment is based on a
misapprehension of facts; (5) when the findings of facts are conflicting; (6)
when in making its findings the CA went beyond the issues of the case, or
its findings are contrary to the admissions of both the appellant and the
appellee; (7) when the findings are contrary to the trial court; (8) when the
findings are conclusions without citation of specific evidence on which they
are based; (9) when the facts set forth in the petition as well as in the
petitioner's main and reply briefs are not disputed by the respondent; (10)
when the findings of fact are premised on the supposed absence of
evidence and contradicted by the evidence on record; and (11) when the
CA manifestly overlooked certain relevant facts not disputed by the
parties, which, if properly considered, would justify a different conclusion. 21
Exceptions (4), (5), (7), and (11) apply to the present petition.
At issue is the proper interpretation of the questioned insurance policy.
Petitioner claims that the CA erred in construing a fire insurance policy on
book debts as one covering the unpaid accounts of IMC and LSPI since such
insurance applies to loss of the ready-made clothing materials sold and
delivered to petitioner.
The Court disagrees with petitioner's stand.
It is well-settled that when the words of a contract are plain and readily
understood, there is no room for construction. 22 In this case, the
questioned insurance policies provide coverage for "book debts in
connection with ready-made clothing materials which have been sold or
delivered to various customers and dealers of the Insured anywhere in the
Philippines."23 ; and defined book debts as the "unpaid account still
appearing in the Book of Account of the Insured 45 days after the time of
the loss covered under this Policy."24 Nowhere is it provided in the
questioned insurance policies that the subject of the insurance is the goods
sold and delivered to the customers and dealers of the insured.
Indeed, when the terms of the agreement are clear and explicit that they
do not justify an attempt to read into it any alleged intention of the parties,
the terms are to be understood literally just as they appear on the face of
the contract.25 Thus, what were insured against were the accounts of IMC
and LSPI with petitioner which remained unpaid 45 days after the loss
through fire, and not the loss or destruction of the goods delivered.
Petitioner argues that IMC bears the risk of loss because it expressly
reserved ownership of the goods by stipulating in the sales invoices that
"[i]t is further agreed that merely for purpose of securing the payment of
the purchase price the above described merchandise remains the property
of the vendor until the purchase price thereof is fully paid." 26
The Court is not persuaded.
The present case clearly falls under paragraph (1), Article 1504 of the Civil
Code:
ART. 1504. Unless otherwise agreed, the goods remain at the seller's risk
until the ownership therein is transferred to the buyer, but when the
Page | 19
ownership therein is transferred to the buyer the goods are at the buyer's
risk whether actual delivery has been made or not, except that:
(1) Where delivery of the goods has been made to the buyer or to a bailee
for the buyer, in pursuance of the contract and the ownership in the goods
has been retained by the seller merely to secure performance by the buyer
of his obligations under the contract, the goods are at the buyer's risk from
the time of such delivery; (Emphasis supplied)
xxxx
Thus, when the seller retains ownership only to insure that the buyer will
pay its debt, the risk of loss is borne by the buyer. 27 Accordingly, petitioner
bears the risk of loss of the goods delivered.
IMC and LSPI did not lose complete interest over the goods. They have an
insurable interest until full payment of the value of the delivered goods.
Unlike the civil law concept of res perit domino, where ownership is the
basis for consideration of who bears the risk of loss, in property insurance,
one's interest is not determined by concept of title, but whether insured
has substantial economic interest in the property.28
Section 13 of our Insurance Code defines insurable interest as "every
interest in property, whether real or personal, or any relation thereto, or
liability in respect thereof, of such nature that a contemplated peril might
directly damnify the insured." Parenthetically, under Section 14 of the
same Code, an insurable interest in property may consist in: (a) an existing
interest; (b) an inchoate interest founded on existing interest; or (c) an
expectancy, coupled with an existing interest in that out of which the
expectancy arises.
Therefore, an insurable interest in property does not necessarily imply a
property interest in, or a lien upon, or possession of, the subject matter of
the insurance, and neither the title nor a beneficial interest is requisite to
the existence of such an interest, it is sufficient that the insured is so
situated with reference to the property that he would be liable to loss
should it be injured or destroyed by the peril against which it is insured. 29
Anyone has an insurable interest in property who derives a benefit from its
existence or would suffer loss from its destruction. 30 Indeed, a vendor or
seller retains an insurable interest in the property sold so long as he has
any interest therein, in other words, so long as he would suffer by its
destruction, as where he has a vendor's lien. 31 In this case, the insurable
interest of IMC and LSPI pertain to the unpaid accounts appearing in their
Books of Account 45 days after the time of the loss covered by the policies.
The next question is: Is petitioner liable for the unpaid accounts?
Art. 2207. If the plaintiff's property has been insured, and he has received
indemnity from the insurance company for the injury or loss arising out of
Page | 20
August 8, 2007
DECISION
AUSTRIA-MARTINEZ, J.:
Before us is a Petition for Review on Certiorari filed by Roberto C. Sicam, Jr.
(petitioner Sicam) and Agencia de R.C. Sicam, Inc. (petitioner corporation)
seeking to annul the Decision1 of the Court of Appeals dated March 31,
2003, and its Resolution2 dated August 8, 2003, in CA G.R. CV No. 56633.
Petitioner Sicam filed his Answer contending that he is not the real partyin-interest as the pawnshop was incorporated on April 20, 1987 and known
as Agencia de R.C. Sicam, Inc; that petitioner corporation had exercised
due care and diligence in the safekeeping of the articles pledged with it
and could not be made liable for an event that is fortuitous.
Respondents subsequently filed an Amended Complaint to include
petitioner corporation.
Page | 21
applicable to this case since the robbery incident happened in 1961 when
the criminality had not as yet reached the levels attained in the present
day; that they are at least guilty of contributory negligence and should be
held liable for the loss of jewelries; and that robberies and hold-ups are
foreseeable risks in that those engaged in the pawnshop business are
expected to foresee.
The CA concluded that both petitioners should be jointly and severally held
liable to respondents for the loss of the pawned jewelry.
Petitioners motion for reconsideration was denied in a Resolution dated
August 8, 2003.
Hence, the instant petition for review with the following assignment of
errors:
THE COURT OF APPEALS ERRED AND WHEN IT DID, IT
OPENED ITSELF TO REVERSAL, WHEN IT ADOPTED
UNCRITICALLY (IN FACT IT REPRODUCED AS ITS OWN
WITHOUT IN THE MEANTIME ACKNOWLEDGING IT) WHAT
THE RESPONDENTS ARGUED IN THEIR BRIEF, WHICH
ARGUMENT WAS PALPABLY UNSUSTAINABLE.
THE COURT OF APPEALS ERRED, AND WHEN IT DID, IT
OPENED ITSELF TO REVERSAL BY THIS HONORABLE COURT,
WHEN IT AGAIN ADOPTED UNCRITICALLY (BUT WITHOUT
ACKNOWLEDGING IT) THE SUBMISSIONS OF THE
RESPONDENTS IN THEIR BRIEF WITHOUT ADDING
ANYTHING MORE THERETO DESPITE THE FACT THAT THE
SAID ARGUMENT OF THE RESPONDENTS COULD NOT HAVE
BEEN SUSTAINED IN VIEW OF UNREBUTTED EVIDENCE ON
RECORD.9
Anent the first assigned error, petitioners point out that the CAs finding
that petitioner Sicam is personally liable for the loss of the pawned
jewelries is "a virtual and uncritical reproduction of the arguments set out
on pp. 5-6 of the Appellants brief."10
Petitioners argue that the reproduced arguments of respondents in their
Appellants Brief suffer from infirmities, as follows:
(1) Respondents conclusively asserted in paragraph 2 of
their Amended Complaint that Agencia de R.C. Sicam, Inc.
is the present owner of Agencia de R.C. Sicam Pawnshop,
and therefore, the CA cannot rule against said conclusive
assertion of respondents;
Page | 22
Our jurisdiction under Rule 45 of the Rules of Court is limited to the review
of errors of law committed by the appellate court. Generally, the findings of
fact of the appellate court are deemed conclusive and we are not dutybound to analyze and calibrate all over again the evidence adduced by the
parties in the court a quo.12 This rule, however, is not without exceptions,
such as where the factual findings of the Court of Appeals and the trial
court are conflicting or contradictory13 as is obtaining in the instant case.
However, after a careful examination of the records, we find no justification
to absolve petitioner Sicam from liability.
The CA correctly pierced the veil of the corporate fiction and adjudged
petitioner Sicam liable together with petitioner corporation. The rule is that
the veil of corporate fiction may be pierced when made as a shield to
perpetrate fraud and/or confuse legitimate issues. 14 The theory of
corporate entity was not meant to promote unfair objectives or otherwise
to shield them.15
Notably, the evidence on record shows that at the time respondent Lulu
pawned her jewelry, the pawnshop was owned by petitioner Sicam himself.
As correctly observed by the CA, in all the pawnshop receipts issued to
respondent Lulu in September 1987, all bear the words "Agencia de R. C.
Sicam," notwithstanding that the pawnshop was allegedly incorporated in
April 1987. The receipts issued after such alleged incorporation were still in
the name of "Agencia de R. C. Sicam," thus inevitably misleading, or at the
very least, creating the wrong impression to respondents and the public as
well, that the pawnshop was owned solely by petitioner Sicam and not by a
corporation.
Even petitioners counsel, Atty. Marcial T. Balgos, in his letter 16 dated
October 15, 1987 addressed to the Central Bank, expressly referred to
petitioner Sicam as the proprietor of the pawnshop notwithstanding the
alleged incorporation in April 1987.
We also find no merit in petitioners' argument that since respondents had
alleged in their Amended Complaint that petitioner corporation is the
present owner of the pawnshop, the CA is bound to decide the case on that
basis.
Section 4 Rule 129 of the Rules of Court provides that an admission, verbal
or written, made by a party in the course of the proceedings in the same
case, does not require proof. The admission may be contradicted only by
showing that it was made through palpable mistake or that no such
admission was made.
Thus, the general rule that a judicial admission is conclusive upon the
party making it and does not require proof, admits of two exceptions, to
wit: (1) when it is shown that such admission was made through palpable
mistake, and (2) when it is shown that no such admission was in fact made.
Page | 23
Petitioner Sicam had alleged in his Answer filed with the trial court that he
was not the real party-in-interest because since April 20, 1987, the
pawnshop business initiated by him was incorporated and known as
Agencia de R.C. Sicam. In the pre-trial brief filed by petitioner Sicam, he
submitted that as far as he was concerned, the basic issue was whether he
is the real party in interest against whom the complaint should be
directed.20 In fact, he subsequently moved for the dismissal of the
complaint as to him but was not favorably acted upon by the trial court.
Moreover, the issue was squarely passed upon, although erroneously, by
the trial court in its Decision in this manner:
Page | 24
Petitioners insist that they are not liable since robbery is a fortuitous event
and they are not negligent at all.
We are not persuaded.
Article 1174 of the Civil Code provides:
Art. 1174. Except in cases expressly specified by the law,
or when it is otherwise declared by stipulation, or when the
nature of the obligation requires the assumption of risk, no
person shall be responsible for those events which could
not be foreseen or which, though foreseen, were inevitable.
Fortuitous events by definition are extraordinary events not foreseeable or
avoidable. It is therefore, not enough that the event should not have been
foreseen or anticipated, as is commonly believed but it must be one
impossible to foresee or to avoid. The mere difficulty to foresee the
happening is not impossibility to foresee the same. 22
To constitute a fortuitous event, the following elements must concur: (a)
the cause of the unforeseen and unexpected occurrence or of the failure of
the debtor to comply with obligations must be independent of human will;
(b) it must be impossible to foresee the event that constitutes the caso
fortuito or, if it can be foreseen, it must be impossible to avoid; (c) the
occurrence must be such as to render it impossible for the debtor to fulfill
obligations in a normal manner; and, (d) the obligor must be free from any
participation in the aggravation of the injury or loss. 23
The burden of proving that the loss was due to a fortuitous event rests on
him who invokes it.24 And, in order for a fortuitous event to exempt one
from liability, it is necessary that one has committed no negligence or
misconduct that may have occasioned the loss. 25
It has been held that an act of God cannot be invoked to protect a person
who has failed to take steps to forestall the possible adverse consequences
of such a loss. One's negligence may have concurred with an act of God in
producing damage and injury to another; nonetheless, showing that the
immediate or proximate cause of the damage or injury was a fortuitous
event would not exempt one from liability. When the effect is found to be
partly the result of a person's participation -- whether by active
intervention, neglect or failure to act -- the whole occurrence is humanized
and removed from the rules applicable to acts of God. 26
Petitioner Sicam had testified that there was a security guard in their
pawnshop at the time of the robbery. He likewise testified that when he
started the pawnshop business in 1983, he thought of opening a vault with
the nearby bank for the purpose of safekeeping the valuables but was
discouraged by the Central Bank since pawned articles should only be
stored in a vault inside the pawnshop. The very measures which petitioners
had allegedly adopted show that to them the possibility of robbery was not
only foreseeable, but actually foreseen and anticipated. Petitioner Sicams
testimony, in effect, contradicts petitioners defense of fortuitous event.
Moreover, petitioners failed to show that they were free from any
negligence by which the loss of the pawned jewelry may have been
occasioned.
Robbery per se, just like carnapping, is not a fortuitous event. It does not
foreclose the possibility of negligence on the part of herein petitioners. In
Co v. Court of Appeals,27 the Court held:
It is not a defense for a repair shop of motor vehicles to
escape liability simply because the damage or loss of a
thing lawfully placed in its possession was due to
carnapping. Carnapping per se cannot be considered as a
fortuitous event. The fact that a thing was unlawfully
and forcefully taken from another's rightful
possession, as in cases of carnapping, does not
automatically give rise to a fortuitous event. To be
considered as such, carnapping entails more than
the mere forceful taking of another's property. It
must be proved and established that the event was
an act of God or was done solely by third parties and
that neither the claimant nor the person alleged to
be negligent has any participation. In accordance
with the Rules of Evidence, the burden of proving
that the loss was due to a fortuitous event rests on
him who invokes it which in this case is the
private respondent. However, other than the police
report of the alleged carnapping incident, no other
evidence was presented by private respondent to the
effect that the incident was not due to its fault. A police
report of an alleged crime, to which only private
respondent is privy, does not suffice to establish the
carnapping. Neither does it prove that there was no fault
on the part of private respondent notwithstanding the
parties' agreement at the pre-trial that the car was
carnapped. Carnapping does not foreclose the possibility of
fault or negligence on the part of private respondent. 28
Just like in Co, petitioners merely presented the police report of the
Paraaque Police Station on the robbery committed based on the report of
petitioners' employees which is not sufficient to establish robbery. Such
report also does not prove that petitioners were not at fault.
Page | 25
On the contrary, by the very evidence of petitioners, the CA did not err in
finding that petitioners are guilty of concurrent or contributory negligence
as provided in Article 1170 of the Civil Code, to wit:
Art. 1170. Those who in the performance of their
obligations are guilty of fraud, negligence, or delay, and
those who in any manner contravene the tenor thereof, are
liable for damages.29
Article 2123 of the Civil Code provides that with regard to pawnshops and
other establishments which are engaged in making loans secured by
pledges, the special laws and regulations concerning them shall be
observed, and subsidiarily, the provisions on pledge, mortgage and
antichresis.
The provision on pledge, particularly Article 2099 of the Civil Code,
provides that the creditor shall take care of the thing pledged with the
diligence of a good father of a family. This means that petitioners must
take care of the pawns the way a prudent person would as to his own
property.
In this connection, Article 1173 of the Civil Code further provides:
Art. 1173. The fault or negligence of the obligor consists in
the omission of that diligence which is required by the
nature of the obligation and corresponds with the
circumstances of the persons, of time and of the place.
When negligence shows bad faith, the provisions of Articles
1171 and 2201, paragraph 2 shall apply.
If the law or contract does not state the diligence which is
to be observed in the performance, that which is expected
of a good father of a family shall be required.
We expounded in Cruz v. Gangan30 that negligence is the omission to do
something which a reasonable man, guided by those considerations which
ordinarily regulate the conduct of human affairs, would do; or the doing of
something which a prudent and reasonable man would not do. 31 It is want
of care required by the circumstances.
A review of the records clearly shows that petitioners failed to exercise
reasonable care and caution that an ordinarily prudent person would have
used in the same situation. Petitioners were guilty of negligence in the
operation of their pawnshop business. Petitioner Sicam testified, thus:
Court:
Q. Do you have security guards in your pawnshop?
Page | 26
Page | 27
cellular phone. She then reported the incident to the police authorities;
however, the thief was not located, and the cellphone was not recovered.
She also reported the loss to the Regional Director of TESDA, and she
requested that she be freed from accountability for the cellphone. The
Resident Auditor denied her request on the ground that she lacked the
diligence required in the custody of government property and was ordered
to pay the purchase value in the total amount of P4,238.00. The COA found
no sufficient justification to grant the request for relief from accountability.
We reversed the ruling and found that riding the LRT cannot per se be
denounced as a negligent act more so because Cruzs mode of transit was
influenced by time and money considerations; that she boarded the LRT to
be able to arrive in Caloocan in time for her 3 pm meeting; that any
prudent and rational person under similar circumstance can reasonably be
expected to do the same; that possession of a cellphone should not hinder
one from boarding the LRT coach as Cruz did considering that whether she
rode a jeep or bus, the risk of theft would have also been present; that
because of her relatively low position and pay, she was not expected to
have her own vehicle or to ride a taxicab; she did not have a government
assigned vehicle; that placing the cellphone in a bag away from covetous
eyes and holding on to that bag as she did is ordinarily sufficient care of a
cellphone while traveling on board the LRT; that the records did not show
any specific act of negligence on her part and negligence can never be
presumed.
Unlike in the Cruz case, the robbery in this case happened in petitioners'
pawnshop and they were negligent in not exercising the precautions justly
demanded of a pawnshop.
WHEREFORE, except for the insurance aspect, the Decision of the Court of
Appeals dated March 31, 2003 and its Resolution dated August 8, 2003, are
AFFIRMED.
Costs against petitioners.
SO ORDERED.
December 4, 2013
Page | 28
Assailed in this petition for review on certiorari 1 are the Decision2 dated
February 12, 2007 and the Resolution 3 dated May 10, 2007 of the Court of
Appeals (CA) in CA-G.R. CV No. 86896 which reversed and set aside the
Decision4 dated January 17, 2006 of the Regional Trial Court of Makati,
Branch 57 (RTC) in Civil Case No. 00-1563, thereby ordering petitioners
Metro Concast Steel Corporation (Metro Concast), Spouses Jose S. Dychiao
and Tiu Oh Yan, Spouses Guillermo and Mercedes Dychiao, and Spouses
Vicente and Filomena Duchiao (individual petitioners) to solidarily pay
respondent Allied Bank Corporation (Allied Bank) the aggregate amount of
P51,064,094.28, with applicable interests and penalty charges.
The Facts
On various dates and for different amounts, Metro Concast, a corporation
duly organized and existing under and by virtue of Philippine laws and
engaged in the business of manufacturing steel, 5 through its officers,
herein individual petitioners, obtained several loans from Allied Bank.
These loan transactions were covered by a promissory note and separate
letters of credit/trust receipts, the details of which are as follows:
<<Reference: http://www.scribd.com/doc/196404620/177921>>
Date Document Amount
December 13, 1996 Promissory Note No. 96-21301 6
P2,000,000.00 November 7, 1995 Trust Receipt No. 96-202365 7
P608,603.04 May 13, 1996 Trust Receipt No. 96-9605228
P3,753,777.40 May 24, 1996 Trust Receipt No. 96-960524 9
P4,602,648.08 March 21, 1997 Trust Receipt No. 97-20472410
P7,289,757.79 June 7, 1996 Trust Receipt No. 96-203280 11
P17,340,360.73 July 26, 1995 Trust Receipt No. 95-20194312
P670,709.24 August 31, 1995 Trust Receipt No. 95-20205313
P313,797.41 November 16, 1995 Trust Receipt No. 96-20243914
Page | 29
(a) their failure to pay their outstanding loan obligations to Allied Bank
must be considered as force majeure ; and
(b) since Allied Bank was the party that accepted the terms and conditions
of payment proposed by Peakstar, petitioners must therefore be deemed to
have settled their obligations to Allied Bank. To bolster their defense,
petitioner Jose Dychiao (Jose Dychiao) testified 28 during trial that it was
Atty. Saw himself who drafted the MoA and subsequently received 29 the
P2,000,000.00 cash and the two (2) Bankwise post-dated checks worth
P1,000,000.00 each from Camiling. However, Atty. Saw turned over only
the two (2) checks and P1,500,000.00 in cash to the wife of Jose Dychiao. 30
Claiming that the subject complaint was falsely and maliciously filed,
petitioners prayed for the award of moral damages in the amount of
P20,000,000.00 in favor of Metro Concast and at least P25,000,000.00 for
each individual petitioner, P25,000,000.00 as exemplary damages,
P1,000,000.00 as attorneys fees, P500,000.00 for other litigation
expenses, including costs of suit.
The RTC Ruling
It also added that "[i]n the final analysis, the aforesaid checks and receipts
were signed by [Atty.] Saw either as representative of [petitioners] or as
partner of the latters legal counsel, and not in anyway as representative of
[Allied Bank]."36
Consequently, the CA granted the appeal and directed petitioners to
solidarily pay Allied Bank their corresponding obligations under the
aforementioned promissory note and trust receipts, plus interests, penalty
charges and attorneys fees. Petitioners sought reconsideration 37 which
was, however, denied in a Resolution 38 dated May 10, 2007. Hence, this
petition.
The Issue Before the Court
After trial on the merits, the RTC, in a Decision dated January 17, 2006,
dismissed the subject complaint, holding that the "causes of action sued
upon had been paid or otherwise extinguished." It ruled that since Allied
Bank was duly represented by its agent, Atty. Saw, in all the negotiations
and transactions with Peakstar considering that Atty. Saw
31
At the core of the present controversy is the sole issue of whether or not
the loan obligations incurred by the petitioners under the subject
promissory note and various trust receipts have already been extinguished.
The Courts Ruling
Article 1231 of the Civil Code states that obligations are extinguished
either by payment or performance, the loss of the thing due, the
condonation or remission of the debt, the confusion or merger of the rights
of creditor and debtor, compensation or novation.
In the present case, petitioners essentially argue that their loan obligations
to Allied Bank had already been extinguished due to Peakstars failure to
perform its own obligations to Metro Concast pursuant to the MoA.
Petitioners classify Peakstars default as a form of force majeure in the
sense that they have, beyond their control, lost the funds they expected to
have received from the Peakstar (due to the MoA) which they would, in
turn, use to pay their own loan obligations to Allied Bank. They further
state that Allied Bank was equally bound by Metro Concasts MoA with
Page | 30
Peakstar since its agent, Atty. Saw, actively represented it during the
negotiations and execution of the said agreement. Petitioners arguments
are untenable. At the outset, the Court must dispel the notion that the MoA
would have any relevance to the performance of petitioners obligations to
Allied Bank. The MoA is a sale of assets contract, while petitioners
obligations to Allied Bank arose from various loan transactions. Absent any
showing that the terms and conditions of the latter transactions have been,
in any way, modified or novated by the terms and conditions in the MoA,
said contracts should be treated separately and distinctly from each other,
such that the existence, performance or breach of one would not depend
on the existence, performance or breach of the other. In the foregoing
respect, the issue on whether or not Allied Bank expressed its conformity
to the assets sale transaction between Metro Concast and Peakstar (as
evidenced by the MoA) is actually irrelevant to the issues related to
petitioners loan obligations to the bank. Besides, as the CA pointed out,
the fact of Allied Banks representation has not been proven in this case
and hence, cannot be deemed as a sustainable defense to exculpate
petitioners from their loan obligations to Allied Bank. Now, anent
petitioners reliance on force majeure, suffice it to state that Peakstars
breach of its obligations to Metro Concast arising from the MoA cannot be
classified as a fortuitous event under jurisprudential formulation. As
discussed in Sicam v. Jorge:39
DECISION
While it may be argued that Peakstars breach of the MoA was unforseen
by petitioners, the same us clearly not "impossible"to foresee or even an
event which is independent of human will." Neither has it been shown that
said occurrence rendered it impossible for petitioners to pay their loan
obligations to Allied Bank and thus, negates the formers force majeure
theory altogether. In any case, as earlier stated, the performance or breach
of the MoA bears no relation to the performance or breach of the subject
loan transactions, they being separate and distinct sources of obligations.
The fact of the matter is that petitioners loan obligations to Allied Bank
remain subsisting for the basic reason that the former has not been able to
prove that the same had already been paid 41 or, in any way, extinguished.
In this regard, petitioners liability, as adjudged by the CA, must perforce
WHEREFORE, the petition is DENIED. The Decision dated February 12, 2007
and Resolution dated May 10, 2007 of the Court of Appeals in CA-G.R. CV
No. 86896 are hereby AFFIRMED with MODIFICATION reckoning the
applicable interests and penalty charges from the date of the extrajudicial
demand or on December 10, 1998. The rest of the appellate courts
dispositions stand.
SO ORDERED.
G.R. No. 118180. September 20, 1996]
DEVELOPMENT BANK OF THE PHILIPPINES, petitioner, vs. COURT OF
APPEALS, Sps. NORMY D. CARPIO and CARMEN ORQUISA; Sps. ROLANDO D.
CARPIO and RAFAELA VILLANUEVA; Sps. ELISEO D. CARPIO and
ANUNCIACION del ROSARIO; LUZ C. REYES, MARIO C. REYES, JULIET REYESRUBIN, respondents.
PADILLA, J.:
This is a petition for review on certiorari under Rule 45 of the Rules of Court
which seeks to set aside the decision xxviii of the Court of Appeals (CA) dated
28 February 1994 in C.A.-G.R. CV No. 37158, as well as the resolution
dated 11 August 1994 denying petitioner's motion for reconsideration.
The facts are undisputed:
Private respondents were the original owners of a parcel of agricultural
land covered by TCT No. T-1432, situated in Barrio Capucao, Ozamis City,
with an area of 113,695 square meters, more or less.
On 30 May 1977, private respondents mortgaged said land to petitioner.
When private respondents defaulted on their obligation, petitioner
foreclosed the mortgage on the land and emerged as sole bidder in the
ensuing auction sale. Consequently, Transfer Certificate of Title No. T10913 was eventually issued in petitioner's name.
On 6 April 1984, petitioner and private respondents entered into a Deed of
Conditional Sale wherein petitioner agreed to reconvey the foreclosed
property to private respondents.
Page | 31
xxx
The trial court held that petitioner interpreted the fourth paragraph of Sec.
6, Rep. Act 6657 literally in conjunction with Sec. 1 of E.O. 407.
xxx
xxx
xxx
while Sec. 1 of E.O. 407 states that:
That, upon completion of the payment herein stipulated and agreed, the
Vendor agrees to deliver to the Vendee/s(,) his heirs, administrators and
assigns(,) a good and sufficient deed of conveyance covering the property,
subject matter of this deed of conditional sale, in accordance with the
provisions of law." (Exh. "A", p. 5, Records)xxix
On 6 April 1990, upon completing the payment of the full repurchase price,
private respondents demanded from petitioner the execution of a Deed of
Conveyance in their favor.
Petitioner then informed private respondents that the prestation to execute
and deliver a deed of conveyance in their favor had become legally
impossible in view of Sec. 6 of Rep. Act 6657 (the Comprehensive Agrarian
Reform Law or CARL) approved 10 June 1988, and Sec. 1 of E.O. 407 issued
10 June 1990.
Aggrieved, private respondents filed a complaint for specific performance
with damages against petitioner before the Regional Trial Court of Ozamis
City, Branch XV. During the pre-trial, the trial court narrowed down the
issue to whether or not Sec. 6 of the CARL (Rep. Act 6657) had rendered
legally impossible compliance by petitioner with its obligation to execute a
deed of conveyance of the subject land in favor of private respondents.
The trial court ordered both parties to file their separate memorandum and
deemed the case submitted for decision thereafter.
On 30 January 1992, the trial court rendered judgment, the dispositive part
of which reads:
Page | 32
"It is a rule that if the obligation depends upon a suspensive condition, the
demandability as well as the acquisition or effectivity of the rights arising
from the obligation is suspended pending the happening or fulfillment of
the fact or event which constitutes the condition. Once the event which
constitutes the condition is fulfilled resulting in the effectivity of the
obligation, its effects retroact to the moment when the essential elements
which gave birth to the obligation have taken place (8 Manresa, 5th Ed. Bk.
1, pa. 33). Applying this precept to the case, the full payment by the
appellee on April 6, 1990 retroacts to the time the contract of conditional
sale was executed on April 6, 1984. From that time, all elements of the
contract of sale were present. Consequently, the contract of sale was
perfected. As such, the said sale does not come under the coverage of
R.A. 6657.
It is likewise interesting to note that despite the mandate of Sec. 1, R.A.
6657, appellant continued to accept the payments made by the appellee
until it was fully paid on April 6, 1990. All that the appellant has to do now
is to execute the final deed of sale in favor of the appellee. To follow the
line of argument of the appellant would only result in an unconscionable
injury to the appellee. Obligations arising from contracts have the force of
law between the contracting parties and should be complied with in good
faith (Flavio Macasaet & Associates, Inc. vs. Commission on Audit, 173
SCRA 352).
Going now to E.O. 407, We hold that the same can neither affect
appellant's obligation under the deed of conditional sale. Under the said
law, appellant is required to transfer to the Republic of the Philippines 'all
lands foreclosed' effective June 10, 1990. Under the facts obtaining, the
subject property has ceased to belong to the mass of foreclosed property
falling within the reach of said law. As earlier explained, the property has
already been sold to herein appellees even before the said E.O. has been
enacted. On this same reason, We therefore need not delve on the
applicability of DBP Circular No. 11."xxxi
In the present petition for review on certiorari, petitioner still insists on its
position that Rep. Act 6657, E.O. 407 and DBP Circular No. 11 rendered its
obligation to execute a Deed of Sale to private respondents "a legal
impossibility."xxxii Petitioner also questions the award of attorney's fees,
nominal damages, and costs in favor of private respondents, as not in
accord with law and the evidence.xxxiii
We rule in favor of private respondents.
In conditional obligations, the acquisition of rights, as well as the
extinguishment or loss of those already acquired, shall depend upon the
happening of the event which constitutes the condition. xxxiv
The deed of conditional sale between petitioner and private respondents
was executed on 6 April 1984. Private respondents had religiously paid the
Page | 33
The award of attorney's fees under Article 2208 of the Civil Code is more of
an exception to the general rule that it is not sound policy to place a
penalty on the right to litigate. While judicial discretion in the award of
attorney's fees is not entirely left out, the same, as a rule, must have a
factual, legal or equitable justification. The matter cannot and should not
be left to speculation and conjecture.xxxvi
BELLOSILLO, J.:
Sometime in 1939, the late Don Ramon Lopez, Sr., who was then a
member of the Board of Trustees of the Central Philippine College (now
Central Philippine University [CPU]), executed a deed of donation in favor
of the latter of a parcel of land identified as Lot No. 3174-B-1 of the
subdivision plan Psd-1144, then a portion of Lot No. 3174-B, for which
Transfer Certificate of Title No. T-3910-A was issued in the name of the
donee CPU with the following annotations copied from the deed of donation
"x x x The matter of attorney's fees cannot be touched once and only in
the dispositive portion of the decision. The text itself must expressly state
the reason why attorney's fees are being awarded. The court, after
reading through the text of the appealed decision, finds the same bereft of
any findings of fact and law to justify the award of attorney's fees. The
matter of such fees was touched but once and appears only in the
dispositive portion of the decision. Simply put, the text of the decision did
not state the reason why attorney's fees are being awarded, and for this
reason, the Court finds it necessary to disallow the same for being
conjectural."xxxvii
While DBP committed egregious error in interpreting Sec. 6 of RA 6657, the
same is not equivalent to gross and evident bad faith when it refused to
execute the deed of sale in favor of private respondents.
For the same reasons stated above, the award of nominal damages in the
amount of P10,000.00 should also be deleted.
The amount of P3,000.00 as litigation expenses and costs against
petitioner must remain.
WHEREFORE, premises considered, the petition is hereby DENIED, and
the decision of the CA is hereby AFFIRMED, for lack of any reversible error,
with the MODIFICATION that attorney's fees and nominal damages awarded
to private respondents are hereby DELETED.
SO ORDERED.
G.R. No. 112127 July 17, 1995
CENTRAL
PHILIPPINE
UNIVERSITY,
petitioner,
vs.
COURT OF APPEALS, REMEDIOS FRANCO, FRANCISCO N. LOPEZ,
CECILIA P. VDA. DE LOPEZ, REDAN LOPEZ AND REMARENE LOPEZ,
respondents.
Page | 34
On 31 May 1991, the trial court held that petitioner failed to comply with
the conditions of the donation and declared it null and void. The court a
quo further directed petitioner to execute a deed of the reconveyance of
the property in favor of the heirs of the donor, namely, private respondents
herein.
Petitioner appealed to the Court of Appeals which on 18 June 1993 ruled
that the annotations at the back of petitioner's certificate of title were
resolutory conditions breach of which should terminate the rights of the
donee thus making the donation revocable.
The appellate court also found that while the first condition mandated
petitioner to utilize the donated property for the establishment of a
medical school, the donor did not fix a period within which the condition
must be fulfilled, hence, until a period was fixed for the fulfillment of the
condition, petitioner could not be considered as having failed to comply
with its part of the bargain. Thus, the appellate court rendered its decision
reversing the appealed decision and remanding the case to the court of
origin for the determination of the time within which petitioner should
comply with the first condition annotated in the certificate of title.
Petitioner now alleges that the Court of Appeals erred: (a) in holding that
the quoted annotations in the certificate of title of petitioner are onerous
obligations and resolutory conditions of the donation which must be
fulfilled non-compliance of which would render the donation revocable; (b)
in holding that the issue of prescription does not deserve "disquisition;"
and, (c) in remanding the case to the trial court for the fixing of the period
within which petitioner would establish a medical college. 2
We find it difficult to sustain the petition. A clear perusal of the conditions
set forth in the deed of donation executed by Don Ramon Lopez, Sr., gives
us no alternative but to conclude that his donation was onerous, one
executed for a valuable consideration which is considered the equivalent of
the donation itself, e.g., when a donation imposes a burden equivalent to
the value of the donation. A gift of land to the City of Manila requiring the
latter to erect schools, construct a children's playground and open streets
on the land was considered an onerous donation. 3 Similarly, where Don
Ramon Lopez donated the subject parcel of land to petitioner but imposed
an obligation upon the latter to establish a medical college thereon, the
donation must be for an onerous consideration.
Under Art. 1181 of the Civil Code, on conditional obligations, the
acquisition of rights, as well as the extinguishment or loss of those already
acquired, shall depend upon the happening of the event which constitutes
the condition. Thus, when a person donates land to another on the
condition that the latter would build upon the land a school, the condition
imposed was not a condition precedent or a suspensive condition but a
resolutory one. 4 It is not correct to say that the schoolhouse had to be
constructed before the donation became effective, that is, before the
donee could become the owner of the land, otherwise, it would be invading
the property rights of the donor. The donation had to be valid before the
fulfillment of the condition. 5 If there was no fulfillment or compliance with
the condition, such as what obtains in the instant case, the donation may
now be revoked and all rights which the donee may have acquired under it
shall be deemed lost and extinguished.
The claim of petitioner that prescription bars the instant action of private
respondents is unavailing.
The condition imposed by the donor, i.e., the building of a
medical school upon the land donated, depended upon the
exclusive will of the donee as to when this condition shall
be fulfilled. When petitioner accepted the donation, it
bound itself to comply with the condition thereof. Since the
time within which the condition should be fulfilled
depended upon the exclusive will of the petitioner, it has
been held that its absolute acceptance and the
acknowledgment of its obligation provided in the deed of
donation were sufficient to prevent the statute of
limitations from barring the action of private respondents
upon the original contract which was the deed of donation.
6
Moreover, the time from which the cause of action accrued for the
revocation of the donation and recovery of the property donated cannot be
specifically determined in the instant case. A cause of action arises when
that which should have been done is not done, or that which should not
have been done is done. 7 In cases where there is no special provision for
such computation, recourse must be had to the rule that the period must
be counted from the day on which the corresponding action could have
been instituted. It is the legal possibility of bringing the action which
determines the starting point for the computation of the period. In this
case, the starting point begins with the expiration of a reasonable period
and opportunity for petitioner to fulfill what has been charged upon it by
the donor.
The period of time for the establishment of a medical college and the
necessary buildings and improvements on the property cannot be
quantified in a specific number of years because of the presence of several
factors and circumstances involved in the erection of an educational
institution, such as government laws and regulations pertaining to
education, building requirements and property restrictions which are
beyond the control of the donee.
Thus, when the obligation does not fix a period but from its nature and
circumstances it can be inferred that a period was intended, the general
rule provided in Art. 1197 of the Civil Code applies, which provides that the
courts may fix the duration thereof because the fulfillment of the obligation
Page | 35
itself cannot be demanded until after the court has fixed the period for
compliance therewith and such period has arrived. 8
This general rule however cannot be applied considering the different set
of circumstances existing in the instant case. More than a reasonable
period of fifty (50) years has already been allowed petitioner to avail of the
opportunity to comply with the condition even if it be burdensome, to
make the donation in its favor forever valid. But, unfortunately, it failed to
do so. Hence, there is no more need to fix the duration of a term of the
obligation when such procedure would be a mere technicality and formality
and would serve no purpose than to delay or lead to an unnecessary and
expensive multiplication of suits. 9 Moreover, under Art. 1191 of the Civil
Code, when one of the obligors cannot comply with what is incumbent
upon him, the obligee may seek rescission and the court shall decree the
same unless there is just cause authorizing the fixing of a period. In the
absence of any just cause for the court to determine the period of the
compliance, there is no more obstacle for the court to decree the rescission
claimed.
Finally, since the questioned deed of donation herein is basically a
gratuitous one, doubts referring to incidental circumstances of a gratuitous
contract should be resolved in favor of the least transmission of rights and
interests. 10 Records are clear and facts are undisputed that since the
execution of the deed of donation up to the time of filing of the instant
action, petitioner has failed to comply with its obligation as donee.
Petitioner has slept on its obligation for an unreasonable length of time.
Hence, it is only just and equitable now to declare the subject donation
already ineffective and, for all purposes, revoked so that petitioner as
donee should now return the donated property to the heirs of the donor,
private respondents herein, by means of reconveyance.
WHEREFORE, the decision of the Regional Trial Court of Iloilo, Br. 34, of 31
May 1991 is REINSTATED and AFFIRMED, and the decision of the Court of
Appeals of 18 June 1993 is accordingly MODIFIED. Consequently, petitioner
is directed to reconvey to private respondents Lot No. 3174-B-1 of the
subdivision plan Psd-1144 covered by Transfer Certificate of Title No. T3910-A within thirty (30) days from the finality of this judgment.
MELO, J.:
The deed of conveyance executed on May 28, 1975 by Juan Galicia, Sr.,
prior to his demise in 1979, and Celerina Labuguin, in favor of Albrigido
Leyva involving the undivided one-half portion of a piece of land situated
at Poblacion, Guimba, Nueva Ecija for the sum of P50,000.00 under the
following terms:
1. The sum of PESOS: THREE THOUSAND
(P3,000.00) is HEREBY acknowledged to have been
paid upon the execution of this agreement;
2. The sum of PESOS: TEN THOUSAND (P10,000.00)
shall be paid within ten (10) days from and after
the execution of this agreement;
3. The sum of PESOS: TEN THOUSAND (P10,000.00)
represents the VENDORS' indebtedness with the
Philippine Veterans Bank which is hereby assumed
by the VENDEE; and
4. The balance of PESOS: TWENTY SEVEN
THOUSAND (P27,000.00.) shall be paid within one
(1) year from and after the execution of this
instrument. (p. 53, Rollo)
is the subject matter of the present litigation between the heirs of Juan
Galicia, Sr. who assert breach of the conditions as against private
respondent's claim anchored on full payment and compliance with the
stipulations thereof.
The court of origin which tried the suit for specific performance filed by
private respondent on account of the herein petitioners' reluctance to
abide by the covenant, ruled in favor of the vendee (p. 64, Rollo) while
respondent court practically agreed with the trial court except as to the
amount to be paid to petitioners and the refund to private respondent are
concerned (p. 46, Rollo).
There is no dispute that the sum of P3,000.00 listed as first installment was
received by Juan Galicia, Sr. According to petitioners, of the P10,000.00 to
be paid within ten days from execution of the instrument, only P9,707.00
Page | 36
was tendered to, and received by, them on numerous occasions from May
29, 1975, up to November 3, 1979. Concerning private respondent's
assumption of the vendors' obligation to the Philippine Veterans Bank, the
vendee paid only the sum of P6,926.41 while the difference the
indebtedness came from Celerina Labuguin (p. 73, Rollo). Moreover,
petitioners asserted that not a single centavo of the P27,000.00
representing the remaining balance was paid to them. Because of the
apprehension that the heirs of Juan Galicia, Sr. are disavowing the contract
inked by their predecessor, private respondent filed the complaint for
specific performance.
and following the appeal interposed with respondent court, Justice Dayrit
with whom Justices Purisima and Aldecoa, Jr. concurred, modified the fourth
paragraph of the decretal portion to read:
4. Ordering the withdrawal of the amount of
P18,500.00 now consigned with the Court, and that
the amount of P16,870.52 be delivered to the heirs
of Juan Galicia, Sr. as payment to the unpaid
balance of the sale, including the reimbursement of
the amount paid to Philippine Veterans Bank,
minus the amount of attorney's fees and damages
awarded in favor of plaintiff. The excess of
P1,649.48 will be returned to plaintiff. The costs
against defendants. (p. 51, Rollo)
As to how the foregoing directive was arrived at, the appellate court
declared:
With respect to the fourth condition stipulated in
the contract, the period indicated therein is
deemed modified by the parties when the heirs of
Juan Galicia, Sr. accepted payments without
objection up to November 3, 1979. On the basis of
receipts presented by appellee commencing from
August 8, 1975 up to November 3, 1979, a total
amount of P13,908.25 has been paid, thereby
leaving a balance of P13,091.75. Said unpaid
Page | 37
Page | 38
may, upon non-fulfillment by the other privy of his part of the prestation,
rescind the contract or seek fulfillment (Article 1191, Civil Code). In short, it
is puerile for petitioners to say that they are the only obligees under the
contract since they are also bound as obligors to respect the stipulation in
permitting private respondent to assume the loan with the Philippine
Veterans Bank which petitioners impeded when they paid the balance of
said loan. As vendors, they are supposed to execute the final deed of sale
upon full payment of the balance as determined hereafter.
Lastly, petitioners argue that there was no valid tender of payment nor
consignation of the sum of P18,520.00 which they acknowledge to have
been deposited in court on January 22, 1981 five years after the amount of
P27,000.00 had to be paid (p. 23, Memorandum for Petitioners; p. 162,
Rollo). Again this suggestion ignores the fact that consignation alone
produced the effect of payment in the case at bar because it was
established below that two or more heirs of Juan Galicia, Sr. claimed the
same right to collect (Article 1256, (4), Civil Code; pp. 4-5, Decision in Civil
Case No. 681-G; pp. 67-68, Rollo). Moreover, petitioners did not bother to
refute the evidence on hand that, aside from the P18,520.00 (not
P18,500.00 as computed by respondent court) which was consigned,
private respondent also paid the sum of P13,908.25 (Exhibits "F" to "CC";
p. 50, Rollo). These two figures representing private respondent's payment
of the fourth condition amount to P32,428.25, less the P3,778.77 paid by
petitioners to the bank, will lead us to the sum of P28,649.48 or a refund of
P1,649.48 to private respondent as overpayment of the P27,000.00
balance.
WHEREFORE, the petition is hereby DISMISSED and the decision appealed
from is hereby AFFIRMED with the slight modification of Paragraph 4 of the
dispositive thereof which is thus amended to read:
4. ordering the withdrawal of the sum of
P18,520.00 consigned with the Regional Trial Court,
and that the amount of P16,870.52 be delivered by
private respondent with legal rate of interest until
fully paid to the heirs of Juan Galicia, Sr. as balance
of the sale including reimbursement of the sum
paid to the Philippine Veterans Bank, minus the
attorney's fees and damages awarded in favor of
private respondent. The excess of P1,649.48 shall
be returned to private respondent also with legal
interest until fully paid by petitioners. With costs
against petitioners.
SPS.
FELIPE
AND
LETICIA
CANNU,
petitioners,
vs.
SPS. GIL AND FERNANDINA GALANG AND NATIONAL HOME
MORTGAGE FINANCE CORPORATION, respondents.
DECISION
CHICO-NAZARIO, J.:
Before Us is a Petition for Review on Certiorari which seeks to set aside the
decision1 of the Court of Appeals dated 30 September 1998 which affirmed
with modification the decision of Branch 135 of the Regional Trial Court
(RTC) of Makati City, dismissing the complaint for Specific Performance and
Damages filed by petitioners, and its Resolution 2 dated 22 July 1999
denying petitioners motion for reconsideration.
A complaint3 for Specific Performance and Damages was filed by
petitioners-spouses Felipe and Leticia Cannu against respondents-spouses
Gil and Fernandina Galang and the National Home Mortgage Finance
Corporation (NHMFC) before Branch 135 of the RTC of Makati, on 24 June
1993. The case was docketed as Civil Case No. 93-2069.
The facts that gave rise to the aforesaid complaint are as follows:
Respondents-spouses Gil and Fernandina Galang obtained a loan from
Fortune Savings & Loan Association for P173,800.00 to purchase a house
and lot located at Pulang Lupa, Las Pias, with an area of 150 square
meters covered by Transfer Certificate of Title (TCT) No. T-8505 in the
names of respondents-spouses. To secure payment, a real estate mortgage
was constituted on the said house and lot in favor of Fortune Savings &
Loan Association. In early 1990, NHMFC purchased the mortgage loan of
respondents-spouses from Fortune Savings & Loan Association for
P173,800.00.
Respondent Fernandina Galang authorized4 her attorney-in-fact, Adelina R.
Timbang, to sell the subject house and lot.
Petitioner Leticia Cannu agreed to buy the property for P120,000.00 and to
assume the balance of the mortgage obligations with the NHMFC and with
CERF Realty5 (the Developer of the property).
Of the P120,000.00, the following payments were made by petitioners:
SO ORDERED.
G.R. No. 139523
Date
Amount Paid
Page | 39
April 6, 1991
Total
P40,000.00
Date
Amount
Receipt No.
July 9, 1990
P 14,312.47
D-50398611
8,000.00
D-72947812
February 4, 1992
10,000.00
D-99912713
6,000.00
E-56374914
10,000.00
E-58243215
7,000.00
E-61832616
15,000.007
15,000.008
5,000.009
P75,000.00
P 55,312.47
Page | 40
Page | 41
...
Page | 42
Page | 43
We do not agree.
There is sufficient evidence showing that demands were made from
petitioners to comply with their obligation. Adelina R. Timbang, attorney-infact of respondents-spouses, per instruction of respondent Fernandina
Galang, made constant follow-ups after the last payment made on 28
November 1991, but petitioners did not pay. 44 Respondent Fernandina
Galang stated in her Answer45 that upon her arrival from America in
October 1992, she demanded from petitioners the complete compliance of
their obligation by paying the full amount of the consideration
(P120,000.00) or in the alternative to vacate the property in question, but
still, petitioners refused to fulfill their obligations under the Deed of Sale
with Assumption of Mortgage. Sometime in March 1993, due to the fact
that full payment has not been paid and that the monthly amortizations
with the NHMFC have not been fully updated, she made her intentions
clear with petitioner Leticia Cannu that she will rescind or annul the Deed
of Sale with Assumption of Mortgage.
We likewise rule that there was no waiver on the part of petitioners to
demand the rescission of the Deed of Sale with Assumption of Mortgage.
The fact that respondents-spouses accepted, through their attorney-in-fact,
payments in installments does not constitute waiver on their part to
exercise their right to rescind the Deed of Sale with Assumption of
Mortgage. Adelina Timbang merely accepted the installment payments as
an accommodation to petitioners since they kept on promising they would
pay. However, after the lapse of considerable time (18 months from last
payment) and the purchase price was not yet fully paid, respondentsspouses exercised their right of rescission when they paid the outstanding
balance of the mortgage loan with NHMFC. It was only after petitioners
stopped paying that respondents-spouses moved to exercise their right of
rescission.
Petitioners cite the case of Angeles v. Calasanz46 to support their claim that
respondents-spouses waived their right to rescind. We cannot apply this
case since it is not on all fours with the case before us. First, in Angeles,
the breach was only slight and casual which is not true in the case before
us. Second, in Angeles, the buyer had already paid more than the principal
obligation, while in the instant case, the buyers (petitioners) did not pay
P45,000.00 of the P120,000.00 they were obligated to pay.
We find petitioners statement that there is no evidence of prejudice or
damage to justify rescission in favor of respondents-spouses to be
unfounded. The damage suffered by respondents-spouses is the effect of
petitioners failure to fully comply with their obligation, that is, their failure
to pay the remaining P45,000.00 and to update the amortizations on the
mortgage loan with the NHMFC. Petitioners have in their possession the
property under litigation. Having parted with their house and lot,
respondents-spouses should be fully compensated for it, not only
monetarily, but also as to the terms and conditions agreed upon by the
parties. This did not happen in the case before us.
Citing Seva v. Berwin & Co., Inc.,47 petitioners argue that no rescission
should be decreed because there is no evidence on record that respondent
Fernandina Galang is ready, willing and able to comply with her own
obligation to restore to them the total payments they made. They added
that no allegation to that effect is contained in respondents-spouses
Answer.
We find this argument to be misleading.
First, the facts obtaining in Seva case do not fall squarely with the case on
hand. In the former, the failure of one party to perform his obligation was
the fault of the other party, while in the case on hand, failure on the part of
petitioners to perform their obligation was due to their own fault.
Second, what is stated in the book of Justice Edgardo L. Paras is "[i]t
(referring to the right to rescind or resolve) can be demanded only if the
plaintiff is ready, willing and able to comply with his own obligation, and
the other is not." In other words, if one party has complied or fulfilled his
obligation, and the other has not, then the former can exercise his right to
rescind. In this case, respondents-spouses complied with their obligation
when they gave the possession of the property in question to petitioners.
Thus, they have the right to ask for the rescission of the Deed of Sale with
Assumption of Mortgage.
On the fourth assigned error, petitioners, relying on Article 1383 of the Civil
Code, maintain that the Court of Appeals erred when it failed to consider
that the action for rescission is subsidiary.
Their reliance on Article 1383 is misplaced.
The subsidiary character of the action for rescission applies to contracts
enumerated in Articles 138148 of the Civil Code. The contract involved in
the case before us is not one of those mentioned therein. The provision
that applies in the case at bar is Article 1191.
In the concurring opinion of Justice Jose B.L. Reyes in Universal Food Corp.
v. Court of Appeals,49 rescission under Article 1191 was distinguished from
rescission under Article 1381. Justice J.B.L. Reyes said:
. . . The rescission on account of breach of stipulations is
not predicated on injury to economic interests of the party
plaintiff but on the breach of faith by the defendant, that
violates the reciprocity between the parties. It is not a
subsidiary action, and Article 1191 may be scanned
without disclosing anywhere that the action for rescission
thereunder is subordinated to anything other than the
culpable breach of his obligations by the defendant. This
rescission is a principal action retaliatory in character, it
Page | 44
MANUEL
C.
PAGTALUNAN,
petitioner,
vs.
RUFINA DELA CRUZ VDA. DE MANZANO, respondent.
DECISION
AZCUNA, J.:
Page | 45
This is a petition for review on certiorari under Rule 45 of the Rules of Court
of the Court of Appeals (CA) Decision promulgated on October 30, 2000
and its Resolution dated March 23, 2001 denying petitioners motion for
reconsideration. The Decision of the CA affirmed the Decision of the
Regional Trial Court (RTC) of Malolos, Bulacan, dated June 25, 1999
dismissing the case of unlawful detainer for lack of merit.
The facts are as follows:
On July 19, 1974, Patricio Pagtalunan (Patricio), petitioners stepfather and
predecessor-in-interest, entered into a Contract to Sell with respondent,
wife of Patricios former mechanic, Teodoro Manzano, whereby the former
agreed to sell, and the latter to buy, a house and lot which formed half of a
parcel of land, covered by Transfer Certificate of Title (TCT) No. T-10029
(now TCT No. RT59929 [T-254773]), with an area of 236 square meters. The
consideration of P17,800 was agreed to be paid in the following manner:
P1,500 as downpayment upon execution of the Contract to Sell, and the
balance to be paid in equal monthly installments of P150 on or before the
last day of each month until fully paid.
It was also stipulated in the contract that respondent could immediately
occupy the house and lot; that in case of default in the payment of any of
the installments for 90 days after its due date, the contract would be
automatically rescinded without need of judicial declaration, and that all
payments made and all improvements done on the premises by
respondent would be considered as rentals for the use and occupation of
the property or payment for damages suffered, and respondent was
obliged to peacefully vacate the premises and deliver the possession
thereof to the vendor.
Petitioner claimed that respondent paid only P12,950. She allegedly
stopped paying after December 1979 without any justification or
explanation. Moreover, in a "Kasunduan"1 dated November 18, 1979,
respondent borrowed P3,000 from Patricio payable in one year either in
one lump sum payment or by installments, failing which the balance of the
loan would be added to the principal subject of the monthly amortizations
on the land.
Lastly, petitioner asserted that when respondent ceased paying her
installments, her status of buyer was automatically transformed to that of
a lessee. Therefore, she continued to possess the property by mere
tolerance of Patricio and, subsequently, of petitioner.
On the other hand, respondent alleged that she paid her monthly
installments religiously, until sometime in 1980 when Patricio changed his
mind and offered to refund all her payments provided she would surrender
the house. She refused. Patricio then started harassing her and began
demolishing the house portion by portion. Respondent admitted that she
failed to pay some installments after December 1979, but that she
resumed paying in 1980 until her balance dwindled to P5,650. She claimed
that despite several months of delay in payment, Patricio never sued for
ejectment and even accepted her late payments.
Respondent also averred that on September 14, 1981, she and Patricio
signed an agreement (Exh. 2) whereby he consented to the suspension of
respondents monthly payments until December 1981. However, even
before the lapse of said period, Patricio resumed demolishing respondents
house, prompting her to lodge a complaint with the Barangay Captain who
advised her that she could continue suspending payment even beyond
December 31, 1981 until Patricio returned all the materials he took from
her house. This Patricio failed to do until his death.
Respondent did not deny that she still owed Patricio P5,650, but claimed
that she did not resume paying her monthly installment because of the
unlawful acts committed by Patricio, as well as the filing of the ejectment
case against her. She denied having any knowledge of the Kasunduan of
November 18, 1979.
Patricio and his wife died on September 17, 1992 and on October 17, 1994,
respectively. Petitioner became their sole successor-in-interest pursuant to
a waiver by the other heirs. On March 5, 1997, respondent received a letter
from petitioners counsel dated February 24, 1997 demanding that she
vacate the premises within five days on the ground that her possession
had become unlawful. Respondent ignored the demand. The Punong
Barangay failed to settle the dispute amicably.
On April 8, 1997, petitioner filed a Complaint for unlawful detainer against
respondent with the Municipal Trial Court (MTC) of Guiguinto, Bulacan
praying that, after hearing, judgment be rendered ordering respondent to
immediately vacate the subject property and surrender it to petitioner;
forfeiting the amount of P12,950 in favor of petitioner as rentals; ordering
respondent to pay petitioner the amount of P3,000 under the Kasunduan
and the amount of P500 per month from January 1980 until she vacates
the property, and to pay petitioner attorneys fees and the costs.
On December 22, 1998, the MTC rendered a decision in favor of petitioner.
It stated that although the Contract to Sell provides for a rescission of the
agreement upon failure of the vendee to pay any installment, what the
contract actually allows is properly termed a resolution under Art. 1191 of
the Civil Code.
The MTC held that respondents failure to pay not a few installments
caused the resolution or termination of the Contract to Sell. The last
payment made by respondent was on January 9, 1980 (Exh. 71).
Thereafter, respondents right of possession ipso facto ceased to be a legal
right, and became possession by mere tolerance of Patricio and his
successors-in-interest. Said tolerance ceased upon demand on respondent
to vacate the property.
Page | 46
The CA found that the parties, as well as the MTC and RTC failed to advert
to and to apply Republic Act (R.A.) No. 6552, more commonly referred to as
the Maceda Law, which is a special law enacted in 1972 to protect buyers
of real estate on installment payments against onerous and oppressive
conditions.
The CA held that the Contract to Sell was not validly cancelled or rescinded
under Sec. 3 (b) of R.A. No. 6552, and recognized respondents right to
continue occupying unmolested the property subject of the contract to sell.
The CA denied petitioners motion for reconsideration in a Resolution dated
March 23, 2001.
SO ORDERED.2
Hence, this petition for review on certiorari.
On appeal, the RTC of Malolos, Bulacan, in a Decision dated June 25, 1999,
reversed the decision of the MTC and dismissed the case for lack of merit.
According to the RTC, the agreement could not be automatically rescinded
since there was delivery to the buyer. A judicial determination of rescission
must be secured by petitioner as a condition precedent to convert the
possession de facto of respondent from lawful to unlawful.
The dispositive portion of the RTC Decision states:
WHEREFORE, judgment is hereby rendered reversing the
decision of the Municipal Trial Court of Guiguinto, Bulacan
and the ejectment case instead be dismissed for lack of
merit.3
The motion for reconsideration and motion for execution filed by petitioner
were denied by the RTC for lack of merit in an Order dated August 10,
1999.
Thereafter, petitioner filed a petition for review with the CA.
Page | 47
Petitioner contends that respondent also had more than the grace periods
provided under the Maceda Law within which to pay. Under Sec. 3 7 of the
said law, a buyer who has paid at least two years of installments has a
grace period of one month for every year of installment paid. Based on the
amount of P12,950 which respondent had already paid, she is entitled to a
grace period of six months within which to pay her unpaid installments
after December, 1979. Respondent was given more than six months from
January 1980 within which to settle her unpaid installments, but she failed
to do so. Petitioners demand to vacate was sent to respondent in February
1997.
There is nothing in the Maceda Law, petitioner asserts, which gives the
buyer a right to pay arrearages after the grace periods have lapsed, in the
event of an invalid demand for rescission. The Maceda Law only provides
that actual cancellation shall take place after 30 days from receipt of the
notice of cancellation or demand for rescission and upon full payment of
the cash surrender value to the buyer.
Petitioner contends that his demand letter dated February 24, 1997 should
be considered the notice of cancellation since the demand letter informed
respondent that she had "long ceased to have any right to possess the
premises in question due to [her] failure to pay without justifiable cause."
In support of his contention, he cited Layug v. Intermediate Appellate
Court8 which held that "the additional formality of a demand on [the
sellers] part for rescission by notarial act would appear, in the premises, to
be merely circuitous and consequently superfluous." He stated that in
Layug, the seller already made a written demand upon the buyer.
In addition, petitioner asserts that whatever cash surrender value
respondent is entitled to have been applied and must be applied to rentals
for her use of the house and lot after December, 1979 or after she stopped
payment of her installments.
Petitioner argues that assuming Patricio accepted respondents delayed
installments in 1981, such act cannot prevent the cancellation of the
Contract to Sell. Installments after 1981 were still unpaid and the
applicable grace periods under the Maceda Law on the unpaid installments
have long lapsed. Respondent cannot be allowed to hide behind the
Maceda Law. She acted with bad faith and must bear the consequences of
her deliberate withholding of and refusal to make the monthly payments.
Petitioner also contends that the applicability of the Maceda Law was never
raised in the proceedings below; hence, it should not have been applied by
the CA in resolving the case.
The Court is not persuaded.
The CA correctly ruled that R.A No. 6552, which governs sales of real estate
on installment, is applicable in the resolution of this case.
Page | 48
that the cash surrender value payable to the buyer had been applied to
rentals of the property after respondent failed to pay the installments due.
Based on the records of the case, the Contract to Sell was not validly
cancelled or rescinded under Sec. 3 (b) of R.A. No. 6552.
The Court notes that this case has been pending for more than ten years.
Both parties prayed for other reliefs that are just and equitable under the
premises. Hence, the rights of the parties over the subject property shall
be resolved to finally dispose of that issue in this case.
First, Patricio, the vendor in the Contract to Sell, died on September 17,
1992 without canceling the Contract to Sell.
Second, petitioner also failed to cancel the Contract to Sell in accordance
with law.
Petitioner contends that he has complied with the requirements of
cancellation under Sec. 3 (b) of R.A. No. 6552. He asserts that his demand
letter dated February 24, 1997 should be considered as the notice of
cancellation or demand for rescission by notarial act and that the cash
surrender value of the payments on the property has been applied to
rentals for the use of the house and lot after respondent stopped payment
after January 1980.
The Court, however, finds that the letter 11 dated February 24, 1997, which
was written by petitioners counsel, merely made formal demand upon
respondent to vacate the premises in question within five days from
receipt thereof since she had "long ceased to have any right to possess the
premises x x x due to [her] failure to pay without justifiable cause the
installment payments x x x."
Clearly, the demand letter is not the same as the notice of cancellation or
demand for rescission by a notarial act required by R.A No. 6552.
Petitioner cannot rely on Layug v. Intermediate Appellate Court 12 to support
his contention that the demand letter was sufficient compliance. Layug
held that "the additional formality of a demand on [the sellers] part for
rescission by notarial act would appear, in the premises, to be merely
circuitous and consequently superfluous" since the seller therein filed an
action for annulment of contract, which is a kindred concept of
rescission by notarial act.13 Evidently, the case of unlawful detainer filed by
petitioner does not exempt him from complying with the said requirement.
In addition, Sec. 3 (b) of R.A. No. 6552 requires refund of the cash
surrender value of the payments on the property to the buyer before
cancellation of the contract. The provision does not provide a different
requirement for contracts to sell which allow possession of the property by
the buyer upon execution of the contract like the instant case. Hence,
petitioner cannot insist on compliance with the requirement by assuming
Considering that the Contract to Sell was not cancelled by the vendor,
Patricio, during his lifetime or by petitioner in accordance with R.A. No.
6552 when petitioner filed this case of unlawful detainer after 22 years of
continuous possession of the property by respondent who has paid the
substantial amount of P12,300 out of the purchase price of P17,800, the
Court agrees with the CA that it is only right and just to allow respondent
to pay her arrears and settle the balance of the purchase price.
For respondents delay in the payment of the installments, the Court, in its
discretion, and applying Article 2209 14 of the Civil Code, may award
interest at the rate of 6% per annum 15 on the unpaid balance considering
that there is no stipulation in the Contract to Sell for such interest. For
purposes of computing the legal interest, the reckoning period should be
the filing of the complaint for unlawful detainer on April 8, 1997.
Based on respondents evidence16 of payments made, the MTC found that
respondent paid a total of P12,300 out of the purchase price of P17,800.
Hence, respondent still has a balance of P5,500, plus legal interest at the
rate of 6% per annum on the unpaid balance starting April 8, 1997.
The third issue is disregarded since petitioner assails an inexistent ruling of
the RTC on the lack of jurisdiction of the MTC over a rescission case when
the instant case he filed is for unlawful detainer.
WHEREFORE, the Decision of the Court of Appeals dated October 30,
2000 sustaining the dismissal of the unlawful detainer case by the RTC is
AFFIRMED with the following MODIFICATIONS:
1. Respondent Rufina Dela Cruz Vda. de Manzano shall pay
petitioner Manuel C. Pagtalunan the balance of the
purchase price in the amount of Five Thousand Five
Hundred Pesos (P5,500) plus interest at 6% per annum
from April 8, 1997 up to the finality of this judgment, and
thereafter, at the rate of 12% per annum;
Page | 49
NICOLAS
P.
DIEGO,
Petitioner,
RODOLFO P. DIEGO and EDUARDO P. DIEGO, Respondents.
vs.
Rodolfo and Eduardo filed their Answer with Counterclaim 7 for damages
and attorneys fees. They argued that Nicolas had no more claim in the
rents in the Diego Building since he had already sold his share to Rodolfo.
Rodolfo admitted having remitted only P250,000.00 to Nicolas. He asserted
that he would pay the balance of the purchase price to Nicolas only after
the latter shall have executed a deed of absolute sale.
Ruling of the Regional Trial Court
After trial on the merits, or on April 19, 2005, the trial court rendered its
Decision8 dismissing Civil Case No. 99-02971-D for lack of merit and
ordering Nicolas to execute a deed of absolute sale in favor of Rodolfo
upon payment by the latter of the P250,000.00 balance of the agreed
purchase price. It made the following interesting pronouncement:
It is undisputed that plaintiff (Nicolas) is one of the co-owners of the Diego
Building, x x x. As a co-owner, he is entitled to [his] share in the rentals of
the said building. However, plaintiff [had] already sold his share to
defendant Rodolfo Diego in the amount of P500,000.00 and in fact, [had]
already received a partial payment in the purchase price in the amount of
P250,000.00. Defendant Eduardo Diego testified that as per
agreement, verbal, of the plaintiff and defendant Rodolfo Diego,
the remaining balance of P250,000.00 will be paid upon the
execution of the Deed of Absolute Sale. It was in the year 1997 when
plaintiff was being required by defendant Eduardo Diego to sign the Deed
of Absolute Sale. Clearly, defendant Rodolfo Diego was not yet in default as
Page | 50
the plaintiff claims which cause [sic] him to refuse to sign [sic] document.
The contract of sale was already perfected as early as the year 1993 when
plaintiff received the partial payment, hence, he cannot unilaterally revoke
or rescind the same. From then on, plaintiff has, therefore, ceased to be a
co-owner of the building and is no longer entitled to the fruits of the Diego
Building.
Equity and fairness dictate that defendant [sic] has to execute the
necessary document regarding the sale of his share to defendant Rodolfo
Diego. Correspondingly, defendant Rodolfo Diego has to perform his
obligation as per their verbal agreement by paying the remaining balance
of P250,000.00.9
To summarize, the trial court ruled that as early as 1993, Nicolas was no
longer entitled to the fruits of his aliquot share in the Diego Building
because he had "ceased to be a co-owner" thereof. The trial court held that
when Nicolas received the P250,000.00 downpayment, a "contract of sale"
was perfected. Consequently, Nicolas is obligated to convey such share to
Rodolfo, without right of rescission. Finally, the trial court held that the
P250,000.00 balance from Rodolfo will only be due and demandable when
Nicolas executes an absolute deed of sale.
Ruling of the Court of Appeals
Nicolas appealed to the CA which sustained the trial courts Decision in
toto. The CA held that since there was a perfected contract of sale between
Nicolas and Rodolfo, the latter may compel the former to execute the
proper sale document. Besides, Nicolass insistence that he has since
rescinded their agreement in 1997 proved the existence of a perfected
sale. It added that Nicolas could not validly rescind the contract because:
"1) Rodolfo ha[d] already made a partial payment; 2) Nicolas ha[d] already
partially performed his part regarding the contract; and 3) Rodolfo opposes
the rescission."10
The CA then proceeded to rule that since no period was stipulated within
which Rodolfo shall deliver the balance of the purchase price, it was
incumbent upon Nicolas to have filed a civil case to fix the same. But
because he failed to do so, Rodolfo cannot be considered to be in delay or
default.
Finally, the CA made another interesting pronouncement, that by virtue of
the agreement Nicolas entered into with Rodolfo, he had already
transferred his ownership over the subject property and as a consequence,
Rodolfo is legally entitled to collect the fruits thereof in the form of rentals.
Nicolas remaining right is to demand payment of the balance of the
purchase price, provided that he first executes a deed of absolute sale in
favor of Rodolfo.
Nicolas moved for reconsideration but the same was denied by the CA in
its Resolution dated October 3, 2007.
Hence, this Petition.
Issues
The Petition raises the following errors that must be rectified:
I
THE HONORABLE COURT OF APPEALS ERRED IN NOT HOLDING THAT THERE
WAS NO PERFECTED CONTRACT OF SALE BETWEEN PETITIONER NICOLAS
DIEGO AND RESPONDENT RODOLFO DIEGO OVER NICOLASS SHARE OF
THE BUILDING BECAUSE THE SUSPENSIVE CONDITION HAS NOT YET BEEN
FULFILLED.
II
THE HONORABLE COURT OF APPEALS ERRED IN HOLDING THAT THE
CONTRACT OF SALE BETWEEN PETITIONER AND RESPONDENT RODOLFO
DIEGO REMAINS LEGALLY BINDING AND IS NOT RESCINDED GIVING
MISPLACED RELIANCE ON PETITIONER NICOLAS STATEMENT THAT THE
SALE HAS NOT YET BEEN REVOKED.
III
THE HONORABLE COURT OF APPEALS ERRED IN NOT HOLDING THAT
PETITIONER NICOLAS DIEGO ACTED LEGALLY AND CORRECTLY WHEN HE
UNILATERALLY RESCINDED AND REVOKED HIS AGREEMENT OF SALE WITH
RESPONDENT RODOLFO DIEGO CONSIDERING RODOLFOS MATERIAL,
SUBSTANTIAL BREACH OF THE CONTRACT.
IV
THE HONORABLE COURT OF APPEALS ERRED IN HOLDING THAT PETITIONER
HAS NO MORE RIGHTS OVER HIS SHARE IN THE BUILDING, DESPITE THE
FACT THAT THERE WAS AS YET NO PERFECTED CONTRACT OF SALE
BETWEEN PETITIONER NICOLAS DIEGO AND RODOLFO DIEGO AND THERE
WAS YET NO TRANSFER OF OWNERSHIP OF PETITIONERS SHARE TO
RODOLFO DUE TO THE NON-FULFILLMENT BY RODOLFO OF THE
SUSPENSIVE CONDITION UNDER THE CONTRACT.
V
THE HONORABLE COURT OF APPEALS ERRED IN NOT HOLDING THAT
RESPONDENT RODOLFO HAS UNJUSTLY ENRICHED HIMSELF AT THE
Page | 51
Page | 52
(signed)
Nicolas Diego25
Page | 53
This Court cannot subscribe to the appellate courts view that Nicolas
should first execute a deed of absolute sale in favor of Rodolfo, before the
latter can be compelled to pay the balance of the price. This is patently
ridiculous, and goes against every rule in the book. This pronouncement
virtually places the prospective seller in a contract to sell at the mercy of
the prospective buyer, and sustaining this point of view would place all
contracts to sell in jeopardy of being rendered ineffective by the act of the
prospective buyers, who naturally would demand that the deeds of
absolute sale be first executed before they pay the balance of the price.
Surely, no prospective seller would accommodate.
In fine, "the need to execute a deed of absolute sale upon
completion of payment of the price generally indicates that it is a
contract to sell, as it implies the reservation of title in the vendor
until the vendee has completed the payment of the price." 36 In
addition, "[a] stipulation reserving ownership in the vendor until full
payment of the price is x x x typical in a contract to sell." 37 Thus, contrary
to the pronouncements of the trial and appellate courts, the parties to this
case only entered into a contract to sell; as such title cannot legally pass to
Rodolfo until he makes full payment of the agreed purchase price.
c) Nicolas did not surrender or deliver title or possession to
Rodolfo.
Page | 54
When the petitioners in the instant case repossessed the disputed house
and lot for failure of private respondents to pay the purchase price in full,
they were merely enforcing the contract and not rescinding it. As
petitioners correctly point out, the Court of Appeals erred when it ruled
that petitioners should have judicially rescinded the contract pursuant to
Articles 1592 and 1191 of the Civil Code. Article 1592 speaks of nonpayment of the purchase price as a resolutory condition. It does not apply
to a contract to sell. As to Article 1191, it is subordinated to the provisions
of Article 1592 when applied to sales of immovable property. Neither
provision is applicable in the present case.46
Similarly, we held in Chua v. Court of Appeals47 that "Article 1592 of the
Civil Code permits the buyer to pay, even after the expiration of the period,
as long as no demand for rescission of the contract has been made upon
him either judicially or by notarial act. However, Article 1592 does not
apply to a contract to sell where the seller reserves the ownership until full
payment of the price,"48 as in this case.1wphi1
Applying the above jurisprudence, we hold that when Rodolfo failed to fully
pay the purchase price, the contract to sell was deemed terminated or
cancelled.49 As we have held in Chua v. Court of Appeals,50 "[s]ince the
agreement x x x is a mere contract to sell, the full payment of the
purchase price partakes of a suspensive condition. The non-fulfillment of
the condition prevents the obligation to sell from arising and
ownership is retained by the seller without further remedies by
the buyer." Similarly, we held in Reyes v. Tuparan51 that "petitioners
obligation to sell the subject properties becomes demandable only upon
the happening of the positive suspensive condition, which is the
respondents full payment of the purchase price. Without respondents
full payment, there can be no breach of contract to speak of
because petitioner has no obligation yet to turn over the title.
Respondents failure to pay in full the purchase price in full is not the
breach of contract contemplated under Article 1191 of the New Civil Code
but rather just an event that prevents the petitioner from being bound to
convey title to respondent." Otherwise stated, Rodolfo has no right to
compel Nicolas to transfer ownership to him because he failed to pay in full
the purchase price. Correlatively, Nicolas has no obligation to transfer his
ownership over his share in the Diego Building to Rodolfo. 52
Thus, it was erroneous for the CA to rule that Nicolas should have filed a
case to fix the period for Rodolfos payment of the balance of the purchase
price. It was not Nicolass obligation to compel Rodolfo to pay the balance;
it was Rodolfos duty to remit it.
It would appear that after Nicolas refused to sign the deed as there was yet
no full payment, Rodolfo and Eduardo hired the services of the Daroya
Accounting Office "for the purpose of estimating the amount to which
[Nicolas] still owes [Rodolfo] as a consequence of the unconsummated
verbal agreement regarding the formers share in the co-ownership of
[Diego Building] in favor of the latter." 53 According to the accountants
report, after Nicolas revoked his agreement with Rodolfo due to nonpayment, the downpayment of P250,000.00 was considered a loan of
Nicolas from Rodolfo.54 The accountant opined that the P250,000.00 should
earn interest at 18%.55 Nicolas however objected as regards the imposition
of interest as it was not previously agreed upon. Notably, the contents of
the accountants report were not disputed or rebutted by the respondents.
In fact, it was stated therein that "[a]ll the bases and assumptions made
particularly in the fixing of the applicable rate of interest have been
discussed with [Eduardo]."56
We find it irrelevant and immaterial that Nicolas described the termination
or cancellation of his agreement with Rodolfo as one of rescission. Being a
layman, he is understandably not adept in legal terms and their
implications. Besides, this Court should not be held captive or bound by
the conclusion reached by the parties. The proper characterization of an
action should be based on what the law says it to be, not by what a party
believed it to be. "A contract is what the law defines it to be x x x and not
what the contracting parties call it."57
On the other hand, the respondents additional submission that Nicolas
cheated them by "vanishing and hibernating" in the USA after receiving
Rodolfos P250,000.00 downpayment, only to come back later and claim
that the amount he received was a mere loan cannot be believed. How
the respondents could have been cheated or disadvantaged by Nicolass
leaving is beyond comprehension. If there was anybody who benefited
from Nicolass perceived "hibernation", it was the respondents, for they
certainly had free rein over Nicolass interest in the Diego Building. Rodolfo
put off payment of the balance of the price, yet, with the aid of Eduardo,
collected and appropriated for himself the rents which belonged to Nicolas.
Eduardo is solidarily liable with Rodolfo as regards the share of
Nicolas in the rents.
For his complicity, bad faith and abuse of authority as the Diego Building
administrator, Eduardo must be held solidarily liable with Rodolfo for all
that Nicolas should be entitled to from 1993 up to the present, or in
respect of actual damages suffered in relation to his interest in the Diego
Building. Eduardo was the primary cause of Nicolass loss, being directly
responsible for making and causing the wrongful payments to Rodolfo, who
received them under obligation to return them to Nicolas, the true
recipient.1wphi1 As such, Eduardo should be principally responsible to
Nicolas as well. Suffice it to state that every person must, in the exercise of
his rights and in the performance of his duties, act with justice, give
everyone his due, and observe honesty and good faith; and every person
who, contrary to law, wilfully or negligently causes damage to another,
shall indemnify the latter for the same.58
Attorneys fees and other costs.
Page | 55
"Although attorneys fees are not allowed in the absence of stipulation, the
court can award the same when the defendants act or omission has
compelled the plaintiff to incur expenses to protect his interest or where
the defendant acted in gross and evident bad faith in refusing to satisfy the
plaintiffs plainly valid, just and demandable claim." 59 In the instant case, it
is beyond cavil that petitioner was constrained to file the instant case to
protect his interest because of respondents unreasonable and unjustified
refusal to render an accounting and to remit to the petitioner his rightful
share in rents and fruits in the Diego Building. Thus, we deem it proper to
award to petitioner attorneys fees in the amount of P50,000.00,60 as well
as litigation expenses in the amount of P20,000.00 and the sum of
P1,000.00 for each court appearance by his lawyer or lawyers, as prayed
for.
SO ORDERED.
Page | 56
Under the contract, Sps. Fajardo undertook to pay the purchase price of
P126,000.00 within a 10-year period, including interest at the rate of nine
percent (9%) per annum. GPI, on the other hand, agreed to execute a final
deed of sale (deed) in favor of Sps. Fajardo upon full payment of the
stipulated consideration. However, despite its full payment of the purchase
price on January 17, 20006 and subsequent demands,7 GPI failed to execute
the deed and to deliver the title and physical possession of the subject lot.
Thus, on May 3, 2006, Sps. Fajardo filed before the Housing and Land Use
Regulatory Board-Expanded National Capital Region Field Office
(HLURBENCRFO) a complaint8 for specific performance or rescission of
contract with damages against GPI and the members of its Board of
Directors namely, Jose C. Go, Evelyn Go, Lourdes G. Ortiga, George Go, and
Vicente Go (individual petitioners), docketed as HLURB Case No. REM050306-13319.
For their part, petitioners maintained that at the time of the execution of
the contract, Sps. Fajardo were actually aware that GPI's certificate of title
had no technical description inscribed on it. Nonetheless, the title to the
subject lot was free from any liens or encumbrances. 11 Petitioners claimed
that the failure to deliver the title to Sps. Fajardo was beyond their control 12
because while GPI's petition for inscription of technical description (LRC
Case No. 4211) was favorably granted 13 by the Regional Trial Court of
Caloocan City, Branch 131 (RTC-Caloocan), the same was reversed 14 by the
CA; this caused the delay in the subdivision of the property into individual
lots with individual titles. Given the foregoing incidents, petitioners thus
argued that Article 1191 of the Civil Code (Code) the provision on which
Sps. Fajardo anchor their right of rescission remained inapplicable since
they were actually willing to comply with their obligation but were only
prevented from doing so due to circumstances beyond their control.
Separately, petitioners pointed out that BSP's adverse claim/levy which
was annotated long after the execution of the contract had already been
settled.
On petition for review, the CA affirmed the above rulings with modification,
fixing the amount to be refunded to Sps. Fajardo at the prevailing market
value of the property18 pursuant to the ruling in Solid Homes v. Tan (Solid
Homes).19
The Petition
Petitioners insist that Sps. Fajardo have no right to rescind the contract
considering that GPI's inability to comply therewith was due to reasons
beyond its control and thus, should not be held liable to refund the
payments they had received. Further, since the individual petitioners never
participated in the acts complained of nor found to have acted in bad faith,
they should not be held liable to pay damages and attorney's fees.
The Court's Ruling
Page | 57
demand for delivery of title. GPI filed the petition before the RTC-Caloocan,
Branch 122 (docketed as LRC Case No. C-5026) only on November 23,
2006,26 following receipt of the letter 27 dated February 10, 2006 and the
filing of the complaint on May 3, 2006, alternatively seeking refund of
payments. While the court a quo decided the latter petition for inscription
in its favor,28 there is no showing that the same had attained finality or that
the approved technical description had in fact been annotated on TCT No.
244220, or even that the subdivision plan had already been approved.
Moreover, despite petitioners allegation29 that the claim of BSP had been
settled, there appears to be no cancellation of the annotations 30 in GPIs
favor. Clearly, the long delay in the performance of GPI's obligation from
date of demand on September 16, 2002 was unreasonable and unjustified.
It cannot therefore be denied that GPI substantially breached its contract
to sell with Sps. Fajardo which thereby accords the latter the right to
rescind the same pursuant to Article 1191 of the Code, viz:
ART. 1191. The power to rescind obligations is implied in reciprocal ones, in
case one of the obligors should not comply with what is incumbent upon
him.
The injured party may choose between the fulfillment and the rescission of
the obligation, with the payment of damages in either case. He may also
seek rescission, even after he has chosen fulfillment, if the latter should
become impossible.
The court shall decree the rescission claimed, unless there be just cause
authorizing the fixing of a period.
This is understood to be without prejudice to the rights of third persons
who have acquired the thing, in accordance with articles 1385 and 1388
and the Mortgage Law.
B. Effects of rescission
At this juncture, it is noteworthy to point out that rescission does not
merely terminate the contract and release the parties from further
obligations to each other, but abrogates the contract from its inception and
restores the parties to their original positions as if no contract has been
made.31 Consequently, mutual restitution, which entails the return of the
benefits that each party may have received as a result of the contract, is
thus required.32 To be sure, it has been settled that the effects of rescission
as provided for in Article 1385 of the Code are equally applicable to cases
under Article 1191, to wit:
xxxx
Page | 58
Page | 59
SERENO, CJ.:
F. ECDIS SYSTEM
Before this Court is a Rule 45 Petition, seeking a review of the 27 July 2009
Court of Appeals (CA) Decision in CA-G.R. CV No. 88989, 1 which modified
the Regional Trial Court (RTC) Decision of 8 January 2007 in Civil Case No.
Q-04-53660.2 The CA held that petitioner substantially breached its
contracts with respondent for the installation of an integrated bridge
system (IBS).
H. BRIDGE CONSOLE
TOTAL COST:
Php 3,800,000
LESS:
OLD
EQUIPMENT TRADE-IN VALUE
MARITIME
1,000,000.00
DISCOUNT
100,000.00
PhP 2,700,000
PhP
270,000.00
Common to both contracts are the following provisions: (1) the IBS and its
components must be compliant with the IMO and CHED standard and with
manuals for simulators/major equipment; (2) the contracts may be
terminated if one party commits a substantial breach of its undertaking;
and (3) any dispute under the agreement shall first be settled mutually
Page | 60
Page | 61
to the amount that he would have earned, had respondent not stopped him
from performing his tasks under the two contracts; moral and exemplary
damages; attorneys fees; litigation expenses; and cost of suit.
Hence, the pertinent issue to be resolved in the instant appeal is whether
the CA gravely erred in (1) finding substantial breach on the part of GL
Enterprises; (2) refusing petitioners claims for damages, and (3) awarding
attorneys fees to Northwestern.
Although the RTC and the CA concurred in ordering restitution, the courts a
quo, however, differed on the basis thereof. The RTC applied the equitable
principle of mutual fault, while the CA applied Article 1191 on rescission.
Page | 62
Q: One of the defects is that the steering wheel was that of an ordinary
automobile. And what is the implication of this?
A: Because. on board Maam, we are using the real steering wheel and the
cadets will be implicated if they will notice that the ship have the same
steering wheel as the car so it is not advisable for them.
Q:. And another one is that the gyrocompass repeater was only refurbished
and it has no serial number. What is wrong with that?
A: It should be original Maam because this gyro repeater, it must to repeat
also the true North being indicated by the Master Gyro Compass so it will
not work properly, I dont know it will work properly. (Underscoring
supplied)
Evidently, the materials delivered were less likely to pass the CHED
standards, because the navigation system to be installed might not
accurately point to the true north; and the steering wheel delivered was
one that came from an automobile, instead of one used in ships. Logically,
by no stretch of the imagination could these form part of the most modern
IBS compliant with the IMO and CHED standards.
Even in the instant appeal, GL Enterprises does not refute that the
equipment it delivered was substandard. However, it reiterates its rejected
excuse that Northwestern should have made an assessment only after the
completion of the IBS.17 Thus, petitioner stresses that it was Northwestern
that breached the agreement when the latter halted the installation of the
materials for the IBS, even if the parties had contemplated a completed
project to be evaluated by CHED. However, as aptly considered by the CA,
respondent could not just "sit still and wait for such day that its
accreditation may not be granted by CHED due to the apparent
substandard equipment installed in the bridge system." 18 The appellate
court correctly emphasized that, by that time, both parties would have
incurred more costs for nothing.
Additionally, GL Enterprises reasons that, based on the contracts, the
materials that were hauled all the way from Quezon City to Laoag City
under the custody of the four designated installers might not have been
the components to be used.19 Without belaboring the point, we affirm the
conclusion of the CA and the RTC that the excuse is untenable for being
contrary to human experience.20
Page | 63
SO ORDERED.
G.R. No. 189145
failed to file their answer within the prescribed reglementary period, thus
prompting Optimum to move for the rendition of judgment.14
December 4, 2013
OPTIMUM
DEVELOPMENT
BANK,
Petitioner,
vs.
SPOUSES BENIGNO V. JOVELLANOS and LOURDES R. JOVELLANOS,
Respondents.
DECISION
PERLAS-BERNABE, J.:
Assailed in this petition for review on certiorari 1 are the Decision2 dated
May 29, 2009 and Resolution 3 dated August 10, 2009 of the Court of
Appeals (CA) in CA-G.R. SP No. 104487 which reversed the Decision 4 dated
December 27, 2007 of the Regional Trial Court of Caloocan City, Branch
128 (RTC) in Civil Case No. C-21867 that, in turn, affirmed the Decision 5
dated June 8, 2007 of the Metropolitan Trial Court, Branch 53 of that same
city (MeTC) in Civil Case No. 06-28830 ordering respondents-spouses
Benigno and Lourdes Jovellanos (Sps. Jovellanos) to, inter alia, vacate the
premises of the property subject of this case.
The Facts
On April 26, 2005, Sps. Jovellanos entered into a Contract to Sell 6 with
Palmera Homes, Inc. (Palmera Homes) for the purchase of a residential
house and lot situated in Block 3, Lot 14, Villa Alegria Subdivision,
Caloocan City (subject property) for a total consideration of P1,015,000.00.
Pursuant to the contract, Sps. Jovellanos took possession of the subject
property upon a down payment of P91,500.00, undertaking to pay the
remaining balance of the contract price in equal monthly installments of
P13,107.00 for a period of 10 years starting June 12, 2005. 7
On August 22, 2006, Palmera Homes assigned all its rights, title and
interest in the Contract to Sell in favor of petitioner Optimum Development
Bank (Optimum) through a Deed of Assignment of even date. 8
On April 10, 2006, Optimum issued a Notice of Delinquency and
Cancellation of Contract to Sell 9 for Sps. Jovellanoss failure to pay their
monthly installments despite several written and verbal notices. 10
In a final Demand Letter dated May 25, 2006, 11 Optimum required Sps.
Jovellanos to vacate and deliver possession of the subject property within
seven (7) days which, however, remained unheeded. Hence, Optimum
filed, on November 3, 2006, a complaint for unlawful detainer 12 before the
MeTC, docketed as Civil Case No. 06-28830. Despite having been served
with summons, together with a copy of the complaint, 13 Sps. Jovellanos
Page | 64
The CA Ruling
In an Amended Decision23 dated May 29, 2009, the CA reversed and set
aside the RTCs decision, ruling to dismiss the complaint for lack of
jurisdiction. It found that the controversy does not only involve the issue of
possession but also the validity of the cancellation of the Contract to Sell
and the determination of the rights of the parties thereunder as well as the
governing law, among others, Republic Act No. (RA) 6552. 24
Accordingly, it concluded that the subject matter is one which is incapable
of pecuniary estimation and thus, within the jurisdiction of the RTC. 25
Undaunted, Optimum moved for reconsideration which was denied in a
Resolution26 dated August 10, 2009. Hence, the instant petition, submitting
that the case is one for unlawful detainer, which falls within the exclusive
original jurisdiction of the municipal trial courts, and not a case incapable
of pecuniary estimation cognizable solely by the regional trial courts.
The Courts Ruling
The petition is meritorious. What is determinative of the nature of the
action and the court with jurisdiction over it are the allegations in the
complaint and the character of the relief sought, not the defenses set up in
an answer.27
A complaint sufficiently alleges a cause of action for unlawful detainer if it
recites that:
(a) initially, possession of the property by the defendant
was by contract with or by tolerance of the plaintiff;
(b) eventually, such possession became illegal upon notice
by plaintiff to defendant of the termination of the latter's
right of possession;
(c) thereafter, defendant remained in possession of the
property and deprived plaintiff of the enjoyment thereof;
and
(d) within one year from the last demand on defendant to
vacate the property, plaintiff instituted the complaint for
ejectment.28
In its complaint, Optimum alleged that it was by virtue of the April 26,
2005 Contract to Sell that Sps. Jovellanos were allowed to take possession
of the subject property. However, since the latter failed to pay the
stipulated monthly installments, notwithstanding several written and
verbal notices made upon them, it cancelled the said contract as per the
Notice of Delinquency and Cancellation dated April 10, 2006. When Sps.
Jovellanos refused to vacate the subject property despite repeated
demands, Optimum instituted the present action for unlawful detainer on
November 3, 2006, or within one year from the final demand made on May
25, 2006.
While the RTC upheld the MeTCs ruling in favor of Optimum, the CA, on the
other hand, declared that the MeTC had no jurisdiction over the complaint
for unlawful detainer, reasoning that the case involves a matter which is
incapable of pecuniary estimation i.e., the validity of the cancellation of
the Contract to Sell and the determination of the rights of the parties under
the contract and law and hence, within the jurisdiction of the RTC. The
Court disagrees. Metropolitan Trial Courts are conditionally vested with
authority to resolve the question of ownership raised as an incident in an
ejectment case where the determination is essential to a complete
adjudication of the issue of possession. 30 Concomitant to the ejectment
courts authority to look into the claim of ownership for purposes of
resolving the issue of possession is its authority to interpret the contract or
agreement upon which the claim is premised. Thus, in the case of Oronce
v. CA,31 wherein the litigants opposing claims for possession was hinged on
whether their written agreement reflected the intention to enter into a sale
or merely an equitable mortgage, the Court affirmed the propriety of the
ejectment courts examination of the terms of the agreement in question
by holding that, "because metropolitan trial courts are authorized to look
into the ownership of the property in controversy in ejectment cases, it
behooved MTC Branch 41 to examine the bases for petitioners claim of
ownership that entailed interpretation of the Deed of Sale with Assumption
of Mortgage."32 Also, in Union Bank of the Philippines v. Maunlad Homes,
Inc.33 (Union Bank), citing Sps. Refugia v. CA,34 the Court declared that
MeTCs have authority to interpret contracts in unlawful detainer cases,
viz.:35
The authority granted to the MeTC to preliminarily resolve the issue of
ownership to determine the issue of possession ultimately allows it to
interpret and enforce the contract or agreement between the plaintiff and
the defendant. To deny the MeTC jurisdiction over a complaint merely
because the issue of possession requires the interpretation of a contract
will effectively rule out unlawful detainer as a remedy. As stated, in an
action for unlawful detainer, the defendants right to possess the property
may be by virtue of a contract, express or implied;
Page | 65
Page | 66
three (3) requisites before the seller may actually cancel the subject
contract: first, the seller shall give the buyer a 60-day grace period to be
reckoned from the date the installment became due; second, the seller
must give the buyer a notice of cancellation/demand for rescission
by notarial act if the buyer fails to pay the installments due at the
expiration of the said grace period; and third, the seller may actually
cancel the contract only after thirty (30) days from the buyers receipt of
the said notice of cancellation/demand for rescission by notarial act. In the
present case, the 60-day grace period automatically operated 42 in favor of
the buyers, Sps. Jovellanos, and took effect from the time that the maturity
dates of the installment payments lapsed. With the said grace period
having expired bereft of any installment payment on the part of Sps.
Jovellanos,43 Optimum then issued a notarized Notice of Delinquency and
Cancellation of Contract on April 10, 2006. Finally, in proceeding with the
actual cancellation of the contract to sell, Optimum gave Sps. Jovellanos an
additional thirty (30) days within which to settle their arrears and reinstate
the contract, or sell or assign their rights to another. 44
It was only after the expiration of the thirty day (30) period did Optimum
treat the contract to sell as effectively cancelled making as it did a final
demand upon Sps. Jovellanos to vacate the subject property only on May
25, 2006. Thus, based on the foregoing, the Court finds that there was a
valid and effective cancellation of the Contract to Sell in accordance with
Section 4 of RA 6552 and since Sps. Jovellanos had already lost their right
to retain possession of the subject property as a consequence of such
cancellation, their refusal to vacate and turn over possession to Optimum
makes out a valid case for unlawful detainer as properly adjudged by the
MeTC.
WHEREFORE, the petition is GRANTED. The Decision dated May 29, 2009
and Resolution dated August 10, 2009 of the Court of Appeals in CA-G.R.
SP No. 104487 are SET ASIDE. The Decision dated June 8, 2007 of
Metropolitan Trial Court, Branch 53, Caloocan City in Civil Case No. 0628830 is hereby REINSTATED.
SO ORDERED.
G.R. No. 185798
Before the Court is a petition for review on certiorari under Rule 45 of the
1997 Rules .of Civil Procedure assailing the Decision 1 of the Court of
Appeals in CA-G.R. SP No. 100450 which affirmed the Decision of the Office
of the President in O.P. Case No. 06-F-216.
As culled from the records, the facts are as follow:
Petitioner Fil-Estate Properties, Inc. is the owner and developer of the
Central Park Place Tower while co-petitioner Fil-Estate Network, Inc. is its
authorized marketing agent. Respondent Spouses Conrado and Maria
Victoria Ronquillo purchased from petitioners an 82-square meter
condominium unit at Central Park Place Tower in Mandaluyong City for a
pre-selling contract price of FIVE MILLION ONE HUNDRED SEVENTY-FOUR
THOUSAND ONLY (P5,174,000.00). On 29 August 1997, respondents
executed and signed a Reservation Application Agreement wherein they
deposited P200,000.00 as reservation fee. As agreed upon, respondents
paid the full downpayment of P1,552,200.00 and had been paying the
P63,363.33 monthly amortizations until September 1998.
Upon learning that construction works had stopped, respondents likewise
stopped paying their monthly amortization. Claiming to have paid a total of
P2,198,949.96 to petitioners, respondents through two (2) successive
letters, demanded a full refund of their payment with interest. When their
demands went unheeded, respondents were constrained to file a
Complaint for Refund and Damages before the Housing and Land Use
Regulatory Board (HLURB). Respondents prayed for reimbursement/refund
of P2,198,949.96 representing the total amortization payments,
P200,000.00 as and by way of moral damages, attorneys fees and other
litigation expenses.
On 21 October 2000, the HLURB issued an Order of Default against
petitioners for failing to file their Answer within the reglementary period
despite service of summons.2
Petitioners filed a motion to lift order of default and attached their position
paper attributing the delay in construction to the 1997 Asian financial
crisis. Petitioners denied committing fraud or misrepresentation which
could entitle respondents to an award of moral damages.
On 13 June 2002, the HLURB, through Arbiter Atty. Joselito F. Melchor,
rendered judgment ordering petitioners to jointly and severally pay
respondents the following amount:
a) The amount of TWO MILLION ONE HUNDRED NINETYEIGHT THOUSAND NINE HUNDRED FORTY NINE PESOS &
96/100 (P2,198,949.96) with interest thereon at twelve
percent (12%) per annum to be computed from the time of
the complainants demand for refund on October 08, 1998
until fully paid,
Page | 67
Page | 68
Page | 69
argument that the 1997 Asian financial crisis is a fortuitous event which
justifies the delay of the construction project. First off, the Court classified
the issue as a question of fact which may not be raised in a petition for
review considering that there was no variance in the factual findings of the
HLURB, the Office of the President and the Court of Appeals. Second, the
Court cited the previous rulings of Asian Construction and Development
Corporation v. Philippine Commercial International Bank 14 and Mondragon
Leisure and Resorts Corporation v. Court of Appeals 15 holding that the 1997
Asian financial crisis did not constitute a valid justification to renege on
obligations. The Court expounded:
Also, we cannot generalize that the Asian financial crisis in 1997 was
unforeseeable and beyond the control of a business corporation. It is
unfortunate that petitioner apparently met with considerable difficulty e.g.
increase cost of materials and labor, even before the scheduled
commencement of its real estate project as early as 1995. However, a real
estate enterprise engaged in the pre-selling of condominium units is
concededly a master in projections on commodities and currency
movements and business risks. The fluctuating movement of the Philippine
peso in the foreign exchange market is an everyday occurrence, and
fluctuations in currency exchange rates happen everyday, thus, not an
instance of caso fortuito.16
The aforementioned decision becomes a precedent to future cases in
which the facts are substantially the same, as in this case. The principle of
stare decisis, which means adherence to judicial precedents, applies.
In said case, the Court ordered the refund of the total amortizations paid
by respondents plus 6% legal interest computed from the date of demand.
The Court also awarded attorneys fees. We follow that ruling in the case
before us.
The resulting modification of the award of legal interest is, also, in line with
our recent ruling in Nacar v. Gallery Frames, 17 embodying the amendment
introduced by the Bangko Sentral ng Pilipinas Monetary Board in BSP-MB
Circular No. 799 which pegged the interest rate at 6% regardless of the
source of obligation.
We likewise affirm the award of attorneys fees because respondents were
forced to litigate for 14 years and incur expenses to protect their rights and
interest by reason of the unjustified act on the part of petitioners. 18 The
imposition of P10,000.00 administrative fine is correct pursuant to Section
38 of Presidential Decree No. 957 which reads:
Section 38. Administrative Fines. The Authority may prescribe and impose
fines not exceeding ten thousand pesos for violations of the provisions of
this Decree or of any rule or regulation thereunder. Fines shall be payable
to the Authority and enforceable through writs of execution in accordance
with the provisions of the Rules of Court.
MEDIALDEA, J.:p
This is a petition for review on certiorari of the decision (pp 21-31, Rollo) of
the Intermediate Appellate Court (now Court of Appeals) in AC-G.R. C.V. No.
02753, 1 which modified the decision of the trial court against herein
private respondent Roberto Regala, Jr., one of the defendants in the case
for sum of money filed by Pacific Banking Corporation.
The facts of the case as adopted by the respondent appellant court from
herein petitioner's brief before said court are as follows:
On October 24, 1975, defendant Celia Syjuco Regala (hereinafter referred
to as Celia Regala for brevity), applied for and obtained from the plaintiff
the issuance and use of Pacificard credit card (Exhs. "A", "A-l",), under the
Terms and Conditions Governing the Issuance and Use of Pacificard (Exh.
Page | 70
In view of defendant Celia Regala's failure to settle her account for the
purchases made thru the use of the Pacificard, a written demand (Exh. "D")
was sent to the latter and also to the defendant Roberto Regala, Jr. (Exh. "
") under his "Guarantor's Undertaking."
The defendants appealed from the decision of the court a quo to the
Intermediate Appellate Court.
Page | 71
the complaint up to the payment at the rate of 14% per annum without
pronouncement as to costs. (p. 32, Rollo)
The respondent appellate court held that "all the other rights of the
guarantor are not thereby lost by the guarantor becoming liable solidarily
and therefore a surety." It further ruled that although the surety's liability is
like that of a joint and several debtor, it does not make him the debtor but
still the guarantor (or the surety), relying on the case of Government of the
Philippines v. Tizon. G.R. No. L-22108, August 30, 1967, 20 SCRA 1182.
Consequently, Article 2054 of the Civil Code providing for a limited liability
on the part of the guarantor or debtor still applies.
It is true that under Article 2054 of the Civil Code, "(A) guarantor may bind
himself for less, but not for more than the principal debtor, both as regards
the amount and the onerous nature of the conditions. 2 It is likewise not
disputed by the parties that the credit limit granted to Celia Regala was
P2,000.00 per month and that Celia Regala succeeded in using the card
beyond the original period of its effectivity, October 29, 1979. We do not
agree however, that Roberto Jr.'s liability should be limited to that extent.
Private respondent Roberto Regala, Jr., as surety of his wife, expressly
bound himself up to the extent of the debtor's (Celia) indebtedness
likewise expressly waiving any "discharge in case of any change or
novation of the terms and conditions in connection with the issuance of the
Pacificard credit card." Roberto, in fact, made his commitment as a surety
a continuing one, binding upon himself until all the liabilities of Celia
Regala have been fully paid. All these were clear under the "Guarantor's
Undertaking" Roberto signed, thus:
. . . Any changes of or novation in the terms and conditions in connection
with the issuance or use of said Pacificard, or any extension of time to pay
such obligations, charges or liabilities shall not in any manner release
me/us from the responsibility hereunder, it being understood that the
undertaking is a continuing one and shall subsist and bind me/us until all
the liabilities of the said Celia Syjuco Regala have been fully satisfied or
paid. (p. 12, supra; emphasis supplied)
Private respondent Roberto Regala, Jr. had been made aware by the terms
of the undertaking of future changes in the terms and conditions governing
the issuance of the credit card to his wife and that, notwithstanding, he
voluntarily agreed to be bound as a surety. As in guaranty, a surety may
secure additional and future debts of the principal debtor the amount of
which is not yet known (see Article 2053, supra).
Page | 72
issued by the Labor Arbiter which deviated from the dispositive portion of
the Decision dated March 10, 1987, thereby holding that the liability of the
six respondents in the case below is solidary despite the absence of the
word "solidary" in the dispositive portion of the Decision, when their
liability should merely be joint. S-jcj
The factual antecedents are undisputed: Supr-eme
In September 1984, private respondent Enrique Sulit, Socorro Mahinay,
Esmeraldo Pegarido, Tita Bacusmo, Gino Niere, Virginia Bacus, Roberto
Nemenzo, Dariogo, and Roberto Alegarbes filed a complaint with the
Department of Labor and Employment, Regional Arbitration Branch No. VII
in Cebu City against Filipinas Carbon Mining Corporation, Gerardo Sicat,
Antonio Gonzales, Chiu Chin Gin, Lo Kuan Chin, and petitioner Industrial
Management Development Corporation (INIMACO), for payment of
separation pay and unpaid wages. Sc-jj
In a Decision dated March 10, 1987, Labor Arbiter Bonifacio B. Tumamak
held that:
"RESPONSIVE, to all the foregoing, judgment is hereby entered, ordering
respondents Filipinas Carbon and Mining Corp. Gerardo Sicat, Antonio
Gonzales/Industrial Management Development Corp. (INIMACO), Chiu Chin
Gin and Lo Kuan Chin, to pay complainants Enrique Sulit, the total award of
P82,800.00; ESMERALDO PEGARIDO the full award of P19,565.00; Roberto
Nemenzo the total sum of P29,623.60 and DARIO GO the total award of
P6,599.71, or the total aggregate award of ONE HUNDRED THIRTY-EIGHT
THOUSAND FIVE
HUNDRED EIGHTY-EIGHT PESOS AND 31/100
(P138,588.31) to be deposited with this Commission within ten (10) days
from receipt of this Decision for appropriate disposition. All other claims are
hereby Dismiss (sic) for lack of merit. Jjs-c
1
Page | 73
"In matters affecting labor rights and labor justice, we have always
adopted the liberal approach which favors the exercise of labor rights and
which is beneficial to labor as a means to give full meaning and import to
the constitutional mandate to afford protection to labor. Considering the
factual circumstances in this case, there is no doubt in our mind that the
respondents herein are called upon to pay, jointly and severally, the claims
of the complainants as was the latters prayers. Inasmuch as respondents
herein never controverted the claims of the complainants below, there is
no reason why complainants prayer should not be granted. Further, in line
with the powers granted to the Commission under Article 218 (c) of the
Labor code, to waive any error, defect or irregularity whether in substance
or in form in a proceeding before Us, We hold that the Writ of Execution be
given due course in all respects." Ed-p
On July 31, 1989, petitioner filed a "Motion To Compel Sheriff To Accept
Payment Of P23,198.05 Representing One Sixth Pro Rata Share of
Respondent INIMACO As Full and Final Satisfaction of Judgment As to Said
Respondent."6 The private respondents opposed the motion. In an Order 7
dated August 15, 1989, the Labor Arbiter denied the motion ruling thus:
"WHEREFORE, responsive to the foregoing respondent INIMACOs Motions
are hereby DENIED. The Sheriff of this Office is order (sic) to accept
INIMACOs tender payment (sic) of the sum of P23,198.05, as partial
satisfaction of the judgment and to proceed with the enforcement of the
Alias Writ of Execution of the levied properties, now issued by this Office,
for the full and final satisfaction of the monetary award granted in the
instant case.
"SO ORDERED." Ed-psc
Petitioner appealed the above Order of the Labor Arbiter but this was again
dismissed by the respondent NLRC in its Resolution 8 dated September 4,
1991 which held that:
"The arguments of respondent on the finality of the dispositive portion of
the decision in this case is beside the point. What is important is that the
Commission has ruled that the Writ of Execution issued by the Labor
Arbiter in this case is proper. It is not really correct to say that said Writ of
Execution varied the terms of the judgment. At most, considering the
nature of labor proceedings there was, an ambiguity in said dispositive
8
Page | 74
portion which was subsequently clarified by the Labor Arbiter and the
Commission in the incidents which were initiated by INIMACO itself. By
sheer technicality and unfounded assertions, INIMACO would now reopen
the issue which was already resolved against it. It is not in keeping with the
established rules of practice and procedure to allow this attempt of
INIMACO to delay the final disposition of this case.
"WHEREFORE, in view of all the foregoing, this appeal is DISMISSED and
the Order appealed from is hereby AFFIRMED. Sce-dp
"With double costs against appellant."
Dissatisfied with the foregoing, petitioner filed the instant case, alleging
that the respondent NLRC committed grave abuse of discretion in affirming
the Order of the Labor Arbiter dated August 15, 1989, which declared the
liability of petitioner to be solidary.
The only issue in this petition is whether petitioners liability pursuant to
the Decision of the Labor Arbiter dated March 10, 1987, is solidary or not.
Calrs-pped
Upon careful examination of the pleadings filed by the parties, the Court
finds that petitioner INIMACOs liability is not solidary but merely joint and
that the respondent NLRC acted with grave abuse of discretion in
upholding the Labor Arbiters Alias Writ of Execution and subsequent
Orders to the effect that petitioners liability is solidary.
A solidary or joint and several obligation is one in which each debtor is
liable for the entire obligation, and each creditor is entitled to demand the
whole obligation.9 In a joint obligation each obligor answers only for a part
of the whole liability and to each obligee belongs only a part of the
correlative rights.10
Well-entrenched is the rule that solidary obligation cannot lightly be
inferred.11 There is a solidary liability only when the obligation expressly so
states, when the law so provides or when the nature of the obligation so
requires.12
In the dispositive portion of the Labor Arbiter, the word "solidary" does not
appear. The said fallo expressly states the following respondents therein as
liable, namely: Filipinas Carbon and Mining Corporation, Gerardo Sicat,
Antonio Gonzales, Industrial Management Development Corporation
(petitioner INIMACO), Chiu Chin Gin, and Lo Kuan Chin. Nor can it be
inferred therefrom that the liability of the six (6) respondents in the case
below is solidary, thus their liability should merely be joint.
Moreover, it is already a well-settled doctrine in this jurisdiction that, when
it is not provided in a judgment that the defendants are liable to pay jointly
and severally a certain sum of money, none of them may be compelled to
satisfy in full said judgment. In Oriental Commercial Co. vs. Abeto and
Mabanag13 this Court held:
"It is of no consequence that, under the contract of suretyship executed by
the parties, the obligation contracted by the sureties was joint and several
in character. The final judgment, which superseded the action for the
enforcement of said contract, declared the obligation to be merely joint,
and the same cannot be executed otherwise."14
Granting that the Labor Arbiter has committed a mistake in failing to
indicate in the dispositive portion that the liability of respondents therein is
solidary, the correction -- which is substantial -- can no longer be allowed in
this case because the judgment has already become final and executory.
Scc-alr
It is an elementary principle of procedure that the resolution of the court in
a given issue as embodied in the dispositive part of a decision or order is
the controlling factor as to settlement of rights of the parties. 15 Once a
decision or order becomes final and executory, it is removed from the
power or jurisdiction of the court which rendered it to further alter or
amend it.16 It thereby becomes immutable and unalterable and any
12
13
14
10
15
11
16
Page | 75
MARIVELES
SHIPYARD
CORP.,
Petitioner,
vs.HON. COURT OF APPEALS, LUIS REGONDOLA, MANUELIT
GATALAN, ORESCA AGAPITO, NOEL ALBADBAD, ROGELIO PINTUAN,
DANILO CRISOSTOMO, ROMULO MACALINAO, NESTOR FERER,
RICKY CUESTA, ROLLY ANDRADA, LARRY ROGOLA, FRANCISCO
LENOGON,
AUGUSTO
QUINTO,
ARFE
BERAMO,
BONIFACIO
TRINIDAD, ALFREDO ASCARRAGA, ERNESTO MAGNO, HONORARIO
HORTECIO, NELBERT PINEDA, GLEN ESTIPULAR, FRANCISCO
COMPUESTO, ISABELITO CORTEZ, MATURAN ROSAURO, SAMSON
CANAS, FEBIEN ISIP, JESUS RIPARIP, ALFREDO SIENES, ADOLAR
ALBERT, HONESTO CABANILLAS, AMPING CASTILLO and ELWIN
REVILLA, Respondents.
17
18
DECISION
QUISUMBING, J.:
For review on certiorari is the Resolution, 1 dated December 29, 1999, of the
Court of Appeals in CA-G.R. SP No. 55416, which dismissed outright the
petition for certiorari of Mariveles Shipyard Corp., due to a defective
certificate of non-forum shopping and non-submission of the required
documents to accompany said petition. Mariveles Shipyard Corp., had filed
a special civil action for certiorari with the Court of Appeals to nullify the
resolution2 of the National Labor Relations Commission (NLRC), dated April
22, 1999, in NLRC NCR Case No. 00-09-005440-96-A, which affirmed the
Labor Arbiters decision,3 dated May 22, 1998, holding petitioner jointly
and severally liable with Longest Force Investigation and Security Agency,
Inc., for the underpayment of wages and overtime pay due to the private
respondents. Likewise challenged in the instant petition is the resolution 4 of
the Court of Appeals, dated July 12, 2000, denying petitioners motion for
reconsideration.
The facts, as culled from records, are as follows:
Sometime on October 1993, petitioner Mariveles Shipyard Corporation
engaged the services of Longest Force Investigation and Security Agency,
Inc. (hereinafter, "Longest Force") to render security services at its
premises. Pursuant to their agreement, Longest Force deployed its security
guards, the private respondents herein, at the petitioners shipyard in
Mariveles, Bataan.
According to petitioner, it religiously complied with the terms of the
security contract with Longest Force, promptly paying its bills and the
contract rates of the latter. However, it found the services being rendered
by the assigned guards unsatisfactory and inadequate, causing it to
terminate its contract with Longest Force on April 1995. 5 Longest Force, in
turn, terminated the employment of the security guards it had deployed at
petitioners shipyard.
On September 2, 1996, private respondents filed a case for illegal
dismissal, underpayment of wages pursuant to the PNPSOSIA-PADPAO
rates, non-payment of overtime pay, premium pay for holiday and rest day,
service incentive leave pay, 13th month pay and attorneys fees, against
both Longest Force and petitioner, before the Labor Arbiter. Docketed as
NLRC NCR Case No. 00-09-005440-96-A, the case sought the guards
reinstatement with full backwages and without loss of seniority rights.
For its part, Longest Force filed a cross-claim 6 against the petitioner.
Longest Force admitted that it employed private respondents and assigned
them as security guards at the premises of petitioner from October 16,
1993 to April 30, 1995, rendering a 12 hours duty per shift for the said
period. It likewise admitted its liability as to the non-payment of the
Page | 76
Apr.
1-Dec. 7,090.00
31/94 (9 mos.)
5,810
1,280.00
11,520.00
Jan.
29/95
mos.)
5,810
1,410.00
5,597
1-Apr. 7,220.00
(3.97
On May 22, 1998, the Labor Arbiter decided NLRC NCR Case No. 00-09005440-96-A, to wit:
WHEREFORE, conformably with the foregoing, judgment is hereby rendered
ordering the respondents as follows:
1. DECLARING respondents Longest Force Investigation & Security Agency,
Inc.1wphi1 and Mariveles Shipyard Corporation jointly and severally liable
to pay the money claims of complainants representing underpayment of
wages and overtime pay in the total amount of P2,700,623.40 based on
the PADPAO rates of pay covering the period from October 16, 1993 up to
April 29, 1995 broken down as follows:
MONTHLY
ACTUA
PADPAO
L
RATES
SALARY
(8
hrs.
duty)
UNDERPAYMEN WAGE
T
DIRRERENTIAL
FOR
THE S
PERIOD
15/93 P5,485
P5,000
P485.00
x2
= P 5,485.00
x 3.5
= 11,602.50
Dec.
16/93-Mar. 6,630
31/94 (3.5 mos)
Oct.
16-Dec. P5,485.00
15/93(2 mos.)
P23,792.70
OVERTIME:
Oct.
16-Dec.
(2 mos.)
UNDERPAYMENT OF WAGES:
PERIOD
COVERED
TOTAL UNDERPAYMENTS - - - - - - - - - - - - - -
P970.00
2
5,000
1,630.00
5,705.00
Page | 77
Apr.
31/94 (9 mos.)
1-Dec. 7,090
x9
31,905.00
Jan.
29/95 (3.97 mos.)
1-Apr. 7,220
x 3.97
14,331.70
87,116.90
87,116.90
87,116.90
87,116.90
87,116.90
87,116.90
87,116.90
87,116.90
87,116.90
87,116.90
TOTAL OVERTIME - - - - - - - - -
P63,324.20
P 87,116.90
87,116.90
87,116.90
87,116.90
Page | 78
87,116.90
87,116.90
87,116.90
87,116.90
87,116.90
87,116.90
87,116.90
87,116.90
87,116.90
87,116.90
87,116.90
87,116.90
GRAND TOTAL
P 2,700,623.90
87,116.90
87,116.90
87,116.90
87,116.90
87,116.90
Backwages:
Page | 79
10/16
12/15/93
P 5,485.00 x 2 mos.
12/16/93
126,684.40
126,684.40
126,684.40
126,684.40
126,684.40
126,684.40
126,684.40
126,684.40
126,684.40
126,684.40
126,684.40
mos.
= 23,205.00
4/1
12/31/94
P 7,090.00 x 9 mos.
TOTAL
126,684.40
= P 10,970.00
3/31/94=3.5
1/1
4/29/95
P 7,220.00 x 3.97 mos.
mos.
mos.
= 63,810.00
3.97
mos.
= 28,663.40
P 126,684.407
P 126,684.408
126,684.40
126,684.40
Page | 80
126,684.40
126,684.40
126,684.40
126,684.40
126,684.40
126,684.40
126,684.40
126,684.40
126,684.40
126,684.40
126,684.40
126,684.40
GRAND TOTAL
P3,927,216.409
126,684.40
126,684.40
126,684.40
126,684.40
Petitioner appealed the foregoing to the NLRC in NLRC NCR Case No. 0009-005440-96-A. The labor tribunal, however, affirmed in toto the decision
of the Labor Arbiter. Petitioner moved for reconsideration, but this was
denied by the NLRC.
Page | 81
The petitioner then filed a special civil action for certiorari assailing the
NLRC judgment for having been rendered with grave abuse of discretion
with the Court of Appeals, docketed as CA-G.R. SP No. 55416. The Court of
Appeals, however, denied due course to the petition and dismissed it
outright for the following reasons:
1. The verification and certification on non-forum shopping is signed not by
duly authorized officer of petitioner corporation, but by counsel (Section 1,
Rule 65, 1997 Rules of Civil Procedure).
2. The petition is unaccompanied by copies of relevant and pertinent
documents, particularly the motion for reconsideration filed before the
NLRC (Section 1, Rule 65, 1997 Rules of Civil Procedure). 12
The petitioner then moved for reconsideration of the order of dismissal.
The appellate court denied the motion, pointing out that under prevailing
case law subsequent compliance with formal requirements for filing a
petition as prescribed by the Rules, does not ipso facto warrant a
reconsideration. In any event, it found no grave abuse of discretion on the
part of the NLRC to grant the writ of certiorari.
Hence, this present petition before us. Petitioner submits that THE COURT
OF APPEALS GRAVELY ERRED:
1. .IN DISMISSING THE PETITION AND DENYING THE MOTION FOR
RECONSIDERATION DESPITE THE FACT THAT PETITIONER SUBSTANTIALLY
COMPLIED WITH THE REQUIREMENTS OF SECTION 1, RULE 65, 1997 RULES
OF CIVIL PROCEDURE.
2. .IN RULING THAT PETITIONER WAS NOT DENIED DUE PROCESS OF LAW.
3. .IN AFFIRMING THE DECISION OF THE NATIONAL LABOR RELATIONS
COMMISSION THAT "LONGEST FORCE" AND PETITIONER ARE JOINTLY AND
SEVERALLY LIABLE FOR PAYMENT OF WAGES AND OVERTIME PAY DESPITE
THE CLEAR SHOWING THAT PETITIONER HAVE ALREADY PAID THE
SECURITY SERVICES THAT WAS RENDERED BY PRIVATE RESPONDENTS.
4. WHEN IT FAILED TO RULE THAT ONLY "LONGEST FORCE" SHOULD BE
SOLELY AND ULTIMATELY LIABLE IN THE INSTANT CASE. 13
We find the issues for our resolution to be: (1) Was it error for the Court of
Appeals to sustain its order of dismissal of petitioners special civil action
for certiorari, notwithstanding subsequent compliance with the
requirements under the Rules of Court by the petitioner? (2) Did the
appellate court err in not holding that petitioner was denied due process of
law by the NLRC? and (3) Did the appellate court grievously err in finding
petitioner jointly and severally liable with Longest Force for the payment of
wage differentials and overtime pay owing to the private respondents?
On the first issue, the Court of Appeals in dismissing CA-G.R. SP No. 55416
observed that: (1) the verification and certification of non-forum shopping
was not signed by any duly authorized officer of petitioner but merely by
petitioners counsel; and (2) the petition was not accompanied by a copy of
motion for reconsideration filed before the NLRC, thus violating Section 1, 14
Rule 65 of the Rules of Court. Hence, a dismissal was proper under Section
3,15 Rule 46 of the Rules.
In assailing the appellate courts ruling, the petitioner appeals to our sense
of compassion and kind consideration. It submits that the certification
signed by its counsel and attached to its petition filed with the Court of
Appeals is substantial compliance with the requirement. Moreover,
petitioner calls our attention to the fact that when it filed its motion for
reconsideration before the Court of Appeals, a joint verification and
certification of non-forum shopping duly signed by its Personnel Manager 16
and a copy of the Motion for Reconsideration 17 filed before the NLRC were
attached therein. Thus, petitioner prays that we take a liberal stance to
promote the ends of justice.
Petitioners plea for liberality, however, cannot be granted by the Court for
reasons herein elucidated.
It is settled that the requirement in the Rules that the certification of nonforum shopping should be executed and signed by the plaintiff or the
principal means that counsel cannot sign said certification unless clothed
with special authority to do so. 18 The reason for this is that the plaintiff or
principal knows better than anyone else whether a petition has previously
been filed involving the same case or substantially the same issues.
Hence, a certification signed by counsel alone is defective and constitutes
a valid cause for dismissal of the petition. 19 In the case of natural persons,
the Rule requires the parties themselves to sign the certificate of nonforum shopping. However, in the case of the corporations, the physical act
of signing may be performed, on behalf of the corporate entity, only by
specifically authorized individuals for the simple reason that corporations,
as artificial persons, cannot personally do the task themselves. 20 In this
case, not only was the originally appended certification signed by counsel,
but in its motion for reconsideration, still petitioner utterly failed to show
that Ms. Rosanna Ignacio, its Personnel Manager who signed the
verification and certification of non-forum shopping attached thereto, was
duly authorized for this purpose. It cannot be gainsaid that obedience to
the requirements of procedural rule is needed if we are to expect fair
results therefrom. Utter disregard of the rules cannot justly be rationalized
by harking on the policy of liberal construction.21
Thus, on this point, no error could be validly attributed to respondent Court
of Appeals. It did not err in dismissing the petition for non-compliance with
the requirements governing the certification of non-forum shopping.
Page | 82
Anent the second issue, petitioner avers that there was denial of due
process of law when the Labor Arbiter failed to have the case tried on the
merits. Petitioner adds that the Arbiter did not observe the mandatory
language of the then Sec. 5(b) Rule V (now Section 11, per amendment in
Resolution No. 01-02, Series of 2002) of the NLRC New Rules of Procedure
which provided that:
If the Labor Arbiter finds no necessity of further hearing after the parties
have submitted their position papers and supporting documents, he shall
issue an Order to that effect and shall inform the parties, stating the
reasons therefor. 22
Petitioners contention, in our view, lacks sufficient basis. Well settled is the
rule that the essence of due process is simply an opportunity to be heard,
or, as applied to administrative proceedings, an opportunity to explain
ones side or an opportunity to seek a reconsideration of the action or
ruling complained of.23 Not all cases require a trial-type hearing. The
requirement of due process in labor cases before a Labor Arbiter is
satisfied when the parties are given the opportunity to submit their
position papers to which they are supposed to attach all the supporting
documents or documentary evidence that would prove their respective
claims, in the event the Labor Arbiter determines that no formal hearing
would be conducted or that such hearing was not necessary. 24 In any
event, as found by the NLRC, petitioner was given ample opportunity to
present its side in several hearings conducted before the Labor Arbiter and
in the position papers and other supporting documents that it had
submitted. We find that such opportunity more than satisfies the
requirement of due process in labor cases.
On the third issue, petitioner argues that it should not be held jointly and
severally liable with Longest Force for underpayment of wages and
overtime pay because it had been religiously and promptly paying the bills
for the security services sent by Longest Force and that these are in
accordance with the statutory minimum wage. Also, petitioner contends
that it should not be held liable for overtime pay as private respondents
failed to present proof that overtime work was actually performed. Lastly,
petitioner claims that the Court of Appeals failed to render a decision that
finally disposed of the case because it did not specifically rule on the
immediate recourse of private respondents, that is, the matter of
reimbursement between petitioner and Longest Force in accordance with
Eagle Security Agency Inc. v. NLRC, 25 and Philippine Fisheries Development
Authority v. NLRC.26
Petitioners liability is joint and several with that of Longest Force, pursuant
to Articles 106, 107 and 109 of the Labor Code which provide as follows:
Page | 83
vs.
REBECCA G. ESTRELLA, RACHEL E. FLETCHER, PHILIPPINE PHOENIX
SURETY & INSURANCE INC., BATANGAS LAGUNA TAYABAS BUS CO.,
and WILFREDO DATINGUINOO, respondents.
DECISION
On the issue of the propriety of the award of overtime pay despite the
alleged lack of proof thereof, suffice it to state that such involves a
determination and evaluation of facts which cannot be done in a petition
for review. Well established is the rule that in an appeal via certiorari, only
questions of law may be reviewed.32
One final point. Upon review of the award of backwages and attorneys
fees, we discovered certain errors that happened in the addition of the
amount of individual backwages that resulted in the erroneous total
amount of backwages and attorneys fees. These errors ought to be
properly rectified now. Thus, the correct sum of individual backwages
should be P126,648.40 instead of P126,684.40, while the correct sum of
total backwages awarded and attorneys fees should be P3,926,100.40 and
P392,610.04, instead of P3,927,216.40 and P392,721.64, respectively.
WHEREFORE, the Resolution of the Court of Appeals in CA-G.R. SP No.
55416 is AFFIRMED with MODIFICATION. Petitioner and Longest Force are
held liable jointly and severally for underpayment of wages and overtime
pay of the security guards, without prejudice to petitioners right of
reimbursement from Longest Force Investigation and Security Agency, Inc.
The amounts payable to complaining security guards, herein private
respondents, by way of total backwages and attorneys fees are hereby set
at P3,926,100.40 and P392,610.04, respectively. Costs against petitioner.
SO ORDERED.
G.R. No. 147791
CONSTRUCTION
PHILIPPINES,
September 8, 2006
DEVELOPMENT
CORPORATION
petitioner,
OF
THE
YNARES-SANTIAGO, J.:
This petition for review assails the March 29, 2001 Decision 1 of the Court of
Appeals in CA-G.R. CV No. 46896, which affirmed with modification the
February 9, 1993 Decision2 of the Regional Trial Court of Manila, Branch 13,
in Civil Case No. R-82-2137, finding Batangas Laguna Tayabas Bus Co.
(BLTB) and Construction Development Corporation of the Philippines
(CDCP) liable for damages.
The antecedent facts are as follows:
mid
left
lower
3rd
chin
leg
Page | 84
not exercise the diligence of a good father of a family in the selection and
supervision of their employees; (3) that BLTB allowed its bus to operate
knowing that it lacked proper maintenance thus exposing its passengers to
grave danger; (4) that they suffered actual damages amounting to
P250,000.00 for Estrella and P300,000.00 for Fletcher; (5) that they
suffered physical discomfort, serious anxiety, fright and mental anguish,
besmirched reputation and wounded feelings, moral shock, and lifelong
social humiliation; (6) that defendants failed to act with justice, give
respondents their due, observe honesty and good faith which entitles them
to claim for exemplary damage; and (7) that they are entitled to a
reasonable amount of attorney's fees and litigation expenses.
CDCP filed its Answer6 which was later amended to include a third-party
complaint against Philippine Phoenix Surety and Insurance, Inc. (Phoenix). 7
On February 9, 1993, the trial court rendered a decision finding CDCP and
BLTB and their employees liable for damages, the dispositive portion of
which, states:
WHEREFORE, judgment is rendered:
In the Complaint
1. In favor of the plaintiffs and against the defendants BLTB, Wilfredo
Datinguinoo, Construction and Development Corporation of the Philippines
(now PNCC) and Espiridion Payunan, Jr., ordering said defendants, jointly
and severally to pay the plaintiffs the sum of P79,254.43 as actual
damages and to pay the sum of P10,000.00 as attorney's fees or a total of
P89,254.43;
2. In addition, defendant Construction and Development Corporation of the
Philippines and defendant Espiridion Payunan, Jr., shall pay the plaintiffs
the amount of Fifty Thousand (P50,000.00) Pesos to plaintiff Rachel
Fletcher and Twenty Five Thousand (P25,000.00) Pesos to plaintiff Rebecca
Estrella;
3. On the counterclaim of BLTB Co. and Wilfredo Datinguinoo
Dismissing the counterclaim;
4. On the crossclaim against Construction and Development Corporation of
the Philippines (now PNCC) and Espiridion Payunan, Jr.
Dismissing the crossclaim;
SO ORDERED.8
The trial court held that BLTB, as a common carrier, was bound to observe
extraordinary diligence in the vigilance over the safety of its passengers. It
must carry the passengers safely as far as human care and foresight
provide, using the utmost diligence of very cautious persons, with a due
regard for all the circumstances. Thus, where a passenger dies or is
injured, the carrier is presumed to have been at fault or has acted
negligently. BLTB's inability to carry respondents to their destination gave
rise to an action for breach of contract of carriage while its failure to rebut
the presumption of negligence made it liable to respondents for the
breach.9
Regarding CDCP, the trial court found that the tractor-truck it owned
bumped the BLTB bus from behind. Evidence showed that CDCP's driver
was reckless and driving very fast at the time of the incident. The gross
negligence of its driver raised the presumption that CDCP was negligent
either in the selection or in the supervision of its employees which it failed
to rebut thus making it and its driver liable to respondents. 10
Unsatisfied with the award of damages and attorney's fees by the trial
court, respondents moved that the decision be reconsidered but was
denied. Respondents elevated the case11 to the Court of Appeals which
affirmed the decision of the trial court but modified the amount of
damages, the dispositive portion of which provides:
WHEREFORE, the assailed decision dated October 7, 1993 of the Regional
Trial Court, Branch 13, Manila is hereby AFFIRMED with the following
MODIFICATION:
1. The interest of six (6) percent per annum on the actual damages of
P79,354.43 should commence to run from the time the judicial demand
was made or from the filing of the complaint on February 4, 1980;
Page | 85
Corporation of
ordered to pay
the amount of
damages and
SO ORDERED.12
The Court of Appeals held that the actual or compensatory damage sought
by respondents for the injuries they sustained in the form of hospital bills
were already liquidated and were ascertained. Accordingly, the 6% interest
per annum should commence to run from the time the judicial demand was
made or from the filing of the complaint and not from the date of
judgment. The Court of Appeals also awarded attorney's fees equivalent to
30% of the total amount recovered based on the retainer agreement of the
parties. The appellate court also held that respondents are entitled to
exemplary and moral damages. Finally, it affirmed the ruling of the trial
court that the claim of CDCP against Phoenix had already prescribed.
The issues for resolution are as follows: (1) whether BLTB and its driver
Wilfredo Datinguinoo are solely liable for the damages sustained by
respondents; (2) whether the damages, attorney's fees and legal interest
awarded by the CA are excessive and unfounded; (3) whether CDCP can
recover under its insurance policy from Phoenix.
Petitioner contends that since it was made solidarily liable with BLTB for
actual damages and attorney's fees in paragraph 1 of the trial court's
decision, then it should no longer be held liable to pay the amounts stated
in paragraph 2 of the same decision. Petitioner claims that the liability for
actual damages and attorney's fees is based on culpa contractual, thus,
only BLTB should be held liable. As regards paragraph 2 of the trial court's
decision, petitioner claims that it is ambiguous and arbitrary because the
dispositive portion did not state the basis and nature of such award.
Respondents, on the other hand, argue that petitioner is also at fault,
hence, it was properly joined as a party. There may be an action arising out
of one incident where questions of fact are common to all. Thus, the cause
of action based on culpa aquiliana in the civil suit they filed against it was
valid.
The petition lacks merit.
Page | 86
to the same extent and in the same manner as if they had performed the
wrongful act themselves. x x x
Joint tort feasors are jointly and severally liable for the tort which they
commit. The persons injured may sue all of them or any number less than
all. Each is liable for the whole damages caused by all, and all together are
jointly liable for the whole damage. It is no defense for one sued alone,
that the others who participated in the wrongful act are not joined with him
as defendants; nor is it any excuse for him that his participation in the tort
was insignificant as compared to that of the others. x x x
Joint tort feasors are not liable pro rata. The damages can not be
apportioned among them, except among themselves. They cannot insist
upon an apportionment, for the purpose of each paying an aliquot part.
They are jointly and severally liable for the whole amount. x x x
A payment in full for the damage done, by one of the joint tort feasors, of
course satisfies any claim which might exist against the others. There can
be but satisfaction. The release of one of the joint tort feasors by
agreement generally operates to discharge all. x x x
Of course the court during trial may find that some of the alleged tort
feasors are liable and that others are not liable. The courts may release
some for lack of evidence while condemning others of the alleged tort
feasors. And this is true even though they are charged jointly and
severally.19
Petitioner's claim that paragraph 2 of the dispositive portion of the trial
court's decision is ambiguous and arbitrary and also entitles respondents
to recover twice is without basis. In the body of the trial court's decision, it
was clearly stated that petitioner and its driver Payunan, Jr., are jointly and
solidarily liable for moral damages in the amount of P50,000.00 to
respondent Fletcher and P25,000.00 to respondent Estrella. 20 Moreover,
there could be no double recovery because the award in paragraph 2 is for
moral damages while the award in paragraph 1 is for actual damages and
attorney's fees.
Petitioner next claims that the damages, attorney's fees, and legal interest
awarded by the Court of Appeals are excessive.
Moral damages may be recovered in quasi-delicts causing physical
injuries.21 The award of moral damages in favor of Fletcher and Estrella in
the amount of P80,000.00 must be reduced since prevailing jurisprudence
fixed the same at P50,000.00.22 While moral damages are not intended to
enrich the plaintiff at the expense of the defendant, the award should
nonetheless be commensurate to the suffering inflicted. 23
Page | 87
Page | 88
Any person having any claim upon the policy issued pursuant to this
chapter shall, without any unnecessary delay, present to the insurance
company concerned a written notice of claim setting forth the nature,
extent and duration of the injuries sustained as certified by a duly licensed
physician. Notice of claim must be filed within six months from date of the
accident, otherwise, the claim shall be deemed waived. Action or suit for
recovery of damage due to loss or injury must be brought in proper cases,
with the Commissioner or Courts within one year from denial of the claim,
otherwise, the claimant's right of action shall prescribe. (As amended by
PD 1814, BP 874.)34
The law is clear and leaves no room for interpretation. A written notice of
claim must be filed within six months from the date of the accident. Since
petitioner never made any claim within six months from the date of the
accident, its claim has already prescribed.
WHEREFORE, the instant petition is DENIED. The Decision of the Court of
Appeals in CA-G.R. CV No. 46896 dated March 29, 2001, which modified
the Decision of the Regional Trial Court of Manila, Branch 13, in Civil Case
No. R-82-2137, is AFFIRMED with the MODIFICATIONS that petitioner is
held jointly and severally liable to pay (1) actual damages in the amount of
P79,354.43; (2) moral damages in the amount of P50,000.00 each for
Rachel Fletcher and Rebecca Estrella; (3) exemplary damages in the
amount of P20,000.00 each for Rebecca Estrella and Rachel Fletcher; and
(4) thirty percent (30%) of the total amount recovered as attorney's fees.
The total amount adjudged shall earn interest at the rate of 6% per annum
from the date of judgment of the trial court until finality of this judgment.
From the time this Decision becomes final and executory and the judgment
amount remains unsatisfied, the same shall earn interest at the rate of
12% per annum until its satisfaction.
SO ORDERED.
G.R. No. 157917
SPOUSES
TEODORO1
and
NANETTE
PERENA,
Petitioners,
vs.
SPOUSES TERESITA PHILIPPINE NICOLAS and L. ZARATE, NATIONAL
RAILWAYS, and the COURT OF APPEALS Respondents.
DECISION
BERSAMIN, J.:
The operator of a. school bus service is a common carrier in the eyes of the
law. He is bound to observe extraordinary diligence in the conduct of his
business. He is presumed to be negligent when death occurs to a
passenger. His liability may include indemnity for loss of earning capacity
even if the deceased passenger may only be an unemployed high school
student at the time of the accident.
The Case
By petition for review on certiorari, Spouses Teodoro and Nanette Perefia
(Perefias) appeal the adverse decision promulgated on November 13,
2002, by which the Court of Appeals (CA) affirmed with modification the
decision rendered on December 3, 1999 by the Regional Trial Court (RTC),
Branch 260, in Paraaque City that had decreed them jointly and severally
liable with Philippine National Railways (PNR), their co-defendant, to
Spouses Nicolas and Teresita Zarate (Zarates) for the death of their 15year old son, Aaron John L. Zarate (Aaron), then a high school student of
Don Bosco Technical Institute (Don Bosco).
Antecedents
The Pereas were engaged in the business of transporting students from
their respective residences in Paraaque City to Don Bosco in Pasong
Tamo, Makati City, and back. In their business, the Pereas used a KIA
Ceres Van (van) with Plate No. PYA 896, which had the capacity to
transport 14 students at a time, two of whom would be seated in the front
beside the driver, and the others in the rear, with six students on either
side. They employed Clemente Alfaro (Alfaro) as driver of the van.
In June 1996, the Zarates contracted the Pereas to transport Aaron to and
from Don Bosco. On August 22, 1996, as on previous school days, the van
picked Aaron up around 6:00 a.m. from the Zarates residence. Aaron took
his place on the left side of the van near the rear door. The van, with its airconditioning unit turned on and the stereo playing loudly, ultimately
carried all the 14 student riders on their way to Don Bosco. Considering
that the students were due at Don Bosco by 7:15 a.m., and that they were
already running late because of the heavy vehicular traffic on the South
Superhighway, Alfaro took the van to an alternate route at about 6:45 a.m.
by traversing the narrow path underneath the Magallanes Interchange that
was then commonly used by Makati-bound vehicles as a short cut into
Makati. At the time, the narrow path was marked by piles of construction
materials and parked passenger jeepneys, and the railroad crossing in the
narrow path had no railroad warning signs, or watchmen, or other
responsible persons manning the crossing. In fact, the bamboo barandilla
was up, leaving the railroad crossing open to traversing motorists.
At about the time the van was to traverse the railroad crossing, PNR
Commuter No. 302 (train), operated by Jhonny Alano (Alano), was in the
vicinity of the Magallanes Interchange travelling northbound. As the train
Page | 89
neared the railroad crossing, Alfaro drove the van eastward across the
railroad tracks, closely tailing a large passenger bus. His view of the
oncoming train was blocked because he overtook the passenger bus on its
left side. The train blew its horn to warn motorists of its approach. When
the train was about 50 meters away from the passenger bus and the van,
Alano applied the ordinary brakes of the train. He applied the emergency
brakes only when he saw that a collision was imminent. The passenger bus
successfully crossed the railroad tracks, but the van driven by Alfaro did
not. The train hit the rear end of the van, and the impact threw nine of the
12 students in the rear, including Aaron, out of the van. Aaron landed in
the path of the train, which dragged his body and severed his head,
instantaneously killing him. Alano fled the scene on board the train, and
did not wait for the police investigator to arrive.
Devastated by the early and unexpected death of Aaron, the Zarates
commenced this action for damages against Alfaro, the Pereas, PNR and
Alano. The Pereas and PNR filed their respective answers, with crossclaims against each other, but Alfaro could not be served with summons.
At the pre-trial, the parties stipulated on the facts and issues, viz:
A. FACTS:
That spouses Zarate were the legitimate parents of Aaron John L.
Zarate;(1)
Spouses Zarate engaged the services of spouses Perea for the adequate
and safe transportation carriage of the former spouses' son from their
residence in Paraaque to his school at the Don Bosco Technical Institute in
Makati City;(2)
During the effectivity of the contract of carriage and in the implementation
thereof, Aaron, the minor son of spouses Zarate died in connection with a
vehicular/train collision which occurred while Aaron was riding the
contracted carrier Kia C(3)eres van of spouses Perea, then driven and
operated by the latter's employee/authorized driver Clemente Alfaro, which
van collided with the train of PNR, at around 6:45 A.M. of August 22, 1996,
within the vicinity of the Magallanes Interchange in Makati City, Metro
Manila, Philippines;
At the time of the vehicular/train collision, the subject site of the
vehicular/train collision was a railroad crossing used by motorists for
crossing the railroad tracks;(4)
During the said time of the vehicular/train collision, there were no
appropriate and safety warning signs and railings at the site commonly
used for railroad crossing;(5)
At the material time, countless number of Makati bound public utility and
private vehicles used on a daily basis the site of the collision as an
alternative route and short-cut to Makati;(6)
The train driver or operator left the scene of the incident on board the
commuter train involved without waiting for the police investigator;(7)
The site commonly used for railroad crossing by motorists was not in fact
intended by the railroad operator for railroad crossing at the time of the
vehicular collision;(8)
PNR received the demand letter of the spouses Zarate;(9)
PNR refused to acknowledge any liability for the vehicular/train
collision;(10)
The eventual closure of the railroad crossing alleged by PNR was an
internal arrangement between the former and its project contractor;
and(11)
The site of the vehicular/train collision was within the vicinity or less than
100 meters from the Magallanes station of PNR.(12)
B. ISSUES
(1) Whether or not defendant-driver of the van is, in the performance of his
functions, liable for negligence constituting the proximate cause of the
vehicular collision, which resulted in the death of plaintiff spouses' son;
(2) Whether or not the defendant spouses Perea being the employer of
defendant Alfaro are liable for any negligence which may be attributed to
defendant Alfaro;
(3) Whether or not defendant Philippine National Railways being the
operator of the railroad system is liable for negligence in failing to provide
adequate safety warning signs and railings in the area commonly used by
motorists for railroad crossings, constituting the proximate cause of the
vehicular collision which resulted in the death of the plaintiff spouses' son;
(4) Whether or not defendant spouses Perea are liable for breach of the
contract of carriage with plaintiff-spouses in failing to provide adequate
and safe transportation for the latter's son;
(5) Whether or not defendants spouses are liable for actual, moral
damages, exemplary damages, and attorney's fees;
Page | 90
(7) Whether or not defendant-spouses are civilly liable for the accidental
death of Aaron John Zarate;
(8) Whether or not defendant PNR was grossly negligent in operating the
commuter train involved in the accident, in allowing or tolerating the
motoring public to cross, and its failure to install safety devices or
equipment at the site of the accident for the protection of the public;
(10) Whether or not defendant PNR should pay plaintiffs directly and fully
on the amounts claimed by the latter in their Complaint by reason of its
gross negligence;
(11) Whether or not defendant PNR is liable to defendants spouses for
actual, moral and exemplary damages and attorney's fees.2
On June 29, 2000, the RTC denied the Pereas motion for reconsideration, 4
reiterating that the cooperative gross negligence of the Pereas and PNR
had caused the collision that led to the death of Aaron; and that the
damages awarded to the Zarates were not excessive, but based on the
established circumstances.
The Zarates claim against the Pereas was upon breach of the contract of
carriage for the safe transport of Aaron; but that against PNR was based on
quasi-delict under Article 2176, Civil Code.
In their defense, the Pereas adduced evidence to show that they had
exercised the diligence of a good father of the family in the selection and
supervision of Alfaro, by making sure that Alfaro had been issued a drivers
license and had not been involved in any vehicular accident prior to the
collision; that their own son had taken the van daily; and that Teodoro
Perea had sometimes accompanied Alfaro in the vans trips transporting
the students to school.
For its part, PNR tended to show that the proximate cause of the collision
had been the reckless crossing of the van whose driver had not first
stopped, looked and listened; and that the narrow path traversed by the
van had not been intended to be a railroad crossing for motorists.
Page | 91
The trial court erred in dismissing the cross-claim of the appellants Pereas
against the Philippine National Railways and in not holding the latter and
its train driver primarily responsible for the incident.
Issues
In this appeal, the Pereas list the following as the errors committed by the
CA, to wit:
The trial court erred in awarding excessive damages and attorneys fees.
The trial court erred in awarding damages in the form of deceaseds loss of
earning capacity in the absence of sufficient basis for such an award.
I. The lower court erred when it upheld the trial courts decision holding the
petitioners jointly and severally liable to pay damages with Philippine
National Railways and dismissing their cross-claim against the latter.
II. The lower court erred in affirming the trial courts decision awarding
damages for loss of earning capacity of a minor who was only a high school
student at the time of his death in the absence of sufficient basis for such
an award.
III. The lower court erred in not reducing further the amount of damages
awarded, assuming petitioners are liable at all.
SO ORDERED.
The CA upheld the award for the loss of Aarons earning capacity, taking
cognizance of the ruling in Cariaga v. Laguna Tayabas Bus Company and
Manila Railroad Company,7 wherein the Court gave the heirs of Cariaga a
sum representing the loss of the deceaseds earning capacity despite
Cariaga being only a medical student at the time of the fatal incident.
Applying the formula adopted in the American Expectancy Table of
Mortality:
2/3 x (80 - age at the time of death) = life expectancy
the CA determined the life expectancy of Aaron to be 39.3 years upon
reckoning his life expectancy from age of 21 (the age when he would have
graduated from college and started working for his own livelihood) instead
of 15 years (his age when he died). Considering that the nature of his work
and his salary at the time of Aarons death were unknown, it used the
prevailing minimum wage of P 280.00/day to compute Aarons gross
annual salary to be P 110,716.65, inclusive of the thirteenth month pay.
Multiplying this annual salary by Aarons life expectancy of 39.3 years, his
gross income would aggregate to P 4,351,164.30, from which his estimated
expenses in the sum of P 2,189,664.30 was deducted to finally arrive at P
2,161,500.00 as net income. Due to Aarons computed net income turning
out to be higher than the amount claimed by the Zarates, only P
2,109,071.00, the amount expressly prayed for by them, was granted.
On April 4, 2003, the CA denied the Pereas motion for reconsideration. 8
Ruling
The petition has no merit.
1.
Were
the
Pereas
and severally liable for damages?
and
PNR
jointly
The Zarates brought this action for recovery of damages against both the
Pereas and the PNR, basing their claim against the Pereas on breach of
contract of carriage and against the PNR on quasi-delict.
The RTC found the Pereas and the PNR negligent. The CA affirmed the
findings.
We concur with the CA.
To start with, the Pereas defense was that they exercised the diligence of
a good father of the family in the selection and supervision of Alfaro, the
van driver, by seeing to it that Alfaro had a drivers license and that he had
not been involved in any vehicular accident prior to the fatal collision with
the train; that they even had their own son travel to and from school on a
daily basis; and that Teodoro Perea himself sometimes accompanied
Alfaro in transporting the passengers to and from school. The RTC gave
scant consideration to such defense by regarding such defense as
inappropriate in an action for breach of contract of carriage.
We find no adequate cause to differ from the conclusions of the lower
courts that the Pereas operated as a common carrier; and that their
Page | 92
Page | 93
roads by the method by which the business was conducted; and (c)
transporting students for a fee. Despite catering to a limited clientle, the
Pereas operated as a common carrier because they held themselves out
as a ready transportation indiscriminately to the students of a particular
school living within or near where they operated the service and for a fee.
The common carriers standard of care and vigilance as to the safety of the
passengers is defined by law. Given the nature of the business and for
reasons of public policy, the common carrier is bound "to observe
extraordinary diligence in the vigilance over the goods and for the safety of
the passengers transported by them, according to all the circumstances of
each case."22 Article 1755 of the Civil Code specifies that the common
carrier should "carry the passengers safely as far as human care and
foresight can provide, using the utmost diligence of very cautious persons,
with a due regard for all the circumstances." To successfully fend off
liability in an action upon the death or injury to a passenger, the common
carrier must prove his or its observance of that extraordinary diligence;
otherwise, the legal presumption that he or it was at fault or acted
negligently would stand.23 No device, whether by stipulation, posting of
notices, statements on tickets, or otherwise, may dispense with or lessen
the responsibility of the common carrier as defined under Article 1755 of
the Civil Code. 24
And, secondly, the Pereas have not presented any compelling defense or
reason by which the Court might now reverse the CAs findings on their
liability. On the contrary, an examination of the records shows that the
evidence fully supported the findings of the CA.
As earlier stated, the Pereas, acting as a common carrier, were already
presumed to be negligent at the time of the accident because death had
occurred to their passenger.25 The presumption of negligence, being a
presumption of law, laid the burden of evidence on their shoulders to
establish that they had not been negligent. 26 It was the law no less that
required them to prove their observance of extraordinary diligence in
seeing to the safe and secure carriage of the passengers to their
destination. Until they did so in a credible manner, they stood to be held
legally responsible for the death of Aaron and thus to be held liable for all
the natural consequences of such death.
There is no question that the Pereas did not overturn the presumption of
their negligence by credible evidence. Their defense of having observed
the diligence of a good father of a family in the selection and supervision of
their driver was not legally sufficient. According to Article 1759 of the Civil
Code, their liability as a common carrier did not cease upon proof that they
exercised all the diligence of a good father of a family in the selection and
supervision of their employee. This was the reason why the RTC treated
this defense of the Pereas as inappropriate in this action for breach of
contract of carriage.
The Pereas were liable for the death of Aaron despite the fact that their
driver might have acted beyond the scope of his authority or even in
violation of the orders of the common carrier. 27 In this connection, the
records showed their drivers actual negligence. There was a showing, to
begin with, that their driver traversed the railroad tracks at a point at
which the PNR did not permit motorists going into the Makati area to cross
the railroad tracks. Although that point had been used by motorists as a
shortcut into the Makati area, that fact alone did not excuse their driver
into taking that route. On the other hand, with his familiarity with that
shortcut, their driver was fully aware of the risks to his passengers but he
still disregarded the risks. Compounding his lack of care was that loud
music was playing inside the air-conditioned van at the time of the
accident. The loudness most probably reduced his ability to hear the
warning horns of the oncoming train to allow him to correctly appreciate
the lurking dangers on the railroad tracks. Also, he sought to overtake a
passenger bus on the left side as both vehicles traversed the railroad
tracks. In so doing, he lost his view of the train that was then coming from
the opposite side of the passenger bus, leading him to miscalculate his
chances of beating the bus in their race, and of getting clear of the train.
As a result, the bus avoided a collision with the train but the van got
slammed at its rear, causing the fatality. Lastly, he did not slow down or go
to a full stop before traversing the railroad tracks despite knowing that his
slackening of speed and going to a full stop were in observance of the right
of way at railroad tracks as defined by the traffic laws and regulations. 28 He
thereby violated a specific traffic regulation on right of way, by virtue of
which he was immediately presumed to be negligent. 29
The omissions of care on the part of the van driver constituted
negligence,30 which, according to Layugan v. Intermediate Appellate
Court,31 is "the omission to do something which a reasonable man, guided
by those considerations which ordinarily regulate the conduct of human
affairs, would do, or the doing of something which a prudent and
reasonable man would not do,32 or as Judge Cooley defines it, (t)he failure
to observe for the protection of the interests of another person, that
degree of care, precaution, and vigilance which the circumstances justly
demand, whereby such other person suffers injury."33
The test by which to determine the existence of negligence in a particular
case has been aptly stated in the leading case of Picart v. Smith, 34
thuswise:
The test by which to determine the existence of negligence in a particular
case may be stated as follows: Did the defendant in doing the alleged
negligent act use that reasonable care and caution which an ordinarily
prudent person would have used in the same situation? If not, then he is
guilty of negligence. The law here in effect adopts the standard supposed
to be supplied by the imaginary conduct of the discreet paterfamilias of the
Roman law. The existence of negligence in a given case is not determined
by reference to the personal judgment of the actor in the situation before
him. The law considers what would be reckless, blameworthy, or negligent
Page | 94
for
loss
of
The RTC awarded indemnity for loss of Aarons earning capacity. Although
agreeing with the RTC on the liability, the CA modified the amount. Both
lower courts took into consideration that Aaron, while only a high school
student, had been enrolled in one of the reputable schools in the
Philippines and that he had been a normal and able-bodied child prior to
his death. The basis for the computation of Aarons earning capacity was
not what he would have become or what he would have wanted to be if not
for his untimely death, but the minimum wage in effect at the time of his
death. Moreover, the RTCs computation of Aarons life expectancy rate
was not reckoned from his age of 15 years at the time of his death, but on
21 years, his age when he would have graduated from college.
We find the considerations taken into account by the lower courts to be
reasonable and fully warranted.
Yet, the Pereas submit that the indemnity for loss of earning capacity was
speculative and unfounded.1wphi1 They cited People v. Teehankee, Jr.,37
where the Court deleted the indemnity for victim Jussi Leinos loss of
earning capacity as a pilot for being speculative due to his having
graduated from high school at the International School in Manila only two
years before the shooting, and was at the time of the shooting only
enrolled in the first semester at the Manila Aero Club to pursue his
ambition to become a professional pilot. That meant, according to the
Court, that he was for all intents and purposes only a high school graduate.
We reject the Pereas submission.
Page | 95
First of all, a careful perusal of the Teehankee, Jr. case shows that the
situation there of Jussi Leino was not akin to that of Aaron here. The CA and
the RTC were not speculating that Aaron would be some highly-paid
professional, like a pilot (or, for that matter, an engineer, a physician, or a
lawyer). Instead, the computation of Aarons earning capacity was
premised on him being a lowly minimum wage earner despite his being
then enrolled at a prestigious high school like Don Bosco in Makati, a fact
that would have likely ensured his success in his later years in life and at
work.
And, secondly, the fact that Aaron was then without a history of earnings
should not be taken against his parents and in favor of the defendants
whose negligence not only cost Aaron his life and his right to work and
earn money, but also deprived his parents of their right to his presence and
his services as well. Our law itself states that the loss of the earning
capacity of the deceased shall be the liability of the guilty party in favor of
the heirs of the deceased, and shall in every case be assessed and
awarded by the court "unless the deceased on account of permanent
physical disability not caused by the defendant, had no earning capacity at
the time of his death."38 Accordingly, we emphatically hold in favor of the
indemnification for Aarons loss of earning capacity despite him having
been unemployed, because compensation of this nature is awarded not for
loss of time or earnings but for loss of the deceaseds power or ability to
earn money.39
This favorable treatment of the Zarates claim is not unprecedented. In
Cariaga v. Laguna Tayabas Bus Company and Manila Railroad Company, 40
fourth-year medical student Edgardo Carriagas earning capacity, although
he survived the accident but his injuries rendered him permanently
incapacitated, was computed to be that of the physician that he dreamed
to become. The Court considered his scholastic record sufficient to justify
the assumption that he could have finished the medical course and would
have passed the medical board examinations in due time, and that he
could have possibly earned a modest income as a medical practitioner.
Also, in People v. Sanchez,41 the Court opined that murder and rape victim
Eileen Sarmienta and murder victim Allan Gomez could have easily landed
good-paying jobs had they graduated in due time, and that their jobs
would probably pay them high monthly salaries from P 10,000.00 to P
15,000.00 upon their graduation. Their earning capacities were computed
at rates higher than the minimum wage at the time of their deaths due to
their being already senior agriculture students of the University of the
Philippines in Los Baos, the countrys leading educational institution in
agriculture.
3.
Were the amounts of damages excessive?
The Pereas plead for the reduction of the moral and exemplary damages
awarded to the Zarates in the respective amounts of P 2,500,000.00 and P
1,000,000.00 on the ground that such amounts were excessive.
Page | 96
2% service charge which was deleted pursuant to Central Bank Circular No.
783. Not fully satisfied with the decision of the appellate court, both
parties filed their respective motions for reconsideration. xli Petitioners
prayed for the reduction of the 5% stipulated penalty for being
unconscionable. The bank, on the other hand, asked that the payment of
interest and penalty be commenced not from the date of filing of complaint
but from the time of default as so stipulated in the contract of the parties.
On 28 October 1998, the Court of Appeals resolved the two motions thusly:
We find merit in plaintiff-appellees claim that the principal sum of
P114,416.00 with interest thereon must commence not on the date of filing
of the complaint as we have previously held in our decision but on the date
when the obligation became due.
Default generally begins from the moment the creditor demands the
performance of the obligation. However, demand is not necessary to
render the obligor in default when the obligation or the law so provides.
In the case at bar, defendants-appellants executed a promissory note
where they undertook to pay the obligation on its maturity date 'without
necessity of demand.' They also agreed to pay the interest in case of nonpayment from the date of default.
x x xx x x
xxx
xxx
xxx
Page | 97
2.
The sum equivalent to 10% of
indebtedness as and for attorneys fees.xlii
the
total
amount
of
the
particularly vis-a-vis the U.S. dollar, taking into account the time frame of
its occurrence. The Bank would stress that only the amount of P5,584.00
had been remitted out of the entire loan of P120,000.00. xlvi
A penalty clause, expressly recognized by law, xlvii is an accessory
undertaking to assume greater liability on the part of an obligor in case of
breach of an obligation. It functions to strengthen the coercive force of the
obligationxlviii and to provide, in effect, for what could be the liquidated
damages resulting from such a breach. The obligor would then be bound
to pay the stipulated indemnity without the necessity of proof on the
existence and on the measure of damages caused by the breach. xlix
Although a court may not at liberty ignore the freedom of the parties to
agree on such terms and conditions as they see fit that contravene neither
law nor morals, good customs, public order or public policy, a stipulated
penalty, nevertheless, may be equitably reduced by the courts if it is
iniquitous or unconscionable or if the principal obligation has been partly or
irregularly complied with.l
The question of whether a penalty is reasonable or iniquitous can be partly
subjective and partly objective. Its resolution would depend on such
factors as, but not necessarily confined to, the type, extent and purpose of
the penalty, the nature of the obligation, the mode of breach and its
consequences, the supervening realities, the standing and relationship of
the parties, and the like, the application of which, by and large, is
addressed to the sound discretion of the court. In Rizal Commercial
Banking Corp. vs. Court of Appeals,li just an example, the Court has
tempered the penalty charges after taking into account the debtors pitiful
situation and its offer to settle the entire obligation with the creditor bank.
The stipulated penalty might likewise be reduced when a partial or
irregular performance is made by the debtor. lii The stipulated penalty might
even be deleted such as when there has been substantial performance in
good faith by the obligor, liii when the penalty clause itself suffers from fatal
infirmity, or when exceptional circumstances so exist as to warrant it. liv
The Court of Appeals, exercising its good judgment in the instant case, has
reduced the penalty interest from 5% a month to 3% a month which
petitioner still disputes. Given the circumstances, not to mention the
repeated acts of breach by petitioners of their contractual obligation, the
Court sees no cogent ground to modify the ruling of the appellate court..
Anent the stipulated interest of 15.189% per annum, petitioners, for the
first time, question its reasonableness and prays that the Court reduce the
amount. This contention is a fresh issue that has not been raised and
ventilated before the courts below. In any event, the interest stipulation,
on its face, does not appear as being that excessive. The essence or
rationale for the payment of interest, quite often referred to as cost of
money, is not exactly the same as that of a surcharge or a penalty. A
penalty stipulation is not necessarily preclusive of interest, if there is an
agreement to that effect, the two being distinct concepts which may
separately be demanded.lv What may justify a court in not allowing the
Page | 98
Page | 99
The Case
Before us is a Petition for Review[1] under Rule 45 of the Rules of Court,
assailing the May 22, 2002 Decision [2] of the Court of Appeals (CA) in CAGR CV No. 51629 and its March 4, 2003 Resolution [3] denying petitioners
Motion for Reconsideration. The assailed Decision disposed thus:
WHEREFORE, in view of the foregoing, judgment is hereby rendered as
follows: (1) In Civil Case No. 93-68266, the appealed decision[,] is
AFFIRMED with MODIFICATION[,] ordering [Respondent] Philippine
Amusement and Gaming Corporation to pay [Petitioner] Pryce Properties
Corporation the total amount of P687,289.50 as actual damages
representing the accrued rentals for the quarter September to November
1993 with interest and penalty at the rate of two percent (2%) per month
from date of filing of the complaint until the amount shall have been fully
paid, and the sum of P50,000.00 as attorneys fees; (2) In Civil Case No.
93-68337, the appealed decision is REVERSED and SET ASIDE and a new
judgment is rendered ordering [Petitioner] Pryce Properties Corporation to
reimburse [Respondent] Philippine Amusement and Gaming Corporation
the amount of P687,289.50 representing the advanced rental deposits,
which amount may be compensated by [Petitioner] Pryce Properties
Corporation with its award in Civil Case No. 93-68266 in the equal amount
of P687,289.50.[4]
The Facts
According to the CA, the facts are as follows:
Sometime in the first half of 1992, representatives from Pryce Properties
Corporation (PPC for brevity) made representations with the Philippine
Amusement and Gaming Corporation (PAGCOR) on the possibility of setting
up a casino in Pryce Plaza Hotel in Cagayan de Oro City. [A] series of
negotiations followed. PAGCOR representatives went to Cagayan de Oro
City to determine the pulse of the people whether the presence of a casino
would be welcomed by the residents. Some local government officials
showed keen interest in the casino operation and expressed the view that
possible problems were surmountable. Their negotiations culminated with
PPCs counter-letter proposal dated October 14, 1992.
On November 11, 1992, the parties executed a Contract of Lease x x x
involving the ballroom of the Hotel for a period of three (3) years starting
December 1, 1992 and until November 30, 1995. On November 13, 1992,
they executed an addendum to the contract x x x which included a lease of
an additional 1000 square meters of the hotel grounds as living quarters
and playground of the casino personnel. PAGCOR advertised the start of
their casino operations on December 18, 1992.
Way back in 1990, the Sangguniang Panlungsod of Cagayan de Oro City
passed Resolution No. 2295 x x x dated November 19, 1990 declaring as a
Page | 100
added that the trial court erred in 1) failing to consider that PPC was
entitled to avail itself of the provisions of Article XX only when PPC was the
party terminating the Contract; 2) not finding that there were valid,
justifiable and good reasons for terminating the Contract; and 3)
dismissing the Complaint of PAGCOR in Civil Case No. 93-68337 for lack of
merit, and not finding PPC liable for the reimbursement of PAGCORS cash
deposits and of the value of improvements.
PAGCOR sent PPC a letter dated September 20, 1993 x x x [stating] that it
was not amenable to the payment of the full rentals citing as reasons
unforeseen legal and other circumstances which prevented it from
complying with its obligations. PAGCOR further stated that it had no other
alternative but to pre-terminate the lease agreement due to the relentless
and vehement opposition to their casino operations. In a letter dated
October 12, 1993 x x x, PAGCOR asked PPC to refund the total of
P1,437,582.25 representing the reimbursable rental deposits and expenses
for the permanent improvement of the Hotels parking lot. In a letter dated
November 5, 1993 x x x, PAGCOR formally demanded from PPC the
payment of its claim for reimbursement.
On November 15, 1993 x x x, PPC filed a case for sum of money in the
Regional Trial Court of Manila docketed as Civil Case No. 93-68266. On
November 19, 1993, PAGCOR also filed a case for sum of money in the
Regional Trial Court of Manila docketed as Civil Case No. 93-68337.
In a letter dated November 25, 1993, PPC informed PAGCOR that it was
terminating the contract of lease due to PAGCORs continuing breach of the
contract and further stated that it was exercising its rights under the
contract of lease pursuant to Article 20 (a) and (c) thereof.
On February 2, 1994, PPC filed a supplemental complaint x x x in Civil
Case No. 93-68266, which the trial court admitted in an Order dated
February 11, 1994. In an Order dated April 27, 1994, Civil Case No. 9368377 was ordered consolidated with Civil Case No. 93-68266. These
cases were jointly tried by the court a quo. On August 17, 1995, the court
a quo promulgated its decision. Both parties appealed.[5]
In its appeal, PPC faulted the trial court for the following reasons: 1) failure
of the court to award actual and moral damages; 2) the 50 percent
reduction of the amount PPC was claiming; and 3) the courts ruling that
the 2 percent penalty was to be imposed from the date of the promulgation
of the Decision, not from the date stipulated in the Contract.
On the other hand, PAGCOR criticized the trial court for the latters failure
to rule that the Contract of Lease had already been terminated as early as
September 21, 1993, or at the latest, on October 14, 1993, when PPC
received PAGCORs letter dated October 12, 1993. The gaming corporation
Regarding the contentions of PPC, the CA held that under Article 1659 of
the Civil Code, PPC had the right to ask for (1) rescission of the Contract
and indemnification for damages; or (2) only indemnification plus the
continuation of the Contract. These two remedies were alternative, not
cumulative, ruled the CA.
As PAGCOR had admitted its failure to pay the rentals for September to
November 1993, PPC correctly exercised the option to terminate the lease
agreement. Previously, the Contract remained effective, and PPC could
collect the accrued rentals. However, from the time it terminated the
Contract on November 25, 1993, PPC could no longer demand payment of
the remaining rentals as part of actual damages, the CA added.
Denying the claim for moral damages, the CA pointed out the failure of PPC
to show that PAGCOR had acted in gross or evident bad faith in failing to
pay the rentals from September to November 1993. Such failure was
shown especially by the fact that PPC still had in hand three (3) months
advance rental deposits of PAGCOR. The former could have simply applied
this deposit to the unpaid rentals, as provided in the Contract. Neither did
PPC adequately show that its reputation had been besmirched or the
hotels goodwill eroded by the establishment of the casino and the public
protests.
Finally, as to the claimed reimbursement for parking lot improvement, the
CA held that PAGCOR had not presented official receipts to prove the
latters alleged expenses. The appellate court, however, upheld the trial
courts award to PPC of P50,000 attorneys fees.
Hence this Petition.[6]
Page | 101
Issues
In their Memorandum, petitioner raised the following issues:
ruled, that Article 1659 of the Civil Code governs; hence, PPC is allegedly
no longer entitled to future rentals, because it chose to rescind the
Contract.
MAIN ISSUE:
Contract Provisions
Sub-Issues:
1.
Were the provisions of Sections 20(a) and 20(c) of the Contract of
Lease relative to the right of PRYCE to terminate the Contract for cause and
to moreover collect rentals from PAGCOR corresponding to the remaining
term of the lease valid and binding?
2.
Did not Article 1659 of the Civil Code supersede Sections 20(a) and
20(c) of the Contract, PRYCE having rescinded the Contract of Lease?
3.
Do the case of Rios, et al. vs. Jacinto Palma Enterprises, et al. and
the other cases cited by PAGCOR support its position that PRYCE was not
entitled to future rentals?
4.
Would the collection by PRYCE of future rentals not give rise to unjust
enrichment?
5.
Could we not have harmonized Article 1659 of the Civil Code and
Article 20 of the Contract of Lease?
6.
Is it not a basic rule that the law, i.e. Article 1659, is deemed written
in contracts, particularly in the PRYCE-PAGCOR Contract of Lease? [7]
The Courts Ruling
The Petition is partly meritorious.
Main Issue:
Article 1159 of the Civil Code provides that obligations arising from
contracts have the force of law between the contracting parties and should
be complied with in good faith.[8] In deference to the rights of the parties,
the law[9] allows them to enter into stipulations, clauses, terms and
conditions they may deem convenient; that is, as long as these are not
contrary to law, morals, good customs, public order or public policy.
Likewise, it is settled that if the terms of the contract clearly express the
intention of the contracting parties, the literal meaning of the stipulations
would be controlling.[10]
In this case, Article XX of the parties Contract of Lease provides in part as
follows:
XX. BREACH OR DEFAULT
a)
The LESSEE agrees that all the terms, conditions and/or covenants
herein contained shall be deemed essential conditions of this contract, and
in the event of default or breach of any of such terms, conditions and/or
covenants, or should the LESSEE become bankrupt, or insolvent, or
compounds with his creditors, the LESSOR shall have the right to terminate
and cancel this contract by giving them fifteen (15 days) prior notice
delivered at the leased premises or posted on the main door thereof. Upon
such termination or cancellation, the LESSOR may forthwith lock the
premises and exclude the LESSEE therefrom, forcefully or otherwise,
without incurring any civil or criminal liability. During the fifteen (15) days
notice, the LESSEE may prevent the termination of lease by curing the
events or causes of termination or cancellation of the lease.
b)
xxx
xxx
xxx
c)
Moreover, the LESSEE shall be fully liable to the LESSOR for the
rentals corresponding to the remaining term of the lease as well as for any
and all damages, actual or consequential resulting from such default and
termination of this contract.
xxx
xxx
x x x. (Italics supplied)
The above provisions leave no doubt that the parties have covenanted 1)
to give PPC the right to terminate and cancel the Contract in the event of a
default or breach by the lessee; and 2) to make PAGCOR fully liable for
Page | 102
rentals for the remaining term of the lease, despite the exercise of such
right to terminate. Plainly, the parties have voluntarily bound themselves
to require strict compliance with the provisions of the Contract by
stipulating that a default or breach, among others, shall give the lessee the
termination option, coupled with the lessors liability for rentals for the
remaining term of the lease.
For sure, these stipulations are valid and are not contrary to law, morals,
good customs, public order or public policy. Neither is there anything
objectionable about the inclusion in the Contract of mandatory provisions
concerning the rights and obligations of the parties. [11] Being the primary
law between the parties, it governs the adjudication of their rights and
obligations. A court has no alternative but to enforce the contractual
stipulations in the manner they have been agreed upon and written. [12] It is
well to recall that courts, be they trial or appellate, have no power to make
or modify contracts.[13] Neither can they save parties from disadvantageous
provisions.
Termination or Rescission?
Well-taken is petitioners insistence that it had the right to ask for
termination plus the full payment of future rentals under the provisions
of the Contract, rather than just rescission under Article 1659 of the Civil
Code. This Court is not unmindful of the fact that termination and
rescission are terms that have been used loosely and interchangeably in
the past. But distinctions ought to be made, especially in this controversy,
in which the terms mean differently and lead to equally different
consequences.
The term rescission is found in 1) Article 1191 [14] of the Civil Code, the
general provision on rescission of reciprocal obligations; 2) Article 1659, [15]
which authorizes rescission as an alternative remedy, insofar as the rights
and obligations of the lessor and the lessee in contracts of lease are
concerned; and 3) Article 1380[16] with regard to the rescission of contracts.
In his Concurring Opinion in Universal Food Corporation v. CA, [17] Justice J.
B. L. Reyes differentiated rescission under Article 1191 from that under
Article 1381 et seq. as follows:
x x x. The rescission on account of breach of stipulations is not predicated
on injury to economic interests of the party plaintiff but on the breach of
faith by the defendant, that violates the reciprocity between the parties. It
is not a subsidiary action, and Article 1191 may be scanned without
disclosing anywhere that the action for rescission thereunder is
subordinated to anything other than the culpable breach of his obligations
to the defendant. This rescission is a principal action retaliatory in
character, it being unjust that a party be held bound to fulfill his promises
when the other violates his. As expressed in the old Latin aphorism: Non
servanti fidem, non est fides servanda. Hence, the reparation of damages
for the breach is purely secondary.
On the contrary, in rescission by reason of lesion or economic prejudice,
the cause of action is subordinated to the existence of that prejudice,
because it is the raison detre as well as the measure of the right to
rescind. x x x.[18]
Relevantly, it has been pointed out that resolution was originally used in
Article 1124 of the old Civil Code, and that the term became the basis for
rescission under Article 1191 (and, conformably, also Article 1659). [19]
Now, as to the distinction between termination (or cancellation) and
rescission (more properly, resolution), Huibonhoa v. CA[20] held that, where
the action prayed for the payment of rental arrearages, the aggrieved
party actually sought the partial enforcement of a lease contract. Thus,
the remedy was not rescission, but termination or cancellation, of the
contract. The Court explained:
x x x. By the allegations of the complaint, the Gojoccos aim was to
cancel or terminate the contract because they sought its partial
enforcement in praying for rental arrearages. There is a distinction in law
between cancellation of a contract and its rescission. To rescind is to
declare a contract void in its inception and to put an end to it as though it
never were. It is not merely to terminate it and release parties from further
obligations to each other but to abrogate it from the beginning and restore
the parties to relative positions which they would have occupied had no
contract ever been made.
x x x. The termination or cancellation of a contract would necessarily
entail enforcement of its terms prior to the declaration of its cancellation in
the same way that before a lessee is ejected under a lease contract, he
has to fulfill his obligations thereunder that had accrued prior to his
ejectment. However, termination of a contract need not undergo judicial
intervention. x x x.[21] (Italics supplied)
Rescission has likewise been defined as the unmaking of a contract, or its
undoing from the beginning, and not merely its termination. Rescission
may be effected by both parties by mutual agreement; or unilaterally by
one of them declaring a rescission of contract without the consent of the
other, if a legally sufficient ground exists or if a decree of rescission is
applied for before the courts. [22] On the other hand, termination refers to an
end in time or existence; a close, cessation or conclusion. With respect
to a lease or contract, it means an ending, usually before the end of the
anticipated term of such lease or contract, that may be effected by mutual
agreement or by one party exercising one of its remedies as a
consequence of the default of the other. [23]
Page | 103
Page | 104
findings, which are not contested by either party, we find that PAGCOR
conducted a series of negotiations and consultations before entering into
the Contract. It did so not only with the PPC, but also with local
government officials, who assured it that the problems were
surmountable. Likewise, PAGCOR took pains to contest the ordinances [34]
before the courts, which consequently declared them unconstitutional. On
top of these developments, the gaming corporation was advised by the
Office of the President to stop the games in Cagayan de Oro City,
prompting the former to cease operations prior to September 1993.
Also worth mentioning is the CAs finding that PAGCORs casino operations
had to be suspended for days on end since their start in December 1992;
and indefinitely from July 15, 1993, upon the advice of the Office of
President, until the formal cessation of operations in September 1993.
Needless to say, these interruptions and stoppages meant that PAGCOR
suffered a tremendous loss of expected revenues, not to mention the fact
that it had fully operated under the Contract only for a limited time.
Petitioner,
DECISION
CHICO-NAZARIO, J.:
Before this Court is a Petition for Review on Certiorari under Rule
45 of the Revised Rules of Court, filed by petitioner Erminda F.
Florentino, seeking to reverse and set aside the Decision, 1 dated
Page | 105
Page | 106
Page | 107
Page | 108
more
Page | 109
Page | 110
i
ii
iii
iv
v
vi
vii
viii
ix
x
xi
xii
xiii
xiv
xv
xvi
xvii
xviii
xix
xx
xxi
xxii
xxiii
xxiv
xxv
xxvi
xxvii
xxviii
xxix
xxx
xxxi
xxxii
xxxiii
xxxiv
xxxv
xxxvi
xxxvii
xxxviii
xxxix
xl
xli
xlii
xliii
xliv
xlv
xlvi
xlvii
xlviii
xlix
l
li
lii
liii
liv
lv
lvi
lvii
lviii
lix
lx
lxi
lxii
lxiii
lxiv